European Organization for Nuclear Research - Organisation européenne pour la recherche nucléaire
Typical corrective intervention
Failure & call of the CCC
•About 30’
access request
•Depending of the LHC status
•Between 1h and few days (2 days)
Diagnostic (pump failure)
•About 1h
RP analysis & transport requested
•1h to be at cern
Rp results & new pump
on site
•between 2&3 hours
Draining & pump
replacement
•Between 2&3 hours
restart of the station
21h30•The failure happen and the CCC call the piquet which make the first diagnostic in remote
22h00•The piquet ask an access for check the system
23h00•After check of the system
00h00•The RP piquet has 1 hours for to be at cern
3h00•The RP analysis need ~3 hours for give the results, during this time we can prepare the material
+3h•Average we need 3 hours for drain a system
6h00
European Organization for Nuclear Research - Organisation européenne pour la recherche nucléaire
• We need about 8h30 of intervention for replace a pump on each experiment, depending of the experimental cavern access for Alice, CMS & Atlas.
• Cavern access request: done by the experiment• RP analysis request: ask by the CV/DC piquet• Transport and support request: done by CV/DC piquet• Sample bottles: RP inspector excepted for the sampling of TOTEM, Evaporative & SPD which need a
special bottle
• Important phone number during non working hours– CV/DC piquet & CCC: 72201– RP inspector: 74848
• Important phone number during working hours– CMS: Lefils Daniel 162915– ATLAS: Crespo-Lopez Olivier 161042– LHCB: Corbaz Florian 165426– Alice: Roussee Sebastien 163650– RP inspector 75252– CCC 72201
Typical corrective intervention