Aker Construction Trade& Industrial INC.
GAZA-TURKISH PALESTINE FRIENDSHIP
HOSPITAL
MONTHLY PROGRESS REPORT
Month: End of September 2011
2
CONSTRUCTION PROGRESS REPORT
( Sep. 2011)
1. Name of Project : GAZA-TURKISH PALESTINE FRIENDSHIP HOSPITAL
Contract No. : AKER-GZ/2011
2. Client : Turkish Development and Cooperation Agency – TIKA
Consultant : Islamic University – Gaza " Engineering Office "
Contractor : Aker Construction Trade& Industrial INC.
3. Site handing over date Actual Start Scheduled Finish
05/ 05 / 2011 14 / 06 / 2011 31 /05 / 2013
6. Occurrences /hindrances unexpected and unforeseen
None
4. Subcontractors working at site during reporting period :
Subcontractor : Saqqa & Khoudary Co. Ltd.
5. Manpower
(Monthly average )
Project manager
Administrative Manager
Engineers
Safety officer
Accountant
Forman
Surveyor
Assistant surveyor
Skilled labor
Unskilled labor
Driver
Office Boy
Guard man
24
24
401
38
24
288
53
54
1859
1006
72
48
72
Total on site 3963
3
7.
Financial Matter
Total Amount : $34,000,000
8.
Material at site :
Material Qty for this month Total
Steel Bars 388.16 Tons 952.81 tons
Waterproof membrane 4500 m2 17000 m2
Timber formwork 208.55 m3 351.22 m3
9.
Equipment on site :
Equipment No. No. of working day
Compressor 2 22
Water pump 2 24
Generator 1 24
Cutting Machine 3 24
Welding machine 1 0
Mobile Crane 1 24
Vibrator 3 20
Loader 1 14
Compactor 2 6
Concrete pump 20 -
Concrete mixer 295 -
Total station 2 18
Level 2 24
Petroleum tank 2 24
Water tank 10 24
Back-hoe excavator 1 3
4
10. Work Performed during report period:
Complete the placing concrete for mat foundation at block A-A',B-B', Qty = 838 m3.
Complete the placing concrete for mat foundation at block F-G, Qty= 1187 m3.
Complete the placing concrete for R.C walls and columns at block C, Qty= 286 m3.
Placing concrete for parts of R.W and R.W foundation, Qty= 401 m3.
Placing concrete for part of R.C walls and columns at block E Qty=161 m3.
Complete the rebar and formwork installation for remaining part of R.C walls at block E.
Complete the Placing concrete for caps foundation at Block A-B,F-G,C-E, Qty= 47 m3.
Continue the rebar and formwork installation for external Retaining Wall.
Continue the rebar and formwork installation for R.C walls and columns at Block D,
A-B,F-G.
Backfilling work on the foundation at Block C.
Placing concrete for up stand beams at block C, Qty = 5.5.
11. Concrete delivered to site during report period:
Description This month Previous Total (m3)
Lean Concrete (B150) 13 892.5 905.50
Protection concrete (B250) - 534 534
External R.W (B250) 401 513 914
Structural Elements (B250) 2510.5 1192 3716.5
2925.5 3131.5 6072
5
11. Progress of work
item of work executed Actual
completion
Planned ahead or
behind
schedule
Site handing over
site mobilization 100% 100% Ahead
Excavation work 100 % 100% Ahead
External Retaining wall R.C 65% 62% Ahead
RF Concrete Structural works
C-D-E Blocks
10 cm Gravel & Sand 100% 100% Ahead Plain concrete under foundation 100% 100% Ahead
Water Proofing works 100% 100% Ahead Protection Concrete 100% 100% Ahead Foundation works 100% 100% Ahead Columns & RC walls -9.0 to -4.5m 85% 84% Ahead 30cm Backfilling on the foundation 35% 15% Ahead Plain concrete (At -9.0m ) 0.0% 0.0% - -4.5m Slab& Beams 0.0% 0.0% - Water proofing works for RC.Walls 0.0% 0.0% - A-A',B-B' Blocks
10 cm Gravel & Sand 100% 100% Ahead Plain concrete under foundation 100% 100% Ahead
water Proofing works 100% 100% Ahead Protection Concrete 100% 100% Ahead
Foundation works 100% 100% Ahead
Columns & RC walls -9.0 to -4.5m 35% 28% Ahead 30-40 cm Backfilling on the foundation 0.0% 0.0%
Plain concrete (At -9.0m ) 0.0% 0.0% -4.50m Beams & Slab 0.0% 0.0% Waterproofing works for RC.Wall 0.0% 0.0% F-G Block 10 cm sand & Gravel 100% 100% Ahead Plain concrete under foundation 100% 100% Ahead
water Proofing works 100% 100% Ahead Protection concrete 100% 100% Ahead Foundation works 100% 86% Ahead Columns & RC walls -9.0 to -4.5m 20% 18% Ahead 30-40 cm Backfilling on the foundation 0.0% 0.0% Ahead
6
12. Work plan for Next month:
Block C-D-E
Complete the placing concrete for remaining part of RC. Wall at block E,D.
Complete the backfilling above foundation at block C-E-D.
Complete the placing lean concrete basement floor at block C-D-E.
Begin the formwork and rebar installation for 2nd
basement slab and beams at block C-D-E .
Placing concrete for 2nd
basement slab and beams at block C.
Block A-A'-B
Complete the placing concrete for R.C walls and columns at block A-A',B.
Begin the backfilling work above foundation at Block A-A',B.
Block F-G
Continue the formwork and rebar installation for R.C walls and columns at block F-G.
Complete the placing concrete for RC walls and columns at block F.
Complete placing concrete for separated columns at block G.
External Retaining Wall:
Continue the formwork and rebar installation for external R.W.
Placing concrete for new parts of R.W and R.W foundations.
13. Schedule:
7
14. Photos of the construction progress:
.
Photo # 2 Rebar installation for columns at Block C
Photo # 1 Rebar installation for R.C walls at block C.
8
Photo # 3 Formwork of columns at block C
Photo # 4 Formwork of columns at block E
9
Photo # 5 Placing concrete for columns at block C
Photo # 6 Placing concrete for RC walls at Block C
10
Photo # 7 Placing Concrete for walls at block E
Photo # 8 Walls At Block C
11
Photo # 9-a Backfilling Work at block C
Photo # 9-b Backfilling at block C
12
Photo # 10 30 cm sand above foundation at block C
Photo # 11 Block C-D-E
13
Photo # 12 Placing concrete for mat foundation at block B
Photo# 13 Placing concrete for mat foundation A-B'
14
Photo # 14 Formwork for caps foundation at block A
Photo # 15 Rebar installation for columns at block A
15
Photo # 16 Formwork for walls and columns at block B
Photo # 17 Rebar installation at block B
16
Photo # 18 Block A-A'-B
Photo # 19 Rebar installation for mat foundation at block G
17
Photo # 20 Placing concrete for mat foundation at block F
Photo # 21-a Placing concrete for mat foundation at block G
18
Photo # 21-b Placing concrete for mat foundation block G
Photo # 22 Block F-G
19
Report #:
Reporting Period:
Date of submission:
Approved by:
Prepared by:
1
01/09/2011 – 30/09/2011
5/10/2011
PM/ Mr. Mahmut CELEPLI
Eng. Hazem Abu Shaaban