UC Davis Chiller and Cooling Tower Replacement
One Shield Ave Davis, CA 95616
Completed June 2009
Owner: The Regents of the University of CA -‐ Davis
255 Cousteau Place Davis, CA 95616 Morgan Meier (530) 757-‐3127 Architect: Turley & Associates 1914 S Street Sacramento, CA 95814 Brian Provencal (916) 325-‐1065 General Contractor: Perryman Mechanical, Inc. 514 Glide Ave. West Sacramento, CA 95691 John Eldeen (916) 371-‐8888 Electrical Engineer: Ken Rubitsky & Associates 1910 S Street Sacramento, CA 95814 Ken Rubitsky (916) 447-‐4477 Building Size: N/A Project Type: Design Assist / Build LEED Qualification: None Job Narrative: The UC Davis Central Chiller and Cooling Tower Replacement project was a design assist project which consisted of the demolition of two steam absorption chillers, one steam driven centrifugal chiller, and one three cell cooling tower. Schetter Electric provided electrical materials and installation for the UC Davis Chiller and Cooling Tower Replacement. Along with the demolition the project also consisted of the installation of one 2,500 ton centrifugal water electric driven chiller and the connection via a new 12kV medium voltage electrical duct bank. Installation of the 12kV duct bank required extensive research, coordination, and timing to maintain all roadways, parking lots, and facilities to keep them active during construction due to the extensive amount of utilities (marked and unmarked) that were involved in the routing of the ¼ mile duct bank from the existing switching station to the central utility plant. Installation of the plant included utility receptacles, interior and exterior lighting, connection to the cooling tower and chiller, supplying and installation of a new 4,160v switchgear, two 12kV transformers, and two 12kV circuit interrupters.
(916) 446-‐2521 | Fax (916) 446-‐2621 | www.schetter.com
CA License No. 245778 • NV License No. B-‐54453 • NV License No. C2-‐54454