Aker Construction Trade& Industrial INC. GAZA-TURKISH PALESTINE FRIENDSHIP HOSPITAL MONTHLY PROGRESS REPORT Month: End of September 2011

Turkish Palestine Friendship Hospital

Embed Size (px)

Citation preview

Page 1: Turkish Palestine Friendship Hospital

Aker Construction Trade& Industrial INC.

GAZA-TURKISH PALESTINE FRIENDSHIP

HOSPITAL

MONTHLY PROGRESS REPORT

Month: End of September 2011

Page 2: Turkish Palestine Friendship Hospital

2

CONSTRUCTION PROGRESS REPORT

( Sep. 2011)

1. Name of Project : GAZA-TURKISH PALESTINE FRIENDSHIP HOSPITAL

Contract No. : AKER-GZ/2011

2. Client : Turkish Development and Cooperation Agency – TIKA

Consultant : Islamic University – Gaza " Engineering Office "

Contractor : Aker Construction Trade& Industrial INC.

3. Site handing over date Actual Start Scheduled Finish

05/ 05 / 2011 14 / 06 / 2011 31 /05 / 2013

6. Occurrences /hindrances unexpected and unforeseen

None

4. Subcontractors working at site during reporting period :

Subcontractor : Saqqa & Khoudary Co. Ltd.

5. Manpower

(Monthly average )

Project manager

Administrative Manager

Engineers

Safety officer

Accountant

Forman

Surveyor

Assistant surveyor

Skilled labor

Unskilled labor

Driver

Office Boy

Guard man

24

24

401

38

24

288

53

54

1859

1006

72

48

72

Total on site 3963

Page 3: Turkish Palestine Friendship Hospital

3

7.

Financial Matter

Total Amount : $34,000,000

8.

Material at site :

Material Qty for this month Total

Steel Bars 388.16 Tons 952.81 tons

Waterproof membrane 4500 m2 17000 m2

Timber formwork 208.55 m3 351.22 m3

9.

Equipment on site :

Equipment No. No. of working day

Compressor 2 22

Water pump 2 24

Generator 1 24

Cutting Machine 3 24

Welding machine 1 0

Mobile Crane 1 24

Vibrator 3 20

Loader 1 14

Compactor 2 6

Concrete pump 20 -

Concrete mixer 295 -

Total station 2 18

Level 2 24

Petroleum tank 2 24

Water tank 10 24

Back-hoe excavator 1 3

Page 4: Turkish Palestine Friendship Hospital

4

10. Work Performed during report period:

Complete the placing concrete for mat foundation at block A-A',B-B', Qty = 838 m3.

Complete the placing concrete for mat foundation at block F-G, Qty= 1187 m3.

Complete the placing concrete for R.C walls and columns at block C, Qty= 286 m3.

Placing concrete for parts of R.W and R.W foundation, Qty= 401 m3.

Placing concrete for part of R.C walls and columns at block E Qty=161 m3.

Complete the rebar and formwork installation for remaining part of R.C walls at block E.

Complete the Placing concrete for caps foundation at Block A-B,F-G,C-E, Qty= 47 m3.

Continue the rebar and formwork installation for external Retaining Wall.

Continue the rebar and formwork installation for R.C walls and columns at Block D,

A-B,F-G.

Backfilling work on the foundation at Block C.

Placing concrete for up stand beams at block C, Qty = 5.5.

11. Concrete delivered to site during report period:

Description This month Previous Total (m3)

Lean Concrete (B150) 13 892.5 905.50

Protection concrete (B250) - 534 534

External R.W (B250) 401 513 914

Structural Elements (B250) 2510.5 1192 3716.5

2925.5 3131.5 6072

Page 5: Turkish Palestine Friendship Hospital

5

11. Progress of work

item of work executed Actual

completion

Planned ahead or

behind

schedule

Site handing over

site mobilization 100% 100% Ahead

Excavation work 100 % 100% Ahead

External Retaining wall R.C 65% 62% Ahead

RF Concrete Structural works

C-D-E Blocks

10 cm Gravel & Sand 100% 100% Ahead Plain concrete under foundation 100% 100% Ahead

Water Proofing works 100% 100% Ahead Protection Concrete 100% 100% Ahead Foundation works 100% 100% Ahead Columns & RC walls -9.0 to -4.5m 85% 84% Ahead 30cm Backfilling on the foundation 35% 15% Ahead Plain concrete (At -9.0m ) 0.0% 0.0% - -4.5m Slab& Beams 0.0% 0.0% - Water proofing works for RC.Walls 0.0% 0.0% - A-A',B-B' Blocks

10 cm Gravel & Sand 100% 100% Ahead Plain concrete under foundation 100% 100% Ahead

water Proofing works 100% 100% Ahead Protection Concrete 100% 100% Ahead

Foundation works 100% 100% Ahead

Columns & RC walls -9.0 to -4.5m 35% 28% Ahead 30-40 cm Backfilling on the foundation 0.0% 0.0%

Plain concrete (At -9.0m ) 0.0% 0.0% -4.50m Beams & Slab 0.0% 0.0% Waterproofing works for RC.Wall 0.0% 0.0% F-G Block 10 cm sand & Gravel 100% 100% Ahead Plain concrete under foundation 100% 100% Ahead

water Proofing works 100% 100% Ahead Protection concrete 100% 100% Ahead Foundation works 100% 86% Ahead Columns & RC walls -9.0 to -4.5m 20% 18% Ahead 30-40 cm Backfilling on the foundation 0.0% 0.0% Ahead

Page 6: Turkish Palestine Friendship Hospital

6

12. Work plan for Next month:

Block C-D-E

Complete the placing concrete for remaining part of RC. Wall at block E,D.

Complete the backfilling above foundation at block C-E-D.

Complete the placing lean concrete basement floor at block C-D-E.

Begin the formwork and rebar installation for 2nd

basement slab and beams at block C-D-E .

Placing concrete for 2nd

basement slab and beams at block C.

Block A-A'-B

Complete the placing concrete for R.C walls and columns at block A-A',B.

Begin the backfilling work above foundation at Block A-A',B.

Block F-G

Continue the formwork and rebar installation for R.C walls and columns at block F-G.

Complete the placing concrete for RC walls and columns at block F.

Complete placing concrete for separated columns at block G.

External Retaining Wall:

Continue the formwork and rebar installation for external R.W.

Placing concrete for new parts of R.W and R.W foundations.

13. Schedule:

Page 7: Turkish Palestine Friendship Hospital

7

14. Photos of the construction progress:

.

Photo # 2 Rebar installation for columns at Block C

Photo # 1 Rebar installation for R.C walls at block C.

Page 8: Turkish Palestine Friendship Hospital

8

Photo # 3 Formwork of columns at block C

Photo # 4 Formwork of columns at block E

Page 9: Turkish Palestine Friendship Hospital

9

Photo # 5 Placing concrete for columns at block C

Photo # 6 Placing concrete for RC walls at Block C

Page 10: Turkish Palestine Friendship Hospital

10

Photo # 7 Placing Concrete for walls at block E

Photo # 8 Walls At Block C

Page 11: Turkish Palestine Friendship Hospital

11

Photo # 9-a Backfilling Work at block C

Photo # 9-b Backfilling at block C

Page 12: Turkish Palestine Friendship Hospital

12

Photo # 10 30 cm sand above foundation at block C

Photo # 11 Block C-D-E

Page 13: Turkish Palestine Friendship Hospital

13

Photo # 12 Placing concrete for mat foundation at block B

Photo# 13 Placing concrete for mat foundation A-B'

Page 14: Turkish Palestine Friendship Hospital

14

Photo # 14 Formwork for caps foundation at block A

Photo # 15 Rebar installation for columns at block A

Page 15: Turkish Palestine Friendship Hospital

15

Photo # 16 Formwork for walls and columns at block B

Photo # 17 Rebar installation at block B

Page 16: Turkish Palestine Friendship Hospital

16

Photo # 18 Block A-A'-B

Photo # 19 Rebar installation for mat foundation at block G

Page 17: Turkish Palestine Friendship Hospital

17

Photo # 20 Placing concrete for mat foundation at block F

Photo # 21-a Placing concrete for mat foundation at block G

Page 18: Turkish Palestine Friendship Hospital

18

Photo # 21-b Placing concrete for mat foundation block G

Photo # 22 Block F-G

Page 19: Turkish Palestine Friendship Hospital

19

Report #:

Reporting Period:

Date of submission:

Approved by:

Prepared by:

1

01/09/2011 – 30/09/2011

5/10/2011

PM/ Mr. Mahmut CELEPLI

Eng. Hazem Abu Shaaban