42
UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER SYSTEMS 21 1300-1 SECTION 21 1300 FIRE SPRINKLER SYSTEMS PART 1 GENERAL 1.01 SECTION INCLUDES A. Wet-pipe sprinkler system. B. System design, installation, and certification. C. Fire department connections. 1.02 REFERENCES A. FM P7825 - Approval Guide; Factory Mutual Research Corporation; current edition. B. NFPA 13 - Standard for the Installation of Sprinkler Systems; National Fire Protection Association; 2010 edition C. UL (FPED) - Fire Protection Equipment Directory; Underwriters Laboratories Inc.; current edition. 1.03 SCOPE OF WORK A. The work covered under this specification shall include the furnishing of all labor, material and equipment, the performing of all operations necessary for the design and installation of an approved automatic sprinkler system, as described herein. B. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. C. This work shall be in accordance with this specification and with the applicable project drawings. D. All work and materials shall comply with the requirements of the National Fire Protection Association #13, Standard for the Installation of Sprinkler Systems, 2010 edition, FM Global Data Sheets 2-0 and 3-0, and all applicable state and local codes. E. In the event of dispute between the requirements of the Contract Documents and jurisdictional authorities or codes, jurisdictional authorities and codes shall take precedence over plans, details, and specifications. F. It shall be this automatic sprinkler contractor’s responsibility to coordinate and provide the appropriate information to the alarms contractor so that the systems will be operational. G. Final payment will not be authorized until accurate and complete record drawings, O&M manuals, and hydraulic calculations have been received and accepted by the Owner's Designated Representative. H. This contractor is responsible for obtaining and incorporating all of the addenda changes into the system design. 1.04 SUBMITTALS A. The sprinkler contractor shall prepare and submit for review and comments copies of working drawings, calculations, and material specification sheets in accordance with Part 3 of this specification. Four copies of the submittal shall be forwarded to the project Architect and additional copies (as noted) to the following: 1. Regional Building Center, 2880 International Circle, Suite 200, Colorado Springs, CO 80910 Attention: Doreen Withee. 2. Note: Review of submittals by FM Global will be done through the owner.

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

Contract Document Set FIRE SPRINKLER SYSTEMS 21 1300-1

SECTION 21 1300

FIRE SPRINKLER SYSTEMS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Wet-pipe sprinkler system.

B. System design, installation, and certification.

C. Fire department connections.

1.02 REFERENCES

A. FM P7825 - Approval Guide; Factory Mutual Research Corporation; current edition.

B. NFPA 13 - Standard for the Installation of Sprinkler Systems; National Fire Protection Association; 2010 edition

C. UL (FPED) - Fire Protection Equipment Directory; Underwriters Laboratories Inc.; current edition.

1.03 SCOPE OF WORK

A. The work covered under this specification shall include the furnishing of all labor, material and equipment, the performing of all operations necessary for the design and installation of an approved automatic sprinkler system, as described herein.

B. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

C. This work shall be in accordance with this specification and with the applicable project drawings.

D. All work and materials shall comply with the requirements of the National Fire Protection Association #13, Standard for the Installation of Sprinkler Systems, 2010 edition, FM Global Data Sheets 2-0 and 3-0, and all applicable state and local codes.

E. In the event of dispute between the requirements of the Contract Documents and jurisdictional authorities or codes, jurisdictional authorities and codes shall take precedence over plans, details, and specifications.

F. It shall be this automatic sprinkler contractor’s responsibility to coordinate and provide the appropriate information to the alarms contractor so that the systems will be operational.

G. Final payment will not be authorized until accurate and complete record drawings, O&M manuals, and hydraulic calculations have been received and accepted by the Owner's Designated Representative.

H. This contractor is responsible for obtaining and incorporating all of the addenda changes into the system design.

1.04 SUBMITTALS

A. The sprinkler contractor shall prepare and submit for review and comments copies of working drawings, calculations, and material specification sheets in accordance with Part 3 of this specification. Four copies of the submittal shall be forwarded to the project Architect and additional copies (as noted) to the following: 1. Regional Building Center, 2880 International Circle, Suite 200, Colorado Springs, CO

80910 Attention: Doreen Withee. 2. Note: Review of submittals by FM Global will be done through the owner.

Page 2: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

Contract Document Set FIRE SPRINKLER SYSTEMS 21 1300-2

B. Purchasing, fabrication, or installation shall not begin until all submittals are acceptable to the

AHJ and the Owner's Designated Representative. It shall be the contractor's responsibility to obtain required permits and approvals in a timely manner as to not delay the work of any other trades.

1.05 GUARANTEES

A. This contractor shall guarantee all equipment, material, and workmanship for a period of one year from date of final certificate. Any defects in equipment, workmanship, or materials that appear or cause trouble of any kind within a period of one year from the date of final certificate shall be remedied, free of charge.

1.06 PERMITS AND LICENSES

A. Contractor shall obtain and pay for all licenses and permits required by the authorities having jurisdiction.

B. Contractor shall coordinate and request all inspections from the authority having jurisdiction. The contractor shall notify the engineer of all such coordinated inspections (date and time) and shall submit to the engineer certificates of inspection and final approval of the inspection authority.

1.07 RELATED WORK UNDER OTHER SECTIONS

A. All wiring to the following sprinkler system alarm devices to be furnished within these specifications under Division 28. 1. Valve tamper switches. 2. Water flow switches.

B. Painting of exposed sprinkler system pipe, where specified, shall be performed by Division 9.

1.08 CUTTING AND PATCHING

A. Cutting and patching of all floor, wall, and ceiling penetrations is the responsibility of this Contractor. This includes all pipe and hanger rod penetrations into ceilings.

B. Use materials that are identical to existing materials. If identical materials are not available or cannot be used where exposed surfaces are involved, use materials that match existing adjacent surfaces to the fullest extent possible with regard to visual effect. Use materials whose installed performance will equal or surpass that of existing materials. 1. Patching shall match existing fire and smoke resistance ratings. At all wall penetrations

provide firestopping material to maintain the rating. At all floor/roof penetrations, provide firestopping material to maintain rating. Submit shop drawings/manufacturer's literature on proposed fire barrier material for review before proceeding with firestopping work.

C. Before cutting existing surfaces, examine surfaces to be cut and patched and conditions under which cutting and patching is to be performed. Take corrective action before proceeding if unsafe or unsatisfactory conditions are encountered. 1. Avoid interference with use of adjoining areas or interruption of free passage to adjoining

areas. 2. Coordinate timing of Work and noise generated by Work to minimize disruption to adjoining

areas. 3. Take all precautions necessary to avoid cutting existing pipe, conduit, or ductwork serving

the building. 4. Cut existing construction using common materials and work results least likely to damage

elements to be retained or adjoining construction.

Page 3: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

Contract Document Set FIRE SPRINKLER SYSTEMS 21 1300-3

5. In general, where cutting is required use hand or small power tools designed for sawing or

grinding, not hammering and chopping. Cut holes and slots neatly to size required with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.

6. Thoroughly clean areas and spaces where cutting and patching is performed or used as access. Remove completely paint, mortar, oils, putty and items of similar nature. Thoroughly clean piping, conduit and similar features before painting or other finishing is applied. Restore damaged pipe covering to its original condition.

PART 2 PRODUCTS

2.01 SPRINKLERS

A. See project drawings (General Notes) for sprinkler selection within given areas.

B. Sprinklers shall be Underwriters Laboratories (UL) listed and FM Global (FM) Approved for their given application. Approved sprinkler manufacturers include: 1. Viking Corporation (Viking).

C. Sprinkler bulb shields shall be provided with all glass bulb sprinklers prior to shipping from the manufacturer. Shields shall remain in place until one of the following has been completed: 1. Sprinkler system has been placed into service, OR 2. Sprinkler has been installed AND the wall or ceiling finish work has been completed.

Note: Acceptable alternatives to bulb shields consist of plastic covers typically included with concealed sprinklers, or “Cocoon Sprinklers,” such as those available from Viking Corp., where the entire sprinkler and escutcheon ring is shipped within a plastic cover. It is the responsibility of the contractor to ensure the manufacturer includes some form of bulb shield prior to shipping the sprinklers. If their preferred supplier is unable to provide bulb protection as described above, then the contractor shall obtain approved sprinklers from a manufacturer that does.

D. Sprinklers using an o-ring seal are NOT allowed.

E. Extended coverage sprinklers must be installed as per their listing. 1. Extended coverage sprinklers shall not be installed in any mechanical areas, boiler rooms,

chiller rooms, or other areas with large and/or frequent obstructions.

F. Quick Response (QR) sprinklers shall be installed within all Light Hazard areas as identified on the project drawings.

G. Sprinkler temperature rating shall be according to NFPA 13 guidelines. 1. Electrical and mechanical rooms shall utilize intermediate temperature rated sprinklers.

2.02 PIPING

A. All fire sprinkler piping and fittings described below to meet requirements outlined in NFPA 13, 2010 edition with the following exceptions: 1. No Press-Fit piping systems. 2. No Poz-Lok piping systems.

B. Piping shall be concealed above suspended ceilings.

C. All sprinkler system pipe 4 inches and larger to be schedule 40 steel.

D. All sprinkler system piping 3 inches and smaller shall be CPVC.

E. Where piping 3 inches in diameter and smaller would be exposed or where CPVC is otherwise prohibited, then piping shall be schedule 40 steel.

Page 4: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

Contract Document Set FIRE SPRINKLER SYSTEMS 21 1300-4

F. Fire sprinkler system pipe fittings shall be 125 pound cast iron screwed fittings, 150 pound

malleable or ductile iron screwed fittings, factory-made wrought steel butt weld fittings, or forged steel fittings socket welded or threaded.

G. Mechanical formed fittings may be used utilizing carbon steel housing with integral pipe stop, and O-ring seal pocket and O-ring, uniformly compressed into permanent mechanical engagement onto pipe.

H. Approved mechanical grooved fitting manufacturers shall be: 1. Victaulic 2. Anvil (GruvLok) 3. Tyco 4. Equivalent. 5. Entire project to use grooved couplings of one manufacturer.

I. At contractor’s option, flexible piping systems may be used in lieu of hard pipe drops providing the product and installation conform to UL/FM listing requirements. Approved manufacturers/ suppliers include: 1. FlexHead Industries – Holliston, MA 2. Viking Supply Net - Hastings, MI 3. Victaulic AquaFlex - Easton, PA 4. Equivalent with prior approval.

J. At contractor’s option, adjustable drop nipples may be used providing the product and installation conform to UL/FM listing requirements. Approved manufacturers/suppliers include: 1. Aegis Technologies - Wayne, PA 2. Anvil (Merit) - Portsmouth, NH 3. Equivalent with prior approval.

K. All main drain and auxiliary drain piping shall be galvanized (inside and out) from the valve to the outlet.

L. See project drawings for additional piping requirements.

2.03 SYSTEM CONTROL VALVES

A. Sprinkler system control valves shall be slow close, butterfly-type with exterior position indicator and UL listed/FM approved for use on fire protection systems. Location of valves as indicated on the plans.

2.04 CHECK VALVE

A. Check valves shall be UL listed and FM approved.

2.05 HANGERS AND SUPPORTS

A. Hangers, hanger rods, clamps, and inserts to meet requirements of NFPA 13, 2010 edition.

B. Trapeze-style hanging assemblies may be used, but only with documentation on the shop drawings validating the sizing of the trapeze members. When a trapeze member is not explicitly listed in NFPA 13 (e.g. Unistrut), documentation must be provided that indicates adequate section modulus and other pertinent parameters are being met.

C. Piping supported by rods that pass through ceiling system shall be pre-approved and shall have escutcheons on the rods.

Page 5: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

Contract Document Set FIRE SPRINKLER SYSTEMS 21 1300-5

2.06 SPRINKLER ALARMS

A. Provide Potter VSR-F vane-type water flow alarm switch (or UL/FM approved equivalent) at wet system riser. Switch to be wired to send alarm signal to FACP upon detection of water flow.

B. Provide UL/FM approved valve tamper switches on all sprinkler control valves. Switches to be wired to send supervisory signal to FACP upon change of position of control valve from normal.

2.07 INSPECTOR'S TEST

A. Furnish and install all materials required for inspector's test connections as shown on plans.

B. Where a test connection passes through an exterior wall, provide a galvanized wall plate at the exterior; provide a galvanized 45° elbow to include an orifice with a diameter equivalent to the smallest orifice sprinkler installed.

2.08 MAIN DRAIN

A. Main drain to be routed through exterior wall as shown on the project drawings. Provide a galvanized wall plate and galvanized 45° elbow at exterior.

2.09 AUXILIARY DRAINS

A. Auxiliary drains shall conform to rules of NFPA 13.

B. For areas trapping between 5 gal. and 50 gal., a ¾ in. garden hose adapter shall be included with the valve and plug. Hose adapter shall be hung from valve handle with tie wire for future use.

C. When necessary to pipe to interior drain or building exterior (trapping volumes in excess of 50 gal.), location shall be approved by engineer/architect.

D. Where the drain passes through an exterior wall, provide a galvanized wall plate, galvanized 45° elbow and a cast in place concrete splash block.

2.10 RELIEF VALVE

A. Provide a relief valve not less than 1/4 inch in size and set to operate at 175 psi or 10 psi in excess of the maximum system pressure, whichever is greater. Relief valve to be located on the wet system riser.

2.11 AIR BLEED VALVE

A. Install a 1 inch ball valve off the top of the highest remote branch line that is located in an accessible area. Place plug in outlet of valve.

B. Install additional ball valves with plugs where indicated on the drawings.

2.12 SPARE HEAD CABINET

A. Provide a sprinkler cabinet containing twelve (12) sprinklers including all types and ratings installed and a sprinkler wrench for each head type shall be provided for emergency use. A proportionate number of each type used shall be provided. However, no less than two of every sprinkler type shall be included. Additional head cabinets may be necessary.

B. Provide an additional cabinet containing at least six (6) concealed sprinkler covers of the same make as those installed within this project. 1. A minimum of two (2) spare covers of each color shall be included.

C. Provide list of sprinklers installed in property within or attached to spare head cabinet.

Page 6: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

Contract Document Set FIRE SPRINKLER SYSTEMS 21 1300-6

2.13 SIGNS A. Contractor shall furnish all necessary signs identifying control valves, inspector’s test

connection, and auxiliary drains. Control valve signs shall identify the valves as “Normally Open” or “Normally Closed.”

B. All signs shall be aluminum with painted white background and fade resistant red lettering. Signs of similar quality may be used upon prior approval by the Architect.

2.14 WALL/FLOOR PENETRATIONS

A. Where pipe passes through walls, floors, or other building construction that by code requires a fire rating, approved fire rated assemblies shall be used, e.g.: approved fire caulking in combination with mineral wool. 1. Acceptable fire caulk products:

a. 3M Fire Barrier CP 25WB+ Sealant. b. Hilti FS-ONE Intumescent Firestop Sealant. c. Equivalent.

B. All pipe penetrations through interior walls, floors, ceilings, and partitions shall be sealed with materials to match the surrounding materials.

C. All pipe penetrations through concrete floors shall be sleeved with steel pipe sleeves at least 2 pipe diameters larger than the piping passing through the sleeve. Sleeve shall extend 1 to 2 inches above the floor.

D. Except as noted on the plans, where exposed pipe passes through indoor finish work, chrome split wall plates (F&C plates) or escutcheons shall be installed. Plates or escutcheons shall be sized to fit snugly around the pipe.

E. Galvanized wall plates and fittings shall be used at the exterior where test or drain piping passes through the exterior wall.

F. Penetrations through an exterior wall to be sealed with foam or mastic; penetrations to be caulked at the outside wall.

G. Holes through rated walls shall be a minimum of 1 in. larger, and maximum of 2 in. larger in diameter than the outside diameter of the pipe passing thru the rated wall. This space shall be filled with mineral wool and sealed with an approved listed fire caulk or sealant. All penetrations of fire rated walls and assemblies shall be UL listed for that purpose, for both the type of pipe material and wall or ceiling/floor construction. Listed alternate methods will be accepted.

PART 3 EXECUTION

3.01 GENERAL RESPONSIBILITY

A. The sprinkler contractor shall be responsible for providing a complete and operating system throughout the entire building as per NFPA 13, 2010 edition. Contractor shall be responsible for review of all architectural drawings and placement of any sprinklers within soffits, skylights, recesses, below mechanical equipment, etc. to meet the guidelines of NFPA 13. Contractor shall meet the requirements of NFPA 13 for obstruction of sprinklers caused by architectural elements shown on the Project Drawings.

B. The sprinkler contractor shall institute a system of quality assurance to assure that the design, installation, materials, inspection, and testing of all components are in accordance with the provisions of this specification and the applicable codes and standards. The quality assurance program shall require that all shop drawings, calculations, and other submittals are checked and signed by a technician with a minimum NICET Level III rating, or sealed by a registered professional engineer who has passed the NCEES professional engineering exam for fire protection.

C. Architect approval must be obtained before any cutting of pipe or commencement of work.

Page 7: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

Contract Document Set FIRE SPRINKLER SYSTEMS 21 1300-7

D. Contractor and required installation employees shall be licensed as required by the State of Colorado and shall maintain the necessary license from the time of bid through completion of the project.

3.02 DESIGN SUBMITTALS

A. The contractor shall coordinate fire protection work prior to submitting Shop Drawings for review.

B. The Owner's Designated Representative will require a minimum of ten (10) working days, excluding transmittal time, to review submittals. The contractor shall allow for this when scheduling their work.

C. Owner's Certificate 1. Provide completed Owner's Certificate per NFPA 13 documenting building use, storage

information, commodity classifications etc. 2. Certificate shall include owner's signature.

D. Sprinkler System Shop Drawings: 1. Prepared in accordance with NFPA 13 guidelines for sprinkler system shop drawings. Shall

include ceiling layout indicating the various materials, elevations, and the tile pattern, as applicable; shall indicate ceiling diffusers, grilles, lighting fixtures, speakers, major HVAC ductwork trunk lines, and electrical cable trays. Where no suspended ceiling is included, or where the structural members are combustible, the structural elements shall be indicated on the drawings.

2. Prepared from full-scale AutoCAD-generated *.dwg format. 3. Plotted at 1/8” or 1/4” scale. 4. In addition to the submitted drawings, the sprinkler contractor shall submit directly to the

engineer an electronic copy of the fire protection drawings. Drawings shall be formatted to be read by AutoCAD 2011 and may be submitted via compact disc (CD) or electronic mail (email).

E. Hydraulic calculations: 1. Hydraulic calculations shall include all information required by NFPA 13.

F. Product Data: *Note that specific device and size being utilized shall be clearly marked or highlighted on submitted material data sheets. 1. Piping materials, including flexible connections and sprinkler specialty fittings. 2. Pipe hangers and supports. 3. Valves, including listed fire-protection valves, unlisted general-duty valves, and specialty

valves and trim. 4. Sprinklers, escutcheons, and guards. Include sprinkler flow characteristics, mounting,

finish, and other pertinent data. 5. Alarm devices, including electrical data. 6. Details of all fire stopping materials and methods to be used at wall/floor penetrations.

3.03 WATER SUPPLY

A. Contractor shall base hydraulic design of system on water supply information provided on the project drawings.

3.04 SPRINKLER SYSTEM DESIGN

A. See project drawings for sprinkler system design parameters.

B. All remote area calculations shall include a 10-psi safety margin.

C. Not all areas will require separate hydraulic calculations, but it should be reasonably clear to the plan reviewer from remote area calculations and pipe sizes that the specified densities can be met. Contractor shall be prepared to prove any area that is not specifically calculated.

Page 8: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

Contract Document Set FIRE SPRINKLER SYSTEMS 21 1300-8

3.05 INSTALLATION-GENERAL

A. The contractor shall coordinate fire protection with all trades. Refer to other related general and mechanical sections for additional information, including any articles addressing submittals and coordination in those sections. Provide input in the preparation of coordination drawings prior to fabrication and installation of materials. 1. Coordinate with other work, including structural, architectural, plumbing piping, ductwork,

electrical piping and equipment, etc., as necessary to interface components of fire sprinkler piping properly with other work.

3.06 INSTALLATION OF PIPES AND PIPE FITTINGS

A. Install pipes and pipe fittings in accordance with NFPA standards and as specified herein. 1. All piping shall be installed in a neat and orderly manner, plumb and parallel to building

structure, and shall be properly supported. Piping shall be concealed in construction work wherever possible. Piping shall be installed above ceiling where ceilings are provided. Exposed piping shall be so located in respect to structural members, beams, joists, lighting fixtures, ducts, etc., so as to maximize aesthetics. The location of all piping and sprinklers shall be subject to the approval of the Architect.

2. Exposed sprinkler piping and components shall not be installed in any public areas less than 7'-0" above finished floor without prior approval of the Owner's Designated Representative.

3. Use reducing fittings for changes in pipe size. 4. Shoulder nipples shall be used where necessary. Close nipples are not acceptable. 5. Cutout disks created by field-cut holes in pipe shall be recovered and wired to the pipe

near the point of cutting. All disks shall be accounted for to assure that no blockage of the pipe would occur as the result of the displacement of these disks.

6. All piping and fittings shall be so installed that the system may be thoroughly drained. Where practicable, all piping should be arranged to drain to the main drain valve. All auxiliary drains shall be piped so the drain valves are in a location acceptable to the Owner and in accessible heated locations without climbing or crawling.

7. All piping passing through exterior walls (drain lines, inspector test connections, fire department connections, etc.) shall have a minimum of four feet of dry piping from any pipe, fittings, or valves containing water to the wall.

3.07 INSTALLATION OF SUPPORTS AND ANCHORS

A. Install pipe supports in accordance with NFPA 13.

3.08 INSTALLATION OF SPRINKLERS

A. Sprinkler head locations shall be coordinated with architectural and structural features, all mechanical and electrical obstructions, light fixtures, diffusers, and grilles. 1. In spaces with lay-in ceiling tiles the sprinklers shall be located in the center of the tile.

See project drawings for details. 2. Sprinkler spray patterns shall not be obstructed by any other ceiling, electrical, mechanical,

or structural components, and shall be located as required by NFPA 13 for horizontal and vertical obstructions.

3. All special sprinklers shall be located and installed as required by their listing.

B. In any area where sprinklers are subject to damage, the piping and sprinklers shall be installed so as to provide the maximum protection from damage. Sprinkler head guards shall be installed on all sprinklers in areas subject to damage.

C. Protective covers or straps on sprinklers utilized by the sprinkler manufacturers for shipping and sprinkler head integrity protection shall remain in place until the sprinkler system installation is complete. It is then the sprinkler contractor's responsibility to ensure that all of the protective covers and straps are removed and that none of the installed sprinklers show damage or glass

Page 9: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

Contract Document Set FIRE SPRINKLER SYSTEMS 21 1300-9

bulbs show obvious leakage. Store sprinklers properly, protect them from heat, handle in accordance with the manufacturer's requirements, and install sprinklers with pipe in place and always wrench tighten the sprinkler with the wrench required by the manufacturer.

3.09 TESTS AND APPROVALS

A. All required system testing outlined in NFPA 13 shall be completed and documented on the Contractor’s Material and Test Certificate (CMTC). These tests include among others: 1. 200 psi Hydrostatic Test

a. System air shall be exhausted through bleed valve prior to performing Hydrostatic Tests.

2. Main Drain Flow Test 3. Sprinkler Alarm Tests

B. Upon completion of above testing: 1. A copy of the CMTC attachment shall be submitted to the Architect and to the approving

agencies. 2. A tag shall be left at the controls stating the results and date of the:

a. Main Drain Test

3.10 FIRE ALARM SYSTEM COORDINATION

A. The sprinkler contractor shall, before the sprinkler system is in service, coordinate with the fire alarm contractor and the central station contractor. 1. Coordination shall include, but is not limited to, all functions of all sprinkler system alarm

and trouble components with the appropriate fire alarm panel functions and central station functions.

2. This contractor shall demonstrate to the Owner's Designated Representative that all sprinkler alarm devices are labeled properly on the alarm panel and the central station and that all are functioning as intended.

3. This contractor shall document the demonstration and provide such documentation to the Owner's Representative in the O&M Manual.

3.11 CLEANING AND PAINTING

A. Where required, painting of sprinkler pipe to be performed by Division 9. However, all sprinkler piping shall be wiped of excess oil, grease, and sealing compound by the sprinkler contractor.

3.12 RECORD DRAWING

A. The contractor shall maintain one set of drawings at the job site used as a master copy. Each change order or other revision, deletion, or addition shall be clearly marked and noted by colored pencil. This copy of plans shall be used to complete record drawings to be submitted as part of the Operation and Maintenance Manuals.

3.13 OPERATION AND MAINTENANCE (O&M) MANUALS

A. Submit specified number of copies of the O&M manual for approval prior to owner’s instructions (number of copies by Division 1).

B. Manual to be a three ring binder and include these components in this order: 1. Cover – identify project name and date, contractor, and 24-hour contact information. 2. Normal conditions of sprinkler system.

a. Normal conditions of sprinkler system section to include typical pressures and valve positions. The purpose of this information is so that the building owner can observe the pressure gauges on the system riser and compare to the given typical static pressures and determine if the system is operational or if there is a problem. Also, the building owner should be able to review the O&M Normal Conditions and know what position each valve should be in under normal conditions (i.e. normally open/closed).

3. Emergency instructions in case of fire.

Page 10: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

Contract Document Set FIRE SPRINKLER SYSTEMS 21 1300-10

4. Emergency instructions in case of accidental discharge. 5. Sprinkler cut sheets. 6. Sprinkler system component cut sheets (to include as a minimum all control valves,

backflow assembly, electrical alarm switches and devices, and any other specialty items, as applicable).

7. Hydraulic calculations. 8. Contractor’s Material & Test Certificate(s) both above and below ground. 9. Approval letters from authority having jurisdiction and FM Global, as applicable. 10. Record drawing (if drawing is too large to be folded and included in the binder, roll and

include separately). 11. An original copy of NFPA 25 INSPECTION, TESTING, AND MAINTENANCE OF WATER

BASED FIRE PROTECTION SYSTEMS, 2008 edition. Photo copies will not be accepted.

C. Contractor to provide owner with a building schematic coated in plastic identifying the location of all sprinklered zones, zone control valves, auxiliary drains, air bleed valves, and inspector’s test connections.

3.14 INFORMATION SIGNS

A. Hydraulic Nameplate 1. A hydraulic design data nameplate similar to that shown in NFPA 13 shall be provided at

the riser(s) for each hydraulic remote area submitted.

B. General Information Sign 1. The sign shall include the following information:

a. Name and location of the facility protected b. Presence of high-piled and/or rack storage c. Maximum height of storage planned d. Commodity classification e. Presence of solid shelving f. Flow test data g. Presence of flammable/combustible liquids h. Presence of hazardous materials i. Presence of other special storage j. Location of auxiliary drains and low point drains k. Original results of main drain flow test l. Name of installing contractor or designer m. Indication of presence and location of antifreeze or other auxiliary systems

2. Such general information shall be provided with a permanently mark weatherproof metal or rigid plastic sign, secured with corrosion-resistant wire, chain, or other acceptable means.

3. Such signs shall be placed at each system control riser, antifreeze loop, and auxiliary system control valve.

3.15 INSTRUCTIONS

A. Furnish, without additional expense to owner, the services of competent instructors who will give full instructions in the care and operation of the automatic sprinkler system equipment. Instruction shall be to the owner’s employees who are to have charge of the equipment.

B. The instruction period for sprinkler system shall not be less than three (3) man-hours.

C. Instructions shall include as a minimum: placing the system in service, taking the system out of service, what to do in case of fire, what to do in case of accidental discharge, identification of primary system components, walk-through showing location of all auxiliary drains, performing an alarm test, reviewing the O&M manual, identifying applicable portions of NFPA 25, and answering any other questions.

END OF SECTION

Page 11: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

Construction Document Set 26 0500 - 1

BASIC ELECTRICAL REQUIREMENTS

SECTION 26 0500

BASIC ELECTRICAL REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Basic Electrical Requirements specifically applicable to Division 26, Division 27, and Division 28 Sections, in addition to Division 1 - General Requirements..

1.02 REFERENCES

A. FM P7825 - Approval Guide; Factory Mutual Research Corporation; current edition.

B. NFPA 70 - National Electrical Code; National Fire Protection Association, 2008.

1.03 DEFINITIONS

A. The meaning and intent of the word "provide" as used in these specifications is the same as the words "The Electrical Contractor (and/or Bidder) shall provide."

B. The word "provide" shall carry the same meaning as "furnish and install."

C. The word "Contractor" shall mean the "Electrical Contractor."

1.04 PERFORMANCE REQUIREMENTS

A. Conform to all applicable Building Codes, ordinances, laws and regulations.

B. Electrical: Conform to NFPA 70 - National Electrical Code.

C. Furnish products listed and classified by Underwriters Laboratories Inc.®, as suitable for purpose specified and shown.

D. Obtain permits, and request inspections from authority having jurisdiction.

E. If the drawings and/or specifications conflict with any regulatory requirement, the regulatory requirement shall be followed. This does not relieve the Contractor from complying with items in the drawings and/or specifications in excess of the regulatory requirements.

F. Test Standards: 1. All materials and equipment shall be listed, labeled or certified by a nationally recognized

testing laboratory to meet Underwriters Laboratories, Inc.®, standards where test standards have been established. Equipment and materials which are not covered by UL® Standards will be accepted provided the equipment and material is listed, labeled, certified or otherwise determined to meet safety requirements of a nationally recognized testing laboratory acceptable to the authority having jurisdiction.

2. Definitions: a. Listed; equipment or device of a kind mentioned which:

1) Is published by a nationally recognized laboratory which makes periodic inspection of production of such equipment.

2) States that such equipment meets nationally recognized standards or has been tested and found safe for use in a specified manner.

b. Labeled; equipment or device is when: 1) It embodies a valid label, symbol, or other identifying mark of a nationally

recognized testing laboratory such as Underwriters Laboratories Inc.® 2) The laboratory makes periodic inspections of the production of such equipment. 3) The labeling indicates compliance with nationally recognized standards or tests

to determine safe use in a specified manner. c. Certified; equipment or product is which:

1) Has been tested and found by a nationally recognized testing laboratory to meet

Page 12: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

Construction Document Set 26 0500 - 2

BASIC ELECTRICAL REQUIREMENTS

nationally recognized standards or to be safe for use in a specified manner. 2) Production of equipment or product is periodically inspected by a nationally

recognized testing laboratory. 3) Bears a label, tag, or other record of certification.

d. Nationally recognized testing laboratory; laboratory which is approved by the authority having jurisdiction.

1.05 PROJECT/SITE CONDITIONS

A. Install Work in locations shown on Drawings, unless prevented by Project conditions.

B. Prepare drawings showing proposed rearrangement of Work to meet Project conditions, including changes to Work specified in other Sections. Obtain permission of Architect/Engineer before proceeding.

1.06 SUBMITTALS

A. Product Data: Submit product data grouped to include complete submittals of related systems, products, and accessories.

B. Shop Drawings: Submit Shop Drawings grouped to include complete submittals of related systems, products, and accessories.

C. Warranty: Submit manufacturer warranty and ensure that forms have been completed in University of Colorado Colorado Springs (UCCS) name and registered with manufacturer.

1.07 DRAWINGS

A. The drawings indicate the general arrangement and extent of electrical work. Do not scale off the electrical drawings. All data shall be field verified with actual field conditions. Review drawings of other trades and adjust work to meet the requirements of conditions shown. Contractor shall be responsible to field measure and confirm mounting heights and location of electrical equipment with respect to counters, radiation and other Architectural, Mechanical or Structural work.

B. The drawings and specifications are complementary each to the other. What is called for by one shall be as binding as if called for by both.

C. Omissions or discrepancies between different drawings or between drawings and specifications or between contract documents and regulations and/or codes shall be brought to the attention of the Architect/Engineer for a decision in writing. Interpretation before the bid shall be by addendum only. If an interpretation is not given by addendum, bid the greater quantity or better quality.

1.08 PERMITS AND LICENSES

A. Obtain and pay for required licenses and permits. Pay for fees and charges for connection to outside services. Pay for use of property other than the site of the work for storage of materials or other purposes.

B. Installation shall be performed by persons licensed and skilled in the trade, and shall be done under the supervision of a master electrician licensed by the State.

1.09 PROGRESS OF WORK

A. Organize electrical work such that the progress of the work will conform to the progress of other trades, and complete the entire installation as soon as the conditions of the building will permit. Any cost resulting from defective or ill-timed work performed under this section shall be borne by this Contractor.

B. Portions of work will be required to be accomplished during other than normal working hours.

Page 13: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

Construction Document Set 26 0500 - 3

BASIC ELECTRICAL REQUIREMENTS

1.10 CORRELATION OF WORK

A. Organize work so that it will not interfere with the work of other trades. Consult the drawings and specifications for work of other trades to correlate information, and consult the architectural and structural drawings for details and dimensions. Verify the location of all outlets. If interference develops, bring it to the attention of the Architect/Engineer for a decision. No additional compensation will be allowed for the moving of misplaced outlets, wiring or equipment.

B. Before roughing-in for electrical equipment furnished by others, verify the voltage and current characteristics and control connections of this equipment, and provide the proper feeders and connections as recommended by the manufacturer of the equipment.

1.11 CUTTING AND PATCHING

A. Lay out all work in advance and where removal of door frames, portions of walls, ceilings or floors are required, and cutting, channeling, chasing, or drilling of building surfaces is necessary for the proper installation of electrical equipment, carefully perform this work in a manner which does not weaken floors and walls. Damaged surfaces shall be repaired at no cost to the Owner.

B. Concrete shall be cut only with rotary type drilling tools. Electrical equipment shall not be cut with torches, and shall be joined only by bolting (i.e., do not weld wireways to panels).

C. Patching, when required, shall be finished to match adjoining surfaces and is subject to approval by the Architect/Engineer.

1.12 EXAMINATION OF SITE

A. Before submitting a bid, each bidder shall examine the site, check the means of installing electrical equipment within the building, making connections to services, and shall be familiar with the existing conditions and limitations. No extras will be allowed because of the Contractor's misunderstanding of the amount of work involved or lack of knowledge of any site conditions which may affect the work. Any apparent variance of the drawings or specifications from the existing conditions at the site shall be called to the attention of the Architect/Engineer before submitting a bid.

1.13 OPERATION AND MAINTENANCE DATA

A. Submit under provisions of Section 01 7800.

B. Format: 1. Prepare data in the form of an instructional manual. 2. Organize in commercial quality, 8-1/2" x 11", three-ring binders with hard black, cleanable,

plastic covers. When multiple binders are used, correlate data into related consistent groupings.

3. Identify each binder on cover with typed or printed title "OPERATION AND MAINTENANCE INSTRUCTIONS," list title of Project and identify subject matter of contents.

4. Arrange contents by section numbers and sequence of Table of Contents by this Project Manual.

5. Provide tabbed flyleaf for each separate product and system, with typed description of product and major component parts of equipment.

6. Text: Manufacturer's printed data or typewritten data on 20-pound paper. 7. Drawings: Provide with reinforced punched binder tab. Bind in with text. Fold larger

drawings to size of text pages.

C. Contents of Each Volume: 1. Table of Contents: Provide title of Project; names, addresses and telephone numbers of

Engineer and Contractor and listing of products and systems indexed to tabbed flyleaves.

Page 14: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

Construction Document Set 26 0500 - 4

BASIC ELECTRICAL REQUIREMENTS

2. Updated Subcontractor, Supplier and Manufacturer List: Indicate any changes made after original submission at start of Project.

3. Include description as to type and quantity of maintenance materials turned over to Owner in accordance with individual sections.

4. Warranties and Bonds: Include all. 5. Shop Drawings and Product Data: Include only those so required by individual sections. 6. Operation and Maintenance Data for Equipment and Systems: Where required by

individual sections, provide manufacturer's recommended operation procedures and maintenance requirements including guide for troubleshooting, disassembly, repair and assembly instructions and alignment, adjusting, balancing and checking instructions.

7. Include a copy of ANSI/NFPA 70B Electrical Equipment Maintenance.

D. Submittals: 1. Submit one copy of completed volumes in final form 15 days prior to final inspection.

Copy will be returned after final inspection, with Engineer's comments. Revise contents of documents as required prior to final submittal. a. Submit two copies of revised volumes of data in final form to Engineer within ten days

after final inspection.

1.14 DELIVERY, STORAGE AND HANDLING

A. Deliver, store, protect and handle Products to site under provisions of Section 01 1600.

1.15 PROJECT RECORD DOCUMENTS

A. Submit under provisions of Section 01 7800.

B. Include all changes and deviations from contract documents. Clearly mark in colored pencil. Include all addendum items and approved change orders.

1.16 MINIMUM REQUIREMENTS

A. References to the National Electrical Code (NEC), Underwriters Laboratories, Inc. (UL), National Fire Protection Association (NFPA), National Electrical Installation Standards (NEIS), and any other applicable standards are minimum installation requirement standards.

B. Drawings and other specification sections shall govern in those instances where requirements are greater than those specified in the above standards.

END OF SECTION

Page 15: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 26 0519 - 1

LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES (600 V AND LESS)

SECTION 26 0519

LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES (600 V AND LESS)

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Wire and cable for 600 volts and less.

B. Wiring connectors and connections.

1.02 RELATED REQUIREMENTS

A. Section 26 0553 - Identification for Electrical Systems.

1.03 REFERENCE STANDARDS

A. NECA 1 - Standard for Good Workmanship in Electrical Contracting; National Electrical Contractors Association; 2006.

B. NETA STD ATS - Acceptance Testing Specifications for Electrical Power Distribution Equipment and Systems; International Electrical Testing Association; 2009.

C. NFPA 70 - National Electrical Code; National Fire Protection Association.

1.04 QUALITY ASSURANCE

A. Conform to requirements of NFPA 70.

B. Products: Furnish products listed and classified by Underwriters Laboratories Inc. as suitable for the purpose specified and indicated.

PART 2 PRODUCTS

2.01 WIRING REQUIREMENTS

A. Concealed Dry Interior Locations: Use only building wire in raceway or building wire with Type THHN/THWN-2 insulation in raceway.

B. Wet or Damp Interior Locations: Use only building wire with Type THHN/THWN-2 insulation in raceway.

C. Use solid conductor for feeders and branch circuits 10 AWG and smaller.

D. Use stranded conductors for control circuits.

E. Use conductor not smaller than 12 AWG for power and lighting circuits.

F. Use conductor not smaller than 14 AWG for control circuits.

G. Use 10 AWG conductors for 20 ampere, 120 volt branch circuits longer than 75 feet.

H. Use 10 AWG conductors for 20 ampere, 277 volt branch circuits longer than 200 feet.

I. Conductor sizes are based on copper unless indicated as aluminum or "AL".

2.02 WIRE MANUFACTURERS

A. Cerro Wire Inc: www.cerrowire.com.

B. Industrial Wire & Cable, Inc: www.iewc.com.

C. Southwire Company: www.southwire.com.

D. Or Equal.

Page 16: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 26 0519 - 2

LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES (600 V AND LESS)

2.03 BUILDING WIRE

A. Description: Single conductor insulated wire.

B. Conductor: Copper.

C. Insulation Voltage Rating: 600 volts.

D. Insulation: NFPA 70, Type THHN/THWN.

2.04 WIRING CONNECTORS

A. Split Bolt Connectors: 1. Product: Blackburn or equal. 2. Description: Suitable for copper and aluminum conductors.

B. Spring Wire Connectors: 1. Product: 3M "Scotchlock" or equal. 2. Description: Twist-on, spring tension.

C. Compression Connectors: 1. Product: Anderson Electric "Versa-Crimp" or equal. 2. Description: Suitable for use with copper or aluminum conductors.

PART 3 EXECUTION

3.01 EXAMINATION

A. Verify that interior of building has been protected from weather.

B. Verify that mechanical work likely to damage wire and cable has been completed.

C. Verify that raceway installation is complete and supported.

3.02 PREPARATION

A. Completely and thoroughly swab raceway before installing wire.

3.03 INSTALLATION

A. Install wire and cable securely, in a neat and workmanlike manner, as specified in NECA 1.

B. Route wire and cable as required to meet project conditions. 1. Where wire and cable destination is indicated and routing is not shown, determine exact

routing and lengths required.

C. Use wiring methods indicated.

D. Pull all conductors into raceway at same time.

E. Use suitable wire pulling lubricant for building wire 4 AWG and larger.

F. Neatly train and lace wiring inside boxes, equipment, and panelboards.

G. Clean conductor surfaces before installing lugs and connectors.

H. Make splices, taps, and terminations to carry full ampacity of conductors with no perceptible temperature rise.

I. Use crimp connectors for copper conductor splices and taps, 6 AWG and larger. Tape uninsulated conductors and connector with electrical tape to 150 percent of insulation rating of conductor.

J. Identify and color code wire and cable under provisions of Section 26 0553. Identify each conductor with its circuit number or other designation indicated.

Page 17: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 26 0519 - 3

LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES (600 V AND LESS)

K. Install products in accordance with manufacturers instructions.

L. Draw conductors into conduit only after conduit system is complete. Install in a manner so as not to injure insulation.

M. Neatly train and lace wiring inside boxes, equipment, and panelboards.

N. Clean conductor surfaces before installing lugs and connectors.

O. Use insulated spring wire connectors with plastic caps for copper conductor splices and taps, 8 AWG and smaller.

P. Use bolted pressure connectors for connecting copper conductors to busbars.

Q. Use factory color coded conductors with separate color for each phase and neutral conductor by integral pigmentation for conductors #10 and smaller and 6 inch taped ends for conductors #8 and larger. Use following code: System Voltage System Voltage Conductor 208/120V 480/277V Phase A Black Brown Phase B Red Orange Phase C Blue Yellow Neutral White White (Gray) Equipment Ground: Green Green (Green with Yellow

Stripe)

R. Make conductor length for parallel feeders identical.

S. Splice only in accessible junction or outlet boxes.

3.04 FIELD QUALITY CONTROL

A. Perform field inspection in accordance with Section 01 4000.

B. Inspect wire for physical damage and proper connection.

C. Measure tightness of bolted connections and compare torque measurements with manufacturer's recommended values.

D. Verify continuity of each branch circuit conductor.

END OF SECTION

Page 18: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 26 0519 - 4

LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES (600 V AND LESS)

Page 19: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 26 0526 - 1

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Grounding and bonding components.

1.02 REFERENCE STANDARDS

A. NETA STD ATS - Acceptance Testing Specifications for Electrical Power Distribution Equipment and Systems; International Electrical Testing Association; 2009.

B. NFPA 70 - National Electrical Code; National Fire Protection Association; 2008.

1.03 QUALITY ASSURANCE

A. Conform to requirements of NFPA 70.

B. Comply with UL 467.

C. Comply with NECA's "Standard of Installation."

D. Products: Listed and classified by Underwriters Laboratories Inc. as suitable for the purpose specified and indicated.

PART 2 PRODUCTS

2.01 MANUFACTURERS

A. Cooper Power Systems: www.cooperpower.com.

B. Framatome Connectors International: www.fciconnect.com.

C. Erico Inc.; Electrical Products Group.

D. ILSCO.

E. Utilco.

2.02 CONNECTORS AND ACCESSORIES

A. Mechanical Connectors: Bronze. 1. Product: Equal to that manufactured by Erico. 2. Substitutions: See Section 01 6000 - Product Requirements.

B. Wire: Stranded copper. Conform to NEC Table 8, except as otherwise indicated, for conductor properties, including stranding.

C. Equipment Grounding and Bonding Conductor: Green insulation, size to meet NFPA 70 requirements.

PART 3 EXECUTION

3.01 EXAMINATION

A. Verify existing conditions prior to beginning work.

3.02 INSTALLATION

A. Provide bonding to meet requirements described in Quality Assurance to meet NFPA 70 (NEC).

B. Install exothermic connections in concealed locations. Install mechanical connectors in exposed locations.

Page 20: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 26 0526 - 2

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

C. Bond metallic conduit systems and equipment isolated from each other with a bonding conductor for ground continuity.

D. Telephone: Provide one #2 copper conductor in conduit from main ground bus to each telephone service termination backboards or cabinets.

E. Data Network System: Provide one #6 copper conductor in conduit from main ground bus to each data network sytem termination rack.

F. Fire Alarm and Detection: Provide one #8 in power supply conduit from main control panel to panelboard ground bus.

G. Connections 1. Tighten screws and bolts for grounding and bonding connectors and terminals according to

manufacturer's published torque-tightening values. Where these requirements are not available, use those specified in UL 486A and UL 486B.

2. Compression-Type Connections: Use hydraulic compression tools to provide correct circumferential pressure for compression connectors. Use tools and dies recommended by manufacturer of connectors. Provide embossing die code or other standard method to make a visible indication that a connector has been adequately compressed on grounding conductor.

3. Moisture Protection: Where insulated grounding conductors are connected to grounding rods or grounding buses, insulate entire area of connection and seal against moisture penetration of insulation and cable.

3.03 FIELD QUALITY CONTROL

A. Use suitable test instrument to measure ground resistance of system. Perform testing in accordance with test instrument manufacturer's recommendations using the fall- of-potential method. Add additional ground rods as required to achieve specified value.

B. Inspect grounding and bonding system conductors and connections for tightness and proper installation.

C. Provide field inspection in accordance with Section 01 4000.

D. Inspect and test in accordance with NETA STD ATS except Section 4.

END OF SECTION

Page 21: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 26 0529 - 1

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

SECTION 26 0529

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Conduit and equipment supports.

B. Anchors and fasteners.

1.02 REFERENCE STANDARDS

A. NECA 1 - Standard Practices for Good Workmanship in Electrical Contracting; National Electrical Contractors Association; 2006.

B. NFPA 70 - National Electrical Code; National Fire Protection Association; 2008.

1.03 QUALITY ASSURANCE

A. Conform to requirements of NFPA 70.

B. Products: Listed and classified by Underwriters Laboratories Inc. as suitable for the purpose specified and indicated.

PART 2 PRODUCTS

2.01 MANUFACTURERS

A. Thomas & Betts Corporation: www.tnb.com.

B. Threaded Rod Company: www.threadedrod.com.

C. Substitutions: See Section 01 6000 - Product Requirements.

2.02 MATERIALS

A. Hangers, Supports, Anchors, and Fasteners - General: Corrosion-resistant materials of size and type adequate to carry the loads of equipment and conduit, including weight of wire in conduit.

B. Supports: Fabricated of structural steel or formed steel members; galvanized or painted.

C. Anchors and Fasteners: 1. Do not use powder-actuated anchors or spring clips. 2. Concrete Structural Elements: Use precast inserts, expansion anchors, or preset inserts. 3. Steel Structural Elements: Use beam clamps, steel ramset fasteners, or welded

fasteners. 4. Concrete Surfaces: Use self-drilling anchors or expansion anchors. 5. Hollow Masonry, Plaster, and Gypsum Board Partitions: Use toggle bolts or hollow wall

fasteners. 6. Solid Masonry Walls: Use expansion anchors or preset inserts. 7. Sheet Metal: Use sheet metal screws. 8. Wood Elements: Use wood screws.

D. Formed Steel Channel: 1. Product: Steel Channel manufactured by B-Line or Unistrut. 2. Substitutions: See Section 01 6000 - Product Requirements.

Page 22: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 26 0529 - 2

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

PART 3 EXECUTION

3.01 INSTALLATION

A. Install hangers and supports as required to adequately and securely support electrical system components, in a neat and workmanlike manner, as specified in NECA 1. 1. Do not fasten supports to pipes, ducts, mechanical equipment, or conduit. 2. Obtain permission from Architect before drilling or cutting structural members.

B. Rigidly weld support members or use hexagon-head bolts to present neat appearance with adequate strength and rigidity. Use spring lock washers under all nuts. Paint all surfaces.

C. Install surface-mounted cabinets and panelboards with minimum of four anchors.

D. In wet and damp locations use steel channel supports to stand cabinets and panelboards 1 inch off wall.

E. Use sheet metal channel to bridge studs above and below cabinets and panelboards recessed in hollow partitions.

END OF SECTION

Page 23: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 26 0534 - 1

CONDUIT

SECTION 26 0534

CONDUIT

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Conduit, fittings and conduit bodies.

1.02 RELATED REQUIREMENTS

A. Section 07 8400 - Firestopping.

B. Section 26 0526 - Grounding and Bonding for Electrical Systems.

C. Section 26 0529 - Hangers and Supports for Electrical Systems.

D. Section 26 0553 - Identification for Electrical Systems.

E. Section 26 0537 - Boxes.

1.03 REFERENCE STANDARDS

A. ANSI C80.1 - American National Standard for Electrical Rigid Steel Conduit (ERSC); 2005.

B. ANSI C80.3 - American National Standard for Steel Electrical Metallic Tubing (EMT); 2005.

C. NECA 1 - Standard Practices for Good Workmanship in Electrical Contracting; National Electrical Contractors Association; 2006.

D. NECA 101 - Standard for Installing Steel Conduit (Rigid, IMC, EMT); National Electrical Contractors Association; 2006.

E. NEMA FB 1 - Fittings, Cast Metal Boxes, and Conduit Bodies for Conduit, Electrical Metallic Tubing, and Cable; National Electrical Manufacturers Association; 2007.

F. NEMA RN 1 - Polyvinyl Chloride (PVC) Externally Coated Galvanized Rigid Steel Conduit and Intermediate Metal Conduit; National Electrical Manufacturers Association; 2005.

G. NFPA 70 - National Electrical Code; National Fire Protection Association; 2008.

1.04 SUBMITTALS

A. See Section 01 3000 - Administrative Requirements for submittals procedures.

B. Project Record Documents: Accurately record actual routing of conduits larger than 2 inches.

1.05 QUALITY ASSURANCE

A. Conform to requirements of NFPA 70.

B. Products: Listed and classified by Underwriters Laboratories Inc. as suitable for purpose specified and shown.

1.06 PROJECT CONDITIONS

A. Verify that field measurements are as shown on Drawings.

B. Verify routing and termination locations of conduit prior to rough-in.

C. Conduit routing is shown on Drawings in approximate locations unless dimensioned. Route as required to complete wiring system.

Page 24: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 26 0534 - 2

CONDUIT

1.07 DELIVERY, STORAGE, AND HANDLING

A. Accept conduit on site. Inspect for damage.

B. Protect conduit from corrosion and entrance of debris by storing above grade. Provide appropriate covering.

PART 2 PRODUCTS

2.01 CONDUIT REQUIREMENTS

A. Conduit Size: Comply with NFPA 70. 1. Minimum Size: 3/4 inch unless otherwise specified. Minimum size for home runs is 3/4

inch.

B. Wet and Damp Locations: Use rigid steel conduit or intermediate metal conduit.

C. Dry Locations: 1. Concealed: Use electrical metallic tubing. 2. Exposed: Use rigid steel conduit or electrical metallic tubing. Use rigid steel conduit

where subject to mechanical injury.

D. Connections to Equipment: Use flexible metal conduit ONLY for connecting to transformers, motors, fixed appliances and recessed luminaires. Use PVC jacketed flexible conduit with liquid-tight fittings in areas of high moisture content.

2.02 METAL CONDUIT

A. Manufacturers: 1. Allied Tube & Conduit: www.alliedtube.com. or equal

B. Rigid Steel Conduit: ANSI C80.1.

C. Fittings and Conduit Bodies: NEMA FB 1; all steel fittings. ANSI/NEMA FB 1; steel threaded, hot dipped galvanized. Connectors with insulated throats installed with bonding type locknuts inside and outside enclosure. Set screw fittings not permitted.

2.03 FLEXIBLE METAL CONDUIT

A. Manufacturers: 1. AFC Cable Systems, Inc: www.afcweb.com. or equal.

B. Description: Interlocked steel construction.

C. Fittings: NEMA FB 1.

2.04 LIQUIDTIGHT FLEXIBLE METAL CONDUIT

A. Manufacturers: 1. AFC Cable Systems, Inc: www.afcweb.com. or equal.

B. Description: Interlocked steel construction with PVC jacket. Provide continuous integral copper ground.

C. Fittings: NEMA FB 1. Rain tight compression ring steel fitting. Connectors with insulated throat.

2.05 ELECTRICAL METALLIC TUBING (EMT)

A. Manufacturers: 1. Allied Tube & Conduit: www.alliedtube.com. or equal.

Page 25: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 26 0534 - 3

CONDUIT

B. Description: ANSI C80.3; galvanized tubing.

C. Fittings and Conduit Bodies: NEMA FB 1; steel set screw insulated throat type.

2.06 FIRESTOP

A. Provide a firestop system with an "F" rating as determined by UL 1479 or ASTM E814 which is equal to the time rating of construction being penetrated. 1. For penetrations by non-combustible items including steel pipe, copper pipe, rigid steel

conduit, and electrical metallic tubing (EMT), the following are acceptable: a. Hilti FS 601 electrometric firestop sealant or Fs 605 HP firestop sealant. b. 3M fire barrier CP25. c. Nelson CLK firestop sealant

2. For fire-rated construction joints and other gaps, the following may be used: a. Hilti FS 601. b. 3M fire barrier CP25. c. Nelson CLK firestop sealant.

3. For penetrations by non-combustible items (penetrants consumed by high heat and flame) including insulated metal pipe, PVC jacketed, flexible cable, or cable bundles, and plastic pipe (closed piping systems), the following are acceptable: a. Hilti FS 611A intumescent firestop sealant. b. 3M barrier CP 25. c. 3M fire barrier FS-195 wrap strip. d. Nelson FSP firestop putty, PCS pipe choke system.

4. For large complex penetrations made to accommodate cable trays, multiple steel and copper pipes, electrical busways or raceways, the following are acceptable: a. Hilti FS 635, trowelable firestop compound. b. 3M fire barrier CS-195 composite sheet. c. Nelson CPS composite sheet, CMP firestop compound.

PART 3 EXECUTION

3.01 EXAMINATION

A. Verify that field measurements are as shown on drawings.

B. Verify routing and termination locations of conduit prior to rough-in.

C. Conduit routing is shown on drawings in approximate locations unless dimensioned. Route as required to complete wiring system.

3.02 INSTALLATION

A. Install conduit securely, in a neat and workmanlike manner, as specified in NECA 1.

B. Install steel conduit as specified in NECA 101.

C. Arrange supports to prevent misalignment during wiring installation.

D. Support conduit using coated steel or malleable iron straps, lay-in adjustable hangers, clevis hangers, and split hangers.

E. Group related conduits; support using conduit rack. Construct rack using steel channel; provide space on each for 25 percent additional conduits.

F. Fasten conduit supports to building structure and surfaces under provisions of Section 26 0529.

G. Do not support conduit with wire or perforated pipe straps. Remove wire used for temporary supports.

Page 26: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 26 0534 - 4

CONDUIT

H. Do not attach conduit to ceiling support wires.

I. Arrange conduit to maintain headroom and present neat appearance.

J. Route conduit parallel and perpendicular to walls.

K. Route conduit installed above accessible ceilings parallel and perpendicular to walls.

L. Maintain adequate clearance between conduit and piping.

M. Maintain 12 inch clearance between conduit and surfaces with temperatures exceeding 104 degrees F.

N. Cut conduit square using saw or pipecutter; de-burr cut ends.

O. Bring conduit to shoulder of fittings; fasten securely.

P. Use conduit hubs to fasten conduit to sheet metal boxes in damp and wet locations, and to cast boxes.

Q. Install no more than equivalent of three 90 degree bends between boxes. Use conduit bodies to make sharp changes in direction, as around beams. Use hydraulic one shot bender to fabricate bends in metal conduit larger than 2 inch size.

R. Avoid moisture traps; provide junction box with drain fitting at low points in conduit system.

S. Provide suitable fittings to accommodate expansion and deflection where conduit crosses control and expansion joints.

T. Provide suitable pull string in each empty conduit except sleeves and nipples.

U. Use suitable caps to protect installed conduit against entrance of dirt and moisture.

V. Conceal conduit in all areas except mechanical and electrical rooms, connections to motors, and connections to surface-mounted cabinets or where noted on Drawings.

W. Install all conduit within the building except where specifically noted.

X. Route conduit continuous from outlet to outlet, outlet to cabinets, outlet to pull or junction boxes. Secure conduit to all boxes with locknuts and bushings in such manner that each system is mechanically and electrically continuous throughout.

Y. Conduit systems must be installed complete before conductors are pulled in.

Z. Repair any damage done to insulation or interior vapor barrier.

AA. Fill conduits which can admit air to or release air from air plenums through the connecting conduit system with sealing compound.

AB. Seal around all conduits passing through partitions such as walls, floor slabs and other elements. For non-rated partitions, sealant to match surrounding surface. For rated partitions, provide fireproofing sealant which preserves the fire resistant rating of the partition. Use materials and methods as directed by the manufacturer of the fireproofing and approved by the Architect/Engineer. See Architectural drawings and existing building drawings for location of new and existing fire-rated partitions.

AC. Ground and bond conduit under provisions of Section 26 0526.

AD. Identify conduit under provisions of Section 26 0553.

Page 27: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 26 0534 - 5

CONDUIT

3.03 INTERFACE WITH OTHER PRODUCTS

A. Install conduit to preserve fire resistance rating of partitions and other elements, using materials and methods specified in this section and Section 07 8400.

END OF SECTION

Page 28: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 26 0534 - 6

CONDUIT

Page 29: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 26 0537 - 1

BOXES

SECTION 26 0537

BOXES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Wall and ceiling outlet boxes.

B. Pull and junction boxes.

1.02 RELATED REQUIREMENTS

A. Section 07 8400 - Firestopping.

1.03 PRODUCTS INSTALLED BUT NOT FURNISHED UNDER THIS SECTION

A. Equipment backboxes for selected items of equipment are furnished by the equipment supplier. Refer to individual specification sections for mounting, size, etc.

1.04 REFERENCE STANDARDS

A. NECA 1 - Standard Practices for Good Workmanship in Electrical Contracting; National Electrical Contractors Association; 2006.

B. NEMA FB 1 - Fittings, Cast Metal Boxes, and Conduit Bodies for Conduit, Electrical Metallic Tubing, and Cable; National Electrical Manufacturers Association; 2007.

C. NEMA OS 1 - Sheet Steel Outlet Boxes, Device Boxes, Covers, and Box Supports; National Electrical Manufacturers Association; 2008.

D. NEMA OS 2 - Nonmetallic Outlet Boxes, Device Boxes, Covers and Box Supports; National Electrical Manufacturers Association; 2008.

E. NEMA 250 - Enclosures for Electrical Equipment (1000 Volts Maximum); National Electrical Manufacturers Association; 2008.

F. NFPA 70 - National Electrical Code; National Fire Protection Association; 2008.

1.05 SUBMITTALS

A. See Section 01 3000 - Administrative Requirements, for submittal procedures.

B. Project Record Documents: Record actual locations and mounting heights of outlet, pull, and junction boxes on project record documents.

1.06 PROJECT CONDITIONS

A. Verify field measurements are as shown on Drawings.

B. Electrical boxes are shown on Drawings in approximate locations unless dimensioned. Install at location required for box to serve intended purpose.

1.07 QUALITY ASSURANCE

A. Conform to requirements of NFPA 70.

B. Products: Provide products listed and classified by Underwriters Laboratories Inc., as suitable for the purpose specified and indicated.

Page 30: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 26 0537 - 2

BOXES

PART 2 PRODUCTS

2.01 MANUFACTURERS

A. Appleton Electric: www.appletonelec.com. or equal

2.02 OUTLET BOXES

A. Sheet Metal Outlet Boxes: NEMA OS 1, galvanized steel. 1. Two-Gang Outlet and Smaller: Utilize 4-inch square box with tile ring or concrete-block

type box. 2-1/8 inch deep minimum. 2. Three-Gang Outlet and Larger: Utilize concrete-block type box only. 2-1/8 inch deep

minimum. 3. Ceiling Boxes: 4 inches square, 1-1/2 inches deep, with a round tile ring.

B. Wall Plates for Finished Areas: As specified in Section 26 2726.

C. Surface Mounted Outlets: Interior Dry Locations. 1. Manufacturer: Raco, or equal. 2. Type: 4-inch square boxes with matching raised covers. 3. Utilize for outlet boxes on exposed conduit runs.

2.03 PULL AND JUNCTION BOXES

A. Sheet Metal Boxes: NEMA OS 1, galvanized steel. 1. Surface Mounted Type: Metal construction, conforming to National Electric Code, with

screw-on or hinged cover. 2. Flush Mounted Type: Overlapping covers with flush head cover retaining screws, prime

coated for flush mounted pull boxes.

B. Hinged Enclosures: As specified in Section 26 2716.

C. Surface Mounted Cast Metal Box: NEMA 250, Type 4; flat-flanged, surface mounted junction box: 1. Material: Galvanized cast iron. 2. Cover: Furnish with ground flange, neoprene gasket, and stainless steel cover screws.

PART 3 EXECUTION

3.01 EXAMINATION

A. Verify locations of outlets in offices and work areas prior to rough-in.

3.02 INSTALLATION

A. Install boxes securely, in a neat and workmanlike manner, as specified in NECA 1.

B. Install in locations as shown on Drawings, and as required for splices, taps, wire pulling, equipment connections, and as required by NFPA 70.

C. Set wall mounted boxes at elevations to accommodate mounting heights indicated.

D. Electrical boxes are shown on Drawings in approximate locations unless dimensioned. 1. Adjust box locations up to 10 feet if required to accommodate intended purpose.

E. Orient boxes to accommodate wiring devices oriented as specified in Section 26 2726.

F. Maintain headroom and present neat mechanical appearance.

G. Install pull boxes and junction boxes above accessible ceilings and in unfinished areas only.

H. Inaccessible Ceiling Areas: Install outlet and junction boxes no more than 6 inches from ceiling

Page 31: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 26 0537 - 3

BOXES

access panel or from removable recessed luminaire.

I. Install boxes to preserve fire resistance rating of partitions and other elements, using materials and methods specified in Section 07 8400 or as directed by Architect/Engineer.

J. Coordinate mounting heights and locations of outlets mounted above counters, benches, and backsplashes.

K. Align adjacent wall mounted outlet boxes for switches, thermostats, and similar devices.

L. Use flush mounting outlet box in finished areas.

M. Locate flush mounting box in masonry wall to require cutting of masonry unit corner only. Coordinate masonry cutting to achieve neat opening.

N. Do not install flush mounting box back-to-back in walls; provide minimum 6 inches separation. Provide minimum 24 inches separation in acoustic and fire rated walls.

O. Secure flush mounting box to interior wall and partition studs. Accurately position to allow for surface finish thickness.

P. Use stamped steel bridges to fasten flush mounting outlet box between studs.

Q. Install flush mounting box without damaging wall insulation or reducing its effectiveness.

R. Use adjustable steel channel fasteners for hung ceiling outlet box.

S. Do not fasten boxes to ceiling support wires.

T. Support boxes independently of conduit, except cast box that is connected to two rigid metal conduits both supported within 12 inches of box.

U. Use gang box where more than one device is mounted together. Do not use sectional box.

V. Use gang box with plaster ring for single device outlets.

W. Surface mounted outlets are permitted only in mechanical and electrical rooms and above removable ceilings.

X. Boxes protruding from the finished wall will not be accepted.

Y. Install flush mounting box without damaging wall insulation or reducing its effectiveness.

Z. Support boxes independently of conduit, except cast box that is connected to two rigid metal conduits both supported within 12 inches of box.

AA. Use 4-inch square box with plaster ring or tile wall box for single or two device outlets. Do not use handy box.

AB. Use surface mounted 4-inch square box with matching raised cover on exposed conduit runs.

AC. Use 4-inch square, 1-1/2 inch deep box with round tile ring in ceiling.

AD. Install outlets at the heights and approximate designated positions as shown on Drawings or indicated in Specifications, unless otherwise directed.

AE. Install outlets in similar rooms in the same relative location in each room.

AF. Locate outlets to clear piping, duct work and other obstructions.

AG. Mounting heights indicated on Drawings are to center line of outlet unless indicated otherwise.

AH. Pull boxes and junction boxes are not indicated on Drawings except for special requirements. Install as required to facilitate pulling wire. Size as required by National Electric Code. Install

Page 32: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 26 0537 - 4

BOXES

above removable ceilings, electrical rooms, utility rooms or storage areas in accessible locations. Installation in finished spaces not permitted without approval of the Architect/Engineer.

AI. Do not mount junction boxes or pull boxes to duct work, ceiling system or other piping. Mount from structural system only. Mount independent of conduit system. Junction boxes supported only from conduit system will not be permitted.

AJ. Provide insulating barriers in gang type switch boxes containing more than one switch when connected to different voltage systems or to different phases of a 277 volt system.

AK. Insulate behind boxes mounted in exterior walls to prevent condensation in boxes.

AL. Mount receptacles in the equipment rooms and in other unfinished areas at 48 inches.

AM. Label all junction box covers with panelboard name and circuit numbers for circuits in junction box. Label all junction box covers with the type of communication system contained within; example: "Nurse Call," "Security," etc.

AN. Coordinate mounting heights and locations of outlets mounted above counters, benches, backsplashes and mechanical radiation.

3.03 ADJUSTING

A. Adjust flush-mounting outlets to make front flush with finished wall material.

B. Install knockout closures in unused box openings.

3.04 CLEANING

A. Clean interior of boxes to remove dust, debris, and other material.

B. Clean exposed surfaces and restore finish.

END OF SECTION

Page 33: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 26 0553 - 1

IDENTIFICATION FOR ELECTRICAL SYSTEMS

SECTION 26 0553

IDENTIFICATION FOR ELECTRICAL SYSTEMS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Nameplates and labels.

B. Wire and cable markers.

C. Color identification of conduit.

1.02 RELATED REQUIREMENTS

A. Section 09 9000 - Painting and Coating.

1.03 REFERENCE STANDARDS

A. NFPA 70 - National Electrical Code; National Fire Protection Association; 2008.

1.04 QUALITY ASSURANCE

A. Conform to requirements of NFPA 70.

B. Products: Listed and classified by Underwriters Laboratories Inc. as suitable for purpose specified and shown.

PART 2 PRODUCTS

2.01 IDENTIFICATION APPLICATIONS

A. Conduit: Conduit markers.

2.02 MANUFACTURERS

A. Brady Corporation: www.bradycorp.com.

B. Seton Identification Products: www.seton.com/aec.

C. HellermannTyton: www.hellermanntyton.com.

D. Substitutions: See Section 01 6000 - Product Requirements.

2.03 CONDUIT COLORS

A. Description: Factory pigmentation of conduit for certain electrical systems.

B. Color: 1. Fire Alarm System: Red.

C. Junction Boxes: 1. The junction boxes for each respective system shall be field painted or factory pigmented

to match the conduit color. 2. Each junction box cover shall be labelled as to the system containted within; example 'Fire

Alarm', 'Telephone', etc.

2.04 JUNCTION BOX LABELS

Page 34: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 26 0553 - 2

IDENTIFICATION FOR ELECTRICAL SYSTEMS

A. Description: Labelling of junction box covers.

B. Locations: 1. Each junction box cover. 2. Label with panel and circuit number all power junction boxes. 3. Label with system description all communication junction boxes.

C. Provide labels per paragraph 2.02 D.

PART 3 EXECUTION

3.01 PREPARATION

A. Degrease and clean surfaces to receive nameplates and labels.

END OF SECTION

Page 35: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 28 3100 - 1

FIRE ALARM SYSTEM

SECTION 28 3100

FIRE ALARM SYSTEM

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Fire alarm system design and installation, including all components, wiring, and conduit.

B. Replacement and removal of existing fire alarm system components, wiring, and conduit indicated.

C. Maintenance of fire alarm system under contract for specified warranty period.

1.02 RELATED SECTIONS

A. Section 07 8400 - Firestopping: Materials and methods for work to be performed by this installer.

B. Section 21 1300 - Fire-Suppression Sprinkler Systems: Supervisory, alarm, and actuating devices installed in sprinkler system.

1.03 REFERENCES

A. NFPA 70 - National Electrical Code; 2008.

B. NFPA 72 - National Fire Alarm Code ; 2007.

C. NFPA 101 - Code for Safety to Life from Fire in Buildings and Structures; 2003.

D. NFPA 601 - Standard for Security Services in Fire Loss Prevention; 2005.

E. IIBC 2006 - International Building Code, 2006

1.04 SUBMITTALS

A. See Section 01 3000 - Administrative Requirements, for submittal procedures.

B. Proposal Documents: Submit the following with cost/time proposal: 1. NFPA 72 "Record of Completion", filled out to the extent known at the time. 2. Manufacturer's detailed data sheet for each control unit, initiating device, and notification

appliance. 3. Certification by Contractor that the system design will comply with the contract documents. 4. Proposed maintenance contract.

C. Drawings must be prepared using AutoCAD Release R2000 or later. 1. Architect will provide floor plan drawings for Contractor's use; verify all dimensions on the

provided drawings.

D. Evidence of designer qualifications.

E. Design Documents: Submit all information required for plan review and permitting by authorities having jurisdiction, including but not limited to floor plans, riser diagrams, and description of operation: 1. Copy (if any) of list of data required by authority having jurisdiction. 2. NFPA 72 "Record of Completion", filled out to the extent known at the time. 3. Clear and concise description of operation, with input/output matrix similar to that shown in

NFPA 72 Appendix A-7-5-2.2(9), and complete listing of software required. 4. System zone boundaries and interfaces to fire safety systems. 5. Location of all components, circuits, and raceways; mark components with identifiers used

in control unit programming.

Page 36: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 28 3100 - 2

FIRE ALARM SYSTEM

6. Manufacturer's detailed data sheet for each component, including wiring diagrams, installation instructions, and circuit length limitations.

7. Description of power supplies; if secondary power is by battery include calculations demonstrating adequate battery power.

8. Certification by either the manufacturer of the control unit or by the manufacturer of each other component that the components are compatible with the control unit.

9. Certification by the manufacturer of the control unit that the system design complies with the contract documents.

10. Certification by Contractor that the system design complies with the contract documents.

F. Evidence of installer qualifications.

G. Evidence of maintenance contractor qualifications, if different from installer.

H. Inspection and Test Reports: 1. Submit inspection and test plan prior to closeout demonstration. 2. Submit documentation of satisfactory inspections and tests. 3. Submit NFPA 72 "Inspection and Test Form," filled out.

I. Operating and Maintenance Data: See Section 01 7800 for additional requirements; revise and resubmit until acceptable; have one set available during closeout demonstration: 1. Complete set of specified design documents, as approved by authority having jurisdiction. 2. Additional printed set of project record documents and closeout documents, bound or filed

in same manuals. 3. Contact information for firm that will be providing contract maintenance and trouble

call-back service. 4. List of recommended spare parts, tools, and instruments for testing. 5. Replacement parts list with current prices, and source of supply. 6. Detailed troubleshooting guide and large scale input/output matrix. 7. Preventive maintenance, inspection, and testing schedule complying with NFPA 72;

provide printed copy and computer format acceptable to UCCS. 8. Detailed but easy to read explanation of procedures to be taken by non-technical

administrative personnel in the event of system trouble, when routine testing is being conducted, for fire drills, and when entering into contracts for remodeling.

J. Project Record Documents: See Section 01 7800 for additional requirements; have one set available during closeout demonstration: 1. Complete set of floor plans showing actual installed locations of components, conduit, and

zones. 2. "As installed" wiring and schematic diagrams, with final terminal identifications. 3. "As programmed" operating sequences, including control events by device, updated

input/output chart, and voice messages by event.

K. Closeout Documents: 1. Certification by manufacturer that the system has been installed in compliance with his

installation requirements, is complete, and is in satisfactory operating condition. 2. NFPA 72 "Record of Completion", filled out completely and signed by installer and

authorized representative of authority having jurisdiction. 3. Maintenance contract. 4. Report on training results.

1.05 QUALITY ASSURANCE

A. Designer Qualifications: NICET Level III or IV (3 or 4) certified fire alarm technician or registered fire protection engineer, employed by fire alarm control panel manufacturer, Contractor, or installer, with experience designing fire alarm systems in the jurisdictional area of the authorities having jurisdiction.

Page 37: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 28 3100 - 3

FIRE ALARM SYSTEM

B. Installer Qualifications: Firm with minimum 3 years documented experience installing fire alarm systems of the specified type and providing contract maintenance service as a regular part of their business. 1. Authorized representative of control unit manufacturer; submit manufacturer's certification

that installer is authorized; include name and title of manufacturer's representative making certification.

2. Installer Personnel: At least 2 years of experience installing fire alarm systems. 3. Supervisor: NICET level III or IV (3 or 4) certified fire alarm technician; furnish name and

address. 4. Contract maintenance office located within 100 miles of project site.

C. Maintenance Contractor Qualifications: Same entity as installer.

1.06 EXTRA MATERIALS AND TOOLS

A. See Section 01 6000 - Product Requirements, for additional provisions.

B. Provide spare parts of same manufacturer and model as those installed; deliver in original packaging, labeled in same manner as in operating and maintenance data.

C. In addition to the items in quantities indicated in PART 2, provide the following: 1. All tools, software, and documentation necessary to modify the fire alarm system using

UCCS's personnel; minimum modification capability to include addition and deletion of devices, circuits, and zones, and changes to system description, operation, and evacuation and instructional messages.

2. CD-ROM copies, 2, of all software not resident in read-only-memory.

1.07 WARRANTY

A. Provide control panel manufacturer's warranty that system components other than wire and conduit are free from defects and will remain so for 1 year after date of Substantial Completion.

B. Provide installer's warranty that the installation is free from defects and will remain so for 1 year after date of Substantial Completion.

PART 2 PRODUCTS

2.01 MANUFACTURERS

A. Fire Alarm Control Units - Basis of Design: SimplexGrinnell ; 4100U: www.simplexgrinnell.com.

B. Initiating Devices, and Notification Appliances: 1. Same manufacturer as control units.

C. Substitutions: See Section 01 6000 - Product Requirements. 1. The project is tying into an exisrting Simplex 4100U FACP, use only UL listed devices for

the existing FACP.

2.02 FIRE ALARM SYSTEM

A. Fire Alarm System: Provide modifications and extensions to the existing automatic fire detection and alarm system: 1. Provide all components necessary, regardless of whether shown in the contract documents

or not. 2. Protected Premises: Entire building shown on drawings. 3. Comply with the following; where requirements conflict, order of precedence of

requirements is as listed: a. The Americans With Disabilities Act (ADA). b. The requirements of the State Fire Marshall.

Page 38: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 28 3100 - 4

FIRE ALARM SYSTEM

c. The requirements of the local authority having jurisdiction. d. Applicable local codes. e. The contract documents (drawings and specifications). f. IBC 2003 g. NFPA 101. h. NFPA 72; where the word "should" is used consider that provision mandatory; where

conflicts between requirements require deviation from NFPA 72, identify deviations clearly on design documents.

4. Evacuation Alarm: Single smoke zone; general evacuation of entire premises. 5. Master Control Unit (Panel): Existing, located at location shown on the drawings. 6. Combined Systems: Do not combine fire alarm system with other non-fire systems. 7. Alarm Sequence of Operation: Actuation of manual fire alarm station, initiating device, fire

extinguishing system operation, heat detector, smoke detector, and water flow switch, or other causes system to enter ALARM, which includes the following operations: a. Alarm notification appliances shall operate continuously. b. Transmit alarm signal to remote alarm receiving station. c. Identify alarm and device on the fire alarm control panel and on the remote

annunciator panel(s). d. Switch HVAC equipment controls to fire alarm mode. e. Transmit signal to building mechanical systems to initiate shutdown of fans and close

associated smoke dampers. f. De-energize electromagnetic door hold-open devices. g. Record events in system memory.

8. System trouble signal initiation shall be by one or more of the following devices or actions: a. Open circuits, shorts and grounds of wiring of initiation device signaling line and

notification appliance circuits. b. Opening, tampering, or removal of alarm initiating and supervisory signal initiating

devices. c. Loss of power at FACP. d. Ground or single break in FACP internal circuits. e. Abnormal AC voltage at FACP. f. A break in standby battery circuitry. g. Failure of battery charging. h. Abnormal position of any switch at FACP or annunciator.

9. Supervisory signal initiation shall be by one or more of the following devices or actions: a. Operation of a fire-protection system valve tamper, standpipe valve supervisory switch

or fire pump alarm switch.

B. Circuits: 1. Initiating Device Circuits (IDC): Class A, Style D. 2. Signaling Line Circuits (SLC) Within Single Building: Class A, Style 6. 3. Notification Appliance Circuits (NAC): Class A, Style Z.

2.03 FIRE SAFETY SYSTEMS INTERFACES

A. Supervision: Provide supervisory signals in accordance with NFPA 72 for the following: 1. Sprinkler water control valves.

B. Alarm: Provide alarm initiation in accordance with NFPA 72 for the following: 1. Sprinkler water flow.

2.04 COMPONENTS

A. General: 1. Provide flush mounted units where installed in finish areas; in unfinished areas, surface

mounted unit are acceptable. 2. Provide legible, permanent labels for each control device, using identification used in

Page 39: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 28 3100 - 5

FIRE ALARM SYSTEM

operation and maintenance data.

B. Fire Alarm Control Units, Initiating Devices, and Notification Appliances: Analog, addressable type; listed by Underwriters Laboratories as suitable for the purpose intended.

C. Master Control Unit: The existign Simplex panel shall monitor all new devices.. 1. Control Panel: Modular construction with surface wall-mounted enclosure. Steel

enclosure with rust-resistant prime coat and baked enamel finish

D. Initiating Devices: 1. Addressable Interface Devices: Microelectronic monitor module listed for use in providing

a system address for listed alarm-initiating devices for wired applications with normally open contacts.

E. Auxiliary Devices 1. Surface Backboxes: Provide surface mounted backboxes by system manufacturer where

devices are surface mounted..

F. Circuit Conductors: Copper; provide 200 feet extra; color code and label. 1. Wire and cable for fire alarm systems shall be UL listed and labeled as complying with

NFPA 70, Article 760. 2. Provide fire alarm circuit conductors with color coded insulation. Color code fire alarm

conductors different from building power wiring. Use one color-code for alarm circuit wiring different from supervisory wiring. Color code audible alarm circuits different from alarm initiating circuits. Contractor shall verify and match the existing buildign fire alarm color coding.

3. Non-Power-Limited Circuits: Solid-copper conductors with 600-V rated, 75 degree C, color-coded insulation. See Section 16123. a. Low-Voltage Circuits: No. 14 AWG, minimum. b. Line-Voltage Circuits: No. 12 AWG, minimum.

G. Instruction Charts: Printed instruction chart for operators, showing steps to be taken when a signal is received (normal, alarm, supervisory, and trouble); easily readable from normal operator's station. 1. Frame: Stainless steel or aluminum with polycarbonate or glass cover. 2. Provide one for each control unit where operations are to be performed. 3. Obtain approval of UCCS prior to mounting; mount in location acceptable to UCCS. 4. Provide extra copy with operation and maintenance data submittal.

PART 3 EXECUTION

3.01 INSTALLATION

A. Install in accordance with applicable codes, NFPA 72, NFPA 70, and the contract documents.

B. Conceal all wiring, conduit, boxes, and supports where installed in finished areas.

C. Obtain UCCS's approval of locations of devices, before installation.

D. Install instruction cards and labels.

E. Use manufacturer recommended specified conductors for signal line circuits and power limited circuits. Install all wiring in conduit. Minimum conduit size of 3/4 inch. See Section 16131 for conduit requirements.

F. All conduit to be red in color utilizing factory pigmentation, not painted in the field.

G. Make conduit and wiring connections to all devices shown on Drawings and as specified.

H. Permanently identify wires in junction boxes and cabinets. Refer to Section 16075 - Electrical Identification.

Page 40: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 28 3100 - 6

FIRE ALARM SYSTEM

I. Paint terminal boxes, junction boxes and cabinets red and label "FIRE ALARM."

J. Splicing of conductors within the fire alarm control panel is NOT allowed. Provide terminal cabinet adjacent to or above FACP to make splices, cabinet to be in concealed when FACP is installed in finished location.

K. Use of "Push-In" pressure connectors for fire alarm wiring is not allowed. Wirenuts shall be used for splicing cables.

L. All surface mounted devices are to be installed in system manufactured boxes.

M. Install wiring according to NECA 1 and TIA/EIA 568-A.

N. Install conduit in accordance with Section 26 0534. The fire alarm system wiring shall be installed in a dedicated raceway in accordance with NFPA 72. Class A circuits shall be installed such that the outgoing and return conductors, existing and returning to the control panel are routed separately and not in the same raceway or enclosure.

O. Ground the FACP to comply with IEEE 1100, see Section 26 0526.

P. Wiring with Enclosures: Separate power-limited and non-power-limited conductors as recommended by manufacturer. Install conductors parallel with or at right angles to sides and back of the enclosure. Bundle, lace, and train conductors to terminal points with no excess. Connect conductors that are terminated, splices, or interrupted in any enclosure associated with the fire alarm system to terminal blocks. Mark each terminal according to the system’s wiring diagrams. Make all connections with approved crimp-on terminal spade lugs, pressure-type terminal blocks, or plus connectors.

3.02 INSPECTION AND TESTING FOR COMPLETION

A. Notify UCCS 7 days prior to beginning completion inspections and tests.

B. Notify authorities having jurisdiction and comply with their requirements for scheduling inspections and tests and for observation by their personnel.

C. Provide the services of the installer's supervisor or person with equivalent qualifications to supervise inspection and testing, correction, and adjustments.

D. Prepare for testing by ensuring that all work is complete and correct; perform preliminary tests as required.

E. Provide all tools, software, and supplies required to accomplish inspection and testing.

F. Perform inspection and testing in accordance with NFPA 72 and requirements of local authorities; document each inspection and test.

G. Correct defective work, adjust for proper operation, and retest until entire system complies with contract documents.

3.03 CLOSEOUT

A. Closeout Demonstration: Demonstrate proper operation of all functions to UCCS. 1. Be prepared to conduct any of the required tests. 2. Have at least one copy of operation and maintenance data, preliminary copy of project

record drawings, input/output matrix, and operator instruction chart(s) available during demonstration.

3. Have authorized technical representative of control unit manufacturer present during demonstration.

4. Demonstration may be combined with inspection and testing required by authority having jurisdiction; notify authority having jurisdiction in time to schedule demonstration.

5. Repeat demonstration until successful.

Page 41: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 28 3100 - 7

FIRE ALARM SYSTEM

3.04 MAINTENANCE

A. Provide to UCCS, at no extra cost, a written maintenance contract for entire manufacturer's warranty period, to include the work described below.

B. Perform routine inspection, testing, and preventive maintenance required by NFPA 72, including: 1. Maintenance of fire safety interface and supervisory devices connected to fire alarm

system. 2. Repairs required, unless due to improper use, accidents, or negligence beyond the control

of the maintenance contractor. 3. Record keeping required by NFPA 72 and authorities having jurisdiction.

C. Provide trouble call-back service upon notification by UCCS: 1. Provide on-site response within 2 hours of notification. 2. Include allowance for call-back service during normal working hours at no extra cost to

UCCS. 3. UCCS will pay for call-back service outside of normal working hours on an hourly basis,

based on actual time spent at site and not including travel time; include hourly rate and definition of normal working hours in maintenance contract.

D. Provide a complete description of preventive maintenance, systematic examination, adjustment, cleaning, inspection, and testing, with a detailed schedule.

E. Maintain a log at each fire alarm control unit, listing the date and time of each inspection and call-back visit, the condition of the system, nature of the trouble, correction performed, and parts replaced. Submit duplicate of each log entry to UCCS's representative upon completion of site visit.

F. Comply with UCCS's requirements for access to facility and security.

END OF SECTION

Page 42: UCCS University Hall Fire Sprinkler System Upgrade Feb. 28 ......UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00 Contract Document Set FIRE SPRINKLER

UCCS University Hall Fire Sprinkler System Upgrade Feb. 28, 2011 RTA 10070.00

CONSTRUCTION DOCUMENT SET 28 3100 - 8

FIRE ALARM SYSTEM