UARB Decision - Final

Embed Size (px)

Citation preview

  • 7/30/2019 UARB Decision - Final

    1/17

    Upper Churchill Power The Unexamined Alternative

    The UARB Decision

    h i l h f dl d

  • 7/30/2019 UARB Decision - Final

    2/17

    Th P i l I h N f dl d R

    The UARB Decision

    Executive Summary

    On July 22, 2013, the UARB in Nova Scotia conditionally approved the Maritime Link Project.The approval was dependent upon the guaranteed availability of surplus energy representing

    about 40% of Muskrat Falls production, being available at market prices over the 35 year term

    of the agreement with Nalcor. This condition should not have been a surprise to observers of

    the Nova Scotia hearings, as it intended to codify what was presented by Emera themselves in

    their application to the UARB.

    The UARB demand to guarantee both the quantity and price of surplus energy over the 35 year

    term is not a minor condition, and should be properly explained to the people of Newfoundland

    and Labrador. Yet in their July 27 and August 3 Letters to the Telegram, both Ed Martin and

    Tom Marshall have not provided any commentary regarding the potential consequences of this

    decision, nor have they offered any insight into how both Nalcor and Emera will proceed.

    The implementation of the UARB condition will mean that Emera no longer will receive 20% of

    the power for 20% of the cost. Instead, Nova Scotia will receive 60% of the power, for what

    amounts to about 30% of the cost. Meeting the UARB condition will have an impact on the

    final rate to the NL consumer. This paper will attempt to further explain the potential impacts

    of this decision.

    Based on the DG2 data provided by Nalcor to the PUB, there is a potential 37% increase in the

    incremental rates charged to NL ratepayers for Muskrat Falls Energy if the conditions of the

    UARB are met. This would be reduced to a 10% increase if all export revenue in the early years

    of the project were used to offset the burden on the NL ratepayer. This is assuming that the

    Holyrood thermal plant can be decommissioned as per the original plan If the allocation of

  • 7/30/2019 UARB Decision - Final

    3/17

    The UARB Decision

    Part I: Introduction

    The decision by the Nova Scotia Utility and Review Board (UARB) to approve the Maritime Linkproject, with a condition that there must be surplus power available at New England market

    rates consistent with Figure 4.4 of the Emera application, represents a fundamental departure

    from the deal that was signed in November 2010. It is perhaps the biggest challenge that the

    project has faced to date, having the potential to put both additional cost, and risk onto the

    Newfoundland rate payer.

  • 7/30/2019 UARB Decision - Final

    4/17

    The UARB Decision

    Accordingly, the Board directs as a condition to its approval of the ML Project that

    NSPML obtain from Nalcor the right to access Nalcor Market-priced Energy

    (consistent with the assumptions in the Application as noted in NSUARB IR-37 andFigure 4-4) when needed to economically serve NSPI and its ratepayers; or provide

    some other arrangement to ensure access to Market-priced Energy. In the Board's

    opinion, such a condition should not create any practical difficulty because it would

    simply codify what NSPML asserts is the effect of the arrangement in any case. It

    would also confirm what NSPML already states is Nalcor's view of their future

    relationship.

    Yet the response from Nalcor, Emera, and the Provincial Government of Newfoundland

    indicates that this decision was clearly not what they expected. Therein lays the great paradox

    of Muskrat Falls. Why is a potential customer willing to purchase 60% of Muskrat Falls power

    under a long-term contract, and at market rates, such a major issue? This paper will attempt to

    explain why.

    Part II: The Original Plan

    Just prior to the decision gate 2 (DG2), in the summer of 2010, Nalcor made the decision to

    proceed with the Muskrat Falls first option. The messaging from Nalcor has been very

    consistent. Muskrat Falls is the lowest cost alternative to meet the provinces growing electrical

    need. Although only 40% of the energy will initially be used for the island demand, the

    domestic requirement will progressively increase until 100% of the Muskrat Falls output isrequired in 2052. This was effectively demonstrated within the July 11, 2011 presentation

    Nalcor made to the Public Utilities Board as shown within Figure 2.

  • 7/30/2019 UARB Decision - Final

    5/17

    The UARB Decision

    Even though only 40% of the energy will be initially used by the ratepayers of Newfoundland, it

    was communicated that the rate payer was responsible for paying for 100% of the project

    costs. Both the provincial government and Nalcor also communicated that any revenue from

    exports would not be used to lower rates for NL ratepayers.

    A power purchase agreement (PPA) was proposed between Nalcor and its subsidiary

    Newfoundland and Labrador Hydro (NLH) where the latter party would sign up to a take or

    pay contract. NLH would be committing to pay for the progressively growing portion of

    Muskrat Falls energy as shown in green within Figure 2. For the information of the reader, the

    take or pay agreement will state that the block of power is provided to Newfoundland Hydro

    for resell to the island consumer. If the power is not used, it must still be paid for.

    As part of the 2010 deal, and in exchange of the construction of the Maritime Link, Emera

    would receive the Nova Scotia Block consisting of 980 GWh energy delivered annually for 35

    years. Figure 3 provides an overlap of the NS Block (980 GWh per year for 35 years)

    superimposed over the take or pay commitment between Nalcor and Newfoundland andLabrador Hydro. As is evident from this graph even with the base plan, there was a shortfall in

    energy in the period from 2038 to 2041. To the knowledge of the Author, Nalcor has never

    explicitly stated how this shortfall would be met.

  • 7/30/2019 UARB Decision - Final

    6/17

    The UARB Decision

    the cost of Muskrat Falls energy for the Newfoundland ratepayer, Nova Scotia ratepayer, and

    the market rate used for surplus energy. As evident the original plan had Muskrat Falls energy

    initially being sold to NL ratepayers at some 4 times the rates assumed by Emera as being

    representative of a competitive market .

    Figure 4: Muskrat Falls Energy Costs Compared to Market (Ref. 6, 7)

  • 7/30/2019 UARB Decision - Final

    7/17

    The UARB Decision

    Part III: The UARB Condition

    Figure 1, as submitted by Emera to the UARB, proposes a blended rate to the Nova Scotiaratepayer that is premised upon the availability of surplus power from both Nalcor and New

    Brunswick. From the period from 2017 to 2041, there is some 1600 GWhr of energy that Emera

    have assumed that they can purchase from Nalcor at the market rate. This 1600 GWhr

    represents some 35% of Muskrat Falls production, post line losses. As shown within Table 2

    this amount of power is assumed to be available from Nalcor from the period of 2017 to 2041.

    Assuming this power comes from Muskrat Falls prior to 2041, the energy supply balance is

    shown within Figure 6.

    Figure 6: Energy Supply Balance Considering UARB Condition

  • 7/30/2019 UARB Decision - Final

    8/17

    The UARB Decision

    As Figure 5 so effectively communicates there will be a revenue shortfall if Nalcor sell the

    additional surplus power at market rates only. If the Newfoundland ratepayer is still expected

    to pay for the entire project, and export revenue is not used to offset the costs, meeting the

    UARB condition will have an impact on our rates.

    Table 3 provides a summary of the rates when considering the impact of the UARB condition.

    This is summarized from the period of 2017 to 2040 in Figures 7 and 8. If Nalcor agree to sell

    the required 1600 GWhr of energy to Emera, at the Market rates as per the UARB condition,

    there will be an estimated 37% increase in unit rates to Newfoundland rate payers over the life

    of the project. This is if provincial government maintain their policy of not using export revenue

    to offset domestic rates. If all export revenue was used to lower domestic rates, there would

    still be a 10% increase in rates. These numbers are based on the DG2 data provided by Nalcor

    during the PUB process.

  • 7/30/2019 UARB Decision - Final

    9/17

    The UARB Decision

    Figure 8: Average Unit Rate for Electricity Paid By Newfoundland Consumers 2017 to 2041

    This is a very simple demonstration of the potential impact of the UARB decision. There are

    some additional points of consideration:

    1) This assumes that the Holyrood plant would still be closed It is very unlikely that with

  • 7/30/2019 UARB Decision - Final

    10/17

    The UARB Decision

    Part IV: Other Sources of Surplus Energy

    Within their application to the UARB Emera clearly promoting a blended rate from 2017 to2040 which is much lower than the rate for the Nova Scotia Block (980 GWhr) only. This is

    verified on Page 23 of the Emera application to the UARB:

    The original application had this surplus power from both Nalcor or New Brunswick. However

    the majority of the 2 TWhr referenced above was intended to come from Nalcor, over the 35

    years of the agreement.

    If Nalcor maintain that Muskrat Falls will be developed primarily for the benefit of

    Newfoundlanders, and they respect the original take or pay concept provided within Figure 2, it

    is unclear where this additional Nalcor generation will come from? In their own submission to

    the Newfoundland Public Utilities Board, Nalcor has effectively demonstrated that there is no

    source of new generation in Newfoundland which can provide that amount of Energy, for

    anything close to the surplus energy rate quoted in Figure 4 4 of the Emera application

  • 7/30/2019 UARB Decision - Final

    11/17

    The UARB Decision

    Yet Upper Churchill power seems to be possible solution to providing market rate power to

    Emera. It must be remembered that Hydro Quebec are obligated to provide open access to

    their power for Canadian markets prior to export to the US. Consider the following excerpt

    from the 1994 decision from the National Energy Board, in granting an export license to Hydro

    Quebec [Ref. 10]:

    In the event that Emera does purchase Upper Churchill Power from Hydro Quebec, would they

    then have access to transmission rights as a partner within the Labrador Island Link? In thecase of dispute resolution, would their 35% ownership in the LIL give them 35% of the

    transmission capacity?

  • 7/30/2019 UARB Decision - Final

    12/17

    The UARB Decision

    Figure 8: Excerpt from Figure 1.2 of Emera Application to UARB noting 1200 MW capacity of LIL

    Emera and Nalcor should clarify if the LIL has a 1200 MW rating. Was there an incremental cost

    to go from the original 900 MW to the 1200 MW rating? If this additional cost exists, is it being

    recovered under the Labrador Island Link agreement? Are Newfoundland ratepayers now

    paying a premium for additional capacity to export extra power to Nova Scotia?

    If power from the Hydro Quebec system is part of the solution to meeting UARB approval then

  • 7/30/2019 UARB Decision - Final

    13/17

    The UARB Decision

    Part V: Conclusion

    It has been a month since the UARB decision was tabled, and to date there has been limitedpublic discussion by either Emera or Nalcor. However from Emeras recent quarterly statement

    to the market it is very likely that re-negotiated agreement between the parties will again have

    to be resent to the UARB for approval [Ref. 12]. This will extend the period until Nalcor can be

    certain that they have a committed partner on the project. It is a precarious position at best.

    However, the question must now be asked. If the revised deal between Nalcor and Emera has

    the potential to increase our rates into the future, should the Public Utilities Board also beprovided the same opportunity for review to ensure it is in the same long term interest of the

    Newfoundland and Labrador rate payer? As the expedited PUB review could be completed in

    parallel with the UARB review it is certainly difficult to understand why this would not be

    demanded by the tax payers of Newfoundland and Labrador.

    As a minimum Nalcor and the Government of Newfoundland and Labrador should answer the

    following simple questions regarding the any revision to the deal with Emera:1) Is there a potential that it will increase NL rates into the future from what was provided

    during DG3?

    2) In the absence of any additional generation (ie: Gull Island) can Holyrood close ifadditional energy is committed to Nova Scotia?

    3) If energy from Alternate Sources is wheeled over the NL grid will Emera have to pay atransmission tariff similar to what Nalcor will pay Emera to wheel power into the US?

    4) If Emera are planning to access Upper Churchill power at market rates, why did Nalcornot consider this power purchase when it confirmed Musrkat Falls as the lowest cost

    ti ?

  • 7/30/2019 UARB Decision - Final

    14/17

    The UARB Decision

    References

    1 http://www.pub.nl.ca/applications/MuskratFalls2011/files/comments/11-JM-2012-02-29-Rev1.pdf2 http://nsuarb.novascotia.ca/sites/default/files/documents/muskratfalls/m-2.pdf3 http://nsuarb.novascotia.ca/sites/default/files/decisions/m05419_decision_maritime_link_project.pdf4 http://www.pub.nl.ca/applications/MuskratFalls2011/files/presentation/Nalcor-ProjectOverview-July18-

    11.pdf

    5 http://www.pub.nl.ca/applications/MuskratFalls2011/files/rfi/CA-KPL-Nalcor-177.pdf6 http://www.pub.nf.ca/applications/muskratfalls2011/files/rfi/CA-KPL-Nalcor-27-Rev1.pdf7 http://nsuarb.novascotia.ca/sites/default/files/documents/muskratfalls/m-11_revised.pdf8 http://www.nl.dailybusinessbuzz.ca/Provincial-News/2013-01-10/article-3153832/NL%3A-Nalcor-to-

    provide-energy-for-Alderon%26rsquo%3Bs-Kami-project/1

    9 http://www.powerinourhands.ca/pdf/UpperChurchill.pdf10 https://www.neb-one.gc.ca/ll-eng/livelink.exe/fetch/2000/90466/94151/94159/94196/94260/1994-12-

    01_Reasons_for_Decision.pdf?nodeid=94264&vernum=0

    11 http://www.powerinourhands.ca/pdf/Agreement.pdf12 http://www.emera.com/en/home/mediacentre/recentnews/2013/newsreleasedetails.aspx?SourceParams

    =reqid-1846769

    13 http://thechronicleherald.ca/novascotia/1144536-dunderdale-link-never-hinged-on-review-board-decision

    http://www.pub.nl.ca/applications/MuskratFalls2011/files/comments/11-JM-2012-02-29-Rev1.pdfhttp://www.pub.nl.ca/applications/MuskratFalls2011/files/comments/11-JM-2012-02-29-Rev1.pdfhttp://nsuarb.novascotia.ca/sites/default/files/documents/muskratfalls/m-2.pdfhttp://nsuarb.novascotia.ca/sites/default/files/documents/muskratfalls/m-2.pdfhttp://nsuarb.novascotia.ca/sites/default/files/decisions/m05419_decision_maritime_link_project.pdfhttp://nsuarb.novascotia.ca/sites/default/files/decisions/m05419_decision_maritime_link_project.pdfhttp://www.pub.nl.ca/applications/MuskratFalls2011/files/presentation/Nalcor-ProjectOverview-July18-11.pdfhttp://www.pub.nl.ca/applications/MuskratFalls2011/files/presentation/Nalcor-ProjectOverview-July18-11.pdfhttp://www.pub.nl.ca/applications/MuskratFalls2011/files/presentation/Nalcor-ProjectOverview-July18-11.pdfhttp://www.pub.nl.ca/applications/MuskratFalls2011/files/presentation/Nalcor-ProjectOverview-July18-11.pdfhttp://www.pub.nl.ca/applications/MuskratFalls2011/files/presentation/Nalcor-ProjectOverview-July18-11.pdfhttp://www.pub.nl.ca/applications/MuskratFalls2011/files/rfi/CA-KPL-Nalcor-177.pdfhttp://www.pub.nl.ca/applications/MuskratFalls2011/files/rfi/CA-KPL-Nalcor-177.pdfhttp://www.pub.nf.ca/applications/muskratfalls2011/files/rfi/CA-KPL-Nalcor-27-Rev1.pdfhttp://www.pub.nf.ca/applications/muskratfalls2011/files/rfi/CA-KPL-Nalcor-27-Rev1.pdfhttp://nsuarb.novascotia.ca/sites/default/files/documents/muskratfalls/m-11_revised.pdfhttp://nsuarb.novascotia.ca/sites/default/files/documents/muskratfalls/m-11_revised.pdfhttp://www.nl.dailybusinessbuzz.ca/Provincial-News/2013-01-10/article-3153832/NL%3A-Nalcor-to-provide-energy-for-Alderon%26rsquo%3Bs-Kami-project/1http://www.nl.dailybusinessbuzz.ca/Provincial-News/2013-01-10/article-3153832/NL%3A-Nalcor-to-provide-energy-for-Alderon%26rsquo%3Bs-Kami-project/1http://www.nl.dailybusinessbuzz.ca/Provincial-News/2013-01-10/article-3153832/NL%3A-Nalcor-to-provide-energy-for-Alderon%26rsquo%3Bs-Kami-project/1http://www.nl.dailybusinessbuzz.ca/Provincial-News/2013-01-10/article-3153832/NL%3A-Nalcor-to-provide-energy-for-Alderon%26rsquo%3Bs-Kami-project/1http://www.nl.dailybusinessbuzz.ca/Provincial-News/2013-01-10/article-3153832/NL%3A-Nalcor-to-provide-energy-for-Alderon%26rsquo%3Bs-Kami-project/1https://www.neb-one.gc.ca/ll-eng/livelink.exe/fetch/2000/90466/94151/94159/94196/94260/1994-12-01_Reasons_for_Decision.pdf?nodeid=94264&vernum=0https://www.neb-one.gc.ca/ll-eng/livelink.exe/fetch/2000/90466/94151/94159/94196/94260/1994-12-01_Reasons_for_Decision.pdf?nodeid=94264&vernum=0https://www.neb-one.gc.ca/ll-eng/livelink.exe/fetch/2000/90466/94151/94159/94196/94260/1994-12-01_Reasons_for_Decision.pdf?nodeid=94264&vernum=0https://www.neb-one.gc.ca/ll-eng/livelink.exe/fetch/2000/90466/94151/94159/94196/94260/1994-12-01_Reasons_for_Decision.pdf?nodeid=94264&vernum=0https://www.neb-one.gc.ca/ll-eng/livelink.exe/fetch/2000/90466/94151/94159/94196/94260/1994-12-01_Reasons_for_Decision.pdf?nodeid=94264&vernum=0http://www.powerinourhands.ca/pdf/Agreement.pdfhttp://www.powerinourhands.ca/pdf/Agreement.pdfhttp://www.emera.com/en/home/mediacentre/recentnews/2013/newsreleasedetails.aspx?SourceParams=reqid-1846769http://www.emera.com/en/home/mediacentre/recentnews/2013/newsreleasedetails.aspx?SourceParams=reqid-1846769http://www.emera.com/en/home/mediacentre/recentnews/2013/newsreleasedetails.aspx?SourceParams=reqid-1846769http://www.emera.com/en/home/mediacentre/recentnews/2013/newsreleasedetails.aspx?SourceParams=reqid-1846769http://www.emera.com/en/home/mediacentre/recentnews/2013/newsreleasedetails.aspx?SourceParams=reqid-1846769http://thechronicleherald.ca/novascotia/1144536-dunderdale-link-never-hinged-on-review-board-decisionhttp://thechronicleherald.ca/novascotia/1144536-dunderdale-link-never-hinged-on-review-board-decisionhttp://thechronicleherald.ca/novascotia/1144536-dunderdale-link-never-hinged-on-review-board-decisionhttp://www.emera.com/en/home/mediacentre/recentnews/2013/newsreleasedetails.aspx?SourceParams=reqid-1846769http://www.emera.com/en/home/mediacentre/recentnews/2013/newsreleasedetails.aspx?SourceParams=reqid-1846769http://www.powerinourhands.ca/pdf/Agreement.pdfhttps://www.neb-one.gc.ca/ll-eng/livelink.exe/fetch/2000/90466/94151/94159/94196/94260/1994-12-01_Reasons_for_Decision.pdf?nodeid=94264&vernum=0https://www.neb-one.gc.ca/ll-eng/livelink.exe/fetch/2000/90466/94151/94159/94196/94260/1994-12-01_Reasons_for_Decision.pdf?nodeid=94264&vernum=0http://www.nl.dailybusinessbuzz.ca/Provincial-News/2013-01-10/article-3153832/NL%3A-Nalcor-to-provide-energy-for-Alderon%26rsquo%3Bs-Kami-project/1http://www.nl.dailybusinessbuzz.ca/Provincial-News/2013-01-10/article-3153832/NL%3A-Nalcor-to-provide-energy-for-Alderon%26rsquo%3Bs-Kami-project/1http://nsuarb.novascotia.ca/sites/default/files/documents/muskratfalls/m-11_revised.pdfhttp://www.pub.nf.ca/applications/muskratfalls2011/files/rfi/CA-KPL-Nalcor-27-Rev1.pdfhttp://www.pub.nl.ca/applications/MuskratFalls2011/files/rfi/CA-KPL-Nalcor-177.pdfhttp://www.pub.nl.ca/applications/MuskratFalls2011/files/presentation/Nalcor-ProjectOverview-July18-11.pdfhttp://www.pub.nl.ca/applications/MuskratFalls2011/files/presentation/Nalcor-ProjectOverview-July18-11.pdfhttp://nsuarb.novascotia.ca/sites/default/files/decisions/m05419_decision_maritime_link_project.pdfhttp://nsuarb.novascotia.ca/sites/default/files/documents/muskratfalls/m-2.pdfhttp://www.pub.nl.ca/applications/MuskratFalls2011/files/comments/11-JM-2012-02-29-Rev1.pdf
  • 7/30/2019 UARB Decision - Final

    15/17

    The UARB Decision

    Table 1: Summary of Take or Pay Contract between Nalcor and Newfoundland Hydro Showing Increased Output

    from Muskrat Falls. (Source: RFI-KPL-27-Rev. 1)

  • 7/30/2019 UARB Decision - Final

    16/17

    The UARB Decision

    A Muskrat Falls Discussion Paper Volume II Page 1

    Exerpt from UARB IR-37 showing how the blended rate was calculated.

  • 7/30/2019 UARB Decision - Final

    17/17

    The UARB Decision

    A Muskrat Falls Discussion Paper Volume II Page 2