Upload
stephany-mathews
View
212
Download
0
Embed Size (px)
Citation preview
TS2-SPS & TS1-LHC
TS2-SPS(On Monday 15th of June for 24hrs)• SPS
– HW: Replacement of HV Switch PFN 7 MKP (Impact 65420)• SW: « Smooth » upgrade in accordance with BE/CO
TS1-LHC Week 25, 5 days
• LHC – SW: FESA Software release in accordance with BE/CO– MKI Point 2 and Point 8 • No request of consignation from the coordination (to confirm)• Improvement of the rise time :
– Adjustement front cell on PFN 2d/point (Impact - 64460 & 64461)
• Replacement FIB AGK 0.5 d/point (Impact to launch)• Update class LhcMKIstate with TDR measurements• Update BETS TDI table
3
TS1-LHC Week 25, 5 days
• LHC Point 4 MKQA – Checking the tightening of the capa bank on AC dip Generator
(Impact to launch)• LHC point 6 LIU-TCDI– Floor Levelling - Impact 64913– Check BEC
4
TS1-LHC Week 25, 5 days
• LHC – LBDS Point 6 – Consignation for EN: From On monday up to Wednesday morning– Inspection inside of some MKD generators HV (Impact 65125)– Cleaning up MKB generators H and may be V (Impact 65125)– Pre-tests (Planning ? Impact to launch)– Noise measurement on IPCO1 at low energy pulsed (Impact to launch)– Cleaning of cabling in GP rack (Impact to launch)– Check UPS powering in UA 63 and ABDT signal on TSU-A in UA67– Put into place of 2 racks in the storage area for electronic spares storage
5