Upload
gingerbeer1111
View
6
Download
0
Tags:
Embed Size (px)
DESCRIPTION
trust power reading
Citation preview
TRUSTPOWER LIMITED v THE COMMISSIONER OF INLAND REVENUE [2013] NZHC 2970 [12
November 2013 ]
IN THE HIGH COURT OF NEW ZEALAND
AUCKLAND REGISTRY
CIV 2011-404-007140
[2013] NZHC 2970
UNDER
the Taxation Administration Act 1994
IN THE MATTER
of the Income Tax Act 2004
BETWEEN
TRUSTPOWER LIMITED
Plaintiff
AND
THE COMMISSIONER OF INLAND
REVENUE
Defendant
Hearing:
12-30 August 2013
Appearances:
G J Harley, S Armstrong, L Hablous and A F Church for
Plaintiff
D H McLellan QC, M Andrews, R Roff and C Kern for
Defendant
Judgment:
12 November 2013 at 10am
(RESERVED) JUDGMENT OF ANDREWS J
This judgment is delivered by me on 12 November 2013 at 10am
pursuant to r 11.5 of the High Court Rules.
.....................................................
Registrar / Deputy Registrar
Solicitors/Counsel: Russell McVeagh, Auckland G J Harley, Barrister, Wellington D H McLellan QC, Barrister, Auckland Crown Law, Wellington Inland Revenue Department, Wellington
Table of Contents Introduction .......................................................................................................... [1] A history of the dispute ........................................................................................ [7] The development pipeline in more detail – feasibility investigation .............. [16]
What are the issues? The pleadings ....................................................................................................... [30]
Matters not pleaded .............................................................................................. [35] Issues emerging in closing submissions ............................................................... [41] The “general permission” and the “capital limitation” .................................. [42] The capital/revenue determination: overview of leading authorities ............ [44] The practical and business point of view – the BP Australia indicia ................... [48]
The “identifiable asset” test................................................................................. [51] Further New Zealand authorities ......................................................................... [52]
Resource consents and the Income Tax Act Resource consents ................................................................................................ [57] Resource consents in the context of the Income Tax Act ...................................... [62] Submissions as to the statutory context ................................................................ [66] Discussion ............................................................................................................ [70]
Are the resource consents obtained by TrustPower, on a stand-alone
basis, assets? Introduction .......................................................................................................... [80] Submissions .......................................................................................................... [87]
Discussion ............................................................................................................ [92]
The BP Australia indicia .................................................................................... [98]
What was the need or occasion which called for the expenditure? ..................... [99] Were the payments made from fixed or circulating capital? .............................. [104]
Was the expenditure of a once and for all nature producing assets or
advantages which were of an enduring benefit for TrustPower? ....................... [111] (a) Was the expenditure of a once and for all or recurrent nature? ................. [113]
(b) Were the assets or advantages produced of an enduring benefit to
TrustPower? ............................................................................................... [119]
How would the payment be treated on ordinary principles of commercial
accounting? ........................................................................................................ [126] Was the expenditure incurred on the business structure of TrustPower,
or as part of the process by which income was earned? .................................... [135] From a practical and business point of view, is the expenditure to be
regarded as capital or revenue in nature? ......................................................... [139]
Was TrustPower’s expenditure in obtaining resource consent incurred
for the purposes of improving its interest in the underlying land? Introduction ........................................................................................................ [142] Discussion .......................................................................................................... [146]
TrustPower’s alternative argument: classification of expenditure Introduction ........................................................................................................ [148] When was TrustPower committed to filing applications for resource
consents? ............................................................................................................ [151]
Discussion .......................................................................................................... [154] Result ................................................................................................................. [157]
Appendix
The four projects: description and chronology 1. Arnold hydro
2. Kaiwera Downs wind farm 3. Mahinerangi wind farm 4. Wairau River Hydro
Introduction
[1] The plaintiff, TrustPower, derives its business income from selling electricity.
It generates (by hydro or wind) approximately one-half of the electricity that it sells
and buys the remainder. TrustPower is New Zealand’s fourth largest retailer, and
fifth largest generator, of electricity.
[2] TrustPower seeks to maintain flexibility as to whether it generates or buys
electricity, as circumstances change. To this end, it has developed a “pipeline” of
generation projects, which it refers to as “the development pipeline”, “the optionality
pipeline”, or “the pipeline”. The pipeline is intended to provide TrustPower with
information as to the viability, feasibility, and costs of building new generation
capacity, to be used when it makes decisions as to how it sources the electricity it
sells.
[3] The development pipeline comprises a number of possible wind or hydro
generation projects, which are at various stages of the feasibility assessment.1 There
are always more projects in the pipeline than TrustPower has the financial or
resource capability to construct, or are needed to supply its customers. Nevertheless,
TrustPower considers the pipeline to be essential, to provide sufficient detailed and
robust information on which it can assess the relative merits of whether to “build” or
“buy”. TrustPower describes the development pipeline as providing it with a suite of
options as to whether to build generation capacity, or buy electricity to sell.
[4] Some projects are progressed through the pipeline to the stage of applying for
various consents (for example, land use consents, water permits, and discharge
permits) under the Resource Management Act 1991 (“the RMA”). In the period
between July 2005 and November 2007, TrustPower applied for, and obtained,
consents (“the resource consents”) in respect of four projects: Arnold River hydro on
the west coast of the South Island (“Arnold”), Kaiwera Downs wind farm, east of
Gore, Southland (“Kaiwera Downs”), Mahinerangi wind farm, west of Dunedin
(“Mahinerangi”), and Wairau River hydro, in Marlborough (“Wairau”). TrustPower
refers to resource consents obtained for projects in the development pipeline as
1 At any time there are approximately 200 projects in the development pipeline.
“Type 2” consents, to distinguish them from consents relating to existing property or
plant (which are “Type 1” consents). Each of the applications for resource consents
included an extensive “Assessment of Effects on the Environment” (“AEE”),
pursuant to s 88 (2) (b) and Schedule 4 of the RMA.
[5] The primary dispute between TrustPower and the Commissioner of Inland
Revenue (“the Commissioner”) is as to the nature of the expenditure (of
approximately $17.7 million) TrustPower incurred in applying for and obtaining the
“Type 2” resource consents in the tax years ending 31 March 2006, 2007, and 2008.2
TrustPower contends that it applied for the resource consents as part of its feasibility
analysis of each project, and before it had committed to the construction of any of
the projects. For that reason, TrustPower submits that the expenditure is revenue
expenditure, incurred in the course of deriving income from the generation and sale
of electricity, and therefore deductible for tax purposes. The Commissioner contends
that the resource consents are themselves intangible capital assets, and that from the
time TrustPower was committed to applying for the consents, the expenditure
incurred in obtaining them is capital expenditure, and therefore not deductible.
[6] If the expenditure is held to be capital, then two secondary issues arise: first,
at what time the expenditure ceased to be “revenue” and became “capital” in nature,
and secondly, whether (after that point) the Commissioner correctly allocated
particular expenditure as capital rather than revenue.
A history of the dispute
[7] TrustPower claimed that its expenditure in respect of each of the proposed
Arnold, Kaiwera Downs, Mahinerangi, and Wairau projects was deductible as
“feasibility expenditure” pursuant to the “general permission” in s DA 1(1) of the
Income Tax Act 2004 (“the ITA 2004”).3 On 31 March 2010 (for Arnold,
Mahinerangi, and Wairau) and 22 June 2010 (for Kaiwera Downs) the Commissioner
2 The exact figure in dispute was agreed between the parties to be $17,672,290 (as noted in a
schedule provided to the Court on 30 August 2013). TrustPower does not claim that expenditure
relating to its “Type 1” consents is revenue in nature. 3 The Income Tax Act 2004 applies in this case rather than its replacement, the Income Tax Act
2007.
issued Notices of Proposed Adjustments disallowing the deductions for the tax years
ending 31 March 2006, 2007, and 2008.
[8] The reason given by the Commissioner for disallowing the deductions was
that the expenditure was capital in nature, because it was incurred for the purpose of
developing and acquiring a capital asset, namely, the four proposed projects.
Expenditure that is of a capital nature cannot be deducted, pursuant to s DA 2(1) of
the ITA 2004 (“the capital limitation”).
[9] TrustPower then began the challenge procedures pursuant to s 138B(1) of the
Tax Administration Act 1994. The dispute was referred to the adjudication unit of
Inland Revenue. At the time the adjudication unit was considering the matter, the
time bar for the 2006 year was due to expire on 31 March 2011. The adjudication
unit was not able to give a decision within time, notwithstanding an extension by
agreement. The assessment for the 2006 tax year was therefore returned to Inland
Revenue’s service delivery group.
[10] On 28 September 2011, the Commissioner issued an amended assessment for
the 2006 tax year, disallowing TrustPower’s claimed deductions for feasibility
expenditure for that year.
[11] On 17 October 2011, the adjudication unit issued a report in respect of the
2007 and 2008 tax years (“the adjudication decision”). The adjudication unit
decided that, because TrustPower had not committed to proceed with the acquisition
or development of any of the proposed projects (in that the Board had not made a
formal documented decision to proceed) in any of the relevant tax years, the
expenditure was not capital in nature. Rather, it was feasibility expenditure, incurred
in order to “weigh up” whether to proceed with the project.
[12] Despite determining that, when considered within the projects to which they
related, the resource consents were part of the feasibility expenditure, the
adjudication unit went on to consider whether the resource consents were stand-
alone assets and, if so, whether they were capital or revenue assets. It concluded that
the resource consents could be either capital or revenue assets, depending on the
facts, but would in most cases be capital. The adjudication unit was not able to
determine which consents were of a capital nature, and was not able to allocate costs
between “mere feasibility expenditure” and “what constitutes the cost of the capital
assets”. The dispute was therefore returned to the service delivery group “to make
necessary adjustments resulting from the above conclusions”.
[13] On 29 March 2012, the Commissioner issued a “re-assessment letter”. The
Commissioner said that the resource consents for the four projects were “long life
consents”, and therefore would provide an enduring benefit to TrustPower. As such,
the Commissioner said, they are capital assets and the costs incurred in obtaining
them are of a capital nature. The Commissioner also said that from the time
TrustPower commenced the resource consent process for a particular project, any
costs incurred for the purpose of obtaining resource consents (as part of that process)
were properly treated as resource consent costs of a capital nature rather than as
feasibility costs.
[14] The Commissioner concluded that expenditure of approximately $17.7
million associated with resource consent applications during the 2006, 2007, and
2008 tax years was capital in nature. The deductions claimed by TrustPower were
therefore disallowed.
[15] TrustPower issued this proceeding on 8 November 2011, challenging the
Commissioner’s amended assessment in respect of the 2006 tax year, only.
Following the receipt of the re-assessment for the 2007 and 2008 tax years,
TrustPower filed an amended statement of claim on 25 May 2012, which challenges
the Commissioner’s re-assessment in respect of each of the 2006, 2007, and 2008 tax
years.
The development pipeline in more detail – feasibility investigation
[16] In his evidence for TrustPower, Dr Harker, Chairman of the TrustPower
Board of Directors, said that the pipeline of generation projects was developed to
enable TrustPower to develop new generation projects as and when profitable. Dr
Harker referred to a “Generation Development Plan” presented to the Board in
October 2002, which summarised the pipeline approach:
TrustPower Limited has identified a number of generation project
opportunities both related to the enhancement of existing assets and green
field projects with potential for generation and associated infrastructure
development. The Board of TrustPower wishes to progress some of the
viable opportunities into robust business cases for development by the
company or for sale.
The following report identifies the key development objectives, outlines the
strategy for establishing and maintaining a project pipeline, presents the
current project portfolio and a timebound action plan for progressing
selected concepts into business cases.
[17] After setting out the “key drivers” of generation development (creating
shareholder wealth, progressing projects which are economically, socially, and
environmentally sustainable, and the efficient use of resources to optimise returns),
the Plan sets out a “development strategy”, beginning with the comment:
To achieve our goal, we need to develop and maintain a healthy concept to
implementation project pipeline. We estimate that about 3 concepts out of
10 will pass the financial and economic hurdles and progress into the
feasibility stage, and only 2 or 3 of the fully appraised projects would gain
resource and land use consents and approvals required for implementation.
[18] In his evidence for TrustPower Mr Kedian, who was General Manager,
Generation at TrustPower, and responsible for overview and management of the
development pipeline from 2005 to 2011, said that the pipeline:
... consists of potential development generation projects, all at different
stages in TrustPower’s feasibility process (a significant number of them are
subsequently eliminated). Projects remain in the pipeline from the time the
project is identified until a decision is made by TrustPower’s Board to
commit either to construction of the generation scheme or to abandon the
project. ...
[19] Projects in the development pipeline are assessed through a three-step
feasibility process. The first step involves the identification of potential generation
sites and a high-level evaluation of the feasibility of this site. There are three stages
within the first step. The first stage involves identifying and evaluating potential
sites (a “desktop” exercise undertaken in-house at TrustPower) and commencing
discussions with affected landowners, with a view to obtaining agreements for access
for investigation and monitoring, and option agreements (preferably by way of
easements) in respect of future use of the land, should the project proceed to
construction. TrustPower may also consider purchasing land.
[20] The second stage of the first feasibility step involves on-site monitoring and
undertaking a high-level evaluation, to determine whether the particular project
should proceed to applications for resource consents. For the purpose of this
evaluation, TrustPower “guesstimate[s]” the cost of the project, because at this stage
no detailed geotechnical analysis of the site has been undertaken, and no detailed
design work done.
[21] The third and final stage of the first feasibility step, if a project passes the
high-level evaluation, and if it is concluded that the project (as currently envisaged)
is likely to be economically viable, is applying for resource consents. In respect of
this stage, Mr Kedian said:
3.16 The third stage of the first step feasibility process is the RMA
consent application. RMA consent is necessary before a decision can be
made to proceed with the second step feasibility study, being an evaluation
of what can be constructed, in terms of the consented project. This enables
TrustPower to analyse comprehensibly the viability of the project in its
second step process, which contemplates detailed design and costing, so as
to be able to commence the preparation of the business case for the
construction of a project.
3.17 There are two aspects to this RMA consent preparation stage of the
first step feasibility analysis. First, no project can proceed to construction
without RMA consent. Secondly, until TrustPower has RMA consent, it
does not know what it can construct or what limitations will be placed on the
scheme operation and therefore cannot determine whether the project is
viable. ... Although detailed and specific in their own terms and framework,
the RMA consents do not enable TrustPower to say “let’s go ahead and build
this”. At this time, these RMA consents reflect only in part what is a
preliminary design concept. I would estimate that at the point of making the
relevant application, engineering design would be about 10% complete. This
point is fundamental and requires some understanding of the engineering and
design complexity of the four projects.
...
3.19 TrustPower engages external experts to carry out analysis of issues
such as the impact on birds, native flora and fauna, and the noise and visual
impact of the proposed project. These studies are essential to TrustPower’s
assessment of whether the project is feasible, irrespective of the RMA
requirements. However, TrustPower also knows that these things may
subsequently impact its ability to obtain RMA consent. The project ideas
start out as purely engineering concepts without any consideration of the
RMA requirements in relation to the effects on the environment or the
community. It therefore requires each external consultant to complete a
“fatal flaw” analysis in order to identify up front any issues that will make
the project impossible to undertake. This occurs at an early stage in the
process, before a firm decision has been made to proceed with an application
for RMA consent. If there are no fatal flaws identified, the external
consultants will continue their work (alongside the other continuing work
streams) and this may all eventually form part of an application for RMA
consent.
[22] Mr Kedian further said that the “Type 2” resource consents “provide what is
the outside ‘shape of the envelope’”, for a project and “the particular resource
consent terms provide some of the relevant parameters”. He went on to say that the
resource consent terms are “no more useful than the wind or hydro data set. Each is
a critical component in the whole picture, but it is the whole picture that is defined in
the second step feasibility analysis.”
[23] The second step of the feasibility process, which is not undertaken until
resource consents are granted, involves the development of all the identified
components within the “envelope”. The second step feasibility work includes
developing the necessary civil engineering and electromechanical designs, calling for
tenders from (but not committing to) manufacturers and construction companies,
analysing how the scheme will be connected to the national grid or a local network,
and analysing the economic feasibility of the project.
[24] The third step of the feasibility process, if the project is considered viable
after the second feasibility step, is the preparation of a business case for
consideration by the Board, in which a recommendation is made to the Board as to
whether the project should proceed to construction, and a capital expenditure budget
approved.
[25] The fact that a generation project is in the development pipeline does not
mean that it will ultimately be constructed. Dr Harker said in evidence that
TrustPower will “postpone its own developments when it is cheaper to purchase and
this postponement can be ongoing”. Purchasing may be the better option, for
example, if other competitors have better new-build options than TrustPower has, or
if other generators or retailers have cheaper electricity available from over-supply.
Against that, reliance on purchasing electricity from other sources carries risks,
which can be minimised if TrustPower has the ability to increase its generation
capacity within a reasonably short period of time.
[26] Dr Harker’s evidence was that “the intention of the development pipeline is
to provide TrustPower with development options that can be weighed up against
other options”. He said:
Development options in the pipeline are just options that enable good
decisions about the source of supply to be made. Put another way,
TrustPower is investing in a “chance” with these projects. While over the
next 20 to 30 years it is possible that all projects in TrustPower’s pipeline
could be built, I can say with confidence that they will not all be built by
TrustPower in the next 10 years. TrustPower will only pursue the “build”
option and progress a project in its development pipeline, where it is
confident that this is a better use of its funds than sourcing supply through
the “buy” option. However, options in the pipeline that may not be
considered to be worthwhile at a particular time help TrustPower assess the
merits and value of either not seeking to increase sales, or meeting existing
or new demands from other wholesale sources.
[27] A key factor in assessing the viability of any project in the development
pipeline is the impact of “HVDC charges”. The HVDC (high voltage direct current)
power line is more commonly known as the “Cook Strait cable”, and links the North
and South island high voltage transmission systems (“the national grid”). A charge is
imposed on South Island generators injecting electricity into the national grid. The
charge can only be avoided if, rather than being injected into the national grid,
electricity from South Island generation is embedded directly into a local distribution
network. Mr Kedian’s evidence was that the HVDC charge has a fundamental effect
on the economics of projects in the development pipeline.
[28] Mr Kedian reported to the TrustPower Board each month on projects in the
development pipeline. A table setting out the pipeline was included in the Agenda
papers. The Table was divided into five sections, reflecting the stage projects had
reached in the development pipeline: “In Final Design/Construction Planning
Phase”, “In Consenting/Engineering Design Phase”, “Land Access/Scoping Phase”,
“Preliminary Investigation Phase”, and “Prospect Parked”.
[29] Chronologies of progress of each of the four projects are set out in the
Appendix to this judgment. The chronologies were derived from an agreed
chronology provided by the parties, and documents in the agreed bundle of
documents.
What are the issues?
The pleadings
[30] In the Amended Statement of Defence to TrustPower’s Amended Statement
of Claim, the Commissioner put in issue (by denying or asserting having no
knowledge of allegations) the majority of TrustPower’s allegations. The
Commissioner also made affirmative allegations in respect of many of TrustPower’s
allegations.
[31] In his submissions for TrustPower, Mr Harley criticised the Commissioner’s
pleading as being, in various respects, unresponsive to TrustPower’s allegations,
factually incorrect or misleading, and contrary to the matters and determinations set
out in the adjudication decision. Mr Harley’s objections are noted. TrustPower’s
position on these matters has been made clear in its reply to the Amended Statement
of Defence,4 and in the evidence and submissions for TrustPower.
[32] Mr Harley referred, in particular, to the Commissioner’s pleading in response
to TrustPower’s allegation (at paragraph 9 of the Amended Statement of Claim) of its
three-step feasibility analysis for potential new generation projects. At paragraph 9
of the Amended Statement of Defence, the Commissioner denies the “three-step”
characterisation of the feasibility analysis, and affirmatively alleges that
TrustPower’s process for analysing and developing potential new electricity
generation projects involved a “four phase, 24 step” process. Mr Harley submitted
that this was contrary to the adjudication unit’s acceptance, in the adjudication
decision, of TrustPower’s characterisation of the feasibility analysis process.
[33] Witnesses for TrustPower, Dr Harker, Mr Kedian, and Mr Campbell, all gave
evidence of the three-step feasibility analysis process. Their characterisation of the
process was not challenged on behalf of the Commissioner, and no evidence was
given for the Commissioner in support of the alleged four phase 24 step process.
4 Dated 10 July 2012, but incorrectly titled “Defendant’s Amended Statement of Reply to
Plaintiff’s Amended Statement of Defence”.
[34] While the role and significance of applications for resource consents is an
issue for determination, I have concluded that there is no real issue as to
TrustPower’s characterisation of the feasibility analysis process. If I am wrong in
that conclusion, then I accept TrustPower’s characterisation of the three-step process
and reject the Commissioner’s alleged four phase 24 step process.
Matters not pleaded
[35] Mr Harley also objected to the Commissioner having, through various
witnesses who gave evidence for the Commissioner, put in issue a number of factual
issues and propositions which were not raised in the pleadings. Again, while the
objection is noted, TrustPower had the opportunity to, and did, file reply evidence,
and the “new” issues were canvassed at the hearing.
[36] Two particular matters raised at the hearing (but not pleaded) must be
mentioned. First, expert evidence was given for the Commissioner to the effect that
TrustPower’s accounting treatment of the expenditure at issue in this proceeding was
inaccurate, and that its financial statements were materially mis-stated and wrong.
TrustPower called expert evidence in reply. I accept Mr Harley’s submission that the
Commissioner’s evidence as to the accuracy of TrustPower’s financial statements is
not relevant to the matters at issue in this proceeding. I have disregarded it in my
consideration of the issues. However, I add that having heard the evidence for
TrustPower and the Commissioner, I could not conclude that TrustPower’s financial
statements were materially mis-stated and wrong.
[37] The second matter relates to the submission made by Mr McLellan QC on
behalf of the Commissioner, that expenditure in obtaining resource consents was
non-deductible, for the reason that it was incurred for the purpose of improving
capital assets; that is, TrustPower’s interests in the underlying land.
[38] Mr Harley submitted that this argument could not be raised now, as it had not
been pleaded, and as it is barred from being raised by s 138G of the Tax
Administration Act. Section 138G(1) provides that the Commissioner and a
“disputant” may raise in a challenge only those matters raised in their Statements of
Position. Mr Harley submitted that the Commissioner’s Statements of Position,
while referring to “rights in relation to land” (in the context of expenditure incurred
in developing the projects themselves, rather than what the resource consents
provided to TrustPower) do not put forward a proposition that the resource consents
are an improvement to the land.
[39] Mr McLellan submitted that the issue of whether the resource consents
enhance or improve land was not “new”. He provided references to the
Commissioner’s Statement of Position. I have not found in those references any
clear statement to the effect that the Commissioner was asserting that the expenditure
incurred in obtaining the resource consents was of a capital nature, having been
incurred for the purpose of improving or enhancing the underlying land. Further, I
accept that there is no pleading to that effect.
[40] Accordingly, I accept Mr Harley’s submission that the argument cannot now
be raised. Notwithstanding that, Mr Harley addressed the argument in his
submissions and, for that reason, the issue will be referred to later in this judgment.
Issues emerging in closing submissions
[41] Although counsel framed the issues in different terms, there are four principal
issues (each of which raises sub-issues) to be determined:
(a) Are the resource consents obtained by TrustPower for the Arnold,
Kaiwera Downs, Mahinerangi, and Wairau projects assets, on a stand-
alone basis, (that is, separate from the projects to which they relate)?
If the answer to this question is “no”, then because TrustPower had
not committed to the projects, the expenditure it incurred in obtaining
the resource consents is feasibility expenditure and therefore
deductible.
(b) If, however, the resource consents are stand-alone assets, the nature of
the expenditure needs to be determined. Are the resource consents
capital or revenue assets? If the answer to this question is that they
are capital assets, then the expenditure incurred in obtaining them will
not be deductible. If the answer is that they are revenue assets, the
expenditure will be deductible.
(c) If the resource consents are capital assets, was the Commissioner
wrong in her conclusions as to the dates from which TrustPower’s
expenditure was to be classified as being principally for the purpose
of obtaining them (such dates being those from which the
Commissioner considers that TrustPower was committed to applying
for the resource consents)?
(d) If the Commissioner was correct as to the dates from which
TrustPower was committed to applying for the resource consents, did
she wrongly allocate expenditure as between feasibility expenditure,
and the expenditure incurred in obtaining the resource consents?
The “general permission” and the “capital limitation”
[42] For taxation purposes, the distinction between capital expenditure and
revenue (income) expenditure is created by the ITA 2004. Pursuant to s DA 1 (the
“general permission”) expenditure which is incurred in deriving assessable income is
deductible:
DA 1 General permission
Nexus with income
(1) A person is allowed a deduction for an amount of expenditure or loss
(including an amount of depreciation loss) to the extent to which the
expenditure or loss is —
(a) incurred by them in deriving —
(i) their assessable income; or
(ii) their excluded income; or
(iii) a combination of their assessable income and
excluded income; or
…
General permission
(2) Subsection (1) is called the general permission.
[43] However, pursuant to s DA 2(1) (the “capital limitation”), a deduction is not
allowed if expenditure is of a capital nature:
DA 2 General limitations
Capital limitation
(1) A person is denied a deduction for an amount of expenditure or loss
to the extent to which it is of a capital nature. This rule is called the
capital limitation.
Relationship of general limitations to general permission
(7) Each of the general limitations in this section overrides the general
permission.
The capital/revenue determination: overview of leading authorities
[44] In his judgment in Inland Revenue Commissioners v British Salmson Aero
Engines Ltd (“British Salmson”) (concerning whether a royalty payment made by a
user of a patent was a capital or income payment), Sir Wilfred Greene MR
observed:5
There … have been … many cases where this matter of capital or income
has been debated. There have been many cases which fall on the border-
line. Indeed, in many cases it is almost true to say that the spin of a coin
would decide the matter almost as satisfactorily as an attempt to find
reasons.
[45] Templeman J expressed a similarly pessimistic view in his judgment in
Tucker (Inspector of Taxes) v Granada Motorway Services Ltd (“Granada Motorway
Services”), concerning a payment made to secure modifications of rent obligations
under a lease.6 His Honour said:
7
The forensic field of conflict involved in this appeal [as to whether a
payment to secure a more favourable lease was of a capital or revenue
nature] is an intellectual minefield in which the principles are elusive …,
analogies are treacherous …, precedents appear to be vague signposts
pointing in different directions …, and the direction finder is said to be
“judicial common sense” … The practice of judicial common sense is
difficult in Revenue cases.
(References omitted)
[46] Despite this pessimism, the courts have formulated and discussed tests for
classifying expenditure as being on capital or revenue account. In Hallstroms Pty
5 Inland Revenue Commissioners v British Salmson Aero Engines Ltd [1938] 2 KB 482 (CA) at
498. 6 Tucker (Inspector of Taxes) v Granada Motorway Services Ltd (1979) 53 TC 92 (ChD).
7 At 96–97.
Ltd v Federal Commissioner of Taxation (“Hallstroms”), Dixon J referred to Sir
Wilfred Greene’s observation in British Salmson, but was:8
… not prepared to concede that the distinction between an expenditure on
account of revenue and an outgoing of a capital nature is so indefinite and
uncertain as to remove the matter from the operation of reason and place it
exclusively within that of chance, or that the discrimen is so unascertainable
that it must be placed in the category of an unformulated question of fact.
[47] His Honour went on to say:9
What is an outgoing of capital and what is an outgoing on account of
revenue depends on what the expenditure is calculated to effect from a
practical and business point of view, rather than upon the juristic
classification of the legal rights, if any, secured, employed or exhausted in
the process.
The practical and business point of view – the BP Australia indicia
[48] In giving the judgment of the Privy Council in BP Australia Ltd v
Commissioner of Taxation for the Commonwealth of Australia (“BP Australia”)
(concerning whether a payment to service station proprietors as consideration for the
proprietors’ agreement to sell one brand of petrol, exclusively, was capital or
revenue), Lord Pearce said in relation to the approach to be taken to the
capital/revenue determination:10
The solution to the problem is not to be found by any rigid test or
description. It has to be derived from many aspects of the whole set of
circumstances some of which may point in one direction, some in the other.
One consideration may point so clearly that it dominates other and vaguer
indications in the contrary direction. It is a common sense appreciation of
all the guiding features which must provide the ultimate answer. Although
the categories of capital and income expenditure are distinct and easily
ascertainable in obvious cases that lie far from the boundary, the line of
distinction is often hard to draw in border line cases; and conflicting
considerations may produce a situation where the answer turns on questions
of emphasis and degree. That answer:
“depends on what the expenditure is calculated to effect from a
practical and business point of view, rather than upon the juristic
classification of the legal rights, if any, secured, employed or
exhausted in the process”
8 Hallstroms Pty Ltd v Federal Commissioner of Taxation (1946) 72 CLR 634 at 646.
9 At 648.
10 BP Australia Ltd v Commissioner of Taxation for the Commonwealth of Australia [1966] AC 224
(PC) at 264–265.
As each new case comes to be argued felicitous phrases from earlier
judgments are used in argument by one side and the other. But those phrases
are not the deciding factor, nor are they of unlimited application. They
merely crystallise particular factors which may incline the scale in a
particular case after a balance of all the considerations has been taken.
(Citation for Hallstroms omitted)
[49] The analysis in BP Australia has been endorsed in New Zealand. In
Commissioner of Inland Revenue v McKenzies (NZ) Ltd (“McKenzies”), the Court of
Appeal considered whether a payment to secure the surrender of a lease was of a
capital or revenue nature.11
Delivering the judgment of the Court (holding that the
payment was capital), Richardson J set out the observations of Lord Pearce in BP
Australia as to the capital/revenue determination, then went on to say:12
Amongst the factors weighed by the judicial committee in BP Australia
were: (a) the need or occasion which called for the expenditure; (b) whether
the payments were made from fixed or circulating capital; (c) whether the
payments were of a once and for all nature producing assets or advantages
which were an enduring benefit; (d) how the payment would be treated on
ordinary principles of commercial accounting; and (e) whether the payments
were expended on the business structure of the tax payer or whether they
were part of the process by which income was earned.
His Honour said that it was “a matter of analysing the particular transaction ... by
reference to the legal arrangements entered into and carried out and taking into
account surrounding circumstances”.13
[50] More recently, the Privy Council endorsed the BP Australia indicia in
Commissioner of Inland Revenue v Wattie (in relation to a determination whether an
incentive payment for entry into a lease was capital or revenue).14
The Privy
Council noted that the BP Australia indicia had been described by Richardson J in
Commissioner of Inland Revenue v Thomas Borthwick & Sons (Australasia) Ltd as
exemplifying the “governing approach” in New Zealand.15
11
Commissioner of Inland Revenue v McKenzies (NZ) Ltd [1988] 2 NZLR 736 (CA). 12
At 740. 13
At 742. 14
Commissioner of Inland Revenue v Wattie [1999] 1 NZLR 529 (PC). 15
Commissioner of Inland Revenue v Thomas Borthwick & Sons (Australasia) Ltd (1992) 16
TRNZ 777 (CA) at 779.
The “identifiable asset” test
[51] The decision of Templeman J in Granada Motorway Services that the
payment was capital expenditure was upheld by the Court of Appeal and the House
of Lords. In the House of Lords, Lord Wilberforce set out what has since been
referred to as the “identifiable asset” test. His Lordship said:16
On the one hand the payment was designed to enable the Company to earn
more profits: from this point of view it might be thought that the payment
should have a revenue character. On the other hand, the payment produced a
modification in the lease, which could be regarded as an identifiable asset,
making the lease less disadvantageous: from this point of view it might be
thought that the payment should be regarded as a capital payment. It is
common in cases which raise the question whether a payment is to be treated
as a revenue or capital payment for indicia to point different ways. In the
end the courts can do little better than form an opinion which way the
balance lies. There are a number of tests which have been stated in reported
cases which it is useful to apply, but we have been warned more than once
not to seek automatically to apply to one case words or formulae which have
been found useful in another ... I think the key to the present case is to be
found in those cases which have sought to identify an asset. In them it
seems reasonably logical to start with the assumption that money spent on
the acquisition of the asset should be regarded as capital expenditure. ...
Later in his judgment, Lord Wilberforce said of the identifiable asset test:17
The test may be to some extent arbitrary, but it provides a means which the
courts can understand for distinguishing capital and income expenditure and
I think that we would be wise to maintain it.
Further New Zealand authorities
[52] In Buckley & Young Ltd v Commissioner of Inland Revenue (“Buckley &
Young”), the Court of Appeal had to decide whether payments to a departing director
of the company were of a capital or revenue character.18
The director agreed to leave
the company, and entered into a restrictive covenant not to compete with, or divulge
information about, the company. In return, he was to be paid $6,000 a year, together
with other payments. In his judgment for the Court, Richardson J observed that:19
... what is involved is the fundamental distinction between the source of the
income and the income earning process; between capital and income;
16
Tucker (Inspector of Taxes) v Granada Motorway Services Ltd (HL), above n 6, at 106–107. 17
At 108. 18
Buckley & Young Ltd v Commissioner of Inland Revenue [1978] 2 NZLR 485 (CA). 19
At 488.
between expenses affecting the business structure or entity and operating
expenses. ... [t]he essential question is as to the true character of the
payments made and the benefits provided. But, while that distinction is well
recognised, it is equally well established that there is no single yardstick or
test. ...
[53] His Honour set out the alternatives on the opposite sides of the
capital/income dividing line in Buckley & Young as follows:20
A payment made as a matter of commercial necessity or expediency to
secure the removal of an unsatisfactory director or employee is referable
only to the current business operations of the taxpayer in gaining its
assessable income and that also stamps it with the character of a revenue and
not a capital disbursement. ... But a payment made to a retiring director or
employee in return for a restrictive covenant ... which has the effect of
buying off competition, of its very nature affects the value of the company’s
goodwill and is referable to the income earning structure rather than to the
income earning process and is of a capital nature.
The Court held that the payments in question had a dual character, as being revenue
(and deductible) insofar as they referred to securing the director’s retirement, and
capital (and not deductible) to the extent that they referred to the restrictive covenant.
[54] In McKenzies, Richardson J observed that in BP Australia, and in the
“companion case” involving Mobil Oil Australia Ltd, the decision was that the
payments were revenue payments, but in Regent Oil Co Ltd v Strick (Inspector of
Taxes), delivered the same day, the House of Lords (with the same Bench) held that
the oil company’s payments were capital expenses.21
His Honour said that:22
The different result is a valuable demonstration of the importance of
evaluating the facts of particular cases and recognising ... that the capital
income field is an intellectual minefield in which the principles are elusive
and analogies are treacherous.
(reference to Granada Motorway Services omitted)
[55] Richardson J also referred to the identifiable asset test set out in Granada
Motorway Services, and observed that Lord Wilberforce had endorsed the test in the
sense that so long as the expenditure in question could be clearly referred to the
acquisition of an assets which satisfied one or other of the accepted categories, the
20
At 489. 21
Regent Oil Co Ltd v Strick (Inspector of Taxes) [1966] AC 295 (HL). 22
McKenzies, above n 11, at 741.
test must be a critical one. However, the test would yield in cases where there were
sufficient indicators pointing the other way.23
[56] As the Court of Appeal observed in McKenzies, in uncomplicated cases, one
or more factors may very clearly point to the expenditure being capital or revenue in
nature, so recourse to all of the factors referred to may be unnecessary. However, in
borderline cases, it is necessary to analyse the facts as a whole, and consider which
factors carry the most weight. As noted in Hallstroms, the capital/revenue decision
requires considering what the expenditure was calculated to effect, from a practical
and business point of view, rather than a juristic classification of legal rights.24
Resource consents and the Income Tax Act
Resource consents
[57] The “Type 2” resource consents obtained by TrustPower were land use
consents, water permits, and discharge permits. Pursuant to s 9 of the RMA, a
person cannot use land in a manner which contravenes a national environmental
standard prescribed under s 43 of the RMA, or a rule in a district or regional plan,
unless such use is either expressly permitted by the RMA, or the person is authorised
to use the land in a manner which is otherwise prohibited by the RMA, national
environmental standards, or a district or regional plan. Similarly, a water consent
permits a person to use water (other than in a coastal marine area) in a way which
would otherwise contravene s 14 of the RMA, and a discharge consent permits a
person to discharge contaminants (other than in a coastal marine area) in a way that
would otherwise contravene s 15 of the RMA,
[58] A resource consent is, therefore, permissive. It authorises a certain land use
or activity, that would otherwise be unlawful. If the consent is exercised, it must be
in accordance with any conditions imposed in the grant of the consent. A person
granted a resource consent is not required by the RMA to exercise it, but if the
consent is not exercised within its prescribed duration, it will lapse.
23
At 746. 24
Hallstroms, above n 8, at 648.
[59] Section 88(1) of the RMA provides that “a person” may apply for a resource
consent. Thus, an application can be made for a resource consent over land the
applicant does not own, or to which the applicant does not have agreed access.25
Section 88(2) provides that the application must be made in the prescribed form and
manner, and must include, in accordance with Schedule 4, an assessment of
environmental effects in such detail as corresponds with the scale and significance of
the effects that the activity may have on the environment.
[60] Section 122(1) of the RMA provides that “a resource consent is neither real
nor personal property”.
[61] Pursuant to s 134 of the RMA, land use and subdivision consents attach to the
land to which they relate, so may be “enjoyed” by the owner and occupier of the
land. If the holder of the consent does not own the land, then the owner and the
holder may each “enjoy” the land use consent. The holder of the resource consent
may transfer the holder’s interest in the consent, pursuant to s 134(3) of the RMA.
Other consents, such as permits to take water or to discharge contaminants, may in
certain circumstances be transferred by the holder of the permit, in accordance with
ss 136 and 137 of the RMA, respectively.
Resource consents in the context of the Income Tax Act
[62] Section DB 13B of the ITA 2004 provides (as amended as from 1 October
2005) that a person who applies for a resource consent under the RMA, and is
refused the grant or withdraws the application, is allowed a deduction for
expenditure incurred in relation to the application, that would have been part of the
cost of depreciable property, or otherwise a deduction, if the application for resource
consent had been granted, and for which a deduction is not allowed under another
provision.
[63] Section EE 53(1) (in subpart EE “Depreciation”) of the ITA 2004 provides
that depreciable intangible property means the property listed in Schedule 17.
Section EE 53(2) sets out the criteria for property to be listed in Schedule 17. It is
25
See MacLaurin v Hexton Holdings Ltd [2008] NZCA 570, (2008) 10 NZCPR 1 (CA), at [47].
required to be intangible, and to have a finite useful life that could be determined
with a reasonable degree of certainty at the date of its acquisition. Section EE 53(3)
provides that property listed in Schedule 17 is depreciable intangible property even if
the criteria in s EE 53(3) are not met.
[64] Pursuant to s OB 1 (definition of “property”), “property” in subpart EE
includes consents granted under the RMA. Thus, for the purposes of subpart EE
(Depreciation), s OB 1 of the ITA 2004 overrides s 122 of the RMA, and resource
consents can be property. The explanatory note to the introduction to s OB 1 states
that the provision was introduced to “include for depreciation purposes consents
under the [RMA]” due to certain consents (those listed in Schedule 17) being able to
be treated as depreciable intangible property.26
[65] The property listed in Schedule 17 of the ITA 2004 (depreciable intangible
property) includes, at clause 9:
9 a consent granted under the [RMA] to do something that otherwise
would contravene sections 12 to 15 of [the RMA] (other than a consent for a
reclamation), being a consent granted in or after the 1996-97 tax year
Submissions as to the statutory context
[66] For the Commissioner, Mr McLellan relied on s OB 1 of the ITA 2004 to
argue that under the ITA, resource consents are property. He further submitted that
ss DB 13B and EE 53 (together with clause 9 of Schedule 17) support the conclusion
that resource consents are prima facie capital assets, and that the purposes of s DB
13B shows that resource consents should be capitalised. In support of this
submission, Mr McLellan referred to the explanatory note on the introduction of the
legislation under which s DB 13B was inserted into the ITA 2004. The explanatory
note in respect of s DB 13B stated:27
Patent and resource management application costs
An amendment is proposed that allows costs associated with patent and
resource management consent applications to be deducted, although the
applications are not granted or are withdrawn. Costs for such applications
26
See Taxation (Miscellaneous Issues) Bill 1995 (No 109-1) (explanatory note) at xv. 27
Taxation (Annual Rates, Venture Capital and Miscellaneous Provisions) Bill 2004 (No 110-1)
(explanatory note) at 5.
cannot currently be claimed under the general deductibility rules as they are
a capital expense. Nor can they be depreciated as there is no depreciable
asset. Under the proposed change, the deductible expenditure consists of
those costs that would have been depreciable if a patent or resource
management consent had been granted.
[67] Mr McLellan also referred to the Commentary on the Bill:28
Patents and certain consents issued under the [RMA] are depreciable
intangible property. To the extent expenditure incurred in applying for a
patent or resource management consent results in an application being
granted, the costs must be capitalised and depreciated. However, if an
application is unsuccessful or is withdrawn, any costs incurred up to that
point are not depreciable as there is no depreciable asset. Nor can this
expenditure be expensed under the general deductibility rules because it is
capital in nature.
Mr McLellan submitted that s DB 13B made it clear that resource consents, once
granted, are capital assets, and hence must be property.
[68] Mr Harley submitted that subpart EE does not apply in this case, as
TrustPower did not use, or have available for use, the resource consents during the
relevant tax years.29
On that basis, he submitted, the consents were not depreciable,
and the expenditure incurred in obtaining them was deductible under the general
permission. Thus, pursuant to s EE 7(j), the resource consents cannot be depreciable
property, s OB 1 cannot apply, and under s 122 of the RMA, the consents would not
be property.
[69] Mr Harley further submitted that s DB 13B of the ITA 2004 is irrelevant to
the issues to be considered in this proceeding. He submitted that s DB 13B cannot
inform the decision as to whether the expenditure is deductible. He submitted that
s DB 13B is not a catch-all provision.
28
Policy Advice Division “Taxation (Annual Rates, Venture Capital and Miscellaneous Provisions)
Bill 2004, Commentary on the Bill” (Inland Revenue, Wellington, 2004) at 9. 29
The relevant tax years were the years ending 31 March 2006, 2007, and 2008. The resource
consents for the projects were granted as follows: Arnold: 17 December 2010; Kaiwera Downs:
30 May 2009; Mahinerangi: 15 December 2008; Wairau: 8 June 2011. In each case the consents
were pursuant to a decision of the Environment Court.
Discussion
[70] In Aoraki Water Trust v Meridian Energy Ltd (“Aoraki Water Trust”)
(concerning an application to take water in respect of which Meridian had a permit to
take all the available water), a Full Court of the High Court referred to s 122 of the
RMA and said that, pursuant to s 122(1), a resource consent is not itself either real or
personal property, but creates a right to use a resource.30
[71] In Marlborough District Council v Valuer-General, Ronald Young J
discussed s 122 in the context of an application for a declaration that mussel farms
authorised by coastal permits under the RMA were rateable as “land”.31
His Honour
accepted that s 122(1) prevents the courts from recognising any property rights, real
or personal, in respect of resource consents except where, and only to the extent that,
Parliament has provided for them. In the case before him, his Honour concluded that
the grant and operation of a coastal permit did not give rise to any real property.32
[72] In another context, concerning different legislation, s 122 of the RMA has not
been regarded as determinative. In its judgment in New Zealand Maori Council v
Attorney-General (“NZ Maori Council”), the Supreme Court accepted that water
permits obtained by Mighty River Power were properly regarded as “interests in the
Waikato River”, and were “assets” as defined in the State-Owned Enterprises Act
1986.33
In this respect, the Court differed from the position taken by Ronald Young J
in the High Court, in reliance on s 122 of the RMA.34
The Supreme Court went on
to observe, however, that the issue before it was not whether the water permits were
property rights, rather whether the public offering of shares in Mighty River Power
constituted a disposal of any such rights. The Court held that it did not.35
[73] In this case, the provisions of the RMA establish the nature of the “legal
arrangements entered into”36
(that is, the resource consents applied for and obtained)
30
Aoraki Water Trust v Meridian Energy Ltd [2005] 2 NZLR 268 (HC) at [35]. 31
Marlborough District Council v Valuer-General [2008] 1 NZLR 690 (HC). 32
At [41]–[59]. 33
New Zealand Maori Council v Attorney-General [2013] NZSC 6, [2013] 3 NZLR 31 (SC) at
[81]. 34
New Zealand Maori Council v Attorney-General [2012] NZHC 3338 at [334]. 35
New Zealand Maori Council v Attorney-General, above n 33, at [81]–[82]. 36
See McKenzies, above n 11, at 742.
but while that is an important part of the analysis, it does not determine the
interpretation and application of the tax legislation. While it is necessary to consider
the nature and effect of the resource consents, the RMA provisions do not dominate.
[74] Turning to the ITA 2004, while the parties agree as to which provisions are
relevant, they disagree as to their application. The first area of disagreement is as to
whether s EE 7(j) applies, and so whether subpart EE applies. I accept Mr Harley’s
submission that, as TrustPower did not use the resource consents, or have them
available for use, during the relevant tax years, subpart EE cannot apply. However,
even if subpart EE did apply, it could only be consents permitting activities
otherwise restricted by ss 12–15 of the RMA that are “depreciable intangible
property” pursuant to Schedule 17 of the ITA 2004. Those consents do not include
land use consents, and it is land use consents which are significant in each of the four
projects referred to in this case.
[75] The second area of dispute concerns s DB 13B. I note, first, that s DB 13B
was amended by the Taxation (Base Maintenance and Miscellaneous Provisions) Act
2005. The Select Committee in 2005 commented that:37
The intent of [the 2004 amendment] was to allow a deduction for costs [of a
resource consent application that is unsuccessful or withdrawn] that would
have been depreciable either in their own right or as part of the cost of other
depreciable property, if the application was granted. However, as a result of
the drafting of this provision, these costs are not deductible if they would
have been part of the cost of other depreciable property had the consent been
granted. This was not intended, and we recommend that the bill be amended
to correct this effect.
We recommend amending the bill to provide that consent costs that would
have been deductible if a resource consent had been granted are also within
the scope of these rules. ...
[76] I conclude that s DB 13B provides no guidance as to how resource consents
should be treated. I do not accept Mr McLellan’s submission that the need for s DB
13B supports the proposition that resource consents are identifiable assets that
should be capitalised and may be able to be depreciated. What s DB 13B provides is
that resource consents may be capitalised; it does not provide that they should be.
37
Taxation (Base Maintenance and Miscellaneous Provisions) Bill (231-2) (select committee
report) at 10.
Further, the commentary indicates that resource consents may be separate, or part of
other depreciable property. I do not accept the submission for the Commissioner that
s DB 13B supports a conclusion that all resource consents are separate assets and
that expenditure incurred in applying for them is non-deductible.
[77] While I do not accept Mr Harley’s submission that the provisions of s DB
13B and Schedule 17 of the ITA 2004 are irrelevant, I conclude that it is appropriate
to exercise caution in drawing inferences from the wording of one section of the ITA
2004 as to the interpretation and application of another section. Referring again to
McKenzies, Richardson J’s observation concerning the applicability of provisions
relating to the tax treatment of other kinds of lease transactions to the deductibility of
payments to surrender leases is instructive:38
… we consider that the provisions of the Income Tax Act referring to the
income tax treatment of receipts and payments in relation to other kinds of
lease transactions are an insubstantial foundation from which to draw
inferences as to the assessability or deductibility of payments in respect of
the surrender of leases, one way or the other.
[78] After referring to provisions relating to leases (which did not deal with
payments made or received on surrender of a lease), Richardson J said:39
In the circumstances it would be unsafe to draw any inference of a legislative
purpose other than that their character as capital or income fall for
determination on general taxation principles.
[79] In interpreting and applying ss DA 1 (the general permission) and DA 2, (the
capital limitation) regard must be had to the scheme and purpose of the ITA 2004 as
a whole. The ITA provides a framework, but will not be determinative as to whether
TrustPower’s expenditure in obtaining the resource consents was capital or revenue
in nature. That issue to be determined by considering what the expenditure was
“calculated to effect from a practical and business point of view”,40
and weighing the
factors set out in BP Australia,41
and McKenzies.42
38
McKenzies, above n 11, at 739–740. 39
At 740. 40
See Hallstroms, above n 8, at 648. 41
BP Australia, above n 10. 42
McKenzies, above n 11.
Are the resource consents obtained by TrustPower, on a stand-alone basis,
assets?
Introduction
[80] Mr Harley submitted that the “logically prior” question to whether the
resource consents were capital or revenue assets (and whether expenditure incurred
in obtaining them was capital or revenue in nature) was whether the resource
consents could properly be said to be “assets”. If they are not assets, he submitted, it
follows that there is no need to consider whether they are capital or revenue assets by
applying the BP Australia tests.
[81] The word “asset” is not generally defined in the ITA 2004.43
The question
whether the resource consents are assets arises out of the identifiable asset test
formulated for the purpose of deciding whether expenditure is on capital or revenue
account: see Granada Motorway Services,44
and McKenzies.45
While the word
“asset” is often seen as referring to a proprietary right in something of value, for tax
purposes, the term “asset” has broader application. In Sun Newspapers Ltd v
Federal Commissioner of Taxation (“Sun Newspapers”), Dixon J considered
whether:46
The result or purpose of the expenditure may be to bring into existence or
procure some asset or advantage of a lasting character which will enure for
the benefit of the organization or “profit-earning subject”.
(Emphasis added)
Accordingly, in order to determine the “logically prior” question, it is necessary to
consider the nature of the resource consents, and what they provide for TrustPower.
[82] The resource consents gave TrustPower permission to do something that it
otherwise could not legally do: to use land, to use water, or to discharge
contaminants. Without land use consents, it could not legally construct any of the
four projects. Without water and discharge permits, it could not legally construct the
43
“Asset” is defined in section CU11 and section DU8, both of which relate to mining. The
definitions are restricted to those subparts. 44
Granada Motorway Services, above n 6, at 106-107. 45
McKenzies, above n 11, at 746. 46
Sun Newspapers Ltd v Federal Commissioner of Taxation (1938) 61 CLR 337 at 361.
Arnold and Wairau hydro projects. Grants of the required resource consents were
necessary for each project to continue along the development pipeline.
[83] The period of a land use consent is unlimited, unless otherwise specified in
the consent. A water or discharge permit may be granted for up to 35 years although
the default duration is five years.47
TrustPower generally sought water and discharge
consents for ten year periods.
[84] Like the ITA 2004, case law is somewhat ambiguous as to whether resource
consents are stand-alone, “separate”, assets. In his decision for the Taxation Review
Authority in Case T53, Judge Barber declined an application by a taxpayer to deduct
legal fees incurred in a successful appeal against the refusal of resource consents
required to carry on a second-hand machinery business.48
In declining the
deduction, Judge Barber said:49
In securing a resource consent it seems to me that the objector has clearly
obtained an enduring benefit or advantage. That resource consent gave the
objector the benefit or advantage of having the legitimate right to trade, or
operate a business, on the particular farmland. This is an intangible benefit
both for the objector company and the land which belongs to GR and his
wife.
Judge Barber said further:50
Mr Brown submits that, on the facts of this case, no identifiable asset is
produced by the expenditure. However, it seems to me that the resource
consent is an intangible asset of the business of the objector. In so far as the
objector submitted that the expenditure related to the protection of a right, I
observe that the expenditure actually relates to the obtaining of a right which
did not previously exist before the granting of the resource consent.
[85] In Milburn New Zealand Ltd v CIR (“Milburn”), Wild J held that expenditure
incurred in obtaining resource consents and licences for Milburn’s quarries for
sourcing aggregate and lime for its cement and concrete business was of a capital,
not revenue nature.51
In the course of considering the “character of the advantage
47
Resource Management Act 1991, s 123. 48
Case T53 (1998) 18 NZTC 8,404 (TRA). 49
At [21]. 50
At [27]. 51
Milburn New Zealand Ltd v CIR (2001) 20 NZTC 17,017 (HC).
sought” (one of the BP Australia indicia), his Honour said of a submission for the
Commissioner that the consents and licences “had a lasting quality”:52
I prefer to view the consents and licences as inseparable from the quarries to
which they are related. But even if they are viewed separately, as assets in
their own right, they are enduring and not recurrent in nature.
[86] In ECC Quarries Ltd v Watkis (Inspector of Quarries) (“ECC Quarries”)
Brightman J considered whether expenses incurred in obtaining relevant consents for
a quarry were capital or revenue.53
In his judgment his Honour expressed doubt as
to whether the consents were assets (in their own right),54
but found that the consents
allowed the subsequent operations of working and winning the minerals. The
consents themselves would not produce profits, but the operations permitted by the
consents would.55
Submissions
[87] Mr Harley submitted that TrustPower’s “Type 2” resource consents cannot be
isolated and seen, on a stand-alone basis, as assets. He submitted that when seen
from TrustPower’s business and practical point of view, the resource consents are
only part of the components of a particular project option, each option is part of the
development pipeline as a whole, and the pipeline is only one of the possible sources
of electricity to be sold by TrustPower. He submitted that the resource consents
“simply tell TrustPower how much fuel it has available to it” and the consents do this
by determining how much water can be used in a hydro station, or how many wind
turbines can be erected on a wind farm. Mr Harley accepted that a grant of resource
consent was necessary to advance a project along the development pipeline, but
pointed out that the grant was not in and of itself sufficient for a decision to be made
to take any project through to the next stage.
[88] Mr Harley further submitted that at the time the resource consents are
granted, the underlying project is inchoate, and has no business utility. The various
conditions imposed in the consent need to be satisfied, and TrustPower needs to
52
At 17,025. 53
ECC Quarries Ltd v Watkis (Inspector of Quarries) [1977] 1 WLR 1386 (ChD). 54
At 1396. 55
At 1397.
make a decision to progress the project to construction, before the project can be
considered as a reality. Without this “reality”, he submitted, neither the underlying
project nor the resource consents were close to being “assets”.
[89] Mr Harley also submitted that the Commissioner’s focus on the resource
consents (and in particular, the AEEs submitted with the application for consents)
focused on the wrong question. He submitted that the proper focus is the role and
place of resource consents in TrustPower’s feasibility and optionality analysis
process. He also submitted that the fact that resource consents may share some
characteristics of real and personal property (such as transferability) did not mean
that the consents were to be recognised by the Court as assets.
[90] Mr McLellan submitted that the resource consents are assets, for the reasons
that they are fundamental aspects of the development pipeline (in which very few
projects are taken to the stage of obtaining resource consents), and the consents
provide value and benefits to TrustPower both by themselves and as part of a
package of rights. He submitted that the resource consents provided TrustPower
with the ability to decide whether to construct the project or defer it until later, the
existence of the consents was a block to any competitor carrying out competing
activity in the same area, and the consents could also be sold by TrustPower. In all
of these respects, the consents were of value to TrustPower. Mr McLellan further
submitted that the resource consents had value to third parties. Accordingly, he
submitted, the consents are properly regarded as assets for tax purposes, under the
ITA 2004.
[91] Mr McLellan also referred to the evidence of Professor Evans, called by the
Commissioner to give expert evidence as to the nature (and in particular the value)
of TrustPower’s resource consents, from the perspective of an economist. Mr
McLellan summarised Professor Evans’ evidence as being that the value of the
resource consents lay in their (a) providing rights to essential resources and the
ability to choose the timing of investment and project expenditure, (b) being property
(intangible assets) independent of (but complementary to) the land to which they
relate, (c) providing enduring flows of services, and (d) being tradable with some
restrictions.
Discussion
[92] I accept Mr Harley’s submission that in none of T53, Milburn, and ECC
Quarries, was a question raised as to whether the taxpayer was committed to
undertaking the operation for which the consents were required. That is, the
taxpayer in T53 was carrying on the business of selling second-hand machinery, and
Milburn and ECC Quarries were concerned with consents for existing quarries.
These cases are, therefore, ones involving what Mr Harley described as “functional
capital assets”. In each case, the consents obtained were a crucial part of carrying on
the business, and are akin to those which TrustPower describes as “Type 1” consents,
for existing operations.
[93] However, the finding in each of these cases that the consents are inseparable
from the business or land to which they relate lends support to the conclusion that
the resource consents in this case cannot be seen as separate assets, on a stand-alone
basis. That is, the consents cannot be seen as assets which are separable from the
projects to which they relate.
[94] I have referred to the evidence for TrustPower in some detail, at [16] to [28],
above, and in the chronologies set out in the Appendix. I accept that TrustPower
obtained the resource consents in the course of taking the respective projects further
along the development pipeline, and that the consents can be said to be part of the
components of each of the project options. While each of the witnesses for
TrustPower accepted that the consents were of value to TrustPower, each said that
that value was only as part of a “bundle”, “package”, or “suite” of rights. I also
accept TrustPower’s evidence that the development pipeline itself is only one part of
TrustPower’s business development: constructing a hydro station or wind turbine to
generate electricity is only one method by which TrustPower sources electricity to
sell. Buying electricity for re-sale is always considered against generating it.
[95] Further, the value of resource consents may be tenuous, at best: for example,
having resource consents is not all that is required for the decision whether to
proceed to construction, or to defer the project. I accept TrustPower’s evidence that
there are many other factors that must be considered. Secondly, the fact that
TrustPower has resource consents will not “block” competitors from competing in
the area. As Mr Campbell said in his evidence for TrustPower, the same wind will
blow across the hill next to where TrustPower has resource consents. I also accept
Mr Harley’s submission that in the absence of a commitment by TrustPower to
proceed to construction, there is very little competitive advantage in holding
resource consents. Further, I accept that resource consents, on a stand-alone basis,
will be of little interest for possible sale. Any value of the consents could only be as
part of a package. Such value as the resource consents may have does not, in my
view, lead to the consents being stand-alone, assets, independent of the projects to
which they relate.
[96] That conclusion is reinforced by the evidence relating to the approach in
relation to Kaiwera Downs (referred to at 2.12 of the Appendix). The offer was to
purchase the site, including the resource consents, technical reports and designs,
landowner agreements, and any physical assets related to the project. That is, the
offer was in relation to the project as a whole, not the resource consents on a stand-
alone basis.
[97] On the particular facts of this case, I therefore find that the resource consents
obtained by TrustPower for the Arnold, Kaiwera Downs, Mahinerangi, and Wairau
projects are not stand-alone assets, separate from the projects to which they relate.
The resource consents are part and parcel of the projects. It would be artificial from
a practical and business point of view to regard them as separate assets in their own
right. The expenditure in obtaining them must, therefore, be treated in the same
manner as the projects. As noted at [11], above, the adjudication unit decided that
expenditure relating to the projects was not capital in nature. Rather, it was
feasibility expenditure. The same conclusion must apply in relation to the
expenditure incurred in obtaining resource consents, as they are not stand-alone
assets, separate from the projects to which they relate. It follows that TrustPower’s
expenditure was feasibility (revenue) expenditure, and is deductible pursuant to the
general permission.
The BP Australia indicia
[98] The above conclusion is sufficient for me to find in favour of TrustPower.
However, for the sake of completeness, and in case it is held that I am wrong in that
conclusion, and the resource consents are stand-alone assets, I go on to consider,
briefly, the BP Australia indicia in order to determine whether they are capital or
revenue assets.
What was the need or occasion which called for the expenditure?
[99] Identifying the need or occasion for expenditure involves considering the
factual background in which the expenditure was incurred, and the reason for the
payment. In Birkdale Service Station Ltd v Commissioner of Inland Revenue, the
Court of Appeal observed that, in that case, the background (in other words, the
“need or occasion for the expenditure”) to the transactions at issue (lump sum
payments made in connection with the taxpayer’s entry into certain agreements) was
of considerable importance.56
If there is more than one reason, the principal reason
for the payment determines the character of the payment.57
[100] Mr Harley submitted that it is evident that there were multiple purposes
behind the expenditure incurred before TrustPower applied for resource consents.
He accepted that one of the purposes of the expenditure was to make an application
for resource consent (if the decision was ultimately made to do so), but submitted
that that was not the principal purpose. None of the purposes was more significant
or more important to TrustPower than others. He submitted that to place emphasis
on one purpose over others was misguided; the focus of the case must be on the
nature or character of the expenditure. The true character of the expenditure incurred
in obtaining resource consents was that it advanced projects along the feasibility
pipeline, and supported pipeline optionality. Thus, the expenditure was of the same
character as TrustPower’s other operating costs.
56
Birkdale Service Station Ltd v Commissioner of Inland Revenue [2001] 1 NZLR 293 (CA) at
[33]. 57
See Christchurch Press Co Ltd v Commissioner of Inland Revenue (1993) 15 NZTC 10,206
(HC) at 10,209.
[101] Mr McLellan submitted that the principal purpose for which TrustPower
incurred the expenditure was to secure resource consents for each of the projects. He
submitted that the principal purpose of instructing consultants to prepare AEEs,
carrying out consultation, and lodging applications for consents was to apply for and
obtain consents. He submitted that it was unrealistic for TrustPower to maintain that
securing resource consents was not the principal purpose of the expenditure.
[102] This question requires the determination of a factual issue. I have accepted
TrustPower’s evidence that the resource consents were applied for and obtained in
the course of taking the respective projects further along the development pipeline. I
would accept that the purpose, or occasion, for the expenditure was not solely or
principally to obtain resource consents. Rather, I would find that the expenditure
was incurred as part of TrustPower’s investigation into the feasibility of the projects,
to define the parameters of possible projects, and to enable an assessment of possible
projects against TrustPower’s other options for sourcing electricity to sell to
customers.
[103] Accordingly, on this aspect of the BP Australia indicia, I would find that the
occasion or need for the expenditure points to it being on revenue rather than capital
account.
Were the payments made from fixed or circulating capital?
[104] The distinction between fixed and circulating capital (as a guide to
determining whether expenditure is of a capital or revenue nature) was noted in the
judgment of the House of Lords in John Smith & Son v Moore, where Viscount
Haldane, drawing on the distinction made by Adam Smith in The Wealth of Nations,
discussed two ways in which profit may be produced: from the sale of purchases on
income account (circulating capital), and from realisation of assets forming part of
the business concern (fixed capital).58
For tax purposes, the former indicates
revenue, the latter capital.
58
John Smith & Son v Moore [1921] 2 AC 16 (HL) at 19.
[105] In Milburn, Wild J was unable to view the test of whether expenditure was
from fixed or circulating capital as compelling, or even useful, and wondered
whether it “might not be given a quiet burial”.59
In Commissioner of Inland Revenue
v Fullers Bay of Islands (“Fullers”) (in which the issue was whether legal fees
incurred in attempting to secure a contract were on capital or revenue account),
Baragwanath J said that the abandonment of the concept of nominal capital in the
Companies Act 1993 pointed to the “unreality” of treating the source of funds as a
significant guide to whether expenditure is to be treated as capital or revenue for tax
purposes.60
Fullers was appealed to the Court of Appeal, which upheld the
reasoning of Baragwanath J.61
In its judgment, the Court of Appeal did not discuss
any of the BP Australia indicia, and made no comment on the utility of the
fixed/circulating capital test.
[106] Mr Harley submitted that in Milburn and Fullers, their Honours did not
correctly refer to the question whether expenditure is part of circulating capital – a
principle with, as he put it, a 120-year pedigree. He submitted that the contrast is
between expenditure which can be seen to create fixed capital assets, and
expenditure which funds revenue operations as cashflows circulate between
purchases of supplies and receipts of sales. On that analysis (adapting the wording
of Lord Pearce in BP Australia), he submitted that the expenditure incurred in
obtaining resource consents could only be seen as part of annual development costs
(circulating capital) which was being turned over and in that process, yielded profits
or loss.62
Mr McLellan submitted that the fixed/circulating capital test did not shed
any light on the issue I have to determine.
[107] The fixed/circulating capital test was applied by the Privy Council in BP
Australia (as “merely one indication and by no means conclusive”63
) and indirectly
endorsed by the Privy Council more recently, by their Lordships’ endorsement of the
BP Australia indicia in Commissioner of Inland Revenue v Wattie.64
The Privy
Council noted that the BP Australia indicia had been described by Richardson J in
59
Milburn, above n 51, at [48]. 60
Commissioner or Inland Revenue v Fullers Bay of Islands [2005] 2 NZLR 255 (HC) at [36]. 61
Fullers Bay of Islands v Commissioner of Inland Revenue (2006) 22 NZTC 19,716 (CA). 62
See BP Australia, above n 10, at 266. 63
BP Australia, ibid. 64
Commissioner of Inland Revenue v Wattie, above n 14.
Commissioner of Inland Revenue v Thomas Borthwick & Sons (Australasia) Ltd as
exemplifying the “governing approach” in New Zealand.65
While I have similar
reservations as to the general utility of this test to those expressed by Baragwanath J
in Fullers, I am not prepared to disregard the test.
[108] In BP Australia, Lord Pearce stated that the test was whether the sums were
“paid out of fixed or circulating capital”.66
This test focuses on the source of the
funds used in the expenditure.67
Lord Pearce contrasted fixed capital:68
... that on which you look to get a return by your trading operations ...
with circulating capital:
... that which comes back in your trading operations ... [expenditure] which
is turned over and in the process of being turned over yields a profit or loss ..
part of the constant demand which must be answered out of the returns of the
trade.
[109] Mr Harley’s submission referred to the use to which the expenditure was put:
contrasting expenditure that creates fixed capital assets, with expenditure that funds
revenue operations as cashflows circulate between purchases of supplies and receipts
of sales. I do not accept that Mr Harley’s submission accurately reflects the
formulation of this test in the authorities.
[110] However, even if Mr Harley is right in his formulation of this test, I do not
find the fixed/circulating capital test useful in this case. First, there is little or no
evidence as to the source of the funds used for the expenditure. Secondly, even if the
focus is on the use of the expenditure, then it would require a determination of the
nature of the resource consents (as capital or revenue assets) before it could be
applied: in other words, on the facts of this case it would be a circular test for
determining if the expenditure incurred in obtaining the resource consents is capital
or revenue in nature.
65
Commissioner of Inland Revenue v Thomas Borthwick & Sons (Australasia) Ltd, above n 15, at
779. 66
BP Australia, above n 10, at 265. 67
See also Mallet v Stavely Coal & Iron Co Ltd [1928] 2 KB 405 (CA) at 413 and 417, and Anglo-
Persian Oil Co Ltd v Dale (Inspector of Taxes) [1932] 1 KB 124 (CA). 68
BP Australia, above n 10, at 265–266.
Was the expenditure of a once and for all nature producing assets or advantages
which were of an enduring benefit for TrustPower?
[111] In British Insulated and Helsby Cables Ltd v Atherton, Viscount Cave
stated:69
... when an expenditure is made, not only once and for all, but with a view to
bringing into existence an asset or an advantage for the enduring benefit of a
trade ... there is very good reason (in the absence of special circumstances
leading to an opposite conclusion) for treating such an expenditure as
properly attributable not to revenue by to capital.
[112] There are two parts to this question: first, whether the expenditure was once
and for all or recurring, and secondly, whether the assets or advantages produced
were of an enduring benefit to TrustPower.
(a) Was the expenditure of a once and for all or recurrent nature?
[113] In Vallambrosa Rubber Co Ltd v Farmer, Lord Dunedin considered it:70
... not a bad criterion of what is capital expenditure as against what is income
expenditure to say that capital expenditure is a thing that is going to be spent
once and for all, and income expenditure is a thing that is going to recur
every year.
In Sun Newspapers Dixon J described the “once and for all” test as a “by no means
successful” attempt to find a test to decide whether expenditure was capital or
revenue.71
His Honour concluded that “recurrence is not a test, it is no more than a
consideration the weight of which depends on the nature of the expenditure.”72
[114] TrustPower acknowledged that, if the focus were solely on individual
resource consents, then the expenditure was properly described as “one-off”.
However, Mr Harley submitted that, as TrustPower regularly incurs expenditure for
obtaining a number of consents within the context of the development pipeline, the
expenditure should be recognised as being recurrent (and pointing towards revenue,
rather than capital, expenditure). Mr McLellan submitted that the expenditure was
“once and for all”, because once obtained, the resource consents endured and did not
69
British Insulated and Helsby Cables Ltd v Atherton [1926] AC 205 (CA) at 213–214. 70
Vallambrosa Rubber Co Ltd v Farmer (1910) 5 TC 529 at 536. 71
Sun Newspapers, above n 46, at 361. 72
Ibid, at 362.
have to be re-applied for in the short to medium term, and once exercised, had a long
duration.
[115] The distinction is not between expenditure which is incurred once only, and
that which is incurred on a regular basis. In Sun Newspapers, Dixon J referred with
approval to the dicta of Rowlatt J in Ounsworth v Vickers Ltd,73
that “the real test is
between expenditure which is made to meet a continuous demand, as opposed to an
expenditure which is made once and for all.”74
In this case the dispute is whether
the resource consents should be seen in isolation, or within the context of the
development pipeline. Lord Pearce considered in BP Australia that it is necessary to
take a broad view of the general operation under which the expenditure was
incurred.75
Taking such a broad view of TrustPower’s operation requires me to
consider the expenditure in obtaining the resource consents within the context of the
development pipeline.
[116] In that context, I would accept TrustPower’s submission that most of the
expenditure was not primarily directed at obtaining the resource consents, but was to
assess the feasibility of the projects and recurrent in nature, being continually
incurred to investigate and define the feasibility of the various projects. It is clear
from the evidence that there were many projects in the pipeline, and some
progressed further than others. Expenditure was continually being made to assess
the feasibility of projects, including (for some projects) expenditure to obtain the
resource consents. While applications for resource consents were not made in all of
the projects in the development pipeline, applications were (to adapt the language of
BP Australia) part of the regular feasibility process, and certainly “one of the current
necessities of” the feasibility process.76
[117] That conclusion can be supported by reference to Commissioner of Taxation v
Ampol Exploration Ltd (“Ampol”).77
That case concerned the nature of expenses
incurred in oil exploration, where the only benefit from the exploration was to be the
73
Ounsworth v Vickers Ltd [1915] 3 KB 267 at 273. 74
Sun Newspapers, above n 46, at 362. 75
BP Australia, above n 10, at 264. 76
Ibid, at 265. 77
Commissioner of Taxation v Ampol Exploration Ltd (1986) 13 FCR 545.
chance of participation in further exploration. In his judgment, holding that the
expenses were deductible, Lockhart J said that the expenditure was:78
... in truth part of the outgoings of the taxpayer in the course of carrying on
its ordinary business activities. It was not expenditure incurred for the
purpose of creating or enlarging a business structure of profit-yielding or
income-producing asset.
In his judgment, Burchett J characterised the expenditure as “an incident in the
operations by which [the business] is carried on.”79
[118] I would conclude that this aspect of the test indicates that the expenditure was
of a revenue nature.
(b) Were the assets or advantages produced of an enduring benefit to
TrustPower?
[119] In Anglo-Persian Oil Co Ltd v Dale (Inspector of Taxes) (“Anglo-Persian
Oil”), Rowlatt J explained that an “enduring benefit” means:80
... a benefit which endures in the way that fixed capital endures; not a benefit
that endures in the sense that for a good number of years it relieves you of a
revenue payment. ... It is not always an actual asset, but it endures in the way
that getting rid of a lease or getting rid of an onerous capital asset ... endures.
Therefore, if expenditure is made to bring about an asset or advantage that endures in
the way that fixed capital endures, this points to the expenditure being capital in
nature.81
[120] Mr Harley accepted that, within the context of the development pipeline, the
resource consents provided benefits to TrustPower, and in that sense, the expenditure
was incurred in order to create or add value. He submitted that this was hardly
surprising, as any company would normally intend expenditure to result in creating
or adding value. More is required before “adding value or a benefit” indicated
expenditure on capital account. However, he submitted, whether the resource
consents were to be seen as securing an enduring benefit is not to be measured by the
78
At 562. 79
At 575, referring to Hallstroms [above n8] at 648. 80
Anglo-Persian Oil Co Ltd v Dale (Inspector of Taxes) (1931) TC 253 at 262, affirmed on appeal
in Anglo-Persian Oil Co Ltd v Dale, above n 67, at 146. 81
Sun Newspapers, above n 46, at 361.
duration of the particular consent. Mr Harley submitted that there is an inherent
uncertainty surrounding the terms and duration of resource consents, once granted,
that is difficult to reconcile with a submission that they provide an enduring benefit
to TrustPower. He further submitted that the resource consents do not produce any
income for TrustPower, absent any commitment to build a generation plant.
[121] Mr Harley also submitted that the resource consents did not provide
TrustPower with an enduring benefit of the kind argued for the Commissioner – that
is, the advantage of strategic optionality as to building the project now, deferring
building, blocking competitors from areas where TrustPower has consents, or selling
the consents. He submitted that the Commissioner’s argument ignored the
multiplicity of purposes served by the development pipeline of which the resource
consents are part, and was based on a misconception of the “value” or “benefit”
provided by the consents.
[122] Mr McLellan submitted that the resource consents provided TrustPower with
an enduring benefit or advantage of strategic optionality. This includes the ability to
proceed immediately with development of the project within the ten-year period
before the consent lapses, to defer construction within that period, to block or
exclude other generators from undertaking competing activities in areas where
TrustPower has been granted consents, or to sell the resource consents (with or
without land, land access rights, or intangible assets such as research and design
work), if the project ceases to be feasible for TrustPower or the price is right.
[123] I accept Mr Harley’s submission that the presence of a project in the
development pipeline does not mean that the project will ultimately result in one of
the benefits argued for by the Commissioner, and referred to in Professor Evans’
evidence. As he submitted, many projects never make it to the stage where any of
the alleged benefits can arise. It is a matter of chance (in the words of TrustPower’s
witnesses, it requires “the stars to align”), whether any project proceeds to that stage.
I also accept Mr Harley’s submission that TrustPower does not know, at the time
expenditure is incurred, whether resource consents will be applied for, or whether the
particular project concerned will progress further along the pipeline.
[124] In Milburn, Wild J considered that regardless of whether the resource
consents were inseparable from the land, or separate assets, they clearly provided an
enduring benefit due to the period of time they were granted for.82
Although I would
accept Mr Harley’s submission that there is an inherent uncertainty surrounding the
terms and duration of resource consents, and whether projects will be progressed
further, the consents last for a significant period, and can therefore provide an
enduring benefit.
[125] This aspect of the BP Australia indicia would, therefore, indicate that the
expenditure in obtaining resource consents should be regarded as capital rather than
revenue expenditure.
How would the payment be treated on ordinary principles of commercial
accounting?
[126] In Milburn, Wild J observed that while accounting treatment might provide a
useful guide in some cases, it is not determinative of the correct treatment for tax
purposes, and it is always subject to the rules of the income tax legislation.83
[127] Expert evidence on accounting standards was called by TrustPower (Mr
Hagen, and Mr Freeman (of PricewaterhouseCoopers, TrustPower’s auditors)) and
by the Commissioner (Mr Hucklesby). They focused on two standards: New
Zealand Equivalent to International Accounting Standards (“NZIAS”) 16 and NZIAS
38. Mr Harley submitted that both NZIAS 16 and NZIAS 38 pointed to the
expenditure on the resource consents being revenue rather than capital. Mr
McLellan submitted that NZIAS 38 applied, and pointed to the expenditure being
capital.
[128] The title of NZIAS 16 is “Property, Plant and Equipment”. Paragraph [2]
provides that it is to be applied in accounting for property, plant and equipment
“except when another Standard requires or permits a different accounting treatment.”
Paragraph [7] provides that:
7. The cost of an item of property, plant and equipment shall be
recognised as an asset if, and only if:
82
Milburn, above n 51, at 17,025. 83
Ibid, at 17,026.
(a) it is probable that future economic benefits associated with
the item will flow to the entity; and
(b) the cost of the item can be measured reliably.
[129] The title of NZIAS 38 is “Intangible Assets”. Paragraph [2] provides that it is
to be applied in accounting for intangible assets, except (as relevant to this case)
intangible assets that are within the scope of another standard. In paragraph [8],
“asset” is defined as a resource:
(a) controlled by an entity as a result of past events; and
(b) from which future economic benefits are expected to flow to
the entity.
An “intangible asset” is defined as:
... an identifiable non-monetary asset without physical substance.
Paragraphs [21] and [22] of NZIAS 38 provide:
21. An intangible asset shall be recognised if, and only if:
(a) it is probable that the expected future economic benefits that
are attributable to the asset will flow to the entity; and
(b) the cost of the asset can be measured reliably.
22. An entity shall assess the probability of future economic benefits
using reasonable and supportable assumptions that represent
management’s best estimate of the set of economic conditions that
will exist over the useful life of the asset.
Paragraph [57] (“Development Phase”) of NZIAS 38 is relevant. It provides:
57. An intangible asset arising from development ... shall be recognised
if, and only if, an entity can demonstrate all of the following:
(a) the technical feasibility of completing the intangible asset so
that it will be available for use or sale.
(b) its intention to complete the intangible asset and use or sell
it.
(c) its ability to sell the intangible asset.
(d) how the intangible asset will generate future economic
benefits. ...
(e) the availability of adequate technical, financial and other
resources to complete the development and to use or sell the
intangible asset.
(f) its ability to measure reliably the expenditure attributable to
the intangible asset during its development.
[130] Mr Hagen’s opinion was that the only difference between NZIAS 16 and
NZIAS 38 is between a tangible and an intangible asset. Whichever applied, the
expenditure incurred by TrustPower in obtaining the resource consents should be
recognised as feasibility costs, and should not be recognised as the costs of acquiring
a capital asset (whether tangible or intangible). Mr Freeman’s opinion was that
NZIAS 16 applied rather than NZIAS 38, because it was very unlikely that an
intangible asset (as defined under NZIAS 38) would result. Mr Hucklesby’s opinion
was that NZIAS 38 applied and that the resource consents were assets, as defined.
[131] For the purposes of this discussion, if the resource consents are stand-alone
assets (contrary to my earlier finding), they could only be intangible assets. As such,
I doubt that NZIAS 16 would apply.
[132] I therefore turn to consider NZIAS 38. Both TrustPower and the
Commissioner accepted that if the resource consents were intangible assets under
NZIAS 38 and not part of the “development phase” (under paragraph [57]) then they
would be treated as capital. Paragraph [57] of NZIAS 38 is crucial.
[133] The resource consents were obtained in the course of progressing projects
along the development pipeline. If the consents were “assets” as defined in NZIAS
38, then they arose from a development phase. There was no evidence that, at the
time the expenditure was incurred, TrustPower intended to complete the projects in
respect of which the resource consents were obtained (as the adjudication report
found, there was no commitment to construct any of the projects), nor any evidence
that TrustPower intended to use or sell the consents, independent of the projects to
which they related. While an offer was made to purchase one of the projects,
including the resource consents, TrustPower did not apply for the consents with the
intention of selling them. Further, in the light of TrustPower’s evidence that there
were always more projects in the development pipeline than it had the financial and
resource capability to construct, TrustPower could not have demonstrated the
availability of adequate technical, financial, or other resources to complete the
projects and use the resource consents. On this basis, under NZIAS 38, the
expenditure would not be recognisable as capital and would properly be treated as
revenue.
[134] Accordingly, I would conclude that this aspect of the BP Australia indicia
indicates that the expenditure in obtaining resource consents should be held to be
revenue rather than capital.
Was the expenditure incurred on the business structure of TrustPower, or as part of
the process by which income was earned?
[135] In Sun Newspapers, Dixon J noted the distinction between:84
... the business entity, structure or organisation set up or established for the
earning or profit” and “the process by which such an organisation operate to
obtain regular returns by means of regular outlay. ...The business structure ...
may assume any of an almost infinite variety of shapes ... In a trade or
pursuit where little or no plant is required, it may be represented by no more
than the intangible elements constituting what is commonly called goodwill
... At the other extreme it may consist in a great aggregate of buildings,
machinery and plant all assembled and systematized as the material means
by which an organized body of men produce and distribute commodities or
perform services.
[136] Mr Harley submitted that the expenditure incurred in obtaining the resource
consents does not create or reflect any business structure of TrustPower. He
submitted that the consents are not means by which TrustPower can produce income,
in the absence of a commitment to build a hydro station or wind turbine. Mr
McLellan submitted that TrustPower’s business structure included capital assets
relating to the generation of electricity, and that the expenditure was incurred
principally for the purpose of creating those assets. He submitted that as TrustPower
cannot legally generate electricity without having such consents, the consents are
fundamental parts of the TrustPower’s business structure.
[137] I would accept Mr Harley’s submission that the consents are not means by
which TrustPower can produce income, in the absence of a commitment to proceed
to construct the project concerned. As Mr Harley submitted, the Mahinerangi project
illustrates this point. The resource consents for this project were granted in
December 2008. The TrustPower Board approved construction of Stage 1 of the
project in April 2010. Although the consents were necessary for the project to be
constructed, they did not generate any electricity, and they did not create any income
for TrustPower.
84
Sun Newspapers, above n 46, at 359–360.
[138] I am satisfied that, if it is held that the resource consents are assets, they
could not be regarded as part of TrustPower’s business structure. I would conclude
that this aspect of the BP Australia indicia indicates that the resource consents should
be found to be revenue assets.
From a practical and business point of view, is the expenditure to be regarded as
capital or revenue in nature?
[139] None of these tests is determinative on its own. Rather, each test assists with
determining the central question posed by Dixon J in Hallstroms: what was
TrustPower’s expenditure incurred in obtaining the resource consents “calculated to
effect from a practical and business point of view”?85
I would conclude that even if
the resource consents were stand-alone assets, from a business and practical point of
view, they were revenue assets, and the expenditure to obtain them is revenue in
nature. As the BP Australia indicia were derived to assist in answering the question
posed in Hallstroms,86
the answer is in large part set out in the analysis of the indicia,
and need not be repeated.
[140] I would accept the force of Mr Harley’s submission that the expenditure
incurred in obtaining the resource consents was indiscriminate as part of
TrustPower’s general business operations expenses. The expenditure was not to
secure the specific consents, but to assist TrustPower in determining a source of
supply of electricity. When seen from TrustPower’s business and practical point of
view, the resource consents are only one of the components of a particular project
option, each option is part of the development pipeline as a whole, and the pipeline is
only one of the possible sources of electricity to be sold by TrustPower. A grant of
resource consents was necessary to advance a project along the development
pipeline, but the grant was not in and of itself sufficient for a decision to be made to
take any project through to the next stage.
[141] TrustPower did not use the resource consents in the tax years concerned, and
it did not generate any income from them. I would accept that the resource consents
were of value to TrustPower, only as part of a “bundle”, “package”, or “suite” of
85
See Hallstroms, above n 8, at 648. 86
See BP Australia, above n 10, at 264–265.
rights, and as part of the development pipeline, which itself is only one part of
TrustPower’s business development. Accordingly, from a practical and business
point of view, I would find that TrustPower’s expenditure incurred in obtaining the
resource consents was incurred as part of the feasibility process and is, therefore,
revenue in nature.
Was TrustPower’s expenditure in obtaining resource consent incurred for the
purposes of improving its interest in the underlying land?
Introduction
[142] I turn to consider, briefly, Mr McLellan’s submission that the expenditure was
non-deductible, as it was incurred to improve a capital asset; that is, TrustPower’s
interest in the underlying land. He submitted that TrustPower owned or had interests
in at least part of the land for all four projects, was committed to obtaining (or had an
expectation that it could obtain) the residual land, and incurred the expenditure to
obtain the consents to “improve the functionality of the land”. He submitted that the
functional connection between the land and the consents was illustrated by evidence
that (in the case of Arnold) TrustPower intended to sell land if it did not obtain the
consents.
[143] Mr McLellan submitted that the resource consents provided TrustPower with
the rights to construct and operate power plants on the land, and thereby improved
the functionality of the land. He referred to ECC Quarries as authority for the
proposition that expenditure incurred to obtain planning permission to improve the
functionality of land (that is, a capital asset).87
[144] In addition to submitting that the argument could not now be raised, Mr
Harley submitted that the Commissioner’s argument had not confronted important
legal and factual hurdles. These were that the resource consents did not become part
of the land to which they relate, so the consents could be transferred independently
of the land, or TrustPower could sell land it owned without the consents.
Accordingly, the present situation is distinguishable from that in ECC Quarries,
where the planning permission could not, by law, be transferred.
87
ECC Quarries Ltd, above n 53.
[145] Secondly, he submitted that the Commissioner could not say that the resource
consents had resulted in an increase in the value of the underlying land, or that the
land had become more advantageous, or how the land had been “radically and
enduringly changed”88
by the resource consents.
Discussion
[146] I accept Mr Harley’s submission that this argument could not succeed. There
is, in this case, no factual foundation for it. As well, the Commissioner’s argument
does not deal with the evidence given by Mr Campbell (TrustPower’s present
General Manager Generation) that TrustPower prefers easements to land ownership.
In the event that, as a result of the resource consents, there was an increase in the
value of land over which TrustPower has an easement, such increase would accrue to
the landowner, not TrustPower. Nor does the Commissioner’s argument deal with
TrustPower’s evidence that it is often the case (particularly in relation to hydro
projects) that land decreases in value if resource consents are granted for
construction of electricity generation plants.
[147] Accordingly, if I were required to consider the Commissioner’s argument that
the resource consents enhanced the value of the underlying land, and the expenditure
incurred in obtaining the consents is therefore capital expenditure, I would find
against the Commissioner.
TrustPower’s alternative argument: classification of expenditure
Introduction
[148] TrustPower’s alternative argument, in the event that I were to find that the
expenditure in obtaining the resource consents was capital rather than revenue
expenditure, was that the Commissioner wrongly classified expenditure in the
“capital” and “revenue” categories. TrustPower claims that the Commissioner has
wrongly classified approximately $6.5 million as consenting (capital) costs.89
I deal
88
See ECC Quarries, at 1397. 89
As set out in the schedule provided to the Court on 30 August 2013, the exact amount claimed
by TrustPower as having been wrongly classified is $6,565.936.
with this briefly, again for the sake of completeness, and because evidence and
submissions on this argument formed a significant part of the hearing.
[149] It was common ground that the classification depended on whether particular
items of expenditure were incurred as part of the “feasibility” process, or as part of
the “consenting” process. It was also common ground that the primary distinction
between the two was to be made on the basis of when TrustPower could be said to
have been “committed” to applying for resource consents.90
TrustPower submitted
that it was not committed to applying for resource consents until very shortly before
the respective applications were filed. The Commissioner says that the commitment
was at a much earlier date.
[150] A second issue, which arises only if I accept the Commissioner’s argument as
to the “commitment date”, is whether all costs after that date must be classified as
“consenting” (and therefore capital), or whether some costs can be regarded as
continuing the feasibility process (and therefore revenue).
When was TrustPower committed to filing applications for resource consents?
[151] Ms Hablous, who argued this point for TrustPower, referred to the evidence
of Dr Harker and Mr Kedian, which was that Mr Kedian made the decision that
resource consents would be applied for, except in the case of Wairau, where the
TrustPower Board approved lodging the application. She submitted that the decision
to lodge the applications could not be, and was not, made until such time as
TrustPower had all the information required to make a decision whether to proceed
with the applications. TrustPower was not in that position until it had all the
consultants’ reports, and had undertaken all necessary assessments. Ms Hablous
submitted that the fact that the reports were later included in the AEEs was
immaterial. TrustPower’s standard instruction to the consultants was that their
reports were to be in a suitable format for inclusion in the AEEs. That was simply to
avoid unnecessary cost in re-submitting and re-formatting reports.
90
As recorded at [11], above, the adjudication unit found that expenditure on the underlying
projects was feasibility, rather than capital, expenditure, on the grounds that TrustPower had not
committed to proceed with the acquisition or development of any of the projects.
[152] In contrast, Mr Andrews, who argued this point for the Commissioner,
submitted that TrustPower was committed to lodging the applications at about the
time it instructed consultants to prepare reports. He submitted that this work would
not have been commissioned had TrustPower not formed the intention to lodge the
applications.
[153] The competing contentions were as outlined below. I note that a full
chronology for each project is set out in the Appendix to this judgment.
(a) Arnold
TrustPower: The decision to apply for resource consents was made at
or around the time the application was lodged on 29 March 2006.
Prior to that date, TrustPower was still considering the economics of
an amended scheme (the Taramakau diversion) and technical
concerns, and continuing discussions with recreational groups;
Commissioner: The decision was made to apply for resource consents
in November 2005, when Board approval was given to expenditure to
acquire land purchases and option agreements. At that time, the
Board was advised that it was anticipated that the resource consent
application would be lodged around the end of November 2005.
(b) Kaiwera Downs
TrustPower: The decision to apply for resource consents was made at
or around the time the application was lodged on 5 November 2007.
Prior to that time TrustPower had commissioned further reports after a
potential “fatal flaw” was revealed in original visual and landscape
feasibility reports, further modelling work was undertaken, and
project economics were assessed.
Commissioner: The decision to apply for resource consents was made
in May 2007, after draft scoping studies for planning, noise, aquatic
assessment, traffic assessment, and terrestrial ecological assessments
were received, noting that on 27 April 2007 the Board was advised
that consent work had started towards application.
(c) Mahinerangi
TrustPower: The decision to apply for resource consents was made at
or around the time the (second) application for resource consent was
lodged in early December 2006, replacing an application that had
been lodged in late June 2006. The second application did not seek
consent to erect turbines on land owned by Dunedin City Council (and
DCC had asked TrustPower to delay lodging the application). The
application had to be re-worked.
Commissioner: the decision to apply for resource consents was made
in November 2005, when briefs of work for social work, landscape
and visual, traffic, and ecological assessments, and legal services were
sent out. At this time, the Board was advised that lodgement of the
resource consent applications was targeted for late February/March
2006.
(d) Wairau
TrustPower: The decision to apply for resource consents was made at
or around the time the Board resolved to approve an application for
resource consents being lodged, at its meeting in June 2005.
TrustPower says that Board approval was necessary (as recorded in a
report to the Board in April 2004) because of the complexities of the
project. The Board was not presented with a full evaluation report, on
which the project economics could be assessed, until 30 June 2005.
Commissioner: The decision to apply for resource consents was made
in September 2004. At this time, the Board was advised that a
resource consent application was to be lodged in November 2004,
subject to receiving Board approval and securing access/easements in
key positions, and that the economics of the project would deteriorate
only if there were difficulty with landowners or resource management
impediments.
Discussion
[154] I accept the evidence given by TrustPower. The Commissioner’s analysis of
TrustPower’s “commitment” rested on the dates on which consultants were
instructed to prepare reports and/or target or “hoped for” dates of lodgement
provided to the Board. I do not accept that these are reliable indicators of
TrustPower being committed to applying for resource consents. I accept on the basis
of TrustPower’s evidence, supported by the matters recorded in the chronologies,
that TrustPower was not committed to lodging applications for resource consents
until such time as it had received and considered all relevant information.
[155] Further, I accept TrustPower’s submission that the fact that consultants were
instructed to prepare reports in a form that was suitable for inclusion in an AEE is
not evidence of a commitment to lodge an application for resource consents. Rather,
it is an indication that TrustPower was mindful of the possibility (or even
anticipated) that an application would be lodged, and wished to have the necessary
reports ready to go if and when the decision was made to apply. From a business and
practical point of view, this would be to reduce cost and unnecessary duplication.
[156] I would find that TrustPower was not committed to lodging applications for
resource consent until at or around the time the applications were lodged.
Accordingly, I would find that the expenditure incurred up until that time is revenue
expenditure and as such is deductible under the general permission. I am, therefore,
not required to consider the second issue, as to classification of costs incurred after
the “commitment” date.
Result
[157] I find in favour of TrustPower on its primary claim. TrustPower is entitled to
the declaration and determinations sought at paragraph 75 of its First Amended
Statement of Claim.
[158] In the event that costs cannot be agreed between the parties, memoranda may
be filed: on behalf of TrustPower within 20 days of the release of this judgment, and
on behalf of the Commissioner within a further 15 days. Unless the parties in their
memoranda request a hearing, a decision as to costs will be made on the papers.
________________________
Andrews J
Appendix
The four projects: description and chronology
The following description and chronology of each of the four proposed projects is
derived, in the main, from the chronology agreed by the parties, and the agreed
bundle of documents.
1. Arnold hydro
1.1 The Arnold River is the outlet of Lake Brunner on the west coast of the South
Island. TrustPower purchased an existing hydro scheme on the Arnold River in April
1999, and began investigating the potential to enlarge the generation output of the
river. TrustPower’s original proposal (at that time referred to as the Dobson Scheme)
was abandoned in early 2005 following individual feasibility work, as TrustPower
was not able to gain access to Department of Conservation land affected by the
scheme. A new proposal for the scheme was then developed, to take water from
upstream of the existing dam, transport it along a canal for approximately 12 kms,
then drop the water through a newly-constructed power station to a regulation pond
and then back into the Arnold River.
1.2 TrustPower commissioned environmental and engineering studies from
December 2004 onwards. TrustPower management reported to the Board each
month, noting progress as to technical feasibility, gaining land access, consultation,
and the anticipated time when resource consents would be applied for. In a Board
report dated 31 May 2005, it was noted that engineering and environmental briefs of
work had been issued, landowner agreements were in place to allow access for
survey work and basic geotechnical investigations, and the programme remained on
schedule for presentation of a business case to the Board in August 2005, and for an
RMA consent application to be lodged in the fourth quarter of 2005.
1.3 In a Board report dated 28 July 2005, it was noted that easement option
negotiations and feasibility assessment were ongoing, and that subject to the
outcome of those, it was planned to lodge a resource consent application in
December 2005.
1.4 Further briefs of work, and instructions for peer review of work, were issued
during July and August 2005. An “Arnold River Hydro Scheme Development
Project Status Report September 2005” was presented to the Board meeting on 29
September 2005. The report concluded by expressing management’s opinion that
there was potentially significant long term value in the Arnold scheme, and that land
acquisition and resource consents were critical to any future development. It was
recommended that the Board approve expenditure to acquire the necessary land for
“phase one” of the scheme, and to proceed to lodge a resource consent application
before the end of 2005. The Board considered that “phase one” did not appear to be
economic, and that further work needed to be undertaken on the proposal.
1.5 Draft assessments and feasibility studies were received from consultants
during October 2005. A report to the Board for its October 2005 meeting recorded
that public open days had been held, the resource consent application remained on
schedule for December 2005, negotiations with landowners were ongoing,
preliminary design was complete, and a financial analysis was to be presented to the
Board at its November 2005 meeting.
1.6 An “Arnold Hydro Scheme Development Update Report November 2005”
was presented to the TrustPower Board meeting on 24 November 2005. The report
was accompanied by an “Arnold Options Valuation Analysis” appendix. The report
concluded with a recommendation that the Board approve expenditure for necessary
land purchases and option agreements for the “Base Arnold Scheme” (equivalent to
“phase one” referred to in the September Project Status Report), to lodge a resource
consent application around the end of 2005, to begin long term monitoring
programmes in relation to an extension of the base scheme (equivalent to “phase
two” in the September Project Status Report, and known as the “Taramakau
Diversion”), and to purchase or secure options over land potentially required for the
Taramakau Diversion. The Board approved the recommendations for land
acquisitions and completion of the RMA consent application.
1.7 Briefs of work were sent to consultants in respect of the Taramakau
Diversion in late November 2005. Management reported to the December 2005
Board meeting that work was under way with “optimisation of the scheme with the
Taramakau scheme included”, work with landowners continued, and ecological
studies for the Taramakau Diversion were “scoped and out for pricing”.
1.8 Management reported to the Board’s 27 February and 3 April 2006 meetings
that the Arnold scheme was in the “consenting/engineering design” phase, that land
negotiations were progressing, and the preparation of the AEE was “slightly behind
schedule due to the Taramakau addition”. The application for a resource consent
was lodged on 29 March 2006. The application was in respect of the project without
the Taramakau Diversion. Lodgement of the application was reported to the Board’s
27 April 2006 meeting, when it was also noted that negotiations were continuing
with landowners and recreational users.
1.9 Feasibility studies and assessments in respect of the Taramakau Diversion
were received in the period from May to September 2006. During the same period,
and up to late 2010, TrustPower purchased a number of parcels of land and obtained,
where necessary, consent from the Overseas Investment Office.
1.10 The hearing of the application for resource consent began on 5 November
2007. The consent process was eventually completed on 17 December 2010, with a
final decision of the Environment Court.
1.11 In July 2011, an “Arnold Hydro Business Case” was submitted to the Board.
In the section headed “Summary and Recommendations”, it was noted that
TrustPower could shelve the project for review in the future, complete “phase one”
of an “Early Contractor Involvement (ECI) process” (and at obtaining a “Reference
Target Out-turn Cost”) then re-assess the project, or complete the full ECI process
and proceed to a construction investment decision. Management recommended the
second alternative and this was approved by the Board.
1.12 Management presented an “Arnold Hydro ECI Phase 1 (Reference TOC)
Preliminary Update” to the Board’s November 2011 meeting. A further update was
presented to the Board’s April 2012 meeting, in which management recommended
that the ECI work would be suspended, to be reviewed on a six-monthly basis.
2. Kaiwera Downs wind farm
2.1 The Kaiwera Downs wind farm project is a proposed wind farm
approximately 15 kilometres south-east of Gore, in Southland. It was initially
referred to as the “Wilson/Jackson Wind Farm”.
2.2 A report for the August 2005 meeting of the TrustPower Board recorded that
two landowners had been signed up, and appeared to have good prospects for wind
development. At the September and October 2005 Board meetings the Kaiwera
Downs project was recorded as being at the “feasibility-land access/modelling”
stage. Management reported to the November 2005 Board meeting that it was
analysing the two wind farms, and that wind modelling was in place.
2.3 At the December 2005 Board meeting, management reported that wind
resource analysis had been completed, and that the opportunity was being
progressed. It was noted that a resource consent application could follow shortly
after another application which was expected to be lodged in February 2006.
2.4 At the February 2006 Board meeting, management reported that additional
monitoring masts were to be installed, additional landowners had been identified and
would be signed up, and indications were that a wind farm was viable. Monitoring
continued throughout 2006, and further landowners were signed up. As from the
report for the September 2006 Board meeting, the Kaiwera Downs project was listed
in the “consenting/engineering design” phase of the generation development pipeline
table included in the agenda papers.
2.5 During December 2006 and January 2007, TrustPower engaged consultants
for the Kaiwera Downs project. Management reported to the February 2007 Board
meeting that landowner agreements were in place with seven sets of landowners,
discussions were being held with two remaining owners, transmission land access
agreements were in place, and wind monitoring reports were encouraging. At the
March 2007 Board meeting, management advised that consultants had been engaged
for civil design work for the consenting phase of the project, and a public meeting
would be held in Southland ahead of submitting a resource consent application. A
public open day was held in Gore on 29 March 2007.
2.6 Scoping reports were received from consultants during April 2007. The
development pipeline table included in the agenda papers for the April 2007 Board
meeting recorded that work had started towards an application for resource consents.
2.7 In a media statement issued on 10 May 2007, commenting on TrustPower’s
audited financial results for the year ended 31 March 2007, it was recorded that
TrustPower was investigating the potential for a wind farm of up to 185 MW at
Kaiwera Downs, land access arrangements were nearing completion, and wind
monitoring was being undertaken. It was also recorded that a resource consent
application was expected to be lodged in the last quarter of 2007.
2.8 An internal preliminary assessment of the feasibility of the Kaiwera Downs
projected dated 28 May 2007 noted a potential fatal flaw, relating to the landscape
and visual effects of the proposed wind farm, and that further analysis was required
to clarify whether those effects were likely to constitute a fatal flaw.
2.9 On 27 June 2007, TrustPower issued further briefs of work to consultants, for
preparation of reports to be included in the AEE required for the resource consent
application. The pipeline development table included in the agenda papers for the
August 2007 Board meeting recorded that the AEE was nearing completion, and the
site location was being refined on an ecological, geotechnical, and wind resource
basis.
2.10 Peer reviewers were engaged in respect of the consultants’ AEE assessments
in late October 2007. The resource consent application was made on 5 November
2007. Peer reviews of the AEE assessments were received by TrustPower during
November and December 2007.
2.11 The hearing for the resource consent application began on 31 March 2008.
Consents were granted in a decision given in June 2008. An appeal to the
Environment Court was resolved by a consent order made on 13 May 2009.
2.12 In early 2010, TrustPower received an approach concerning a possible
purchase from TrustPower of two wind farm projects: Kaiwera Downs and
Mahinerangi. Following execution of a confidentiality deed, TrustPower provided
an Information Memorandum concerning both projects. In April 2010, TrustPower
received an offer to purchase the Kaiwera Downs site, including the resource
consent, technical reports and designs, landowner agreements, and any physical
assets related to the project. The offer was subject to due diligence and approval by
the offeror’s Board. Although discussions continued for some time, an offer was not
accepted.
2.13 The Kaiwera Downs project has not been developed further, although
feasibility modelling work has continued, and land option agreements have been
extended.
3. Mahinerangi wind farm
3.1 The Mahinerangi project is a proposed wind farm west of Dunedin. It is
close to two TrustPower hydro schemes, Deep Stream and Waipori. Mahinerangi
was earlier referred to as “Eldorado” or “Waipori Wind”. Mahinerangi was
identified in the generation pipeline table for the September 2005 TrustPower Board
meeting, as being in the “land access / monitoring” phase.
3.2 TrustPower engaged consultants to provide landscape/visual and ecological
(terrestrial, aquatic and avian) assessments for the feasibility study phase, in late
October 2005. Management reported to the TrustPower Board meeting in October
2005 that original impressions of a good wind site had been confirmed, that an
application for resource consent to install a “Met Mast” had been submitted, and that
it was aiming to apply for a resource consent for the Mahinerangi wind farm early in
2006.
3.3 In late November 2005, TrustPower engaged consultants to provide
assessment reports to be included in the AEE for an application for resource consent
for Mahinerangi. Management reported to the November 2005 Board meeting that
landowner agreements were proceeding well, and that environmental and
engineering studies were under way, targeting February/March 2006 for lodging an
application for resource consent. The Board was advised at its January 2006 meeting
that management was still on target to lodge a resource consent application in late
February or early March.
3.4 Management reported to TrustPower’s January 2006 Board meeting that
potential turbine sites had been identified, and option agreements had been signed
with two landowners. Negotiations were continuing with four further landowners,
one of which was the Dunedin City Council. Main concerns with the projected
related to the visual impact, traffic effects during construction, and the impact on a
local lizard population. A resource consent application was expected to be lodged in
early April 2006.
3.5 The report for the 3 April 2006 TrustPower Board meeting recorded that
negotiations with the four landowners were continuing, and that a resource consent
application was expected to be lodged in May 2006. At the Board meeting on 27
April 2006, management reported on requests for expressions of interest from
turbine manufacturers, and public and individual consultations that had been held.
3.6 In its media statement issued on 12 May 2007, on the release of its audited
financial results for the year ended 31 March 2006, TrustPower recorded that it
expected to lodge a resource consent application for the Mahinerangi project “within
the next month”, and that it was likely that the project would be completed in stages.
3.7 Management reported at the June 2006 TrustPower Board meeting that
lodging of the resource consent application had been delayed at the request of the
Dunedin City Council. The application for resource consent was lodged in late June
2006.
3.8 A “Valuation Update Report [Mahinerangi] Wind Investment Opportunity”
was presented to the TrustPower Board’s June 2006 meeting. The report set out the
result of computer modelling of the project costs against various changing
circumstances (including exchange rate movements, local construction costs,
availability of imported equipment, HVDC charges, and the uncertainty of resource
consenting and land access) and projected revenue. The report recommended that
TrustPower complete remaining landowner agreements, secure a resource consent
for a 300MW wind farm, and monitor the site to obtain a comprehensive high quality
data set.
3.9 At the August 2006 Board meeting, management reported that it was giving
consideration to reducing the “consenting window” for the Mahinerangi project to
exclude the Dunedin City Council land. The Chief Executive noted that he would be
meeting with the Council to advise that TrustPower would be proceeding with a
smaller project on privately owned land.
3.10 In early September 2006, TrustPower asked its consultants to revise their
earlier assessment reports to allow for a change to the development envelope, to
allow for a maximum generation capacity of 200MW. A second application for
resource consent for Mahinerangi was lodged in early December 2006. The first
application was formally cancelled in January 2007.
3.11 The hearing of the second resource consent application began on 10 May
2007. A decision to grant the consents was given on 27 September 2007. The
decision was appealed to the Environment Court, which issued an interim decision in
July 2008 and a final decision granting consent on 15 December 2008.
3.12 As noted in respect of the Kaiwera Downs project, TrustPower received an
approach as to a possible purchase of the Mahinerangi project in early 2010. No
offer was made in respect of Mahinerangi.
3.13 In a media statement issued on 5 February 2010 on the release of its third
quarter operating results at 31 December 2009, TrustPower recorded that it was
seeking pricing from wind turbine suppliers for Stage 1 of the Mahinerangi project,
and that that process would assist in determining whether it was economically
feasible to progress the project.
3.14 A business case for Mahinerangi Stage 1 was presented to the TrustPower
Board meeting in April 2010. The Board accepted management’s recommendation
to approve construction of Stage 1, from which electricity was to be supplied to the
local distribution network. Stage 1 was completed in May 2011.
4. Wairau River Hydro
4.1 TrustPower purchased the Branch River Scheme in Marlborough in 1998.
The Branch River is a tributary of the Wairau River. Following the purchase,
TrustPower began investigating the potential for an additional hydro scheme on the
Wairau River.
4.2 Management reported to the TrustPower Board meeting on 31 January 2002
that work had started on a survey for a proposed diversion of water from the river,
and that scoping work for environmental and ecological assessments was under way.
In October 2002, management reported as to two potential Wairau River schemes,
one upstream and one downstream of the existing Branch scheme.
4.3 In February and May 2003, management reported as to negotiations with
landowners for access for investigation and feasibility assessment. In May 2003
management also reported that proposals had been sought from consultants for
environmental assessments of the project. Studies were to commence during May,
with a view to completing an AEE for a resource consent application by March 2004.
It was further reported that the key objective of the study was to quantify the river
flow available for electricity generation, and confirm the economic viability of the
project.
4.4 During the remainder of 2003, TrustPower engaged consultants to prepare
feasibility assessments, including assessments of the possible effects of the project
on the landscape and cultural and archaeological aspects of the Wairau Valley, and to
investigate the impact of increased traffic, noise, and dust in construction.
4.5 Tenders were called for geotechnical and engineering assessments in
September 2003, with a target of lodging a resource consent application by March
2004. The terms of reference for the engineering assessments noted that the key
objective of the assessments was to present a preliminary design for the scheme that
was technically and economically viable and environmentally sustainable.
4.6 In a report for the December 2003 TrustPower Board meeting, management
recorded that draft feasibility reports were being reviewed, final draft environmental
and engineering assessment reports would be released for peer review at the end of
January 2004, and work had started on compiling a summary feasibility report and
AEE report. Management continued to report on progress as to technical and
economic appraisal of the project, and consultation with affected landowners, with a
view to the negotiation of easements.
4.7 In a “Project Status Update” presented to the Board on 29 April 2004, it was
recorded that lodgement of an application for resource consents was subject to
receiving the approval of the Board, and securing access/easements to all land in
question.
4.8 A “Wairau Valley Hydro Scheme Feasibility Report” was presented to the
TrustPower Board at its September 2004 meeting, in respect of a scheme to divert
part of the Wairau River flow into the Branch River scheme, then to convey the
water through interconnecting canals and penstocks to five new power stations
spaced over about 46 km in the Wairau Valley. The project was considered to be a
robust, environmentally, technically, and economically viable proposition. Major
risks that could halt development were considered to be the denial of resource
consent, and denial of access by one or more landowners along the scheme.
4.9 A “Wairau Valley Hydro Scheme Development Evaluation Report” was
presented to the June 2005 TrustPower Board meeting. The report noted that the
scheme layout and project design had been refined since the 2004 feasibility
assessment, to mitigate the impact on affected properties and the environment. It
was also noted that as at the date of the report, TrustPower had agreed access to 74
per cent of the required land. Project risks were listed as being denial of resource
consent, a change in government policy, an increasing imbalance between
construction industry supply and demand, and increasing costs. Management sought
and obtained Board approval to lodge an application for resource consent.
4.10 The application for resource consent was lodged on 14 July 2005.
TrustPower continued to seek to secure land access by land acquisition and easement
agreements, and to engage consultants to peer review assessments and respond to
requests for further information under s 92 of the RMA. The application for
resource consent was heard over the period from June to December 2006. An
interim decision was issued in June 2007, and a final decision on 14 July 2008.
Appeals to the Environment Court were heard over the period from November 2009
to May 2010, and the Court’s final decision granting consent was delivered on 8 June
2011.
4.11 While application for resource consent was progressing through the local
authority and Environment Court, TrustPower continued to seek to secure land
access by acquisition or easement agreements. As at the date of the Environment
Court’s final decision, TrustPower had not been able to secure access agreements
with the owners of 36.7 per cent of the land required for the project. Five
landowners were considered to be unlikely to agree to access.
4.12 In his evidence in this Court Mr Campbell (who has been TrustPower’s
general manager, Generation since April 2011) said that Wairau hydro has not
progressed to second step feasibility. It has unresolved land access issues and until
these issues are resolved, the project is not practicable. He added that under current
market conditions the project is also not likely to be economically viable.