20
Trish Mast External Independent Review [email protected] u October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October 9, 2007

Trish Mast External Independent [email protected] October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Embed Size (px)

Citation preview

Page 1: Trish Mast External Independent Reviewpmast@slac.stanford.edu October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Trish Mast

External Independent Review [email protected]

October 9, 2007

Linac Coherent Light Source (LCLS)

The Rebaseline Process

Trish MastOctober 9, 2007

Page 2: Trish Mast External Independent Reviewpmast@slac.stanford.edu October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Trish Mast

External Independent Review [email protected]

October 9, 2007 2

Project Management Controls System (PMCS)

Project Controls Team

PMCS Structure

Rates, Escalation, Burdens

Resource Loaded Schedule

The Rebaseline Process

Page 3: Trish Mast External Independent Reviewpmast@slac.stanford.edu October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Trish Mast

External Independent Review [email protected]

October 9, 2007 3

PMCS Team

The PMCS group is composed of 5 Project Controls/Scheduling analysts

The entire PMCS group is contract labor through Deltek, Inc.

Page 4: Trish Mast External Independent Reviewpmast@slac.stanford.edu October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Trish Mast

External Independent Review [email protected]

October 9, 2007 4

PMCS Team

The PMCS team supports the Project Office and CAMs

Trish Mast: Project Office, Undulator, Commissioning

Jeff Chan: Installation

Manny Abela: Injector, Linac, & E-Beam Systems Controls

Jay Doubrava: Photon SystemsAnita Malahowski: Conventional Facilities

Page 5: Trish Mast External Independent Reviewpmast@slac.stanford.edu October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Trish Mast

External Independent Review [email protected]

October 9, 2007 5

ACCOUNTINGSYSTEMS

Sheet 1 of 1

ActivityID

ActivityDescr iption

Or igDur

Ear lyStar t

Ear lyFinish

1 LCLS PROJECT - PED & CONSTRUCTION1.04 UNDULATOR SYSTEM1.04.05 Diagnostics

1.04.05.09 Radiation Detection Monitor (RDM)UN509_0010 Specification and Requirements - RDM 10 08/16/06 08/29/06

UN509_0090 Preliminary Design - RDM 25 08/30/06 10/04/06

UN509_0100 Design Review - RDM 5 10/05/06 10/11/06

UN509_0110 Final Design - RDM 20 10/12/06 11/08/06

UN509_0120 Design Complete - RDM 0 11/08/06

UN509_0130 Prepare B id of RDM Package 10 11/09/06 11/22/06

UN509_0240 Develop Installation Plan - RDM 15 11/09/06 12/01/06

UN509_0140 Bid Process - RDM 30 11/27/06 01/16/07

UN509_0250 Review installation P lan - RDM 5 12/04/06 12/08/06

UN509_0141 Evaluate B id - RDM 3 01/17/07 01/19/07

UN509_0150 AWARD: RDM Package (1) 5 01/22/07 01/26/07

UN509_0155 AWARD: RDM Package (1) Sppt 5 01/22/07 01/26/07

UN509_0160 AWARD: of RDM Complete 0 01/26/07

UN509_0170 Receive - RDM (1) 30 01/29/07 03/09/07

UN509_0180 QA - RDM 10 03/12/07 03/23/07

UN509_0190 Approve - RDM 3 03/26/07 03/28/07

UN509_0200 Pack RDM for Shipping 10 03/29/07 04/11/07

UN509_0210 Write Shipping Paper Work - RDM 5 04/12/07 04/18/07

UN509_0230 Transmit Engineering Data to S lac - RDM 5 04/12/07 04/18/07

UN509_0232 RFI: Radiation Detection Monitor 0 04/18/07

UN509_0220 Ship RDM to SLAC 8 04/19/07 04/30/07

FY06 FY07AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPOCT

Specification and Requirements - RDM

Preliminary Design - RDM

Design Review - RDM

Final Design - RDM

Design Complete - RDM

Prepare B id of RDM Package

Develop Installation Plan - RDM

Bid Process - RDM

Review installation P lan - RDM

Evaluate B id - RDM

AWARD: RDM Package (1)

AWARD: RDM Package (1) Sppt

AWARD: of RDM Complete

Receive - RDM (1)

QA - RDM

Approve - RDM

Pack RDM for Shipping

Write Shipping Paper Work - RDM

Transmit Engineering Data to S lac - RDM

RFI: Radiation Detection Monitor

Ship RDM to SLAC

Re s o u rc e /Co s t Pro f i l e L e g e n d

Pla n n e d v a l u e c u rv e

Ea rn e d v a l u e c u rv e

Cu rre n t e s t ima te c u rv e

To ta l e a rl y c o s t p e r Mo n th (Cu rre n t Es t ima te )

To ta l o f Al l Re s o u rc e s De ta i l s c a l e (l e ft): X 1 0 0 0 0

Cu mu la t i v e s c a le (ri g h t): X 1 0 0 0 0

AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPOCTFY06 FY07

2

4

6

8

1 0

1 2

1 4

1 6

4

8

1 2

1 6

2 0

2 4

2 8

3 2 x 1 0 0 0 0 x 1 0 0 0 0

Sheet 1 of 1

Sheet 1 of 1

ActivityID

ActivityDescr iption

Or igDur

Ear lyStar t

Ear lyFinish

1 LCLS PROJECT - PED & CONSTRUCTION1.04 UNDULATOR SYSTEM1.04.05 Diagnostics

1.04.05.09 Radiation Detection Monitor (RDM)UN509_0010 Specification and Requirements - RDM 10 08/16/06 08/29/06

UN509_0090 Preliminary Design - RDM 25 08/30/06 10/04/06

UN509_0100 Design Review - RDM 5 10/05/06 10/11/06

UN509_0110 Final Design - RDM 20 10/12/06 11/08/06

UN509_0120 Design Complete - RDM 0 11/08/06

UN509_0130 Prepare B id of RDM Package 10 11/09/06 11/22/06

UN509_0240 Develop Installation Plan - RDM 15 11/09/06 12/01/06

UN509_0140 Bid Process - RDM 30 11/27/06 01/16/07

UN509_0250 Review installation P lan - RDM 5 12/04/06 12/08/06

UN509_0141 Evaluate B id - RDM 3 01/17/07 01/19/07

UN509_0150 AWARD: RDM Package (1) 5 01/22/07 01/26/07

UN509_0155 AWARD: RDM Package (1) Sppt 5 01/22/07 01/26/07

UN509_0160 AWARD: of RDM Complete 0 01/26/07

UN509_0170 Receive - RDM (1) 30 01/29/07 03/09/07

UN509_0180 QA - RDM 10 03/12/07 03/23/07

UN509_0190 Approve - RDM 3 03/26/07 03/28/07

UN509_0200 Pack RDM for Shipping 10 03/29/07 04/11/07

UN509_0210 Write Shipping Paper Work - RDM 5 04/12/07 04/18/07

UN509_0230 Transmit Engineering Data to S lac - RDM 5 04/12/07 04/18/07

UN509_0232 RFI: Radiation Detection Monitor 0 04/18/07

UN509_0220 Ship RDM to SLAC 8 04/19/07 04/30/07

FY06 FY07AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPOCT

Specification and Requirements - RDM

Preliminary Design - RDM

Design Review - RDM

Final Design - RDM

Design Complete - RDM

Prepare B id of RDM Package

Develop Installation Plan - RDM

Bid Process - RDM

Review installation P lan - RDM

Evaluate B id - RDM

AWARD: RDM Package (1)

AWARD: RDM Package (1) Sppt

AWARD: of RDM Complete

Receive - RDM (1)

QA - RDM

Approve - RDM

Pack RDM for Shipping

Write Shipping Paper Work - RDM

Transmit Engineering Data to S lac - RDM

RFI: Radiation Detection Monitor

Ship RDM to SLAC

Re s o u rc e /Co s t Pro f i l e L e g e n d

Pla n n e d v a l u e c u rv e

Ea rn e d v a l u e c u rv e

Cu rre n t e s t ima te c u rv e

To ta l e a rl y c o s t p e r Mo n th (Cu rre n t Es t ima te )

To ta l o f Al l Re s o u rc e s De ta i l s c a l e (l e ft): X 1 0 0 0 0

Cu mu la t i v e s c a le (ri g h t): X 1 0 0 0 0

AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPOCTFY06 FY07

2

4

6

8

1 0

1 2

1 4

1 6

4

8

1 2

1 6

2 0

2 4

2 8

3 2 x 1 0 0 0 0 x 1 0 0 0 0

Sheet 1 of 1

COST ESTIMATE

CHANGE CONTROL

PMCS UTILITY

Sheet 1 of 1

Activity

ID

Activity

Descr iption

Or ig

Dur

E ar ly

S tar t

E ar ly

Finish

1 LCLS PROJECT - PED & CONSTRUCTION1.04 UNDULATOR SYSTEM1.04.05 Diagnostics

1.04.05.09 Radiation Detection Monitor (RDM)UN509_0010 S pecification and Requirements - RDM 10 08/16/06 08/29/06

UN509_0090 P reliminary Design - RDM 25 08/30/06 10/04/06

UN509_0100 Design Review - RDM 5 10/05/06 10/11/06

UN509_0110 Final Design - RDM 20 10/12/06 11/08/06

UN509_0120 Design Complete - RDM 0 11/08/06

UN509_0130 P repare B id of RDM P ackage 10 11/09/06 11/22/06

UN509_0240 Develop Installation P lan - RDM 15 11/09/06 12/01/06

UN509_0140 B id P rocess - RDM 30 11/27/06 01/16/07

UN509_0250 Review installation P lan - RDM 5 12/04/06 12/08/06

UN509_0141 E valuate B id - RDM 3 01/17/07 01/19/07

UN509_0150 A W A RD: RDM P ackage (1) 5 01/22/07 01/26/07

UN509_0155 A W A RD: RDM P ackage (1) S ppt 5 01/22/07 01/26/07

UN509_0160 A W A RD: of RDM Complete 0 01/26/07

UN509_0170 Receive - RDM (1) 30 01/29/07 03/09/07

UN509_0180 QA - RDM 10 03/12/07 03/23/07

UN509_0190 A pprove - RDM 3 03/26/07 03/28/07

UN509_0200 P ack RDM for S hipping 10 03/29/07 04/11/07

UN509_0210 W rite S hipping P aper W ork - RDM 5 04/12/07 04/18/07

UN509_0230 Transmit E ngineering Data to S lac - RDM 5 04/12/07 04/18/07

UN509_0232 RFI: Radiation Detection Monitor 0 04/18/07

UN509_0220 S hip RDM to S LA C 8 04/19/07 04/30/07

FY 06 FY 07AUG S E P OCT NOV DE C JAN FE B MAR AP R MAY JUN JUL AUG S E POCT

S pecification and Requirements - RDM

P reliminary Design - RDM

Design Review - RDM

Final Design - RDM

Design Complete - RDM

P repare B id of RDM P ackage

Develop Installation P lan - RDM

B id P rocess - RDM

Review installation P lan - RDM

E valuate B id - RDM

A W A RD: RDM P ackage (1)

A W A RD: RDM P ackage (1) S ppt

A W A RD: of RDM Complete

Receive - RDM (1)

QA - RDM

A pprove - RDM

P ack RDM for S hipping

W rite S hipping P aper W ork - RDM

Transmit E ngineering Data to S lac - RDM

RFI: Radiation Detection Monitor

S hip RDM to S LA C

Res ourc e/Cos t Profi le Legend

Planned v alue c urv e

Earned v alue c urv e

Current es timate c urv e

Total early c os t per Month (Current Es timate)

Total of Al l Res ourc es Detai l s c ale (le ft): X 10000

Cumulativ e s c ale (right): X 10000

AUG S E P OCT NOV DE C JAN FE B MAR AP R MAY JUN JUL AUG S E POCTFY 06 FY 07

2

4

6

8

1 0

1 2

1 4

1 6

4

8

1 2

1 6

2 0

2 4

2 8

3 2 x 1 0 0 0 0 x 1 0 0 0 0

Sheet 1 of 1

Sheet 1 of 1

ActivityID

ActivityDescr iption

OrigDur

Ear lyStar t

Ear lyFinish

1 LCLS PROJECT - PED & CONSTRUCTION1.04 UNDULATOR SYSTEM

1.04.05 Diagnostics1.04.05.09 Rad iation Detection Monitor (RDM)UN509_0010 Specification and Requirements - RDM 10 08/16/06 08/29/06

UN509_0090 Preliminary Design - RDM 25 08/30/06 10/04/06

UN509_0100 Design Review - RDM 5 10/05/06 10/11/06

UN509_0110 Final Design - RDM 20 10/12/06 11/08/06

UN509_0120 Design Complete - RDM 0 11/08/06

UN509_0130 Prepare Bid of RDM Package 10 11/09/06 11/22/06

UN509_0240 Develop Installation Plan - RDM 15 11/09/06 12/01/06

UN509_0140 Bid Process - RDM 30 11/27/06 01/16/07

UN509_0250 Review installation Plan - RDM 5 12/04/06 12/08/06

UN509_0141 Evaluate Bid - RDM 3 01/17/07 01/19/07

UN509_0150 AWARD: RDM Package (1) 5 01/22/07 01/26/07

UN509_0155 AWARD: RDM Package (1) Sppt 5 01/22/07 01/26/07

UN509_0160 AWARD: of RDM Complete 0 01/26/07

UN509_0170 Receive - RDM (1) 30 01/29/07 03/09/07

UN509_0180 QA - RDM 10 03/12/07 03/23/07

UN509_0190 Approve - RDM 3 03/26/07 03/28/07

UN509_0200 Pack RDM for Shipping 10 03/29/07 04/11/07

UN509_0210 Write Shipping Paper Work - RDM 5 04/12/07 04/18/07

UN509_0230 Transmit Engineering Data to Slac - RDM 5 04/12/07 04/18/07

UN509_0232 RFI: Radiation Detection Monitor 0 04/18/07

UN509_0220 Ship RDM to SLAC 8 04/19/07 04/30/07

FY06 FY07AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPOCT

Specification and Requirements - RDM

Preliminary Design - RDM

Design Review - RDM

Final Design - RDM

Design Complete - RDM

Prepare Bid of RDM Package

Develop Installation Plan - RDM

Bid Process - RDM

Review installation Plan - RDM

Evaluate Bid - RDM

AWARD: RDM Package (1)

AWARD: RDM Package (1) Sppt

AWARD: of RDM Complete

Receive - RDM (1)

QA - RDM

Approve - RDM

Pack RDM for Shipping

Write Shipping Paper Work - RDM

Transmit Engineering Data to Slac - RDM

RFI: Radiation Detection Monitor

Ship RDM to SLAC

Res ourc e /Cos t Pro fi l e Legend

Planned v a lue c urv e

Earned v a lue c urv e

Curren t es timate c urv e

Tota l earl y c os t per Month (Curren t Es timate)

To ta l o f Al l Res ourc es Deta i l s c a le (le ft): X 10000

Cumula tiv e s c a le (righ t): X 10000

AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPOCTFY06 FY07

2

4

6

8

1 0

1 2

1 4

1 6

4

8

1 2

1 6

2 0

2 4

2 8

3 2 x 1 0 0 0 0 x 1 0 0 0 0

Sheet 1 of 1

PRIMAVERA SCHEDULES PMB(COBRA)

MONTHLY STATUS MONTHLY REPORT

PMCS System Architecture

Page 6: Trish Mast External Independent Reviewpmast@slac.stanford.edu October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Trish Mast

External Independent Review [email protected]

October 9, 2007 6

Rates, Escalation, Burdens

Rates, Escalation and Burdens are reviewed regularly and updated as needed to provide the most accurate cost baseline.Have defined SLAC, ANL, and LLNL rate structures.Buildup of fully burdened rate is performed in Cobra

Overhead: OPC Labor @ 40%Overhead: TEC Non-Labor @ 4.32%, OPC Non-Labor @ 5.04%Escalation: SLAC/LLNL Labor rates @ 4.0%/YearEscalation: ANL Labor rates @ 4.5%/YearEscalation: M&S Rates use DOE guidelines

Basis for Escalation Rates consist of:Laboratory published escalation ratesDOE Escalation guidelines

P3 provides the budgeted quantities for each planned resource to Cobra.

Page 7: Trish Mast External Independent Reviewpmast@slac.stanford.edu October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Trish Mast

External Independent Review [email protected]

October 9, 2007 7

Resource Breakdown Structure

12

3

4

5

1

2

3

4

5

123

RBS - BE

WBS

FUND

Page 8: Trish Mast External Independent Reviewpmast@slac.stanford.edu October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Trish Mast

External Independent Review [email protected]

October 9, 2007 8

Resource Loaded Schedules

Sheet 1 of 1

ActivityID

ActivityDescription

OrigDur

EarlyStart

EarlyFinish

1 LCLS PROJECT - PED & CONSTRUCTION1.04 UNDULATOR SYSTEM

1.04.05 Diagnostics1.04.05.09 Radiation Detection Monitor (RDM)UN509_0010 Specification and Requirements - RDM 1008/16/06 08/29/06

UN509_0090 Preliminary Design - RDM 2508/30/06 10/04/06

UN509_0100 Design Review - RDM 5 10/05/06 10/11/06

UN509_0110 Final Design - RDM 2010/12/06 11/08/06

UN509_0120 Design Complete - RDM 0 11/08/06

UN509_0130 Prepare Bid of RDM Package 1011/09/06 11/22/06

UN509_0240 Develop Installation Plan - RDM 1511/09/06 12/01/06

UN509_0140 Bid Process - RDM 3011/27/06 01/16/07

UN509_0250 Review installation Plan - RDM 5 12/04/06 12/08/06

UN509_0141 Evaluate Bid - RDM 3 01/17/07 01/19/07

UN509_0150 AWARD: RDM Package (1) 5 01/22/07 01/26/07

UN509_0155 AWARD: RDM Package (1) Sppt 5 01/22/07 01/26/07

UN509_0160 AWARD: of RDM Complete 0 01/26/07

UN509_0170 Receive - RDM (1) 3001/29/07 03/09/07

UN509_0180 QA - RDM 1003/12/07 03/23/07

UN509_0190 Approve - RDM 3 03/26/07 03/28/07

UN509_0200 Pack RDM for Shipping 1003/29/07 04/11/07

UN509_0210 Write Shipping Paper Work - RDM 5 04/12/07 04/18/07

UN509_0230 Transmit Engineering Data to Slac - RDM 5 04/12/07 04/18/07

UN509_0232 RFI: Radiation Detection Monitor 0 04/18/07

UN509_0220 Ship RDM to SLAC 8 04/19/07 04/30/07

FY06 FY07AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPOCT

Specification and Requirements - RDM

Preliminary Design - RDM

Design Review - RDM

Final Design - RDM

Design Complete - RDM

Prepare Bid of RDM Package

Develop Installation Plan - RDM

Bid Process - RDM

Review installation Plan - RDM

Evaluate Bid - RDM

AWARD: RDM Package (1)

AWARD: RDM Package (1) Sppt

AWARD: of RDM Complete

Receive - RDM (1)

QA - RDM

Approve - RDM

Pack RDM for Shipping

Write Shipping Paper Work - RDM

Transmit Engineering Data to Slac - RDM

RFI: Radiation Detection Monitor

Ship RDM to SLAC

Resource/Cost Profile Legend

Planned value curve

Earned value curve

Current estimate curve

Total early cost per Month (Current Estimate)

Total of All Resources Detail scale (left): X 10000

Cumulative scale (right): X 10000

AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPOCTFY06 FY07

2

4

6

8

10

12

14

16

4

8

12

16

20

24

28

32 x 10000 x 10000

Sheet 1 of 1

Page 9: Trish Mast External Independent Reviewpmast@slac.stanford.edu October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Trish Mast

External Independent Review [email protected]

October 9, 2007 9

Configuration Controlled Milestones

Defined Level 1, 2, 3 Milestones Level 1 controlled by DOE Acquisition Executive

Level 2 controlled by DOE Federal Project Director

Level 3 controlled by LCLS Project Director

Level 1-3 Milestones are under formal configuration control.

Page 10: Trish Mast External Independent Reviewpmast@slac.stanford.edu October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Trish Mast

External Independent Review [email protected]

October 9, 2007 10

Integrated SchedulesUndulator Hall Construction

Und/QD/Vac/BPM Prealign

Undulator Installation

Quadrupoles

Vacuum Chamber

Undulator Hall B.O.

RFBPMs

Cherenkov Detector

Beam Finder Wire

Stages & Stands

Support/Mover

MMF Construction

MMF B.O.

Undulator Test Stands

Undulator Handling Equipment

Fiducialization System

Undulator Measurement and Fiducialization

Undulator Magnet Assembly

1st Light

Level 3 Milestones

Level 4 Milestones

Page 11: Trish Mast External Independent Reviewpmast@slac.stanford.edu October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Trish Mast

External Independent Review [email protected]

October 9, 2007 11

Critical Path Analysis

Top three critical paths were run and analyzed

All constraints removed from database exceptFunding constraints

Shutdown constraints

Top three paths to CD4 were calculated

Page 12: Trish Mast External Independent Reviewpmast@slac.stanford.edu October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Trish Mast

External Independent Review [email protected]

October 9, 2007 12

The Rebaseline Process

Rebaseline effort broken into 3 Steps: Step 1: Update database to include actuals thru June 2007

Step 2: Update the Database with all CR related effects

Step 3: Perform an comprehensive bottoms up Estimate to Complete and update rates

Page 13: Trish Mast External Independent Reviewpmast@slac.stanford.edu October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Trish Mast

External Independent Review [email protected]

October 9, 2007 13

Backup Slides

(Note: These backup slides are provided to demonstrate samples of output and reports. The data

contained in these samples does not necessarily represent the current PMB)

Page 14: Trish Mast External Independent Reviewpmast@slac.stanford.edu October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Trish Mast

External Independent Review [email protected]

October 9, 2007 14

Detailed Cost Estimate Report (DCE)

Page 15: Trish Mast External Independent Reviewpmast@slac.stanford.edu October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Trish Mast

External Independent Review [email protected]

October 9, 2007 15

CPR Drilldown (Level 2)

Page 16: Trish Mast External Independent Reviewpmast@slac.stanford.edu October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Trish Mast

External Independent Review [email protected]

October 9, 2007 16

BCWS, BCWP,ACWP Report (SPA)

Page 17: Trish Mast External Independent Reviewpmast@slac.stanford.edu October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Trish Mast

External Independent Review [email protected]

October 9, 2007 17

Obligation Report (OSCUM)

Page 18: Trish Mast External Independent Reviewpmast@slac.stanford.edu October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Trish Mast

External Independent Review [email protected]

October 9, 2007 18

Milestone Dictionary

Page 19: Trish Mast External Independent Reviewpmast@slac.stanford.edu October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Trish Mast

External Independent Review [email protected]

October 9, 2007 19

WBS Dictionary

Page 20: Trish Mast External Independent Reviewpmast@slac.stanford.edu October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October

Trish Mast

External Independent Review [email protected]

October 9, 2007 20

Responsibility Assignment Matrix (RAM)