61
I-15 CORE On-Street Survey First Quarter 2012

UDOT Q1 2012 Report

Embed Size (px)

Citation preview

Page 1: UDOT Q1 2012 Report

I-15 COREOn-Street Survey

First Quarter 2012

Page 2: UDOT Q1 2012 Report
Page 3: UDOT Q1 2012 Report

Compiled by

Brigham Young UniversityApril 2012

Erik WestesenAccount Director

Thomas WhiteAccount Executive

Natalie SivertsenFrancesco LoliRebecca Lane

Account Coordinators

Rachel CoolManager, Bradley Public Relations

Page 4: UDOT Q1 2012 Report
Page 5: UDOT Q1 2012 Report

Table of ContentsExecutive Summary........................................................................................2Survey Instrument..........................................................................................4Q1 2012 Survey Results - Demographic Responses.........................5Q1 2012 Survey Results - Total..................................................................9 Question 1...............................................................................................10 Question 4...............................................................................................21Area Specific Results...................................................................................23 Demographic Responses by Area.................................................24 Question 1 by area...............................................................................29 Question 4 by area..............................................................................45Key Findings....................................................................................................53 Overall Results......................................................................................54 Detailed Results....................................................................................55

Page 6: UDOT Q1 2012 Report

2

Executive Summary

This booklet contains the results of the man-on-the-street survey research carried out by the Bradley Public Relations Agency at BYU in addition to phone survey researchconducted by Service Sampling International, for the first quarter of 2012.

Student volunteers and employees of the agency administered the surveys at retail and grocery stores in each of the four areas established by UDOT: American Fork/Pleasant Grove, Orem, Provo, and Spanish Fork/Springville (areas identified on the map on page 3). A total of 448 surveys were completed between March 24 - 31, 2012. Following collection, the data was analyzed and compared to the three preceding quarters, as seen throughout this report.

Here, the results are broken down by question and by area. First, we have included the demographic information of respondents included on the survey instrument (see page 4). Next, we included graphs showing the overall results for questions 1 and 4 as compared to Q2 2011 as well as Q3 and Q4 of 2011. Following this section we have provided the area specific results for questions 1 and 4. Finally, we have summarized our key findings, with a detailed look at overall trends.

For example, we observed an increase in the aggregate average score to 2.85 on a five-point scale with 1.00 meaning the most negative and 5.00 meaning the most positive. This was due in large part to a large increase in Spanish Fork/Springville’s overall average score.

These results represent a collective opinion of those sampled. Their responses, as con-tained in this report, serve as a quick snapshot of current public opinion regarding the I-15 Core Corridor Expansion project. It is important to note that the results of this survey are not statistically significant unless viewed as a whole; individual area samples are not sub-stantial enough to stand alone.

NotesPhone survey data is displayed separately from man-on-the-street data, and is not included in the overall average scores.

Some graphical representations omit data labels (number above a graph bar indicating value). This is due to the space required to show a whole year’s worth of data for certain data sets. Specific values are available on the CD enclosed within this booklet. Scale frequency has been increased to better compensate for this change.

Page 7: UDOT Q1 2012 Report

3

Zone 1 - Lehi, American Fork and Pleasant Grove exits. Surveys completed at American Fork WalMart and nearby locations.

Zone 2 - Orem exits. Surveys completed at University Mall and Costco.

Zone 3 - Provo exits. Surveys completed on BYU campus and nearby locations in Provo.

Zone 4 - Springville and Spanish Fork exits. Surveys completed at the Springville WalMart, Maceys in Spanish Fork and nearby locations.

Page 8: UDOT Q1 2012 Report

4

Survey Instrument

1. On a scale of one to five with one meaning completely disagree and five meaning completely agree,please rate the project on the following:

Please answer the following questions based on your experience in the past month with the I-15 CORE road construction project (on I-15 from Lehi Main Street to Spanish Fork Main Street).

1 2 3 4 5

1 2 3 4 5

1 2 3 4 5

1 2 3 4 5

1 2 3 4 5

1 2 3 4 5

1 2 3 4 5

1 2 3 4 5

1 2 3 4 5

1 2 3 4 5

1 2 3 4 5

Indifferent Agree

2. Which city do you live in?

Alpine American Fork Cedar Hills Eagle Mountain Highland Lehi Lindon Mapleton Orem Pleasant Grove Payson Provo Santaquin Saratoga Springs Spanish Fork Springville Vineyard Other (list)

_________________________ Refuse

4. Several methods are being used to help people stay informed about construction activities. Of the following methods, which ones do you use to stay informed about the I-15 construction project? Choose all that apply:

4 p.m. to 7 p.m. After 7 p.m.

Before 6 a.m. 6 a.m. to 9 a.m. 9 a.m. to 4 p.m.

Project e-mail updates Project website updates Electronic roadway signs Door hangers/fliers Radio messages Television

Social media (Facebook, Twitter, YouTube)

Local meetings/public events Newspaper stories or advertisements City newsletter/website

Thank you for your input! If you have additional comments or concerns, please write them below or on the back of this page.

I feel safe when driving through the construction zones.

Compared to other road construction projects I’ve experienced,

crews are maintaining a safe roadway.

Dust is kept under control.

Construction noise is kept under control.

Lane markings are clear.

Construction signs are easy to read.

The detour routes are clear and easy to navigate (or drive).

Access to I-15 on- and off-ramps has been maintained.

The construction crews are courteous.

Construction does not increase my travel time.

When compared to other roadway construction I have experienced,

the travel delays are reasonable.

Disagree

3. What time(s) of the day do you drive on I-15 the most? Choose all that apply:

Page 9: UDOT Q1 2012 Report

5

Q1 2012 Survey Results - Demographic Responses

Page 10: UDOT Q1 2012 Report

6

2. Which city do you live in?

0.00%  

5.00%  

10.00%  

15.00%  

20.00%  

25.00%  

30.00%  

35.00%  

Alpine

 

American  F

ork  

Cedar  H

ills  

Eagle

 Mounta

in  

Highla

nd  

Lehi  

Lindon  

Mapleton  

Orem

 

Pleasa

nt  Grove  

Payso

n  

Provo  

Santa

quin  

Sarat

oga  S

prings  

Spanish

 Fork  

Springville

 

Vineyard

 

Other/N

on-­‐Re

sponse  

On  the  Street  Survey  Results  

Q4  2011  

Q1  2012  

9  

27  

5  2  

12  

33  

10  

4  

88  

29  

19  

66  

9  7  

41  

23  

2  

14  

0  

10  

20  

30  

40  

50  

60  

70  

80  

90  

100  

Alpi

ne  

 Am

erican

 For

k  

 Ced

ar  H

ills  

 Eag

le  M

ount

ain  

 Hig

hlan

d  

 Leh

i  

 Lin

don  

 Map

leto

n  

 Ore

m  

 Ple

asan

t  Gro

ve  

 Pay

son  

 Pro

vo  

 San

taqu

in  

 Sar

atog

a  Sp

rings

 

 Spa

nish

 For

k  

 Spr

ingv

ille  

 Vin

eyar

d  

 Oth

er/N

on-­‐R

espo

nse  

Phone  Survey  Results  

Page 11: UDOT Q1 2012 Report

7

3. What time(s) of day do you drive on I-15 the most? Select all that apply.

3.36%  

21.68%  

36.13%  

29.58%  

9.24%  

0.00%  

5.00%  

10.00%  

15.00%  

20.00%  

25.00%  

30.00%  

35.00%  

40.00%  

Before  6  am    6-­‐9  am    9-­‐4  pm    4-­‐7  pm    a7er  7  pm  

Num

ber  o

f  Respo

nden

ts  

Phone  Sample  Travel  Times  Q1  2012  

0.00%  

5.00%  

10.00%  

15.00%  

20.00%  

25.00%  

30.00%  

35.00%  

40.00%  

Before  6  am   6-­‐9am   9-­‐4pm   4-­‐7pm   a6er  7  pm  

Travel  Times  by  Quarter  

Q2  

Q3  

Q4  

Q1  

Page 12: UDOT Q1 2012 Report

8

Page 13: UDOT Q1 2012 Report

9

Q1 2012 Survey Results - Total

Graphical Representations of Questions Comparative Q2 2011-Q1 2012

Page 14: UDOT Q1 2012 Report

10

1, p1: I feel safe when driving through the construction zones. (Scale of 1-5 with 1 meaning completely disagree and 5 meaning completely agree):

26.8%  

31.8%  

19.9%  

14.4%  

7.1%  

32.6%  31.6%  

19.6%  

10.3%  

5.9%  

30.8%  30.8%  

20.9%  

12.9%  

4.6%  

30.2%  

32.0%  

18.0%  

13.5%  

6.3%  

0%  

5%  

10%  

15%  

20%  

25%  

30%  

35%  

40%  

1   2   3   4   5  

I  Feel  Safe  -­‐  On  the  Street  

Q2  2011  

Q3  2011  

Q4  2011  

Q1  2012  

0.00%  

5.00%  

10.00%  

15.00%  

20.00%  

25.00%  

30.00%  

35.00%  

40.00%  

1   2   3   4   5  

I  Feel  Safe  Street  v.  Phone  

Street  Survey  Percentages  

Phone  Survey  Percentages  

Page 15: UDOT Q1 2012 Report

11

1, p2: Compared to other road construction projects I’ve experienced, crews are maintaining a safe roadway. (Scale of 1-5 with 1 meaning completely dis-agree and 5 meaning completely agree):

0.00%  

5.00%  

10.00%  

15.00%  

20.00%  

25.00%  

30.00%  

35.00%  

40.00%  

1   2   3   4   5  

Maintain  Safe  Roadway  Street  v.  Phone    

Street  Surveys    Percentages  

Phone  percentages  

14.7%  

20.1%  

27.9%   28.4%  

8.8%  

10.9%  

19.2%  

33.3%  

26.7%  

10.0%  

12.4%  

17.6%  

30.0%  29.1%  

11.0%  

0%  

5%  

10%  

15%  

20%  

25%  

30%  

35%  

1   2   3   4   5  

Maintain  Safe  Roadway  -­‐  On  the  Street  

Q3  2011  

Q4  2011  

Q1  2012  

Page 16: UDOT Q1 2012 Report

12

1, p3: Dust is kept under control (Scale of 1-5 with 1 meaning completely dis-agree and 5 meaning completely agree):

9.9%  

16.5%  

25.5%  

32.8%  

15.4%  

9.6%  

13.0%  

26.7%  

30.9%  

19.9%  

6.1%  

14.6%  

21.7%  

32.8%  

24.8%  

7.7%  

10.2%  

23.3%  

37.6%  

21.3%  

0%  

5%  

10%  

15%  

20%  

25%  

30%  

35%  

40%  

1   2   3   4   5  

Dust  -­‐  On  the  Street  

Q2  2011  

Q3  2011  

Q4  2011  

Q1  2012  

0.00%  

5.00%  

10.00%  

15.00%  

20.00%  

25.00%  

30.00%  

35.00%  

40.00%  

45.00%  

1   2   3   4   5  

Dust  -­‐  Street  v.  Phone    

Street  Surveys    Percentages  

Phone  Percentages  

Page 17: UDOT Q1 2012 Report

13

1, p4: Construction noise is kept under control. (Scale of 1-5 with 1 meaning completely disagree and 5 meaning completely agree):

0.00%  

5.00%  

10.00%  

15.00%  

20.00%  

25.00%  

30.00%  

35.00%  

40.00%  

45.00%  

1   2   3   4   5  

Noise  -­‐  Street  v.  Phone  

Street  Surveys    Percentages  

Phone  Percentages  

8.3%  

11.2%  

30.0%  

34.6%  

15.8%  

7.6%  

10.8%  

31.2%  

27.5%  

22.9%  

6.8%  

9.7%  

25.0%  

35.9%  

22.6%  

6.3%  

10.8%  

29.5%  

32.9%  

20.5%  

0%  

5%  

10%  

15%  

20%  

25%  

30%  

35%  

40%  

1   2   3   4   5  

Noise  -­‐  On  the  Street  

Q2  2011  

Q3  2011  

Q4  2011  

Q1  2012  

Page 18: UDOT Q1 2012 Report

14

1, p5: Lane markings are clear. (Scale of 1-5 with 1 meaning completely dis-agree and 5 meaning completely agree):

33.8%  

28.9%  

14.2%   15.2%  

7.8%  

38.1%  

29.1%  

16.3%  

11.4%  

5.1%  

39.0%  

30.4%  

15.3%  11.7%  

3.6%  

0%  

5%  

10%  

15%  

20%  

25%  

30%  

35%  

40%  

45%  

1   2   3   4   5  

Clear  Lane  Markings  -­‐  On  the  Street  

Q3  2011  

Q4  2011  

Q1  2012  

0.00%  

5.00%  

10.00%  

15.00%  

20.00%  

25.00%  

30.00%  

35.00%  

40.00%  

45.00%  

1   2   3   4   5  

Clear  Lane  Markings  -­‐  Street  v.  Phone  

Street  Surveys    Percentages  

Phone  Percentages  

Page 19: UDOT Q1 2012 Report

15

1, p6: Construction signs are easy to read. (Scale of 1-5 with 1 meaning com-pletely disagree and 5 meaning completely agree):

33.8%  

28.9%  

14.2%   15.2%  

7.8%  

38.1%  

29.1%  

16.3%  

11.4%  

5.1%  

39.0%  

30.4%  

15.3%  11.7%  

3.6%  

0%  

5%  

10%  

15%  

20%  

25%  

30%  

35%  

40%  

45%  

1   2   3   4   5  

Clear  Lane  Markings  -­‐  On  the  Street  

Q3  2011  

Q4  2011  

Q1  2012  

0.00%  

5.00%  

10.00%  

15.00%  

20.00%  

25.00%  

30.00%  

35.00%  

1   2   3   4   5  

Easy  to  Read  -­‐  Street  v.  Phone  

Street  Surveys    Percentages  

Phone  Percentages  

Page 20: UDOT Q1 2012 Report

16

1, p7: The detour routes are clear and easy to navigate (or drive). (Scale of 1-5 with 1 meaning completely disagree and 5 meaning completely agree):

18.6%  

25.7%  

28.9%  

20.6%  

6.2%  

26.0%  

30.9%  

20.6%  

15.2%  

7.4%  

27.7%  

25.8%   24.1%  

17.8%  

4.6%  

24.5%  

35.1%  

21.8%  

14.5%  

4.1%  

0%  

5%  

10%  

15%  

20%  

25%  

30%  

35%  

40%  

1   2   3   4   5  

Detours  -­‐  On  the  Street  

Q2  2011  

Q3  2011  

Q4  2011  

Q1  2012  

0.00%  

5.00%  

10.00%  

15.00%  

20.00%  

25.00%  

30.00%  

35.00%  

40.00%  

1   2   3   4   5  

Detours  -­‐  Street  v.  Phone  

Street  Surveys    Percentages  

Phone  Percentages  

Page 21: UDOT Q1 2012 Report

17

1, p8: Access to I-15 on- and off-ramps has been maintained. (Scale of 1-5 with 1 meaning completely disagree and 5 meaning completely agree):

19.3%  

28.5%  

19.8%  

23.4%  

9.0%  

21.6%  

25.2%  

23.0%  

18.1%  

8.6%  

17.1%  

24.0%  

24.7%  

23.2%  

11.0%  

15.6%  

20.3%  

28.0%  

26.0%  

10.2%  

0%  

5%  

10%  

15%  

20%  

25%  

30%  

1   2   3   4   5  

Ramps  -­‐  On  the  Street  

Q2  2011  

Q3  2011  

Q4  2011  

Q1  2012  

0.00%  

5.00%  

10.00%  

15.00%  

20.00%  

25.00%  

30.00%  

35.00%  

40.00%  

1   2   3   4   5  

Ramps  -­‐  Street  v.  Phone  

Street  Surveys    Percentages  

Phone  Percentages  

Page 22: UDOT Q1 2012 Report

18

1, p9: The construction crews are courteous. (Scale of 1-5 with 1 meaning com-pletely disagree and 5 meaning completely agree):

0.00%  

5.00%  

10.00%  

15.00%  

20.00%  

25.00%  

30.00%  

35.00%  

40.00%  

45.00%  

50.00%  

1   2   3   4   5  

Crews  -­‐  Street  v.  Phone  

Street  Surveys    Percentages  

Phone  Percentages  

19.3%  

28.5%  

19.8%  

23.4%  

9.0%  

21.6%  

25.2%  

23.0%  

18.1%  

8.6%  

17.1%  

24.0%  

24.7%  

23.2%  

11.0%  

15.6%  

20.3%  

28.0%  

26.0%  

10.2%  

0%  

5%  

10%  

15%  

20%  

25%  

30%  

1   2   3   4   5  

Ramps  -­‐  On  the  Street  

Q2  2011  

Q3  2011  

Q4  2011  

Q1  2012  

Page 23: UDOT Q1 2012 Report

19

1, p10: Construction does not increase my travel time. (Scale of 1-5 with 1 meaning completely disagree and 5 meaning completely agree):

40.7%  

26.3%  

16.3%  

11.2%  

5.6%  

50.7%  

20.8%  

8.6%  

7.4%  

12.5%  

47.1%  

22.8%  

12.6%  

8.0%  

9.5%  

46.8%  

22.7%  

13.1%  

8.8%   8.6%  

0%  

10%  

20%  

30%  

40%  

50%  

60%  

1   2   3   4   5  

Travel  Delays  -­‐  On  the  Street  

Q2  2011  

Q3  2011  

Q4  2011  

Q1  2012  

0.00%  

5.00%  

10.00%  

15.00%  

20.00%  

25.00%  

30.00%  

35.00%  

40.00%  

45.00%  

50.00%  

1   2   3   4   5  

Travel  Delays  -­‐  Street  v.  Phone  

Street  Surveys    Percentages  

Phone  Percentages  

Page 24: UDOT Q1 2012 Report

20

1, p11: When compared to other roadway construction I have experienced, the travel delays are reasonable. (Scale of 1-5 with 1 meaning completely disagree and 5 meaning completely agree):

11.3%  

19.6%  

26.3%  

32.3%  

10.6%  

25.0%   24.3%  

27.0%  

15.9%  

7.8%  

16.5%  

18.9%  

30.6%  

21.4%  

12.6%  

16.3%  

18.5%  

32.7%  

21.7%  

10.8%  

0%  

5%  

10%  

15%  

20%  

25%  

30%  

35%  

1   2   3   4   5  

Reasonable  Delays  -­‐  On  the  Street  

Q2  2011  

Q3  2011  

Q4  2011  

Q1  2012  

0.00%  

5.00%  

10.00%  

15.00%  

20.00%  

25.00%  

30.00%  

35.00%  

40.00%  

1   2   3   4   5  

Reasonable  Delays  -­‐  Street  v.  Phone  

Street  Surveys    Percentages  

Phone  Percentages  

Page 25: UDOT Q1 2012 Report

21

Snapshot of preferred communications methods across all areas; Q1 2012 (per-centage):

34.9%  

11.6%  

1.8%  

20.6%  

10.4%  

30.9%  

19.1%  

3.7%  

18.4%  

10.0%  

38.3%  

12.4%  

2.7%  

17.2%  

11.2%  

40.1%  

16.9%  

3.5%  

25.8%  

11.7%  

0%  

5%  

10%  

15%  

20%  

25%  

30%  

35%  

40%  

45%  

Television   Socia  media   Mee<ngs   Newspaper   City  newsleEer  

Preferred  Comm  (con-nued)  -­‐  On  the  Street  

Q2  2011  

Q3  2011  

Q4  2011  

Q1  2012  

9.3%  11.1%  

42.2%  

4.1%  

34.2%  

9.1%  

15.2%  

41.4%  

7.1%  

38.7%  

8.7%  

15.8%  

41.5%  

5.1%  

36.9%  

7.7%  

12.0%  

47.2%  

7.3%  

37.3%  

0%  

10%  

20%  

30%  

40%  

50%  

60%  

70%  

Project  email  updates  

Project  website  updates  

Electronic  roadway  signs  

Door  hangers/fliers   Radio  messages  

Preferred  Comm  -­‐  On  the  Street  

Q2  2011  

Q3  2011  

Q4  2011  

Q1  2012  

Page 26: UDOT Q1 2012 Report

22

10.7%  14.8%  

64.0%  

13.3%  

43.9%  

0%  

10%  

20%  

30%  

40%  

50%  

60%  

70%  

Project  email  updates  

Project  website  updates  

Electronic  roadway  signs  

Door  hangers/fliers   Radio  messages  

Preferred  Comm  -­‐  Phone  

Q1  2012  

43.6%  

8.2%  

6.9%  

33.7%  

18.1%  

0%  

5%  

10%  

15%  

20%  

25%  

30%  

35%  

40%  

45%  

50%  

Television   Socia  media   Mee<ngs   Newspaper   City  newsleEer  

Preferred  Comm  (con-nued)  -­‐  Phone  

Q1  2012  

Page 27: UDOT Q1 2012 Report

23

Area SpecificGraphical Representations of Questions

Scale in this section is actual number of responses and/or average from actual number of responses

Page 28: UDOT Q1 2012 Report

24

American Fork / Lehi (Past 2 Quarters)

0  

5  

10  

15  

20  

25  

30  

35  

Alpine

 

Amer

ican

 For

k  

Ceda

r  Hills  

Eagle  M

ount

ain  

High

land

 

Lehi  

Lind

on  

Map

leto

n  

Ore

m  

Plea

sant

 Gro

ve  

Pays

on  

Prov

o  

Sant

aquin  

Sara

toga

 Spr

ings

 

Span

ish  For

k  

Sprin

gville  

Vine

yard

 

Oth

er/N

on-­‐R

espo

nse  

American  Fork  Sample  CiKes  

Q3  2011   Q4  2011  

14  

32  

47  44  

17  

0  

10  

20  

30  

40  

50  

60  

Before  6  am   6-­‐9am   9-­‐4pm   4-­‐7pm   a4er  7  pm  

Num

ber  o

f  Respo

nden

ts  

American  Fork  Sample  Travel  Times  

Q4  2011  

Page 29: UDOT Q1 2012 Report

25

Orem (Past 2 Quarters)

1  

3   3  2  

0  1   1  

0  

42  

2   2  

31  

1  0  

4  2  

0  

12  

2  3   3  

5  

0  

3  

0  

2  

32  

1   1  

35  

2  

0  

8  

1  0  

13  

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

Alpi

ne  

Amer

ican

 Fo

rk  

Ceda

r  Hill

s  

Eagl

e  M

ount

ain  

High

land

 

Lehi

 

Lind

on  

Map

leto

n  

Ore

m  

Plea

sant

 Gr

ove  

Pays

on  

Prov

o  

Sant

aqui

n  

Sara

toga

 Sp

rings

 

Span

ish  F

ork  

Sprin

gvill

e  

Vine

yard

 

Oth

er/N

on-­‐

Resp

onse

 

Orem  Sample  CiMes  

12  

23  

45  

63  

43  

2  

37  

51  

63  

35  

0  

10  

20  

30  

40  

50  

60  

70  

Before  6  am   6-­‐9am   9-­‐4pm   4-­‐7pm   a4er  7  pm  

Num

ber  o

f  Respo

nden

ts  

Orem  Sample  Travel  Times  Q4  2011  Q1  2012  

Page 30: UDOT Q1 2012 Report

26

Provo (Past 2 Quarters)

0   1   0   0   1   1   0  2  

8  

1   0  

83  

0   0   1   2  0  

3  0   0   0   0  

2   1   0   0  

25  

0   0  

78  

0   0  2   2  

0  

9  

0  

10  

20  

30  

40  

50  

60  

70  

80  

90  

Alpi

ne  

Amer

ican

 For

k  

Ceda

r  Hill

s  

Eagl

e  M

ount

ain  

High

land

 

Lehi

 

Lind

on  

Map

leto

n  

Ore

m  

Plea

sant

 Gro

ve  

Pays

on  

Prov

o  

Sant

aqui

n  

Sara

toga

 Sp

rings

 

Span

ish  F

ork  

Sprin

gvill

e  

Vine

yard

 

Oth

er/N

on-­‐

Resp

onse

 

Provo  Sample  CiPes  

3  

24  

40  

47  

32  

7  

34  30  

64  

38  

0  

10  

20  

30  

40  

50  

60  

70  

Before  6  am   6-­‐9am   9-­‐4pm   4-­‐7pm   a5er  7  pm  

Num

ber  o

f  Respo

nden

ts  

Provo  Sample  Travel  Times  

Q4  2011  Q1  2012  

Page 31: UDOT Q1 2012 Report

27

Springville / Spanish Fork (Past 2 Quarters)

0   1   0   0   0   0   0  

12  

4  0   0  

5  

0   0  

6  

72  

0   1  0   0   0   0   0   0   1  4   3  

0  

6  

0  

7  

0  

65  

14  

0  

10  

0  

10  

20  

30  

40  

50  

60  

70  

80  

Alpi

ne  

Amer

ican

 For

k  

Ceda

r  Hill

s  

Eagl

e  M

ount

ain  

High

land

 

Lehi

 

Lind

on  

Map

leto

n  

Ore

m  

Plea

sant

 Gro

ve  

Pays

on  

Prov

o  

Sant

aqui

n  

Sara

toga

 Spr

ings

 

Span

ish  F

ork  

Sprin

gvill

e  

Vine

yard

 

Oth

er/N

on-­‐R

espo

nse  

Springville  Sample  CiOes  

11  

36  

46  48  

21  

6  

30  

55  

51  

25  

0  

10  

20  

30  

40  

50  

60  

Before  6  am   6-­‐9am   9-­‐4pm   4-­‐7pm   a5er  7  pm  

Num

ber  o

f  Respo

nden

ts  

Springville  Sample  Travel  Times  Q4  2011  Q1  2012  

Page 32: UDOT Q1 2012 Report

28

Phone Survey

9  

27  

5  2  

12  

33  

10  

4  

88  

29  

19  

66  

9  7  

41  

23  

2  

14  

0  

10  

20  

30  

40  

50  

60  

70  

80  

90  

100  

Alpi

ne  

 Am

erican

 For

k  

 Ced

ar  H

ills  

 Eag

le  M

ount

ain  

 Hig

hlan

d  

 Leh

i  

 Lin

don  

 Map

leto

n  

 Ore

m  

 Ple

asan

t  Gro

ve  

 Pay

son  

 Pro

vo  

 San

taqu

in  

 Sar

atog

a  Sp

rings

 

 Spa

nish

 For

k  

 Spr

ingv

ille  

 Vin

eyar

d  

 Oth

er/N

on-­‐R

espo

nse  

Phone  Survey  Results  

3.36%  

21.68%  

36.13%  

29.58%  

9.24%  

0.00%  

5.00%  

10.00%  

15.00%  

20.00%  

25.00%  

30.00%  

35.00%  

40.00%  

Before  6  am    6-­‐9  am    9-­‐4  pm    4-­‐7  pm    a7er  7  pm  

Num

ber  o

f  Respo

nden

ts  

Phone  Sample  Travel  Times  Q1  2012  

Page 33: UDOT Q1 2012 Report

29

Question 1 by area:On a scale of one to five with one meaning completely disagree and five meaning

completely agree, please rate the project on the following:

Page 34: UDOT Q1 2012 Report

30

Area responses to Question 1 Categories by area (averages on a 1-5 scale):

1  1.25  1.5  

1.75  2  

2.25  2.5  

2.75  3  

3.25  3.5  

3.75  4  

4.25  4.5  

4.75  5  

Safe   Dust     Noise   Easy  to  read  signs  

Clear  and  navigable  detours  

Ramps   Crews  courteous  

No  delays   Reasonable  delays  

Overall  response  

Safe  roadway  

Clear  lane  markings  

American  Fork  Q2  2011   Q3  2011   Q4  2011   Q1  2012  

1  1.25  1.5  

1.75  2  

2.25  2.5  

2.75  3  

3.25  3.5  

3.75  4  

Safe   Dust     Noise   Easy  to  read  signs  

Clear  and  navigable  detours  

Ramps   Crews  courteous  

No  delays   Reasonable  delays  

Overall  response  

Safe  roadway  

Clear  lane  markings  

Orem  Q2  2011   Q3  2011   Q4  2011   Q1  2012  

Page 35: UDOT Q1 2012 Report

31

1  1.25  1.5  

1.75  2  

2.25  2.5  

2.75  3  

3.25  3.5  

3.75  4  

4.25  4.5  

4.75  5  

Safe   Dust     Noise   Easy  to  read  signs  

Clear  and  navigable  detours  

Ramps   Crews  courteous  

No  delays   Reasonable  delays  

Overall  response  

Safe  roadway  

Clear  lane  markings  

Provo  Q2  2011   Q3  2011   Q4  2011   Q1  2012  

1  

1.5  

2  

2.5  

3  

3.5  

4  

4.5  

5  

Safe   Dust     Noise   Easy  to  read  signs  

Clear  and  navigable  detours  

Ramps   Crews  courteous  

No  delays   Reasonable  delays  

Overall  response  

Safe  roadway  

Clear  lane  markings  

Spanish  Fork  Q2  2011   Q3  2011   Q4  2011   Q1  2012  

Page 36: UDOT Q1 2012 Report

32

Average aggregate Question 1 responses by area (averages of all Question 1 categories on a 1-5 scale):

3.01  

3.99   3.98  

3.18  2.87  

3.38  

4.07  

2.53  

3.38   3.32   3.54  

2.61  

1  

1.5  

2  

2.5  

3  

3.5  

4  

4.5  

5  

Safe   Dust     Noise   Easy  to  read  signs  

Easy  to  follow  

Clear  and  navigable  detours  

Ramps   Crews  courteous  

No  delays   Reasonable  delays  

Overall  response  

Safe  roadway  

Clear  lane  markings  

Phone  Q1  2012  

2.73  

2.87   2.98  

2.85   2.86  2.7  

2.94   2.94  

2.5  

2.77  2.75   2.7  

3.02  2.93  

2.85  2.76  

2.94  2.77  

2.91   2.94  

3.32  

1  

1.5  

2  

2.5  

3  

3.5  

4  

4.5  

5  

American  Fork   Orem   Provo   Spanish  Fork   All     Phone  

Q2  2011   Q3  2011   Q4  2011   Q1  2012  

Page 37: UDOT Q1 2012 Report

33

Aver

age

resp

onse

s to

all Q

uest

ion

1 ca

tego

ries

rega

rdle

ss o

f are

a (1

to 5

scal

e):

2.34

 

3.54

 3.51

 

2.72

 

2.39

 

2.95

 

3.66

 

2.10

 

2.93

 2.94

 3.09

 

2.11

 

1  1.25

 1.5  

1.75

 2  2.25

 2.5  

2.75

 3  3.25

 3.5  

3.75

 4  4.25

 4.5  

4.75

 5  

Safe  

Dust    

Noise  

Easy  to

 read  

signs  

Clear  a

nd  

navigable  

detours  

Ramps  

Crew

s  courteou

s  No  de

lays  

Reason

able  

delays  

Overall  

respon

se  

Safe  ro

adway  Clear  lane  

markings  

Q2  20

11  

Q3  20

11  

Q4  20

11  

Q1  20

12  

Page 38: UDOT Q1 2012 Report

34

I feel safe when driving through the construction zones (average response on a 1 to 5 scale):

32  

28  

25  

16  

9  

39  

38  

15  

8  

5  

30  

24  23  

23  

1  

38  

25  

19   18  

4  0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

1   2   3   4   5  

American  Fork  -­‐  "Safe"  

32  

35  

22  

14  

8  

24  

28  

23  

16  

10  

37  

40  

18  

4  

8  

27  

35  

28  

11  10  

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

1   2   3   4   5  

Orem  -­‐  "Safe"  

21  

43  

18  

20  

6  

28  

33  

22  

13  

6  

29  27  

24  

16  

7  

28  

51  

14  

18  

8  

0  

10  

20  

30  

40  

50  

60  

1   2   3   4   5  

Provo  -­‐  "Safe"  

32   33  

22  

13  

8  

42  

30  

20  

5  3  

31  

36  

21  

10  

3  

41  

31  

19  

13  

6  

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

1   2   3   4   5  

Spanish  Fork  -­‐  "Safe"  

2.47  

2.38  2.51  

2.37  

2.07  

2.6  

2.37  

1.97  

2.42  

2.12  

2.47  

2.19  2.28  

2.48   2.39  

2.2  

3.01  

1  

1.5  

2  

2.5  

3  

3.5  

4  

4.5  

5  

American  Fork   Orem   Provo   Spanish  Fork   Phone  

Q2  2011  

Q3  2011  

Q4  2011  

Q1  2012  

Page 39: UDOT Q1 2012 Report

35

Compared to other road construction projects I’ve experienced, crews are maintaining a safe roadway (average response on a 1 to 5 scale):

16  

21  

32  

24  

12  14  14  

33  33  

7  

21  

14  

26  

33  

10  

0  

5  

10  

15  

20  

25  

30  

35  

1   2   3   4   5  

American  fork  -­‐  "Maintain  Safe  Roadway"  

10  

12  

34  35  

10  

15  

24  

40  

18  

10  9  

19  

39  

30  

14  

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

1   2   3   4   5  

Orem  -­‐  "Maintain  safe  roadway"  

15  

21  

15  

40  

11  

6  

23  

33  

27  

14  13  

20  

41  

33  

12  

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

1   2   3   4   5  

Provo  -­‐  "Maintain  safe  roadway"  

19  

28  

33  

17  

3  

10  

18  

31  32  

10  

12  

25  

27  

33  

13  

0  

5  

10  

15  

20  

25  

30  

35  

1   2   3   4   5  

Spanish  Fork  -­‐  "Maintain  Safe  Roadway"  

2.95  

3.23  3.11  

2.57  

3.05  

2.85  

3.19   3.14  2.97  

3.19   3.09   3.09  

3.54  

0  

0.5  

1  

1.5  

2  

2.5  

3  

3.5  

4  

American  Fork   Orem   Provo   Spanish  Fork   Phone  

Q3  2011  

Q4  2011  

Q1  2012  

Page 40: UDOT Q1 2012 Report

36

Dust is kept under control (average response on a 1 to 5 scale):

11  

19  

28  

35  

17  

11  

4  

13  

31  

36  

16  13   14  

19  

32  

26  

0  

5  

10  

15  

20  

25  

30  

35  

40  

1   2   3   4   5  

American  Fork  -­‐  "Dust"  

14  

18  

22  

36  

21  

5  

16  

29  

32  

19  

9  

20  

15  

30  

33  

5  

17  

29  

37  

23  

0  

5  

10  

15  

20  

25  

30  

35  

40  

1   2   3   4   5  

Orem  -­‐  "Dust"  

8  

13  

29  

38  

19  

6  

18  

25  26  

27  

5  

14  

20  

36  

28  

9  11  

34  

40  

24  

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

1   2   3   4   5  

Provo  -­‐  "Dust"  

10  

22  

32  

34  

10  

15  

8  

29  

34  

14  

7  

13  

23  

33  

25  

7  3  

21  

57  

21  

0  

10  

20  

30  

40  

50  

60  

1   2   3   4   5  

Spanish  Fork  -­‐  "Dust"  

3.25   3.29  3.44  

3.11  

3.37   3.44   3.49  

3.24  

3.47   3.54  

3.66  3.55  

3.42  3.5   3.5  

3.75  

3.99  

1  

1.5  

2  

2.5  

3  

3.5  

4  

4.5  

5  

American  Fork   Orem   Provo   Spanish  Fork   Phone  

Q2  2011  

Q3  2011  

Q4  2011  

Q1  2012  

Page 41: UDOT Q1 2012 Report

37

Construction noise is kept under control (average response on a 1 to 5 scale):

6  

14  

37  

36  

17  

12  13  

27  

29  

24  

6  5  

36  

38  

16  

10  9  

32  

29  

24  

0  

5  

10  

15  

20  

25  

30  

35  

40  

1   2   3   4   5  

American  Fork  -­‐  "Noise"  

12  

16  

28  

34  

20  

3  

13  

32  

27   26  

12  

10  

27  

30  

28  

3  

9  

40  

36  

23  

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

50  

1   2   3   4   5  

Orem  -­‐  "Noise"  

11  

8  

29  

41  

19  

4  

8  

33  

27  

30  

5  

13  

17  

40  

28  

12  

19  

30  

36  

22  

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

1   2   3   4   5  

Provo  -­‐  "Noise"  

7  

11  

37  

40  

13  12  

10  

35  

29  

13  

5  

12  

23  

40  

21  

3  

11  

29  

45  

22  

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

50  

1   2   3   4   5  

Spanish  Fork  -­‐  "Noise"  

3.4  

3.31  

3.45  

3.38  3.38  

3.59  3.7  

3.21  

3.52   3.49  

3.71  

3.59  3.46  

3.6  

3.31  

3.65  

3.98  

1  

1.5  

2  

2.5  

3  

3.5  

4  

4.5  

5  

American  Fork   Orem   Provo   Spanish  Fork   Phone  

Q2  2011  

Q3  2011  

Q4  2011  

Q1  2012  

Page 42: UDOT Q1 2012 Report

38

Lane markings are clear (average response on a 1 to 5 scale):

39  

27  

15  13  

11  

39  

37  

14  

9  

2  

49  

27  

14  11  

3  

0  

10  

20  

30  

40  

50  

60  

1   2   3   4   5  

American  fork  -­‐  "Lanes  markings  clear"  

28   31  

16  

15   11  

48  

24   22  

9  

4  

39  34  

16  

16  

6  

0  

10  

20  

30  

40  

50  

60  

1   2   3   4   5  

Orem  -­‐  "Lane  markings  clear"  

26  

36  

13  

19  

8  

33  

28  

12  

19  

11  

47  

37  

19  

12  

4  

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

50  

1   2   3   4   5  

Provo  -­‐  "Lane  Markings  Clear"  

45  

24  

14  

15  

2  

37  

31  

19  

10  

4  

38  37  

19  

13  

3  

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

50  

1   2   3   4   5  

Spanish  Fork  -­‐  "Lane  Markings  Clear"  

2.33  2.5   2.48  

2.05  1.99   2.04  

2.49  

2.14  1.96  

2.24  2.07  

2.15  

2.61  

0  

0.5  

1  

1.5  

2  

2.5  

3  

American  Fork   Orem   Provo   Spanish  Fork   Phone  

Q3  2011  

Q4  2011  

Q1  2012  

Page 43: UDOT Q1 2012 Report

39

Construction signs are easy to read (average response on a 1 to 5 scale):

40  

27  

21  

15  

7  

21  

30  

25  

19  

10  

31  

28  

18  17  

7  

24   25  

25  

22  

8  

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

1   2   3   4   5  

American  Fork  -­‐  "Easy  to  Read"  

25  

32  

24  19  

11  

17  

19  

26  

21  

18  

37  

16  

26  

16  

12  16  

27  

29  

29  

10  

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

50  

1   2   3   4   5  

Orem  -­‐  "Easy  to  Read"  

30  

24  

14  

31  

7  

17  19  

16  

35  

15  

20   21   23  

25  

14  

25  

33  

24  

29  

8  

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

50  

1   2   3   4   5  

Provo  -­‐  "Easy  to  Read"  

33  

35  

12  

15  

13  

25  

30  

19  

20  

6  

19  

26  

23  

25  

8  

25  24  

30  

24  

5  

0  

5  

10  

15  

20  

25  

30  

35  

40  

1   2   3   4   5  

Spanish  Fork  -­‐  "Easy  to  Read"  

2.29  

2.63   2.63  

2.44  

2.69  

3.04  3.12  

2.52  2.42  

2.53  

2.92  2.77  

2.66  

2.91  

2.68   2.63  

3.18  

1  

1.5  

2  

2.5  

3  

3.5  

4  

4.5  

5  

American  Fork   Orem   Provo   Spanish  Fork   Phone  

Q2  2011  

Q3  2011  

Q4  2011  

Q1  2012  

Page 44: UDOT Q1 2012 Report

40

The detour routes are clear and easy to navigate (or drive) [average response on a 1 to 5 scale]:

25  

32  32  

18  

3  

30  29  

21  19  

6  

25  

32  

23  20  

1  

32  

29  

22  20  

1  0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

50  

1   2   3   4   5  

American  Fork  -­‐  "Detours"  

46  

21  

19  

14  

7  

22  

36  

17  16  

10  

40  

26  

24  

13  

4  

21  

46  

20  17  

7  

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

50  

1   2   3   4   5  

Orem  -­‐  "Detours"  

12  

28  

31  

29  

8  

16  

35  

22  19  

10  

26   26  25  

17  

9  

26  

48  

25  

17  

3  0  

10  

20  

30  

40  

50  

60  

1   2   3   4   5  

Provo  -­‐  "Detours"  

19  

26  

32  

23  

8  

38  

26  

24  

8  

4  

23   22  

27  

23  

5  

29  

32  

29  

10  

7  

0  

5  

10  

15  

20  

25  

30  

35  

40  

1   2   3   4   5  

Spanish  Fork  -­‐  "Detours"  

2.47  

2.64  

2.94  

2.77  

2.45  2.56  

2.73  

2.14  

2.41  

2.21  

2.58  2.65  

2.32  

2.49  2.35  

2.39  

2.87  

1  

1.5  

2  

2.5  

3  

3.5  

4  

4.5  

5  

American  Fork   Orem   Provo   Spanish  Fork   Phone  

Q2  2011  

Q3  2011  

Q4  2011  

Q1  2012  

Page 45: UDOT Q1 2012 Report

41

Access to I-15 on- and off-ramps has been maintained (average response on a 1 to 5 scale):

32  

26  

20  

24  

8  

28   28  26  

15  

8  

18  

27  26   25  

5  

18  19  

26  

34  

7  

0  

5  

10  

15  

20  

25  

30  

35  

40  

1   2   3   4   5  

American  Fork  -­‐  "Ramps"  

14  

34  

23   26  

13  

18  

26  

27  

19  

11  

24  

28  

21  

18   16  17  

23  

30  

29  

12  

0  

5  

10  

15  

20  

25  

30  

35  

40  

1   2   3   4   5  

Orem  -­‐  "Ramps"  

18  

32  

21  

26  

10  

21  

22  

20  

25  

14  14  

26  

29  

20  

13  

17  

27  

39  

23  

13  

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

1   2   3   4   5  

Provo  -­‐  "Ramps"  

20  

32  

22  

26  

8  

35  

27  

21  

15  

2  

14  

17  

25  

32  

11  

17  

21  

29   29  

13  

0  

5  

10  

15  

20  

25  

30  

35  

40  

1   2   3   4   5  

Spanish  Fork  -­‐  "Ramps"  

2.55  

2.91  

2.79  2.72  

2.5  

2.79   2.89  

2.22  

2.72   2.76  

2.92  3.09  

2.93   2.96   2.9  3  

3.38  

1  

1.5  

2  

2.5  

3  

3.5  

4  

4.5  

5  

American  Fork   Orem   Provo   Spanish  Fork   Phone  

Q2  2011  

Q3  2011  

Q4  2011  

Q1  2012  

Page 46: UDOT Q1 2012 Report

42

The construction crews are courteous. (average response on a 1 to 5 scale):

4  

8  

41  

34  

23  

6   9  

32  

35  

23  

5   7  

30  33  

25  

4  

9  

37  

30  

24  

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

50  

1   2   3   4   5  

American  Fork  -­‐  "Crews"  

7  9  

30  

31   33  

8  

5  

35  

30  

23  

7   7  

50  

20  

23  

2   3  

47  

39  

20  

0  

10  

20  

30  

40  

50  

60  

1   2   3   4   5  

Orem  -­‐  "Crews"  

2  

5  

28  

43  

28  

5  5  

40  

28  

24  

3   2  

41  

30  

27  

5  

6  

50  

32  

25  

0  

10  

20  

30  

40  

50  

60  

1   2   3   4   5  

Provo  -­‐  "Crews"  

2  4  

23  

46  

33  

19  

6  

36  

20  

19  

6  

5  

31  33  

26  

2  

8  

23  

47  

29  

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

50  

1   2   3   4   5  

Spanish  Fork  -­‐  "Crews"  

3.58  3.67  

3.85  3.96  

3.57   3.54   3.6  

3.14  

3.66  

3.42  

3.74  3.67  

3.59   3.65  3.56  

3.85  

4.07  

1  

1.5  

2  

2.5  

3  

3.5  

4  

4.5  

5  

American  Fork   Orem   Provo   Spanish  Fork   Phone  

Q2  2011  

Q3  2011  

Q4  2011  

Q1  2012  

Page 47: UDOT Q1 2012 Report

43

Construction does not increase my travel time. (average response on a 1 to 5 scale):

46  

30  

21  

8  

5  

57  

22  

10  

6  

10  

53  

31  

9  

4   4  

55  

18  

11   13  

7  

0  

10  

20  

30  

40  

50  

60  

1   2   3   4   5  

American  Fork  -­‐  "Time  Delays"  

45  

18  

6  

11  

21  

61  

16  13  

5  

12  

44  

27  

19  

6  

15  

0  

10  

20  

30  

40  

50  

60  

70  

1   2   3   4   5  

Orem  -­‐  "Time  Delays"  

35  

33  

16  15  

6  

46  

27  

10  9   10  

42  

22  

14   14  11  

67  

28  

9  

5  

10  

0  

10  

20  

30  

40  

50  

60  

70  

80  

1   2   3   4   5  

Provo  -­‐  "Travel  Delays"  

48  

29  

14  11  

6  

59  

18  

9  

4  

10  

38  

25  

16  

10  

12  

42  

28  

19  

15  

6  

0  

10  

20  

30  

40  

50  

60  

70  

1   2   3   4   5  

Spanish  Fork  -­‐  "Time  Delays"  

2.05  2.21  

2.28  

2.06  1.95  

2.46  

2.12  

1.88  1.76  

1.98  

2.32   2.34  

2.03  

2.29  

1.85  

2.23  

2.53  

1  

1.5  

2  

2.5  

3  

3.5  

4  

4.5  

5  

American  Fork   Orem   Provo   Spanish  Fork   Phone  

Q2  2011  

Q3  2011  

Q4  2011  

Q1  2012  

Page 48: UDOT Q1 2012 Report

44

When compared to other roadway construction i have experienced, the travel delays are reasonable. (average response on a 1 to 5 scale):

14  

20  

27  

38  

10  

24  

26  

26  

15  

10  

23  

26   27  

21  

10  

14  

18  

42  

26  

11  

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

1   2   3   4   5  

Orem  -­‐  "Reasonable"  

15  

24  

31  32  

8  

27  

31  

25  

16  

6  

21  

18  

33  

18  

11  

24  

15  

34  

21  

9  

0  

5  

10  

15  

20  

25  

30  

35  

40  

1   2   3   4   5  

American  fork  -­‐  "Reasonable"  

8  

21  

26  

38  

14  

25  

19  

28  

22  

8  

14  

16  

29  

27  

17  

19  

29  

38  

21  

12  

0  

5  

10  

15  

20  

25  

30  

35  

40  

1   2   3   4   5  

Provo  -­‐  "Reasonable"  

12  

20  

30  32  

14  

26  23  

31  

12  

8  10  

18  

37  

22  

14  15  

20  

31  

28  

16  

0  

5  

10  

15  

20  

25  

30  

35  

40  

1   2   3   4   5  

Spanish  Fork  -­‐  "Reasonable"  

2.95  3.09  

3.27  3.15  

2.46  2.61  

2.7  

2.53  

2.8  2.71  

3.17  3.12  

2.77  

3.02  

2.82  

3.09  

3.38  

1  

1.5  

2  

2.5  

3  

3.5  

4  

4.5  

5  

American  Fork   Orem   Provo   Spanish  Fork   Phone  

Q2  2011  

Q3  2011  

Q4  2011  

Q1  2012  

Page 49: UDOT Q1 2012 Report

45

Question 4 by area:

Several methods are being used to help people stay informed about construction activities. Of the following methods, which ones do you use to stay informed about the I-15

construction project? Choose all that apply:

Metric is actual number of responses out of ~100 respondent sample. Because each sample is out of ~100, this is essentially interchangeable with a percentage.

Page 50: UDOT Q1 2012 Report

46

0  5  

10  15  20  25  30  35  40  45  50  55  60  65  

Email   Website   Electronic  Roadway  Signs  

 Door  Hangers  

Radio   TV    Social    Media  

Local      Events    Newspapers  

 City    Website  

American  Fork  

0  5  

10  15  20  25  30  35  40  45  50  55  60  65  

Email   Website   Electronic  Roadway  Signs  

 Door  Hangers  

Radio   TV    Social    Media  

Local      Events    Newspapers  

 City    Website  

Orem  

Page 51: UDOT Q1 2012 Report

47

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

50  

55  

60  

Email   Website   Roadway  signs  Door  Hangers   Radio   TV   Social  Media   Local  Events   Newspapers   City  Website  

Provo  

0  

5  

10  

15  

20  

25  

30  

35  

40  

45  

50  

55  

Email   Website   Electronic  Roadway  Signs  

 Door  Hangers  

Radio   TV    Social    Media  

Local      Events    Newspapers  

 City    Website  

Spanish  Fork  

Page 52: UDOT Q1 2012 Report

48

Free Response by area:American Fork:

• Whenfreewaytrafficisbad-citydrivingisoutofcontrol!• Theblindentrancesontofreewayareahugehazard.Therockchipssuck!• Idon’ttravelSouthveryoften.I’mnottoosureoftheroadconditionsthatdirection.• Iwasalmostinanaccident.• Whenexitsarechangedyouneedtogivebetternoticetoallowchangeoflanes.I’vemissedexits

becauseIdidn’tseesignageanddidn’tknowexitswereearlierthanexpected.• Thestreetsareridiculoustodriveon.Theyareunsafeandpacked-toomanyaccidents.• ItisBullshit.IhavedroveI-15onseveraloccassionsandbarrellshavebeenblowingintooncoming

traffic.• NotSAFE!Iusedtoownanexcavationcompanyandwehadtohaveatrafficcontrolplanapprovedby

UDOT.WhereisUDOTNOW?• Thankyouforchangingmytire.I’msogreatful!• Whereistheplanning?• TheworstsigningandetcisgoingsouthandturningofftouniversityexitorstayingonI-15.• Idon’tdriveonI-15veryoften.ItrytostayinAFasmuchaspossible

Orem:

• Ihavetodriveitanywaysoitdoesn’tmatter• Iwishtheywouldhurryupandfinishsowecanmoveonwithourlives!• Idon’ttravelalot.

Spanish Fork: • Workingonallthemajorsideroadsandfrontageroadsaswellasthefreewaymakesitdifficultand frustrating.

Provo:

• Iwishthesignswereeasiertonotice(i.e.ProvoCenterStreet,exit).TheyblendinwiththeorangeallaroundTheremovalofoldlanelines,additionoftemplines,cones,andvaryingasphaltcolorsmakeithardtonavigateandunderstandtrafficpattern.Idoappreciatetheworkbeingdoneandunderstandthenecessitybuttheeverywhere-nessofitistiresomeandveryinconvenient.IfitwereclearerandifIhaddonemoretobeinformed,itwouldbebetter.Thelanesareroughtounderstand.

• Themainthingtheycouldimproveisroadsignsandlanemarkings.Sometimesyoucan’ttellwhatyourlaneis,creatingincreaseddanger.Lackofadvancedwarning,inparticularlanereduction,seemtobethebiggestcauseoftrafficjams.Driversdon’thaveenoughwarningtochangelanes,leadingtobackingupwhentheytrytochangeatthelastmoment.

Page 53: UDOT Q1 2012 Report

49

Phone Free Response by area:

American Fork:

• Iwishitwasdone.• Thelanemarkingareconfusingattheoff-rampsontheSouthboundrouteintheUniversityhighway.• It’sreallyunsafe.They’resplittingexits,andit’sjustdangerous.• Theyhavedonearemarkablejobtomaintainthesafetyandcleanlinessoftheroad,evenifthe

constructionisstillgoingon.• Thepreviouslanemarkingwasn’terasedclearlycausingthepreviouslaneandthecurrentlanemarkingsto

becombined.• Therewasasignthatsays21milesnorthofLehi,butitwasnot.Theirsignsareconfusing.Theyneedto

dosomethingonit.Whenmyfrienddrovethere,shewaslostbecauseofthewrongsign.Weneedtohaveatrafficlightbadly.

• Ihadanaccidentonthefreeway.IhadaverypositiveresponsefromProvoofficeronthehighway.Thelanemarkingsisextremelydifficultandpeoplearegettinghighlyconfused,especiallywhenitrains.Theyneedtofigureoutabetterwaytomarkthecurrentlaneandgetridoftheoldlane.

Orem:

• Onvariousroadsides,therearesignsthatsaysomanyminutesthatwayandsomanyminutesthisway.Ican’tsaythatimpactsthedriver’sdecision.Idon’tthinkthatitishelpfulonewayoranother.It’sabigwasteofmoney.UDOTisdoingagoodjob,though.

• Iamgratefulandfeelwonderfulthattheyhavedonethis,butIfeelanxiouswhenIamridingontheroad.Theyarechangingthechannelsthatwearegoingthrough,anditfillsmewithsomuchanxiety.Ireallyneedtofocusandbeattentivebecausethelinesareveryobviousthatitisfilled.Overall,UDOThasdoneaverygoodjob,anditisachallengingjob.Theelectronicsignsaregood.Thecrewswerecourteous.It’sagoodthingthattherearenoaccidentsthathavehappened.

• Theyneedmorepatrolmenbecauseweusedtotravelonthatroad.• They’vegottoaccommodatecommutertrafficathightraffictimes.Theycannotarbitrarilyclosemajor

thoroughfareswithoutproperadvancedwarning,likeUniversityparkways.• Sometimes,thelanemarkingsarehardtodetermineatnight.• Byusingorangepaintinremarkingconstructionlanes,thereisgreatervisibilitythatwouldresultforthe

drivers.• Signsareclearlydoneinroads.InSpanishFork,Idonotfeelsafeinthatarea.• TheentrancetoProvoistooslowintheI-15.Thereistrafficcongestion.• TheonlyconcernIhaveisonthecenterstreetinOrem.Thelightsthereandonthe12thWestarenot

coordinatedwell,sothereisahugebackup.• It’saboutwideningtheroadtohavethreetosixlanes.Itshouldonlytaketwomonths,andthat’sthe

most.• Wethinktheyhaveaverygoodjobintrafficcontrolconsideringthatitisacomplexproject.Theyhave

doneitverywell.• Myonlyconcernisthatthereisthatonesectiononthe15thsouthnear1600northonrampswherein

linesarenotclear.Idonotknowwheremylaneisclearlygoing.

Page 54: UDOT Q1 2012 Report

50

• Whatbothersmethemostisthenarrowlanes.Itisverychallenginganddangerouswhenpassingthroughbigtrucks.Secondly,therearenoemergencylanes.Thethirdoneisthere’salotofdebris,whichiskindofdangerous.

• Iwouldliketoseemoreinformationonthestops,whattheyaregoingtomakeaswellaswhereandwhen.Ihopetheywillhavemoreadvertisementsabouttheconstruction.

Provo:

• It’stheProvoCenterStreet.Thedesignofthefreewaytheymadewasconfusing.Somepartsaredangerous.IfIamdrivingfromtheEasttoWest,Ihavetoturnleft.There’sacrowdedanddangerouspart.

• Thelanesaretoonarrow.• Lastnightaround7PM,weenteredthe8-NorthEntranceFreewayinOremandthegreenlightwason.My

husbandthinksthegreenlightslowsthingsdown.• We’vebeencallingfromsomeoneinUDOTabouttherampon1600roadthatwasclosed.Itcausestraffic.

Thewaittimeiswaytoolong.• Itisaboutwheretheydothelanesplit.Theyhavetoputmoresignsaheadormakeitclearer.There

shouldbeclearerwarningforwhatistocome.

Spanish Fork:

• IwanttohavethemmakesurethatthelanesinSpanishForkoff-ramparenothorrible.Mycarhastotipsidewaysslightly,whichisdangerous.Theyshouldleveltheasphaltbetterandmakeitconcrete.

• Asidefromnotbeingabletoseethemarkingsonthelanes,theyaredoingaprettygoodjob.Thereisanunevennessoftheroadandthepavingoftheasphaltfromoldtonew,butconsideringthesizeoftheproject,theyaredoingagoodjob.

• TheyaredoingwonderfullyexceptfortheunevensurfacesinSpringvilleandOrem,whicharealot.• Therewassomuchofthedebristhatwastornupandallofthosewereunsafe.• Itwouldbetherocktrucks.Theyaccidentallythrewovertheroadandhitmycarandwindshield.

Page 55: UDOT Q1 2012 Report

51

Page 56: UDOT Q1 2012 Report

52

Page 57: UDOT Q1 2012 Report

53

Key Findings

Summary of results

Page 58: UDOT Q1 2012 Report

54

Overall ResultsThe average of all Q1 2012 responses gathered in the four man-on-the-street surveys was 2.94 on a five-point scale. This shows an increase from the last quarter, which yielded an overall average of 2.85.

The most negative geographic area in Q1 2012 was American Fork/Lehi receiving a 2.76. Although American Fork also experienced the most negative in overall score it isimproving. The area of Provo yielded the most significant decrease in overall score going from 3.02 to 2.77, whereas in Q4 2011 it scored as the most positive geographical area. Scores decreased in the following questions: “Maintain safe roadways,” “Noise,” “Lane markings clear,” “Easy to read,” “Detours,” “Travel delays,” and “Reasonable.”

The most positive geographic area in Q1 2012 was Orem with a score of 2.94 on a five-point scale. There was an increase on every question except for “Lane markings clear” and “Travel delays.”

Five categories in Question 1 increased in average score from Q1 2012. The four categories that yielded a decrease in score from Q1 2012 were “Noise,” “Detours,” “Reasonable delays,” and “Clear lane markings.” “Dust” and “No delays” were the two categories that maintained their scores from Q4 2011.

“Construction crews are courteous” received the highest average response with a score of 3.66 on a five-point scale. “No delays” was the weakest point once again in Q1 2012 with an average of 2.1 on a five-point scale.

We saw a general increasing trend in all the communication method categories except“Project email updates” and “Project website updates.” “Electronic roadway signs” emerged as the communication method most used again at 47.2%. “Television” emerged second place at 40.1% and “Radio” at third place with 37.3%. The most significant increase in preferred communi-cation method was “Newspapers” which increased from 17.2% in Q4 2011 to 25.8% in Q1 2012.

Page 59: UDOT Q1 2012 Report

55

Detailed ResultsAn Increase in Overall Average

The largest contributing factor for an increase in overall average score was the significant increase in score in Orem. • Orem was the area with the most positive growth receiving a 2.94 on a five-point scale, up from 2.7 in Q4 2011. • American Fork experienced increases in overall scores. • Five out of 11 categories in Question 1 increased in score from Q4 2011.

If Provo had not experienced such a drastic decrease in score, the project would have achieved a greater overall average. • The most positive geographic area in Q1 2012 was Orem with a score of 2.94 on a five-point scale, increasing on all but two questions. • American Fork experienced growth in their average overall response score from 2.75 in Q4 2011 to 2.76 on a five-point scale.

Most Improvement

The Question 1 category that experienced the most positive growth in Q1 2012 ascompared to Q4 2011 was “Ramps.” • In American Fork “Ramps” increased to 2.93, from 2.72 Q4 in 2011. • In Orem “Ramps” increase to 2.96, from 2.76 in Q4 2011. • Provo and Springville remained about the same.

Most Decline

When asked to agree or disagree with the statement “The detour routes are clear and easy to navigate,” people responded more negatively to this statement than Q4 2011. • American Fork received 2.41, down from 2.32 in Q4 2011, based on a five- point scale • Springville received 2.39, down from 2.58 in Q4 2011, based on a five-point scale. • Provo received 2.35, down from 2.58 in Q4 2011, based on a five-point scale. • Orem recieved 2.49, up from 2.21 in Q4 2011, based on a five-point scale.

Page 60: UDOT Q1 2012 Report

56

Communication

In Q1 2012, respondents generally still look to electronic roadway signs and traditional media sources like television and radio more than non-traditional media sources; however, “Newspaper” experienced the most positive growth. The most significant decline in the percentage points was seen in “Project website updates.” Social media the category that showed the largest decrease in category Q4 2011 showed significant increase in Q1 2012. • “Television” experienced positive growth of 1.8%. “Television” experienced growth in percentage points in all four areas except Provo. • “Electronic roadway signs” was reported as the most used method of communication in Provo, American Fork and Spanish Fork. • The most used method of non-traditional communication was “Social media” at 16.9%. • “Local meetings/public events” experienced an overall increase of 0.8%, with increases in all areas except for Springville. • “Project email updates” experienced a 1% decline, much of it coming from American Fork and Orem. • “Door hangers/fliers” experienced a 2.2% increase. The most significant de cline came from American Fork. • “Radio messages” experienced a 0.4% increase, with increase in America Fork and decrease in Springville. • “Newspapers” experienced a 8.6% increase, with the most significant increases in Orem and Springville.

Page 61: UDOT Q1 2012 Report

57

RecommendationsSomething Accomplishable

The following are recommendations that may help UDOT increase the public’s perception about the project. The following areas are reasonable and accomplishable.

Improvements in Provo

Provo received the largest decrease in overall ratings. The most significant decreases were in the categories of “Clear lane markings,” “No delays,” “Noise,” “Easy to read signs,” and “Clear and navegable detours.” The following comments highlight the general feeling in Provo, and the need for a focus on improvement in the area.• I wish the signs were easier to notice (i.e. Provo Center Street, exit). They blend in with

the orange all around The removal of old lane lines, addition of temp lines, cones, and varying asphalt colors make it hard to navigate and understand traffic pattern. The lanes are rough to understand.

• The main thing they could improve are road signs and lane markings. Sometimes you can’t tell what your lane is, creating increased danger. Lack of advanced warning, in particular lane reduction, seem to be the biggest cause of traffic jams. Drivers don’t have enough warning to change lanes, leading to backing up when they try to change at the last moment.

Communication Campaign

A significant number of complaints were expressed in the “Free Response” section of the survey regarding delays. Although the delays cannot be eliminated until the project is done, the reason for the delays can be better communicated.

This may be done through the most effective methods of preferred communication shown in the “Preferred Communication” charts. “Radios messages,” “Television,” and “Electronic Roadway Signs,” have highest percentages of preference in receiving notificationsregarding the I-15 construction areas.

With a recent increase in the “Newspaper” category, now might be the best time to utilize newspapers in helping drivers understand the need for construction and why it causes traffic delays.