Upload
vanhanh
View
471
Download
20
Embed Size (px)
Citation preview
Integrity Commitment Passion Seamlessness Speed
CII 18th National Award for Excellence in Energy Management 2017
UltraTech Cement Limited: Unit - Rawan Cement Works
Team Members:1. Mr. Ram Prakash Nolkha 2. Mr. Pradeep Agrawal 3. Mr. Deepak Kumar
Integrity Commitment Passion Seamlessness Speed
1. Business and Unit Overview
2. Cement Manufacturing Process & Unit’s Milestones
3. Various Certifications and Energy Management System
4. Reduction in SEC, Innovation and Various Encon Projects
5. GHG Inventorization, Sustainability, Safety & CSR Activities
6. Best Practices (Green Supply Chain), Awards and Accolades
Contents
Integrity Commitment Passion Seamlessness Speed
Hirmi Cement Works
Jafrabad Cement Works
Magdalla Cement Works
Ratnagiri Cement Works
Andhra Pradesh Cement Works
Arrakonam Cement Works
Awarpur Cement
Works
Jharsuguda Cement Works
West Bengal Cement Works
Bathinda Cement Works
Aditya Cement
Vikram Cement
Gujarat Cement Works
Kotputli Cement Works
Hotgi Cement Works
Rajashree Cement Works
Ginigera Cement
Works
Panipat Cement WorksDadri Cement Works
Aligarh Cement Works
RWCW
Integrated Units
Grinding Units
Bulk Terminals
Mangalore Bulk
Terminal
Shankarapally Bulk Terminal
Navi Mumbai Cement Unit
Dankuni Cement Works
Patna Cement Works
Cochin Bulk Terminal
Pune Bulk Terminal Unit
Sewagram Cement Works
Wanakbori Cement
Works
Nagpur Cement Works
Jhajjar Cement Works
Units SymbolNumber of
Units
Integrated Plants 18
Grinding Units 25
Bulk Terminals 7
Business Overview
BSBT- Dodballapur
Reddipalayam Cement Works
Largest Cement Player in India by an Even Larger Margin
14 MILLION TPA
(2004)
93.00MILLION
TPA(2017)
Balaji Cement Works
Sidhi Cement Works
Bela Cement Works
Baga Cement Works
Dalla Cement Works
Bagheri Cement Works
Roorkee Cement WorksSikandarabad Cement Works
Tanda Cement Works
Integrity Commitment Passion Seamlessness Speed
Our Aspiration, Going Forward
Looking Ahead
No. 3 in the World
25% Market Share
Add 30 Million Tonne Capacity
Double our revenues
Triple the EBITDA
One in three homes built in India with UltraTech Cement
Integrity Commitment Passion Seamlessness Speed
UltraTech Rawan Cement Works At a Glance
RWCW Major Equipment Details
Line 1 (1995) Line 2 (2013)
RAW MILL
Loesche VRM 375 TPH
KHD Roller Press 3 × 275 TPH
COAL MILL
Loesche VRM 40 TPH
Pfeiffer VRM 90 TPH
KILN
FLSmidth (SLC + ILC)5600 TPD
KHD (4 Strings ILC)10000 TPD
CEMENT MILL
KHD RP + Ball Mill (PPC – 305 TPH)(OPC – 220 TPH)
Polycom for Slag Grinding
(PSC – 220 TPH)
BrownfieldProject
3.30 MTPA Year 2013
Capacity Enhanced 1.87 MTPA Year 2008
Greenfield Project1.0 MTPA Year 1995
Clinker: 5.17 MTPA Cement: 2.50 MTPATPP Capacity: 55 MWWHRS: 15 MW
Plant Capacity RWCW is the largest unit of UltraTech
Cement Ltd. in Eastern Cluster of India
RWCW
Integrity Commitment Passion Seamlessness Speed
VISION
To be the Leader in Building Materials with focus on our Values & create a Sustainablefuture in the UltraTech Cement of Aditya Birla Group.
MISSION
Leading with latest technologies for delivering the values to our customer's by followingfour focal areas:
1. Sustainability
2. Quality & Bosstomer Satisfaction
3. Employee Engagement & Team Empowerment
4. Cost Effectiveness & Innovation
Unit’s Vision & Mission
Integrity Commitment Passion Seamlessness Speed
Cement Manufacturing Process
Mining CrushingClinkerisation
Clinker
Grinding
PackingDelivery
Truck
Coal Grinding
Delivery
Rack
Delivery
Bulker
Additives
Stacking & Reclaiming
LS Grinding
Post Clinkerization
Pre Clinkerization
Integrity Commitment Passion Seamlessness Speed
Our Final Products
PPC PSC OPC 43 Grade
Integrity Commitment Passion Seamlessness Speed
Unit’s Milestones & Achievements
Rated as one of the best Cement plant in Safety with clear focus on Environment, Zero %Ground Water usage in Plant & Colony, Green Band in External BCE Audit
Highest Conversion factor of 1.72 – Lowest Carbon Footprints/Specific CO2 Emissionsamong all UltraTech plants
Manufacturing of Green Clinker & Successful Plant scale trial of Composite Cement(received license from BIS for manufacturing of Composite cement)
First Unit in UltraTech to achieve output of >12500 TPD Clinker from line-2 Kiln with100% Petcoke, SEC of <50 kWh/MT of Clinker & 695 kCal/kg of Clinker
2nd Lowest Cost of Cement manufacturing in UltraTech for FY 2016-17 and presently weare at no. 1 in Q1 – FY18 among all plants of UTCL
In-house manufacturing of Grinding Aid and lowest power consumption in PPC grindingamong all UltraTech Cement Plants (22.22 kWh/MT in July’2017)
Integrity Commitment Passion Seamlessness Speed
Unit’s Best Practices
❖ Effective Safety Culture deployment in every action
❖ Cross functional SWOT Analysis every year in presence of Top management
❖ Structured Energy Management System for continual improvement
❖ Centralized Total Lubrication Management
❖ Use of Slag as Raw Material in Clinkerisation – Green Clinker
❖ Shutdown Management System
❖ Well organized Inspection System (R1R2/S1S2) & Effective Preventive Maintenance
❖ Organized Hazardous Waste handling system
❖ Man less Operation of LS Stacker and Reclaimer in both lines
❖ Execution of Basic Condition Evaluation
❖ Use of PPF in place of HSD during light up of Kiln and TPP
❖ Effective Cross functional Why-Why Analysis of each breakdowns on fortnightly basis
Integrity Commitment Passion Seamlessness Speed
Certifications
SA 8000 ISO 27001ISO 9001, 14001, OHSAS 18001
Integrity Commitment Passion Seamlessness Speed
Energy Management Policy
❖ Energy Policy implemented in 2009
❖ Energy Policy states unit’s commitment towards continual energy performance improvement
❖ Energy policy is communicated at all levels
❖ Daily Review of Energy & PAT data w.r.t BEST
❖ Dedicated Energy Cell with fortnightly review
❖ Three layer Team Structure for stringent Monitoring
❖ Six Sigma Projects on Energy Conservation
❖ Real time power consumption data monitoring through online Energy Monitoring System
❖ Committed for continual improvement
Integrity Commitment Passion Seamlessness Speed
Energy Management Structure
COO & EP Chairman
FH-TechChampion
LSC RM Kiln CMPacking
Plant
WT Clinker Loading
TPPAC, P&V
Township Utilities
Energy Manager
Energy Cell Functioning Focus Area
Restoring Basic Condition of Equipments
Process/Energy Optimization
Awareness / Campaign /Knowledge Management
Technical Cell
Innovation
Technological Up-gradation
Integrity Commitment Passion Seamlessness Speed
Energy Monitoring, Reporting & Implementation Methodology
Online Energy Monitoring System
Integrity Commitment Passion Seamlessness Speed
Energy Monitoring, Reporting & Implementation Methodology
❖ Energy Management Cell with clear cut responsibilities.
❖ Daily monitoring of Energy Deviation report.
❖ Benchmarking with National/International/Group
Units/Cluster units and action plan for improvement.
❖ Regular study of Equipments on deviation and their
analysis.
❖ Process Evaluation & Identification of Energy Conservation
scope.
❖ Feasibility study of suggestions and designing proposals for
sanctions.
❖ Promoting energy saving idea generation by shop floor
teams and time bound implementation
❖ Organizing Internal and External Energy Audit.
Monitoring & Review Formats
Description Formats
Daily Co-ordination meeting on Power and Performance review
Review of Daily Power Report for any deviation
Energy Cell Meeting Points Compliance review
Energy Audit (Internal & External) Points Compliance
Integrity Commitment Passion Seamlessness Speed
Dedicated Energy Cell
1 LS Crusher
Mr. Lalit Nayak Electrical(SH)
Mr. Amit Shekhar Mech.
Mr. Rishi Verma Instt.
Mr. Devendra Deshmukh Mines Operations
Mr. Manish Paliwal Elect.
2 Raw Mill
Mr. Yogendra Verma Electrical(SH)
Mr. Pushraj Mech.
Mr. Shashikant Tiwary Mech.
Mr. Rishi Verma Instt.
Mr. Sanjay Kateria Process
3 Coal Mill
Mr. Prakash Hardeniya Electrical(SH)
Mr. Karan raj Gupta Mech.
Mr. Animesh Sumen Mech.
Mr. kishor Nalge Instt.
Mr. Sanjeev Choubey Process
4 Kiln
Mr. Byomjit Dixit Electrical(SH)
Mr. R.K. Tiwari Mech
Mr. Pramit Ujjain Mech
Mr. Adityaram Instt.
Mr. Vikas Sahu Process
5Cement
Mill
Mr. Ashok Ojha Electrical(SH)
Mr. Sudhanshu Barik Mech
Mr. Rajesh Jaiswal Instt.
Mr. Manish Mishra Process
6Packing
Plant
Mr. Ashok Ojha Electrical(SH)
Mr. Sanjeev Mishra PP Operation
Mr. Rajkumar Soni Mech
Mr. Rajesh Jaiswal Instt.
7 TPP
Mr. P.S. Rangnath Electrical(SH)
Mr. Neeraj Singh Mech
Mr. Lovkesh Kumar Instt.
Mr. Pawan Pothghan Operation
8 WHR
Mr. Ravi Raw Electrical(SH)
Mr. Dharmendra Manikpuri
Mech
Mr. Abhishek Sen Instt.
Mr. Rajesh Sharma Operation
9 Utility
Mr. Yogendra Verma Electrical(SH)
Mr S P Yadav Utility (SH)
Mr. Shyam Narayan Sahu Mech.
Mr. Krishnakanth Singh Instt.
Mr. Ankush Gwande Electrical
Cross Functional Action Team for Energy ConservationEnergy Cell Meeting
All team presentssectionwise Powerand Performance
Discussion overdeviation (if any)
New Ideas on powersaving
Target date andResponsibilityallocation
Last meeting MOMreview
Integrity Commitment Passion Seamlessness Speed
Employee Involvement & Team Work
Kaizen & Suggestions Schemes
Annual Improvement Projects
Organization Knowledge
KIP Visits
External & Internal Trainings on Energy
Participation in Seminars
Team competition
Energy Conservation Week
Awareness creating to all Colony residents for Energy Conservation
Online Training need identification throughPoornata on Energy Conservation
Reward & Recognition
1000
1500
2000
2500
3000
2014-15 2015-16 2016-17
1821 17572112
NO
S.
Kaizens/Suggestions Implemented
75
95
115
135
155
175
2014-15 2015-16 2016-17
142.2
122.54
162.31
Monetary Savings in Rs. Lacs
Integrity Commitment Passion Seamlessness Speed
Employee Involvement & Team Work
Annual SWOT Analysis
Integrity Commitment Passion Seamlessness Speed
Employee Involvement & Team Work
Monthly Masscom Meeting
Award – Encon Project
Best Encon Suggestion Award
Good Work Done Award
COO & EP Addressing
Monthly Masscom Meeting
Integrity Commitment Passion Seamlessness Speed
Unit’s Performance
Integrity Commitment Passion Seamlessness Speed
Unit’s Performance
5.00
15.00
25.00
35.00
45.00
2014-15 2015-16 2016-17
34.7938.85
43.04
Clinker Production (LMT)
5.00
10.00
15.00
20.00
25.00
2014-15 2015-16 2016-17
19.49 19.88 19.84
Cement Production (LMT)
GO
OD
GO
OD
Production figures are combined for both Lines
Integrity Commitment Passion Seamlessness Speed
Unit’s Performance
%
26
28
30
32
34
36
2014-15 2015-16 2016-17 NationalBM
30.10
33.68 34.35 35.00
Flyash Addition %
%
20253035404550556065
2014-15 2015-16 2016-17 NationalBM
42.04 45.9849.55
65.00
Slag Addition %
GO
OD
GO
OD
In Q1: FY 2017-18 Flyash Addition is 34.72 % In Q1: FY 2017-18 Slag Addition is 54.07 %
Integrity Commitment Passion Seamlessness Speed
Electrical Energy Performance
National Benchmark Reference: CII Energy Benchmarking Manual 2015, Version 2.0Global Benchmarking: BEE presentation during interactive workshop on normalization factor in Ahmedabad
40
50
60
70
2014-15 2015-16 2016-17 NationalBM (Top 3
Plants)
61.38 61.2056.10
49.17
KW
H/M
T O
F C
LIN
KER
Specific Power Consumption KWh Per MT of Clinker (Both Lines)
In Q1 2017-18: Achieved 55.90 kWh/MT of Clinker
GO
OD
30
40
50
60
70
2014-15 2015-16 2016-17 NationalBM
61.50 60.9254.92
49.17
KW
H/M
T O
F C
LIN
KER
Specific Power Consumption KWh Per MT of Clinker (Line-2)
GO
OD
In August’17: Achieved Output of >12500 TPD with 100% Petcoke with SPC of <50 Units/MT of Clinker
Integrity Commitment Passion Seamlessness Speed
Electrical Energy Performance
58
60
62
64
66
68
70
72
74
2014-15 2015-16 2016-17 NationalBM
GlobalBM
72.5670.79
68.59
65.0464
KW
H/M
T O
F C
EMEN
T
Total Specific Power Consumption KWh Per MT of Cement
In Q1 2017-18: Achieved 65.99 kWh/MT of Cement
GO
OD
10
20
30
2014-15 2015-16 2016-17 NationalBM
22.41 23.37 23.67 23.75
KW
H/M
T O
F C
EMEN
T
PPC Specific Power Consumption KWh Per MT of Cement
In Q1 2017-18: Achieved 22.57 kWh/MT of PPC
* Lowest Power Consumption in PPC Grinding among all UTCL (22.22 kWh/Mt in July’2017)
GO
OD
Integrity Commitment Passion Seamlessness Speed
Thermal Energy Performance
620
640
660
680
700
720
2014-15 2015-16 2016-17 NationalBM
GlobalBM
711715
704
686
658
Specific Heat Consumption(kCal/KG of Clinker)
SHC Values are combined for both Lines
10
30
50
70
90
2014-15 2015-16 2016-17
57.94
75.8384.70
Petcoke Consumption (%)Heat Basis
GO
OD
Lower %age in Line-1
Petcoke Consumption % of both LinesG
OO
D
100 % Petcoke Consumption in Line-2 since 2015-16
Integrity Commitment Passion Seamlessness Speed
PAT Status
0.057
0.058
0.059
0.06
0.061
0.062
0.063
0.064
0.065
Base Line PAT Cycle 2 Target SEC PAT Cycle 2 Actual in FY 2016-17Series1 0.0647 0.0616 0.0598
0.0647
0.0616
0.0598
MTO
E/TO
N O
F EQ
UIV
ALE
NT
CEM
ENT
GTG Energy Consumption GO
OD
Save Energy - Save Money - Save the Planet
Integrity Commitment Passion Seamlessness Speed
There is a thin line between using energy and wasting energy
Innovative Projects
Integrity Commitment Passion Seamlessness Speed
Innovative Project – 1Manufacturing of Green Clinker
Benefits: Electrical Energy saving of 15.78 Lac KWh/Annum
Increase in Clinker production by 2.0 %
CO2 emission reduction 744.20 Lacs kgCO2 per annum
Conservation of natural resources (Limestone) 1.49 times of slag
Converting waste to wealth
Savings of 5.02 Crore INR per annum @ 2% GBFS addition
1000
6000
11000
16000
21000
26000
2015-16 2016-17
9453
24434
GREEN CLINKER (MT)
In Q1 FY18: Total Green Clinker produced is 17796 MT
Actions: Characteristics of GBFS was found very near to Clinker
In house Design and Execution of Fully automatic Raw SlagFeeding system in line-1 and line-2
Dedicated feeding system made for both lines by FOC material
Compatibility of GBFS with Raw Mix established keeping in mindchemical constituents such as MgO, Mn2O3 & Al2O3
Daily target of adding 300 MT Raw Slag in both lines
Phases Normal Clinker Green Clinker
C3S 46.80 46.89
C2S 26.33 26.83
C3A 9.15 9.69
C4AF 10.52 11.07
GO
OD
Integrity Commitment Passion Seamlessness Speed
Slag and AFR Feeding System
Slag Feeding in Line-1 Ramp for Slag
Feeding in Line-1
Slag Feeding BC in Line-1
Slag Feeding Hopper
in Line-2
Slag Feeding BC in
Line-2
Slag Feeding BE in
Line-2
Integrity Commitment Passion Seamlessness Speed
Innovative Project – 2In-house Grinding Aid Manufacturing
Agitator for Mixing Powder Feeder
Transfer Pump Dosing SkidBenefits:❖ Reduction in Grinding Power
Consumption 0.85 KWh/Ton of Cementby production enhancement
❖ Cement Quality enhanced and we are thebest among all competitors in the cluster
❖ Reduction in Cement Manufacturing Cost
Objective:To Develop and manufacture top quality, costeffective In house Grinding Aid by setting upa manufacturing facility at Rawan CementWorks.
The Grinding Aid manufacturing system
successfully commissioned at RWCW.
Integrity Commitment Passion Seamlessness Speed
Innovative Project – 3Modification in Roller Press Material Feeding System
Objective:To modify existing material feeding system of line-2 Roller
Press SKS Separator discharge to Roller press feeding Pre Bin
through chute instead of existing conveying air slide (362AS1
/AS2/ AS3)
Benefits: 6 Nos. Blowers were eliminated from the system
Electrical saving of 2.83 Lac kWh/Annum
Elimination of frequent Airslide jamming
Elimination of 3 Nos. Airslide maintenance
Increased availability of Roller press
Total Saving for 3 nos. Roller Press on account of AirslideMaintenance, Production loss, Blower Power = 270.58lacs/annum
Integrity Commitment Passion Seamlessness Speed
:Case Study:
Specific Power Reduction in Line - 2 Pyro Section by 15.0%
Encon Projects
Energy conservation is the only solution
Integrity Commitment Passion Seamlessness Speed
A PARETO Chart of section wise power consumption was plotted and analyzed.
9.48
5.284.66 4.36
2.55
0.47
0
10
20
30
40
50
60
70
80
90
100
0
1
2
3
4
5
6
7
8
9
10
PreheaterFans
KilnAuxiliaries
CoolerFans
BaghouseFans
Kiln MainDrive
Vent Fan
Power Consumption Cummulative %
The major contributors forhigher Kiln section powerare:1. Preheater fans, 2. Kiln Auxiliaries, 3. Cooler fans4. Baghouse fans.
RWCW Line-2 Pyro Powerconsumption for Q1-FY16was 26.80 kWh/Mt of Clk
Problem Analysis
Integrity Commitment Passion Seamlessness Speed
Tools & Methodology Used
Problem Solving Tools/Methods were adopted for Energy Conservation:
ISHIKAWA Diagram (Fish Bone Analysis)
Cause and Effect Diagram, Pareto Analysis, DMAIC Approach etc.
Brainstorming Sessions
Why-Why Analysis
Monthly Energy Cell Meeting
Adoption of Energy Saving Methods
Replication of Ideas from sister concern units
Energy Audit
Integrity Commitment Passion Seamlessness Speed
Due to Rain water
penetrating into the system
High Moisture
Variation in
Raw Mix
Humidity
Ambient
Temperature
Process Fans Power High
Inadequate
TrainingLack
of Experience
Unnecessary high
speed of fan
Poor
Maintenance
Mother Earth MaterialMan
MethodMoneyMachine
Unstable
Operation
Not performing timely
Cleaning of PH
Cyclones & Inlet
Adjustment
of Power
Variation in
Fuel Mix
Old Design
Over Rated
Overloading of
Equipment
Frequent change in
Power frequency
Higher Preheater
Fan Outlet
Draught
Measuring
Instrument not
correct
Wrong method of
operation
Frequent start-stop
Not following of
fan curve
Consumption of
Unsized AFR
Frequent variation
in output rate
Frequent speed
variation
High Pressure
Drop
Higher Cone Gap
Poor calibration of fuel
& kiln feeding system
High
False Air
High
Excess Air
Poor Process
Optimization
Analyzer readings
not correct
High
Dust loading
Petcoke
residue high
Kiln feed
Residue high
High CO
formation
in system
High Sulphur
Petcoke
Idle
Running
Low Fan
Efficiency
ISHIKAWA Diagram
Integrity Commitment Passion Seamlessness Speed
Encon Project – 1Cooler Fans Inlet Duct Modification
BEFORE
55.00 mmWC
98.00 mmWC
240 mmWC
480 mmWC
∆ P = (240 - 98 = 142 mmWC)
Vertical Casing Horizontal Casing
AFTER❖ Total 14 nos of
Cooler Fans
❖ Cooler fanswere consuming2100 kWh(Beforemodification)
❖ Power SavingPotential wascalculated 505kWh
Integrity Commitment Passion Seamlessness Speed
4.17
3.793.33 3.07 3.50 3.42
2.00
2.50
3.00
3.50
4.00
4.50
FY 2016 Q1 - FY17 Q2 - FY17 Q3- FY17 Q4 - FY17 FY 2017
Cooler Fans Power Consumption (kWh/Mt of Clinker)
After identifying the power losses, Vertical inlet casing of cooler fans had been modified tohorizontal to reduce the excess pressure drop. Further cooler fans flow rate was alsooptimized w.r.t. kiln feed rate and desired WHRS inlet temperature in close association withOEM. After implementing the both tasks,
Achieved the Specific Power reduction of 0.75 kWh/MT of Clinker
Benefits Achieved
Due to Breakdown
Integrity Commitment Passion Seamlessness Speed
Baghouse Fans process optimization work was done to save power. After false airreduction, Preheater fans speed was reduced and therefore we got enough margin toreduce BH fans speed also. Logic was modified after brainstorming & trials to operatethe Baghouse at reduced inlet pressure from -60 mmWG to -30 mmWG which reducedthe BH fans power consumption by approx. 0.84 kWh/MT of Clinker
3.26
2.622.40
2.382.31
2.42
2.002.202.402.602.803.003.203.40
FY 2016 Q1 - FY17 Q2 - FY17 Q3- FY17 Q4 - FY17 FY 2017
RABH Fans Power Consumption (kWh/Mt of Clinker)
Encon Project – 2Process Optimization of RABH Fans
Integrity Commitment Passion Seamlessness Speed
Encon Project – 3Cooler ESP Stack Height Increase
BEFORE AFTERBenefits Achieved
❖ Static head of Coolervent fan was reduced.
❖ ESP fan powerconsumption reducedfrom 0.52 Units to0.36 kWh/Mt ofClinker.
❖ Power saving of 0.16kWh/Mt of Clinker
Project Execution Cost was Rs. 24.0 Lacs
Integrity Commitment Passion Seamlessness Speed
Encon Project – 4Size Reduction of Kiln Coal Firing Line
BEFORE AFTER
❖ With use of 100%
Petcoke in line-2 it was
calculated that pipe dia
was over sized.
❖ Reduced the line size
from 324 NB to 273 NB
❖ Power saving of 0.10
kWh/Mt of Clinker.
Benefits Achieved
Integrity Commitment Passion Seamlessness Speed
Encon Project – 5Louver Dampers Removal in PH Downcomer
Excess Pressure Drop of 35 mmWG across
Louver Damper
BEFORE AFTER
Benefits Achieved:After executing the task,Specific Power saving of0.311 kWh/Mt of Clinkerwas achieved.
4 nos. Louver Dampers were removed
Integrity Commitment Passion Seamlessness Speed
Encon Project – 6Optimization of Dilution Air Fan
Before After
Benefits Achieved:
Dilution Air Fan wasstopped during normalplant operation afterkeeping the outletdamper 100% open andinlet damper 90%closed.
❖ Total power savingswas achieved 0.16Unit/Mt of Clinker
Logic was made for automatic operation when RABH Inlet
Temperature is high
Integrity Commitment Passion Seamlessness Speed
Encon Project – 7Optimization of Reverse Air Fan
REVERSE AIR FAN
Reverse air fan in RABHsection is having VFD andexcess pressure drop of 20mmWG was measuredacross the dampertherefore it was removedfor power saving.
We had also developed the logic forRA fan operation w.r.t. DP to savepower consumption. At present, RAfan is running at 150 rpm when theDP is <110 mmWG & Whenever theDP is >110 mmWG, RA fan speedincreases to 1450 rpm.
Benefits Achieved:
Fan Inlet Damper
Removed
❖ Fan Running Hrs at 1450 RPM = 11Hrs/day (Power Consumption is 86kWh)
❖ Fan Running Hrs at 150 RPM = 13Hrs/day (Power Consumption is 5kWh)
❖ Power Saving = 0.10 kWh/Mt of Clk
Integrity Commitment Passion Seamlessness Speed
Encon Project – 8Suction Box Modification of Preheater Fans
There was a high velocity at preheater fan inlet suction box 29 to 30 m/sec which was
leading to high resistance (pressure drop of 30 mmWG from common down comer to
fan inlet suction box). We have done in house modification of suction box by enlarging
area by 32%. Same has been done without taking any help from consultant / OEM /Experts.
Initially Suction Box width was 1010
mm, it was increased up to 1335 mm.
By enlarging the area we were able to
reduce the suction box velocity from 29
to 20 m/sec. Project was implemented
successful with power saving of 0.20
kWh/Mt of Clinker.
BEFORE AFTER
Integrity Commitment Passion Seamlessness Speed
Encon Project – 9False Air Reduction in Pyro Section & WHRS
After commissioning of WHRS, False air ingress throughout the system (Pyro clone
outlet to fans inlet) became very high resulting to increase in power consumption of
Preheater fans. Cross function team was prepared for identifying the ingress areas
across the preheater and WHRS on weekly basis as well as action plan were made for
arresting the identified leakages which was well executed on priority basis to reduce
false air in the system.
❖ Feed Pipes Flange Joints❖ Welding Cracks❖ Expansion Joints❖ Cyclone Man Doors ❖ Poking Holes❖ Feed Pipes Flap Gates
❖ WHRS Bypass Dampers❖ WHRS Inlet & Outlet Dampers❖ Downcomer Ducts Expansions❖ Thermocouple Points❖ PC Analyzer Probes❖ Various Locations of WHRS
Concern Areas were identified as:
Integrity Commitment Passion Seamlessness Speed
WHRS Inlet Damper Flap Gates
Thermocouple Flange Joints Cyclone Doors
WHRS
WHRS
WHRS
Leakages Identification Task
Integrity Commitment Passion Seamlessness Speed
35.62
27.24
22.34
15.90
9.88
5
10
15
20
25
30
35
40
FY16 Q1-FY17 Q2-FY17 Q3-FY17 Q4-FY17
RWCW Line-2 Pyro Section False Air %age Trend With WHRS
False Air Trend
Integrity Commitment Passion Seamlessness Speed
7.98
7.30 7.41
6.406.58
6.92
5
6
7
8
9
FY 2016 Q1 - FY17 Q2 - FY17 Q3- FY17 Q4 - FY17 FY 2017
Preheater Fans Power Consumption (kWh/Mt of Clinker)
After continuous team efforts, we were able to reduced the false air infiltration aggressively inPreheater & WHRS and achieved the target i.e. below 10% (combined for Preheater + WHRS).Achieved Result: PH fans power consumption reduced by 1.06 kWh/MT of Clinker
Benefits Achieved
Integrity Commitment Passion Seamlessness Speed
Encon Project – 10Modification in Opening of Inlet Dampers of PH Fans
BEFORE AFTER
Benefits Achieved:
After execution oftask, total powersaving was achievedin Preheater fanswas 0.18 kWh/Mt ofClinker.
Integrity Commitment Passion Seamlessness Speed
After putting cross functional efforts and doing several improvement tasks for power saving inline-2 Pyro section, we are able to achieve specific power consumption <19.0 in Q3-FY17 andoverall SPC of FY17 was 19.77 kWh/Mt of Clinker (FY17)
(Cost Benefits = 3.30 Units × 3091736 Mt × Rs. 3.80 = 387.70 Lacs/Annum)
23.07
20.9319.88
18.9319.47 19.77
15161718192021222324
FY 2016 Q1 - FY17 Q2 - FY17 Q3- FY17 Q4 - FY17 FY 2017
Line-2 Pyro Power Consumption (kWh/Mt of Clinker) • Poor market demand in themonth of Jan’17
• Line-2 Cooler breakdown inthe month of March’17
• Use of High Sulphur SaudiPetcoke in Q4
Final Outcome
Integrity Commitment Passion Seamlessness Speed
Total saving = 387.70 Lacs/Annum (Saving in Power) + 422.94 Lacs/Annum (Saving in Thermal)
₹ 810.64 Lacs/Annum for FY 2016-17
Particulars FY 2015-16 FY 2016-17
Specific Heat Consumption 714 kCal/kg of Clinker 698 kCal/kg of Clinker
Total Clinker Produced 26.16 LMT 30.917 LMT
Thermal Saving 16 kCal/kg of Clinker
Monitory Saving ₹ 422.94 Lakhs/Annum
By reducing the Preheater Exit Gas Losses & Increased Cooler Efficiency we were able toreduce line-2 Specific Heat Consumption
Benefits on account of Thermal Energy
Integrity Commitment Passion Seamlessness Speed
Replicability of Encon Projects
❖ Installation of VFD and PID based operation (without fan inlet damper) in allBagfilters (above 15 kW):
❖Modification in Process fans Inlet suction Box:
❖ Cooler chimney height increase:
❖ Dilution Air Fan Optimization:
RC-IV
Dhar Project in Madhya Pradesh
RWCW - II RC-IV (Coal Mill) APCW
RC-IV RWCW - II RC-IIIPlanned at KCW &
RWCW-I
RWCW - II RC - IV
RWCW
Journey Towards Excellence Continues…
Integrity Commitment Passion Seamlessness Speed
Energy Conservation Projects 2014-15
A thing which burns never returns
Integrity Commitment Passion Seamlessness Speed
Energy Conservation Projects 2014-15
S.No. Energy Saving TasksAnnual Energy Savings Savings
(Lacs/Annum)Electrical (kWh) Thermal (MTOE)
1PH Fan GRR logic taken in Plant PLC for stopping when driverunning in SPRS mode.
285120 - 10.83
2Raw Meal transport CKT modified to remove air slides and its 06nos blowers.
283140 - 7.22
3 Elimination of Roots blower for K Pump 32400 - 1.70
4 Reversible belt conveyor elimination from line 2 Coal Crusher 323400 - 16.90
5 Provision of Energy savers in lighting load circuit 81468 - 4.30
6 Stage Reduction in feed pump 380160 - 19.90
7Cooler ESP Discharge Modification in Line-2 (Discharge Chute inplace of Screw Conveyor)
58608 - 3.10
8Provision of speed control in place of damper control by installingMVVFD in BFP & SA fan
1550400 - 81.20
Integrity Commitment Passion Seamlessness Speed
Energy Conservation Projects 2015-16
Save Today – Survive Tomorrow
Integrity Commitment Passion Seamlessness Speed
Energy Conservation Projects 2015-16
S.No. Energy Saving TasksAnnual Energy Savings Savings
(Lacs/Annum)Electrical (kWh) Thermal (MTOE)
1Instrument Air Consumption optimization by Interconnection ofInstrument Compressors of Line # 01 & Line # 02
316800 - 14.20
2Install EE pump of 200 m3/hr and 30 M head at WHRB in place ofexisting ACW pump
257416 - 11.60
3 Removal of Louver damper in Roller Press Separator fans in line-2 495000 - 22.22
4 Removal of Louver damper in Preheater fans in line-2 (4 Nos) 660000 - 29.60
5 LED street lights Installation 8773 - 0.33
6 Optimization of Dilution Air Fan in Line-2 RABH Section 494672 - 18.79
7Stopped the Hotbin Bucket elevator and Transport system byProviding a By Pass Conveyor system
173135 - 6.57
8Energy saving in reducing Idle Running of Line-1 & 2 RAL for Rawmill Transport system with Logic Modification
110774 - 4.20
9 8 Nos Bagfilters of Line-2 Coal transport system had been stopped 190852 - 7.25
Integrity Commitment Passion Seamlessness Speed
Energy Conservation Projects 2015-16
S.No. Energy Saving TasksAnnual Energy Savings Savings
(Lacs/Annum)Electrical (kWh) Thermal (MTOE)
10Replacement of W/T-1 water spray pump motor from 18.5 kw to9.3 kw
19800 - 0.75
11One compressor stopped among 4 compressors for line-2 processoperation after arresting the leakages
1188000 - 45.14
12 High mast towers convention lights were replaced by LED 19833 - 0.75
13 Installation of VFD in all ACC fans, BFP, ACW 2958450 - 35.50
Integrity Commitment Passion Seamlessness Speed
Energy Conservation Projects 2016-17
Energy conserved is Energy produced
Integrity Commitment Passion Seamlessness Speed
Energy Conservation Projects 2016-17
S.No. Energy Saving Tasks
Annual Energy SavingsSavings
(Lacs/Annum)Electrical (kWh) Thermal (MTOE)
1 Manufacturing of Green Clinker in both lines 1578067 - 63.10
2 Single bucket elevator operation for Line 2 Raw Meal feed 576198 - 21.89
3 Line-2 Cooler ESP Stack Height Increased By 10 M 494678 - 18.79
4 Line-2 Preheater Fans Inlet Modification 772934 - 29.37
5 LED lights in Plant 10205 - 0.38
6 Heat resistant Painting in line-2 top cyclones - 0.000211
7 Insulation fixing work in line-2 top cyclones - 0.000256
8Kiln RABH RA Fan (422FN3) damper removed and PID basedoperation w.r.t. RABH DP
309174 - 11.74
9Cooler ESP RAL-16 nos motor intermittent stopping of RAL forpower reduction
63360 - 2.40
Integrity Commitment Passion Seamlessness Speed
Energy Conservation Projects 2016-17
S.No. Energy Saving Tasks
Annual Energy SavingsSavings
(Lacs/Annum)Electrical (kWh)
Thermal (MTOE)
10 Line-1 Coal Mill Fan Inlet Damper Removal 297660 - 11.31
11 Line-1 Raw Mill Fan Inlet Damper Removal 363000 - 13.79
12 Ball Mill Close circuit separator fan inlet damper removal 376200 - 14.30
13 Slag Mill V-Separator fan inlet damper removal 281952 - 10.70
14 Slag Mill main & auxiliary Baghouse fans inlet damper removal 217800 - 8.27
15Removal of clinker silo bag filter damper & installation of DP transmitter toregulate the fan speed with VFD in PID loop.
556512 - 21.14
16Parallel kiln firing pipe line for petcoke of size 250 NB ( size reduced fromexisting 300 NB to 250 NB), to reduce the transport air quantity & in turnpower consumption.
309174 - 11.74
17Crusher main bag filter damper removal & intermittent stoppage of bag filtermaterial transport ckt. i.e. (2 nos screw conveyor)
264000 - 10.03
18 VFD installation at bag filter fan 332 FN1 & 332FNC 145200 - 5.51
Integrity Commitment Passion Seamlessness Speed
Energy Conservation Projects 2016-17
S.No. Energy Saving TasksAnnual Energy Savings Savings
(Lacs/Annum)Electrical (kWh) Thermal (MTOE)
19RP-1 V separator modification (increase in guide vanes height toincrease material retention time and to improve air flow).
2627976 - 99.8620 RP-1 feed gate zero position adjustment.
21Raw mill hopper feeding system modification to improve/ balancesegregation.
22Logic modification in RM transport circuit to eliminate idle runningof equipment
1082095 - 41.11
23Logic modification in RM additive hopper feeding circuit toeliminate idle running of equipment
772925 - 29.37
24DP point relocation to optimize PH outlet draft and to reduceRABH fan power
927521 - 35.24
25Increase in crusher output up to 1800 TPH & reduction in idlerrunning of Equipments
927520 - 35.24
26 Stopping of seal air fan after 2 hrs stoppage of line-1 Raw Mill 6878 - 0.26
Integrity Commitment Passion Seamlessness Speed
Energy Conservation Projects 2016-17
S.No. Energy Saving Tasks
Annual Energy SavingsSavings
(Lacs/Annum)Electrical (kWh)
Thermal (MTOE)
27 Orifice removal from line-2 coal mill fan duct 61835 - 2.34
28 Reduction of Pressure drop in downcomer duct of line-2 6449896 319.26
29 Arresting of air leakages in line-1 coal mill circuit 1238926 61.32
30 Arresting of air leakages in line-1 PH Calciner circuit 918720 45.47
31 Arresting of air leakages in line-1 ILC circuit 1573704 77.89
32 Arresting of air leakages in line-1 kiln string 148896 7.37
33 Arresting of air leakages in line-2 Roller Press Circuit (3 nos.) 10585080 523.96
34 Arresting of air leakages in line-2 coal mill circuit 1386000 68.60
35 Arresting of air leakages in line-2 PH circuit (String 1&2) 5513112 272.89
36 Arresting of air leakages in line-2 PH circuit (String 3&4) 6443712 318.96
Integrity Commitment Passion Seamlessness Speed
Energy Conservation Projects 2016-17
S.No. Energy Saving Tasks
Annual Energy SavingsSavings
(Lacs/Annum)Electrical (kWh)
Thermal (MTOE)
37 Arresting of air leakages in line-1 Raw Mill Circuit 2198592 - 108.83
38 Installation of EE pump of 450 m3/hr & 35 M head in place of WP 7/8 316008 - 15.64
39 Installation of PID based VFD at one compressor of line-2 245520 - 12.15
40 Slag feeding circuit modification & Extension of 611BC-3 145200 - 5.51
41 Running of stand by Blower 681BL6 stopped 49896 - 1.89
42 Improved the Generator terminal power factor from 0.91 to 0.95 - - 48.19
Integrity Commitment Passion Seamlessness Speed
Ongoing Projects 2017-19
Energy Conservation for the Future Generation
Integrity Commitment Passion Seamlessness Speed
Ongoing Encon Projects
S.No. Energy Saving Tasks
Energy Savings Capex Required (Rs. Lacs)
TargetElectrical (kWh)
Thermal (MTOE)
1 ABC Inlet modification in line-1 Cooler - 0.001067 250.00 Nov’17
260 nos VFD is to be installed in Bagfilters (>15 kW) and PID based operation after inlet damper removal
1980000 - 120.00 Oct’17
3 Installation of dedicated power line between RWCW and HCW - Mar’18
4 2 Nos. VFD installation in line-1 Cooler fans 178200 - 20.00 Nov’17
5 3 Nos. VFD installation in line-1 Coal firing blower 311256 - 32.00 Nov’17
6 Replacement of 2 nos line-1 Cooler fans with high efficient 122400 - 17.00 Nov’17
7 Installation of EE pump of 350 m3/hr & 60 M head in place of WP 14B pump 340243 - 7.00 Nov’17
8 Installation of EE pump of 200 m3/hr & 50 M head in place of WP 15B pump 272842 - 5.00 Nov’17
9 Installation of EE pump of 50 m3/hr & 50 M head in place of WP 12 51181 - 2.00 Nov’17
10Replacement of existing ELGI 821CP1 compressor with EE compressor in line-1
369468 - 20.00 Nov’17
11 Installation of VFD at 821CP4 compressor to save unload power in line-1 129730 - 5.00 Nov’17
Integrity Commitment Passion Seamlessness Speed
Ongoing Encon Projects
S.No. Energy Saving Tasks
Energy Savings Capex Required (Rs. Lacs)
TargetElectrical (kWh)
Thermal (MTOE)
12 Installation of VFD at 341CP3 compressor to save unload power in line-1 429660 - 10.00 Nov’17
13 Line-1 kiln String Top Cyclone Modification - 0.000446 N.A. Aug’17
14 Line-1 Kiln Burner Replacement with low NOx burner - 0.000342 Aug’17
15 Cement Mill ESP to Baghouse Conversion - - Sept’17
16 Line-1 Cooler Chimney Height Extension by 15.0 meter 396000 - 30.00 Nov’17
17Hot Air Recirculation connection to seal air pockets at SKS separator bottom of line-2 Roller Press (3 Nos)
- N.A. Sept’17
18 Replacement of line-1 Kiln String fan with high efficiency 396000 - 50.00 -
19 Replacement of line-1 PC String fan with high efficiency 1425600 - 50.00 -
20 Line-1 SLC Precalciner Modification - - 350.00 Nov’17
21 Line-1 Coal Mill Cyclones are to be removed to reduce excess pressure drop 726000 - 10.00 Nov’17
Integrity Commitment Passion Seamlessness Speed
GHG Inventorization
250300350400450500550
2014-15 2015-16 2016-17 NationalBM
506472 465 450
KG
CO
2/M
T O
F C
EMEN
T
Specific CO2 Emission
500
550
600
650
700
2014-15 2015-16 2016-17
676661 644
KG
CO
2/M
T O
F P
RO
DU
CT
Specific CO2 Emission
Cementitious Product Cement
* Lowest Carbon Footprints/Specific Emissions among all UltraTech plants
GO
OD
GO
OD
Integrity Commitment Passion Seamlessness Speed
Utilization of Renewable Energy
GREEN TOWNSHIP
800 KWp Solar Panels Installed in plant
Working since FY 2011-12
Colony Power requirement mainly catered through Solar power generation
700000
800000
900000
1000000
2014-15 2015-16 2016-17
840476913376
966506
KW
H
Solar Power Generation
GO
OD
Integrity Commitment Passion Seamlessness Speed
Utilization of Waste Material
List of Alternate fuel used at Rawan Cement Works WOODEN CHIPS
FMCG WASTE
MIX AGRO WASTE
PHARMA LIQUID
PHARMA SOLID
SAW DUST
SUGARCANE BAGGASE
PLASTIC WASTE
NON HAZARDOUS WASTES (POULRTY)
CASHEWNUT SHELL
COCONUT SHELL
FOOTWEAR SCRAP
250
300
350
400
450
500
550
2014-15 2015-16 2016-17
291.50
364.57
667.52
MET
RIC
TO
NN
E
AFR Consumption
GO
OD
In Q1 FY 2017-18: Total AFR Consumption = 625 MT
Integrity Commitment Passion Seamlessness Speed
Utilization of Waste Material
Plastic Waste Solid Pharma Waste FMCG Waste
Liquid Pharma WastePlastic Waste Charota
Integrity Commitment Passion Seamlessness Speed
Waste Heat Recovery System
Waste Heat Recovery System of 15 MW (6 nos.Boilers) at Rawan Cement Works is meant to operatecontinuously with any of the Clinkerisation systemrunning. Running of WHRS results in fossil fuelconservation, better environment and low power costdue to reduction in Grid and TPP power mix %
2
22
42
62
82
102
2014-15 2015-16 2016-17
83.26 80.1275.44
16.746.53
2.69
013.07
21.57
Power Mix % - Increase in WHRS Power Share
TPP GRID WHRS
GO
OD
Integrity Commitment Passion Seamlessness Speed
Best Practices in Green Supply Chain
Reuse Rakes
❖ Reverse Logistics in Fly Ash Bulker, Coal Wagons,
Raw Material Trucks (Hywa)
❖ Eye on Wheels – to reduce truck turnaround time
❖Maximise Bulk Cement Dispatches
100150200250
2015-16 2016-17
231259
NO
S.
Reverse Logistics – No. of Rakes
GO
OD
Integrity Commitment Passion Seamlessness Speed
Safety InitiativesWe Care For Safety
Unit’s Safety Best Practices
Gate meeting on every 1st day of month
Full Day Safety Round “One Day Safety Officer”
Mentor-Mentee Engagement of workers for Safety cultureimprovement
Extending safety beyond work place: First- Day, First –hour,Safety- hours & Bicycle helmet for ABPS School students
Safety Observation by all Management cadre employees(two nos. per month)
On the Job Safety awareness by animated cartoon/videosthrough “Safety Rath”
Daily Tool box talk at different location in plant
Theme based Safety Campaign on Monthly basis
Online Permit System
Online reporting system for EHS
Integrity Commitment Passion Seamlessness Speed
Glimpses of Safety Activities
Gate Meeting Theme Based Campaign
Theme Based CampaignGate Meeting
Daily Tool Box Talk
Daily Tool Box Talk
Integrity Commitment Passion Seamlessness Speed
Glimpses of Safety Activities
Safety Helmets for Students
Training on wheel
Mentor Mentee
Mentor Mentee Safety Awareness at School
Training By Animated Films
Integrity Commitment Passion Seamlessness Speed
Glimpses of Safety Activities
Foot over Bridge & Drop Gate Road Safety Initiative LOTOTO System
Foot over Bridge & Drop Gate LOTOTO System Road Safety Initiative
Integrity Commitment Passion Seamlessness Speed
Environmental Initiatives
Green Belt Development
5000
10000
15000
20000
25000
2014-15 2015-16 2016-17
21126
1514712982
19124
14214
11631
Area: Plant, Colony & Mines
No. of Sapling Planted Survived Plants
Rain Water Harvesting Pond
Entire water requirement for Plant and Colony is being fulfilled by Rain Water Pond
Unit is committed to develop Green Belt in Plant, Colony & Mines with cumulative survival rate of >90%
Integrity Commitment Passion Seamlessness Speed
Environmental Initiatives
Line-1 Raw Mill ESP to Baghouse Conversion FY 2016-17
Capex Amount: Rs. 21 Crore
Line-1 Coal Mill ESP to Baghouse Conversion FY 2016-17
Capex Amount: Rs. 6 Crore
Before: 50 mg/Nm3After: <20 mg/Nm3
Before: 50 mg/Nm3After: <20 mg/Nm3
Integrity Commitment Passion Seamlessness Speed
Environmental Initiatives
Covered Belt Conveyors Coal & Petcoke Shed
Limestone Pile Shed Green Township with LED Lights
Integrity Commitment Passion Seamlessness Speed
Green Township and Plant
Integrity Commitment Passion Seamlessness Speed
CSR Initiatives
State : ChhattisgarhDistrict : BalodabazarFamilies : 6197 Population : 30598
Adopted 22 Operational Villages
100
150
200
250
300
350
2014-15 2015-16 2016-17
235 226
308
253 253201
Expenditure Under CSRRs. Lacs
Budget Actual
GO
OD
Integrity Commitment Passion Seamlessness Speed
CSR Initiatives
Unit’s Key Focus Area under CSR are: Education, Health, Skill Development, Basic Needs like Road, Electricity, Water etc.
Scholarship Distribution
Medical CampDesk Bench in School
Plantation by MLA Health Centre
Concrete Road
Integrity Commitment Passion Seamlessness Speed
Glimpses of CSR Initiatives
Beauty Training Tailor Training IT Training
Mother School Lab Training Thela Distribution
Integrity Commitment Passion Seamlessness Speed
Glimpses of CSR Initiatives
Pond Cleaning Rangmanch Mass Marriage
Driving TrainingBorewellCommunity Centre
Integrity Commitment Passion Seamlessness Speed
Awards: Journey Towards Excellence
Rajiv Gandhi
CII
En
erg
y A
war
d
Exce
llen
ce in
In
no
vati
on
-C
WC
M
Raj
iv G
and
hi
Nat
ion
al Q
ual
ity
Ch
airm
an W
CM
GO
LD
Aw
ard
Stat
e -
Ene
rgy
Effi
cie
ncy
A
war
d b
y C
RED
A
(Co
nse
cuti
ve S
ince
20
14
)
IMC
Ram
a K
rish
na
Baj
aj
Qu
alit
y A
war
d
DL
Shah
Qu
alit
y A
war
d
(GO
LD)
CSR
Exc
elle
nce
Aw
ard
20
17
2008
2008
2008
2009
2011
2014
2015
2016
2017
CII 18th National Award for Excellence in Energy Management 2017
Integrity Commitment Passion Seamlessness Speed
Awards: Journey Towards Excellence
IMC Rama Krishna Bajaj National Quality Performance Excellence Trophy 2015
in Manufacturing Category
3rd Position in Overall Performance CategoryMines Environment & Mineral Conservation
2016
Integrity Commitment Passion Seamlessness Speed
Awards: Journey Towards Excellence
Energy Efficiency Award 2015 & 2016 in Cement Sector
organised by CREDA, Raipur
QCI - DL Shah Quality Awards 2016GOLD AWARD
organised at New Delhi
Integrity Commitment Passion Seamlessness Speed
Awards: Journey Towards Excellence
CSR India International Conclave - 2017 CSR Excellence Award 2017 - Project of the Year in
Cement Sector & Skill Development
Regional Level presentation in National Level Competition “REPRISM-2017” by Aditya Birla Group
in the category of Energy Conservation
Integrity Commitment Passion Seamlessness Speed