2006 Strategy IV
Lease of 228,000 rsf of Office space in NYC Midtown
Lease of 80,000 sf for Library Swing Space
In Long Island City
2006 2007 2008 2009 2010 2011 2012 2013 2014
Fit-out May ’07 – Dec ’07
2007 Strategy IV
2006 2007 2008 2009 2010 2011 2012 2013 2014
Fit-outApr ‘07 – Dec ‘07
Construct 100,000 sf North LawnTemporary Conference Building July ‘07 – June ‘08
Last Q 2007 / First Q 2008 Strategy IV
Construct July ’07 – June ‘08
2006 2007 2008 2009 2010 2011 2012 2013 2014
Move remainder of top floors into vacated areas belowDec ’07 – Jan’08
Move 228,000 rsf of office function to Swing Space Dec ’07 – Jan ‘08
On site Swing Space
Jan ’08 – Nov ’12
Move Library to Long Island CityDec ‘07
2008 Strategy IV
Construct July ’07 – June ‘08OccupyJune ’08
Refurbish General Assembly BuildingJune ’08 – Feb ‘11
Library Swing SpaceDec ’07 - Dec ‘13
On site Swing Space
Jan ’08 – Nov ‘12
2006 2007 2008 2009 2010 2011 2012 2013 2014
Secretariat roof top reinforcement & infrastructureFeb ’08 – Feb ’09
Office Swing SpaceDec ’07 – Dec ‘13
Refurbish BasementsJuly ’08 – July ‘10
2009 Strategy IV
Library Swing SpaceDec ’07 - Dec ‘13
2006 2007 2008 2009 2010 2011 2012 2013 2014
RefurbishJune ’08 – Feb ‘11
On site Swing Space
Jan ’08 – Nov ’12
Office Swing SpaceDec ’07 – Dec ‘13
Refurbish top 10 floorsof Secretariat BuildingFeb ’09 – Apr ‘10
Refurbish July ’08 – July ‘10
2010 Strategy IV
Library Swing SpaceDec ’07 - Dec ‘13
2006 2007 2008 2009 2010 2011 2012 2013 2014
RefurbishMay ‘10 – Jul ‘11
CompleteJune ‘10
RefurbishJune ’08 – Feb ’11
On site Swing Space
Jan ’08 – Nov ’12
Office Swing SpaceDec ’07 – Dec ‘13
Complete Apr ‘10
2011 Strategy IV
Refurbish 1st Basement and First Floor of Conference BuildingFeb ’11 – July ‘12
Library Swing SpaceDec ’07 - Dec ‘13
2006 2007 2008 2009 2010 2011 2012 2013 2014
RefurbishJuly ‘11 – Sept ’12
On site Swing Space
Jan ‘08 – Nov ‘12
Office Swing SpaceDec ’07 – Dec ‘13 Complete
Jul ‘11
CompleteFeb ‘11
2012 Strategy IV
Library Swing SpaceDec ‘07 - Dec ‘13
Refurbish 2nd, 3rd and 4th floor of Conference BuildingAug ’12 – Oct ‘13
2006 2007 2008 2009 2010 2011 2012 2013 2014
Refurbish LibraryDec ’12 – Dec ‘13
Office Swing SpaceDec ’07 – Dec ‘13 Complete
Sept ‘12
RefurbishOct ’12 – Dec ‘13
2013 Strategy IV
ReoccupyOct ‘13
Dismantle Temporary BuildingOct ’13 – Dec ‘13
2006 2007 2008 2009 2010 2011 2012 2013 2014
Refurbish South Annex
Nov ’13 – Apr ‘14
Office Swing SpaceDec ’07 – Dec ‘13
Library Swing SpaceDec ‘07 - Dec ‘13
Refurbish LibraryDec ’12 – Dec ‘13
RefurbishOct ’12 – Dec ‘13
Last Q 2013 / First Q 2014 Strategy IV
Dismantle Temporary BuildingOct ’13 – Dec ‘13
2006 2007 2008 2009 2010 2011 2012 2013 2014
Vacate Swing Space
Refurbish South AnnexNov ’13 – Apr ‘14
CompleteDec ‘13
CompleteDec ‘13