TRIO-CINEMA 1 UCB, 8/10/2010
CINEMA Project UpdateThomas Immel
UCB/SSLSpace Sciences Laboratory
University of California, Berkeley
TRIO-CINEMA 2 UCB, 8/10/2010
Summer 2010 Highlights
Core Flight Software CompleteMechanical Design Approaching CompletionAvionics Stack Moved for Harness @ MICD v14Solar Panel Design and Test CompleteAttitude Control System Demonstrated w/SimulinkPower Systems Tested and CharacterizedIIF Specification Complete – IIF Spec v2.2IIB Layout Complete – Ready for FabricationMagnetometer ICD and Tech Report Revised
TRIO-CINEMA 3 UCB, 8/10/2010
S-Band Radio
S-Band Radio:Emheiser TransmitterEDTC-01E1A102-C0
Ready to order once pigtail length is determined (a current Mech and EE task) Max length 10.5”, current estimate 9.4”.
RG316 Coaxial to be used for this and UHF Helium Receiver.
TRIO-CINEMA 4 UCB, 8/10/2010
Avionics Stack from Bottom Up
Flight Processor not ordered. 2nd dev unit purchased at SSL, 3 total dev units for UCB CINEMA.Flight Clyde EPS thoroughly tested by Nestor Vargas and FSW team.
•Charge current calibration•Max. Power Point Tracking•Battery discharge power cutoff : Found to be instantaneous
Flight Battery delivered, cold stored.Flight UHF Helium Radio Receiver powered up. Testing procedures under development, but help is needed here.
TRIO-CINEMA 5 UCB, 8/10/2010
Instrument Interface Board v2.0
Final revision of IIB from John Diaz replaces Nanonics 65 pin connector with 2 (2x17) floppy drive connectors. This has implications for harnessing that are not completely appreciated at the moment, but it is a much easier connector to work with. We’re ready to send this board out for quotes. Parts list needs to be checked twice. Layout done in
DipTrace
TRIO-CINEMA 6 UCB, 8/10/2010
KHU has also developed a test IIB board. Layout is quite different, but based upon the same schematic and so should be electrically compatible with UPR IIB. Incompatible with MICD due to large test connector.
Layout done in Allegro
Instrument Interface Board v2.0
TRIO-CINEMA 7 UCB, 8/10/2010
MAGIC
MAGIC Experiment Test Unit (ETU) delivery end of August. Test board w/PC104 connector and single-axis magnetometer. Other axes provided with test connections for test voltages.
Delivery in 4-6 weeks. Preparation for its arrival should include:1)Initial FPGA programming2) Test harness preparation3) Development of testing procedures, CPDs
TRIO-CINEMA 8 UCB, 8/10/2010
CHANGES
1) FPGA MAG interface simplified. dsPIC Flight Software will command all reads of MAGIC ADC.
2) Change to an application-specific integrated circuit (ASIC) necessitates major changes in STEIN electronics. Until that is clarified, STEIN FPGA and electronics work is halted.
3) Development of alternative to GSEOS is now supported at UCB. Presentation and demonstration on Thursday.
TRIO-CINEMA 9 UCB, 8/10/2010
What are our top priorities?
Develop UHF radio test procedures.Develop IIB/FPGA code.Produce the first set of IIBs.Produce 10 flight solar panels.Develop the Ground Support Software and Equipment.Prepare to receive the MAGIC ETU.Determine performance of sun sensors.
TRIO-CINEMA 10 UCB, 8/10/2010
What are our top risks?
Known Unknowns:Fail to develop Ground Support SoftwareUnexpected glitches with ADC reading of MAGICTest of S-Band transmitter likely lengthy and difficult.Difficulty with ACSHarness innerconnect to SBAND, HELIUM, IIB, MAGIC, HVPS, STEIN will be difficult, same with all solar panels and radio connections.
Unknown Unknowns:Communication with eventual STEIN via new GSE (as if GSEOS would be easier)?Performance of IIB?What will break when we shake?
TRIO-CINEMA 11 UCB, 8/10/2010
What are our top strengths?
TRIO-CINEMA 12 UCB, 8/10/2010