Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Tunnelling in the Himalayas:
risk assessment and management for tunnelling in extreme
geological conditions
Dr Ian McFeat-Smith, Director
IMS Tunnel Consultancy Ltd
RISK MANAGEMENT FOR TUNNELLING IN
EXTREME GEOLOGICAL CONDITIONS
• Key risks and challenges for tunnelling in the Himalayas
• Geological classification & risks arising from mis-classification
• Water inflow risks & mitigation ( TBM & drill and blast )
• Risks & appropriate measures for drill and blast
• Case History of a TBM in extreme ground conditions in the Philippines
• Code of Practice and Risk Management Plan
• Key risk mitigation measures for tunnelling in the Himalayas
• Risk evaluation
for one party is
not necessarily
the same for
another - it
involves a
considerable
amount of
judgment
• To objectively
evaluate risks
requires a
considerable
level of
expertise
RISK MANAGEMENT FOR TUNNELLING IN
EXTREME GEOLOGICAL CONDITIONS
RISK MANAGEMENT FOR TUNNELLING IN
EXTREME GEOLOGICAL CONDITIONS
- Summary of key risks
• Access and portal instability
• Risks from variable rock mass quality
• Risks from unfavourable orientation of joints / features
• Risks from weathering effects and tunnelling in major fault gouge zones
• Stress induced risks
- rock bursts
- squeezing / convergence
• Risks from sudden inrushes
- water inflows
- silt / debris inflow
RISK MANAGEMENT FOR TUNNELLING IN
EXTREME GEOLOGICAL CONDITIONS
Ground Classification Systems
- overly complex classification systems create risks of selection of inappropriate methodology
- in critical situations we rarely can see, or have time to evaluate the geological features affecting the tunnel
- KIS
Water and Silt Inflows Risks at Parbati &
Dulhaste HEP Headrace Tunnels
At Dulhaste in Kashmir
inflows of over 1,000l/sec innundated an open TBM depositing 4,000m3 of sediments. The project was abandoned for 50 years
Above, Left. Water Inflows at Parbati HEP Headrace tunnel deposited over 4,000m3 of sediments burried a TBM resulting in delays of over 15 months todate
Conventionally Excavated Tunnels at 12- 20 m span
Water Inflow Risks - easier access for probing and grouting
Water Inflow Risks for Large Span Tunnels in the Himalayas Mitigation – Selection of appropriate modern grouting materials,
patterns, and plant for local ground conditions
IMS Rock
Class
Grouting
Required
Grout
Materials
Kgs/ MFC/ m
grout hole
1 None or spot targeted MFC; OPC if
joints > 0.5mm
10
2 Limited - continuous MFC 15
3 Continuous MFC 26
4 Continuous MFC 50
5A Continuous, closer
spacing in stages
MFC/UFC 21
5B Ditto UFC 100
Conventionally Excavated Tunnels at 12- 20 m Water inflow risks - Extensive drilling and grouting in Poor Rock
Design of Temporary Support Systems
Based on IMS Rock Classes
IMS
Rock
Class
Description Support System for 12-20m span
Tunnels
1 Massive competent
rock mass
Feature dowels
2 Favourable rock mass Feature dowels with shotcrete in
overbreak
3 Moderately fractured /
weathered rock
Feature dowels 2.4m c/c in roof with
50mm shotcrete
4 Highly fractured or
weathered
Feature dowels 2.2m c/c in roof with
70mm shotcrete
5A Fault zones or
completely weathered
Feature dowels 1.6m c/c with 90mm FR
shotcrete
5B Fault gouge / soils Fully grouted pipe pile roof; Steel
arches at 0.7m c/c; 250mm FR shotcrete
in roof, 150mm in walls
Major Soft Ground / Weathered Zone at Portal Risk Mitigation – Full Face Excavation, Steel Ribs, Fibre
Shotcrete and Face Support designed and installed using IMS
Rock Classification System
Major Fault Gouge Zones with High Cover Risk Mitigation – Plaxis modelling, support analysis, close
supervision of top heading using horizontal pipe piling, steel arch
ribs and FR shotcrete support
Tunnelling in Extreme Geological Conditions
for Umiray Angat Scheme in the Philippines Anticipated Physical and Geological Risks -
• Difficult access - extreme logistical concerns
• 4.88m diam, 13.2 km long tunnel from only one portal
• Variable geological conditions - hard basalt agglomerate intercalated with soft sedimentary rocks
• Cover up to 1,200m in an earthquake zone with potential for severe convergence, major fault zones and major water inflows
Tunnelling for Umiray Angat Scheme in Philippines Risk Mitigation: In order to deal with these extreme conditions
the contractor GLF/SELI elected to:
Transport all plant and
service the first 5kms of
TBM drive and its back
up by helicopter.
To drive the long tunnel
by double shielded
TBM from a single
portal
To purpose design a
state of the art double
shielded hard rock TBM
with hexagonal
segmental lining
Tunnelling in Extreme Geological Conditions
in Umiray Angat Scheme In Philippines Geological profile, actual tunnelling conditions and TBM progress
Tunnelling in Extreme Geological Conditions
for Umiray Angat Scheme in the Philippines
• Individual inflows of over
200l/sec and cumulative water
inflows of about 850 l/sec
• Despite these and other
challenges the Contractor managed
to complete the tunnel excavation
and lining in 24 months; averaging
530m/month
• Jamming of the TBM shield in six long sections of tunnel due to severe convergence
• Cave-ins up to 10m high above the TBM cutterhead at fault gouge zones. This was managed by an arrangement and plant for installing short resin grouted bars through the cutterhead
Innovative Double Shielded TBM Design
for Tunnelling through Extreme Geological Conditions
• TBM shield diameters progressively reduced
to better cope with and converging ground
• Short cutterhead (reducing the incidence of
stoppages by blocks and boulders and
minimizing ground disturbance in poor
ground) with rear loading cutters
• Access for probing and drilling from inside
the shield
• Very high cutterhead power and torque
• Variable frequency drive
• Very high main and auxiliary thrust
• The telescopic shield design introduced
new SELI active articulation system
Tai Po to
Butterfly Valley
- Cumulative water
inflows experienced
in TBM Tunnels at
700m cover.
- Tail-off of inflows
of 37% in 117 days
New Code of Practice for Tunnels
• Client responsible for sufficiency of site investigations
• Geotechnical data forms part of contract
• Geotechnical baseline conditions to be drawn up by Client or Tenderer
• Geotechnical baseline conditions used for assessing unexpected geological conditions
• Risk assessment and management at all stages of development of project
• Continuous tracking and mitigation of risks through risk register
• Insurance cover may be suspended or cancelled in event of a breach of code requirements
RISK MATRIX FOR TUNNELLING IN THE HIMALAYAS
Consequence
Insignificant Minor Moderate Major Catastrophic
Description C1 C2 C3 C4 C5
Rare L1 R1 R1 R1 R2 R3
Unlikely L2 R1 R1 R2 R2 R3
Possible L3 R1 R2 R2 R3 R3
Likely L4 R2 R2 R3 R3 R4 Lik
elih
oo
d
Almost certain L5 R2 R3 R3 R4 R4
Legend: Low risk Moderate risk High risk Extreme risk
R1 R2 R3 R4
Risk Management Systems
Risk management systems ensure that:
• Risks are identified for all aspects of the project
• Identified risks are evaluated as a product of their “Frequency” and “Consequences”
• Risk mitigation plans are established and implemented for each risk
• Resources are focussed on the most significant risks
• Risk status is reviewed on a scheduled basis
• Risk management activities driven by senior management
- Risk assessment and Mitigation Measures
Risk Key Mitigation Measures
Access difficulties Logistical planning; additional resources
Slope instability Carry out additional SI and analysis
Unexpected low
rockhead at portal
Advance and vertical probing; close monitoring of
support and ground movements; good
supervision at tunnel face; face support.
Extremely hard,
abrasive quartzites
Conduct appropriate testing as part of contract SI
Unexpected
geological
conditions
Carry out more SI; use better drilling methods
Be prepared to reject lowest tender for contract
Have design & contracts reviewed by experts
Enforce compliance with codes for safety and risk
Ensure contractor has adequate resources
Conduct partnering, VE workshops
Risk assessment and Mitigation Measures Risk Key Mitigation Measures
Severe ground
squeezing
Experienced temporary support designer on site
Close monitoring; and additional support
Consider multiple face headings
Rock bursts; major
overbreak
due to high stress
Protection and safehaven for workers
High awareness of safety issues and control
Toolbox talks; safety incentive schemes
Close monitoring; observational method
Face, roof and wall support to suit conditions
Major inrush of
ground water; silt
flows
Utilize probing equipment for high pressures
State of the art grouting, grout mixes and plant
Draw up Emergency & Contingency Plan before event
Insufficient time in
Programme /
Breakdown of
stakeholder
relationships
Realistic risk management plan by competent engrs
Early consultation between all stakeholders
Non-contractual partnering to ensure co-operation
Clear lines of communication and responsibility
Conduct workshops for information sharing
Typical Emergency and
Contingency Action Plan
Incident - Major Collapse at TBM Cutterhead
• Stop TBM excavation but maintain support pressure
• Check safety of personnel and plant & Inform appropriate authorities
• Check for surface impacts if appropriate; Determine whether collapse has stabilized & secure tunnel if possible
• Investigate nature of geological feature by probing
• Review collapse and potential impacts
• Mobilise remedial measures and stabilise collapse area
• Review operation and recommence asap
• Mobilise for planned permanent reinstatement
Tunnel for Tolo Effluent Export Scheme –
HK Governments first TBM project - 7.5 km long tunnel
completed within budget and 6 months ahead of programme;
using double shielded TBM
Re-measurement
Risk Sharing Contract for Tolo Tunnel: Payment for geological conditions made on re-measurement of IMS
rock classes
Existing Contractual Arrangements
and negative attitudes towards Risk Sharing carries
a Large Price Tag
Mitigating Risks
for Underground Projects
• Well targeted site investigations as an investment to reduce
uncertainty and risks
• Planning - seek specialist advice particularly on risks, opportunities and programmes
• Encourage technical innovation and alternative designs from contractors
• Use Partnering to focus on openness, co-operation and fair payment
• Ensure that real engineering risk assessment and management is implemented and driven by senior management
• Use risk sharing and re-measurement contracts
RISK MANAGEMENT FOR TUNNELLING IN
EXTREME GEOLOGICAL CONDITIONS
• Key risks and challenges for tunnelling in the Himalayas
• Geological classification & risks arising from mis-classification
• Water inflow risks & mitigation ( TBM & drill and blast )
• Risks & appropriate measures for drill and blast
• Case History of a TBM in extreme ground conditions in the Philippines
• Code of Practice and Risk Management Plan
• Key risk mitigation measures for tunnelling in the Himalayas