Tutorial 1 - How to Steel Detail a Crushing Station

  • Upload
    venkiee

  • View
    219

  • Download
    0

Embed Size (px)

Citation preview

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    1/73

    1 | P a g e

    THE STEEL DETAILER

    V 3.02012

    TUTORIAL 1

    HOW TO DETAIL A

    CRUSHING STATION

    Date Revision Description

    8/3/2013 A INITIAL ISSUE

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    2/73

    2 | P a g e

    CONTENTSLESSON 1 - How to Install your Tutorial

    LESSON 2 - Project Log-In and Insert Driving Sketch Frame

    LESSON 3 - Insert Columns and Duplicate Members

    LESSON 4 - Insert Beams

    LESSON 5 - Copy Connections

    LESSON 6 - Copy Member

    LESSON 7 - Punch Holes

    LESSON 8 - Insert and Duplicate Bracing

    LESSON 9 - Insert Stairs

    LESSON 10 - Insert Handrails

    LESSON 11 - Insert Crusher

    LESSON 12 - Copy Project

    LESSON 13 - Lock Members

    LESSON 14 - Creating General Arrangements

    LESSON 15 - Update Drawing Revisions and Create PDFs

    LESSON 16 - Create Reports

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    3/73

    3 | P a g e

    LESSON 1 HOW TO INSTALL THE TUTORIAL

    PREREQUISITES

    SolidWorks 2012 or 2013 Installed. The Steel Detailer V3.0 Server or V4.0 Server Installed The Steel Detailer Member Library to be empty (Refer STEP 1)

    VIDEO - http://www.youtube.com/watch?v=6KXcSM75600

    STEP 1 If you have already uploaded Library Members before otherwise jump to LESSON 2

    Follow Step 1 and Backup Your Database

    Download and Install Microsoft SQL 2005 Management Studio SP3.0 For more

    information refer to The Steel Detailer Manual

    http://www.microsoft.com/en-au/download/details.aspx?id=14630

    1.1 Start The Management Studio inStart/All Programs

    Select the local instance to Which TheSteel Detailer Database id installed. Andthen Select Connect.

    1.2 Select Server objects and thenBack Up a Database

    http://www.youtube.com/watch?v=6KXcSM75600http://www.youtube.com/watch?v=6KXcSM75600http://www.youtube.com/watch?v=6KXcSM75600http://www.microsoft.com/en-au/download/details.aspx?id=14630http://www.microsoft.com/en-au/download/details.aspx?id=14630http://www.microsoft.com/en-au/download/details.aspx?id=14630http://www.microsoft.com/en-au/download/details.aspx?id=14630http://www.microsoft.com/en-au/download/details.aspx?id=14630http://www.youtube.com/watch?v=6KXcSM75600
  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    4/73

    4 | P a g e

    1.3 Select TheSteelDetailer for theDatabase. Then Select Add.

    1.4 Select Add then the . Button

    1.5 Select a file location that you will remember.

    Name the Filename and place a date at the end.

    Select OK 3 times.

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    5/73

    5 | P a g e

    1.6 Expand the Object Explorer out to see theMemberLibrary Table

    Right Mouse Click and Select Open Table

    1.7 Select holding down the shift key 1 thru and the last record and delete the records.

    Once there are empty rows, close Microsoft SQL Server 2005 Management Studio. You are readyto install the Tutorial

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    6/73

    6 | P a g e

    1.8 Backup Your Member Library Archives.

    You can find where the library archives are by selecting the link below

    C:\Windows\TSD Member Library Database Location.txt

    Browse to the folder that is called Member Library and rename it to Member Library2.

    This will also ensure that you keep a copy of the old Archives.

    STEP 2 Download Tutorial 1 for your country.

    STEP 3 Right mouse Click and Select Run as Administrator

    STEP 4 Select Next

    http://c/Windows/TSD%20Member%20Library%20Database%20Location.txthttp://c/Windows/TSD%20Member%20Library%20Database%20Location.txthttp://c/Windows/TSD%20Member%20Library%20Database%20Location.txt
  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    7/73

    7 | P a g e

    STEP 5 Accept the terms and then SelectNext

    STEP 6 Select the Local Install SQL ExpressInstance. In some situations it will have thename of your PC and then SQL Express. Selectthis if the other is not available.

    Leave the preset settings and

    Select Next.

    STEP 7 Select Install

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    8/73

    8 | P a g e

    The following File Structure and files have been installed for the tutorial

    C:\The Steel Detailer \ TSD Australian Trial Tutorials Depending on Country Installed.

    The following Members have been added to the Weldment Member Library

    http://c/The%20Steel%20Detailer/http://c/The%20Steel%20Detailer/http://c/The%20Steel%20Detailer/
  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    9/73

    9 | P a g e

    LESSON 2 PROJECT LOGIN AND INSERT DRIVING SKETCH PREREQUISITES

    LESSON 1 Completed Installed the TSD Tutorial for 2012 OR 2013

    VIDEO - http://www.youtube.com/watch?v=kQ9XGy-wJZw

    STEP 1 Select TSDProjects TSD Login

    STEP 2 Select Project 9999

    http://www.youtube.com/watch?v=kQ9XGy-wJZwhttp://www.youtube.com/watch?v=kQ9XGy-wJZwhttp://www.youtube.com/watch?v=kQ9XGy-wJZwhttp://www.youtube.com/watch?v=kQ9XGy-wJZw
  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    10/73

    10 | P a g e

    STEP 3 Select WBS Code AA, TUTORIAL PROJECT

    STEP 4 Select LOG-IN

    STEP 5 Ensure 9999-AA is open and Select Top Plane and Select Create Sketch

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    11/73

    11 | P a g e

    STEP 6 Insert SketchPoint on Origin

    You can rename thesketch to anything youlike

    STEP 7 Select TSDMembers menu, select FRAMES

    STEP 8 Select the Model Picture of the Frame

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    12/73

    12 | P a g e

    STEP 9 Select the Sketch Point Radial Button

    STEP 10 *Select the Sketch Point inthe Graphics Area

    STEP 11 Select the Green Tick

    STEP 12 Select the Red X or press Escape to close the Member window after the frame has beeninserted.

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    13/73

    13 | P a g e

    LESSON 3 INSERT COLUMNS AND DUPLICATE MEMBERS

    PREREQUISITES

    LESSON 2 Completed

    VIDEO - http://www.youtube.com/watch?v=f8XUKKsBPvg

    STEP 1 Select TSDMembers menu, Select Columns

    STEP 2 Select the Model Picture of the Column

    STEP 3 Select Sketch FrameVertical Sketch Segment

    http://www.youtube.com/watch?v=f8XUKKsBPvghttp://www.youtube.com/watch?v=f8XUKKsBPvghttp://www.youtube.com/watch?v=f8XUKKsBPvghttp://www.youtube.com/watch?v=f8XUKKsBPvg
  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    14/73

    14 | P a g e

    STEP 4 Select Green Tick

    STEP 5 Repeatstep 2,3 &4 toinsert thenext column.

    STEP 6 Select the Red X or press Escape to close the Member window after the columnshave been inserted.

    STEP 7 Rebuild and Save

    STEP 8 Select the 2unrequiredcleats onColumn 001BasePlateConnectionandSuppressthem

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    15/73

    15 | P a g e

    STEP 9 Selectthe 4 sketches

    associatedwith theunrequiredcleats andhide them

    STEP 10 EditThe MemberSketch Next toEach Cleat inthe COLUMNWeldmentMemberBasePlateConnection

    STEP 11 Makethe MemberSketch line

    PARALLEL tothe framelayout sketch.The sketch willbe fullydefined. Dothis for bothbrace cleats inthe column.

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    16/73

    16 | P a g e

    STEP 12

    Repeat step 8-11 for Column2. Your 2columns willnow look likethis

    STEP 13 Select TSDMembers Menu and DuplicateMember

    STEP 14 Select

    the main SteelSection in theModel of theWeldmentMember toDuplicate

    STEP 15 Selectthe MemberSketch FrameVertical LegDIAGONALY inopposite corner.

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    17/73

    17 | P a g e

    STEP 16 Select the Tick

    STEP 17 Delete the duplicate mate that aligns the duplicated column

    STEP 18 Rotate the duplicated column to the correct orientation by flipping the alignment of theParallel mate

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    18/73

    18 | P a g e

    STEP 19 Repeat Step 14. Thru 18. on the opposite column. Your model will look like this

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    19/73

    19 | P a g e

    LESSON 4 INSERT AND DUPLICATE BEAMS

    PREREQUISITES

    LESSON 3 Completed

    VIDEO - http://www.youtube.com/watch?v=uWB9pLsV8a8

    STEP 1 Select TSDMembers menu, Select Beams

    STEP 2 Select the 1 st Model Picture of the Beam

    STEP 3 SelectSketch FrameHorizontal SketchSegment

    http://www.youtube.com/watch?v=uWB9pLsV8a8http://www.youtube.com/watch?v=uWB9pLsV8a8http://www.youtube.com/watch?v=uWB9pLsV8a8http://www.youtube.com/watch?v=uWB9pLsV8a8
  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    20/73

    20 | P a g e

    STEP 4 Select Green Tick

    STEP 5 Select the Red X or press Escape to close the Member window after the beam has beeninserted.

    STEP 6 Select The Beam MemberAssembly 9999-AABE001 and theFrame Member Assembly holdingctrl down Right Mouse Click andselect Isolate

    STEP 7 In Beam 9999-AABE001Right Mouse Select the CN05-CP02 Sketch and Edit Sketch from the flyout toolbar.

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    21/73

    21 | P a g e

    STEP 8 On the Right end of the Beam select the sketch point and DELETE any existing relationshipsand place it over the intersecting point of the frame

    STEP 9 Do this also for CN04-CP02

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    22/73

    22 | P a g e

    STEP 10 And AlsoCN03-BR01

    STEP 11 Select TSDMembers menu and then Duplicate Member

    STEP 12 Select the MainSelection on the Beam

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    23/73

    23 | P a g e

    STEP 13 Then select theSketch segment line on

    the far end

    STEP 14 Select Green Tick

    STEP 15 Select TSDMembers menu and Select Beams

    STEP 16 Select the Second Beam Model type

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    24/73

    24 | P a g e

    STEP 17 Select the FarLeft top sketch segment

    STEP 18 Select the Green Tick

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    25/73

    25 | P a g e

    LESSON 5 COPY CONNECTIONS

    PREREQUISITES

    LESSON 4 Completed

    VIDEO - http://www.youtube.com/watch?v=3TuZkfUJ1_s

    STEP 1 Select TSDConnections, Copy Connection

    STEP 2 Select the Plate on the Bracing Connection on the Front Beam

    STEP 3 Select the Intersection Point on the rear of the Sketch Frame

    http://www.youtube.com/watch?v=3TuZkfUJ1_shttp://www.youtube.com/watch?v=3TuZkfUJ1_shttp://www.youtube.com/watch?v=3TuZkfUJ1_shttp://www.youtube.com/watch?v=3TuZkfUJ1_s
  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    26/73

    26 | P a g e

    STEP 4 Select the Main Section of the rear Beam

    STEP 5 Select any other beam

    STEP 6 Select the Green Tick

    STEP 7 Select ThePerpendicular Mate

    and Edit the Feature

    STEP 8 Change to aCoincident Mate

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    27/73

    27 | P a g e

    STEP 9 Flip the matealignment

    STEP 10 We will now insert the centre beams. Select TSDMembersmenu and Select Beams

    STEP 11 Select the Third Beam Model type

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    28/73

    28 | P a g e

    STEP 12 Select the sketch line as shown

    STEP 13 Select the Green Tick

    STEP 14 Repeat STEP 10 to STEP 13 for the next 2sketch lines as shown

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    29/73

    29 | P a g e

    STEP 15 Select TSDConnections, Copy Connection

    STEP 16 On thefirst of the 3 newbeamconnections,select the face of

    the connectioncleat

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    30/73

    30 | P a g e

    STEP 17

    Select the

    intersectionpoint for theconnection

    STEP 18 Select themember thatthe newconnectionwill be

    welded to

    STEP 19 Select any other beam

    STEP 20 Select the Green Tick

    STEP 21 Suppress and Unsuppress the new connection.

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    31/73

    31 | P a g e

    STEP 22 Rotate thenewconnection inBeam 9999-AABE002 toalign with thebeam

    STEP 23 Theconnectionnow looks likethis

    STEP 24 Openbeam

    9999-AABE002

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    32/73

    32 | P a g e

    STEP 25 Edit the properties of the new fin plate and uncheck the exclude from bill of materials box

    STEP 26

    Suppress the

    fasteners.

    STEP 27 Repeat step 30 to step 40 to copy connections from the other 2 internal beams

    STEP 28 At this stage we would recommend updating the drawing of the beam with the newconnection and the drawings of the connections before copying the beam.

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    33/73

    33 | P a g e

    STEP 29 Right mouse click on the beam assembly9999-AABE002 to open the drawing

    STEP 30 Select TSD Utilities, Hide Excluded Componentsin Drawings.

    If adding a view after using this function, you must run itagain.

    STEP 31 Update the drawing, add dimensions and sections as required to locate the new fin platesand brace cleat.

    STEP 32 Open the drawing of the beam by Right Mouse clicking on a face of the beam

    STEP 33 Adjust the views and dimensions to fit on the page.

    STEP 34 Open the Fin plate drawing and the Brace cleat drawing in the same way and update themas required.

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    34/73

    34 | P a g e

    LESSON 6 COPY MEMBER

    PREREQUISITES

    LESSON 5 Completed

    VIDEO - http://www.youtube.com/watch?v=Kc6GfEfjKB8

    STEP 1 To copy the rear beam you must delete all external references outside of the beamassembly. This will be on the first Member Sketch and some of the connection sketches at thebottom of the beam assembly. They will need to be redefined afterthe copy process is completed.

    STEP 2 Select TSDMembers and Copy Member

    STEP 3 Select theMainSection ofthe rearbeam

    STEP 4 Select the front Sketch Frame Line Segment

    http://www.youtube.com/watch?v=Kc6GfEfjKB8http://www.youtube.com/watch?v=Kc6GfEfjKB8http://www.youtube.com/watch?v=Kc6GfEfjKB8http://www.youtube.com/watch?v=Kc6GfEfjKB8
  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    35/73

    35 | P a g e

    STEP 5 Select Green Tick

    STEP 6 Redefine the sketch relations that were deleted to do the copy member.

    STEP 7 Define the connection points in the new copied beam by isolating the new beam and the firstframe member

    STEP 8 Exit Isolate.

    STEP 9 The connections on the new beam need to be reversed to align with the fin plates on theintersecting beams.

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    36/73

    36 | P a g e

    STEP 10 Suppress the existingfin plate in the connection of

    the new beam

    STEP 11 Unsuppress the alternate fin plate

    STEP 12 Repeat step 10to 11for the remaining 2 fin plate

    connections on the newbeam.

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    37/73

    37 | P a g e

    LESSON 7 PUNCH HOLES

    PREREQUISITES

    LESSON 6 Completed

    VIDEO - http://www.youtube.com/watch?v=aLlzDNGZdTc

    STEP 1 Select TSDUtilities Punch Holes

    STEP 2 Select the

    back of the plate atthe lower left corner

    STEP 3 Select the farface of the FrontBeam Web

    STEP 4 Select Green Tick.

    STEP 5 Do this also for the other end of the samebeam.

    STEP 6 Do NOT attempt to punch holes in the beam on the far side as this is a duplicate beam

    http://www.youtube.com/watch?v=aLlzDNGZdTchttp://www.youtube.com/watch?v=aLlzDNGZdTchttp://www.youtube.com/watch?v=aLlzDNGZdTchttp://www.youtube.com/watch?v=aLlzDNGZdTc
  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    38/73

    38 | P a g e

    LESSON 8 INSERT AND DUPLICATE BRACING

    PREREQUISITES

    LESSON 7 Completed

    VIDEO - http://www.youtube.com/watch?v=gV30-EISC3g

    STEP 1 Isolate Beam9999-AABE001 and theframe sketch.

    STEP 2 Expand theFeature tree down to

    the first connection.Edit Member Sketch2

    STEP 3 Make thesketch line Parallel tothe Bracing set outsketch line

    http://www.youtube.com/watch?v=gV30-EISC3ghttp://www.youtube.com/watch?v=gV30-EISC3ghttp://www.youtube.com/watch?v=gV30-EISC3ghttp://www.youtube.com/watch?v=gV30-EISC3g
  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    39/73

    39 | P a g e

    STEP 4 Exitthe sketch.

    STEP 5 EditMemberSketch3

    STEP 6 Make thesketch lineparallel tothe bracing

    set outsketch

    STEP 7 EditAssembly and exit Isolate. There is no need to do this on the opposite beam because its the same.

    STEP 8 Repeat Step1 to Step 7for theotherBeams9999-AABE002and 9999-

    AABE006

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    40/73

    40 | P a g e

    STEP 9 Select TSDMembers menu, select Bracing

    STEP 10 Select the 1st

    Model Picture of thebracing

    STEP 11 Select thefront left bracingsketch segment

    STEP 12 Select the Green Tick

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    41/73

    41 | P a g e

    STEP 13 Select the Red X or press Escape to close the Member window after the brace has beeninserted.

    STEP 14 Create a Parallel mate between the Front plane of thebrace to the front plane of the assembly to fully define the brace.

    STEP 15 Isolate the brace, column 1 and beam 1.

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    42/73

    42 | P a g e

    STEP 16 Select the Left Cut Sketch in the brace and edit sketch

    STEP 17 Delete the 400dimension defining the end cutof the brace

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    43/73

    43 | P a g e

    STEP 17 Make the top right sketch segment collinear to the set out line as shown

    STEP 18 Exit the sketch and rebuild. The end cut andfasteners will be in the correct position.

    STEP 19 Selectthe Right CutSketch in thebrace and editsketch

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    44/73

    44 | P a g e

    STEP 20 Delete the dimensiondefining the end cut of the

    brace

    STEP 21 Make thebottom left sketchsegment collinearto the set out lineas shown

    STEP 22 Exit the sketch and rebuild. The end cut andfasteners will be in the correct position.

    STEP 23 Select TSDMembers menu, select Bracing

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    45/73

    45 | P a g e

    STEP 24 Select the 2 nd Model Picture of the bracing

    STEP 25 Select thefront rightbracing sketchsegment

    STEP 26 Select the Green Tick

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    46/73

    46 | P a g e

    STEP 27 Select the Red X or press Escape to close the Member window after the brace has beeninserted.

    STEP 28 Create a Parallel mate between the Front plane ofthe brace to the front plane of the assembly to fully definethe brace.

    STEP 29 Isolate thebrace,column 2and beam 1.

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    47/73

    47 | P a g e

    STEP 30 Repeat step 16 to 23 to define the ends of brace 2.

    NOTE! If abrace is onthe wrongside of theset outline, fliptheparallelmate

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    48/73

    48 | P a g e

    STEP 31 Repeat Steps 9to 31 to insert the 2bracing members onthe far left side.

    STEP 32 Suppress thecope cut at the bottomof brace 3.

    STEP 33 Suppress thecope cut at the bottomof brace 4.

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    49/73

    49 | P a g e

    STEP 34 Yourmodel will

    look like this

    STEP 35 FollowingLESSON 2, Step13 to 16Duplicate thefront bracingto the far side.

    STEP 36 Thenduplicate thebracing fromthe far left tothe right hand

    side

    NOTE! SomeBracing willrequire aparallel mateto define itfully in theassembly.

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    50/73

    50 | P a g e

    LESSON 9 INSERT STAIRS

    PREREQUISITES

    LESSON 8 Completed

    VIDEO - http://www.youtube.com/watch?v=wda25oE3aNI

    STEP 1 Select TSDMembers menu, select STAIRS

    STEP 2 Select the Model Picture of the stair

    STEP 3 Select the horizontalsketch segment in the stairlayout sketch

    http://www.youtube.com/watch?v=wda25oE3aNIhttp://www.youtube.com/watch?v=wda25oE3aNIhttp://www.youtube.com/watch?v=wda25oE3aNIhttp://www.youtube.com/watch?v=wda25oE3aNI
  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    51/73

    51 | P a g e

    STEP 4 Select the diagonal sketchsegment in the stair layout sketch

    Step 5 Select the green tick

    Step 6 Select the Red X or pressEscape to close the Member

    window after the stair has beeninserted.

    Step 7 Isolate the stair and theframe assembly.

    STEP 8 In the drivingsketch part 9999-AAST001D01, Edit theTread and Grating

    Sketch

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    52/73

    52 | P a g e

    STEP 9 Select the top leglength dimension and make itdriven

    STEP 10 Select the end point ofthe top sketch line and make itcoincident to the end point ofthe stair set out sketch

    STEP 11 Exit the sketch andIsolation, then rebuild withCTRL Q,

    STEP 12 Copy the fin plateconnections from the stair tothe beam. Refer to LESSON 5.

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    53/73

    53 | P a g e

    LESSON 10 INSERT HANDRAILS

    PREREQUISITES

    LESSON 9 Completed

    VIDEO - http://www.youtube.com/watch?v=qnOwT6-LcN4

    STEP 1 Isolate the Frameassembly

    STEP 2 Select TSDMembers menu, select HANDRAILS

    STEP 3 Select the 1 ST Model Picture of the Top Mountedhandrail

    http://www.youtube.com/watch?v=qnOwT6-LcN4http://www.youtube.com/watch?v=qnOwT6-LcN4http://www.youtube.com/watch?v=qnOwT6-LcN4http://www.youtube.com/watch?v=qnOwT6-LcN4
  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    54/73

    54 | P a g e

    STEP 4 Select the sketch optio

    STEP 5 Select the top sketch

    name Level 1 Beam Sketch

    STEP 6 Select the green tick

    STEP 7 Select theRed X or pressEscape to closethe Memberwindow after thestair has beeninserted.

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    55/73

    55 | P a g e

    STEP 8 Show thestair assemblyalso.

    STEP 9 In thefeature tree,expand thehandrail abovethe stair (9999-

    AAHA002) andedit MemberSketch

    STEP 10 Delete theEqual Lengthrelation

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    56/73

    56 | P a g e

    STEP 11 Dimensionthe endpoint to thesketch pointfor the stairfin plateconnection.

    STEP 12 Exit the sketch and rebuild.

    STEP 13 Select TSDMembers menu, select HANDRAILS

    STEP 14 Select the 2 nd Model Picture of the Top Mounted handrail

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    57/73

    57 | P a g e

    STEP 15 Select thehorizontal sketch segmentin the left hand stringerlayout sketch

    STEP 16 Select the lefthand diagonal sketchsegment in stringer layoutsketch

    STEP 17 Select the green tick

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    58/73

    58 | P a g e

    STEP 18 Select the 3 rd ModelPicture of the Top Mounted

    handrail

    STEP 19 Select the horizontalsketch segment in the righthand stringer layout sketch

    STEP 20 Select the diagonalsketch segment in the right

    hand stringer layout sketch

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    59/73

    59 | P a g e

    STEP 21 Select the green tick

    STEP 22 Select theRed X or pressEscape to close theMember windowafter the handrails

    have been inserted.

    STEP 23 Adjust theMember sketch onHandrail 2 (9999-

    AAHA002) to get thecorrect gap to thestair handrail

    STEP 24 Edit theHandrail SetoutSketch for handrail 2

    STEP 25 Adjust thekickplate offsetdimension to bringto 2 kickplatestogether

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    60/73

    60 | P a g e

    STEP 26 Exit the sketch and rebuild.

    STEP 27 Following LESSON 6, punch holes from the handrail base plates through the top flanges ofthe beams and stair stringers

    STEP 28 Your model will look like this

    And with sketches hidden-

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    61/73

    61 | P a g e

    LESSON 11 INSERT CRUSHER

    PREREQUISITES

    LESSON 10 Completed

    VIDEO - http://www.youtube.com/watch?v=acAC0YLysQk

    STEP 1 Select TSDMembers menu, Select Vendor Equipment

    STEP 2 Select CRUSHER for ModelType and TSD for Model Supplier,

    Select the ModelType, Select Sketch Point

    STEP 3 Select Sketch Frame Sketch Point

    STEP 4 Select Green Tick

    http://www.youtube.com/watch?v=acAC0YLysQkhttp://www.youtube.com/watch?v=acAC0YLysQkhttp://www.youtube.com/watch?v=acAC0YLysQkhttp://www.youtube.com/watch?v=acAC0YLysQk
  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    62/73

    62 | P a g e

    LESSON 12 COPY PROJECT

    PREREQUISITES

    LESSON 11 Completed

    VIDEO - http://www.youtube.com/watch?v=0Yu9-lj2Tvo

    STEP 1 Close the Assembly and anythingelse, but leave SolidWorks open.

    STEP 2 Select TSDProjects, Copy Project

    STEP 3 Select Get SQL Servers

    STEP 4 Select SQL Server Instance[(Local)/SQLExpress, is the default].Select Project to Copy(9999,TUTORIAL PROJECT)

    Select Get Files

    Note: The picture is an example.

    http://www.youtube.com/watch?v=0Yu9-lj2Tvohttp://www.youtube.com/watch?v=0Yu9-lj2Tvohttp://www.youtube.com/watch?v=0Yu9-lj2Tvohttp://www.youtube.com/watch?v=0Yu9-lj2Tvo
  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    63/73

    63 | P a g e

    STEP 5 Select SQL Server Instance [(Local)/SQLExpress, is the default].

    Enter Data as per the image to the right.

    Select Update List

    Note: The picture to the right is an example only.

    STEP 6 Select Create

    STEP 7 Select Exit

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    64/73

    64 | P a g e

    STEP 8 Select TSDProjects, Project Login,

    STEP 9 Select Project 9997, COPY TUTORIAL PROJECT 1, Select AA,TUTORIAL PROJECT for WBS Code

    Select LOG-IN

    STEP 10 Saveand Close

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    65/73

    65 | P a g e

    LESSON 13 LOCK MEMBERS

    PREREQUISITES

    LESSON 12 Completed

    VIDEO - http://www.youtube.com/watch?v=51bgSPTX74A

    STEP 1 Select TSDProjects TSD Login

    STEP 2 Select Project 9999

    STEP 3 Select WBS Code AA, TUTORIAL PROJECT

    STEP 4 Select LOG-IN

    http://www.youtube.com/watch?v=51bgSPTX74Ahttp://www.youtube.com/watch?v=51bgSPTX74Ahttp://www.youtube.com/watch?v=51bgSPTX74Ahttp://www.youtube.com/watch?v=51bgSPTX74A
  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    66/73

    66 | P a g e

    STEP 5 Select TSDMembers, Lock Member

    STEP 6 Select the Main Section of theColumn 001

    STEP 7 Select the Bolted Connection for capturing the Bolts with theMember,

    I.e. BP01 is the connection that has the Bolts for the baseplateconnection.

    STEP 8 Hit Green Tick

    STEP 9 After Lock has occurred, Hit Ctr Q and Ctr S

    STEP 10 Repeat STEPS 5 - 9 until all Members are completed

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    67/73

    67 | P a g e

    The completed model should look like this, after all Members are locked.

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    68/73

    68 | P a g e

    LESSON 14 CREATING GENERAL ARANGEMENTS

    PREREQUISITES

    LESSON 13 Completed

    VIDEO - http://www.youtube.com/watch?v=XXsEUDIlBk0

    STEP 1 Select File Menu, New

    Any A3 Drawing Sheet is good.

    STEP 2 Select Next

    STEP 3 Insert a side Elevationof 9999-AA, Hit the Green Tick

    http://www.youtube.com/watch?v=XXsEUDIlBk0http://www.youtube.com/watch?v=XXsEUDIlBk0http://www.youtube.com/watch?v=XXsEUDIlBk0http://www.youtube.com/watch?v=XXsEUDIlBk0
  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    69/73

    69 | P a g e

    STEP 4 Select View Layout Tab in theCommand Manager, then Project View

    Place 3 More Views, TOP, LEFT, ISOMETRIC

    STEP 5 Change Scale to suit ie A3 (1:75)

    Right Mouse Click Drawing, Select Properties

    STEP 6 Select the Annotation TAB on the CommandManager, Note

    STEP 7 Select ColumnC001 Edge and Pick tothe left of the Column,then select Link toProperty.

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    70/73

    70 | P a g e

    STEP 8 Select Component towhich., then Select AssemblyDoc

    as field

    STEP 9 Click of to the side to setthe note

    STEP 10 Copy the annotationcreated in 7 from 1 Section toanother and notice the updatedsection.

    If the note does not displayanything it means the memberhas not been locked.

    STEP 11 Save the General Arrangement in the WBS 9999-AA directory.

    C:\The Steel Detailer \ \ Project\9999\9999-AA\

    - Your Country.

    http://c/The%20Steel%20Detailer/http://c/The%20Steel%20Detailer/http://c/The%20Steel%20Detailer/
  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    71/73

    71 | P a g e

    LESSON 15 UPDATING REVISIONS AND CREATE PDFs

    PREREQUISITES

    LESSON 14 Completed

    VIDEO - http://www.youtube.com/watch?v=T11ZfQHJpX8

    STEP 1 Select TSDDrawings, Document Manager

    STEP 2 Select Document Status Filter, Locked

    STEP 3 Select the Select All Tick

    STEP 4 Select Modify Revisions

    STEP 5 Select Update Current Revision Radial Button, Enter in Data,Select Update,

    http://www.youtube.com/watch?v=T11ZfQHJpX8http://www.youtube.com/watch?v=T11ZfQHJpX8http://www.youtube.com/watch?v=T11ZfQHJpX8http://www.youtube.com/watch?v=T11ZfQHJpX8
  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    72/73

    72 | P a g e

    STEP 6 Select OK

    STEP 7 Select Create PDFs

    STEP 8 Select UPDATE

    STEP 9 After PDFs ar e Complete,Check the PDF folder found

    C:\The Steel Detailer\

  • 8/13/2019 Tutorial 1 - How to Steel Detail a Crushing Station

    73/73

    LESSON 16 CREATE REPORTS

    PREREQUISITES

    LESSON 15 Completed

    VIDEO - http://www.youtube.com/watch?v=A-paxBEE1_Q

    STEP 1 Select TSDDrawings, Reports

    STEP 2 Select CUT LIST

    A Material Cut List is created

    STEP 3 Select Total Radial Button, then BOLT LIST

    A Total Bolt List is created

    STEP 4 Select By Member, Then BOLT LIST

    A By Member Bolt List is created

    STEP 5 VENDOR LIST

    A Vendor List is created

    STEP 6 Select FLAT BAR LIST

    A Flat Bar List is created

    STEP 7 Select PLATE LIST

    A Plate List is created

    Note: All reports are place into respective folder in the Project Folder

    C:\The Steel Detailer \ TSD Australian Trial Tutorials\Project\9999

    - Your Country.

    http://www.youtube.com/watch?v=A-paxBEE1_Qhttp://www.youtube.com/watch?v=A-paxBEE1_Qhttp://www.youtube.com/watch?v=A-paxBEE1_Qhttp://c/The%20Steel%20Detailer/http://c/The%20Steel%20Detailer/http://c/The%20Steel%20Detailer/http://www.youtube.com/watch?v=A-paxBEE1_Q