54
CDH Vertical Shaft Study Report 209050-00014-000-GE-REP-0001 Rev 0 4-Feb-2014 Av. La Encalada 1257, Piso 8, Surco, Lima, Peru Tel: +51 1 437 7473 Fax: +51 1 437 7216 www.worleyparsons.com

TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

Embed Size (px)

DESCRIPTION

shaft

Citation preview

Page 1: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

CDH

Vertical Shaft Study Report

209050-00014-000-GE-REP-0001

Rev 0

4-Feb-2014

Av. La Encalada 1257, Piso 8, Surco, Lima, Peru Tel: +51 1 437 7473 Fax: +51 1 437 7216 www.worleyparsons.com

Page 2: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0
Page 3: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 3 Rev 0 (04-Feb-14)

TABLE OF CONTENT

1 INTRODUCTION ..................................................................................................... 6

2 EXECUTIVE SUMMARY ......................................................................................... 7

3 USER REQUIREMENTS ....................................................................................... 10

3.1 Shaft configuration .................................................................................................10

3.2 Surface infrastructure.............................................................................................11

3.3 Shaft duty ..............................................................................................................11

4 DESIGN CRITERIA ............................................................................................... 12

5 TECHNICAL REPORT ........................................................................................... 13

5.1 Surface layout ........................................................................................................13

5.2 Winding plant .........................................................................................................15

5.3 Ropes and attachments .........................................................................................16

5.4 Conveyances .........................................................................................................17

5.5 Shaft configuration .................................................................................................17

5.6 Loading arrangements ...........................................................................................18

5.7 Shaft spillage arrangements ..................................................................................19

6 SHAFT SERVICES ................................................................................................ 21

6.1 Power distribution ..................................................................................................21

6.2 Service water supply ..............................................................................................23

6.3 Compressed air service system .............................................................................24

6.4 Dewatering system ................................................................................................25

7 PROJECT COSTS ................................................................................................ 27

7.1 Capital requirements ..............................................................................................27

7.2 Operating Costs (Opex) .........................................................................................29

8 CONCLUSION ....................................................................................................... 30

ANNEX 1: CAPEX ............................................................................................................... 31

ANNEX 2: OPEX ................................................................................................................. 32

ANNEX 3: WINDER DUTIES ............................................................................................... 33

Page 4: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 4 Rev 0 (04-Feb-14)

ANNEX 4: LOAD PROFILES ............................................................................................... 34

ANNEX 5: SCHEDULE ........................................................................................................ 35

Page 5: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 5 Rev 0 (04-Feb-14)

List of Figures

Figure 1: Locality Plan ........................................................................................................... 6

Figure 2: Distribution Of Capex ............................................................................................. 8

Figure 3: Opex Distribution .................................................................................................... 9

Figure 4 : Shaft Crossection ................................................................................................ 10

Figure 5: General Surface Layout ........................................................................................ 14

Figure 6 : Shaft Configuration .............................................................................................. 18

Figure 7 : Proposed Loading Arrangements ........................................................................ 19

Figure 8 : Shaft Spillage Cleaning Arrangements ................................................................ 20

Figure 9 : Service Water Reticulation .................................................................................. 24

Figure 10 : Shaft Bottom Dewatering ................................................................................... 26

List of Tables

Table 1: Capital Requirements By Discipline ......................................................................... 8

Table 2: Shaft Operational Costs ........................................................................................... 9

Table 3: Study Design Criteria ............................................................................................. 12

Table 4: Rock Winder Duty .................................................................................................. 16

Table 5: Man/Material Winder Duty ..................................................................................... 16

Table 6: Total Electrical Load .............................................................................................. 21

Table 7 : Capital Requirement By Wbs ................................................................................ 27

Table 8 : Capital Cash Flow................................................................................................. 28

Table 9 : Detailed OPEX ..................................................................................................... 29

Page 6: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 6 Rev 0 (04-Feb-14)

1 INTRODUCTION

Basados Canteras Del Hallazgo (CDH) are in the process of doing a trade-off study on ore

reserve access at the Chucapaca Shaft Project, situated in the Andes mountainous range in

the Moquegua district of Peru.

FIGURE 1: LOCALITY PLAN

The trade-off study will be based on the most feasible access configuration. It is the intention

to do a comparison between decline ramps and a vertical shaft complex, for the transporting

of men,material and rock to the underground workings. The study considers both capital

(CAPEX) and operating (OPEX) cost.

WorleyParsons have been given the contract to evaluate the shaft complex requirements as

part of the trade-off study.

This report outlines the optimal vertical shaft configuration and services selected to support

the CAPEX and OPEX submitted.

Page 7: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 7 Rev 0 (04-Feb-14)

2 EXECUTIVE SUMMARY

WorleyParsons has concluded the study based on sound engineering practices in terms of

the shaft infrastructure and in accordance with user requirements given by CDH. The

request was that the study be done to an accuracy level of 30% in terms of the estimate and

50% in terms of labor

The scope of work given by CDH is as follows:

• Surface infrastructure;

- Winding plant and associated services

- Lamproom and shift control centre

- Ore handling facilities

• Vertical shaft infrastructure for men, material and rock hoisting;

• Loading arrangements;

• Shaft pumping and spillage arrangements;

• CAPEX and OPEX for the shaft infrastructure only.

An optimal shaft dimension was found to be 5 m diameter by 455m deep. This will facilitate

the hoisting of men, material and rock.

Ore handling facilities include the conveying of ore to a stockpile and waste conveying to a

bin from where it will be transported by truck to the process plant and waste dump facilities.

The resultant capital requirements are tabled in Table 1 and Figure 2 represents the

distribution of the CAPEX :

Page 8: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 8 Rev 0 (04-Feb-14)

TABLE 1: CAPITAL REQUIREMENTS BY DISCIPLINE

Labour Labour Material Const Eqpt Process Eqpt AmountManhour Total Cost Total Cost Total Cost Total Cost Total Cost

(m-h) (US$) (US$) (US$) (US$) (US$)1500 General Surface - Buildings and Infrastructure 57 966 550 790 214 752 1 713 445 - 2 478 987 1600 Shafts - Surface System 172 113 1 826 384 2 780 694 1 587 420 8 734 710 14 929 208 1700 Shafts - Mining & Engineering 262 168 2 878 667 1 567 958 6 600 203 2 282 702 13 329 530 9000 Indirect Cost - 2 062 917 1 905 221 3 886 169 3 139 962 10 994 270

Contingency (25%) 123 062 1 829 689 1 617 156 3 446 809 3 539 344 10 432 999 TOTAL COST 615 310 9 148 447 8 085 782 17 234 047 17 696 718 52 164 993

ÍTEM DESCRIPCIÓN

FIGURE 2: DISTRIBUTION OF CAPEX

The operating costs are tabled in TABLE 2 and FIGURE 3 represents the distribution of the

operating costs

Page 9: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 9 Rev 0 (04-Feb-14)

TABLE 2: SHAFT OPERATIONAL COSTS

Month (US$) Annual (US$) $/t

01 $71 474 $857 693 0.74 02 $20 000 $240 000 0.21 03 $87 019 $1 044 228 0.90

TOTAL COST $178 493 $2 141 921 1.85

LABOR

POWERMAINTENANCE COST - CONSUMABLES

Item Description

FIGURE 3: OPEX DISTRIBUTION

The majority of the capital costs were derived from quotations as submitted by the suppliers

and others were extracted from the WorleyParsons data base.

The OPEX was calculated on the following:

• Manpower requirements for shaft operations, including the Lamproom;

• Typical 24 hr load profiles including diversity factors for winding operations;

• Estimated consumables required for maintenance.

Page 10: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 10 Rev 0 (04-Feb-14)

3 USER REQUIREMENTS

3.1 Shaft configuration

Figure 4 is a representation of the shaft depth and level access elevations to the reserves,

as submitted by CDH.

FIGURE 4 : SHAFT CROSSECTION

Page 11: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 11 Rev 0 (04-Feb-14)

Included in the layout is an addit, on level 4600, which CMH will develop for the following:

• Exploration purposes;

• Ventilation requirements;

• Trackless mining equipment;

• Drainage system for mine return water.

3.2 Surface infrastructure

Provision is to be made for rock handling facilities and a Lamproom.

In terms of rock handling, ore is to be conveyed via a conveyor system to a stockpile facility

to allow for the loading of trucks for transportation to the process plant. Waste is to be

conveyed to a storage bin/silo, designed to facilitate the transport of the waste to the waste

dump facility by means of trucks.

Material cars will be transported via the shaft and therefore, a marshal yard is required for

this purpose. Cognizance is to be taken of this to determine the bank terrace area required.

3.3 Shaft duty

The shaft is required for men, material and rock hoisting. The station landings are to be

excavated such that long material can be slung to the working levels. The shaft duty is

defined as follows:

• 150 persons per shift;

• 3000 tons per day reef and 800 tons per day waste;

• Shaft services to include service water piping, compressed air piping, mine return

water piping and shaft cabling.

Page 12: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 12 Rev 0 (04-Feb-14)

4 DESIGN CRITERIA

CDH has included the following design criteria:

TABLE 3: STUDY DESIGN CRITERIA

DESCRIPTION CRITERIA

Ore handling facilities 3000 t/day (dry)

Waste handling facilities 800 t/day (dry)

Depth of shaft 400 m

Personnel hoisting 150 persons (both ways)

Mine return water below level 4600 20 l/s

Plant availability 96 %

S.G. of broken ore 2.2

Production shifts 2 per day

Study accuracy for labour +50 %

Study accuracy for equipment +30 %

DESIGN CRITERIA BASED ON INDUSTRY NORMS

Compressed air consumption 0.13 kg/s per 1000 tons broken per day

Service water requirements 0.75 m³ per ton broken

Material car requirements 90 t per material car

Brocken rock lump size 300 mm

Page 13: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 13 Rev 0 (04-Feb-14)

5 TECHNICAL REPORT

5.1 Surface layout

In Order to establish the footprint of the surface area to be terraced, the area required for the

sinking contractor was established to house the following:

• A contractor yard for site offices, consumable and equipment storage and workshop

facilities;

• A laydown area for stacking of jigged bunton sets and guides;

• Ring fencing of the surface area for construction and operational security.

Figure 5 represents the area required and includes the proposed layout for the winding

plants, headgear and Lamproom:

Page 14: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 14 Rev 0 (04-Feb-14)

FIGURE 5: GENERAL SURFACE LAYOUT

The layout is conceptual and can be optimised with the project going forward

Page 15: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 15 Rev 0 (04-Feb-14)

5.2 Winding plant

The preferred winder configuration selected was standard double drum winders. For the

purpose of standardization, motor drives are proposed to be duplicated. Squirrel cage AC

motor drives are recommended and these are standard motors readily available.

Provision is made for a spare motor as the turnaround time for repairs is excessive.

The winders are equipped with the following:

• Controlled braking;

• Upper and lower limit overwind protection;

• Over-speed protection;

• Slack/tight rope monitoring;

• Rope coiling protection;

• Man/material winding speed – 7 m/s (regulated);

• Rock winder speed – 9 m/s (regulated);

• Factor of Safety of winder ropes – 5 (regulated);

• Minimum drum over rope diameter – 80 (regulated);

• Locked bell system (Beltronic or equivalent);

• Ecam communication systems.

The rock winder duty is tabulated in TABLE 4.

Page 16: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 16 Rev 0 (04-Feb-14)

TABLE 4: ROCK WINDER DUTY

ROCK WINDER DUTY Description Unit Value Skip capacity tons 7

Winding speed m/s 7 Number of skips per hour no. 32

Production per day tons 4362 Drum and sheave diameter m 3.2

Rope diameter mm 35 RMS value of motor kW 645

Selected motor rating kW 1000

The man/material winder duty is tabulated in TABLE 5.

TABLE 5: MAN/MATERIAL WINDER DUTY

MAN/MATERIAL WINDER DUTY Description Unit Value

Cage capacity men 56 Winding speed m/s 7

Number of men per hour men. 710 Cage configuration decks 2

Drum and sheave diameter m 3.2 Rope diameter mm 30

RMS value of motor kW 464 Selected motor rating kW 600

5.3 Ropes and attachments

Standard galvanized triangular strand ropes with fiber core were selected. One set of spare

ropes per winder is provided for.

Cappel attachments, commonly used in Peru, were selected for ease of attachment to the

conveyances (no splicing). Humble hooks with resin sockets may be the client’s preference

and can be provided for. A spare set of attachments are provided for each winder.

Page 17: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 17 Rev 0 (04-Feb-14)

5.4 Conveyances

• Rock hoisting skips

Standard bottom discharge skips with a camel back opening cam was selected and includes

a trigger arm locking device to prevent the inadvertent opening up of the skips in transit.

Spare skips are provided for.

Underslung inspection/repair baskets are provided for each rock compartment;

• Man/material hoisting

A double deck cage configuration was selected with roller shutter doors. Slinging lugs are

included for the slinging of long material and the attachment of the inspection baskets.

A counter weight conveyance with a capacity of 70% of the attached load for men/material

hoisting has been accounted for.

Underslung inspection/repair baskets are provided for the man/material compartment and for

the counterweight compartment.

5.5 Shaft configuration

The shaft diameter was selected on the basis that the maximum lump size for rock will be

300mm. The minimum footprint for the skips should therefore be no less than 1m by 1m.

Smaller dimensions will result in rock hanging up during skip discharge. Considering the fact

that material cars are to be transported in the cage, a 5 m diameter shaft was selected with

a cage footprint of 2.5 m long by 2.1 m wide. It should be noted that material, chutes and

boxes need to be designed, taking cognizance of the limited footprint.

All service piping is placed in areas for ease of access for installation and maintenance

purposes. Shaft cabling is housed in front of the 2 deck conveyance to facilitate the

installation of the shaft cabling via the 2 decks of the man/material conveyance. This position

is convenient for installation via the 2 deck man cage and for future maintenance purposes.

Figure 2 represents the shaft configuration selected.

Page 18: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 18 Rev 0 (04-Feb-14)

FIGURE 6 : SHAFT CONFIGURATION

5.6 Loading arrangements

The reef production is 3000 t/d or 1500 t per production shift. For the purpose of this study, it

is assumed that the storage capacity for reef, to the loading station, should be approximately

equal to that produced during 1 production shift. Considering the low tonnage of waste, a 2.4

m diameter ore pass of 350 ton capacity will suffice. A 5m lined silo (use shaft formwork for

lining) with a capacity of 1900 t lined silo is recommended for reef storage underground.

Standard belt and flask loading arrangements are proposed with flask loading cells and spill

free flask discharge arrangements. Interlocking between the winder, flask discharge and

loading belt is provided for. Changeover from ore to waste, and vice versa, will be

interlocked to ensure the system is set up to load and discharge to the appropriate surface

stockpile/silo.

Page 19: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 19 Rev 0 (04-Feb-14)

Figure 3 represents the loading arrangements accounted for:

FIGURE 7 : PROPOSED LOADING ARRANGEMENTS

5.7 Shaft spillage arrangements

The relatively low production tons and the introduction of spill free loading arrangements, will

result in minor spillage handling requirements.

A decline equipped with a spillage winch and a 2 t tipping hopper is proposed. The hopper

will discharge directly onto the loading belt via an ore pass.

Cage loading of spillage cars via an established platform below the spillage box could be

investigated as part of optimization going forward with the study.

Figure 8 represents a schematic of a typical loading arrangement proposed for this project:

Page 20: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 20 Rev 0 (04-Feb-14)

FIGURE 8 : SHAFT SPILLAGE CLEANING ARRANGEMENTS

Page 21: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 21 Rev 0 (04-Feb-14)

6 SHAFT SERVICES

The services for the Chucapaca Shaft Project comprises of the following:

• Electrical reticulation;

• Service Water;

• Compressed air services;

• Dewatering facilities;

• Services for the winder house (Water and compressed air);

• Services in the Headgear (Water and compressed air).

6.1 Power distribution

• Electrical Load

The total electric load is summarized in the following table:

TABLE 6: TOTAL ELECTRICAL LOAD

ITEM DESCRIPCTION ACTIVE POWER

KW

REACTIVE POWER

1 SURFACE

1.1 Winder Service 598 196

1.2 Winder Production 1197 393

1.3 Motor Control Center Winder Production 129 69

1.4 Motor Control Center Winder Service 136 71

1.5 Conveyor N°1 27 13

1.6 Conveyor N°2 72 34.8

1.7 Conveyor N°3 36 17

1.8 Lamp Camp 162 78

1.9 Chutes 7.5 4.8

Page 22: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 22 Rev 0 (04-Feb-14)

ITEM DESCRIPCTION ACTIVE POWER

KW

REACTIVE POWER

1.10 Auxiliary Services 68.4 33.1 1 UNDERGROUND

2.1 4750 Level 34.2 16.6

2.2 4700 Level 34.2 16.6

2.3 4650 Level 70.3 37

2.4 4600 Level 34.2 16.6

2.5 Top Silos 191.3 101.7

2.6 Loading Station 244.7 124.7

2.7 Shaft Bottom 59.8 31.6

TOTAL 3101.6 1254.5

• Principle 13.8 kV and 4.16 kV Substation

The Principal 13.8 kV and 4.16 kV Substation shall be located on principal Station. This

substation shall comprise of a 13.8 kV metal-clad switchgear GIS and a 4.16 kV metal-clad

switchgear GIS – referred to as the principal 13.8 kV switchboard and principal 4.16 kV

switchboard respectively from this point forward. The principal 13.8 kV switchboard shall

supply the rock and man winder convertor transformers (To be specified by the winder

Vendor), 2 x 700 kVA 13.8/4.16 kV distribution transformers and will house one spare feeder

panel for future expansion.

The principal 4.16 kV switchboard shall distribute power to all other 4.16 kV, 480 V and 230

V electrical equipment and shall comprise of two separate bus sections separated by a bus

section/riser panel. Each bus section shall be supplied via a 800 kVA distribution transformer

with each bus section designed to have an equally distributed load.

• Subsidiary 4.16 kV Switchboards

A total of 3 subsidiary 4.16 kV switchboards connected in a ring configuration and supplied

from the principal 4.16 kV switchboard shall be utilized to distribute power to station

distribution panels, MCCs and lighting panels.

Page 23: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 23 Rev 0 (04-Feb-14)

• 480 V Motor Control Centres (MCCs)

480 V MCC metal-enclosed assemblies shall be utilized to drive all 480 V motors. These

include the winder auxiliaries at the Principle Station and Loading Station will supply

conveyor, vibrating, chutes.

• 480 V Distribution Panels (DPs)

480 V distribution panels shall be used to distribute power at 480 V to subsidiary 480 V

distribution panels, lighting and small power transformers and welding sockets.

6.2 Service water supply

For the calculation of service water, the following ratio of water consumption per ton mined is considered:

• 0.75 m³ of water / Ton mined;

• The daily production is 3,800 Ton/day;

• The daily service water consumption will then be 2 850 m³/day.

It is assumed that 70% of water is consumed during the drilling period that is approximately 5.5 hours in duration, if there are two shifts per day, it will be 11 hours of drilling per day, thus, the peak water flow will be 182 m³/hr or 51 l/s.

The pipe nominal size required for this flow is 150 mm diameter. A Schedule 40 pipe is required for the 400 m head

Each working level will have a pressure reducing valve station (PRVS) to reduce pressure to a maximum pressure 10 bar feeding the workings.

See FIGURE 8 for more details:

Page 24: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 24 Rev 0 (04-Feb-14)

FIGURE 9 : SERVICE WATER RETICULATION

6.3 Compressed air service system

For calculating the Compressed air requirements, the following ratio of compressed air

consumption per tons mined is considered:

• 0.13 kg/s air / 1000 ton broken;

• The daily production is then 3,800 ton/day.

Thus compressed air consumption will be 0.494 kg/s, at normal conditions (density of 1

kg/m³), the Air flow will be 0.494 m³/s (29.64 m³/min).

The altitude of the mine is approximately 5000 AMSL, the atmospheric pressure being 55

kPa (a).

Assuming a site temperature of 10°C flow of free air is calculated to be:

Page 25: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 25 Rev 0 (04-Feb-14)

Where:

• qFAD: Flow rate to the operation site conditions;

• qN: Flow Rate to the Normal Conditions;

• TFAD: Site Temperature in K, for this case is 10°C (283K);

• TN: Temperature to Normal Conditions in K, 20°C (293K);

• PFAD: Site Atmospheric Pressure in bar is 0.55 bar;

• PN : Pressure at Normal Conditions in bar is 1 bar.

Thus the flow at altitude (qFAD) is 52.1 m³/min.

The pipe nominal size required for this flow is 150 mm diameter.

The Air pressure required in the operations is 4.5 bar minimum, the pressure drop for this

pipe size and flow is approximately 0.016 bar per 100 meters of pipe.

A 150 diameter Schedule 20 A53 Gr.B steel pipe is selected.

6.4 Dewatering system

The dewatering flow required is 20 l/s and the discharge level for the water is 4,600. The

dewatering system will be located at the shaft bottom (level 4,442). The proposed system for

dewatering consists of the following:

• The mine water collects in a sump located at the shaft bottom. This sump has two

vertical spindle pumps (one stand by) installed. These pumps are 5HP, 20 l/s. These

sump pumps sends the water to a containment pond of 72m3 (retention of 1 hour) also

located at the shaft bottom. . This retention pond is about 3x4x6m. The pond feeds

the main pumping system. The pipe length from the sump to the pond has been

estimated in 25m. The pipe will be a 150 mm diameter steel pipe (A53 Gr.B), Schedule

40, Flanged Class 150;

Page 26: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 26 Rev 0 (04-Feb-14)

• The main pumping system consist of two positive displacement pumps of 22 kW @ 20

l/s delivery each (one on standby). This pump sends the water to the discharge point

located on level 4,600 from where it will be gravitate out the mine. For the required

flow, the pipe will be 100 mm diameter schedule 40 and the total length of the pipe will

be 225 m;

See FIGURE 3 for schematic of the proposed dewatering system.

FIGURE 10 : SHAFT BOTTOM DEWATERING

Page 27: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 27 Rev 0 (04-Feb-14)

7 PROJECT COSTS

7.1 Capital requirements

TABLE 7 lists the capital requirements by Work Breakdown Structure in the format

requested by CDH.

The costs include a contingency of 25%, which is based on recent quotations and costs

extracted from the WorleyParsons data base on recent projects

TABLE 7 : CAPITAL REQUIREMENT BY WBS

10001500 General Surface - Buildings and Infrastructure 57 966 550 790 214 752 1 713 445 - 2 478 987 1510 General & Site Development 57 466 545 927 64 752 1 670 020 - 2 280 699 1520 Laydown Area - - - - - - 1530 Roads & Drainage 350 3 325 - 14 963 - 18 288 1540 Parking, Bus & Taxi Rank - - - - - - 1550 Environmental Stockpile - - - - - - 1560 Waste Dump - - - - - - 1570 HT Substation 150 1 538 150 000 28 463 - 180 000

1600 Shafts - Surface System 172 113 1 826 384 2 780 694 1 587 420 8 734 710 14 929 208 1610 General & Site Development 7 405 80 555 216 021 54 016 - 350 592 1620 Shaft Bank - - - - - - 1630 Winding Plant 145 431 1 553 084 2 155 314 1 188 015 7 121 076 12 017 489 1640 Reef and Waste Storage & Conveying 4 274 47 019 - 70 763 588 910 706 692 1660 Electrical Distribution 1 337 13 706 217 600 29 814 - 261 120 1670 Substations 9 724 93 613 97 800 221 627 979 200 1 392 240 1680 Lamp & Crush Ontel 3 942 38 407 93 959 23 185 45 524 201 075

1700 Shafts - Mining & Engineering 262 168 2 878 667 1 567 958 6 600 203 2 282 702 13 329 530 1710 General - - - 383 000 - 383 000 1720 Vertical Shaft 193 555 2 129 084 594 610 4 750 940 - 7 474 635 1730 Station 01 5 121 55 758 45 945 125 869 38 101 265 673 1740 Station 02 5 121 55 758 45 945 125 869 38 101 265 673 1750 Station 03 5 164 56 199 45 945 151 189 166 901 420 233 1760 Station 04 7 069 77 187 45 945 179 441 38 101 340 673 1770 Station 05 7 069 77 187 45 945 179 441 38 101 340 673 1780 Loading Station and pumping 29 261 318 071 657 443 543 839 1 608 296 3 127 649 1790 Shaft Bottom 9 811 109 424 86 180 160 615 355 101 711 320

Direct Costs Subtotal: 492 248 5 255 840 4 563 404 9 901 068 11 017 412 30 737 724 9000 Indirect Cost - 2 062 917 1 905 221 3 886 169 3 139 962 10 994 270 9100 EPCM - 1 051 168 912 681 1 980 214 - 3 944 063 9200 Temporary Facilities - 315 350 273 804 594 064 - 1 183 219 9250 Temporary Services - 525 584 456 340 990 107 - 1 972 031 9300 CM Supplied Construction Equipment - 105 117 91 268 198 021 - 394 406 9400 Safety & Health - 13 140 11 409 24 753 - 49 301 9500 Freight - - 114 085 - 2 203 482 2 317 567 9600 QAQC - 52 558 45 634 99 011 110 174 307 377 9610 Vendor Representatives - - - - 275 435 275 435 9620 First Fill - - - - 330 522 330 522 9650 Commisioning - - - - 220 348 220 348 9700 Spares - - - - - -

Indirect Costs Subtotal: - 2 062 917 1 905 221 3 886 169 3 139 962 10 994 270 Contingency (25%) 123 062 1 829 689 1 617 156 3 446 809 3 539 344 10 432 999

TOTAL COST 615 310 9 148 447 8 085 782 17 234 047 17 696 718 52 164 993

MaterialTotal Cost

(US$)

Const EqptTotal Cost

(US$)

Mine

Process EqptTotal Cost

(US$)

Total Cost(US$)Item Description

LabourManhour

(m-h)

LabourTotal Cost

(US$)

Page 28: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 28 Rev 0 (04-Feb-14)

TABLE 8 represents the cash flow for the project up to commissioning of the shaft. The cash

flow is based on the supply of the sinking kibble winder and shaft headgear frame by CDH.

TABLE 8 : CAPITAL CASH FLOW

Year 1 Year 2 Year 3 Year 4 Year 5

10001500 General Surface - Buildings and Infrastructure - 2 478 987 - - - 1510 General & Site Development 2 280 699 1520 Laydown Area1530 Roads & Drainage 18 288 1540 Parking, Bus & Taxi Rank1550 Environmental Stockpile1560 Waste Dump1570 HT Substation 180 000

1600 Shafts - Surface System - - 7 055 457 7 542 116 331 635 1610 General & Site Development 350 592 1620 Shaft Bank1630 Winding Plant 6 008 744 6 008 744 1640 Reef and Waste Storage & Conveying 706 692 1660 Electrical Distribution 130 560 130 560 1670 Substations 696 120 696 120 1680 Lamp & Crush Ontel 201 075

1700 Shafts - Mining & Engineering - - 2 625 390 4 622 780 6 081 359 1710 General 383 000 1720 Vertical Shaft 2 242 390 2 989 854 2 242 390 1730 Station 01 265 673 1740 Station 02 265 673 1750 Station 03 420 233 1760 Station 04 340 673 1770 Station 05 340 673 1780 Loading Station and pumping 3 127 649 1790 Shaft Bottom 711 320

Direct Costs Subtotal: - 2 478 987 9 680 847 12 164 897 6 412 994 9000 Indirect Cost 798 673 4 425 173 1 653 418 1 912 718 2 204 288 9100 EPCM 788 813 788 813 788 813 788 813 788 813 9200 Temporary Facilities 1 183 219 9250 Temporary Services 1 972 031 9300 CM Supplied Construction Equipment 394 406 9400 Safety & Health 9 860 9 860 9 860 9 860 9 860 9500 Freight 695 270 927 027 695 270 9600 QAQC 76 844 76 844 76 844 76 844 9610 Vendor Representatives 82 631 110 174 82 631 9620 First Fill 330 522 9650 Commisioning 220 348 9700 Spares

Indirect Costs Subtotal: 798 673 4 425 173 1 653 418 1 912 718 2 204 288 Contingency (25%) 199 668 1 726 040 2 833 566 3 519 404 2 154 321

TOTAL COST 998 341 8 630 200 14 167 831 17 597 018 10 771 603

Item DescriptionStudy Construction

Mine

Page 29: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 29 Rev 0 (04-Feb-14)

7.2 Operating Costs (Opex)

TABLE 9 lists the expected OPEX for steady state production

TABLE 9 : DETAILED OPEX

Item Quant $/t

Unit Mhr Total Mhr Unit Total

1 OPEX1.1 LABOR 0.74

1.1.1 Engineers – shared servie with trackless mining 0.50 $ 12,461.04 $ 6,230.52 $ 149,532.50 $ 74,766.251.1.3 Shaft operations Supervisors (Engineering) – 1 per day + relief 1.00 $ 3,030.64 $ 3,030.64 $ 36,367.65 $ 36,367.651.1.4 Boilermakers – 1 off (1 per day shared + relief) 1.00 $ 3,030.64 $ 3,030.64 $ 36,367.65 $ 36,367.651.1.5 Fitters – 1 per day shared + spare 1.00 $ 3,030.64 $ 3,030.64 $ 36,367.65 $ 36,367.651.1.6 Electrical – 3 off same as fitters Yes 3.00 $ 3,030.64 $ 9,091.91 $ 36,367.65 $ 109,102.941.1.7 Bell operators - 3 3.00 $ 3,030.64 $ 9,091.91 $ 36,367.65 $ 109,102.941.1.8 Banksmen - 3 3.00 $ 2,687.50 $ 8,062.50 $ 32,250.00 $ 96,750.001.1.9 Helpers - 5 5.00 $ 2,687.50 $ 13,437.50 $ 32,250.00 $ 161,250.001.1.10 Loading operations – 2 operators per shift (one for silo control, one for the convey 5.00 $ 2,687.50 $ 13,437.50 $ 32,250.00 $ 161,250.001.1.11 Supervisors for lamp room - 3 1.00 $ 3,030.64 $ 3,030.64 $ 36,367.65 $ 36,367.651.1.12 Lamp repairers - $ 3,030.64 $ 0.00 $ 36,367.65 $ 0.001.1.13 Shift controllers - $ 2,687.50 $ 0.00 $ 32,250.00 $ 0.001.1.14 Helpers for lamp issuing - $ 2,687.50 $ 0.00 $ 32,250.00 $ 0.00

1.2 MAINTENANCE COST - CONSUMABLES 0.21 1.2.1 Ore handling at 3 % of equipment cost of $4 200 000 per annum 1.00 $ 10,500.00 $ 10,500.00 $ 126,000.00 $ 126,000.001.2.2 Winding plant at 1.5 % of equipment cost of $7 000 000 per annum 1.00 $ 8,750.00 $ 8,750.00 $ 105,000.00 $ 105,000.001.2.3 lamproom at 3 % of equipment cost of $300 000 per annum 1.00 $ 750.00 $ 750.00 $ 9,000.00 $ 9,000.001.3 POWER 0.90

1.3.1 Power cost during construciotn - $ 17,700.00 $ 0.00 $ 212,400.00 $ 0.001.3.2 Power cost at full production 1.00 $ 87,019.00 $ 87,019.00 $ 1,044,228.03 $ 1,044,228.03

TOTAL COST $ 178,493 $ 2,141,921 1.85

DescriptionMonth (US$) Annual (US$)

The OPEX is based on the following:

• Labor requirements for the shaft complex inclusive of the Lamproom;

• A typical 24 hr load profile and applying diversity factors for power consumption;

• The estimated cost of consumables for maintenance purposes.

Page 30: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

VERTICAL SHAFT STUDY REPORT

209050-00014-000-GE-REP-0001 30 Rev 0 (04-Feb-14)

8 CONCLUSION

WorleyParsons have concluded the study using sound and proven engineering practices in

terms of ore handling and shaft infrastructure. Where possible, quotations were obtained

from suppliers and the balance of the costs was derived from recent projects as per the data

base.

In terms of the shaft configuration, it is proposed that the potential to transport all equipment

down the vertical shaft, hence eliminating ramps to the workings, be considered in the next

phase of the project. This is considered to be optimal in terms of shaft designs but, early

extraction of ore is key to the project, and may be an overriding factor in the provision of the

proposed ramps.

Page 31: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

209050-00014-000-GE-REP-0001 31 Rev 0 (04-Feb-14)

ANNEX 1: CAPEX

Page 32: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

Prepared by: Julio Villanueva

SHAFT DESIGN - CHUCAPACA Date: 27/01/2014

209050-00014 Review: B

Year 1 Year 2 Year 3 Year 4 Year 5

1000

1500 General Surface - Buildings and Infrastructure - 2,478,987 - - -

1510 General & Site Development 2,280,699

1520 Laydown Area

1530 Roads & Drainage 18,288

1540 Parking, Bus & Taxi Rank

1550 Environmental Stockpile

1560 Waste Dump

1570 HT Substation 180,000

1600 Shafts - Surface System - - 7,055,457 7,542,116 331,635

1610 General & Site Development 350,592

1620 Shaft Bank

1630 Winding Plant 6,008,744 6,008,744

1640 Reef and Waste Storage & Conveying 706,692

1660 Electrical Distribution 130,560 130,560

1670 Substations 696,120 696,120

1680 Lamp & Crush Ontel 201,075

1700 Shafts - Mining & Engineering - - 2,625,390 4,622,780 6,081,359

1710 General 383,000

1720 Vertical Shaft 2,242,390 2,989,854 2,242,390

1730 Station 01 265,673

1740 Station 02 265,673

1750 Station 03 420,233

1760 Station 04 340,673

1770 Station 05 340,673

1780 Loading Station and pumping 3,127,649

1790 Shaft Bottom 711,320

Direct Costs Subtotal: - 2,478,987 9,680,847 12,164,897 6,412,994

9000 Indirect Cost 798,673 4,425,173 1,653,418 1,912,718 2,204,288

9100 EPCM 788,813 788,813 788,813 788,813 788,813

9200 Temporary Facilities 1,183,219

9250 Temporary Services 1,972,031

9300 CM Supplied Construction Equipment 394,406

9400 Safety & Health 9,860 9,860 9,860 9,860 9,860

9500 Freight 695,270 927,027 695,270

9600 QAQC 76,844 76,844 76,844 76,844

9610 Vendor Representatives 82,631 110,174 82,631

9620 First Fill 330,522

9650 Commisioning 220,348

9700 Spares

Indirect Costs Subtotal: 798,673 4,425,173 1,653,418 1,912,718 2,204,288

Contingency (25%) 199,668 1,726,040 2,833,566 3,519,404 2,154,321

TOTAL COST 998,341 8,630,200 14,167,831 17,597,018 10,771,603

CASH FLOW

Document Nr:

Project:

Project Nr:

Item DescriptionStudy Construction

Mine

Page 33: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

Prepared by: Julio Villanueva

Date: 27/01/2014

Review: B

Total

# WBS L2# WBS

L3

# WBS

L4Discip. Item Description UoM Quant Unit Cost

Unit Mhr Total Mhr Rate Unit Total Unit Total Unit Total Unit Total (US$) (US$)

1500 T 01.01 General Surface - Buildings and Infrastructure

1500 1510 T 01.01.01 General & Site Development

1500 1511 T 01.01.01.01 Platform Earthworks

1500 02 01.01.01.01.01 Civil

1500 1510 1511 02 01.01.01.01.01.01 Cut m3 878,600.00 0.06 52,716.00 9.50 0.57 500,802.00 - - 1.80 1,581,480.00 - - 2.37 2,082,282.00

1500 1510 1511 02 01.01.01.01.01.02 Fill m3 38,000.00 0.10 3,800.00 9.50 0.95 36,100.00 - - 2.28 86,640.00 - - 3.23 122,740.00

1500 03 01.01.01.01.02 Structural

1500 1510 1511 03 01.01.01.01.02.01 Perimeter fence m 380.00 2.50 950.00 9.50 23.75 9,025.00 170.40 64,752.00 5.00 1,900.00 - 199.15 75,677.00

1500 1510 1511 03 01.01.01.01.02.02 - - - - - - - -

1500 1512 T 01.01.01.02 Activity 02

1500 02 01.01.01.02.01 Civil

1500 1510 1511 02 01.01.01.01.02.01 - - - - - - - -

1500 1510 1511 02 01.01.01.01.02.02 - - - - - - - -

1500 03 01.01.01.02.02 Structural

1500 1510 1511 03 01.01.01.02.02.01 - - - - - - - -

1500 1510 1511 03 01.01.01.02.02.02 - - - - - - - -

1500 1520 T 01.01.02 Laydown Area

1500 1521 T 01.01.02.01 Activity 01

1500 02 01.01.02.01.01 Civil

1500 1520 1521 02 01.01.02.01.01.01 - - - - - - - -

1500 1520 1521 02 01.01.02.01.01.02 - - - - - - - -

1500 03 01.01.02.01.02 Structural

1500 1520 1521 03 01.01.02.01.02.01 - - - - - - - -

1500 1520 1521 03 01.01.02.01.02.02 - - - - - - - -

1500 1522 T 01.01.02.02 Activity 02

1500 02 01.01.02.02.01 Civil

1500 1520 1521 02 01.01.02.01.02.01 - - - - - - - -

1500 1520 1521 02 01.01.02.01.02.02 - - - - - - - -

1500 03 01.01.02.02.02 Structural

1500 1520 1521 03 01.01.02.02.02.01 - - - - - - - -

1500 1520 1521 03 01.01.02.02.02.02 - - - - - - - -

1500 1530 T 01.01.03 Roads & Drainage

1500 1531 T 01.01.03.01 Roads

1500 02 01.01.03.01.01 Civil

1500 1530 1531 02 01.01.03.01.01.01 - - - - - - - -

1500 1530 1531 02 01.01.03.01.01.02 - - - - - - - -

1500 1532 T 01.01.03.02 Drainage

1500 02 01.01.03.02.01 Civil

1500 1530 1532 02 01.01.03.01.02.01 Gutter of derivation m 350.00 1.00 350.00 9.50 9.50 3,325.00 - 42.75 14,962.50 - 52.25 18,287.50

1500 1530 1532 02 01.01.03.01.02.02 - - - - - - - -

1500 1540 T 01.01.04 Parking, Bus & Taxi Rank

1500 1541 T 01.01.04.01 Activity 01

1500 02 01.01.04.01.01 Civil

1500 1540 1541 02 01.01.04.01.01.01 - - - - - - - -

1500 1540 1541 02 01.01.04.01.01.02 - - - - - - - -

1500 03 01.01.04.01.02 Structural

1500 1540 1541 03 01.01.04.01.02.01 - - - - - - - -

1500 1540 1541 03 01.01.04.01.02.02 - - - - - - - -

1500 1542 T 01.01.04.02 Activity 02

1500 02 01.01.04.02.01 Civil

1500 1540 1542 02 01.01.04.01.02.01 - - - - - - - -

1500 1540 1542 02 01.01.04.01.02.02 - - - - - - - -

1500 03 01.01.04.02.02 Structural

1500 1540 1542 03 01.01.04.02.02.01 - - - - - - - -

1500 1540 1542 03 01.01.04.02.02.02 - - - - - - - -

1500 1550 T 01.01.05 Environmental Stockpile

1500 1551 T 01.01.05.01 Activity 01

1500 02 01.01.05.01.01 Civil

1500 1550 1551 02 01.01.05.01.01.01 - - - - - - - -

1500 1550 1551 02 01.01.05.01.01.02 - - - - - - - -

1500 1552 T 01.01.05.02 Activity 02

1500 02 01.01.05.02.01 Civil

1500 1550 1551 02 01.01.05.01.02.01 - - - - - - - -

1500 1550 1551 02 01.01.05.01.02.02 - - - - - - - -

CAPEX

SCOPING STUDY

SHAFT DESIGN - CHUCAPACA

209050-00014

Total Cost

Document Nr:

Project:

Project Nr:

Labour Manhour (mh) Labour Cost (US$) Material Cost (US$) Const Eqpt (US$) Process Eqpt (US$)

Page 34: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

Prepared by: Julio Villanueva

Date: 27/01/2014

Review: B

Total

# WBS L2# WBS

L3

# WBS

L4Discip. Item Description UoM Quant Unit Cost

Unit Mhr Total Mhr Rate Unit Total Unit Total Unit Total Unit Total (US$) (US$)

CAPEX

SCOPING STUDY

SHAFT DESIGN - CHUCAPACA

209050-00014

Total Cost

Document Nr:

Project:

Project Nr:

Labour Manhour (mh) Labour Cost (US$) Material Cost (US$) Const Eqpt (US$) Process Eqpt (US$)

1500 1560 T 01.01.06 Waste Dump

1500 1561 T 01.01.06.01 Activity 01

1500 02 01.01.06.01.01 Civil

1500 1560 1561 02 01.01.06.01.01.01 - - - - - - - -

1500 1560 1561 02 01.01.06.01.01.02 - - - - - - - -

1500 1562 T 01.01.06.02 Activity 02

1500 02 01.01.06.02.01 Civil

1500 1560 1562 02 01.01.06.01.02.01 - - - - - - - -

1500 1560 1562 02 01.01.06.01.02.02 - - - - - - - -

1500 1570 T 01.01.07 HT Substation

1500 1571 T 01.01.07.01 Overhead Powerline

1500 02 01.01.07.01.01 Civil

1500 1570 1571 02 01.01.07.01.01.01 - - - - - - - -

1500 1570 1571 02 01.01.07.01.01.02 - - - - - - - -

1500 03 01.01.07.01.02 Structural

1500 1570 1571 03 01.01.07.01.02.01 - - - - - - - -

1500 1570 1571 03 01.01.07.01.02.02 - - - - - - - -

1500 06 01.01.07.01.03 Electrical

1500 1570 1571 06 01.01.07.01.03.01 Power Line, 13.8kv, wood pole km 5.00 30.00 150.00 10.25 307.50 1,537.50 30,000.00 150,000.00 5,692.50 28,462.50 - 36,000.00 180,000.00

1500 1570 1571 06 01.01.07.01.03.02 - - - - - - - -

1500 1572 T 01.01.07.02 Activity 02

1500 02 01.01.07.02.01 Civil

1500 1570 1572 02 01.01.07.01.02.01 - - - - - - - -

1500 1570 1572 02 01.01.07.01.02.02 - - - - - - - -

1500 03 01.01.07.02.02 Structural

1500 1570 1572 03 01.01.07.02.02.01 - - - - - - - -

1500 1570 1572 03 01.01.07.02.02.02 - - - - - - - -

1500 06 01.01.07.02.03 Electrical

1500 1570 1572 06 01.01.07.02.03.01 - - - - - - - -

1500 1570 1572 06 01.01.07.02.03.02 - - - - - - - -

1600 T 01.02 Shafts - Surface System

1600 1610 T 01.02.01 General & Site Development

1600 1611 T 01.02.01.01 Activity 01

1600 02 01.02.01.01.01 Civil

1600 1610 1611 02 01.02.01.01.01.01 - - - - - - - -

1600 1610 1611 02 01.02.01.01.01.02 - - - - - - - -

1600 03 01.02.01.01.02 Structural

Conveyor Foundations (L=150m)

1600 1610 1611 03 01.02.01.01.02.01 Excavation m3 50.00 0.22 11.00 9.50 2.09 104.50 - - 3.41 170.50 - - 5.50 275.00

1600 1610 1611 03 01.02.01.01.02.02 Compacting m2 14.00 1.95 27.30 9.50 18.53 259.35 - - 5.55 77.70 - - 24.08 337.05

1600 1610 1611 03 01.02.01.01.02.03 Blinding - 50mm - 10 mPa m3 0.70 4.20 2.94 9.50 39.90 27.93 188.50 131.95 6.78 4.75 - - 235.18 164.63

1600 1610 1611 03 01.02.01.01.02.04 Shuttering Bases- Single Use m2 42.00 1.90 79.80 9.50 18.05 758.10 8.87 372.54 3.79 159.18 - - 30.71 1,289.82

1600 1610 1611 03 01.02.01.01.02.05 Reinforcing - Bases - 130kg/m³ - Supply & Fix t 1.30 59.00 76.70 9.50 560.50 728.65 1,394.00 1,812.20 78.47 102.01 - - 2,032.97 2,642.86

1600 1610 1611 03 01.02.01.01.02.06 Concrete - 25 mPa m3 10.00 7.98 79.80 9.50 75.81 758.10 387.26 3,872.60 12.89 128.90 - - 475.96 4,759.60

1600 1610 1611 03 01.02.01.01.02.07 Woodfloat Bases m2 14.00 1.90 26.60 9.50 18.05 252.70 8.87 124.18 3.79 53.06 - - 30.71 429.94

1600 1610 1611 03 01.02.01.01.02.08 Shuttering Plinth- Single Use m2 77.00 1.90 146.30 9.50 18.05 1,389.85 8.87 682.99 3.79 291.83 - - 30.71 2,364.67

1600 1610 1611 03 01.02.01.01.02.09 Reinforcing - Plinths - 130kg/m³ - Supply & Fix t 1.09 59.00 64.43 9.50 560.50 612.07 1,394.00 1,522.25 78.47 85.69 - - 2,032.97 2,220.00

1600 1610 1611 03 01.02.01.01.02.10 Fix Foundation Bolts ea 56.00 0.10 5.60 11.00 1.10 61.60 4.01 224.56 1.60 89.60 - - 6.71 375.76

1600 1610 1611 03 01.02.01.01.02.11 Concrete - 25 mPa m3 8.40 7.98 67.03 9.50 75.81 636.80 387.26 3,252.98 12.89 108.28 - - 475.96 3,998.06

1600 1610 1611 03 01.02.01.01.02.12 Woodfloat Plinths m2 2.80 1.90 5.32 9.50 18.05 50.54 8.87 24.84 3.79 10.61 - - 30.71 85.99

1600 1610 1611 03 01.02.01.01.02.13 Back Fill m3 30.90 0.39 12.05 9.50 3.71 114.48 - - 1.11 34.30 - - 4.82 148.78

1600 1610 1611 03 01.02.01.01.02.14 Conveyor Steelwork t 85.00 80.00 6,800.00 11.00 880.00 74,800.00 2,400.00 204,000.00 620.00 52,700.00 - - 3,900.00 331,500.00

1600 07 01.02.03.01.06 Instrumentation

1600 1630 1631 07 01.02.03.01.06.01 Fiber Optic MM 12 wires m 1,000.00 0.27 270.00 10.25 2.77 2,767.50 7.38 7,380.00 3.69 3,690.00 - 13.84 13,837.50

1600 1630 1631 07 01.02.03.01.06.02 Leaky Feeder m 1,000.00 0.27 270.00 10.25 2.77 2,767.50 4.00 4,000.00 2.00 2,000.00 - 8.77 8,767.50

1600 1630 1631 07 01.02.03.01.06.03 Cable Cu, S / UTP m 600.00 0.34 204.00 10.25 3.49 2,091.00 0.74 442.62 0.37 221.31 - 4.59 2,754.93

1600 1630 1631 07 01.02.03.01.06.04 Telephone Cable m 300.00 0.30 90.00 10.25 3.08 922.50 0.15 45.00 0.08 22.50 - 3.30 990.00

1600 1612 T 01.02.01.02 Activity 02

1600 02 01.02.01.02.01 Civil

1600 1610 1612 02 01.02.01.02.01.01 - - - - - - - -

1600 1610 1612 02 01.02.01.02.01.02 - - - - - - - -

1600 03 01.02.01.02.02 Structural

1600 1610 1612 03 01.02.01.02.02.01 - - - - - - - -

1600 1610 1612 03 01.02.01.02.02.02 - - - - - - - -

1600 1620 T 01.02.02 Shaft Bank

Page 35: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

Prepared by: Julio Villanueva

Date: 27/01/2014

Review: B

Total

# WBS L2# WBS

L3

# WBS

L4Discip. Item Description UoM Quant Unit Cost

Unit Mhr Total Mhr Rate Unit Total Unit Total Unit Total Unit Total (US$) (US$)

CAPEX

SCOPING STUDY

SHAFT DESIGN - CHUCAPACA

209050-00014

Total Cost

Document Nr:

Project:

Project Nr:

Labour Manhour (mh) Labour Cost (US$) Material Cost (US$) Const Eqpt (US$) Process Eqpt (US$)

1600 1621 T 01.02.02.01 Terrace

1600 02 01.02.02.01.01 Civil

1600 1620 1621 02 01.02.02.01.01.01 - - - - - - - -

1600 1620 1621 02 01.02.02.01.01.02 - - - - - - - -

1600 1622 T 01.02.02.02 Railways & Spur

1600 03 01.02.02.02.01 Structural

1600 1620 1622 03 01.02.02.02.01.01 Steel Structures - - - - - - - - -

1600 1620 1622 03 01.02.02.02.01.02 - - - - - - - -

1600 1623 T 01.02.02.03 Mine Vehicles

1600 04 01.02.02.03.01 Mechanical

1600 1620 1623 04 01.02.02.03.01.01 - - - - - - - -

1600 1620 1623 04 01.02.02.03.01.02 - - - - - - - -

1600 1624 T 01.02.02.04 Banksmans Cabin

1600 03 01.02.02.04.01 Structural

1600 1620 1624 03 01.02.02.04.01.01 - - - - - - - -

1600 1620 1624 03 01.02.02.04.01.02 - - - - - - - -

1600 1630 T 01.02.03 Winding Plant

1600 1631 T 01.02.03.01 Headgear

1600 02 01.02.03.01.01 Civil

1600 1630 1631 02 01.02.03.01.01.01 - - - - - - - -

1600 1630 1631 02 01.02.03.01.01.02 - - - - - - - -

1600 03 01.02.03.01.02 Structural

RACKER LEG FOUNDATIONS

1600 1630 1631 03 01.02.03.01.02.01 Excavation m3 224.41 0.22 49.37 9.50 2.09 469.02 - - 3.41 765.24 - - 5.50 1,234.27

1600 1630 1631 03 01.02.03.01.02.02 Compacting m2 53.68 1.95 104.67 9.50 18.53 994.33 - - 5.55 297.90 - - 24.08 1,292.23

1600 1630 1631 03 01.02.03.01.02.03 Blinding - 50mm - 10 mPa m3 2.61 4.20 10.96 9.50 39.90 104.14 188.50 491.99 6.78 17.70 - - 235.18 613.82

1600 1630 1631 03 01.02.03.01.02.04 Shuttering Bases- Single Use m2 67.47 1.90 128.19 9.50 18.05 1,217.83 8.87 598.46 3.79 255.71 - - 30.71 2,072.00

1600 1630 1631 03 01.02.03.01.02.05 Reinforcing - Bases - 130kg/m³ - Supply & Fix t 8.77 59.00 517.49 9.50 560.50 4,916.20 1,394.00 12,226.91 78.47 688.27 - - 2,032.97 17,831.38

1600 1630 1631 03 01.02.03.01.02.06 Concrete - 25 mPa m3 67.47 7.98 538.41 9.50 75.81 5,114.90 387.26 26,128.43 12.89 869.69 - - 475.96 32,113.02

1600 1630 1631 03 01.02.03.01.02.07 Woodfloat Bases m2 53.68 1.90 101.98 9.50 18.05 968.83 8.87 476.10 3.79 203.43 - - 30.71 1,648.36

1600 1630 1631 03 01.02.03.01.02.08 Shuttering Plinth- Single Use m2 21.24 1.90 40.36 9.50 18.05 383.42 8.87 188.42 3.79 80.51 - - 30.71 652.34

1600 1630 1631 03 01.02.03.01.02.09 Reinforcing - Plinths - 130kg/m³ - Supply & Fix t 2.76 59.00 162.93 9.50 560.50 1,547.80 1,394.00 3,849.48 78.47 216.69 - - 2,032.97 5,613.97

1600 1630 1631 03 01.02.03.01.02.10 Fix Foundation Bolts ea 64.00 0.10 6.40 11.00 1.10 70.40 4.01 256.64 1.60 102.40 - - 6.71 429.44

1600 1630 1631 03 01.02.03.01.02.11 Concrete - 25 mPa m3 24.24 7.98 193.45 9.50 75.81 1,837.79 387.26 9,387.96 12.89 312.48 - - 475.96 11,538.22

1600 1630 1631 03 01.02.03.01.02.12 Woodfloat Plinths m2 7.04 1.90 13.38 9.50 18.05 127.07 8.87 62.44 3.79 26.68 - - 30.71 216.20

1600 1630 1631 03 01.02.03.01.02.13 Back Fill m3 130.09 0.39 50.74 9.50 3.71 481.99 - - 1.11 144.40 - - 4.82 626.39

HEADGEAR & BIN FOUNDATIONS

1600 1630 1631 03 01.02.03.01.02.14 Excavation m3 187.01 0.22 41.14 9.50 2.09 390.85 - - 3.41 637.70 - - 5.50 1,028.56

1600 1630 1631 03 01.02.03.01.02.15 Compacting m2 53.68 1.95 104.67 9.50 18.53 994.33 - - 5.55 297.90 - - 24.08 1,292.23

1600 1630 1631 03 01.02.03.01.02.16 Blinding - 50mm - 10 mPa m3 2.61 4.20 10.96 9.50 39.90 104.14 188.50 491.99 6.78 17.70 - - 235.18 613.82

1600 1630 1631 03 01.02.03.01.02.17 Shuttering Bases- Single Use m2 67.47 1.90 128.19 9.50 18.05 1,217.83 8.87 598.46 3.79 255.71 - - 30.71 2,072.00

1600 1630 1631 03 01.02.03.01.02.18 Reinforcing - Bases - 130kg/m³ - Supply & Fix t 8.77 59.00 517.49 9.50 560.50 4,916.20 1,394.00 12,226.91 78.47 688.27 - - 2,032.97 17,831.38

1600 1630 1631 03 01.02.03.01.02.19 Concrete - 25 mPa m3 67.47 7.98 538.41 9.50 75.81 5,114.90 387.26 26,128.43 12.89 869.69 - - 475.96 32,113.02

1600 1630 1631 03 01.02.03.01.02.20 Woodfloat Bases m2 53.68 1.90 101.98 9.50 18.05 968.83 8.87 476.10 3.79 203.43 - - 30.71 1,648.36

1600 1630 1631 03 01.02.03.01.02.21 Shuttering Plinth- Single Use m2 21.24 1.90 40.36 9.50 18.05 383.42 8.87 188.42 3.79 80.51 - - 30.71 652.34

1600 1630 1631 03 01.02.03.01.02.22 Reinforcing - Plinths - 130kg/m³ - Supply & Fix t 2.76 59.00 162.91 9.50 560.50 1,547.65 1,394.00 3,849.11 78.47 216.67 - - 2,032.97 5,613.44

1600 1630 1631 03 01.02.03.01.02.23 Fix Foundation Bolts ea 64.00 0.10 6.40 11.00 1.10 70.40 4.01 256.64 1.60 102.40 - - 6.71 429.44

1600 1630 1631 03 01.02.03.01.02.24 Concrete - 25 mPa m3 21.24 7.98 169.51 9.50 75.81 1,610.36 387.26 8,226.18 12.89 273.81 - - 475.96 10,110.34

1600 1630 1631 03 01.02.03.01.02.25 Woodfloat Plinths m2 7.04 1.90 13.38 9.50 18.05 127.07 8.87 62.44 3.79 26.68 - - 30.71 216.20

1600 1630 1631 03 01.02.03.01.02.26 Back Fill m3 98.30 0.39 38.34 9.50 3.71 364.20 - - 1.11 109.11 - - 4.82 473.31

1600 1630 1631 03 01.02.03.01.02.27 Steel Structures t 390.00 80.00 31,200.00 11.00 880.00 343,200.00 2,400.00 936,000.00 620.00 241,800.00 - - 3,900.00 1,521,000.00

1600 04 01.02.03.01.03 Mechanical

1600 1630 1631 04 01.02.03.01.03.01 Sheave Wheel ea 4.00 2,216.00 8,864.00 11.00 24,375.99 97,503.95 - 16,250.66 65,002.63 203,133.22 812,532.88 243,759.86 975,039.46

1600 1630 1631 04 01.02.03.01.03.02 Crane 10t ea 2.00 310.91 621.82 11.00 3,420.00 6,840.00 - 2,280.00 4,560.00 28,500.00 57,000.00 34,200.00 68,400.00

1600 1630 1631 04 01.02.03.01.03.03 Reception Chute ea 2.00 163.64 327.27 11.00 1,800.00 3,600.00 15,000.00 30,000.00 1,200.00 2,400.00 - 18,000.00 36,000.00

1600 1630 1631 04 01.02.03.01.03.04 Arc Chute ea 1.00 75.87 75.87 11.00 834.60 834.60 - 556.40 556.40 6,955.00 6,955.00 8,346.00 8,346.00

1600 1630 1631 04 01.02.03.01.03.05 1 Discharge Chute + 1 Vibrating Feeder + 1 Conveyor Loading Chute + support steel complete with access platform, handrails and stairwaysea 1.00 2,351.73 2,351.73 11.00 25,869.00 25,869.00 - 17,246.00 17,246.00 215,575.00 215,575.00 258,690.00 258,690.00

1600 05 01.02.03.01.04 Piping

1600 1630 1631 05 01.02.03.01.04.01 Compressed air service pipe. Ø2", Sch40, Class 150, Carbon Steel Galvanized, Threaded (Includes valves and accesories)m 50.00 2.50 125.00 11.00 27.50 1,375.00 24.00 1,200.00 29.76 1,488.00 - 81.26 4,063.00

1600 1630 1631 05 01.02.03.01.04.02 Water Service pipe. Ø2", Sch40, Class 150, Carbon Steel Galvanized, Threaded (Includes valves and accesories)m 50.00 2.50 125.00 11.00 27.50 1,375.00 24.00 1,200.00 29.76 1,488.00 - 81.26 4,063.00

1600 06 01.02.03.01.05 Electrical

1600 1630 1631 06 01.02.03.01.05.01 Panelboard 480V, 25kA, 60Hz, 150A ea 4.00 31.20 124.80 10.25 319.80 1,279.20 - 2,180.20 8,720.80 12,500.00 50,000.00 15,000.00 60,000.00

1600 1630 1631 06 01.02.03.01.05.02 Panelboard 230V, 25kA, 60Hz, 60A ea 4.00 31.20 124.80 10.25 319.80 1,279.20 - 980.20 3,920.80 6,500.00 26,000.00 7,800.00 31,200.00

1600 1630 1631 06 01.02.03.01.05.03 Lightning, PDC ea 1.00 8.00 8.00 10.25 82.00 82.00 - 718.00 718.00 4,000.00 4,000.00 4,800.00 4,800.00

1600 1630 1631 06 01.02.03.01.05.04 Bulk Materials (Lighting, welding socket, earthing, trays,etc) lot 1.00 34.15 34.15 10.25 350.00 350.00 3,500.00 3,500.00 350.00 350.00 - 4,200.00 4,200.00

1600 07 01.02.03.01.06 Instrumentation

1600 1630 1631 07 01.02.03.01.06.01 Sistema de telececomunicaciones incluye: Gabinete de telecomunicaciones pedestal ea 1.00 10.00 10.00 10.25 102.50 102.50 - 522.64 522.64 1,045.27 1,045.27 1,670.41 1,670.41

1600 1630 1631 07 01.02.03.01.06.02 switch de telecomunicaciones ea 1.00 3.70 3.70 10.25 37.93 37.93 - 1,394.88 1,394.88 2,789.76 2,789.76 4,222.57 4,222.57

1600 1630 1631 07 01.02.03.01.06.03 Transceiver SFP ea 2.00 3.00 6.00 10.25 30.75 61.50 - 480.08 960.15 960.15 1,920.30 1,470.98 2,941.95

1600 1630 1631 07 01.02.03.01.06.04 patch panel para fibra óptica ea 1.00 2.50 2.50 10.25 25.63 25.63 - 214.51 214.51 429.01 429.01 669.14 669.14

1600 1630 1631 07 01.02.03.01.06.05 Accesorios ea 1.00 78.79 78.79 10.25 807.60 807.60 1,000.00 1,000.00 500.00 500.00 - 2,307.60 2,307.60

1600 1630 1631 07 01.02.03.01.06.06 CCTV Incuye: Cámara IP -Térmica, ea 1.00 12.40 12.40 10.25 127.10 127.10 - 7,922.60 7,922.60 15,845.19 15,845.19 23,894.89 23,894.89

Page 36: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

Prepared by: Julio Villanueva

Date: 27/01/2014

Review: B

Total

# WBS L2# WBS

L3

# WBS

L4Discip. Item Description UoM Quant Unit Cost

Unit Mhr Total Mhr Rate Unit Total Unit Total Unit Total Unit Total (US$) (US$)

CAPEX

SCOPING STUDY

SHAFT DESIGN - CHUCAPACA

209050-00014

Total Cost

Document Nr:

Project:

Project Nr:

Labour Manhour (mh) Labour Cost (US$) Material Cost (US$) Const Eqpt (US$) Process Eqpt (US$)

1600 1630 1631 07 01.02.03.01.06.07 Fuente para cámara IP ea 1.00 2.50 2.50 10.25 25.63 25.63 - 71.62 71.62 143.23 143.23 240.47 240.47

1600 1630 1631 07 01.02.03.01.06.08 PABX Incluye: Teléfono emergencia para trabajos en ambiente minero,ea 1.00 1.00 1.00 10.25 10.25 10.25 - 251.53 251.53 503.05 503.05 764.83 764.83

1600 1630 1631 07 01.02.03.01.06.09 conversor de medios ea 1.00 3.50 3.50 10.25 35.88 35.88 - 231.04 231.04 462.07 462.07 728.98 728.98

1600 1630 1631 07 01.02.03.01.06.10 LEAKY FEEDER Incluye: Amplificador, fin de línea y splitter ea 1.00 5.00 5.00 10.25 51.25 51.25 - 750.00 750.00 1,500.00 1,500.00 2,301.25 2,301.25

1600 1630 1631 07 01.02.03.01.06.11 Tablero eléctrico instrumentación 120VAC ea 1.00 10.00 10.00 10.25 102.50 102.50 - 2,075.00 2,075.00 4,150.00 4,150.00 6,327.50 6,327.50

1600 1632 T 01.02.03.02 Winder House

1600 02 01.02.03.02.01 Civil

1600 1630 1632 02 01.02.03.02.01.01 - - - - - - - -

1600 1630 1632 02 01.02.03.02.01.02 - - - - - - - -

1600 03 01.02.03.02.02 Structural

1600 1630 1632 03 01.02.03.02.02.01 Concrete Structures (foundations) m3 368.90 7.98 2,943.82 9.50 75.81 27,966.31 387.26 142,860.21 12.89 4,755.12 - - 475.96 175,581.64

LEAN TOO FOUNDATIONS

1600 1630 1632 03 01.02.03.02.02.02 Shuttering Bases - Single Use m2 24.00 1.90 45.60 9.50 18.05 433.20 8.87 212.88 3.79 90.96 - - 30.71 737.04

1600 1630 1632 03 01.02.03.02.02.03 Reinforcing - 130kg/m³ - Supply & Fix t 1.17 59.00 69.03 9.50 560.50 655.79 1,394.00 1,630.98 78.47 91.81 - - 2,032.97 2,378.57

1600 1630 1632 03 01.02.03.02.02.04 Woodfloat Bases m2 9.00 1.90 17.10 9.50 18.05 162.45 8.87 79.83 3.79 34.11 - - 30.71 276.39

1600 1630 1632 03 01.02.03.02.02.05 Shuttering Plinths - Single Use m2 32.00 1.90 60.80 9.50 18.05 577.60 8.87 283.84 3.79 121.28 - - 30.71 982.72

1600 1630 1632 03 01.02.03.02.02.06 Reinforcing - 130kg/m³ - Supply & Fix t 0.83 59.00 49.09 9.50 560.50 466.34 1,394.00 1,159.81 78.47 65.29 - - 2,032.97 1,691.43

1600 1630 1632 03 01.02.03.02.02.07 Fix Foundation Bolts ea 16.00 0.10 1.60 11.00 1.10 17.60 4.01 64.16 1.60 25.60 - - 6.71 107.36

1600 1630 1632 03 01.02.03.02.02.08 Woodfloat Plinths m2 2.56 1.90 4.86 9.50 18.05 46.21 8.87 22.71 3.79 9.70 - - 30.71 78.62

1600 1630 1632 03 01.02.03.02.02.09 Back Fill m3 32.95 0.39 12.85 9.50 3.71 122.08 - - 1.11 36.57 - - 4.82 158.65

CRANE FOUNDATIONS

1600 1630 1632 03 01.02.03.02.02.10 Excavation m3 448.35 0.22 98.64 9.50 2.09 937.05 - - 3.41 1,528.87 - - 5.50 2,465.93

1600 1630 1632 03 01.02.03.02.02.11 Compacting m2 147.00 1.95 286.65 9.50 18.53 2,723.18 - - 5.55 815.85 - - 24.08 3,539.03

1600 1630 1632 03 01.02.03.02.02.12 Blinding - 50mm - 10 mPa m3 5.40 4.20 22.68 9.50 39.90 215.46 188.50 1,017.90 6.78 36.61 - - 235.18 1,269.97

1600 1630 1632 03 01.02.03.02.02.13 Shuttering Bases - Single Use m2 144.00 1.90 273.60 9.50 18.05 2,599.20 8.87 1,277.28 3.79 545.76 - - 30.71 4,422.24

1600 1630 1632 03 01.02.03.02.02.14 Reinforcing - 130kg/m³ - Supply & Fix t 14.04 59.00 828.36 9.50 560.50 7,869.42 1,394.00 19,571.76 78.47 1,101.72 - - 2,032.97 28,542.90

1600 1630 1632 03 01.02.03.02.02.15 Woodfloat Bases m2 108.00 1.90 205.20 9.50 18.05 1,949.40 8.87 957.96 3.79 409.32 - - 30.71 3,316.68

1600 1630 1632 03 01.02.03.02.02.16 Shuttering Plinths - Single Use m2 204.00 1.90 387.60 9.50 18.05 3,682.20 8.87 1,809.48 3.79 773.16 - - 30.71 6,264.84

1600 1630 1632 03 01.02.03.02.02.17 Reinforcing - 130kg/m³ - Supply & Fix t 9.87 59.00 582.15 9.50 560.50 5,530.45 1,394.00 13,754.60 78.47 774.26 - - 2,032.97 20,059.31

1600 1630 1632 03 01.02.03.02.02.18 Fix Foundation Bolts ea 192.00 0.10 19.20 11.00 1.10 211.20 4.01 769.92 1.60 307.20 - - 6.71 1,288.32

1600 1630 1632 03 01.02.03.02.02.19 Woodfloat Plinths m2 30.36 1.90 57.68 9.50 18.05 548.00 8.87 269.29 3.79 115.06 - - 30.71 932.36

1600 1630 1632 03 01.02.03.02.02.20 Back Fill m3 259.05 0.39 101.03 9.50 3.71 959.78 - - 1.11 287.55 - - 4.82 1,247.33

GABLE FOUNDATIONS

1600 1630 1632 03 01.02.03.02.02.21 Excavation m3 73.20 0.22 16.10 9.50 2.09 152.99 - - 3.41 249.61 - - 5.50 402.60

1600 1630 1632 03 01.02.03.02.02.22 Compacting m2 24.00 1.95 46.80 9.50 18.53 444.60 - - 5.55 133.20 - - 24.08 577.80

1600 1630 1632 03 01.02.03.02.02.23 Blinding - 50mm - 10 mPa m3 0.68 4.20 2.84 9.50 39.90 26.93 188.50 127.24 6.78 4.58 - - 235.18 158.75

1600 1630 1632 03 01.02.03.02.02.24 Shuttering Bases - Single Use m2 36.00 1.90 68.40 9.50 18.05 649.80 8.87 319.32 3.79 136.44 - - 30.71 1,105.56

1600 1630 1632 03 01.02.03.02.02.25 Reinforcing - 130kg/m³ - Supply & Fix t 1.76 59.00 103.55 9.50 560.50 983.68 1,394.00 2,446.47 78.47 137.71 - - 2,032.97 3,567.86

1600 1630 1632 03 01.02.03.02.02.26 Woodfloat Bases m2 13.25 1.90 25.18 9.50 18.05 239.16 8.87 117.53 3.79 50.22 - - 30.71 406.91

1600 1630 1632 03 01.02.03.02.02.27 Shuttering Plinths - Single Use m2 48.00 1.90 91.20 9.50 18.05 866.40 8.87 425.76 3.79 181.92 - - 30.71 1,474.08

1600 1630 1632 03 01.02.03.02.02.28 Reinforcing - 130kg/m³ - Supply & Fix t 1.25 59.00 73.46 9.50 560.50 697.82 1,394.00 1,735.53 78.47 97.70 - - 2,032.97 2,531.05

1600 1630 1632 03 01.02.03.02.02.29 Fix Foundation Bolts ea 24.00 0.10 2.40 11.00 1.10 26.40 4.01 96.24 1.60 38.40 - - 6.71 161.04

1600 1630 1632 03 01.02.03.02.02.30 Woodfloat Plinths m2 3.84 1.90 7.30 9.50 18.05 69.31 8.87 34.06 3.79 14.55 - - 30.71 117.93

1600 1630 1632 03 01.02.03.02.02.31 Back Fill m3 49.67 0.39 19.37 9.50 3.71 184.03 - - 1.11 55.13 - - 4.82 239.16

BRICK WALL FOUNDATION

1600 1630 1632 03 01.02.03.02.02.32 Excavation m3 71.78 0.22 15.79 9.50 2.09 150.02 - - 3.41 244.76 - - 5.50 394.78

1600 1630 1632 03 01.02.03.02.02.33 Compacting m2 95.70 1.95 186.62 9.50 18.53 1,772.92 - - 5.55 531.16 - - 24.08 2,304.07

1600 1630 1632 03 01.02.03.02.02.34 Mesh m2 143.55 1.50 215.33 11.00 16.50 2,368.58 35.00 5,024.25 17.50 2,512.13 - 69.00 9,904.95

1600 1630 1632 03 01.02.03.02.02.35 Concrete - 25 mPa m3 23.93 7.98 190.96 9.50 75.81 1,814.13 387.26 9,267.13 12.89 308.46 - - 475.96 11,389.72

1600 1630 1632 03 01.02.03.02.02.36 Woodfloat Bases m2 95.70 1.90 181.84 9.50 18.05 1,727.46 8.87 848.89 3.79 362.72 - - 30.71 2,939.07

1600 1630 1632 03 01.02.03.02.02.37 Brick work m2 55.03 10.00 550.30 9.50 95.00 5,227.83 184.50 10,153.00 22.00 1,210.66 - - 301.50 16,591.48

1600 1630 1632 03 01.02.03.02.02.38 Back Fill m3 32.13 0.39 12.53 9.50 3.71 119.03 - - 1.11 35.66 - - 4.82 154.69

FLOOR

1600 1630 1632 03 01.02.03.02.02.39 Compacting m2 992.43 1.95 1,935.24 9.50 18.53 18,384.77 - - 5.55 5,507.99 - - 24.08 23,892.75

1600 1630 1632 03 01.02.03.02.02.40 Mesh - Top and Bottom m2 1,984.86 1.50 2,977.29 11.00 16.50 32,750.19 35.00 69,470.10 17.50 34,735.05 - 69.00 136,955.34

1600 1630 1632 03 01.02.03.02.02.41 Shuttering Bases - Single Use - 200mm Thick Slab m2 28.88 1.90 54.87 9.50 18.05 521.24 8.87 256.14 3.79 109.45 - - 30.71 886.83

1600 1630 1632 03 01.02.03.02.02.42 Shuttering Bases - Single Use - 150mm Thick Slab m2 110.25 1.90 209.48 9.50 18.05 1,990.01 8.87 977.92 3.79 417.85 - - 30.71 3,385.78

1600 1630 1632 03 01.02.03.02.02.43 Concrete - 25 mPa - 200mm Thick Slab m3 28.88 7.98 230.44 9.50 75.81 2,189.20 387.26 11,183.10 12.89 372.23 - - 475.96 13,744.53

1600 1630 1632 03 01.02.03.02.02.44 Concrete - 25 mPa - 150mm Thick Slab m3 110.25 7.98 879.80 9.50 75.81 8,358.05 387.26 42,695.42 12.89 1,421.12 - - 475.96 52,474.59

1600 1630 1632 03 01.02.03.02.02.45 Woodfloat - 200mm Thick Slab m2 144.39 1.90 274.34 9.50 18.05 2,606.20 8.87 1,280.72 3.79 547.23 - - 30.71 4,434.15

1600 1630 1632 03 01.02.03.02.02.46 Woodfloat - 150mm Thick Slab m2 735.04 1.90 1,396.58 9.50 18.05 13,267.47 8.87 6,519.80 3.79 2,785.80 - - 30.71 22,573.08

1600 1630 1632 03 01.02.03.02.02.47 Steel Structurres - Winder House t 86.40 80.00 6,912.00 11.00 880.00 76,032.00 2,400.00 207,360.00 620.00 53,568.00 - - 3,900.00 336,960.00

1600 1630 1632 03 01.02.03.02.02.48 Cladding m2 4,670.00 1.20 5,604.00 9.50 11.40 53,238.00 25.93 121,093.10 18.34 85,647.80 - 55.67 259,978.90

1600 04 01.02.03.02.03 Mechanical

1600 1630 1632 04 01.02.03.02.03.01 Overhead Crane ea 1.00 1,003.90 1,003.90 11.00 11,042.88 11,042.88 - 7,361.92 7,361.92 92,024.00 92,024.00 110,428.80 110,428.80

1600 05 01.02.03.02.04 Piping

1600 1630 1632 05 01.02.03.02.04.01 Compressed air service pipe. Ø2", Sch40, Class 150, Carbon Steel Galvanized, Threaded (Includes valves and accesories)m 100.00 2.50 250.00 11.00 27.50 2,750.00 24.00 2,400.00 29.76 2,976.00 - 81.26 8,126.00

1600 1630 1632 05 01.02.03.02.04.02 Water Service pipe. Ø2", Sch40, Class 150, Carbon Steel Galvanized, Threaded (Includes valves and accesories)m 100.00 2.50 250.00 11.00 27.50 2,750.00 24.00 2,400.00 29.76 2,976.00 - 81.26 8,126.00

1600 06 01.02.03.02.05 Electrical

1600 1630 1632 06 01.02.03.02.05.01 Panelboard 480V, 25kA, 60Hz, 150A ea 7.00 31.20 218.40 10.25 319.80 2,238.60 - 2,180.20 15,261.40 12,500.00 87,500.00 15,000.00 105,000.00

1600 1630 1632 06 01.02.03.02.05.02 Panelboard 230V, 25kA, 60Hz, 60A ea 7.00 31.20 218.40 10.25 319.80 2,238.60 - 980.20 6,861.40 6,500.00 45,500.00 7,800.00 54,600.00

1600 1630 1632 06 01.02.03.02.05.03 Bulk Materials (Lighting, welding socket, earthing, trays,etc) lot 1.00 53.66 53.66 10.25 550.00 550.00 5,500.00 5,500.00 550.00 550.00 - 6,600.00 6,600.00

1600 07 01.02.03.02.06 Instrumentation

1600 1630 1632 07 01.02.03.02.06.01 Sistema de telecomunicaciones incluye: Gabinete de telecomunicaciones 42 RUea 3.00 10.00 30.00 10.25 102.50 307.50 - 975.00 2,925.00 1,950.00 5,850.00 3,027.50 9,082.50

1600 1630 1632 07 01.02.03.02.06.02 switch de telecomunicaciones ea 3.00 3.70 11.10 10.25 37.93 113.78 - 1,686.00 5,058.00 3,372.00 10,116.00 5,095.93 15,287.78

1600 1630 1632 07 01.02.03.02.06.03 patch panel para fibra óptica ea 3.00 2.50 7.50 10.25 25.63 76.88 - 333.04 999.11 666.07 1,998.21 1,024.73 3,074.19

Page 37: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

Prepared by: Julio Villanueva

Date: 27/01/2014

Review: B

Total

# WBS L2# WBS

L3

# WBS

L4Discip. Item Description UoM Quant Unit Cost

Unit Mhr Total Mhr Rate Unit Total Unit Total Unit Total Unit Total (US$) (US$)

CAPEX

SCOPING STUDY

SHAFT DESIGN - CHUCAPACA

209050-00014

Total Cost

Document Nr:

Project:

Project Nr:

Labour Manhour (mh) Labour Cost (US$) Material Cost (US$) Const Eqpt (US$) Process Eqpt (US$)

1600 1630 1632 07 01.02.03.02.06.04 Accesorios ea 3.00 78.79 236.37 10.25 807.60 2,422.79 1,000.00 3,000.00 500.00 1,500.00 - 2,307.60 6,922.79

1600 1630 1632 07 01.02.03.02.06.05 CCTV Incluye: Servidor de video ea 1.00 12.40 12.40 10.25 127.10 127.10 - 3,374.50 3,374.50 6,748.99 6,748.99 10,250.59 10,250.59

1600 1630 1632 07 01.02.03.02.06.06 Monitor 42" ea 2.00 1.00 2.00 10.25 10.25 20.50 - 1,094.78 2,189.56 2,189.56 4,379.12 3,294.59 6,589.18

1600 1630 1632 07 01.02.03.02.06.07 Jostick de mando ea 1.00 0.50 0.50 10.25 5.13 5.13 - 337.45 337.45 674.90 674.90 1,017.48 1,017.48

1600 1630 1632 07 01.02.03.02.06.08 Cámara IP-IR con PoE ea 3.00 12.40 37.20 10.25 127.10 381.30 - 550.74 1,652.22 1,101.48 3,304.44 1,779.32 5,337.96

1600 1630 1632 07 01.02.03.02.06.09 Accesorios ea 1.00 218.72 218.72 10.25 2,241.89 2,241.89 2,776.12 2,776.12 1,388.06 1,388.06 - 6,406.07 6,406.07

1600 1630 1632 07 01.02.03.02.06.10 PABX Incluye: Central PABX ea 1.00 1.00 1.00 10.25 10.25 10.25 - 1,291.68 1,291.68 2,583.36 2,583.36 3,885.29 3,885.29

1600 1630 1632 07 01.02.03.02.06.11 Teléfonos IP ea 3.00 3.00 9.00 10.25 30.75 92.25 - 252.72 758.16 505.44 1,516.32 788.91 2,366.73

1600 1630 1632 07 01.02.03.02.06.12 Accesorios ea 1.00 39.40 39.40 10.25 403.80 403.80 505.44 505.44 252.72 252.72 - 1,161.96 1,161.96

1600 1630 1632 07 01.02.03.02.06.13 LEAKY FEEDER Incluye: Estación base ea 1.00 5.00 5.00 10.25 51.25 51.25 - 10,000.00 10,000.00 20,000.00 20,000.00 30,051.25 30,051.25

1600 1630 1632 07 01.02.03.02.06.14 Accesorios ea 1.00 7.88 7.88 10.25 80.76 80.76 100.00 100.00 50.00 50.00 - 230.76 230.76

1600 1630 1632 07 01.02.03.02.06.15 Servidores sistema de control ea 2.00 20.00 40.00 10.25 205.00 410.00 - 2,500.00 5,000.00 5,000.00 10,000.00 7,705.00 15,410.00

1600 1630 1632 07 01.02.03.02.06.16 Servidor de control de acceso ea 1.00 20.00 20.00 10.25 205.00 205.00 - 3,500.00 3,500.00 7,000.00 7,000.00 10,705.00 10,705.00

1600 1630 1632 07 01.02.03.02.06.17 Tablero eléctrico instrumentación 120VAC ea 4.00 10.00 40.00 10.25 102.50 410.00 - 2,075.00 8,300.00 4,150.00 16,600.00 6,327.50 25,310.00

1600 1633 T 01.02.03.03 Rock Winder

1600 02 01.02.03.03.01 Civil

1600 1630 1633 02 01.02.03.03.01.01 - - - - - - - -

1600 1630 1633 02 01.02.03.03.01.02 - - - - - - - -

1600 03 01.02.03.03.02 Structural

1600 1630 1633 03 01.02.03.03.02.01 Excavation m3 192.99 0.22 42.46 9.50 2.09 403.34 - - 3.41 658.09 - - 5.50 1,061.43

1600 1630 1633 03 01.02.03.03.02.02 Compacting m2 51.88 1.95 101.16 9.50 18.53 961.04 - - 5.55 287.92 - - 24.08 1,248.96

1600 1630 1633 03 01.02.03.03.02.03 Blinding - 50mm - 10 mPa m3 2.59 4.20 10.89 9.50 39.90 103.50 188.50 488.95 6.78 17.59 - - 235.18 610.03

1600 1630 1633 03 01.02.03.03.02.04 Shuttering - Single Use m2 201.40 1.90 382.66 9.50 18.05 3,635.27 8.87 1,786.42 3.79 763.31 - - 30.71 6,184.99

1600 1630 1633 03 01.02.03.03.02.05 Reinforcing - 130kg/m³ - Supply & Fix t 19.22 59.00 1,134.16 9.50 560.50 10,774.55 1,394.00 26,797.00 78.47 1,508.44 - - 2,032.97 39,079.99

1600 1630 1633 03 01.02.03.03.02.06 Fix Foundation Bolts and Sleeves ea 23.00 0.10 2.30 11.00 1.10 25.30 4.01 92.23 1.60 36.80 - - 6.71 154.33

1600 1630 1633 03 01.02.03.03.02.07 Concrete - 35 MPa m3 147.87 7.98 1,180.00 9.50 75.81 11,210.02 387.26 57,264.14 12.89 1,906.04 - - 475.96 70,380.21

1600 1630 1633 03 01.02.03.03.02.08 Woodfloat m2 48.54 1.90 92.23 9.50 18.05 876.15 8.87 430.55 3.79 183.97 - - 30.71 1,490.66

1600 1630 1633 03 01.02.03.03.02.09 Back Fill m3 26.52 0.39 10.34 9.50 3.71 98.26 - - 1.11 29.44 - - 4.82 127.69

1600 1630 1633 03 01.02.03.03.02.10 Steel Structurres - platforms t 3.00 80.00 240.00 11.00 880.00 2,640.00 2,400.00 7,200.00 620.00 1,860.00 - - 3,900.00 11,700.00

1600 04 01.02.03.03.03 Mechanical

1600 1630 1633 04 01.02.03.03.03.01 Rock Winder ea 1.00 18,272.73 18,272.73 11.00 201,000.00 201,000.00 - 134,000.00 134,000.00 1,675,000.00 1,675,000.00 2,010,000.00 2,010,000.00

1600 05 01.02.03.03.04 Piping

1600 1630 1633 05 01.02.03.03.04.01 - - - - - - - -

1600 1630 1633 05 01.02.03.03.04.02 - - - - - - - -

1600 06 01.02.03.03.05 Electrical

1600 1630 1633 06 01.02.03.03.05.01 Motor Electric 600kW, 480V, Induction ea 3.00 100.00 300.00 10.25 1,025.00 3,075.00 - 19,775.00 59,325.00 104,000.00 312,000.00 124,800.00 374,400.00

1600 07 01.02.03.03.06 Instrumentation

1600 1630 1633 07 01.02.03.03.06.01 Control System & Instrumentation lot 1.00 1,756.10 1,756.10 10.25 18,000.00 18,000.00 - 12,000.00 12,000.00 150,000.00 150,000.00 180,000.00 180,000.00

1600 1630 1633 07 01.02.03.03.06.02 - - - - - - - -

1600 1634 T 01.02.03.04 Rock Winding Ropes and attacments

1600 04 01.02.03.04.01 Mechanical

1600 1630 1634 04 01.02.03.04.01.01 Wire Rope m 2,000.00 0.50 994.91 11.00 5.47 10,944.00 45.60 91,200.00 3.65 7,296.00 - 54.72 109,440.00

1600 1630 1634 04 01.02.03.04.01.02 Thimple Cappels ea 4.00 176.84 707.35 11.00 1,945.20 7,780.80 - 1,296.80 5,187.20 16,210.00 64,840.00 19,452.00 77,808.00

1600 1635 T 01.02.03.05 Skips and Service Cage

1600 03 01.02.03.05.01 Structural

1600 1630 1635 03 01.02.03.05.01.01 - - - - - - - -

1600 1630 1635 03 01.02.03.05.01.02 - - - - - - - -

1600 04 01.02.03.05.02 Mechanical

Skips

1600 1630 1635 04 01.02.03.05.02.01 Bottom dump Skip ea 3.00 1,423.18 4,269.55 11.00 15,655.00 46,965.00 - 10,436.67 31,310.00 130,458.33 391,375.00 156,550.00 469,650.00

1600 1630 1635 04 01.02.03.05.02.02 Set, guide rollers, suspensions, brackets ea 2.00 220.91 441.82 11.00 2,430.00 4,860.00 - 1,620.00 3,240.00 20,250.00 40,500.00 24,300.00 48,600.00

1600 1630 1635 04 01.02.03.05.02.03 Inspction hood, mounts to top of Skip ea 1.00 106.64 106.64 11.00 1,173.00 1,173.00 - 782.00 782.00 9,775.00 9,775.00 11,730.00 11,730.00

1600 1630 1635 04 01.02.03.05.02.04 Fixed Dump Plates and Scrolls ea 2.00 279.55 559.09 11.00 3,075.00 6,150.00 - 2,050.00 4,100.00 25,625.00 51,250.00 30,750.00 61,500.00

1600 1630 1635 04 01.02.03.05.02.05 Catch gear sufficient for two (2) Skip compartments ea 1.00 2,032.80 2,032.80 11.00 22,360.80 22,360.80 - 14,907.20 14,907.20 186,340.00 186,340.00 223,608.00 223,608.00

Service Cage

1600 1630 1635 04 01.02.03.05.02.06 Service Cage, Double Deck, 2 Guide ea 2.00 1,888.75 3,777.49 11.00 20,776.20 41,552.40 - 13,850.80 27,701.60 173,135.00 346,270.00 207,762.00 415,524.00

1600 1630 1635 04 01.02.03.05.02.07 Set, guide rollers, suspensions, brackets ea 2.00 220.91 441.82 11.00 2,430.00 4,860.00 - 1,620.00 3,240.00 20,250.00 40,500.00 24,300.00 48,600.00

1600 1630 1635 04 01.02.03.05.02.08 Inspction hood, mounts to top of Cage ea 1.00 96.27 96.27 11.00 1,059.00 1,059.00 - 706.00 706.00 8,825.00 8,825.00 10,590.00 10,590.00

1600 1630 1635 04 01.02.03.05.02.09 Drop test to prove cage safety mechanism on steel guides ea 1.00 410.95 410.95 11.00 4,520.40 4,520.40 - 3,013.60 3,013.60 37,670.00 37,670.00 45,204.00 45,204.00

1600 1630 1635 04 01.02.03.05.02.10 Catch gear sufficient for one (1) Cage compartment ea 1.00 1,619.02 1,619.02 11.00 17,809.20 17,809.20 - 11,872.80 11,872.80 148,410.00 148,410.00 178,092.00 178,092.00

Counterweight

1600 1630 1635 04 01.02.03.05.02.11 Counterweight, bail and slab type ea 1.00 636.93 636.93 11.00 7,006.20 7,006.20 - 4,670.80 4,670.80 58,385.00 58,385.00 70,062.00 70,062.00

1600 1630 1635 04 01.02.03.05.02.12 Set, guide rollers, brackets ea 1.00 146.07 146.07 11.00 1,606.80 1,606.80 - 1,071.20 1,071.20 13,390.00 13,390.00 16,068.00 16,068.00

1600 1630 1635 04 01.02.03.05.02.13 Inspection hood for installation on top of counterweight ea 1.00 83.45 83.45 11.00 918.00 918.00 - 612.00 612.00 7,650.00 7,650.00 9,180.00 9,180.00

1600 1630 1635 04 01.02.03.05.02.14 Catch gear sufficient for one (1) Cage compartment ea 1.00 1,619.02 1,619.02 11.00 17,809.20 17,809.20 - 11,872.80 11,872.80 148,410.00 148,410.00 178,092.00 178,092.00

1600 1636 T 01.02.03.06 Man Material Winder

1600 02 01.02.03.06.01 Civil

1600 1630 1636 02 01.02.03.03.06.01 - - - - - - - -

1600 1630 1636 02 01.02.03.03.06.02 - - - - - - - -

1600 03 01.02.03.06.02 Structural

1600 1630 1636 03 01.02.03.06.02.01 Excavation m3 192.99 0.22 42.46 9.50 2.09 403.34 - - 3.41 658.09 - - 5.50 1,061.43

1600 1630 1636 03 01.02.03.06.02.02 Compacting m2 51.88 1.95 101.16 9.50 18.53 961.04 - - 5.55 287.92 - - 24.08 1,248.96

1600 1630 1636 03 01.02.03.06.02.03 Blinding - 50mm - 10 mPa m3 2.59 4.20 10.89 9.50 39.90 103.50 188.50 488.95 6.78 17.59 - - 235.18 610.03

Page 38: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

Prepared by: Julio Villanueva

Date: 27/01/2014

Review: B

Total

# WBS L2# WBS

L3

# WBS

L4Discip. Item Description UoM Quant Unit Cost

Unit Mhr Total Mhr Rate Unit Total Unit Total Unit Total Unit Total (US$) (US$)

CAPEX

SCOPING STUDY

SHAFT DESIGN - CHUCAPACA

209050-00014

Total Cost

Document Nr:

Project:

Project Nr:

Labour Manhour (mh) Labour Cost (US$) Material Cost (US$) Const Eqpt (US$) Process Eqpt (US$)

1600 1630 1636 03 01.02.03.06.02.04 Shuttering - Single Use m2 201.40 1.90 382.66 9.50 18.05 3,635.27 8.87 1,786.42 3.79 763.31 - - 30.71 6,184.99

1600 1630 1636 03 01.02.03.06.02.05 Reinforcing - 130kg/m³ - Supply & Fix t 19.22 59.00 1,134.16 9.50 560.50 10,774.55 1,394.00 26,797.00 78.47 1,508.44 - - 2,032.97 39,079.99

1600 1630 1636 03 01.02.03.06.02.06 Fix Foundation Bolts and Sleeves ea 23.00 0.10 2.30 11.00 1.10 25.30 4.01 92.23 1.60 36.80 - - 6.71 154.33

1600 1630 1636 03 01.02.03.06.02.07 Concrete - 35 MPa m3 147.87 7.98 1,180.00 9.50 75.81 11,210.02 387.26 57,264.14 12.89 1,906.04 - - 475.96 70,380.21

1600 1630 1636 03 01.02.03.06.02.08 Woodfloat m2 48.54 1.90 92.23 9.50 18.05 876.15 8.87 430.55 3.79 183.97 - - 30.71 1,490.66

1600 1630 1636 03 01.02.03.06.02.09 Back Fill m3 26.52 0.39 10.34 9.50 3.71 98.26 - - 1.11 29.44 - - 4.82 127.69

1600 1630 1636 03 01.02.03.06.02.10 Steel Structurres - platforms t 3.00 80.00 240.00 11.00 880.00 2,640.00 2,400.00 7,200.00 620.00 1,860.00 - - 3,900.00 11,700.00

1600 04 01.02.03.06.03 Mechanical

1600 1630 1636 04 01.02.03.06.03.01 Man Material Winder ea 1.00 17,400.00 17,400.00 11.00 191,400.00 191,400.00 - 127,600.00 127,600.00 1,595,000.00 1,595,000.00 1,914,000.00 1,914,000.00

1600 05 01.02.03.06.04 Piping

1600 1630 1636 05 01.02.03.06.04.01 - - - - - - - -

1600 1630 1636 05 01.02.03.06.04.02 - - - - - - - -

1600 06 01.02.03.06.05 Electrical

1600 1630 1636 06 01.02.03.06.05.01 Motor Electric 600kW, 480V, Induction ea 1.00 100.00 100.00 10.25 1,025.00 1,025.00 - 19,775.00 19,775.00 104,000.00 104,000.00 124,800.00 124,800.00

1600 07 01.02.03.06.06 Instrumentation

1600 1630 1636 07 01.02.03.06.06.01 Control System & Instrumentation lot 1.00 1,756.10 1,756.10 10.25 18,000.00 18,000.00 - 12,000.00 12,000.00 150,000.00 150,000.00 180,000.00 180,000.00

1600 1630 1636 07 01.02.03.06.06.02 - - - - - - - -

1600 1637 T 01.02.03.07 Man Material Winding Ropes and attacments

1600 04 01.02.03.07.01 Mechanical

1600 1630 1637 04 01.02.03.07.01.01 Wire Rope m 2,000.00 0.50 994.91 11.00 5.47 10,944.00 45.60 91,200.00 3.65 7,296.00 - 54.72 109,440.00

1600 1630 1637 04 01.02.03.07.01.02 Thimple Cappels ea 4.00 176.84 707.35 11.00 1,945.20 7,780.80 - 1,296.80 5,187.20 16,210.00 64,840.00 19,452.00 77,808.00

1600 1638 T 01.02.03.08 Conveyances and Inspection Baskets

1600 03 01.02.03.08.01 Structural

1600 1630 1638 03 01.02.03.08.01.01 - - - - - - - -

1600 1630 1638 03 01.02.03.08.01.02 - - - - - - - -

1600 1640 T 01.02.04 Reef and Waste Storage & Conveying

1600 1641 T 01.02.04.01 Waste Bin

1600 03 01.02.04.01.01 Structural

1600 1640 1641 03 01.02.04.01.01.01 - - - - - - - -

1600 1640 1641 03 01.02.04.01.01.02 - - - - - - - -

1600 04 01.02.04.01.02 Mechanical

1600 1640 1641 04 01.02.04.01.02.01 Diverter Chute ea 1.00 272.73 272.73 11.00 3,000.00 3,000.00 - 2,000.00 2,000.00 25,000.00 25,000.00 30,000.00 30,000.00

1600 1640 1641 04 01.02.04.01.02.02 Discharge Chute ea 2.00 75.87 151.75 11.00 834.60 1,669.20 - 556.40 1,112.80 6,955.00 13,910.00 8,346.00 16,692.00

1600 1642 T 01.02.04.02 Conveyor

1600 04 01.02.04.02.01 Mechanical

1600 1640 1642 04 01.02.04.02.01.01 Belt Conveyor 1 m 20.00 35.00 700.00 11.00 385.00 7,700.00 - 615.00 12,300.00 5,000.00 100,000.00 6,000.00 120,000.00

1600 1640 1642 04 01.02.04.02.01.02 Belt Conveyor 2 m 25.00 35.00 875.00 11.00 385.00 9,625.00 - 615.00 15,375.00 5,000.00 125,000.00 6,000.00 150,000.00

1600 1640 1642 04 01.02.04.02.01.03 Belt Conveyor 3 m 65.00 35.00 2,275.00 11.00 385.00 25,025.00 - 615.00 39,975.00 5,000.00 325,000.00 6,000.00 390,000.00

1600 1643 T 01.02.04.03 Reef Stock pile

1600 02 01.02.04.03.01 Civil

1600 1640 1643 02 01.02.04.03.01.01 - - - - - - - -

1600 1640 1643 02 01.02.04.03.01.02 - - - - - - - -

1600 1660 T 01.02.06 Electrical Distribution

1600 1661 T 01.02.06.01 Cable Racking and Trenches

1600 02 01.02.06.01.01 Civil

1600 1660 1661 02 01.02.06.01.01.01 - - - - - - - -

1600 1660 1661 02 01.02.06.01.01.02 - - - - - - - -

1600 03 01.02.06.01.02 Structural

1600 1660 1661 03 01.02.06.01.02.01 - - - - - - - -

1600 1660 1661 03 01.02.06.01.02.02 - - - - - - - -

1600 1662 T 01.02.06.02 Electrical cables

1600 06 01.02.06.02.01 Electrical

1600 1660 1662 06 01.02.06.02.01.01 Electrical cables, medium voltage 13.8 kV m 80.00 0.30 24.00 10.25 3.08 246.00 135.00 10,800.00 23.93 1,914.00 - 162.00 12,960.00

1600 1660 1662 06 01.02.06.02.01.02 Electrical cables, medium voltage 4.16 kV m 800.00 0.30 240.00 10.25 3.08 2,460.00 121.00 96,800.00 21.13 16,900.00 - 145.20 116,160.00

1600 1660 1662 06 01.02.06.02.01.03 Electrical cables, low voltage 480V and 230V lot 1.00 1,073.17 1,073.17 10.25 11,000.00 11,000.00 110,000.00 110,000.00 11,000.00 11,000.00 - 132,000.00 132,000.00

1600 1670 T 01.02.07 Substations

1600 1671 T 01.02.07.01 HT & LV Substation

1600 02 01.02.07.01.01 Civil

1600 1670 1671 02 01.02.07.01.01.01 - - - - - - - -

1600 1670 1671 02 01.02.07.01.01.02 - - - - - - - -

1600 03 01.02.07.01.02 Structural

1600 1670 1671 03 01.02.07.01.02.01 Substations - Civil Woks m2 160.00 50.53 8,084.21 9.50 480.00 76,800.00 480.00 76,800.00 240.00 38,400.00 - 1,200.00 192,000.00

1600 1670 1671 03 01.02.07.01.02.02 - - - - - - - -

1600 06 01.02.07.01.03 Electrical

1600 1670 1671 06 01.02.07.01.03.01 Switchgear SF6, 630A, 13.8 kV, 60Hz, 25 kA, 7 feeders ea 1.00 25.00 25.00 10.25 256.25 256.25 - 58,543.75 58,543.75 294,000.00 294,000.00 352,800.00 352,800.00

1600 1670 1671 06 01.02.07.01.03.02 Switchgear SF6, 630A, 4.16 kV, 60Hz, 25 kA, 3 feeders ea 1.00 25.00 25.00 10.25 256.25 256.25 - 23,743.75 23,743.75 120,000.00 120,000.00 144,000.00 144,000.00

Page 39: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

Prepared by: Julio Villanueva

Date: 27/01/2014

Review: B

Total

# WBS L2# WBS

L3

# WBS

L4Discip. Item Description UoM Quant Unit Cost

Unit Mhr Total Mhr Rate Unit Total Unit Total Unit Total Unit Total (US$) (US$)

CAPEX

SCOPING STUDY

SHAFT DESIGN - CHUCAPACA

209050-00014

Total Cost

Document Nr:

Project:

Project Nr:

Labour Manhour (mh) Labour Cost (US$) Material Cost (US$) Const Eqpt (US$) Process Eqpt (US$)

1600 1670 1671 06 01.02.07.01.03.03 Isolation Distribution Transformer 700 kVA, Dyn5, 13.8/0.48kV ea 3.00 18.00 54.00 10.25 184.50 553.50 - 4,815.50 14,446.50 25,000.00 75,000.00 30,000.00 90,000.00

1600 1670 1671 06 01.02.07.01.03.04 Variable Frecuency Drive, AFE, 600 kW, 60Hz ea 3.00 400.00 1,200.00 10.25 4,100.00 12,300.00 - 21,900.00 65,700.00 130,000.00 390,000.00 156,000.00 468,000.00

1600 1670 1671 06 01.02.07.01.03.05 Distribution Transformer 800 kVA 13.8/4.16 kV, Dyn5 ea 1.00 18.00 18.00 10.25 184.50 184.50 - 5,815.50 5,815.50 30,000.00 30,000.00 36,000.00 36,000.00

1600 1670 1671 06 01.02.07.01.03.06 Distribution Transformer 750 kVA 13.8/0.48 kV, Dyn5 ea 1.00 18.00 18.00 10.25 184.50 184.50 - 5,415.50 5,415.50 28,000.00 28,000.00 33,600.00 33,600.00

1600 1670 1671 06 01.02.07.01.03.07 Switchboard 480V, 25KA, Main breaker 1000A, Nema 4 ea 1.00 25.00 25.00 10.25 256.25 256.25 - 4,743.75 4,743.75 25,000.00 25,000.00 30,000.00 30,000.00

1600 1670 1671 06 01.02.07.01.03.08 Panelboard 230V, 25kA, 60Hz ea 2.00 31.20 62.40 10.25 319.80 639.60 - 980.20 1,960.40 6,500.00 13,000.00 7,800.00 15,600.00

1600 1670 1671 06 01.02.07.01.03.09 Charging and bank battery, 125Vdc, ea 1.00 8.00 8.00 10.25 82.00 82.00 - 758.00 758.00 4,200.00 4,200.00 5,040.00 5,040.00

1600 1670 1671 06 01.02.07.01.03.10 Bulk Materials (Lighting, welding socket, earthing, trays,etc) lot 1.00 204.88 204.88 10.25 2,100.00 2,100.00 21,000.00 21,000.00 2,100.00 2,100.00 - 25,200.00 25,200.00

1600 1680 T 01.02.08 Lamp & Crush Ontel

1600 1681 T 01.02.08.01 Lamp Room

1600 03 01.02.08.01.01 Structural

1600 1680 1681 03 01.02.08.01.01.01 Concrete Structures f'c=280 kg/cm2 m3 57.09 7.98 455.56 9.50 75.81 4,327.84 387.26 22,107.90 12.89 735.86 - - 475.96 27,171.60

1600 1680 1681 03 01.02.08.01.01.02 Steel Structures t 3.00 80.00 240.00 11.00 880.00 2,640.00 2,400.00 7,200.00 620.00 1,860.00 - - 3,900.00 11,700.00

1600 1680 1681 03 01.02.08.01.01.03 brick wall m2 250.00 10.00 2,500.00 9.50 95.00 23,750.00 184.50 46,125.00 22.00 5,500.00 - - 301.50 75,375.00

1600 1680 1681 03 01.02.08.01.01.04 Excavation m3 87.82 0.22 19.32 9.50 2.09 183.54 - - 3.41 299.47 - - 5.50 483.01

1600 1680 1681 03 01.02.08.01.01.05 Blinding - 50mm - 10 mPa m3 1.20 4.20 5.04 9.50 39.90 47.88 188.50 226.20 6.78 8.14 - - 235.18 282.22

1600 1680 1681 03 01.02.08.01.01.06 Back Fill m3 84.00 0.39 32.76 9.50 3.71 311.22 - - 1.11 93.24 - - 4.82 404.46

1600 1680 1681 03 01.02.08.01.01.07 waste m3 84.00 0.10 8.40 9.50 0.95 79.80 - 1.79 150.36 - 2.74 230.16

1600 1680 1681 03 01.02.08.01.01.08 formwork m2 62.00 1.90 117.80 9.50 18.05 1,119.10 8.87 549.94 3.79 234.98 - - 30.71 1,904.02

1600 1680 1681 03 01.02.08.01.01.09 Steel Structures t 3.00 80.00 240.00 11.00 880.00 2,640.00 2,400.00 7,200.00 620.00 1,860.00 - - 3,900.00 11,700.00

1600 1682 T 01.02.08.02 Lamps and Lamp chargers

1600 06 01.02.08.02.01 Electrical

1600 1680 1682 06 01.02.08.02.01.01 Transformer 100kVA, 480/230V, Dyn5 ea 1.00 18.00 18.00 10.25 184.50 184.50 - 1,815.50 1,815.50 10,000.00 10,000.00 12,000.00 12,000.00

1600 1680 1682 06 01.02.08.02.01.02 Panelboard 480V, 25kA, 60Hz, 150A ea 1.00 31.20 31.20 10.25 319.80 319.80 - 2,180.20 2,180.20 12,500.00 12,500.00 15,000.00 15,000.00

1600 1680 1682 06 01.02.08.02.01.03 Panelboard 230V, 25kA, 60Hz, 60A ea 1.00 31.20 31.20 10.25 319.80 319.80 - 980.20 980.20 6,500.00 6,500.00 7,800.00 7,800.00

1600 1680 1682 06 01.02.08.02.01.04 Bulk Materials (Lighting, small power, earthing, trays,etc) lot 1.00 92.68 92.68 10.25 950.00 950.00 9,500.00 9,500.00 950.00 950.00 - 11,400.00 11,400.00

1600 1683 T 01.02.08.03 Crush

1600 02 01.02.08.03.01 Civil

1600 1680 1683 02 01.02.08.03.01.01 - - - - - - - -

1600 1680 1683 02 01.02.08.03.01.02 - - - - - - - -

1600 03 01.02.08.03.02 Structural

1600 1680 1683 03 01.02.08.03.02.01 - - - - - - - -

1600 1680 1683 03 01.02.08.03.02.02 - - - - - - - -

1600 06 01.02.08.03.03 Electrical

1600 1680 1683 06 01.02.08.03.03.01 Panelboard 230V, 25kA, 60Hz, 60A ea 1.00 31.20 31.20 10.25 319.80 319.80 - 980.20 980.20 6,500.00 6,500.00 7,800.00 7,800.00

1600 07 01.02.08.03.04 Instrumentation

1600 1680 1683 07 01.02.08.03.04.01 Control de acceso incluye: Detector de tarjetas ea 1.00 3.50 3.50 10.25 35.88 35.88 - 100.00 100.00 200.00 200.00 335.88 335.88

1600 1680 1683 07 01.02.08.03.04.02 Accesorios ea 1.00 3.94 3.94 10.25 40.38 40.38 50.00 50.00 25.00 25.00 - 115.38 115.38

1600 1680 1683 07 01.02.08.03.04.03 Sistema de telececomunicaciones incluye: Gabinete de telecomunicaciones pedestal ea 1.00 10.00 10.00 10.25 102.50 102.50 - 522.64 522.64 1,045.27 1,045.27 1,670.41 1,670.41

1600 1680 1683 07 01.02.08.03.04.04 switch de telecomunicaciones ea 1.00 3.70 3.70 10.25 37.93 37.93 - 1,394.88 1,394.88 2,789.76 2,789.76 4,222.57 4,222.57

1600 1680 1683 07 01.02.08.03.04.05 Transceiver SFP ea 2.00 3.00 6.00 10.25 30.75 61.50 - 352.40 704.80 704.80 1,409.60 1,087.95 2,175.90

1600 1680 1683 07 01.02.08.03.04.06 patch panel para fibra óptica ea 1.00 2.50 2.50 10.25 25.63 25.63 - 214.51 214.51 429.01 429.01 669.14 669.14

1600 1680 1683 07 01.02.08.03.04.07 Accesorios ea 1.00 78.79 78.79 10.25 807.60 807.60 1,000.00 1,000.00 500.00 500.00 - 2,307.60 2,307.60

1600 1680 1683 07 01.02.08.03.04.08 Tablero eléctrico instrumentación 120VAC ea 1.00 10.00 10.00 10.25 102.50 102.50 - 2,075.00 2,075.00 4,150.00 4,150.00 6,327.50 6,327.50

1700 T 01.03 Shafts - Mining & Engineering

1700 1710 T 01.03.01 General

1700 1711 T 01.03.01.01 Preliminary Works

1700 01 01.03.01.01.01 Mining

1700 1710 1711 01 01.03.01.01.01.01 Mobilization and Demobilization lot 1.00 - - - - 143,000.00 143,000.00 - 143,000.00 143,000.00

1700 1710 1711 01 01.03.01.01.01.02 Mobilization and Demobilization(Sinking Winder 800 HP) lot 1.00 - - - - 240,000.00 240,000.00 - 240,000.00 240,000.00

1700 1720 T 01.03.02 Vertical Shaft

1700 1721 T 01.03.02.01 Activity 01

1700 01 01.03.02.01.01 Mining

Civil Works

1700 1720 1721 01 01.03.02.01.01.01 Shaft Collar Foundation (Lv 4897) lot 1.00 1,688.31 1,688.31 11.00 18,571.43 18,571.43 - 46,428.57 46,428.57 - 65,000.00 65,000.00

1700 1720 1721 01 01.03.02.01.01.02 Ore Bins Foundations(Lv 4897) lot 1.00 259.74 259.74 11.00 2,857.14 2,857.14 - 7,142.86 7,142.86 - 10,000.00 10,000.00

1700 1720 1721 01 01.03.02.01.01.03 Galloway winder and Sinking Winder Foundations(Lv 4897) lot 1.00 129.87 129.87 11.00 1,428.57 1,428.57 - 3,571.43 3,571.43 - 5,000.00 5,000.00

1700 1720 1721 01 01.03.02.01.01.04 Production Winder Foundation(Lv 4897) lot 1.00 837.66 837.66 11.00 9,214.29 9,214.29 - 23,035.71 23,035.71 - 32,250.00 32,250.00

1700 1720 1721 01 01.03.02.01.01.05 Service Winder Foundation(Lv 4897) lot 1.00 558.44 558.44 11.00 6,142.86 6,142.86 - 15,357.14 15,357.14 - 21,500.00 21,500.00

1700 1720 1721 01 01.03.02.01.01.06 Bin walls Foundation(Lv 4482) lot 1.00 389.61 389.61 11.00 4,285.71 4,285.71 - 10,714.29 10,714.29 - 15,000.00 15,000.00

1700 1720 1721 01 01.03.02.01.01.07 Sub Station Foundation (Lv 4750, 4700, 4650, 4600, 4522, 4482, 4442)lot 7.00 44.16 309.09 11.00 485.71 3,400.00 - 1,214.29 8,500.00 - 1,700.00 11,900.00

Building for Winder

1700 1720 1721 01 01.03.02.01.01.08 Walls and Slabs Foundations (excavation and concrete) lot 1.00 290.91 290.91 11.00 3,200.00 3,200.00 - 8,000.00 8,000.00 - 11,200.00 11,200.00

1700 1720 1721 01 01.03.02.01.01.09 Steel structure (supply, pre assembly and assembly) lot 1.00 6,422.08 6,422.08 11.00 70,642.86 70,642.86 - 176,607.14 176,607.14 - 247,250.00 247,250.00

1700 1720 1721 01 01.03.02.01.01.10 Overhead Travelling Crane (supply, pre assembly and assembly) lot 1.00 1,974.03 1,974.03 11.00 21,714.29 21,714.29 - 54,285.71 54,285.71 - 76,000.00 76,000.00

1700 1720 1721 01 01.03.02.01.01.11 Electrical System (Lighting, power plugs, earthing) lot 1.00 502.60 502.60 11.00 5,528.57 5,528.57 - 13,821.43 13,821.43 - 19,350.00 19,350.00

Mounting structure of constructive system of Shaft

1700 1720 1721 01 01.03.02.01.01.12 Sinking Shaft Winder Assembly(Lv 4897) lot 1.00 3,896.10 3,896.10 11.00 42,857.14 42,857.14 - 107,142.86 107,142.86 - 150,000.00 150,000.00

Page 40: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

Prepared by: Julio Villanueva

Date: 27/01/2014

Review: B

Total

# WBS L2# WBS

L3

# WBS

L4Discip. Item Description UoM Quant Unit Cost

Unit Mhr Total Mhr Rate Unit Total Unit Total Unit Total Unit Total (US$) (US$)

CAPEX

SCOPING STUDY

SHAFT DESIGN - CHUCAPACA

209050-00014

Total Cost

Document Nr:

Project:

Project Nr:

Labour Manhour (mh) Labour Cost (US$) Material Cost (US$) Const Eqpt (US$) Process Eqpt (US$)

1700 1720 1721 01 01.03.02.01.01.13 Sheave and Accesories Assembly(Lv 4897) lot 1.00 488.08 488.08 11.00 5,368.86 5,368.86 - 13,422.14 13,422.14 - 18,791.00 18,791.00

1700 1720 1721 01 01.03.02.01.01.14 Galloway Winders Assembly(3) lot 1.00 587.01 587.01 11.00 6,457.14 6,457.14 - 16,142.86 16,142.86 - 22,600.00 22,600.00

1700 1720 1721 01 01.03.02.01.01.15 Galloway Assembly(3) lot 1.00 587.01 587.01 11.00 6,457.14 6,457.14 - 16,142.86 16,142.86 - 22,600.00 22,600.00

1700 1720 1721 01 01.03.02.01.01.16 Cryderman Assembly lot 1.00 298.70 298.70 11.00 3,285.71 3,285.71 - 8,214.29 8,214.29 - 11,500.00 11,500.00

Preliminary Facilities Construction Shaft

1700 1720 1721 01 01.03.02.01.01.17 Safety Door lot 1.00 254.55 254.55 11.00 2,800.00 2,800.00 - 7,000.00 7,000.00 - 9,800.00 9,800.00

1700 1720 1721 01 01.03.02.01.01.18 Buckets (2.4 m3) lot 3.00 259.74 779.22 11.00 2,857.14 8,571.43 - 7,142.86 21,428.57 - 10,000.00 30,000.00

1700 1720 1721 01 01.03.02.01.01.19 Formwork lot 2.00 571.43 1,142.86 11.00 6,285.71 12,571.43 - 15,714.29 31,428.57 - 22,000.00 44,000.00

1700 1720 1721 01 01.03.02.01.01.20 Sinking Winder( 800 HP) month 8.53 1,038.96 8,863.64 11.00 11,428.57 97,500.00 - 28,571.43 243,750.00 - 40,000.00 341,250.00

1700 1720 1721 01 01.03.02.01.01.21 Sinking Winder sheaves lot 1.00 519.48 519.48 11.00 5,714.29 5,714.29 - 14,285.71 14,285.71 - 20,000.00 20,000.00

1700 1720 1721 01 01.03.02.01.01.22 Sinking Winder ropes lot 1.00 584.42 584.42 11.00 6,428.57 6,428.57 - 16,071.43 16,071.43 - 22,500.00 22,500.00

1700 1720 1721 01 01.03.02.01.01.23 Galloway Winders (3) lot 3.00 2,259.74 6,779.22 11.00 24,857.14 74,571.43 - 62,142.86 186,428.57 - 87,000.00 261,000.00

1700 1720 1721 01 01.03.02.01.01.24 Spares kit (Sinking winder, and Galloway winders) lot 1.00 1,558.44 1,558.44 11.00 17,142.86 17,142.86 - 42,857.14 42,857.14 - 60,000.00 60,000.00

1700 1720 1721 01 01.03.02.01.01.25 Galloway lot 1.00 1,688.31 1,688.31 11.00 18,571.43 18,571.43 - 46,428.57 46,428.57 - 65,000.00 65,000.00

1700 1720 1721 01 01.03.02.01.01.26 Cryderman lot 1.00 2,857.14 2,857.14 11.00 31,428.57 31,428.57 - 78,571.43 78,571.43 - 110,000.00 110,000.00

1700 1720 1721 01 01.03.02.01.01.27 Galloway Accesories lot 1.00 2,571.43 2,571.43 11.00 28,285.71 28,285.71 - 70,714.29 70,714.29 - 99,000.00 99,000.00

1700 1720 1721 01 01.03.02.01.01.28 System discharge bucket depth lot 1.00 636.36 636.36 11.00 7,000.00 7,000.00 - 17,500.00 17,500.00 - 24,500.00 24,500.00

1700 1720 1721 01 01.03.02.01.01.29 Shaft Bottom pumps (50 HP) lot 2.00 155.84 311.69 11.00 1,714.29 3,428.57 - 4,285.71 8,571.43 - 6,000.00 12,000.00

1700 1720 1721 01 01.03.02.01.01.30 Electrical Equipment and accesories lot 1.00 311.69 311.69 11.00 3,428.57 3,428.57 - 8,571.43 8,571.43 - 12,000.00 12,000.00

1700 1720 1721 01 01.03.02.01.01.31 Conic Plug ( d = 2.4 m) lot 1.00 259.74 259.74 11.00 2,857.14 2,857.14 - 7,142.86 7,142.86 - 10,000.00 10,000.00

1700 1720 1721 01 01.03.02.01.01.32 Workshops installation (concrete, mechanical, electrical and cellar) lot 1.00 122.03 122.03 11.00 1,342.29 1,342.29 - 3,355.71 3,355.71 - 4,698.00 4,698.00

Excavation Shaft

1700 1720 1721 01 01.03.02.01.01.33 Shaft Sinking - Rock Tipe III y IV ( Lv 4897/4442) m 455.00 58.44 26,590.91 11.00 642.86 292,500.00 - 1,607.14 731,250.00 - 2,250.00 1,023,750.00

1700 1720 1721 01 01.03.02.01.01.34 Shaft Concrete Resurfacing (Lv 4897/4442) m 455.00 37.34 16,988.64 11.00 410.71 186,875.00 - 1,026.79 467,187.50 - 1,437.50 654,062.50

1700 1720 1721 01 01.03.02.01.01.35 Steel Structures installation September (Lv 4897/4442) m 455.00 34.90 15,880.68 11.00 383.93 174,687.50 - 959.82 436,718.75 - 1,343.75 611,406.25

1700 1720 1721 01 01.03.02.01.01.36 Galloway removal lot 1.00 36.61 36.61 11.00 402.69 402.69 - 1,006.71 1,006.71 - 1,409.40 1,409.40

1700 1720 1721 01 01.03.02.01.01.37 Pocket Excavation Lv-4482 m3 1,446.91 2.73 3,946.12 11.00 30.00 43,407.36 - 75.00 108,518.40 - 105.00 151,925.76

Sustaining Shaft

1700 1720 1721 01 01.03.02.01.01.38 Hydrabolt Installation 2.1 m ea 5,460.00 0.81 4,424.73 11.00 8.91 48,672.00 - 22.29 121,680.00 - 31.20 170,352.00

1700 1720 1721 01 01.03.02.01.01.39 Cable Bolting 8´ m 1,200.00 1.04 1,246.75 11.00 11.43 13,714.29 - 28.57 34,285.71 - 40.00 48,000.00

1700 1720 1721 01 01.03.02.01.01.40 Welded Mesh installation 4´´x4´´ #8 m2 11,206.69 0.49 5,530.57 11.00 5.43 60,836.31 - 13.57 152,090.78 - 19.00 212,927.10

1700 1720 1721 01 01.03.02.01.01.41 Shotcrete 50mm width @ 25 Mpa (with fiber) m2 3,735.56 1.45 5,433.55 11.00 16.00 59,769.01 - 40.00 149,422.52 - 56.00 209,191.53

1700 1720 1721 01 01.03.02.01.01.42 Shotcrete 100mm width @ 25 Mpa (with fiber) m2 - 1.90 - 11.00 20.91 - - 52.29 - - 73.20 -

1700 1720 1721 01 01.03.02.01.01.43 Shaft Supplies lot 1.00 4,692.09 4,692.09 11.00 51,613.03 51,613.03 - 129,032.57 129,032.57 - 180,645.60 180,645.60

Concreto

1700 1720 1721 01 01.03.02.01.01.44 Suministros Pique anillo de concreto (455 m) m3 2,470.05 12.36 30,536.18 11.00 135.99 335,898.00 - 339.97 839,745.00 - 475.96 1,175,643.00

Shaft Ventilation

1700 1720 1721 01 01.03.02.01.01.45 Ventilation (Lv-1000, 100 HP @ 50K cfm) ea 1.00 1,558.44 1,558.44 11.00 17,142.86 17,142.86 - 42,857.14 42,857.14 - 60,000.00 60,000.00

1700 02 01.03.02.01.02 Civil

1700 1720 1721 02 01.03.02.01.02.01 - - - - - - - -

1700 1720 1721 02 01.03.02.01.02.02 - - - - - - - -

1700 03 01.03.02.01.03 Structural

1700 1720 1721 03 01.03.02.01.03.01 Concrete Structures include in mining data - - - - - - - -

1700 1720 1721 03 01.03.02.01.03.02 Steel Structures t 219.86 80.00 17,588.67 11.00 880.00 193,475.33 2,400.00 527,660.00 620.00 136,312.17 - - 3,900.00 857,447.50

1700 04 01.03.02.01.04 Mechanical

1700 1720 1721 04 01.03.02.01.04.01 - - - - - - - -

1700 1720 1721 04 01.03.02.01.04.02 - - - - - - - -

1700 05 01.03.02.01.05 Piping

Compressed air system

1700 1720 1721 05 01.03.02.01.05.01 Pipe Ø6", Sch40, Carbon Steel, mechanical couplings each 6m (includes valves, accesories and painting)m 455.00 10.00 4,550.00 11.00 110.00 50,050.00 45.00 20,475.00 56.00 25,480.00 - 211.00 96,005.00

1700 1720 1721 05 01.03.02.01.05.02 Steel structures for piping supports (includes construction, painting and installation)kg 2,000.00 0.08 160.00 11.00 0.88 1,760.00 2.50 5,000.00 1.12 2,240.00 - 4.50 9,000.00

Water service system

1700 1720 1721 05 01.03.02.01.05.03 Pipe Ø6", Sch40, Carbon Steel, mechanical couplings each 6m (includes valves, accesories and painting)m 455.00 10.00 4,550.00 11.00 110.00 50,050.00 45.00 20,475.00 56.00 25,480.00 - 211.00 96,005.00

1700 1720 1721 05 01.03.02.01.05.04 Steel structures for piping supports (includes construction, painting and installation)kg 2,000.00 0.08 160.00 11.00 0.88 1,760.00 2.50 5,000.00 1.12 2,240.00 - 4.50 9,000.00

Dewatering Pipe

1700 1720 1721 05 01.03.02.01.05.05 Pipe Ø4", Sch80, Carbon Steel, mechanical couplings each 6m (includes valves, accesories and painting)m 250.00 4.50 1,125.00 11.00 49.50 12,375.00 45.00 11,250.00 46.00 11,500.00 - 140.50 35,125.00

1700 1720 1721 05 01.03.02.01.05.06 Steel structures for piping supports (includes construction, painting and installation)kg 900.00 0.08 72.00 11.00 0.88 792.00 2.50 2,250.00 1.12 1,008.00 - 4.50 4,050.00

1700 06 01.03.02.01.06 Electrical

1700 1720 1721 06 01.03.02.01.06.01 Bulk Materials (Clamp fo cables, trays,etc) lot 1.00 24.39 24.39 10.25 250.00 250.00 2,500.00 2,500.00 250.00 250.00 - 3,000.00 3,000.00

1700 07 01.03.02.01.07 Instrumentation

1700 1720 1721 07 01.03.02.01.07.01 - - - - - - - -

1700 1720 1721 07 01.03.02.01.07.02 - - - - - - - -

1700 1730 T 01.03.03 Station 01

1700 1731 T 01.03.03.01 Activity 01

1700 01 01.03.03.01.01 Mining

1700 1730 1731 01 01.03.03.01.01.01 Estation 4750 lot 1.00 3,896.10 3,896.10 11.00 42,857.14 42,857.14 - 107,142.86 107,142.86 - 150,000.00 150,000.00

1700 1730 1731 01 01.03.03.01.01.02 - - - - - - - -

1700 02 01.03.03.01.02 Civil

1700 1730 1731 02 01.03.03.01.02.01 - - - - - - - -

1700 1730 1731 02 01.03.03.01.02.02 - - - - - - - -

1700 03 01.03.03.01.03 Structural

1700 1730 1731 03 01.03.03.01.03.01 Concrete Structures f'c=280 kg/cm2 m3 31.00 7.98 247.38 9.50 75.81 2,350.11 387.26 12,005.06 12.89 399.59 - - 475.96 14,754.76

1700 1730 1731 03 01.03.03.01.03.02 Steel Structures t 8.28 80.00 662.00 11.00 880.00 7,282.00 2,400.00 19,860.00 620.00 5,130.50 - - 3,900.00 32,272.50

1700 04 01.03.03.01.04 Mechanical

1700 1730 1731 04 01.03.03.01.04.01 - - - - - - - -

Page 41: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

Prepared by: Julio Villanueva

Date: 27/01/2014

Review: B

Total

# WBS L2# WBS

L3

# WBS

L4Discip. Item Description UoM Quant Unit Cost

Unit Mhr Total Mhr Rate Unit Total Unit Total Unit Total Unit Total (US$) (US$)

CAPEX

SCOPING STUDY

SHAFT DESIGN - CHUCAPACA

209050-00014

Total Cost

Document Nr:

Project:

Project Nr:

Labour Manhour (mh) Labour Cost (US$) Material Cost (US$) Const Eqpt (US$) Process Eqpt (US$)

1700 1730 1731 04 01.03.03.01.04.02 - - - - - - - -

1700 05 01.03.03.01.05 Piping

Pressure reduction station for water service

1700 1730 1731 05 01.03.03.01.05.01 Pressure reduction valve Ø3", Carbon steel, flanged 300 Class ea 2.00 5.00 10.00 11.00 55.00 110.00 2,000.00 4,000.00 345.00 690.00 - 2,400.00 4,800.00

1700 1730 1731 05 01.03.03.01.05.02 Safety valve Ø2"xØ3", Carbon steel, flanged ea 1.00 4.50 4.50 11.00 49.50 49.50 2,500.00 2,500.00 450.50 450.50 - 3,000.00 3,000.00

1700 1730 1731 05 01.03.03.01.05.03 Pressure gauge, Ø1/2" connection, Dial Ø4", Scale 0-200PSIG ea 2.00 2.50 5.00 11.00 27.50 55.00 150.00 300.00 2.50 5.00 - 180.00 360.00

1700 1730 1731 05 01.03.03.01.05.04 Pipe Ø3" Sch 80, flanged Class 300 (include accesorioes) m 2.00 2.50 5.00 11.00 27.50 55.00 25.00 50.00 31.00 62.00 - 83.50 167.00

1700 1730 1731 05 01.03.03.01.05.05 Gate valve Ø3", flanged class 300, Carbon Steel. ea 4.00 3.00 12.00 11.00 33.00 132.00 500.00 2,000.00 67.00 268.00 - 600.00 2,400.00

1700 1730 1731 05 01.03.03.01.05.06 Buterfly valve Ø3", lug style, class 150, Ductile iron ea 1.00 2.50 2.50 11.00 27.50 27.50 250.00 250.00 22.50 22.50 - 300.00 300.00

Station for Compressed air service -

1700 1730 1731 05 01.03.03.01.05.07 Buterfly valve Ø4", lug style, class 150, Ductile iron ea 2.00 2.50 5.00 11.00 27.50 55.00 300.00 600.00 32.50 65.00 - 360.00 720.00

1700 1730 1731 05 01.03.03.01.05.08 Water trap Ø1", Carbon Steel ea 1.00 1.50 1.50 11.00 16.50 16.50 200.00 200.00 23.50 23.50 - 240.00 240.00

1700 1730 1731 05 01.03.03.01.05.09 Pipe Ø4" Sch 40, flanged Class 150 (include accesorioes) m 1.00 4.50 4.50 11.00 49.50 49.50 30.00 30.00 46.00 46.00 - 125.50 125.50

1700 1730 1731 05 01.03.03.01.05.10 Pressure gauge, Ø1/2" connection, Dial Ø4", Scale 0-200PSIG ea 1.00 2.50 2.50 11.00 27.50 27.50 150.00 150.00 2.50 2.50 - 180.00 180.00

1700 06 01.03.03.01.06 Electrical

1700 1730 1731 06 01.03.03.01.06.01 Panelboard 480V, 25kA, 60Hz, 150A ea 1.00 31.20 31.20 10.25 319.80 319.80 - 2,180.20 2,180.20 12,500.00 12,500.00 15,000.00 15,000.00

1700 1730 1731 06 01.03.03.01.06.02 Panelboard 230V, 25kA, 60Hz, 60A ea 1.00 31.20 31.20 10.25 319.80 319.80 - 980.20 980.20 6,500.00 6,500.00 7,800.00 7,800.00

1700 1730 1731 06 01.03.03.01.06.03 Transformer 20kVA, 480/230V, Dyn5 ea 1.00 18.00 18.00 10.25 184.50 184.50 - 315.50 315.50 2,500.00 2,500.00 3,000.00 3,000.00

1700 1730 1731 06 01.03.03.01.06.04 Transformer 3.5kVA, 230/120V, Dyn5 ea 1.00 18.00 18.00 10.25 184.50 184.50 - 115.50 115.50 1,500.00 1,500.00 1,800.00 1,800.00

1700 1730 1731 06 01.03.03.01.06.05 UPS 1KVA, 120VAC, 1PH ea 1.00 2.00 2.00 10.25 20.50 20.50 - 219.50 219.50 1,200.00 1,200.00 1,440.00 1,440.00

1700 1730 1731 06 01.03.03.01.06.06 Bulk Materials (Lighting, welding socket, earthing, trays,etc) lot 1.00 29.27 29.27 10.25 300.00 300.00 3,000.00 3,000.00 300.00 300.00 - 3,600.00 3,600.00

1700 07 01.03.03.01.07 Instrumentation

1700 1730 1731 07 01.03.03.01.07.01 Sistema de telececomunicaciones incluye: Gabinete de telecomunicaciones pedestal ea 1.00 10.00 10.00 10.25 102.50 102.50 - 522.64 522.64 1,045.27 1,045.27 1,670.41 1,670.41

1700 1730 1731 07 01.03.03.01.07.02 switch de telecomunicaciones ea 1.00 3.70 3.70 10.25 37.93 37.93 - 1,394.88 1,394.88 2,789.76 2,789.76 4,222.57 4,222.57

1700 1730 1731 07 01.03.03.01.07.03 Transceiver SFP ea 2.00 3.00 6.00 10.25 30.75 61.50 - 480.08 960.15 960.15 1,920.30 1,470.98 2,941.95

1700 1730 1731 07 01.03.03.01.07.04 patch panel para fibra óptica ea 1.00 2.50 2.50 10.25 25.63 25.63 - 214.51 214.51 429.01 429.01 669.14 669.14

1700 1730 1731 07 01.03.03.01.07.05 Accesorios ea 1.00 78.79 78.79 10.25 807.60 807.60 1,000.00 1,000.00 500.00 500.00 - 2,307.60 2,307.60

1700 1730 1731 07 01.03.03.01.07.06 CCTV Incuye: Cámara IP-IR con PoE ea 1.00 12.40 12.40 10.25 127.10 127.10 - 550.74 550.74 1,101.48 1,101.48 1,779.32 1,779.32

1700 1730 1731 07 01.03.03.01.07.07 PABX Incluye: Teléfono emergencia para trabajos en ambiente minero,ea 1.00 1.00 1.00 10.25 10.25 10.25 - 251.53 251.53 503.05 503.05 764.83 764.83

1700 1730 1731 07 01.03.03.01.07.08 conversor de medios ea 1.00 3.50 3.50 10.25 35.88 35.88 - 231.04 231.04 462.07 462.07 728.98 728.98

1700 1730 1731 07 01.03.03.01.07.09 LEAKY FEEDER Incluye: Amplificador, fin de línea y splitter ea 1.00 5.00 5.00 10.25 51.25 51.25 - 750.00 750.00 1,500.00 1,500.00 2,301.25 2,301.25

1700 1730 1731 07 01.03.03.01.07.10 Tablero eléctrico instrumentación 120VAC ea 1.00 10.00 10.00 10.25 102.50 102.50 - 2,075.00 2,075.00 4,150.00 4,150.00 6,327.50 6,327.50

1700 1740 T 01.03.04 Station 02

1700 1741 T 01.03.04.01 Activity 01

1700 01 01.03.04.01.01 Mining

1700 1740 1741 01 01.03.04.01.01.01 Estation 4700 lot 1.00 3,896.10 3,896.10 11.00 42,857.14 42,857.14 - 107,142.86 107,142.86 - 150,000.00 150,000.00

1700 1740 1741 01 01.03.04.01.01.02 - - - - - - - -

1700 02 01.03.04.01.02 Civil

1700 1740 1741 02 01.03.04.01.02.01 - - - - - - - -

1700 1740 1741 02 01.03.04.01.02.02 - - - - - - - -

1700 03 01.03.04.01.03 Structural

1700 1740 1741 03 01.03.04.01.03.01 Concrete Structures f'c=280 kg/cm2 m3 31.00 7.98 247.38 9.50 75.81 2,350.11 387.26 12,005.06 12.89 399.59 - - 475.96 14,754.76

1700 1740 1741 03 01.03.04.01.03.02 Steel Structures t 8.28 80.00 662.00 11.00 880.00 7,282.00 2,400.00 19,860.00 620.00 5,130.50 - - 3,900.00 32,272.50

1700 04 01.03.04.01.04 Mechanical

1700 1740 1741 04 01.03.04.01.04.01 - - - - - - - -

1700 1740 1741 04 01.03.04.01.04.02 - - - - - - - -

1700 05 01.03.04.01.05 Piping

Pressure reduction station for water service

1700 1740 1741 05 01.03.04.01.05.01 Pressure reduction valve Ø3", Carbon steel, flanged 300 Class ea 2.00 5.00 10.00 11.00 55.00 110.00 2,000.00 4,000.00 345.00 690.00 - 2,400.00 4,800.00

1700 1740 1741 05 01.03.04.01.05.02 Safety valve Ø2"xØ3", Carbon steel, flanged ea 1.00 4.50 4.50 11.00 49.50 49.50 2,500.00 2,500.00 450.50 450.50 - 3,000.00 3,000.00

1700 1740 1741 05 01.03.04.01.05.03 Pressure gauge, Ø1/2" connection, Dial Ø4", Scale 0-200PSIG ea 2.00 2.50 5.00 11.00 27.50 55.00 150.00 300.00 2.50 5.00 - 180.00 360.00

1700 1740 1741 05 01.03.04.01.05.04 Pipe Ø3" Sch 80, flanged Class 300 (include accesorioes) m 2.00 2.50 5.00 11.00 27.50 55.00 25.00 50.00 31.00 62.00 - 83.50 167.00

1700 1740 1741 05 01.03.04.01.05.05 Gate valve Ø3", flanged class 300, Carbon Steel. ea 4.00 3.00 12.00 11.00 33.00 132.00 500.00 2,000.00 67.00 268.00 - 600.00 2,400.00

1700 1740 1741 05 01.03.04.01.05.06 Buterfly valve Ø3", lug style, class 150, Ductile iron ea 1.00 2.50 2.50 11.00 27.50 27.50 250.00 250.00 22.50 22.50 - 300.00 300.00

Station for Compressed air service -

1700 1740 1741 05 01.03.04.01.05.07 Buterfly valve Ø4", lug style, class 150, Ductile iron ea 2.00 2.50 5.00 11.00 27.50 55.00 300.00 600.00 32.50 65.00 - 360.00 720.00

1700 1740 1741 05 01.03.04.01.05.08 Water trap Ø1", Carbon Steel ea 1.00 1.50 1.50 11.00 16.50 16.50 200.00 200.00 23.50 23.50 - 240.00 240.00

1700 1740 1741 05 01.03.04.01.05.09 Pipe Ø4" Sch 40, flanged Class 150 (include accesorioes) m 1.00 4.50 4.50 11.00 49.50 49.50 30.00 30.00 46.00 46.00 - 125.50 125.50

1700 1740 1741 05 01.03.04.01.05.10 Pressure gauge, Ø1/2" connection, Dial Ø4", Scale 0-200PSIG ea 1.00 2.50 2.50 11.00 27.50 27.50 150.00 150.00 2.50 2.50 - 180.00 180.00

1700 06 01.03.04.01.06 Electrical

1700 1740 1741 06 01.03.04.01.06.01 Panelboard 480V, 25kA, 60Hz, 150A ea 1.00 31.20 31.20 10.25 319.80 319.80 - 2,180.20 2,180.20 12,500.00 12,500.00 15,000.00 15,000.00

1700 1740 1741 06 01.03.04.01.06.02 Panelboard 230V, 25kA, 60Hz, 60A ea 1.00 31.20 31.20 10.25 319.80 319.80 - 980.20 980.20 6,500.00 6,500.00 7,800.00 7,800.00

1700 1740 1741 06 01.03.04.01.06.03 Transformer 20kVA, 480/230V, Dyn5 ea 1.00 18.00 18.00 10.25 184.50 184.50 - 315.50 315.50 2,500.00 2,500.00 3,000.00 3,000.00

1700 1740 1741 06 01.03.04.01.06.04 Transformer 3.5kVA, 230/120V, Dyn5 ea 1.00 18.00 18.00 10.25 184.50 184.50 - 115.50 115.50 1,500.00 1,500.00 1,800.00 1,800.00

1700 1740 1741 06 01.03.04.01.06.05 UPS 1KVA, 120VAC, 1PH ea 1.00 2.00 2.00 10.25 20.50 20.50 - 219.50 219.50 1,200.00 1,200.00 1,440.00 1,440.00

1700 1740 1741 06 01.03.04.01.06.06 Bulk Materials (Lighting, welding socket, earthing, trays,etc) lot 1.00 29.27 29.27 10.25 300.00 300.00 3,000.00 3,000.00 300.00 300.00 - 3,600.00 3,600.00

1700 07 01.03.04.01.07 Instrumentation

1700 1740 1741 07 01.03.04.01.07.01 Sistema de telececomunicaciones incluye: Gabinete de telecomunicaciones pedestal ea 1.00 10.00 10.00 10.25 102.50 102.50 - 522.64 522.64 1,045.27 1,045.27 1,670.41 1,670.41

1700 1740 1741 07 01.03.04.01.07.02 switch de telecomunicaciones ea 1.00 3.70 3.70 10.25 37.93 37.93 - 1,394.88 1,394.88 2,789.76 2,789.76 4,222.57 4,222.57

1700 1740 1741 07 01.03.04.01.07.03 Transceiver SFP ea 2.00 3.00 6.00 10.25 30.75 61.50 - 480.08 960.15 960.15 1,920.30 1,470.98 2,941.95

1700 1740 1741 07 01.03.04.01.07.04 patch panel para fibra óptica ea 1.00 2.50 2.50 10.25 25.63 25.63 - 214.51 214.51 429.01 429.01 669.14 669.14

1700 1740 1741 07 01.03.04.01.07.05 Accesorios ea 1.00 78.79 78.79 10.25 807.60 807.60 1,000.00 1,000.00 500.00 500.00 - 2,307.60 2,307.60

1700 1740 1741 07 01.03.04.01.07.06 CCTV Incuye: Cámara IP-IR con PoE ea 1.00 12.40 12.40 10.25 127.10 127.10 - 550.74 550.74 1,101.48 1,101.48 1,779.32 1,779.32

1700 1740 1741 07 01.03.04.01.07.07 PABX Incluye: Teléfono emergencia para trabajos en ambiente minero,ea 1.00 1.00 1.00 10.25 10.25 10.25 - 251.53 251.53 503.05 503.05 764.83 764.83

1700 1740 1741 07 01.03.04.01.07.08 conversor de medios ea 1.00 3.50 3.50 10.25 35.88 35.88 - 231.04 231.04 462.07 462.07 728.98 728.98

Page 42: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

Prepared by: Julio Villanueva

Date: 27/01/2014

Review: B

Total

# WBS L2# WBS

L3

# WBS

L4Discip. Item Description UoM Quant Unit Cost

Unit Mhr Total Mhr Rate Unit Total Unit Total Unit Total Unit Total (US$) (US$)

CAPEX

SCOPING STUDY

SHAFT DESIGN - CHUCAPACA

209050-00014

Total Cost

Document Nr:

Project:

Project Nr:

Labour Manhour (mh) Labour Cost (US$) Material Cost (US$) Const Eqpt (US$) Process Eqpt (US$)

1700 1740 1741 07 01.03.04.01.07.09 LEAKY FEEDER Incluye: Amplificador, fin de línea y splitter ea 1.00 5.00 5.00 10.25 51.25 51.25 - 750.00 750.00 1,500.00 1,500.00 2,301.25 2,301.25

1700 1740 1741 07 01.03.04.01.07.10 Tablero eléctrico instrumentación 120VAC ea 1.00 10.00 10.00 10.25 102.50 102.50 - 2,075.00 2,075.00 4,150.00 4,150.00 6,327.50 6,327.50

1700 1750 T 01.03.05 Station 03

1700 1751 T 01.03.05.01 Activity 01

1700 01 01.03.05.01.01 Mining

1700 1750 1751 01 01.03.05.01.01.01 Estation 4650 lot 1.00 3,896.10 3,896.10 11.00 42,857.14 42,857.14 - 107,142.86 107,142.86 - 150,000.00 150,000.00

1700 1750 1751 01 01.03.05.01.01.02 - - - - - - - -

1700 02 01.03.05.01.02 Civil

1700 1750 1751 02 01.03.05.01.02.01 - - - - - - - -

1700 1750 1751 02 01.03.05.01.02.02 - - - - - - - -

1700 03 01.03.05.01.03 Structural

1700 1750 1751 03 01.03.05.01.03.01 Concrete Structures f'c=280 kg/cm2 m3 31.00 7.98 247.38 9.50 75.81 2,350.11 387.26 12,005.06 12.89 399.59 - - 475.96 14,754.76

1700 1750 1751 03 01.03.05.01.03.02 Steel Structures t 8.28 80.00 662.00 11.00 880.00 7,282.00 2,400.00 19,860.00 620.00 5,130.50 - - 3,900.00 32,272.50

1700 04 01.03.05.01.04 Mechanical

1700 1750 1751 04 01.03.05.01.04.01 - - - - - - - -

1700 1750 1751 04 01.03.05.01.04.02 - - - - - - - -

1700 05 01.03.05.01.05 Piping

Pressure reduction station for water service

1700 1750 1751 05 01.03.05.01.05.01 Pressure reduction valve Ø3", Carbon steel, flanged 300 Class ea 2.00 5.00 10.00 11.00 55.00 110.00 2,000.00 4,000.00 345.00 690.00 - 2,400.00 4,800.00

1700 1750 1751 05 01.03.05.01.05.02 Safety valve Ø2"xØ3", Carbon steel, flanged ea 1.00 4.50 4.50 11.00 49.50 49.50 2,500.00 2,500.00 450.50 450.50 - 3,000.00 3,000.00

1700 1750 1751 05 01.03.05.01.05.03 Pressure gauge, Ø1/2" connection, Dial Ø4", Scale 0-200PSIG ea 2.00 2.50 5.00 11.00 27.50 55.00 150.00 300.00 2.50 5.00 - 180.00 360.00

1700 1750 1751 05 01.03.05.01.05.04 Pipe Ø3" Sch 80, flanged Class 300 (include accesorioes) m 2.00 2.50 5.00 11.00 27.50 55.00 25.00 50.00 31.00 62.00 - 83.50 167.00

1700 1750 1751 05 01.03.05.01.05.05 Gate valve Ø3", flanged class 300, Carbon Steel. ea 4.00 3.00 12.00 11.00 33.00 132.00 500.00 2,000.00 67.00 268.00 - 600.00 2,400.00

1700 1750 1751 05 01.03.05.01.05.06 Buterfly valve Ø3", lug style, class 150, Ductile iron ea 1.00 2.50 2.50 11.00 27.50 27.50 250.00 250.00 22.50 22.50 - 300.00 300.00

Station for Compressed air service -

1700 1750 1751 05 01.03.05.01.05.07 Buterfly valve Ø4", lug style, class 150, Ductile iron ea 2.00 2.50 5.00 11.00 27.50 55.00 300.00 600.00 32.50 65.00 - 360.00 720.00

1700 1750 1751 05 01.03.05.01.05.08 Water trap Ø1", Carbon Steel ea 1.00 1.50 1.50 11.00 16.50 16.50 200.00 200.00 23.50 23.50 - 240.00 240.00

1700 1750 1751 05 01.03.05.01.05.09 Pipe Ø4" Sch 40, flanged Class 150 (include accesorioes) m 1.00 4.50 4.50 11.00 49.50 49.50 30.00 30.00 46.00 46.00 - 125.50 125.50

1700 1750 1751 05 01.03.05.01.05.10 Pressure gauge, Ø1/2" connection, Dial Ø4", Scale 0-200PSIG ea 1.00 2.50 2.50 11.00 27.50 27.50 150.00 150.00 2.50 2.50 - 180.00 180.00

1700 06 01.03.05.01.06 Electrical

1700 1750 1751 06 01.03.05.01.06.01 Switchgear 4.16 Kv, 630A, 60Hz, 3 Feeders 25kA ea 1.00 25.00 25.00 10.25 256.25 256.25 - 19,743.75 19,743.75 100,000.00 100,000.00 120,000.00 120,000.00

1700 1750 1751 06 01.03.05.01.06.02 Transformer 250kVA, 4160/480V, Dyn5 ea 1.00 18.00 18.00 10.25 184.50 184.50 - 3,415.50 3,415.50 18,000.00 18,000.00 21,600.00 21,600.00

1700 1750 1751 06 01.03.05.01.06.03 Panelboard 480V, 25kA, 60Hz, 300A ea 1.00 31.20 31.20 10.25 319.80 319.80 - 4,340.20 4,340.20 23,300.00 23,300.00 27,960.00 27,960.00

1700 1750 1751 06 01.03.05.01.06.04 Panelboard 230V, 25kA, 60Hz, 60A ea 1.00 31.20 31.20 10.25 319.80 319.80 - 980.20 980.20 6,500.00 6,500.00 7,800.00 7,800.00

1700 1750 1751 06 01.03.05.01.06.05 Transformer 20kVA, 480/230V, Dyn5 ea 1.00 18.00 18.00 10.25 184.50 184.50 - 315.50 315.50 2,500.00 2,500.00 3,000.00 3,000.00

1700 1750 1751 06 01.03.05.01.06.06 Transformer 3.5kVA, 230/120V, Dyn5 ea 1.00 18.00 18.00 10.25 184.50 184.50 - 115.50 115.50 1,500.00 1,500.00 1,800.00 1,800.00

1700 1750 1751 06 01.03.05.01.06.07 UPS 1KVA, 120VAC, 1PH ea 1.00 2.00 2.00 10.25 20.50 20.50 - 219.50 219.50 1,200.00 1,200.00 1,440.00 1,440.00

1700 1750 1751 06 01.03.05.01.06.08 Bulk Materials (Lighting, welding socket, earthing, trays,etc) lot 1.00 29.27 29.27 10.25 300.00 300.00 3,000.00 3,000.00 300.00 300.00 - 3,600.00 3,600.00

1700 07 01.03.05.01.07 Instrumentation

1700 1750 1751 07 01.03.05.01.07.01 Sistema de telececomunicaciones incluye: Gabinete de telecomunicaciones pedestal ea 1.00 10.00 10.00 10.25 102.50 102.50 - 522.64 522.64 1,045.27 1,045.27 1,670.41 1,670.41

1700 1750 1751 07 01.03.05.01.07.02 switch de telecomunicaciones ea 1.00 3.70 3.70 10.25 37.93 37.93 - 1,394.88 1,394.88 2,789.76 2,789.76 4,222.57 4,222.57

1700 1750 1751 07 01.03.05.01.07.03 Transceiver SFP ea 2.00 3.00 6.00 10.25 30.75 61.50 - 480.08 960.15 960.15 1,920.30 1,470.98 2,941.95

1700 1750 1751 07 01.03.05.01.07.04 patch panel para fibra óptica ea 1.00 2.50 2.50 10.25 25.63 25.63 - 214.51 214.51 429.01 429.01 669.14 669.14

1700 1750 1751 07 01.03.05.01.07.05 Accesorios ea 1.00 78.79 78.79 10.25 807.60 807.60 1,000.00 1,000.00 500.00 500.00 - 2,307.60 2,307.60

1700 1750 1751 07 01.03.05.01.07.06 CCTV Incuye: Cámara IP-IR con PoE ea 1.00 12.40 12.40 10.25 127.10 127.10 - 550.74 550.74 1,101.48 1,101.48 1,779.32 1,779.32

1700 1750 1751 07 01.03.05.01.07.07 PABX Incluye: Teléfono emergencia para trabajos en ambiente minero,ea 1.00 1.00 1.00 10.25 10.25 10.25 - 251.53 251.53 503.05 503.05 764.83 764.83

1700 1750 1751 07 01.03.05.01.07.08 conversor de medios ea 1.00 3.50 3.50 10.25 35.88 35.88 - 231.04 231.04 462.07 462.07 728.98 728.98

1700 1750 1751 07 01.03.05.01.07.09 LEAKY FEEDER Incluye: Amplificador, fin de línea y splitter ea 1.00 5.00 5.00 10.25 51.25 51.25 - 750.00 750.00 1,500.00 1,500.00 2,301.25 2,301.25

1700 1750 1751 07 01.03.05.01.07.10 Tablero eléctrico instrumentación 120VAC ea 1.00 10.00 10.00 10.25 102.50 102.50 - 2,075.00 2,075.00 4,150.00 4,150.00 6,327.50 6,327.50

1700 1760 T 01.03.06 Station 04

1700 1761 T 01.03.06.01 Activity 01

1700 01 01.03.06.01.01 Mining

1700 1760 1761 01 01.03.06.01.01.01 Estation 4522 lot 1.00 5,844.16 5,844.16 11.00 64,285.71 64,285.71 - 160,714.29 160,714.29 - 225,000.00 225,000.00

1700 1760 1761 01 01.03.06.01.01.02 - - - - - - - -

1700 02 01.03.06.01.02 Civil

1700 1760 1761 02 01.03.06.01.02.01 - - - - - - - -

1700 1760 1761 02 01.03.06.01.02.02 - - - - - - - -

1700 03 01.03.06.01.03 Structural

1700 1760 1761 03 01.03.06.01.03.01 Concrete Structures f'c=280 kg/cm2 m3 31.00 7.98 247.38 9.50 75.81 2,350.11 387.26 12,005.06 12.89 399.59 - - 475.96 14,754.76

1700 1760 1761 03 01.03.06.01.03.02 Steel Structures t 8.28 80.00 662.00 11.00 880.00 7,282.00 2,400.00 19,860.00 620.00 5,130.50 - - 3,900.00 32,272.50

1700 04 01.03.06.01.04 Mechanical

1700 1760 1761 04 01.03.06.01.04.01 - - - - - - - -

1700 1760 1761 04 01.03.06.01.04.02 - - - - - - - -

1700 05 01.03.06.01.05 Piping

Pressure reduction station for water service

1700 1760 1761 05 01.03.06.01.05.01 Pressure reduction valve Ø3", Carbon steel, flanged 300 Class ea 2.00 5.00 10.00 11.00 55.00 110.00 2,000.00 4,000.00 345.00 690.00 - 2,400.00 4,800.00

1700 1760 1761 05 01.03.06.01.05.02 Safety valve Ø2"xØ3", Carbon steel, flanged ea 1.00 4.50 4.50 11.00 49.50 49.50 2,500.00 2,500.00 450.50 450.50 - 3,000.00 3,000.00

1700 1760 1761 05 01.03.06.01.05.03 Pressure gauge, Ø1/2" connection, Dial Ø4", Scale 0-200PSIG ea 2.00 2.50 5.00 11.00 27.50 55.00 150.00 300.00 2.50 5.00 - 180.00 360.00

1700 1760 1761 05 01.03.06.01.05.04 Pipe Ø3" Sch 80, flanged Class 300 (include accesorioes) m 2.00 2.50 5.00 11.00 27.50 55.00 25.00 50.00 31.00 62.00 - 83.50 167.00

1700 1760 1761 05 01.03.06.01.05.05 Gate valve Ø3", flanged class 300, Carbon Steel. ea 4.00 3.00 12.00 11.00 33.00 132.00 500.00 2,000.00 67.00 268.00 - 600.00 2,400.00

1700 1760 1761 05 01.03.06.01.05.06 Buterfly valve Ø3", lug style, class 150, Ductile iron ea 1.00 2.50 2.50 11.00 27.50 27.50 250.00 250.00 22.50 22.50 - 300.00 300.00

Station for Compressed air service -

1700 1760 1761 05 01.03.06.01.05.07 Buterfly valve Ø4", lug style, class 150, Ductile iron ea 2.00 2.50 5.00 11.00 27.50 55.00 300.00 600.00 32.50 65.00 - 360.00 720.00

Page 43: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

Prepared by: Julio Villanueva

Date: 27/01/2014

Review: B

Total

# WBS L2# WBS

L3

# WBS

L4Discip. Item Description UoM Quant Unit Cost

Unit Mhr Total Mhr Rate Unit Total Unit Total Unit Total Unit Total (US$) (US$)

CAPEX

SCOPING STUDY

SHAFT DESIGN - CHUCAPACA

209050-00014

Total Cost

Document Nr:

Project:

Project Nr:

Labour Manhour (mh) Labour Cost (US$) Material Cost (US$) Const Eqpt (US$) Process Eqpt (US$)

1700 1760 1761 05 01.03.06.01.05.08 Water trap Ø1", Carbon Steel ea 1.00 1.50 1.50 11.00 16.50 16.50 200.00 200.00 23.50 23.50 - 240.00 240.00

1700 1760 1761 05 01.03.06.01.05.09 Pipe Ø4" Sch 40, flanged Class 150 (include accesorioes) m 1.00 4.50 4.50 11.00 49.50 49.50 30.00 30.00 46.00 46.00 - 125.50 125.50

1700 1760 1761 05 01.03.06.01.05.10 Pressure gauge, Ø1/2" connection, Dial Ø4", Scale 0-200PSIG ea 1.00 2.50 2.50 11.00 27.50 27.50 150.00 150.00 2.50 2.50 - 180.00 180.00

1700 06 01.03.06.01.06 Electrical

1700 1760 1761 06 01.03.06.01.06.01 Panelboard 480V, 25kA, 60Hz, 150A ea 1.00 31.20 31.20 10.25 319.80 319.80 - 2,180.20 2,180.20 12,500.00 12,500.00 15,000.00 15,000.00

1700 1760 1761 06 01.03.06.01.06.02 Panelboard 230V, 25kA, 60Hz, 60A ea 1.00 31.20 31.20 10.25 319.80 319.80 - 980.20 980.20 6,500.00 6,500.00 7,800.00 7,800.00

1700 1760 1761 06 01.03.06.01.06.03 Transformer 20kVA, 480/230V, Dyn5 ea 1.00 18.00 18.00 10.25 184.50 184.50 - 315.50 315.50 2,500.00 2,500.00 3,000.00 3,000.00

1700 1760 1761 06 01.03.06.01.06.04 Transformer 3.5kVA, 230/120V, Dyn5 ea 1.00 18.00 18.00 10.25 184.50 184.50 - 115.50 115.50 1,500.00 1,500.00 1,800.00 1,800.00

1700 1760 1761 06 01.03.06.01.06.05 UPS 1KVA, 120VAC, 1PH ea 1.00 2.00 2.00 10.25 20.50 20.50 - 219.50 219.50 1,200.00 1,200.00 1,440.00 1,440.00

1700 1760 1761 06 01.03.06.01.06.06 Bulk Materials (Lighting, welding socket, earthing, trays,etc) lot 1.00 29.27 29.27 10.25 300.00 300.00 3,000.00 3,000.00 300.00 300.00 - 3,600.00 3,600.00

1700 07 01.03.06.01.07 Instrumentation

1700 1760 1761 07 01.03.06.01.07.01 Sistema de telececomunicaciones incluye: Gabinete de telecomunicaciones pedestal ea 1.00 10.00 10.00 10.25 102.50 102.50 - 522.64 522.64 1,045.27 1,045.27 1,670.41 1,670.41

1700 1760 1761 07 01.03.06.01.07.02 switch de telecomunicaciones ea 1.00 3.70 3.70 10.25 37.93 37.93 - 1,394.88 1,394.88 2,789.76 2,789.76 4,222.57 4,222.57

1700 1760 1761 07 01.03.06.01.07.03 Transceiver SFP ea 2.00 3.00 6.00 10.25 30.75 61.50 - 480.08 960.15 960.15 1,920.30 1,470.98 2,941.95

1700 1760 1761 07 01.03.06.01.07.04 patch panel para fibra óptica ea 1.00 2.50 2.50 10.25 25.63 25.63 - 214.51 214.51 429.01 429.01 669.14 669.14

1700 1760 1761 07 01.03.06.01.07.05 Accesorios ea 1.00 78.79 78.79 10.25 807.60 807.60 1,000.00 1,000.00 500.00 500.00 - 2,307.60 2,307.60

1700 1760 1761 07 01.03.06.01.07.06 CCTV Incuye: Cámara IP-IR con PoE ea 1.00 12.40 12.40 10.25 127.10 127.10 - 550.74 550.74 1,101.48 1,101.48 1,779.32 1,779.32

1700 1760 1761 07 01.03.06.01.07.07 PABX Incluye: Teléfono emergencia para trabajos en ambiente minero,ea 1.00 1.00 1.00 10.25 10.25 10.25 - 251.53 251.53 503.05 503.05 764.83 764.83

1700 1760 1761 07 01.03.06.01.07.08 conversor de medios ea 1.00 3.50 3.50 10.25 35.88 35.88 - 231.04 231.04 462.07 462.07 728.98 728.98

1700 1760 1761 07 01.03.06.01.07.09 LEAKY FEEDER Incluye: Amplificador, fin de línea y splitter ea 1.00 5.00 5.00 10.25 51.25 51.25 - 750.00 750.00 1,500.00 1,500.00 2,301.25 2,301.25

1700 1760 1761 07 01.03.06.01.07.10 Tablero eléctrico instrumentación 120VAC ea 1.00 10.00 10.00 10.25 102.50 102.50 - 2,075.00 2,075.00 4,150.00 4,150.00 6,327.50 6,327.50

1700 1770 T 01.03.07 Station 05

1700 1771 T 01.03.07.01 Activity 01

1700 01 01.03.07.01.01 Mining

1700 1770 1771 01 01.03.07.01.01.01 Estation 4482 lot 1.00 5,844.16 5,844.16 11.00 64,285.71 64,285.71 - 160,714.29 160,714.29 - 225,000.00 225,000.00

1700 1770 1771 01 01.03.07.01.01.02 - - - - - - - -

1700 02 01.03.07.01.02 Civil

1700 1770 1771 02 01.03.07.01.02.01 - - - - - - - -

1700 1770 1771 02 01.03.07.01.02.02 - - - - - - - -

1700 03 01.03.07.01.03 Structural

1700 1770 1771 03 01.03.07.01.03.01 Concrete Structures f'c=280 kg/cm2 m3 31.00 7.98 247.38 9.50 75.81 2,350.11 387.26 12,005.06 12.89 399.59 - - 475.96 14,754.76

1700 1770 1771 03 01.03.07.01.03.02 Steel Structures t 8.28 80.00 662.00 11.00 880.00 7,282.00 2,400.00 19,860.00 620.00 5,130.50 - - 3,900.00 32,272.50

1700 04 01.03.07.01.04 Mechanical

1700 1770 1771 04 01.03.07.01.04.01 - - - - - - - -

1700 1770 1771 04 01.03.07.01.04.02 - - - - - - - -

1700 05 01.03.07.01.05 Piping

Pressure reduction station for water service

1700 1770 1771 05 01.03.07.01.05.01 Pressure reduction valve Ø3", Carbon steel, flanged 300 Class ea 2.00 5.00 10.00 11.00 55.00 110.00 2,000.00 4,000.00 345.00 690.00 - 2,400.00 4,800.00

1700 1770 1771 05 01.03.07.01.05.02 Safety valve Ø2"xØ3", Carbon steel, flanged ea 1.00 4.50 4.50 11.00 49.50 49.50 2,500.00 2,500.00 450.50 450.50 - 3,000.00 3,000.00

1700 1770 1771 05 01.03.07.01.05.03 Pressure gauge, Ø1/2" connection, Dial Ø4", Scale 0-200PSIG ea 2.00 2.50 5.00 11.00 27.50 55.00 150.00 300.00 2.50 5.00 - 180.00 360.00

1700 1770 1771 05 01.03.07.01.05.04 Pipe Ø3" Sch 80, flanged Class 300 (include accesorioes) m 2.00 2.50 5.00 11.00 27.50 55.00 25.00 50.00 31.00 62.00 - 83.50 167.00

1700 1770 1771 05 01.03.07.01.05.05 Gate valve Ø3", flanged class 300, Carbon Steel. ea 4.00 3.00 12.00 11.00 33.00 132.00 500.00 2,000.00 67.00 268.00 - 600.00 2,400.00

1700 1770 1771 05 01.03.07.01.05.06 Buterfly valve Ø3", lug style, class 150, Ductile iron ea 1.00 2.50 2.50 11.00 27.50 27.50 250.00 250.00 22.50 22.50 - 300.00 300.00

Station for Compressed air service -

1700 1770 1771 05 01.03.07.01.05.07 Buterfly valve Ø4", lug style, class 150, Ductile iron ea 2.00 2.50 5.00 11.00 27.50 55.00 300.00 600.00 32.50 65.00 - 360.00 720.00

1700 1770 1771 05 01.03.07.01.05.08 Water trap Ø1", Carbon Steel ea 1.00 1.50 1.50 11.00 16.50 16.50 200.00 200.00 23.50 23.50 - 240.00 240.00

1700 1770 1771 05 01.03.07.01.05.09 Pipe Ø4" Sch 40, flanged Class 150 (include accesorioes) m 1.00 4.50 4.50 11.00 49.50 49.50 30.00 30.00 46.00 46.00 - 125.50 125.50

1700 1770 1771 05 01.03.07.01.05.10 Pressure gauge, Ø1/2" connection, Dial Ø4", Scale 0-200PSIG ea 1.00 2.50 2.50 11.00 27.50 27.50 150.00 150.00 2.50 2.50 - 180.00 180.00

1700 06 01.03.07.01.06 Electrical

1700 1770 1771 06 01.03.07.01.06.01 Panelboard 480V, 25kA, 60Hz, 150A ea 1.00 31.20 31.20 10.25 319.80 319.80 - 2,180.20 2,180.20 12,500.00 12,500.00 15,000.00 15,000.00

1700 1770 1771 06 01.03.07.01.06.02 Panelboard 230V, 25kA, 60Hz, 60A ea 1.00 31.20 31.20 10.25 319.80 319.80 - 980.20 980.20 6,500.00 6,500.00 7,800.00 7,800.00

1700 1770 1771 06 01.03.07.01.06.03 Transformer 20kVA, 480/230V, Dyn5 ea 1.00 18.00 18.00 10.25 184.50 184.50 - 315.50 315.50 2,500.00 2,500.00 3,000.00 3,000.00

1700 1770 1771 06 01.03.07.01.06.04 Transformer 3.5kVA, 230/120V, Dyn5 ea 1.00 18.00 18.00 10.25 184.50 184.50 - 115.50 115.50 1,500.00 1,500.00 1,800.00 1,800.00

1700 1770 1771 06 01.03.07.01.06.05 UPS 1KVA, 120VAC, 1PH ea 1.00 2.00 2.00 10.25 20.50 20.50 - 219.50 219.50 1,200.00 1,200.00 1,440.00 1,440.00

1700 1770 1771 06 01.03.07.01.06.06 Bulk Materials (Lighting, welding socket, earthing, trays,etc) lot 1.00 29.27 29.27 10.25 300.00 300.00 3,000.00 3,000.00 300.00 300.00 - 3,600.00 3,600.00

1700 07 01.03.07.01.07 Instrumentation

1700 1770 1771 07 01.03.07.01.07.01 Sistema de telececomunicaciones incluye: Gabinete de telecomunicaciones pedestal ea 1.00 10.00 10.00 10.25 102.50 102.50 - 522.64 522.64 1,045.27 1,045.27 1,670.41 1,670.41

1700 1770 1771 07 01.03.07.01.07.02 switch de telecomunicaciones ea 1.00 3.70 3.70 10.25 37.93 37.93 - 1,394.88 1,394.88 2,789.76 2,789.76 4,222.57 4,222.57

1700 1770 1771 07 01.03.07.01.07.03 Transceiver SFP ea 2.00 3.00 6.00 10.25 30.75 61.50 - 480.08 960.15 960.15 1,920.30 1,470.98 2,941.95

1700 1770 1771 07 01.03.07.01.07.04 patch panel para fibra óptica ea 1.00 2.50 2.50 10.25 25.63 25.63 - 214.51 214.51 429.01 429.01 669.14 669.14

1700 1770 1771 07 01.03.07.01.07.05 Accesorios ea 1.00 78.79 78.79 10.25 807.60 807.60 1,000.00 1,000.00 500.00 500.00 - 2,307.60 2,307.60

1700 1770 1771 07 01.03.07.01.07.06 CCTV Incuye: Cámara IP-IR con PoE ea 1.00 12.40 12.40 10.25 127.10 127.10 - 550.74 550.74 1,101.48 1,101.48 1,779.32 1,779.32

1700 1770 1771 07 01.03.07.01.07.07 PABX Incluye: Teléfono emergencia para trabajos en ambiente minero,ea 1.00 1.00 1.00 10.25 10.25 10.25 - 251.53 251.53 503.05 503.05 764.83 764.83

1700 1770 1771 07 01.03.07.01.07.08 conversor de medios ea 1.00 3.50 3.50 10.25 35.88 35.88 - 231.04 231.04 462.07 462.07 728.98 728.98

1700 1770 1771 07 01.03.07.01.07.09 LEAKY FEEDER Incluye: Amplificador, fin de línea y splitter ea 1.00 5.00 5.00 10.25 51.25 51.25 - 750.00 750.00 1,500.00 1,500.00 2,301.25 2,301.25

1700 1770 1771 07 01.03.07.01.07.10 Tablero eléctrico instrumentación 120VAC ea 1.00 10.00 10.00 10.25 102.50 102.50 - 2,075.00 2,075.00 4,150.00 4,150.00 6,327.50 6,327.50

1700 1780 T 01.03.08 Loading Station and pumping

1700 1781 T 01.03.08.01 Activity 01

1700 01 01.03.08.01.01 Mining

1700 1780 1781 01 01.03.08.01.01.01 Loading Station and pumping 4442 lot 1.00 2,597.40 2,597.40 11.00 28,571.43 28,571.43 - 71,428.57 71,428.57 - 100,000.00 100,000.00

1700 1780 1781 01 01.03.08.01.01.02 - - - - - - - -

1700 02 01.03.08.01.02 Civil

1700 1780 1781 02 01.03.08.01.02.01 - - - - - - - -

Page 44: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

Prepared by: Julio Villanueva

Date: 27/01/2014

Review: B

Total

# WBS L2# WBS

L3

# WBS

L4Discip. Item Description UoM Quant Unit Cost

Unit Mhr Total Mhr Rate Unit Total Unit Total Unit Total Unit Total (US$) (US$)

CAPEX

SCOPING STUDY

SHAFT DESIGN - CHUCAPACA

209050-00014

Total Cost

Document Nr:

Project:

Project Nr:

Labour Manhour (mh) Labour Cost (US$) Material Cost (US$) Const Eqpt (US$) Process Eqpt (US$)

1700 1780 1781 02 01.03.08.01.02.02 - - - - - - - -

1700 03 01.03.08.01.03 Structural

1700 1780 1781 03 01.03.08.01.03.01 Concrete Structures f'c=280 kg/cm2 m3 291.00 7.98 2,322.18 9.50 75.81 22,060.71 387.26 112,692.66 12.89 3,750.99 - - 475.96 138,504.36

1700 1780 1781 03 01.03.08.01.03.02 Steel Structures ( include grizzlys) t 39.00 80.00 3,120.00 11.00 880.00 34,320.00 2,400.00 93,600.00 620.00 24,180.00 - - 3,900.00 152,100.00

1700 04 01.03.08.01.04 Mechanical

1700 1780 1781 04 01.03.08.01.04.01 Rock Breaker ea 2.00 327.27 654.55 11.00 3,600.00 7,200.00 - 2,400.00 4,800.00 30,000.00 60,000.00 36,000.00 72,000.00

1700 1780 1781 04 01.03.08.01.04.02 Grizzly (02ea) t 42.00 80.00 3,360.00 11.00 880.00 36,960.00 2,400.00 100,800.00 680.00 28,560.00 - - 3,960.00 166,320.00

1700 1780 1781 04 01.03.08.01.04.03 Crane 2t ea 2.00 169.75 339.49 11.00 1,867.20 3,734.40 - 1,244.80 2,489.60 15,560.00 31,120.00 18,672.00 37,344.00

1700 1780 1781 04 01.03.08.01.04.04 In-Line Chute Assembly ea 2.00 2,351.73 4,703.45 11.00 25,869.00 51,738.00 - 17,246.00 34,492.00 215,575.00 431,150.00 258,690.00 517,380.00

1700 1780 1781 04 01.03.08.01.04.04.01 01 Discharge Chute - - - - - - - -

1700 1780 1781 04 01.03.08.01.04.04.02 01 Vibrating Feeder - - - - - - - -

1700 1780 1781 04 01.03.08.01.04.04.03 01 Conveyor Loading Chute - - - - - - - -

1700 1780 1781 04 01.03.08.01.04.04.04 Support steel complete with access platform - - - - - - - -

1700 1780 1781 04 01.03.08.01.04.04.05 Handrails and stairways - - - - - - - -

1700 1780 1781 04 01.03.08.01.04.05 Belt Conveyor 36" L=80m ea 1.00 2,850.00 2,850.00 11.00 31,350.00 31,350.00 - 20,900.00 20,900.00 261,250.00 261,250.00 313,500.00 313,500.00

1700 1780 1781 04 01.03.08.01.04.06 Double Compartment Loading Station ea 1.00 5,490.55 5,490.55 11.00 60,396.00 60,396.00 - 40,264.00 40,264.00 503,300.00 503,300.00 603,960.00 603,960.00

1700 1780 1781 04 01.03.08.01.04.06.01 01 Transfer Chute - - - - - - - -

1700 1780 1781 04 01.03.08.01.04.06.02 02 Loading Flask - - - - - - - -

1700 1780 1781 04 01.03.08.01.04.06.03 02 Discharge Gate Arc Style - - - - - - - -

1700 1780 1781 04 01.03.08.01.04.06.04 02 Discharge Chute - - - - - - - -

1700 1780 1781 04 01.03.08.01.04.06.05 Access plataforms complete with handrails - - - - - - - -

1700 1780 1781 04 01.03.08.01.04.06.06 Ladder (caged) - - - - - - - -

1700 1780 1781 04 01.03.08.01.04.06.07 Stairways - - - - - - - -

1700 1780 1781 04 01.03.08.01.04.06.08 Support steel - - - - - - - -

1700 1780 1781 04 01.03.08.01.04.06.09 Load cell weight system complete with with weight indicate - - - - - - - -

1700 1780 1781 04 01.03.08.01.04.07 Loading Station Spares lot 1.00 - 11.00 - - - 15,780.67 15,780.67 - 15,780.67 15,780.67

1700 05 01.03.08.01.05 Piping

Dewatering Pumping System

1700 1780 1781 05 01.03.08.01.05.01 Positive displacement Pumps, 30HP, 20 l/s, TDH=180m ea 2.00 645.00 1,290.00 11.00 7,095.00 14,190.00 150,000.00 300,000.00 105,405.00 210,810.00 - 262,500.00 525,000.00

1700 1780 1781 05 01.03.08.01.05.02 Contention pond (civil works), Capacity 72m3 (Include asociated instrumentation)ea 1.00 509.09 509.09 11.00 5,600.00 5,600.00 12,000.00 12,000.00 2,400.00 2,400.00 - 20,000.00 20,000.00

1700 1780 1781 05 01.03.08.01.05.03 Vertical spindle Sump Pumps 5HP, 20 l/s, TDH=15m ea 2.00 700.00 1,400.00 11.00 7,700.00 15,400.00 14,000.00 28,000.00 2,800.00 5,600.00 - 24,500.00 49,000.00

1700 1780 1781 05 01.03.08.01.05.04 Sump (civil works), Capacity 6m3 ea 1.00 63.64 63.64 11.00 700.04 700.04 1,500.00 1,500.00 300.00 300.00 - 2,500.04 2,500.04

1700 1780 1781 05 01.03.08.01.05.05 Pipe Ø4" Sch 40, Flanges Class 150, Carbon Steel (Include Vlaves, accesories and painting)m 30.00 4.50 135.00 11.00 49.50 1,485.00 45.00 1,350.00 46.00 1,380.00 - 140.50 4,215.00

1700 06 01.03.08.01.06 Electrical

1700 1780 1781 06 01.03.08.01.06.01 Switchgear 4.16 kV, 630A, 60Hz, 3 Feeders 25kA ea 1.00 25.00 25.00 10.25 256.25 256.25 - 19,743.75 19,743.75 100,000.00 100,000.00 120,000.00 120,000.00

1700 1780 1781 06 01.03.08.01.06.02 Transformer 600kVA, 4160/480V, Dyn5 ea 1.00 18.00 18.00 10.25 184.50 184.50 - 4,815.50 4,815.50 25,000.00 25,000.00 30,000.00 30,000.00

1700 1780 1781 06 01.03.08.01.06.03 Motor Control Center 480V, 25kA, 60Hz, 1000A ea 1.00 100.00 100.00 10.25 1,025.00 1,025.00 - 26,975.00 26,975.00 140,000.00 140,000.00 168,000.00 168,000.00

1700 1780 1781 06 01.03.08.01.06.04 Panelboard 230V, 25kA, 60Hz, 60A ea 1.00 31.20 31.20 10.25 319.80 319.80 - 980.20 980.20 6,500.00 6,500.00 7,800.00 7,800.00

1700 1780 1781 06 01.03.08.01.06.05 Transformer 20kVA, 480/230V, Dyn5 ea 1.00 18.00 18.00 10.25 184.50 184.50 - 315.50 315.50 2,500.00 2,500.00 3,000.00 3,000.00

1700 1780 1781 06 01.03.08.01.06.06 Transformer 3.5kVA, 230/120V, Dyn5 ea 1.00 18.00 18.00 10.25 184.50 184.50 - 115.50 115.50 1,500.00 1,500.00 1,800.00 1,800.00

1700 1780 1781 06 01.03.08.01.06.07 UPS 1KVA, 120VAC, 1PH ea 1.00 2.00 2.00 10.25 20.50 20.50 - 219.50 219.50 1,200.00 1,200.00 1,440.00 1,440.00

1700 1780 1781 06 01.03.08.01.06.08 Bulk Materials (Lighting, welding socket, earthing, trays,etc) lot 1.00 63.41 63.41 10.25 650.00 650.00 6,500.00 6,500.00 650.00 650.00 - 7,800.00 7,800.00

1700 07 01.03.08.01.07 Instrumentation

1700 1780 1781 07 01.03.08.01.07.01 Sistema de telececomunicaciones incluye: Gabinete de telecomunicaciones pedestal ea 1.00 10.00 10.00 10.25 102.50 102.50 - 522.64 522.64 1,045.27 1,045.27 1,670.41 1,670.41

1700 1780 1781 07 01.03.08.01.07.02 switch de telecomunicaciones ea 1.00 3.70 3.70 10.25 37.93 37.93 - 1,394.88 1,394.88 2,789.76 2,789.76 4,222.57 4,222.57

1700 1780 1781 07 01.03.08.01.07.03 Transceiver SFP ea 2.00 3.00 6.00 10.25 30.75 61.50 - 480.08 960.15 960.15 1,920.30 1,470.98 2,941.95

1700 1780 1781 07 01.03.08.01.07.04 patch panel para fibra óptica ea 1.00 2.50 2.50 10.25 25.63 25.63 - 214.51 214.51 429.01 429.01 669.14 669.14

1700 1780 1781 07 01.03.08.01.07.05 Accesorios ea 1.00 78.79 78.79 10.25 807.60 807.60 1,000.00 1,000.00 500.00 500.00 - 2,307.60 2,307.60

1700 1780 1781 07 01.03.08.01.07.06 CCTV Incuye: Cámara IP -Térmica, ea 2.00 12.40 24.80 10.25 127.10 254.20 - 7,922.60 15,845.19 15,845.19 31,690.38 23,894.89 47,789.77

1700 1780 1781 07 01.03.08.01.07.07 Fuente para cámara IP ea 2.00 2.50 5.00 10.25 25.63 51.25 - 71.62 143.23 143.23 286.46 240.47 480.94

1700 1780 1781 07 01.03.08.01.07.08 PABX Incluye: Teléfono emergencia para trabajos en ambiente minero,ea 1.00 1.00 1.00 10.25 10.25 10.25 - 251.53 251.53 503.05 503.05 764.83 764.83

1700 1780 1781 07 01.03.08.01.07.09 conversor de medios ea 1.00 3.50 3.50 10.25 35.88 35.88 - 231.04 231.04 462.07 462.07 728.98 728.98

1700 1780 1781 07 01.03.08.01.07.10 LEAKY FEEDER Incluye: Amplificador, fin de línea y splitter ea 1.00 5.00 5.00 10.25 51.25 51.25 - 750.00 750.00 1,500.00 1,500.00 2,301.25 2,301.25

1700 1780 1781 07 01.03.08.01.07.11 Tablero eléctrico instrumentación 120VAC ea 1.00 10.00 10.00 10.25 102.50 102.50 - 2,075.00 2,075.00 4,150.00 4,150.00 6,327.50 6,327.50

1700 1790 T 01.03.09 Shaft Bottom

1700 1791 T 01.03.09.01 Activity 01

1700 01 01.03.09.01.01 Mining

1700 1790 1791 01 01.03.09.01.01.01 Shaft Bottom lot 1.00 3,896.10 3,896.10 11.00 42,857.14 42,857.14 - 107,142.86 107,142.86 - 150,000.00 150,000.00

1700 1790 1791 01 01.03.09.01.01.02 - - - - - - - -

1700 02 01.03.09.01.02 Civil

1700 1790 1791 02 01.03.09.01.02.01 - - - - - - - -

1700 1790 1791 02 01.03.09.01.02.02 - - - - - - - -

1700 03 01.03.09.01.03 Structural

1700 1790 1791 03 01.03.09.01.03.01 Concrete Structures f'c=280 kg/cm2 m3 40.00 7.98 319.20 9.50 75.81 3,032.40 387.26 15,490.40 12.89 515.60 - - 475.96 19,038.40

1700 1790 1791 03 01.03.09.01.03.02 Steel Structures t 25.00 80.00 2,000.00 11.00 880.00 22,000.00 2,400.00 60,000.00 620.00 15,500.00 - - 3,900.00 97,500.00

1700 04 01.03.09.01.04 Mechanical

1700 1790 1791 04 01.03.09.01.04.01 Spillage Winder 50 kW ea 1.00 3,218.18 3,218.18 11.00 35,400.00 35,400.00 - 23,600.00 23,600.00 295,000.00 295,000.00 354,000.00 354,000.00

1700 1790 1791 04 01.03.09.01.04.02 Wire Rope m 150.00 0.49 11.00 5.35 802.80 44.60 6,690.00 3.57 535.20 - 53.52 8,028.00

1700 1790 1791 04 01.03.09.01.04.03 Spillage car ea 1.00 125.45 11.00 1,380.00 1,380.00 - 920.00 920.00 11,500.00 11,500.00 13,800.00 13,800.00

1700 1790 1791 04 01.03.09.01.04.04 Spillage Sheave Wheel ea 1.00 114.55 114.55 11.00 1,260.00 1,260.00 - 840.00 840.00 10,500.00 10,500.00 12,600.00 12,600.00

1700 05 01.03.09.01.05 Piping

1700 1790 1791 05 01.03.09.01.05.01 - - - - - - - -

1700 1790 1791 05 01.03.09.01.05.02 - - - - - - - -

1700 06 01.03.09.01.06 Electrical

1700 1790 1791 06 01.03.09.01.06.01 Panelboard 480V, 25kA, 60Hz, 150A ea 1.00 31.20 31.20 10.25 319.80 319.80 - 2,180.20 2,180.20 12,500.00 12,500.00 15,000.00 15,000.00

Page 45: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

Prepared by: Julio Villanueva

Date: 27/01/2014

Review: B

Total

# WBS L2# WBS

L3

# WBS

L4Discip. Item Description UoM Quant Unit Cost

Unit Mhr Total Mhr Rate Unit Total Unit Total Unit Total Unit Total (US$) (US$)

CAPEX

SCOPING STUDY

SHAFT DESIGN - CHUCAPACA

209050-00014

Total Cost

Document Nr:

Project:

Project Nr:

Labour Manhour (mh) Labour Cost (US$) Material Cost (US$) Const Eqpt (US$) Process Eqpt (US$)

1700 1790 1791 06 01.03.09.01.06.02 Panelboard 230V, 25kA, 60Hz, 60A ea 1.00 31.20 31.20 10.25 319.80 319.80 - 980.20 980.20 6,500.00 6,500.00 7,800.00 7,800.00

1700 1790 1791 06 01.03.09.01.06.03 Transformer 20kVA, 480/230V, Dyn5 ea 1.00 18.00 18.00 10.25 184.50 184.50 - 315.50 315.50 2,500.00 2,500.00 3,000.00 3,000.00

1700 1790 1791 06 01.03.09.01.06.04 Transformer 3.5kVA, 230/120V, Dyn5 ea 1.00 18.00 18.00 10.25 184.50 184.50 - 115.50 115.50 1,500.00 1,500.00 1,800.00 1,800.00

1700 1790 1791 06 01.03.09.01.06.05 UPS 1KVA, 120VAC, 1PH ea 1.00 2.00 2.00 10.25 20.50 20.50 - 219.50 219.50 1,200.00 1,200.00 1,440.00 1,440.00

1700 1790 1791 06 01.03.09.01.06.06 Bulk Materials (Lighting, welding socket, earthing, trays,etc) lot 1.00 29.27 29.27 10.25 300.00 300.00 3,000.00 3,000.00 300.00 300.00 - 3,600.00 3,600.00

1700 07 01.03.09.01.07 Instrumentation

1700 1790 1791 07 01.03.09.01.07.01 Sistema de telececomunicaciones incluye: Gabinete de telecomunicaciones pedestal ea 1.00 10.00 10.00 10.25 102.50 102.50 - 522.64 522.64 1,045.27 1,045.27 1,670.41 1,670.41

1700 1790 1791 07 01.03.09.01.07.02 switch de telecomunicaciones ea 1.00 3.70 3.70 10.25 37.93 37.93 - 1,394.88 1,394.88 2,789.76 2,789.76 4,222.57 4,222.57

1700 1790 1791 07 01.03.09.01.07.03 Transceiver SFP ea 2.00 3.00 6.00 10.25 30.75 61.50 - 480.08 960.15 960.15 1,920.30 1,470.98 2,941.95

1700 1790 1791 07 01.03.09.01.07.04 patch panel para fibra óptica ea 1.00 2.50 2.50 10.25 25.63 25.63 - 214.51 214.51 429.01 429.01 669.14 669.14

1700 1790 1791 07 01.03.09.01.07.05 Accesorios ea 1.00 78.79 78.79 10.25 807.60 807.60 1,000.00 1,000.00 500.00 500.00 - 2,307.60 2,307.60

1700 1790 1791 07 01.03.09.01.07.06 CCTV Incuye: Cámara IP-IR con PoE ea 1.00 12.40 12.40 10.25 127.10 127.10 - 550.74 550.74 1,101.48 1,101.48 1,779.32 1,779.32

1700 1790 1791 07 01.03.09.01.07.07 PABX Incluye: Teléfono emergencia para trabajos en ambiente minero,ea 1.00 1.00 1.00 10.25 10.25 10.25 - 251.53 251.53 503.05 503.05 764.83 764.83

1700 1790 1791 07 01.03.09.01.07.08 conversor de medios ea 1.00 3.50 3.50 10.25 35.88 35.88 - 231.04 231.04 462.07 462.07 728.98 728.98

1700 1790 1791 07 01.03.09.01.07.09 LEAKY FEEDER Incluye: Amplificador, fin de línea y splitter ea 1.00 5.00 5.00 10.25 51.25 51.25 - 750.00 750.00 1,500.00 1,500.00 2,301.25 2,301.25

1700 1790 1791 07 01.03.09.01.07.10 Tablero eléctrico instrumentación 120VAC ea 1.00 10.00 10.00 10.25 102.50 102.50 - 2,075.00 2,075.00 4,150.00 4,150.00 6,327.50 6,327.50

9000 T 01.05 Indirect Cost

9000 9100 01.05.01 EPCM 1,051,168 912,681 1,980,214 3,944,063

9000 9200 01.05.03 Temporary Facilities 315,350 273,804 594,064 1,183,219

9000 9250 01.05.04 Temporary Services 525,584 456,340 990,107 1,972,031

9000 9300 01.05.05 CM Supplied Construction Equipment 105,117 91,268 198,021 394,406

9000 9400 01.05.06 Safety & Health 13,140 11,409 24,753 49,301

9000 9500 01.05.07 Freight 114,085 2,203,482 2,317,567

9000 9600 01.05.08 QAQC 52,558 45,634 99,011 110,174 307,377

9000 9610 01.05.09 Vendor Representatives 275,435 275,435

9000 9620 01.05.10 First Fill 330,522 330,522

9000 9650 01.05.11 Commisioning 220,348 220,348

9000 9700 01.05.12 Spares -

Contingency (25%) 123,062 1,829,689 1,617,156 3,446,809 3,539,344 10,432,999

615,310 9,148,447 8,085,782 17,234,047 17,696,718 52,164,993

Page 46: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

209050-00014-000-GE-REP-0001 32 Rev 0 (04-Feb-14)

ANNEX 2: OPEX

Page 47: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

Prepared by: Julio Villanueva

Date: 3‐Feb‐14

Project Nr: 2090‐00014 Review: 0

1,160,000 TPY

Item Quant $/t

Unit Mhr Total Mhr Unit Total1 OPEX

1.1 LABOR 0.74                         

1.1.1 Engineers – shared servie with trackless mining 0.50          $ 12,461.04 $ 6,230.52 $ 149,532.50 $ 74,766.25

1.1.3 Shaft operations Supervisors (Engineering) –  1 per day + relief 1.00          $ 3,030.64 $ 3,030.64 $ 36,367.65 $ 36,367.65

1.1.4 Boilermakers – 1 off (1 per day shared + relief)  1.00          $ 3,030.64 $ 3,030.64 $ 36,367.65 $ 36,367.65

1.1.5 Fitters – 1 per day shared + spare  1.00          $ 3,030.64 $ 3,030.64 $ 36,367.65 $ 36,367.65

1.1.6 Electrical – 3 off same as fitters Yes 3.00          $ 3,030.64 $ 9,091.91 $ 36,367.65 $ 109,102.94

1.1.7 Bell operators ‐ 3 3.00          $ 3,030.64 $ 9,091.91 $ 36,367.65 $ 109,102.94

1.1.8 Banksmen ‐ 3 3.00          $ 2,687.50 $ 8,062.50 $ 32,250.00 $ 96,750.00

1.1.9 Helpers ‐ 5 5.00          $ 2,687.50 $ 13,437.50 $ 32,250.00 $ 161,250.00

1.1.10 Loading operations – 2 operators per shift (one for silo control, one for the conveyor) 5.00          $ 2,687.50 $ 13,437.50 $ 32,250.00 $ 161,250.00

1.1.11 Supervisors for  lamp room ‐ 3 1.00          $ 3,030.64 $ 3,030.64 $ 36,367.65 $ 36,367.65

1.1.12 Lamp repairers   ‐            $ 3,030.64 $ 0.00 $ 36,367.65 $ 0.00

1.1.13 Shift controllers  ‐            $ 2,687.50 $ 0.00 $ 32,250.00 $ 0.00

1.1.14 Helpers for lamp issuing  ‐            $ 2,687.50 $ 0.00 $ 32,250.00 $ 0.00

1.2 MAINTENANCE COST ‐ CONSUMABLES 0.21                         

1.2.1 Ore handling at 3 % of equipment cost of $4 200 000 per annum 1.00          $ 10,500.00 $ 10,500.00 $ 126,000.00 $ 126,000.00

1.2.2 Winding plant at 1.5 % of equipment cost of $7 000 000 per annum 1.00          $ 8,750.00 $ 8,750.00 $ 105,000.00 $ 105,000.00

1.2.3 lamproom at 3 % of equipment cost of $300 000 per annum 1.00          $ 750.00 $ 750.00 $ 9,000.00 $ 9,000.00

1.3 POWER 0.90                         

1.3.1 Power cost during construciotn ‐            $ 17,700.00 $ 0.00 $ 212,400.00 $ 0.00

1.3.2 Power cost at full production 1.00          $ 87,019.00 $ 87,019.00 $ 1,044,228.03 $ 1,044,228.03

TOTAL COST $ 178,493 $ 2,141,921 1.85

Description

OPEXSCOPING STUDY

SHAFT DESIGN ‐ CHUCAPACA

Document Nr:

Project:

Annual Production:

Month (US$) Annual (US$)

Page 48: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

209050-00014-000-GE-REP-0001 33 Rev 0 (04-Feb-14)

ANNEX 3: WINDER DUTIES

Page 49: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

Winder: TH2 Chucapaca Shaft

Man Winder Vertical

Geared Cage / Cage

Hoisting & Lowering Load Double Drum

Run By: J Vollenbroek Run No: 1.00

For: TwoDeck hoisting 400m File No:

Drg No: double drum winder Date & Time April 2013

Note:

18.30

PRODUCTION: INPUT PRODUCTION: OUTPUT

Payload ---------- [tons] 5.00 CycleTime --------------------- [s] 283.86

Hrs Per Day ---------- 18.00 Trips Per Hour ----------------- 12.68

Days Per Month ------- 23.00 MenPerTrip -------------- 56.00

Length Of Wind -------- [m] 400.00 MenPerHour -------------- 710.22

Rope Speed --------- [m/s] 7.00 ROPE:

Accel ----------- [m/s^2] 0.25 Safety Factor 2 ------------ 6.52

Decel ----------- [m/s^2] 0.25 Safety Factor -------- [%] 144.82

Creep Out Speed ----- [m/s] 0.50 Capacity Factor ---------- 7.73

Creep In Speed ------ [m/s] 0.50 Capacity Factor ------- [%] 77.30

Creep Out Dist -------- [m] 5.00 Layers ------------------ 1.36

Creep In Dist --------- [m] 5.00 Actual D/d ratio -------- 106.67

Loading Pause -------- [s] 180.00 Ideal min. D/d ratio ---- 67.20

ROPE: Rope Pull ----------- [kN] 97.75

CageMass --------- [tons] [tons] 3.40 Coils Per Layer ----------- 47.00

No Counterweight ( = 0) 0.00 Height Above Drum ---- [mm] 55.53

Drum Diameter -------- [m] 3.20 MECHANICAL

LebusThickness ----- [mm] 0.00 RMS/Rated Torque ----- [%] 50.00

Drum Width ----------- [m] 1.50 Peak/Rated Torque (Max 180) [%] 125.37

Number Ropes ------------- 1.00 Peak/RMS torque ------ [%] 250.74

Rope Diameter ------- [mm] 30.00 RMS torque -------- [kN.m] 50.75

Rope Mass --------- [kg/m] 3.91 Peak Torque ------- [kN.m] 127.25

Break Force --------- [kN] 637.00 Rated Torque ------ [kN.m] 101.50

Tensile Strength --- [MPa] 1800.00 Calc Speed --------- [rpm] 56.45

Construction ----- Scaw ropes - 6x30 Tri Calc / Rated Speed ----- [%] 100.00

D/d factor -------------- 42.00 Gear Ratio --------------- 1.37

Dead Turns --------------- 25.00 ELECTRICAL

Pitch Factor ------------- 1.05 RMS Motor Power --- [kW] 464

Longest Distance ----- [m] 400.00 RMS Motor Current ------- [A] 0

Incline ----------- [deg] 90.00 Peak Accel / Decel Power -------- [kW] 752

MOTOR & GEAR: Peak Accel / Decel Current ------- [A] 0

============= (0=don't know) Accel / Decel Time -------- [s] [s] 26.00

Rated Speed -------- [rpm] 56.45 Static Power @ shaft bottom [kW]

Rated Power --------- [kW] 600.00 MISCELLANEOUS:

Rated Amps ----------- [A] Approx Diameter -- [feet] 10.50

Gear Ratio --------------- Approx Width ------ [feet] 4.92

Gear Efficiency ------ [%] 100.00 Drum Dia ------------- [m] 3.20

MISCELLANEOUS: Min Dia -------------- [m] 3.23

Inert Drum ------ [kg.m^2] 750000.00 Mean Dia ------------- [m] 3.25

Inert Sheave ---- [kg.m^2] 20000.00 Single Drum Accel - [m/s^2] 0.34

Inert Rotor ----- [kg.m^2] 25000.00 CageFactor ------------- 0.68

Shaft Efficiency ----- [%] 95.00 Natural Decel ---- [m/s^2] 0.04

Drum speed [rpm] 41.10

WINDER DUTY CYCLE CALCULATION

DOUBLE DRUM

Power consumption kw hr per cycle - Brace to lowest level

Manmaterial winder duty 27/01/2014

Page 50: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

Winder: TH2 Chucapaca Shaft

Rock Winder Vertical

Geared Skip / Skip

Hoisting & Lowering Load Double Drum

Run By: J Vollenbroek Run No: 1.00

For: Rock hoisting 455m File No:

Drg No: double drum winder Date & Time January 2014

Note:

14.78

PRODUCTION: INPUT PRODUCTION: OUTPUT

Payload ---------- [tons] 7.00 CycleTime --------------------- [s] 103.98

Hrs Per Day ---------- 18.00 Trips Per Hour ----------------- 34.62

Days Per Month ------- 23.00 Tons Per Hour ------------- 242.35

Length Of Wind -------- [m] 455.00 Tons Per Month ------------ 87400.00 100,333.25

Rope Speed --------- [m/s] 9.00 ROPE:

Accel ----------- [m/s^2] 0.30 Safety Factor 2 ------------ 6.71

Decel ----------- [m/s^2] 0.30 Safety Factor -------- [%] 149.21

Creep Out Speed ----- [m/s] 0.50 Capacity Factor ---------- 8.13

Creep In Speed ------ [m/s] 0.50 Capacity Factor ------- [%] 90.31

Creep Out Dist -------- [m] 3.00 Layers ------------------ 1.73

Creep In Dist --------- [m] 3.00 Actual D/d ratio -------- 91.43

Loading Pause -------- [s] 12.00 Ideal min. D/d ratio ---- 75.60

ROPE: Rope Pull ----------- [kN] 132.99

SkipMass --------- [tons] 4.20 Coils Per Layer ----------- 40.00

No Counterweight ( = 0) 0.00 Height Above Drum ---- [mm] 64.79

Drum Diameter -------- [m] 3.20 MECHANICAL

LebusThickness ----- [mm] 0.00 RMS/Rated Torque ----- [%] 70.34

Drum Width ----------- [m] 1.50 Peak/Rated Torque (Max 180) [%] 104.36

Number Ropes ------------- 1.00 Peak/RMS torque ------ [%] 148.37

Rope Diameter ------- [mm] 35.00 RMS torque -------- [kN.m] 142.78

Rope Mass --------- [kg/m] 5.18 Peak Torque ------- [kN.m] 211.84

Break Force --------- [kN] 893.00 Rated Torque ------ [kN.m] 203.00

Tensile Strength --- [MPa] 1800.00 Calc Speed --------- [rpm] 56.45

Construction ----- Scaw ropes - 6x30 Tri Calc / Rated Speed ----- [%] 100.00

D/d factor -------------- 42.00 Gear Ratio --------------- 1.08

Dead Turns --------------- 25.00 ELECTRICAL

Pitch Factor ------------- 1.05 RMS Motor Power --- [kW] 1023

Longest Distance ----- [m] 455.00 RMS Motor Current ------- [A] 0

Incline ----------- [deg] 90.00 Peak Accel / Decel Power -------- [kW] 1252

MOTOR & GEAR: Peak Accel / Decel Current ------- [A] 0

============= (0=don't know) Accel / Decel Time -------- [s] [s] 28.33

Rated Speed -------- [rpm] 56.45 Static Power @ shaft bottom [kW]

Rated Power --------- [kW] 1200.00 MISCELLANEOUS:

Rated Amps ----------- [A] Approx Diameter -- [feet] 10.50

Gear Ratio --------------- Approx Width ------ [feet] 4.92

Gear Efficiency ------ [%] 100.00 Drum Dia ------------- [m] 3.20

MISCELLANEOUS: Min Dia -------------- [m] 3.24

Inert Drum ------ [kg.m^2] 800000.00 Mean Dia ------------- [m] 3.27

Inert Sheave ---- [kg.m^2] 20000.00 Single Drum Accel - [m/s^2] 0.61

Inert Rotor ----- [kg.m^2] 25000.00 Skip Factor -------------- 0.60

Shaft Efficiency ----- [%] 95.00 Natural Decel ---- [m/s^2] 0.06

Drum speed [rpm] 52.49

WINDER DUTY CYCLE CALCULATION

DOUBLE DRUM

Power consumption kw hr per cycle - Brace to lowest level

Rock winder duty 27/01/2014

Page 51: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

209050-00014-000-GE-REP-0001 34 Rev 0 (04-Feb-14)

ANNEX 4: LOAD PROFILES

Page 52: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

0

200

400

600

800

1000

1200

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

kW

Hour

Diagram Load Construction

0

500

1000

1500

2000

2500

3000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

kW

Hour

Diagram Load Production

Page 53: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

209050-00014-000-GE-REP-0001 35 Rev 0 (04-Feb-14)

ANNEX 5: SCHEDULE

Page 54: TWP Shaft Report_209050-00014-000-GE-REP-0001-R0

Id Task Name Duración Comienzo Fin

1 Typical Shaft Sinking 1641 d lun 13/01/14 vie 24/04/20

2 PROJECT EXECUTION PERIOD 1641 d lun 13/01/14 vie 24/04/20

3 SECTION 1 : STUDY, CIVIL AND EARTH WORKS

726 d lun 13/01/14 lun 24/10/16

4 Prefeasibility study 96 d lun 13/01/14 lun 26/05/14

5 Stage gate review & approval 90 d mar 27/05/14 lun 29/09/14

6 Winder Purchase and installation 350 d mar 06/01/15 mar 10/05/16

7 Headgear purchase and installation 270 d mar 28/04/15 mar 10/05/16

8 Feasibility study 180 d mar 30/09/14 lun 08/06/15

9 Stage gate review & approval 90 d mar 09/06/15 lun 12/10/15

10 Power, access road and site preperation 90 d mar 13/10/15 lun 15/02/16

11 Shaft collar and winder civils 60 d mar 16/02/16 lun 09/05/16

12 Commision sinking winder and winder house 120 d mar 10/05/16 lun 24/10/16

13 Contractor site establishment 90 d mar 10/05/16 lun 12/09/16

14 SECTION 2 : SHAFT SINKING AND DEVELOPMENT - 5 dia

945 d mar 13/09/16 vie 24/04/20

15 SCHEDULE 1 : MAIN SHAFT SINK & LINE 945 d mar 13/09/16 vie 24/04/20

16 Pre-Sink 50m @ 0,7 m/d 71 d mar 13/09/16 mar 20/12/16

17 Slow-Sink [email protected] m/d 61 d mié 21/12/16 mié 15/03/17

18 Sink & Line to Level 1 - 147 m @ 2.2m/d 67 d jue 16/03/17 vie 16/06/17

19 Station Excavation and station D Development - 15 m @1,8 m/d

45 d lun 19/06/17 jue 17/08/17

20 Sink & Line to Level 2 - 50m @ 2.2 m/d 23 d vie 18/08/17 mar 19/09/17

21 Station Excavation and station D Development - 15 m @1,8 m/d

45 d mié 20/09/17 mar 21/11/17

22 Sink & Line to 3 Level - 50m @ 1.8m/d 23 d mié 22/11/17 vie 22/12/17

23 Station Excavation and station D Development - 15 m @1,8 m/d

45 d lun 25/12/17 vie 23/02/18

24 Sink & Line to Level 4 - 50m @ 1.8m/d 23 d lun 26/02/18 mié 28/03/18

25 Station Excavation and station D Development - 15 m @1,8 m/d

45 d jue 29/03/18 mié 30/05/18

26 Sink & Line to 5 Level - 78 m @ 1.8m/d 35 d jue 31/05/18 mié 18/07/18

27 Station Excavation and station D Development - 15 m @1,8 m/d

45 d jue 19/07/18 mié 19/09/18

28 Sink & Line to loading Level 50m @ 1.8m/d 28 d jue 20/09/18 lun 29/10/18

29 Station Excavation and station D Development 60m @1,8 m/d

60 d mar 30/10/18 lun 21/01/19

30 Sink & Line to Shaft Bottom - 40 m @ 2.2m/d 19 d mar 22/01/19 vie 15/02/19

31 Shaft bottom and second outlet 60 d lun 18/02/19 vie 10/05/19

32 Headgear changeover for equipping 30 d lun 13/05/19 vie 21/06/19

33 MAIN SHAFT EQUIPPING @ 140 m/month 100 d lun 24/06/19 vie 08/11/19

34 Headgear changeover to permanent and rope up

30 d lun 11/11/19 vie 20/12/19

35 Construct loading station 60 d lun 23/12/19 vie 13/03/20

36 Commission shaft 30 d lun 16/03/20 vie 24/04/20

M-1 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 M27 M28 M29 M30 M31 M32 M33 M34 M35 M36 M37 M38 M39 M40 M41 M42 M43 M44 M45 M46 M47 M48 M49 M50 M51 M52 M53 M54 M55 M56 M57 M58 M59 M60 M61 M62 M63 M64 M65 M66 M67 M68 M69 M70 M71 M72 M73 M74 M75 M76 M77 M

año 1 año 2 año 3 año 4 año 5 año 6

Chucapaca Shaft Project

Page 1 of 1 CHUCAPACA PROGRAM_RevA