Tropical Storm Irene The Impact on Ulster County and the Phoenicia Bridge Ulster County –New York Presented by Scott Davis, P.E.

Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Tropical   Storm   IreneThe Impact on Ulster County and the Phoenicia BridgeUlster County –New York

Presented by Scott Davis, P.E.

Page 2: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

August 28, 2011

Page 3: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

NYS Region 8‐ Ulster County

Page 4: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -
Page 5: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Ulster County 8‐12 inches of Rain

Page 6: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Burnham Hollow Bridge

Page 7: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Burnham Hollow Bridge Replaced

Page 8: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Dry Brook Bridge

Page 9: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Dry Brook Bridge Replaced

Page 10: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Maben Hollow Bridge

Page 11: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Maben Hollow Road Replaced

Page 12: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Steve Fischer Road Culvert 

Page 13: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Steve Fischer Bridge Replacement

Page 14: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Bridge replaces Culvert

Page 15: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

The Phoenicia Bridge

Page 16: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Original Truss Bridge

Page 17: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

1976 Truss Bridge Removed

Page 18: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

1976‐ Replacement Structure

Page 19: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Existing StructureBuilt in 1976Total Length 255 feet ‐ 3 spansRolled 36 inch deep GirdersReinforced Concrete deck with SIP’s 7 ½” thick34 feet in width with two travel lanesStub abutments on H‐Pile FoundationsPiers are H‐piles with diagonal bracing encased in concretePile foundations are embedded 65 feetSpan 1 replaced in 1995 after flood

Page 20: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

As the flood waters recede

Page 21: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

The Damage

Page 22: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -
Page 23: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

The Evaluation Begins

Page 24: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -
Page 25: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Access was an issue

Page 26: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Anchor Bolts Shear off

Page 27: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

OPTIONS

Replace bridge with new structure

Remove bridge and do not replace

Repair existing bridge

Page 28: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

FINDINGS• Undersized anchor bolts at span 1 sheared  

• Span 1 shifted 18 inches off bearings

• Increased cracking at pier 2 under girder 4

• Guide rail and deck completely removed

• Reinforcement exposed in deck slab

• Bridge joint completely failed

• Diaphragm bolts sheared

• Debris lodged in steel superstructure

• Steel girders out of plane vertical and horizontal from shifting of pedestals

• Bridge does not have adequate hydraulic opening

Page 29: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

ENTER

• Ulster County DPW

• NYCDEP‐ NYC watershed

• NYSDOT

• NYSDEC

• SOB (Save Our Bridge People)

Page 30: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Replacement Option

Page 31: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Crossroads and Rail 

Page 32: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Removal of the Existing Bridgewithout Replacement

• Structure has been in service since 1976

• Removal could cost more than repairs

• Businesses suffering

• Permanent detour around  Main Street

• Hydraulic Opening not an issue

Page 33: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Repair of the Existing Bridge

• Overall Repairs to Bridge where feasible 

• Cost of repairs 

• Repairs could be made by County

• Hydraulic opening could be increased by dredging stream bed to original elevation

• Important Link to the Hamlet would be re‐established for businesses

Page 34: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

It’s official – Bridge to be RepairedPhoenicia's Bridge Street Bridge over the Esopus Creek, knocked out of commission by the Irene floods last summer and thought to be un‐fixable, will be put back in service after all, Ulster County officials say.

A press release issued today by the office of Mike Hein, Ulster County executive:

Phoenicia, NY – County Executive Mike Hein is extremely pleased to announce that a preliminary assessment by the independent engineering firm Peak Engineering indicates that the damage caused to the Bridge Street Bridge in Phoenicia by Hurricane Irene and Tropical Storm Lee is not irreparable as originally thought.  As such, the Ulster County Bridge Crew is expected to be able to provide the necessary repairs in order to reopen this vital link to the Hamlet of Phoenicia.

According to County Executive Hein, “Hurricane Irene was the worst natural disaster in our County’s history, causing over $15 million in damages to County infrastructure, “I fully recognize the importance of this bridge to the business district and the citizens of Phoenicia.  .  Though there is an extensive amount of work to be done on the Bridge Street Bridge, we look forward to celebrating its reopening by July 4th weekend.”

Page 35: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

County Begins work • Bridge to be jacked and slid back into place

• Diaphragms repaired

• Capbeam cracking repaired

• New bearings and anchor bolts to be installed

• New joint system to be installed

• Steel beams to be straightened at connection plates

• New wearing surface over repaired deck

• New guiderail

Page 36: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Jacking operations

Page 37: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Bearings Reset & Joint Replaced

• Insert bearing and Joint details

Page 38: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

The Repairs

Page 39: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

DPW completes work ahead of schedule

Page 40: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

DPW completes work ahead of schedule

Page 41: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Ribbon Cutting

Page 42: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

Bridge is OPEN!

Page 43: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

QUESTION

• Why was this bridge important to the Town of Phoenicia when there was another route into town with less than a mile detour?

• ANSWER: Local businesses in downtown benefitted greatly from the traffic that was generated by the Bridge Street route.

Page 44: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

QUESTION

• What is the minimum diameter anchor bolt NYS requires.

• ANSWER: 1”

Page 45: Tropical Storm Irene - New York State Department of ......Irene and Tropical Storm Lee is not irreparable as originally thought. ... Microsoft PowerPoint - Peak Engineering PLLC -

QUESTION

• How did the concrete deck help to prevent complete collapse?

• ANSWER: The deck wedged itself against the backwall.