Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
DESY MAC Meeting 09. Nov. 041
DESY MAC Meeting 9. Nov. 2004
TTF2 (TESLA Test Facility, Phase 2) VUV FEL (Vacuum-Ultraviolet Free-Electron Laser)
Overview and Status
Jörg Rossbach
DESY MAC Meeting 09. Nov. 042
BC 3 BC 2
260 m
Overview
Injector 3Injector 3LOLALOLA
DESY MAC Meeting 09. Nov. 043
TTF External Contributions to Installation and Operation
MBIGun Laser
SLACTransverse deflecting cavityLOLA
INFN FrascatiOTR Diagnostics
CE SaclayFreq.TunerBPMs
FNALRF Gun / CryogenicsRF Modulators
INFN MilanoCathodesAccel.Modules
Installation
AyvazyanSimrock
Warsaw Univ.LLRF
Schreiber
Honkavaara
SchlarbKlose
LangeNölle / Baboi
Schreiber
DESY Coord.
MBIGun Laser
SLACTransverse deflecting cavityLOLA
INFN FrascatiOTR Diagnostics
CE SaclayFreq.TunerBPMs / HOM Studies
INFN MilanoCathodes
Operation
RehlichITEPMoscow Univ.
Ctrls
ChorobaProtvinoRF
AyvazyanRehlich
YerPhiCtrls
additional manpower
DESY MAC Meeting 09. Nov. 044
2 2 HelmholtzHelmholtz “Virtual Research Centers” :“Virtual Research Centers” :
1.1. Electron gunsElectron guns
2.2. Advanced beam diagnostics Advanced beam diagnostics
New PartnersNew Partners
EU Infrastructure EU Infrastructure ProgrammeProgramme::
1.1. EUROFELEUROFEL
2.2. CARECARE
3.3. Synchrotron Radiation I3Synchrotron Radiation I3
Several more under progress …Several more under progress …
DESY MAC Meeting 09. Nov. 045
VUV FEL beam parameters
40 mm keVLong. emittance σE × σl
2500 APeak current
150 fsBunch length (rms)
65 µmBeam size in undulator
2 mrad mmNorm. emittance at undulator entrance
1.2 mrad mmNormalized emittance from injector (1 nC)
VUV FEL@ 6 nm (1 GeV)
DESY MAC Meeting 09. Nov. 046
TTF2 Time Structure
• Repetition rate
• Macro-pulse
• Bunch
• Slice
t
100msDuty cycle ~ 0.8%
within pulse trainmax. 9 mA
t
I 800µs macro-pulseIpeak~ 2.5 kA
It
I1.0-0.111µs bunch spacing
1 nC100 fs
2-5 kA
~ psSlice ~ e.g. 10 fs
Without3rd harm. cav.
DESY MAC Meeting 09. Nov. 047
The TTF with its VUV FEL is The TTF with its VUV FEL is
–– a new type of FEL radiation user facility a new type of FEL radiation user facility –– an FEL research machinean FEL research machine
–– a testa test--bed for bed for s.cs.c. . linaclinac technologytechnology
–– a prototype for the European XFELa prototype for the European XFEL
Consequence:Consequence:TTF needs several stages for electron beam manipulation and fullTTF needs several stages for electron beam manipulation and full control of control of beam parameters during all of these stages.beam parameters during all of these stages.
flexible optics lattice, thusflexible optics lattice, thus many many quadrupolequadrupole magnets and power suppliesmagnets and power supplies
lots of beam diagnosticslots of beam diagnostics
high density of special componentshigh density of special components
VUV FEL is not suited to estimate XFEL or ILC VUV FEL is not suited to estimate XFEL or ILC costs&effortscosts&efforts just by scaling length or beam energy!just by scaling length or beam energy!
Machine characteristics
DESY MAC Meeting 09. Nov. 048
Priorities and Milestones
Due to unexpected financial restrictions some major cost drivingDue to unexpected financial restrictions some major cost drivingcomponents needed to be delayed.components needed to be delayed.
necessary to renecessary to re--define priorities. Decision: delay power supplies define priorities. Decision: delay power supplies cablingcablinglong bunch train issues long bunch train issues
Milestones:Milestones:
1: Injector commissioning up to ACC21: Injector commissioning up to ACC2
2: Complete vacuum system2: Complete vacuum system
3: FEL commissioning at ~30nm wavelength with “single” bunch 3: FEL commissioning at ~30nm wavelength with “single” bunch
4: Full bunch train operation4: Full bunch train operation
DESY MAC Meeting 09. Nov. 049
TTF2 Schedule of the last year
1’2004end vacuum installationend vacuum installation
installation of remaining componentsinstallation of remaining components
end shutdownend shutdown
•••••••••••••••• start vacuum installationstart vacuum installation
commissioning complete accelerator commissioning complete accelerator now
9’2003
survey of magnetssurvey of magnets
6’2004commissioning injector commissioning injector
survey of components and final alignmentsurvey of components and final alignment
incl. module installation & all magnetsincl. module installation & all magnets
incl. module processingincl. module processing((diagnostics,cables,container,PS,interlock,photondiagnostics,cables,container,PS,interlock,photon beamlinebeamline))
installation of injectorinstallation of injectorinstallation of guninstallation of gun
11’2004
DESY MAC Meeting 09. Nov. 0410
Progress since June 2003Progress since June 2003::•• Machine completely installed, vacuum closed Machine completely installed, vacuum closed
•• Injector commissioned up to ACC2; Injector commissioned up to ACC2; emittanceemittance ok for 30 nmok for 30 nm
•• Commissioning of entire machine started 1. Sept. 2004Commissioning of entire machine started 1. Sept. 2004
•• Accumulated delay of ~ 3 months w.r.t. June 2003Accumulated delay of ~ 3 months w.r.t. June 2003
Overview and Status
TTF2 installation schedule contained ~ 450 topicsTTF2 installation schedule contained ~ 450 topicsTalk by M. Talk by M. KKöörferrfer
DESY MAC Meeting 09. Nov. 0411
InjectorInjector
General concept:
1.1. Full performance test of gun components at PITZ/Full performance test of gun components at PITZ/ZeuthenZeuthen
2.2. Installation at TTFInstallation at TTF
1
2
3
12
3
0
0.5
1
y,mmx,mm
Laser spoton cathode:
σx = 0.51± 0.02 mm
σy = 0.62± 0.02 mm
Present TTF gun:Present TTF gun:
Test at PITZ: ε = 1.7 π mm mrad
downstream BC2: ε ≈ 3 π mm mrad
First First emittanceemittance measurement (measurement (vertvert.) .) at ~100 at ~100 MeVMeV, no compression, no compression
Compression by BC2 Compression by BC2 clearycleary observedobservedNo quantitative measurement yetNo quantitative measurement yet
DESY MAC Meeting 09. Nov. 0412
InjectorInjector
Improvement plans:1.1. Transversely homogenous laser spot on cathodeTransversely homogenous laser spot on cathode2.2. Longitudinal flat top profileLongitudinal flat top profile3.3. Increase electric field on cathode Increase electric field on cathode
1
2
3
12
3
0
0.5
1
y,mmx,mm
σx = 0.57± 0.02 mm
σy = 0.58± 0.02 mm
First test at PITZ:First test at PITZ:
εx = 1.9 π mm mradεy = 1.3 π mm mrad
Talk by M. Talk by M. KrassilnikovKrassilnikov
DESY MAC Meeting 09. Nov. 0413
Tunnel layout: Concept and Experience
Intention:Intention: tunnel design tunnel design prototyping TESLA tunnelprototyping TESLA tunnel
Experience:+ cabling is less time consuming+ cabling is less time consuming+ short cable length+ short cable length-- bad cable tray access below walkwaybad cable tray access below walkway-- time consuming cabling beside the containerstime consuming cabling beside the containers--For TTF2: container more expensive than standard racksFor TTF2: container more expensive than standard racks
32 Container32 Container
Conclusion for TESLA & XFEL:Conclusion for TESLA & XFEL: different tunnel layout; different tunnel layout; Conclusion for ILC:Conclusion for ILC: tbdtbd; experience and numbers available; experience and numbers available
DESY MAC Meeting 09. Nov. 0414
Mechanical Design Tools: Full 3D representation
DESY MAC Meeting 09. Nov. 0415
Vacuum
BC 3 BC 2
All vacuum chambers particle free installed All vacuum chambers particle free installed using local clean roomsusing local clean rooms
DESY MAC Meeting 09. Nov. 0416
Electron beam diagnostics
Charge MonitorsCharge MonitorsToroidsToroids: available: available ++
ScreensScreensOTR’sOTR’s installed & commissionedinstalled & commissioned ++
BPMsBPMsall all BPMsBPMs installed and cabledinstalled and cabled ++but only 20 Read out Electronics availablebut only 20 Read out Electronics availableProblem: delivery of milled Problem: delivery of milled rfrf--housing and availability of housing and availability of rfrf –– connectorsconnectors ----
BPMsBPMs at „Strategic Positions“:at „Strategic Positions“: ------ Injector: Full InstrumentationInjector: Full Instrumentation-- BC3: 2 BC3: 2 BPMsBPMs UpUp-- and Downstreamand Downstream-- LOLA: 2 LOLA: 2 BPMsBPMs-- Bypass Line: 2 Bypass Line: 2 BPMsBPMs-- Dump Line: 1 BPMDump Line: 1 BPM
... and much more beam diagnostics... and much more beam diagnostics
talk by Dirk Noelletalk by Dirk NoelleNew Generation of BPM ElectronicsNew Generation of BPM Electronicsavailable by End of 2004available by End of 2004
DESY MAC Meeting 09. Nov. 0417
SchedulesSchedules
Task Milestone Milestone(as of 19. 8. 2003)
Commissioning of accelerating modules ACC 3,4,5 incl.
proof of max. gradient
Modules commissioned
1.9.2003
Vacuum system entire machine Vacuum closed xx. 1. 2004
Commissioning injectorup to ACC2incl. commissioning modules
ACC1 and ACC2
First beam up to ACC2
15. 3. 2004
Installation of remaining components
all installations completed
14. 5. 2004
Commissioning entire machine,except for collimator and undulator
First beam through bypass into dump
14. 6. 2004
Commissioning of collimator and undulator beamline
First beam through undulator into dump
Commissioning photon diagnostics in the tunnel
Beam intensity and spectrum of spontaneous radiation
1. 8. 2004
Milestone(rev. Jan 2004)
Milestone(9. 11. 2004)
15. 9.200315.9.2003
12. 2. 2004 mid of Febr. 2004
21. 4. 2004 29. 4. 2004
26. 8. 2004 1. 9. 2004 (except PS & BPMs)
16. 9. 2004 end of 10.2004
30. 9. 2004 end of 11. 2004
end of end of 12. 2004 12. 2004
DESY MAC Meeting 09. Nov. 0418
Major reasons for delay w.r.t. schedule of August 2003:Major reasons for delay w.r.t. schedule of August 2003:
Magnetic shielding of ACC1 cavities reMagnetic shielding of ACC1 cavities re--fabricated 2 times fabricated 2 times 4 weeks4 weeks
More time needed for installation beyond vacuum (e.g. cabling , More time needed for installation beyond vacuum (e.g. cabling , container),container),
partially due to conflicts with HERA priority partially due to conflicts with HERA priority 4 weeks4 weeks
Severe delay of Severe delay of PSsPSs: late order due to financial restrictions + company went : late order due to financial restrictions + company went bankrupt bankrupt no beam through bypass before end of Oct. 04 no beam through bypass before end of Oct. 04 4 weeks4 weeks
SchedulesSchedules
DESY MAC Meeting 09. Nov. 0419
Allocation of responsibilities:Allocation of responsibilities:
Hardware work packages Hardware work packages
(almost unchanged since 2001):(almost unchanged since 2001):
Zuständigkeiten TTF2Zuständigkeiten TTF2
KryogenikKryogenik [email protected]@desy.de,,
Magnete Magnete [email protected]@desy.de,,
Umbau, Einbau, Montage Umbau, Einbau, Montage [email protected]@desy.de,,
KollimatorKollimator allg. allg. [email protected]@desy.de
KollimatorKollimator Vakuum Vakuum [email protected]@desy.de
Diagnostik Diagnostik [email protected]@desy.de,,
Bunch compressor 3 Bunch compressor 3 allgallg. . [email protected]@desy.de
Bunch compressor 3 Bunch compressor 3 VakuumVakuum [email protected]@desy.de
ZwischenZwischen--und und ErsatzbeamlErsatzbeaml. . [email protected]@desy.de
Bypass Bypass [email protected]@ifh.de,,
UndulatorUndulator [email protected]@desy.de,,
Vermessung Vermessung [email protected]@desy.de,,
UebersichtszeichnungenUebersichtszeichnungen [email protected]@desy.de,,
Spektrometer+DumpSpektrometer+Dump [email protected]@desy.de,,
Injektor III allg. Injektor III allg. [email protected]@desy.de,,
Injektor III Vakuum Injektor III Vakuum [email protected]@desy.de
RF RF gungun + + laserlaser [email protected]@desy.de
TESLA Module TESLA Module berndbernd..petersenpetersen@@desydesy.de,.de,
Undul.kammerUndul.kammer + + ZwischenstZwischenst. . [email protected]@desy.de
Kontrollen Kontrollen [email protected]@desy.de
Wasser und Strom Wasser und Strom [email protected]@desy.de
RF Versorgung RF Versorgung [email protected]@desy.de
Feedback Feedback [email protected]@desy.de,,
Cavities Cavities [email protected]@desy.de
KopplerKoppler [email protected]@desy.de
MagnetMagnet--NetzgerNetzgeräätete [email protected]@desy.de
KoordinationKoordination VakuumVakuum [email protected]@desy.de
KabelKabel [email protected]@desy.de
GestelleGestelle [email protected]@desy.de
PersonenPersonen--InterlockInterlock [email protected]@desy.de
TechnischesTechnisches InterlockInterlock [email protected]@desy.de
PhotonenPhotonen--DiagnoseDiagnose [email protected]@desy.de
DESY MAC Meeting 09. Nov. 0420
DESY technical/administrative groups Groups fromTESLA CollaborationNew International
Collaborators
TESLACollaboration Board
DESY TTF / VUV-FEL Project GroupChair: Project leader FEL technology J. RossbachCo-Chair: Project leader LINAC technology H. Weise
Project leader photons J. Feldhaus
Members: - people responsible for the individual work packages- members of the Coordination Board
DESY Directorate
DESY TTF / VUV-FEL Coordination BoardChair: M Division Leader D. TrinesCo-Chair: FS Division Leader J. Schneider
Members:• Project leader FEL technology J. Rossbach• Project leader LINAC technology H. Weise• Project leader photons J. Feldhaus• FEL concepts M. Yurkov• TESLA TEST Facility R&D coordinator C. Pagani• Representative of V3 (PoF related issues) U. Wolframm
TTF / VUV-FEL Organigramm
DESY MAC Meeting 09. Nov. 0421
TTF / VUV-FEL Commissioning
Gun OperationGun Operationllrfllrf (FSM)(FSM) AyvazyanAyvazyanllrfllrf (closed loop)(closed loop) KotthausKotthausphase stability laser / RF phase stability laser / RF SimrockSimrockwater regulation; water regulation; rfrf tune gun tune gun CarneiroCarneirotechnical interlocktechnical interlock SchreiberSchreibergun dark current meas. gun dark current meas. HanHanlaser beam linelaser beam line KloseKloselaserlaser SchreiberSchreiberlaser serverlaser server PetrosyanPetrosyanlaser controlslaser controls RehlichRehlichstreak camera laserstreak camera laser SchreiberSchreibercathode productioncathode production SertoreSertoreFaraday cupsFaraday cups CarneiroCarneiro / / NölleNölletoroidstoroids NölleNölleBPMBPM NölleNöllecollimatorcollimator FlöttmannFlöttmannphase scanphase scan SertoreSertoreenergy, energy spread energy, energy spread SchlarbSchlarbbeam based alignmentbeam based alignment KrassilnikovKrassilnikovbucking coil fieldbucking coil field FlöttmannFlöttmannenvelope matchingenvelope matching FlöttmannFlöttmannstudy effect of laser mirror study effect of laser mirror MiltchevMiltchevwakefieldwakefield effectseffects KimKimquantum efficiency quantum efficiency SchreiberSchreiberphase charge studies phase charge studies SertoreSertore
TTF TTF LinacLinac ACC1 ACC1 –– ACC5ACC5llrfllrf AyvazyanAyvazyanphase calibrationphase calibration AyvazyanAyvazyansetset--up nominal opticsup nominal optics CastroCastromagnetsmagnets CastroCastroOTR screensOTR screens HonkavaaraHonkavaaratoroidstoroids NölleNölleBPMsBPMs NölleNöllewire scannerswire scanners WernerWernerbeam loss detectionbeam loss detection PugachovPugachovdark current transmissiondark current transmission FlöttmannFlöttmannspot size and shapespot size and shapeHonkavaaraHonkavaaracheck envelope matching (check envelope matching (injinj.).) FlöttmannFlöttmannemittanceemittance measurement with screensmeasurement with screens HonkavaaraHonkavaarabunch compressor 2bunch compressor 2 KimKimbeam with compressionbeam with compression LimbergLimbergbunch length monitoring (bunch length monitoring (pyropyro)) SchlarbSchlarbmeasurement beam energymeasurement beam energy CastroCastroenergy spreadenergy spread SchlarbSchlarbcompensate dispersioncompensate dispersion GolubevaGolubevastreak camera (TOSY)streak camera (TOSY) GrimmGrimmIR interferometerIR interferometer GrimmGrimmvelocity bunchingvelocity bunching CarneiroCarneirotimetime--ofof--flight (TOF)flight (TOF) KolleweKollewemeasure phase stabilitymeasure phase stability SimrockSimrockfinal state machine LLRFfinal state machine LLRF BrandtBrandtestablish golden orbitestablish golden orbit CastroCastromodule operationmodule operation KostinKostinHOM studiesHOM studies BaboiBaboi
Electron Beam Downstream of Electron Beam Downstream of LinacLinacACC7 section:ACC7 section:
LOLALOLA Ross / KloseRoss / KloseLOLA KickerLOLA Kicker SchlarbSchlarb / Obier/ Obierelectroelectro--optical sampling (EOS)optical sampling (EOS) SteffenSteffentiming meas. By EOS (TEO)timing meas. By EOS (TEO) SchlarbSchlarbbunch compress. bunch compress. Meas.byMeas.by CDRCDR SchlarbSchlarbdtodto. By IR interferometer. By IR interferometer GrimmGrimm
collimatorcollimator KörferKörferorbit feedbackorbit feedback BalewskiBalewskiestablish bypass operationestablish bypass operation CastroCastrobeam diagnostics bypassbeam diagnostics bypass NölleNölleundulatorundulator::
beam losses in beam losses in undulatorundulator KörferKörfer / / PugatchovPugatchovelectron orbit / beam based electron orbit / beam based alignmalignm.. FaatzFaatzwire scannerswire scanners SachwitzSachwitz
electron spectrometer / beam dumpelectron spectrometer / beam dump SchmitzSchmitz
Photon Beam DiagnosticsPhoton Beam Diagnosticsintensity and spatial distributionintensity and spatial distribution
MCP detectorsMCP detectors YurkovYurkovHASYLAB systemsHASYLAB systems TreuschTreusch
spectral distributionspectral distribution TiedkeTiedkedipole radiation, timing w/ respect dipole radiation, timing w/ respect
to pumpto pump--probe laserprobe laser PlönjesPlönjesFEL photon beam transferFEL photon beam transfer TiedkeTiedke
VUV FEL responsibilities for commissioning proceduresVUV FEL responsibilities for commissioning procedures(13(13--AugustAugust--2004)2004)
DESY MAC Meeting 09. Nov. 0422
•• Machine completely installed, vacuum closed Machine completely installed, vacuum closed
•• Injector commissioned up to ACC2; Injector commissioned up to ACC2; emittanceemittance okok
•• Commissioning of entire machine started 1. Sept. 2004Commissioning of entire machine started 1. Sept. 2004
•• Electron beam through bypass on beam dumpElectron beam through bypass on beam dump
Summary