22
DESY MAC Meeting 09. Nov. 04 1 DESY MAC Meeting 9. Nov. 2004 TTF2 (TESLA Test Facility, Phase 2) VUV FEL (Vacuum-Ultraviolet Free-Electron Laser) Overview and Status Jörg Rossbach

TTF2 (TESLA Test Facility, Phase 2) VUV FEL (Vacuum-Ultraviolet … · 2004. 11. 5. · Kollimator Vakuum [email protected] Diagnostik [email protected], Bunch compressor

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

  • DESY MAC Meeting 09. Nov. 041

    DESY MAC Meeting 9. Nov. 2004

    TTF2 (TESLA Test Facility, Phase 2) VUV FEL (Vacuum-Ultraviolet Free-Electron Laser)

    Overview and Status

    Jörg Rossbach

  • DESY MAC Meeting 09. Nov. 042

    BC 3 BC 2

    260 m

    Overview

    Injector 3Injector 3LOLALOLA

  • DESY MAC Meeting 09. Nov. 043

    TTF External Contributions to Installation and Operation

    MBIGun Laser

    SLACTransverse deflecting cavityLOLA

    INFN FrascatiOTR Diagnostics

    CE SaclayFreq.TunerBPMs

    FNALRF Gun / CryogenicsRF Modulators

    INFN MilanoCathodesAccel.Modules

    Installation

    AyvazyanSimrock

    Warsaw Univ.LLRF

    Schreiber

    Honkavaara

    SchlarbKlose

    LangeNölle / Baboi

    Schreiber

    DESY Coord.

    MBIGun Laser

    SLACTransverse deflecting cavityLOLA

    INFN FrascatiOTR Diagnostics

    CE SaclayFreq.TunerBPMs / HOM Studies

    INFN MilanoCathodes

    Operation

    RehlichITEPMoscow Univ.

    Ctrls

    ChorobaProtvinoRF

    AyvazyanRehlich

    YerPhiCtrls

    additional manpower

  • DESY MAC Meeting 09. Nov. 044

    2 2 HelmholtzHelmholtz “Virtual Research Centers” :“Virtual Research Centers” :

    1.1. Electron gunsElectron guns

    2.2. Advanced beam diagnostics Advanced beam diagnostics

    New PartnersNew Partners

    EU Infrastructure EU Infrastructure ProgrammeProgramme::

    1.1. EUROFELEUROFEL

    2.2. CARECARE

    3.3. Synchrotron Radiation I3Synchrotron Radiation I3

    Several more under progress …Several more under progress …

  • DESY MAC Meeting 09. Nov. 045

    VUV FEL beam parameters

    40 mm keVLong. emittance σE × σl

    2500 APeak current

    150 fsBunch length (rms)

    65 µmBeam size in undulator

    2 mrad mmNorm. emittance at undulator entrance

    1.2 mrad mmNormalized emittance from injector (1 nC)

    VUV FEL@ 6 nm (1 GeV)

  • DESY MAC Meeting 09. Nov. 046

    TTF2 Time Structure

    • Repetition rate

    • Macro-pulse

    • Bunch

    • Slice

    t

    100msDuty cycle ~ 0.8%

    within pulse trainmax. 9 mA

    t

    I 800µs macro-pulseIpeak~ 2.5 kA

    It

    I1.0-0.111µs bunch spacing

    1 nC100 fs

    2-5 kA

    ~ psSlice ~ e.g. 10 fs

    Without3rd harm. cav.

  • DESY MAC Meeting 09. Nov. 047

    The TTF with its VUV FEL is The TTF with its VUV FEL is

    –– a new type of FEL radiation user facility a new type of FEL radiation user facility –– an FEL research machinean FEL research machine

    –– a testa test--bed for bed for s.cs.c. . linaclinac technologytechnology

    –– a prototype for the European XFELa prototype for the European XFEL

    Consequence:Consequence:TTF needs several stages for electron beam manipulation and fullTTF needs several stages for electron beam manipulation and full control of control of beam parameters during all of these stages.beam parameters during all of these stages.

    flexible optics lattice, thusflexible optics lattice, thus many many quadrupolequadrupole magnets and power suppliesmagnets and power supplies

    lots of beam diagnosticslots of beam diagnostics

    high density of special componentshigh density of special components

    VUV FEL is not suited to estimate XFEL or ILC VUV FEL is not suited to estimate XFEL or ILC costs&effortscosts&efforts just by scaling length or beam energy!just by scaling length or beam energy!

    Machine characteristics

  • DESY MAC Meeting 09. Nov. 048

    Priorities and Milestones

    Due to unexpected financial restrictions some major cost drivingDue to unexpected financial restrictions some major cost drivingcomponents needed to be delayed.components needed to be delayed.

    necessary to renecessary to re--define priorities. Decision: delay power supplies define priorities. Decision: delay power supplies cablingcablinglong bunch train issues long bunch train issues

    Milestones:Milestones:

    1: Injector commissioning up to ACC21: Injector commissioning up to ACC2

    2: Complete vacuum system2: Complete vacuum system

    3: FEL commissioning at ~30nm wavelength with “single” bunch 3: FEL commissioning at ~30nm wavelength with “single” bunch

    4: Full bunch train operation4: Full bunch train operation

  • DESY MAC Meeting 09. Nov. 049

    TTF2 Schedule of the last year

    1’2004end vacuum installationend vacuum installation

    installation of remaining componentsinstallation of remaining components

    end shutdownend shutdown

    •••••••••••••••• start vacuum installationstart vacuum installation

    commissioning complete accelerator commissioning complete accelerator now

    9’2003

    survey of magnetssurvey of magnets

    6’2004commissioning injector commissioning injector

    survey of components and final alignmentsurvey of components and final alignment

    incl. module installation & all magnetsincl. module installation & all magnets

    incl. module processingincl. module processing((diagnostics,cables,container,PS,interlock,photondiagnostics,cables,container,PS,interlock,photon beamlinebeamline))

    installation of injectorinstallation of injectorinstallation of guninstallation of gun

    11’2004

  • DESY MAC Meeting 09. Nov. 0410

    Progress since June 2003Progress since June 2003::•• Machine completely installed, vacuum closed Machine completely installed, vacuum closed

    •• Injector commissioned up to ACC2; Injector commissioned up to ACC2; emittanceemittance ok for 30 nmok for 30 nm

    •• Commissioning of entire machine started 1. Sept. 2004Commissioning of entire machine started 1. Sept. 2004

    •• Accumulated delay of ~ 3 months w.r.t. June 2003Accumulated delay of ~ 3 months w.r.t. June 2003

    Overview and Status

    TTF2 installation schedule contained ~ 450 topicsTTF2 installation schedule contained ~ 450 topicsTalk by M. Talk by M. KKöörferrfer

  • DESY MAC Meeting 09. Nov. 0411

    InjectorInjector

    General concept:

    1.1. Full performance test of gun components at PITZ/Full performance test of gun components at PITZ/ZeuthenZeuthen

    2.2. Installation at TTFInstallation at TTF

    1

    2

    3

    12

    3

    0

    0.5

    1

    y,mmx,mm

    Laser spoton cathode:

    σx = 0.51± 0.02 mm

    σy = 0.62± 0.02 mm

    Present TTF gun:Present TTF gun:

    Test at PITZ: ε = 1.7 π mm mrad

    downstream BC2: ε ≈ 3 π mm mrad

    First First emittanceemittance measurement (measurement (vertvert.) .) at ~100 at ~100 MeVMeV, no compression, no compression

    Compression by BC2 Compression by BC2 clearycleary observedobservedNo quantitative measurement yetNo quantitative measurement yet

  • DESY MAC Meeting 09. Nov. 0412

    InjectorInjector

    Improvement plans:1.1. Transversely homogenous laser spot on cathodeTransversely homogenous laser spot on cathode2.2. Longitudinal flat top profileLongitudinal flat top profile3.3. Increase electric field on cathode Increase electric field on cathode

    1

    2

    3

    12

    3

    0

    0.5

    1

    y,mmx,mm

    σx = 0.57± 0.02 mm

    σy = 0.58± 0.02 mm

    First test at PITZ:First test at PITZ:

    εx = 1.9 π mm mradεy = 1.3 π mm mrad

    Talk by M. Talk by M. KrassilnikovKrassilnikov

  • DESY MAC Meeting 09. Nov. 0413

    Tunnel layout: Concept and Experience

    Intention:Intention: tunnel design tunnel design prototyping TESLA tunnelprototyping TESLA tunnel

    Experience:+ cabling is less time consuming+ cabling is less time consuming+ short cable length+ short cable length-- bad cable tray access below walkwaybad cable tray access below walkway-- time consuming cabling beside the containerstime consuming cabling beside the containers--For TTF2: container more expensive than standard racksFor TTF2: container more expensive than standard racks

    32 Container32 Container

    Conclusion for TESLA & XFEL:Conclusion for TESLA & XFEL: different tunnel layout; different tunnel layout; Conclusion for ILC:Conclusion for ILC: tbdtbd; experience and numbers available; experience and numbers available

  • DESY MAC Meeting 09. Nov. 0414

    Mechanical Design Tools: Full 3D representation

  • DESY MAC Meeting 09. Nov. 0415

    Vacuum

    BC 3 BC 2

    All vacuum chambers particle free installed All vacuum chambers particle free installed using local clean roomsusing local clean rooms

  • DESY MAC Meeting 09. Nov. 0416

    Electron beam diagnostics

    Charge MonitorsCharge MonitorsToroidsToroids: available: available ++

    ScreensScreensOTR’sOTR’s installed & commissionedinstalled & commissioned ++

    BPMsBPMsall all BPMsBPMs installed and cabledinstalled and cabled ++but only 20 Read out Electronics availablebut only 20 Read out Electronics availableProblem: delivery of milled Problem: delivery of milled rfrf--housing and availability of housing and availability of rfrf –– connectorsconnectors ----

    BPMsBPMs at „Strategic Positions“:at „Strategic Positions“: ------ Injector: Full InstrumentationInjector: Full Instrumentation-- BC3: 2 BC3: 2 BPMsBPMs UpUp-- and Downstreamand Downstream-- LOLA: 2 LOLA: 2 BPMsBPMs-- Bypass Line: 2 Bypass Line: 2 BPMsBPMs-- Dump Line: 1 BPMDump Line: 1 BPM

    ... and much more beam diagnostics... and much more beam diagnostics

    talk by Dirk Noelletalk by Dirk NoelleNew Generation of BPM ElectronicsNew Generation of BPM Electronicsavailable by End of 2004available by End of 2004

  • DESY MAC Meeting 09. Nov. 0417

    SchedulesSchedules

    Task Milestone Milestone(as of 19. 8. 2003)

    Commissioning of accelerating modules ACC 3,4,5 incl.

    proof of max. gradient

    Modules commissioned

    1.9.2003

    Vacuum system entire machine Vacuum closed xx. 1. 2004

    Commissioning injectorup to ACC2incl. commissioning modules

    ACC1 and ACC2

    First beam up to ACC2

    15. 3. 2004

    Installation of remaining components

    all installations completed

    14. 5. 2004

    Commissioning entire machine,except for collimator and undulator

    First beam through bypass into dump

    14. 6. 2004

    Commissioning of collimator and undulator beamline

    First beam through undulator into dump

    Commissioning photon diagnostics in the tunnel

    Beam intensity and spectrum of spontaneous radiation

    1. 8. 2004

    Milestone(rev. Jan 2004)

    Milestone(9. 11. 2004)

    15. 9.200315.9.2003

    12. 2. 2004 mid of Febr. 2004

    21. 4. 2004 29. 4. 2004

    26. 8. 2004 1. 9. 2004 (except PS & BPMs)

    16. 9. 2004 end of 10.2004

    30. 9. 2004 end of 11. 2004

    end of end of 12. 2004 12. 2004

  • DESY MAC Meeting 09. Nov. 0418

    Major reasons for delay w.r.t. schedule of August 2003:Major reasons for delay w.r.t. schedule of August 2003:

    Magnetic shielding of ACC1 cavities reMagnetic shielding of ACC1 cavities re--fabricated 2 times fabricated 2 times 4 weeks4 weeks

    More time needed for installation beyond vacuum (e.g. cabling , More time needed for installation beyond vacuum (e.g. cabling , container),container),

    partially due to conflicts with HERA priority partially due to conflicts with HERA priority 4 weeks4 weeks

    Severe delay of Severe delay of PSsPSs: late order due to financial restrictions + company went : late order due to financial restrictions + company went bankrupt bankrupt no beam through bypass before end of Oct. 04 no beam through bypass before end of Oct. 04 4 weeks4 weeks

    SchedulesSchedules

  • DESY MAC Meeting 09. Nov. 0419

    Allocation of responsibilities:Allocation of responsibilities:

    Hardware work packages Hardware work packages

    (almost unchanged since 2001):(almost unchanged since 2001):

    Zuständigkeiten TTF2Zuständigkeiten TTF2

    KryogenikKryogenik [email protected]@desy.de,,

    Magnete Magnete [email protected]@desy.de,,

    Umbau, Einbau, Montage Umbau, Einbau, Montage [email protected]@desy.de,,

    KollimatorKollimator allg. allg. [email protected]@desy.de

    KollimatorKollimator Vakuum Vakuum [email protected]@desy.de

    Diagnostik Diagnostik [email protected]@desy.de,,

    Bunch compressor 3 Bunch compressor 3 allgallg. . [email protected]@desy.de

    Bunch compressor 3 Bunch compressor 3 VakuumVakuum [email protected]@desy.de

    ZwischenZwischen--und und ErsatzbeamlErsatzbeaml. . [email protected]@desy.de

    Bypass Bypass [email protected]@ifh.de,,

    UndulatorUndulator [email protected]@desy.de,,

    Vermessung Vermessung [email protected]@desy.de,,

    UebersichtszeichnungenUebersichtszeichnungen [email protected]@desy.de,,

    Spektrometer+DumpSpektrometer+Dump [email protected]@desy.de,,

    Injektor III allg. Injektor III allg. [email protected]@desy.de,,

    Injektor III Vakuum Injektor III Vakuum [email protected]@desy.de

    RF RF gungun + + laserlaser [email protected]@desy.de

    TESLA Module TESLA Module berndbernd..petersenpetersen@@desydesy.de,.de,

    Undul.kammerUndul.kammer + + ZwischenstZwischenst. . [email protected]@desy.de

    Kontrollen Kontrollen [email protected]@desy.de

    Wasser und Strom Wasser und Strom [email protected]@desy.de

    RF Versorgung RF Versorgung [email protected]@desy.de

    Feedback Feedback [email protected]@desy.de,,

    Cavities Cavities [email protected]@desy.de

    KopplerKoppler [email protected]@desy.de

    MagnetMagnet--NetzgerNetzgeräätete [email protected]@desy.de

    KoordinationKoordination VakuumVakuum [email protected]@desy.de

    KabelKabel [email protected]@desy.de

    GestelleGestelle [email protected]@desy.de

    PersonenPersonen--InterlockInterlock [email protected]@desy.de

    TechnischesTechnisches InterlockInterlock [email protected]@desy.de

    PhotonenPhotonen--DiagnoseDiagnose [email protected]@desy.de

  • DESY MAC Meeting 09. Nov. 0420

    DESY technical/administrative groups Groups fromTESLA CollaborationNew International

    Collaborators

    TESLACollaboration Board

    DESY TTF / VUV-FEL Project GroupChair: Project leader FEL technology J. RossbachCo-Chair: Project leader LINAC technology H. Weise

    Project leader photons J. Feldhaus

    Members: - people responsible for the individual work packages- members of the Coordination Board

    DESY Directorate

    DESY TTF / VUV-FEL Coordination BoardChair: M Division Leader D. TrinesCo-Chair: FS Division Leader J. Schneider

    Members:• Project leader FEL technology J. Rossbach• Project leader LINAC technology H. Weise• Project leader photons J. Feldhaus• FEL concepts M. Yurkov• TESLA TEST Facility R&D coordinator C. Pagani• Representative of V3 (PoF related issues) U. Wolframm

    TTF / VUV-FEL Organigramm

  • DESY MAC Meeting 09. Nov. 0421

    TTF / VUV-FEL Commissioning

    Gun OperationGun Operationllrfllrf (FSM)(FSM) AyvazyanAyvazyanllrfllrf (closed loop)(closed loop) KotthausKotthausphase stability laser / RF phase stability laser / RF SimrockSimrockwater regulation; water regulation; rfrf tune gun tune gun CarneiroCarneirotechnical interlocktechnical interlock SchreiberSchreibergun dark current meas. gun dark current meas. HanHanlaser beam linelaser beam line KloseKloselaserlaser SchreiberSchreiberlaser serverlaser server PetrosyanPetrosyanlaser controlslaser controls RehlichRehlichstreak camera laserstreak camera laser SchreiberSchreibercathode productioncathode production SertoreSertoreFaraday cupsFaraday cups CarneiroCarneiro / / NölleNölletoroidstoroids NölleNölleBPMBPM NölleNöllecollimatorcollimator FlöttmannFlöttmannphase scanphase scan SertoreSertoreenergy, energy spread energy, energy spread SchlarbSchlarbbeam based alignmentbeam based alignment KrassilnikovKrassilnikovbucking coil fieldbucking coil field FlöttmannFlöttmannenvelope matchingenvelope matching FlöttmannFlöttmannstudy effect of laser mirror study effect of laser mirror MiltchevMiltchevwakefieldwakefield effectseffects KimKimquantum efficiency quantum efficiency SchreiberSchreiberphase charge studies phase charge studies SertoreSertore

    TTF TTF LinacLinac ACC1 ACC1 –– ACC5ACC5llrfllrf AyvazyanAyvazyanphase calibrationphase calibration AyvazyanAyvazyansetset--up nominal opticsup nominal optics CastroCastromagnetsmagnets CastroCastroOTR screensOTR screens HonkavaaraHonkavaaratoroidstoroids NölleNölleBPMsBPMs NölleNöllewire scannerswire scanners WernerWernerbeam loss detectionbeam loss detection PugachovPugachovdark current transmissiondark current transmission FlöttmannFlöttmannspot size and shapespot size and shapeHonkavaaraHonkavaaracheck envelope matching (check envelope matching (injinj.).) FlöttmannFlöttmannemittanceemittance measurement with screensmeasurement with screens HonkavaaraHonkavaarabunch compressor 2bunch compressor 2 KimKimbeam with compressionbeam with compression LimbergLimbergbunch length monitoring (bunch length monitoring (pyropyro)) SchlarbSchlarbmeasurement beam energymeasurement beam energy CastroCastroenergy spreadenergy spread SchlarbSchlarbcompensate dispersioncompensate dispersion GolubevaGolubevastreak camera (TOSY)streak camera (TOSY) GrimmGrimmIR interferometerIR interferometer GrimmGrimmvelocity bunchingvelocity bunching CarneiroCarneirotimetime--ofof--flight (TOF)flight (TOF) KolleweKollewemeasure phase stabilitymeasure phase stability SimrockSimrockfinal state machine LLRFfinal state machine LLRF BrandtBrandtestablish golden orbitestablish golden orbit CastroCastromodule operationmodule operation KostinKostinHOM studiesHOM studies BaboiBaboi

    Electron Beam Downstream of Electron Beam Downstream of LinacLinacACC7 section:ACC7 section:

    LOLALOLA Ross / KloseRoss / KloseLOLA KickerLOLA Kicker SchlarbSchlarb / Obier/ Obierelectroelectro--optical sampling (EOS)optical sampling (EOS) SteffenSteffentiming meas. By EOS (TEO)timing meas. By EOS (TEO) SchlarbSchlarbbunch compress. bunch compress. Meas.byMeas.by CDRCDR SchlarbSchlarbdtodto. By IR interferometer. By IR interferometer GrimmGrimm

    collimatorcollimator KörferKörferorbit feedbackorbit feedback BalewskiBalewskiestablish bypass operationestablish bypass operation CastroCastrobeam diagnostics bypassbeam diagnostics bypass NölleNölleundulatorundulator::

    beam losses in beam losses in undulatorundulator KörferKörfer / / PugatchovPugatchovelectron orbit / beam based electron orbit / beam based alignmalignm.. FaatzFaatzwire scannerswire scanners SachwitzSachwitz

    electron spectrometer / beam dumpelectron spectrometer / beam dump SchmitzSchmitz

    Photon Beam DiagnosticsPhoton Beam Diagnosticsintensity and spatial distributionintensity and spatial distribution

    MCP detectorsMCP detectors YurkovYurkovHASYLAB systemsHASYLAB systems TreuschTreusch

    spectral distributionspectral distribution TiedkeTiedkedipole radiation, timing w/ respect dipole radiation, timing w/ respect

    to pumpto pump--probe laserprobe laser PlönjesPlönjesFEL photon beam transferFEL photon beam transfer TiedkeTiedke

    VUV FEL responsibilities for commissioning proceduresVUV FEL responsibilities for commissioning procedures(13(13--AugustAugust--2004)2004)

  • DESY MAC Meeting 09. Nov. 0422

    •• Machine completely installed, vacuum closed Machine completely installed, vacuum closed

    •• Injector commissioned up to ACC2; Injector commissioned up to ACC2; emittanceemittance okok

    •• Commissioning of entire machine started 1. Sept. 2004Commissioning of entire machine started 1. Sept. 2004

    •• Electron beam through bypass on beam dumpElectron beam through bypass on beam dump

    Summary