TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDY 2013 CONGESTION MANAGEMENT PROCESS

TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

TRI‐CITYMETROPOLITANAREATRANSPORTATIONSTUDY

2013CONGESTIONMANAGEMENTPROCESS

Page 2: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council
Page 3: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

TRI‐CITYMETROPOLITANAREATRANSPORTATIONSTUDY

The TRI‐CITYMETROPOLITAN AREA TRANSPORTATION STUDY (Tri‐MATS) is theMetropolitanPlanningOrganization(MPO)designatedbytheGovernortodevelopandimplementacoordinated,comprehensive, and continuing planning process that addresses issues related to thetransportationsystemsofregionalsignificanceintheurbanarea.Tri‐MATSisgovernedbyaBoardcomprised of elected officials from the jurisdictions within the Kennewick‐sco‐Richlandmetropolitan area which are responsible for building and operating our transportationinfrastructure.ThisCongestionManagementProcesshasbeen financed inpart throughgrants from theFederalHighwayAdministration,FederalTransitAdministration,andtheWashingtonStateDepartmentofTransportation.Tri‐MATSandtheauthorsaresolelyresponsibleforthematerialcontainedherein.

ADOPTED

December20th,2013BFCOGherebygivespublicnoticethatitistheagencypolicytoassurefullcompliancewithTitleVIofthe1964CivilRightsAct,theCivilRightsRestorationActof1987,ExecutiveOrder12898onEnvironmentalJustice,andrelatedstatutesandregulationsinallprograms

andactivities.

Page 4: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013CongestionManagementProcessAdvisoryCommittee

JohnDeskins CityofKennewickMikePawlak CityofPascoJeffPeters CityofRichlandRoscoeSlade CityofWestRichlandPaulGonseth WashingtonStateDepartmentofTransportationTonyKalmbach BenFranklinTransitCarolMoser CommunityHealthAllianceBrianMalley Benton‐FranklinCouncilofGovernmentsCarlBerkowitz 3‐RiversBicycleClub

Page 5: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

TableofContentsINTRODUCTIONANDBACKGROUND..............................................................................................................................1

Introduction...........................................................................................................................................................................1

Purpose....................................................................................................................................................................................1

TheCongestionManagementProcess.........................................................................................................................1

DiscussiononCongestion................................................................................................................................................2

2011‐2032MetropolitanTransportationPlan.......................................................................................................3

COMPONENTSOFACMP......................................................................................................................................................3

CMPStudyArea....................................................................................................................................................................3

CMPCorridors........................................................................................................................................................................5

PerformanceMeasures......................................................................................................................................................5

DataFramework...................................................................................................................................................................7

PeriodicReview.....................................................................................................................................................................7

CMPDATASOURCES...............................................................................................................................................................7

TravelTimeProgram..........................................................................................................................................................8

TrafficCounts.........................................................................................................................................................................8

TransitSystemData...........................................................................................................................................................9

MetropolitanAreaCollisionTrends..........................................................................................................................10

APPENDICES............................................................................................................................................................................11

AppendixA–FederalRegulationsAddressingtheCMP...................................................................................13

AppendixB–2011‐2032MetropolitanTransportationPlan.........................................................................19

AppendixC–CMPCongestedCorridorTrackingMatrix.................................................................................41

AppendixD–CongestedCorridorData...................................................................................................................45

AppendixE–TravelTimeDataCollection.............................................................................................................97

AppendixF–TransitSystemData..........................................................................................................................101

AppendixG–TransportationSystemComponentsintheCMPStudyArea..........................................107

AppendixH–PublicComment.................................................................................................................................113

Page 6: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

TABLES

Table1:CMPCongestedCorridors..............................................................................................................................5

Table2:FrequencyofCongestedCorridorTrafficCounts..................................................................................8

Table3:MetropolitanAreaCollisionOutcomes2002‐2010...........................................................................10

Table4:BFTVanpoolOperationsData–1995‐2010......................................................................................103

Table5:ParkandRideLotsinBentonandFranklinCounties....................................................................105

MAPSANDFIGURES

Map1:CMPStudyArea......................................................................................................................................................4

Map2:CMPCongestedCorridors.................................................................................................................................6

Figure1:MetropolitanAreaCollisions2002‐2010.............................................................................................10

Figure2:BenFranklinTransitVanpoolRidership1990‐2010...................................................................103

Figure3:BenFranklinTransitVanpoolMiles1990‐2010............................................................................104

Map3:ParkandRideLotsinBentonandFranklinCounties.......................................................................106

Map4:CMPStudyAreaandthe2013FederalFunctionalClassSystem...............................................109

Map5:CMPStudyAreaandthe2011WSDOTFreightandGoodsSystem...........................................110

Map6:CMPStudyAreaandthe2013BFTFixedRouteBusRoutes,.......................................................111

Map7:CMPStudyAreaandthe2009BFCGBikeMapBikeRoutes.........................................................112

Page 7: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page1

TRI‐CITYMETROPOLITANAREATRANSPORTATIONSTUDYCongestionManagementProcess

INTRODUCTIONANDBACKGROUNDIntroductionAstheTri‐Citymetropolitanareacontinuestogrow,trafficcongestionwillneedtobeevaluatedandappropriatelymanaged.Thepurposeofthisdocument,theTri‐CitiesMetropolitanAreaCongestionManagementProcess,istodevelopstrategiesandimplementacongestionmanagementprocess(CMP)ensuringthatthemetropolitanareacontinuestogetthemaximumbenefitfrombothourexistingandnewtransportationsystem.TheTri‐CitiesMetropolitanAreabecameaTransportationManagementArea(TMA)asaresultofthe2010census,whichdeterminedtheKennewick‐Pasco‐RichlandUrbanAreapopulationhadsurpassedapopulationof200,000.ThatpopulationthresholdtriggerstheTMAdesignationunderFederallaw.AsaTMA,BFCGisrequiredtodevelopaCongestionManagementProcess.AdeadlineofJanuary18,2014isestablishedinlawforsubmittalofourinitialCMPtotheFederalHighwayAdministration(FHWA)andtheFederalTransitAdministration(FTA).ThisisaDRAFTRegionalCMPfortheTri‐CityMetropolitanAreaTransportationStudy(Tri‐MATS).ThisistheinitialCMPfortheTri‐MATSarea.TheCMPisdevelopedinordertofacilitatethemonitoring,analysisandreductionofcongestioninthemajorregionaltravelcorridors.Itwillbemodifiedovertime,withnewelementsphasedinasadditionalinfrastructurefordatacollection,andtheorganizationalstructuretoanalyzeanddisseminatethedataisdesignedandimplemented.ThisdocumentdescribestheelementsoftheTri‐CitiesCMP–whatwillevolveintoacomprehensivesetofpolicies,performancemeasures,ongoingactivitiesandrecommendedfutureactionsdesignedtomanagetrafficcongestionandtomaintainhighlevelsoftransportationserviceintheTri‐CitiesMetropolitanArea.PurposeThepurposeoftheCMPistoidentifycongestedareasandbringanobjectivebasistodevelopingthosestrategiesthatwillallowtheregiontoachievethegreatestbenefitforitsinvestment.AccordingtoTitle23Part450CSection450.320,aCMPmust: Measuremulti‐modaltransportationsystemperformance Identifythecausesofcongestion Assessalternativeactions Implementcost‐effectiveactions;and Evaluatetheeffectivenessofimplementedactions.

Toaccomplishtheseobjectives,theCMPfeaturesasignificantcomponentofdatacollectionandmonitoringofactivities,setsforwardperformancemeasuresorcriteriaforidentifyingwhenactionisneeded,andidentifyingthemanagementstrategiesthatwillbemosteffective.TheCongestionManagementProcessCongestionManagementistheapplicationofstrategiestoimprovetransportationsystemperformanceandreliabilitybyreducingtheadverseimpactsofcongestiononthemovementofpeopleandgoods.ACongestionManagementProcessisaregionally‐acceptedapproachformanagingcongestionthatprovidesaccurate,timelyinformationontransportationsystem

Page 8: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page2 Benton‐FranklinCouncilofGovernments

performanceandassessesalternativestrategiesforcongestionmanagementthatmeetstateandlocalneeds.ThisistheinitialCongestionManagementProcessforourmetropolitanarea,andassuchisverymuchabroadpresentationofrelevantconcepts.AstheRegionalCMPisrefinedinfutureupdates,itwillprovidemoredetailedpresentationsoftheoperationalcharacteristicsofthemajortravelcorridorsintheregionandserveasabasisfortheselectionofimprovementsdesignedtoeffectivelyaddresstheidentifiedproblems.TheRegionalCMPestablishedinthisProcessaddressestwoissues:first,itmeetsthefederalrequirementsthattheareaimplementaCMP;andsecond,itlaysthefoundationfortheevolvingsystematicdatacollection,analysis,andinterpretationactivitiesthatcomprisethebackboneoftheRegionalCMP.DevelopmentoftheCMPisongoing,andthedocumentitselfwillbeupdatedataminimumofeverytwoyears.DiscussiononCongestionCongestioncanbedefinedtooasslowordifficultmovementbypeopleorvehiclesasaresultofovercrowdingbyeithervehiclesorpeoplerelativetothecarryingcapacityofthefacility.Congestioncanbecharacterizedbyfourqualitiesordimensions:intensity,duration,extentandvariability.Thesefourdimensionsallowforabetterunderstandingofhowtheroadsarebeingimpactedbythecongestion.Intensitycanbethoughtofasthenumberofpeopleorvehiclesthatarepartofthecongestion.Durationisthetemporaldimension,measuringhowlongthecongestioneventlasts.Theamountofroadsorgeographicareaincludedinthecongestioneventistheextent.Variabilityisthemeasureforhowfrequentlycongestiontakesplaceonthatroadwaysegment.Therearetwobroadcategoriesofcongestion:recurringornonrecurringcongestion.Recurringcongestioncanbeattributabletothephysicalqualitiesofthefacilities:changesinthenumberoflanes,geometricconstraints,signalsthatarenotcoordinated,andpooraccessmanagementtotheadjacentlanduses.Nonrecurringcongestionisduetoeventsthathappenrandomlyorinfrequently,includingweatherrelatedissues,incidentsandspecialevents.Nonrecurringcongestionisdifficult,butnotimpossible,toplanforandtodeviseeffectivemitigationstrategies.Oftenthestrategiesinvolvequicklyremovingthecauseofcongestionorprovidinganalternateroute.Forthemostpart,nonrecurrentcongestioncannotbeaddressedinasystematicway.Trafficincidentscanbemitigatedtoadegreebyprojectstoaddresshowtrafficflowsalongacorridorandatintersections,butthehumanoperatingthevehicleisstillthemaincontributingfactorforthemajorityofcrashes.Similarly,properdrainageoftheroadswillensurethattheimpactofextremeweatherislessened,buttherewillbeatimewhenthatisnotsufficient.Whenthathappens,ensuringthattheregionhasplansinplacetodealwithroadclosureswillbeimportant.Toeffectivelymitigaterecurringcongestion,nowandinthefuture,amulti‐facetedapproachisnecessaryutilizingeffortswithdifferenttimescales.Quickesttoimplementincludetransportationdemandmanagementefforts,suchaspromotionofrideshare,telecommuting,bikingandusingpublictransit(assumingitisavailable).Othersolutionsforrecurrentcongestionincludeprovidingtravelerswithinformationonthecurrenttrafficconditions.Medium‐termsolutionse.g.solutionsdevelopedoveratime‐scaleofa

Page 9: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page3

fewyears,include:includeaddingadditionalpublictransit,iffeasible,andworkingwithemployersonimplementingflexibleschedulesandofferingtelecommutingasoptionsfortheirworkers.Roadprojectssuchasrebuildingtohighercapacities,modifyingthegeometry,orconstructingnewfacilitiesarealsointhemediumtolong‐term(ten‐year)timeframe.Longer‐termsolutionswouldentailchangestothebuiltenvironment,suchasplacinghomesclosertojobs(orviceversa)andchangingtheland‐usetopermitandencourageachangefromthesingle‐usezoningandland‐usepatternsthathavebeenprevalentformanydecades.2011‐2032MetropolitanTransportationPlanInJune2013,BFCGstaffmetwithstafffromFHWA,FTAandWSDOTforaTMACoordinationReviewofBFCGMPOworkproducts.TheintentwastogiveBFCGstaffanunderstandingofstrengths,weaknessesandnextstepsforourinitialCertificationReviewin2016,anddeadlinesforvariousTMAworkproducts.TheCongestionManagementProcesswasaprincipalcomponentofthereview.Anoutcomeofthereviewwasarecommendationthatsectionsofthe2011‐2032MetropolitanTransportationPlan(MTP)beincorporatedintotheCMP.ComponentsoftheMTPsuchasperformancemeasures,goalsandstrategies,travelmodelresultsandcongestionbackgrounddiscussion(includingacharacterizationofcongestionasatrafficvolumetoroadcarryingcapacityratio,avolume/capacityof.85),areapplicabletotheCMP.Additionally,theMTPhasbeenreviewedandapprovedbytheTechnicalandPolicyAdvisoryCommitteesandadoptedbytheBFCGBoard.IncorporatingMTPcomponentstotheCMPwillservetwopurposes.TheMTPandtheCMPareinterrelated,andincorporatingoneintotheotherenhancestherelationship.Additionally,utilizationofsectionsoftheMTP,whichhavebeenalreadybeenadoptedbyBFCG,willsavetime.TheCMPAdvisoryCommitteeagreedthatapplicablesectionsofthe2011‐2032MTPshouldbeincorporatedintocomparablesectionsoftheCMP.Thosepartsofthe2011MTPareinAppendixB.RelevantsectionsoftheMTPwillbeincorporatedintotheCMPasitisdeveloped.COMPONENTSOFACMPComponentsoftheBFCGRegionalCMPareoutlinedbelow.ItshouldbenotedthattheitemspresentedbelowwillevolveovertimeasexperienceisgainedinimplementingtheCMPsystemandanalyzingtheresultantdata. Developasetofcongestionidentificationmeasuresfortheregion. Establishaframeworkforgatheringandanalyzingthedatanecessarytodeterminehowthe

transportationsystemisoperating;whatmightbecausingcongestiononthesystem,whatactionsmightbeappropriatetoaddressthecongestion,andhoweffectivegivensolutionsmightbeinsolvingtheproblem.

Ensuretheevaluationofalternativestoaddresstheproblembothforthepresentandthefuturetransportationsystem.

Planhowandwhowillimplementthepreferredsolution,andhowitwouldbefunded. Provideforamechanismtomonitortheperformanceofthesystemtoascertainthe

continuedeffectivenessoftheimplementedsolution.CMPStudyAreaTheTri‐CitiesUrbanizedAreaBoundary(UZA)asapprovedbyFHWAin2013istheformalboundaryoftheCMPstudyarea(seeMap1).TheUZAwillchangeasaresultofeachcensusandtheCMPboundarywillchangewithit.Map1belowshowstheCMPStudyAreaandtheCongestedCorridors.

Page 10: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page4 Benton‐FranklinCouncilofGovernments

Map1:CM

PStu

dyA

rea

Page 11: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page5

CMPCorridorsTheinitiallistofcongestedcorridorshastwosources:thelistofcongestedcorridorsfromChapterSevenofthe2011MTP:ModelResultsandMetropolitanSystemEvaluation,andtheprofessionaljudgmentofengineeringstaffofMPOjurisdictions.The.85v/cmeasurementforcongestionestablishedinChapterSevenwillbeonecriteriausedtoevaluatecongestiononstreetsegmentsthathavebeenidentifiedbycityengineeringstaff.Congestedcorridorsmaybeaddedordeletedovertime.ThecorridorsselectedfortheinitialregionalCMPareshowninMap2.Asstated,thelistofcorridorsbeinganalyzedissubjecttomodificationovertime.ThecorridorsarelistedinTable1below.

TABLE1:CMPCONGESTEDCORRIDORSPerformanceMeasuresThedevelopmentofperformancemeasurestoidentifycongestionisthefirststepindefiningaCMP.Inmanyapplications,thetraditionalmeasurehasbeenthevolume‐to‐capacityratio(v/c).Existingtrafficcountsonidentifiedcorridorswillbethebasisofaninitialv/ccalculationandsubsequentcongestionidentificationmeasures.TheCMPwillusemeasuresthattrackautousagewithinaspecificcorridor.Traveltimealongthecorridors,ascapturedbypilotvehiclesusingaGPS(GlobalPositioningSystem)locationdevicewillbeimplementedastheinitialstageofdatacapturefortheCMP.However,partofthefocusofaCMPistoexpandtheconsiderationofsolutionstoincludealternativemodesandinnovativesolutions.Whiletheuseofv/casacongestionidentificationmeasureisappropriateduringtheinitialstagesofCMPdevelopment,asthedocumentevolves,moresophisticatedmeasuresthataddressmulti‐modalaspectsofthetransportationsystemwillberequiredinthefuture.

RICHLANDCONGESTEDCORRIDORSQueensgateDrive:KeeneRoadtoDuportailStreetGeorgeWashingtonWay:ColumbiaPointDrivenorthtoHornRapidsRoadStevensDrive:SR240toHornRapidsRoad

KENNEWICKCONGESTEDCORRIDORSColumbiaCenterBoulevard:ClearwaterAvenuetoWillametteAvenueClearwaterAvenue:US395toKelloggStreet

PASCOCONGESTEDCORRIDORSRoad68:ChapelHillBoulevardtoSandifurParkwayRoad100:ChapelHillBoulevardtoSandifurParkwayCourtStreet:Road40to20thAvenue20thAvenue:LewisStreettoArgentRoad

WSDOTCONGESTEDCORRIDORSSR240:Milepost20.48(Route10)toMilepost28.84(StevensDrive)SR240:Milepost30.63(JadwinAvenue)toMilepost34.57(SR182offramp)SR182:Milepost.87(DallasRoad)toMilepost4.40(I‐182westboundonrampfrom

GeorgeWashingtonWaysouthbound)

Page 12: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page6 Benton‐FranklinCouncilofGovernments

Map2:CM

PCon

gestedCorrid

ors

Page 13: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page7

Additionalmeasurescanbeaddedafterthebasicdatacollectionandanalysisprocessisinplace.Aregionaltrafficcountprogrammorefocusedoncongestedcorridorswillbedeveloped.Thesectionsofthe2011MTPincludedinAppendixBcontainmultiplegoalsandpossibleperformancemeasuresforconsideration.DataFrameworkCurrently,theframeworkforgatheringthedataneededbytheCMPisnotfullydeveloped.Forexample,trafficcounts:whileindividualjurisdictionshavecyclicaltrafficcountprograms,andcountdataontheiridentifiedcorridors,thosecountshavenotoccurredconsistentlyovertime.Jurisdictionsmayneedtoestablisharegularprogramofcountsonidentifiedcongestedcorridorstotrackvolumechangesovertime.Aprocessfortrackingtraveltimeoncongestedcorridorsisdescribedlaterinthisdocument.Thesuccessoftheprocessasoutlinedwillbereviewedovertimeanditwillbemodifiedifitisdeemednecessary.ToolsandprocesseswillneedtobedevelopedthroughacooperativeprocedurebetweentheMPOandthecitiestoensurethatthedatagatheredwillnotonlymeettheneedsoftheCMPrequirementsbutwillsatisfytheneedsoftheindividualjurisdictionsandagencies.Intheshort‐termcurrentdatacollectiontechniqueswillbesufficient;asadditionalperformancemeasuresareintroduced,newmethodstocollecttherequisitedatawillberequired.PeriodicReviewThefinalrequirementforaCMPisthatitprovidesanongoingreviewoftheregionalsystemasthealternativesarebroughtonline,todeterminehoweffectivethesolutionisworking.ThatisonepurposeoftheCorridorTrackingMatrixinAppendixC.Thisreviewformsatypeoffeedbacktotheplanningprocess,toinformanddirectthedecisionmakersastothepotentialeffectivenessoffutureprojects.CMPinPracticeAsof2014thedatacollectionprogramwillconsistofmeasuringthetraveltimealongselectedcorridors.Trafficcountswillcontinueandbeenhanced,andcollisiondatawillbemonitoredandevaluated.CMPDATASOURCESCurrentlyfourmeasurementprogramshavebeenidentifiedtocontributetoabasicunderstandingoftheoperationsoftheregionaltransportationsystem,includingwhere,andhowmuch,congestionexists.Theseareprogramsdesignedtomeasure:i]traveltime,ii]trafficcounts,iii]transitsystemdataandiv]collisiondata.Theseprogramsarenotatthesamelevelofmaturity.Theprocesstotracktraveltimeandeffectivelyanalyzethedataisunderdesign.TMAmemberjurisdictionshaveoperationaltrafficcountprogramswithdataavailableforthecorridors,butexistingdatamustbesupplementedbyamoreuniformcountprogram.Thenewprogram,withincreasedfrequencyofcounts,willneedtobeagreedupon.Transitsystemdataandcollisiondataprogramsareoperational.Thissectionofthereportincludesamoredetaileddescriptionofeachprogram,includingadiscussionofthedatathatisbeinggeneratedandpotentialissueswiththeimplementation.

Page 14: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page8 Benton‐FranklinCouncilofGovernments

TravelTimeProgramThetraveltimeprogram,asoutlinedinAppendixE,involvesdrivingvehiclesalongacorridorduringthemorningandeveningcommuteperiods.ThevehicleswillbeequippedwithaGPSanddatarecordingdevice,whichcapturesthevehicle’slocationandspeedalongwithtimeofdayforeachsecondoftravel.Thedataisprocessedbyspecializedsoftwarethatprovidesavisualdisplayoftheinformation,aswellassummariessuchasaveragespeedandaveragetraveltimebetweencheckpoints.TrafficCountsAsecondprogramisthecollectionandanalysisoftrafficvolumesonthecongestedcorridors.Typically,jurisdictionsinthemetropolitanareacollecttrafficcountsonathreeorfouryearcycles.Inaddition,WSDOToperatesanumberofpermanentcountersontheirfacilitiesinthearea.Aswithcollisiondata,jurisdictionshaveindicatedtheypreferpresentationofthemostrecentthreeyearsofdata(2010‐2012)tocharacterizevolumesontheircorridors.Todemonstratetheavailabilityofexistingdata,Table2belowshowsthenumberofcountsoneachofthecongestedcorridorsduringthelastsixyears.

Table2:FrequencyofTrafficCountsonCongestedCorridors

FREQUENCYOFTRAFFICCOUNTSONCONGESTEDCORRIDORS 2013 2012 2011 2010 2009 2008 2007

CityofRichlandQueensgateDrive X(2) X X(2)

GeorgeWashingtonWay X(3) X X(3)

StevensDrive X

CityofKennewickColumbiaCenterBoulevard X(5) X(5)

ClearwaterAvenue X(4) X(4)

CityofPascoRoad68 X(2) X(4) X(3) X X

Road100 X X

CourtStreet X(2) X(7) X(3)

20thAvenue X(5) X(2) X(4) X

WSDOTSR240(StevensDrive)* X X X X SR240(Bypass)* X X X X

I‐182(DallasRdtoGway)* X X X X Sources:MPOJurisdictionsand2012WSDOTAnnualTrafficReport

Thetableshowsthehistoricalfrequencyofeachjurisdiction’strafficcountsalongtheiridentifiedcorridors.Asshown,RichlandandKennewickhaveverylimitedcountdataontheiridentifiedcorridorsduringthatperiod.Jurisdictionshaveacknowledgedtheirestablishedtrafficcountprogramsmaynotbesufficienttosupplyenoughdatatotrackvolumesontheiridentifiedcorridors.Itmaybenecessarytodevelopaspecificcountprogramforcongestedcorridorstosupplementjurisdictions’establishedcountprograms.

Page 15: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page9

Agroupconsensusappearstobebuildingaroundtheideaofhiringaconsultanttoperformcountsatthesametimespecificallyforallidentifiedcongestedcorridors.ThiswillbefurtherdevelopedbytheAdvisoryCommittee.TransitSystemDataBenFranklinTransit(BFT)currentlydoesnotcapturepassengerdatainamannerapplicabletotheCMPneeds.However,theagencyisintegraltocomponentsofthetransportationsystemthatmateriallyaffectcongestioninthemetropolitanarea,andaregermanetotheCMPprocess.ThosearetheBFTVanpoolProgramandthemetropolitanareaparkandridesystem.Bothcomponentsaresummarizedhere,withadditionalbackgrounddataoneachinAppendixF.MuchofthetextinAppendixF,andallofthetablesandfiguresarefromthe2011‐2032MTP,tablesandfigureswillbeupdated.BenFranklinTransitVanpoolProgramIn1982,BenFranklinTransit,alongwiththenowdefunctWashingtonStateEnergyOffice,begansponsoringapilotride‐shareprogramintheTri‐Cities.Priortothatdatenopubliclyorganizedridesharingactivitieswereavailableinthearea.Atthattime,theFederalDepartmentofEnergy(DOE)maintainedabussystemtotransportemployeestoselectworksitesontheHanfordReservation.BecauseoftheHanfordReservation’srelativelydistantlocation,manyHanfordemployeesutilizedcarpoolsandvanpoolsfortraveltowork.RidesharingactivitiesincreasedthroughouttheTri‐CitiesduetoBFTpromotionofitsvanpoolprogramduringthe1980s.Inthemid1990’stheDOEdiscontinuedtheircommuterbusserviceandBFTwasabletofillthegapwithanaggressivevanpoolprogram.Overtime,utilizationofBFT’svanpoolprogramhasgrown,andBFThasmaintaineditslinkagetotheHanfordjobsite.BenFranklinTransitcurrentlyhas260Vanpoolvansontheroad;theirprimarydestinationistheHanfordArea;andtheirvanpoolserviceranksfourthinthestateinnumberofvansinservice.BasedonBFTdataasofSeptember2013,theprogramaveraged2,352,381passengermilespermonthwhilecarryinganaverageof73,975passengerspermonthsofarthisyear.MetropolitanAreaParkandRideSystemTheexistingparkandridesystembegandevelopmentintheearly1980’s.Currentlyitiscomprisedof15formalparkandridelotsinBentonandFranklinCountiesandanumberofinformallots.TheCMPdiscussionwillreviewdataconcerningtheformalparkandridelots.OccupancydatapresentedinAppendixFhasbeencollectedbytheWSDOTSouthCentralRegionalofficeinYakima.Thetwo‐countyareainventoryofparkandridelotsincludesbothparkandrideandparkandpoolfacilities.OwnershipofmostformalmetropolitanareaparkandridelotsisdividedbetweenWSDOTandBFT.BFTalsoleasesparkandridesites.Distinguishingbetweenthetwo,WSDOTfacilitiesareprimarilyparkandpoollotsadjacenttomajorroadwayintersectionssuchasSR240/SR224orI‐182/Queensgateandaresitedtocapturethevanpoolandcarpooluser.BFT‐ownedparkandridefacilitiesarelocatedattransitcentersintheirrespectivecommunities.Thefocusofthesefacilitiesisonthetransituserratherthanthecommuter,thoughcommutersmayusethem.

Page 16: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page10 Benton‐FranklinCouncilofGovernments

MetropolitanAreaCollisionTrendsCollisions,whetherresultingininjuriesorpropertydamage,arealeadingcauseofnon‐recurrentcongestion.Informationregardingcollisionsontheregion’sroadsiscollectedbytheWSDOTStatewideTravelandCollisionDataOffice.Byexaminingthedataforcollisionsalongacorridorbeforeandafteraprojecthasbeeninstalled,itshouldbepossibletodeterminehoweffectivetheprojecthasbeeninmeetingitssafetygoals.Metropolitanareaautomobile‐relatedcollisiondatafortheyears2002–2010ispresentedbelowtoprovidehistoricalcontext.IndividualcorridoranalysisreportspresentedinAppendixDpresentcollisiondatafortheyears2010–2012summarizedinatable.Thatdataisdepictedonamaptohelpidentifywhetheranylocationsonthecorridorexperienceadisproportionatenumberofcrashesandtopotentiallydeviseprogramsandprojectsthatwilladdresstheseareas.

Table3:MetropolitanAreaCollisionOutcomes‐2002‐2010

MetropolitanAreaCollisionOutcomes‐2002‐2010

YEARS AREA COLLISIONS INJURIES FATALITIES *PEDESTRIANS *BICYCLISTS

2002‐2004 MPO 5,942 1,832 8 101 82

%ofIncidents 30.83% 0.13% 1.70% 1.38%

2005‐2007 MPO 5,902 1,784 10 85 76

%ofIncidents 30.23% 0.17% 1.44% 1.29%

2008‐2010 MPO 5,452 1,638 4 101 78

%ofIncidents 30.04% 0.07% 1.85% 1.43%

Source:WSDOTStatewideTravelCollisionDataOffice

*Totalsincludebothinjuriesandfatalities

Figure1:MetropolitanAreaCollisions‐2002‐2010

Source:WSDOTStatewideTravelCollisionDataOffice

INJURIES

COLLISIONS‐

1,000

2,000

3,000

4,000

5,000

6,000

NumberofCollisions

YearsofOccurence

MetropolitanAreaCollisions‐ 2002‐2010

Page 17: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page11

APPENDICES

Page 18: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page12 Benton‐FranklinCouncilofGovernments

AppendixA–FederalRegulationsAddressingtheCMP.......................................................................................13

AppendixB–2011‐2032MetropolitanTransportationPlan.............................................................................19

AppendixC–CMPCongestedCorridorTrackingMatrix.....................................................................................41

AppendixD–CongestedCorridorData.......................................................................................................................45

AppendixE–TravelTimeDataCollection..................................................................................................................97

AppendixF–TransitSystemData..............................................................................................................................101

AppendixG–TransportationSystemComponentsintheCMPStudyArea..............................................107

AppendixH–PublicComment.....................................................................................................................................113

Page 19: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page13

APPENDIXAFederalRegulationsAddressing

TheTMACongestionManagementProcess

Page 20: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page14 Benton‐FranklinCouncilofGovernments

Page 21: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page15

Title23:Highways

PART450—PLANNINGASSISTANCEANDSTANDARDS

SubpartC—MetropolitanTransportationPlanningandProgramming

§450.320Congestionmanagementprocessintransportationmanagementareas.

(a)ThetransportationplanningprocessinaTMAshalladdresscongestionmanagementthroughaprocessthatprovidesforsafeandeffectiveintegratedmanagementandoperationofthemultimodaltransportationsystem,basedonacooperativelydevelopedandimplementedmetropolitan‐widestrategy,ofnewandexistingtransportationfacilitieseligibleforfundingundertitle23U.S.C.andtitle49U.S.C.Chapter53throughtheuseoftraveldemandreductionandoperationalmanagementstrategies.

(b)ThedevelopmentofacongestionmanagementprocessshouldresultinmultimodalsystemperformancemeasuresandstrategiesthatcanbereflectedinthemetropolitantransportationplanandtheTIP.ThelevelofsystemperformancedeemedacceptablebyStateandlocaltransportationofficialsmayvarybytypeoftransportationfacility,geographiclocation(metropolitanareaorsubarea),and/ortimeofday.Inaddition,considerationshouldbegiventostrategiesthatmanagedemand,reducesingleoccupantvehicle(SOV)travel,andimprovetransportationsystemmanagementandoperations.Wheretheadditionofgeneralpurposelanesisdeterminedtobeanappropriatecongestionmanagementstrategy,explicitconsiderationistobegiventotheincorporationofappropriatefeaturesintotheSOVprojecttofacilitatefuturedemandmanagementstrategiesandoperationalimprovementsthatwillmaintainthefunctionalintegrityandsafetyofthoselanes.

(c)Thecongestionmanagementprocessshallbedeveloped,established,andimplementedaspartofthemetropolitantransportationplanningprocessthatincludescoordinationwithtransportationsystemmanagementandoperationsactivities.Thecongestionmanagementprocessshallinclude:

(1)Methodstomonitorandevaluatetheperformanceofthemultimodaltransportationsystem,identifythecausesofrecurringandnon‐recurringcongestion,identifyandevaluatealternativestrategies,provideinformationsupportingtheimplementationofactions,andevaluatetheeffectivenessofimplementedactions;

(2)Definitionofcongestionmanagementobjectivesandappropriateperformancemeasurestoassesstheextentofcongestionandsupporttheevaluationoftheeffectivenessofcongestionreductionandmobilityenhancementstrategiesforthemovementofpeopleandgoods.Sincelevelsofacceptablesystemperformancemayvaryamonglocalcommunities,performancemeasuresshouldbetailoredtothespecificneedsoftheareaandestablishedcooperativelybytheState(s),affectedMPO(s),andlocalofficialsinconsultationwiththeoperatorsofmajormodesoftransportationinthecoveragearea;

(3)Establishmentofacoordinatedprogramfordatacollectionandsystemperformancemonitoringtodefinetheextentanddurationofcongestion,tocontributeindeterminingthecausesofcongestion,andevaluatetheefficiencyandeffectivenessofimplementedactions.Totheextentpossible,thisdatacollectionprogramshouldbecoordinatedwithexistingdatasources(including

Page 22: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page16 Benton‐FranklinCouncilofGovernments

archivedoperational/ITSdata)andcoordinatedwithoperationsmanagersinthemetropolitanarea;

(4)Identificationandevaluationoftheanticipatedperformanceandexpectedbenefitsofappropriatecongestionmanagementstrategiesthatwillcontributetothemoreeffectiveuseandimprovedsafetyofexistingandfuturetransportationsystemsbasedontheestablishedperformancemeasures.Thefollowingcategoriesofstrategies,orcombinationsofstrategies,aresomeexamplesofwhatshouldbeappropriatelyconsideredforeacharea:

(i)Demandmanagementmeasures,includinggrowthmanagementandcongestionpricing;

(ii)Trafficoperationalimprovements;

(iii)Publictransportationimprovements;

(iv)ITStechnologiesasrelatedtotheregionalITSarchitecture;and

(v)Wherenecessary,additionalsystemcapacity;

(5)Identificationofanimplementationschedule,implementationresponsibilities,andpossiblefundingsourcesforeachstrategy(orcombinationofstrategies)proposedforimplementation;and

(6)Implementationofaprocessforperiodicassessmentoftheeffectivenessofimplementedstrategies,intermsofthearea'sestablishedperformancemeasures.Theresultsofthisevaluationshallbeprovidedtodecisionmakersandthepublictoprovideguidanceonselectionofeffectivestrategiesforfutureimplementation.

(d)InaTMAdesignatedasnonattainmentareaforozoneorcarbonmonoxidepursuanttotheCleanAirAct,FederalfundsmaynotbeprogrammedforanyprojectthatwillresultinasignificantincreaseinthecarryingcapacityforSOVs(i.e.,anewgeneralpurposehighwayonanewlocationoraddinggeneralpurposelanes,withtheexceptionofsafetyimprovementsortheeliminationofbottlenecks),unlesstheprojectisaddressedthroughacongestionmanagementprocessmeetingtherequirementsofthissection.

(e)InTMAsdesignatedasnonattainmentforozoneorcarbonmonoxide,thecongestionmanagementprocessshallprovideanappropriateanalysisofreasonable(includingmultimodal)traveldemandreductionandoperationalmanagementstrategiesforthecorridorinwhichaprojectthatwillresultinasignificantincreaseincapacityforSOVs(asdescribedinparagraph(d)ofthissection)isproposedtobeadvancedwithFederalfunds.IftheanalysisdemonstratesthattraveldemandreductionandoperationalmanagementstrategiescannotfullysatisfytheneedforadditionalcapacityinthecorridorandadditionalSOVcapacityiswarranted,thenthecongestionmanagementprocessshallidentifyallreasonablestrategiestomanagetheSOVfacilitysafelyandeffectively(ortofacilitateitsmanagementinthefuture).Othertraveldemandreductionandoperationalmanagementstrategiesappropriateforthecorridor,butnotappropriateforincorporationintotheSOVfacilityitself,shallalsobeidentifiedthroughthecongestionmanagementprocess.AllidentifiedreasonabletraveldemandreductionandoperationalmanagementstrategiesshallbeincorporatedintotheSOVprojectorcommittedtobytheStateandMPOforimplementation.

Page 23: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page17

(f)Statelaws,rules,orregulationspertainingtocongestionmanagementsystemsorprogramsmayconstitutethecongestionmanagementprocess,iftheFHWAandtheFTAfindthattheStatelaws,rules,orregulationsareconsistentwith,andfulfilltheintentof,thepurposesof23U.S.C.134and49U.S.C.5303.

§450.338Phase‐inofnewrequirements.

(a)MetropolitantransportationplansandTIPsadoptedorapprovedpriortoJuly1,2007maybedevelopedusingtheTEA‐21requirementsortheprovisionsandrequirementsofthispart.

(b)FormetropolitantransportationplansandTIPsthataredevelopedunderTEA‐21requirementspriortoJuly1,2007,theFHWA/FTAaction(i.e.,conformitydeterminationsandSTIPapprovals)mustbecompletednolaterthanJune30,2007.FormetropolitantransportationplansinattainmentareasthataredevelopedunderTEA‐21requirementspriortoJuly1,2007,theMPOadoptionactionmustbecompletednolaterthanJune30,2007.IftheseactionsarecompletedonorafterJuly1,2007,theprovisionsandrequirementsofthispartshalltakeeffect,regardlessofwhenthemetropolitantransportationplanorTIPweredeveloped.

(c)OnandafterJuly1,2007,theFHWAandtheFTAwilltakeactiononanewTIPdevelopedundertheprovisionsofthispart,eveniftheMPOhasnotyetadoptedanewmetropolitantransportationplanundertheprovisionsofthispart,aslongastheunderlyingtransportationplanningprocessisconsistentwiththerequirementsintheSAFETEA‐LU.

(d)Theapplicableaction(seeparagraph(b)ofthissection)onanyamendmentsorupdatestometropolitantransportationplansandTIPsonorafterJuly1,2007,shallbebasedontheprovisionsandrequirementsofthispart.However,administrativemodificationsmaybemadetothemetropolitantransportationplanorTIPonorafterJuly1,2007intheabsenceofmeetingtheprovisionsandrequirementsofthispart.

(e)FornewTMAs,thecongestionmanagementprocessdescribedin§450.320shallbeimplementedwithin18monthsofthedesignationofanewTMA.

Page 24: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page18 Benton‐FranklinCouncilofGovernments

Page 25: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page19

APPENDIXB2011‐2032MetropolitanTransportationPlan

Page 26: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page20 Benton‐FranklinCouncilofGovernments

Asreferencedearlier, in June2013,BFCGstaffmetwithstaff fromFHWA,FTAandWSDOTforaTMA Coordination Review of BFCG work products. An outcome of the review was arecommendation that sections of the 2011‐2032 Metropolitan Transportation Plan (MTP) beincorporatedintotheCMP. SectionsoftheMTP–performancemeasures,goals,strategies, travelmodel results andbackgrounddiscussion (including a characterization of congestion as aV/Cof.85)–areapplicabletotheCMP.TheMTPhasbeenreviewedandapprovedbytheTechnicalandPolicyAdvisoryCommitteesandadoptedbytheBFCGBoard.Thosesectionsofthe2011‐2032MTParebelow.

Page 27: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page21

CHAPTERTHREE‐REGIONALTRANSPORTATIONGOALS&POLICIES

INTRODUCTIONThegoals,policies,andstrategiesweredevelopedthroughthetransportationplanningprocessandsubsequentlyadoptedbytheBFCGBoard.Thesegoalsandpolicieswillguideanddirecttheregionaltransportationplanningprocessforthenexttwentyyears.MISSIONThemissionofthisRegionalTransportationPlanistodevelopandmaintainabalancedregionaltransportationsystemthatprovidesaccessandmobilityforpeople,goods,andservicesinasafe,convenient,andenergyefficientmanner;minimizesimpactsupontheenvironment;iscoordinatedthroughamulti‐jurisdictionaleffort;iscompatiblewithadjacentlanduses;facilitatesplannedeconomicgrowth;andmaintainsthelivabilityofthecommunitiesacrosstheentireregion.GOALSOFTHERTP: Thepreparationandimplementationofalongrangeplanwhichidentifiestransportation

relateddeficienciesandproblems,providescleardirection,andseekscomprehensiveleast‐costsolutionsformaintainingtheintegrityofthetransportationsysteminBenton,Franklin,andWallaWallaCounties;

Atransportationsystemthatisintegratedwithlocallandusepolicies;

Atransportationsystemthatprovideslowercostsolutionsintheformoftransit,

vanpool/carpool,bicycling,andwalking,inlieuofexpandingcapacity; Atransportationsystemthatprovidesaccessforgoods,services,andpeoplewhile

minimizingtotalsystemcosts; Atransportationsystemthatprovidesaccessandmobilityforallcitizensregardlessofage,

race,orability; Atransportationsystemthatgivesaccesswhileminimizingenergyconsumptionand

environmentalimpacts; Atransportationsystemthatmeetstheneedsforsustainedeconomicgrowth;

Atransportationsystemthatisconsistentwithlocal,regional,stateandfederalpolicies;

and Atransportationsystemthatassuresimprovementsareconsistentwithandsupportsthe

valuesofcommunitiesandneighborhoodstructures.

POLICIESPolicy1–Access&AccessManagementItisthepolicyoftheBenton‐FranklinCouncilofGovernmentstosupportaregionaltransportationsystemthatemphasizesaccessandaccessmanagementandencouragesthememberjurisdictionstoadoptpoliciesincorporatingaccessmanagementintotheirconstructionprojectsandprojectprioritizationprocesses.

Page 28: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page22 Benton‐FranklinCouncilofGovernments

ActionStrategiesEstablishasystemtodefineacceptablelevelsofaccessibilityofallmodestovariouslandusesforallpotentialusersofthetransportationsystemthroughminimumservicestandards.Supportlandusestrategiesthatreducemobilityrequirementssuchasmixed‐usedevelopment,transitorienteddevelopment,andinfilldevelopment.Encouragemulti‐modalaccessibilitytolandusesincludingmeasureswhichprovideaccessforthetransportationdisadvantagedandmobilitychallenged.Encouragecitiesandcountiestoincorporateaccessmanagementintotheircomprehensiveplanningandintotheirlanduseandsubdivisionregulationsandpolicies.Encourageincorporationofaccessmanagementintoprojectprioritizationandselectioncriteria.Encouragecitiesandcountiestoincorporateaccessmanagementintotheirconstructionprojects.Encouragedeveloperstoincorporateaccessmanagementintotheirplans.Policy2‐EfficiencyItisthepolicyoftheBFCGtosupportaregionaltransportationsystemthat1)Maintainsthegreatestefficiencyofmovementintermsoftraveltimeanddistanceand2)Requirestransportationinvestmentdecisionstomaximizethefullnetbenefitsofthesystem.ActionStrategiesExplorethepossibilityofassimilatingcosteffectivenessofalternativesupplyanddemandinvestments,longtermlevelofservice/life‐cyclecostcomparisons,andothereconomiccriteriaintotheplanningprocessinordertodevelopcost‐effectivesolutionsandmoreefficienttransportationfacilities(i.e.least‐costplanning).Encouragecoordinatedplanningpracticesandroadandstreetstandardsamongthecountiesandtheircitiesandtowns.Discourageinefficientmodesoftransportation,suchassingleoccupancyvehicles(SOVs),duringpeakhours.Promotemaintainingtheefficiencyoftheexistingtransportationsystemsbysupportinginvestmentsinoperationalstrategiesandtechnologies.PromoteTransportationDemandManagement(TDM)strategies,voluntaryCommuteTripReduction(CTR),transit,HOV,bicycling,andwalking.Policy3‐BalanceItisthepolicyoftheBFCGtosupportaregionaltransportationsystemthat1)Stressesmulti‐modalismwithminimumservicestandards,2)Providestransportationoptions,3)Avoidsdependenceonanyparticularmode,especiallysingleoccupancyvehicles,and4)Optimizestheefficiencyofeachmode.ActionStrategiesEncouragesystemsandfacilitiesthataccommodatemultiplemodes,whenpossible,especiallyalongtransportationcorridorsthatprovideuserswithcost‐effectivechoicesintheirtraveloptions.

Page 29: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page23

Supportdemandmanagementtechniquesthatstrengthentheefficienciesofeachmodeoftransportation.Supporttheuseofthemostefficientformoftransportationforeacharea,recognizingthatnotallmodesareappropriateforeacharea.Encourageefficientmulti‐modaltransportationsystemsthatarebasedonregionalprioritiesandcoordinatedwithcountyandcitycomprehensiveplans.Policy4–Safety&SecurityItisthepolicyoftheBFCGtoprovideatransportationsystemthatmaintainsandimprovessafetyandsecurityinallaspectsofthetransportationnetwork,includingbothusersandnon‐usersofthesystem.ActionStrategiesSupportandpromoteregion‐wideparticipationinthestate’seffortstoidentifytrafficsafetyneedsandguideinvestmentdecisionstoachievesignificantreductionsintrafficfatalitiesandseriousinjuriesonallpublicroads(SHSP:TargetZero).Supportandpromoteprogramsthatensurebothstructurallyandoperationallysafeandsecurepedestrian,bicycle,automobile,truck,rail,waterway,andairtravelmovement.Encouragedevelopmentoftransportationsafetygoals(e.g.roadsafetytargetsandpolicies)toprovidedirectiontothesafetycomponentofaplan.Encourageinteragencycooperationbetweengovernmentalandprivateenterprisestoincreaseoverallsafetyandsecurityawareness.Promotehighlevelsofsafetystandardsforallmodesoftransportationsothatusersfeelsafeandsecureastheytravel.Implementtrafficcalmingmeasurestoreduceautomobilespeedsinpedestrianareas,suchasresidentialneighborhoodsandschoolzones.EncouragecitiesandcountiestoseekcompetitivefundingsolutionsthroughWSDOT’sSafeRoutestoSchoolsProgram.Policy5–SafetyConsciousPlanning(SCP)ItisthepolicyoftheBFCGtopromoteintegrationofurbanlanduseandtransportationplanningeffortsthroughimplementationofsafetyconsciousplanning.ActionStrategiesMonitornationaleffortstowarddevelopmentofauser‐friendlycollisionpredictionmodelandtheassociatedanalyticaltechniquestodiagnoseandidentifyareasinwhichthereispotentialtoimprovetheinherentsafetyofthetransportationsystem.Promotesafetyconsiderationsaskeycriteriainevaluatingprojectsandprogrammingexpenditures.Ensurethatthemeasuresincorporatedinaplaneffectivelyreflectroadsafetyissues.

Page 30: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page24 Benton‐FranklinCouncilofGovernments

Encourageplanimplementationstrategiesthateffectivelyimplementandreflectroadsafetyprioritiesandfinancialprogramming.StresstheneedforSCPinlanduseplanningdecisionsandprocesses.StressthatSCPisalsoanintegralpartoftransportationplanningforallmodesoftravel.Policy6‐EnvironmentalResponsibilityItisthepolicyoftheBFCGtoprovidearegionaltransportationsystemthatlimitsandmitigatesadverseandharmfulimpactsontheenvironment.ActionStrategiesEnsureallelementsoftheRTPsupportenvironmentalresponsibilityinordertomeetfederalandstaterequirements.Promoteenvironmentallyefficientmodesoftransportationsuchastransit,HOVs,bicycling,andwalkinginordertominimizenegativeimpactsontheenvironment.Promotedevelopmentofalternativestoactionsthatadverselyimpacttheenvironment.Coordinatewithlocalagenciesinidentifyingandmitigatingtheeffectsofthetransportationsystemonsensitiveareas.Promotethepreservationofagriculturallandsandopenspacesandtheconservationoffishandwildlifehabitat.Promoteconsistencywithenvironmentalrulesandregulations.Policy7‐TransportationFinancingItisthepolicyoftheBFCGtopromotefundingstrategiesthatensureregionalfinancialstabilityforthetransportationnetwork.ActionStrategiesWorkwithcommunity,businessandcitizeninterestgroupstoestablishagreementontransportationneedsandtoseeksupportonfundingmeasurestofinancecapitalimprovementprojects,includinginnovativefinancingstrategies.Encouragethestatelegislaturetoindexthestatemotorfueltaxtoinflationtoforestallever‐decreasingbuyingpower.Encouragethestatelegislaturetoconsiderfundingalternativestothegastaxasvehiclesgetmorefuelefficient,hybridize,orusealternativefuels.Encouragethestatelegislaturetoexempttransportationconstructionprojectsfromtheretailsalestaxthatcurrentlyshiftstransportationfundsbackintothegeneralfund.Policy8‐IntergovernmentalCooperationIncludingRegionalConsistency&CertificationItisthepolicyoftheBFCGtoprovidearegionaltransportationplanningprocessthat1)Coordinatesfederal,state,regional,andlocalcomprehensiveplans,policiesandlegislationand2)Emphasizescooperationamongjurisdictions.

Page 31: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page25

ActionStrategiesContinuetoencourageactiveparticipationbyallmembersoftheTri‐MATSMPO/RTPOstructureatthetechnical,policy,andboardlevels,includingtheformationofspecialcommitteesforspecificprojectsorprograms.Promoteandhostmeetingsandworkshopspertinenttoregionaltransportationissues,policies,andplanning.Coordinatebetweenstateandmemberjurisdictionsconcerningtechnicalmethodsanddatatoidentifyandanalyzeneedsofregionalsignificance.Provideforcoordinationbetweenthestateandmemberjurisdictionsonmajortransportationdecisionsinvolvingalltransportationmodes.Developregional“guidelinesandprinciples”toserveasaguidefordeveloping,updating,andreviewinglocalcomprehensiveplantransportationelements.(SeeAppendixC).CertifythatthetransportationelementsofcomprehensiveplansconformtotheappropriaterequirementsofRCW36.70A.070andrecommendstepstomeettheRCWrequirementsinWashingtonAdministrativeCode(WAC)365‐195‐325.CertifyconsistencybetweenthetransportationelementsoflocalcomprehensiveplansandthisRegionalTransportationPlan.DetermineconsistencyofcitycomprehensiveplantransportationelementswiththeCountywideplanningpoliciesadoptedbytherespectiveBoardsofCountyCommissionersandthecitieswithinthosecounties.DevelopachecklistforcertifyingconformityoftransportationelementswiththeGMAandtheRegionalTransportationPlan.(SeeAppendixC)Discussandresolveanyinconsistenciesidentifiedduringthecertificationprocess,firstwithjurisdictionalstaff,andifnecessary,attheTechnicalandPolicyAdvisoryCommitteelevels.TheBFCGBoardwillmakethedecisiononanyissuesofinconsistency.Policy9‐CitizenInvolvementandPublicEducationTheBFCGinJuly1994adopted“PublicInvolvementProceduresforTransportationPlanning”(lastrevisedandadoptedJanuary2008).TheBFCGdevelopsandmaintainson‐goingprogramsthatincludecitizenparticipationinalltransportationrelateddecisions.ActionStrategiesMakeinformationabouttransportationplans,policies,projects,andprogramsavailabletothepublicinanunderstandableform.Developongoingpubliceducationprogramsandtransportationforumsaboutregionalandstatewidetransportationplanningtoassurethepublicisinformedoncurrentissues,proposedimprovements,newtechnologies,andupcomingevents.Continuetoapprisethemedia(newspapers,radio,andtelevision)ofnewsworthytransportationinformationforpublicationorgeneraldisclosure.Arrangeinterviews,printanddistributeflyers,etc.

Page 32: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page26 Benton‐FranklinCouncilofGovernments

Continuetoincludeup‐to‐datetransportationinformationintheBFCGmonthlynewsletter(circulation300).ContinuetoexpandandimproveBFCGPublicInvolvementProcedurestoattainthemosteffectivecitizeninvolvementandawareness.Communicatewithpotentialusersofthetransportationsystem,includingtheprivatesector,toensurethattransportationdecisionsthatimpactprivatefacilitiesorpublicservicesarecoordinatedwiththeaffectedusersorindustries.Policy10–Livability,Sustainability&LandUseItisthepolicyoftheBFCGtoencouragetransportationrelateddecisionsthatmaintainandenhancelivabilityandsustainabilityforallcitizensandcommunitieswithinBenton,Franklin,andWallaWallacounties.ActionStrategiesPromotetransportationprojectsandimprovementsthatsupportcommunitygoalsofaccesstojobs,affordablehousing,andgoodschools.Maximizetransportationchoicesthatwillimproveregional,community,andneighborhoodlivability.Promotetransportationprojectsandimprovementsthatenhanceandprotectacommunity’saestheticvalues.Workwithcitizensandcommunitygroupstoassuretransportationprojectssupportlivabilitywithinneighborhoodsandcommunities.Promotetheprovisionofgreenbelts,parks,andpathsandpreservationofopenspacerelativetotransportationimprovementprojectsandnewinfrastructuredevelopment.Encourageinfilldevelopmentandredevelopmentinareaswhereaccesstoalternativetransportationisprovided.Supportdevelopmentsthatprovideoptionsforpeopletolive,work,andshopinthesameareasandaccomplishday‐to‐dayneedsclosetohomeviamobilityoptionsotherthansingle‐occupancyvehicles.Supportincreaseddensitiesandin‐filldevelopmentforefficientuseofurbanlandwhilestillmaintainingopen‐spaceareaandresidentialprivacyandsafety.Strivetoimprovecirculationandaccesswithinareasthataremostlikelytosupportmixed‐usedevelopments,in‐filldevelopment,andincreaseddensity.SupporttheeffortsoftheAllianceforaLivableandSustainableCommunity.Policy11‐PedestriansandBicyclesItisthepolicyoftheBFCGtopromotepedestrianandbicycletravelasessentialmodesoftransportationbothwithinexistingcommunitiesandnewdevelopmentandtoprovideopportunitiesforthesafeandefficientuseofpedestrianandbicyclefacilitiesasalegitimatealternativetomotorizedtravelandforimprovedhealth.

Page 33: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page27

ActionStrategiesDevelop,implement,andmaintain,apedestrianandbicycleplanthatisconsistentwithfederal,state,andlocalpedestriangoalsandobjectives.1

EstablishBicycle/PedestrianAdvisoryCommittee(BPAC)tooversee,promote,review,andmakerecommendationsonregionalbicycleandpedestrianissues.Assignahighprioritytotheprovisionofbicycleandpedestrianaccessinlocalcomprehensiveplans.Encouragelocaljurisdictionstodevelopordinanceswhichrequiretheprovisionofsafe,adequate,andconvenientaccessforpedestriansandbicyclesinnewdevelopment.Encourageprovisionofsidewalksandbicyclelanesonarterialsandschoolroutes.EncouragelocaljurisdictionsandschooldistrictstocooperativelyseekfundsthroughWSDOT’sSafeRoutestoSchoolsProgram.Encouragetheconnectionofparks,openspaces,waterandotherrecreationareastoresidentialareaswithbicycleandpedestrianpathsandwhenappropriate,equestrianpaths.Promotetheadoptionofefficientnon‐motorizedcompatiblelandusepatternsandzoningrequirements.Encourageconsiderationofpedestrian/bicycletransportationneedsrelativetoallurbantransportationimprovementprojectsandsubdivisiondevelopments.1See2010RegionalBicycleandPedestrianTransportationPlanforBenton,FranklinandWallaWallaCountiesandTri‐CitiesUrbanArea,October2010BFCG.Policy12‐TransitElementItisthepolicyoftheBFCGto1)SupportBenFranklinTransitandValleyTransitandtheirgoalsandpolicies;2)Promoteatransitsystemwhichoffersalternativestothesingleoccupancyvehicle;3)Promoteatransitsystemthatoffersservicestocitizenswithspecialtransportationneeds;4)Promotelandusepatternsthatsupporttheuseoftransit;and5)SupportintercitybusservicebetweenWallaWallaandtheTri‐Cities.ActionStrategiesSupportourtransitagenciesintheireffortstomaintaineffectiveandpredictableoperationsofthetransitsystemstomeetcustomers’expectations.SupporttheGrapeLine’scontinuationofintercitybusservicebetweenWallaWallaandtheTri‐Cities.Integratetheregionaltransitsystemswithothermodesoftransportationincludingair,rail,auto,bicycles,andpedestrianstofacilitatesmoothinter‐modalconnections.Evaluatethepossibilityofprovidingfurtherintercitytransitserviceasaviablealternativetohighwayexpansion.

Page 34: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page28 Benton‐FranklinCouncilofGovernments

PeriodicallyreevaluatetheviabilityofprovidingsomeformoftransitservicetothoseruralRTPOcommunitiesnotcurrentlyhavingsuchservice.Encouragetransitfriendlylanduseplansanddevelopmentpatterns.Supportservicestothosecitizenswithspecialtransportationneeds.SpecialtransportationneedsasdefinedbyRCW47.06B.012;“Personswithspecialtransportationneeds”meansthosepersons,includingtheirpersonalattendants,whobecauseofphysicalormentaldisabilityincomestatus,orageareunabletotransportthemselvesorpurchasetransportation.Policy13‐TransportationDemandManagement/CommuteTripReductionItisthepolicyoftheBFCGtopromotestrategiesthatofferlow‐costsolutionstocapacitychallengesonourstreetsandhighways.ActionStrategiesWorkwithWSDOT,BenFranklinTransit,urbanjurisdictions,andmajoremployerstodevelopandimplementavoluntaryCommuteTripReductionprogramfortheTri‐Citiestoreducesingleoccupancyvehicleuse,vehiclemilestraveled,andminimizetriplengthduringpeakperiods.Overallbenefitswillbereducedcongestionanddelay,cleanerairandlessfuelconsumption.Continuetoworkwithdecision‐makers,jurisdictions,andotheragenciestoencouragetheDepartmentofEnergy(DOE)toimplementtheFederalEmployeesCommuteTripSubsidyProgram.Encourageemployerstoofferflexibleworkschedules(flextime);telecommuting,4‐dayworkweek,andotherincentivesthatreducepeakperiodtravelandlessentheneedforroadwaycapacity.Encouragecommercialdriverstomakedeliveriesandtheshippingoffreightduringoff‐peakhours.Investigatewaysinwhichparkingcanbemanagedtodecreasedrivealonecommuters.Explorelandusestrategiesthatcanreducetheuseofsingleoccupancyvehicles.ContinuefacilitationoftheurbanTransportationDemandManagementCommittee.Policy14‐StreetsandHighwaysItisthepolicyoftheBFCGtoencourageanetworkofstreetsandhighwaysthat1)Supportsabalancedandefficientmulti‐modaltransportationnetwork;2)Isaccessibleforavarietyofusers;3)Meetstheneedsforsafelymovingpeople,goods,andservicesthroughouttheregion;4)Contributestothelivabilityofbothurbanandruralcommunities.ActionStrategiesEncourageconsiderationofmulti‐modalneedsandaccessibility,includingpedestriansandbicycles,freightandgoodsmovement,etc.,relativetoallurbantransportationimprovementprojectsandsubdivisiondevelopments.Promotetransportationimprovementsthatenhancecommunityaccessandlivability.Promotetransportationimprovementsthatmeetinfrastructureneedsoftheregion’smajorsourcesofeconomicgrowthandvitality,includingrecreationandtourism.Maintainthearterialstreetsystemforthesafeandeconomicalmovementofpeople,goods,andserviceswithinandthroughtheregionandtopromoteadiversifiedeconomy.

Page 35: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page29

Encouragepreservationoftransportationcorridorsforfuturegrowth.Policy15‐Air/Waterways/RailItisthepolicyoftheBFCGtoencourageairandrailpassengerfacilitiesandservicesandriverandrailfreightfacilitiesandservicesthatenhanceregionaleconomiccompetitiveness.ActionStrategiesEnsurethattheimpactofsurroundingdevelopmentonairportoperationsisminimizedandadjacentlandusedecisionsareconsistentwithairportoperations.Promoteexpansionofmainlinefreightrailroadcapacitybytherailroadsandtheimprovementofrailaccesstoandefficientuseofinter‐modalterminalsandports.Promotecontinuationandimprovementoffreightserviceonbranchandlightdensityraillinesandpreservationofanyessentiallinesthreatenedwithabandonment.Supportandencourageprojectstoreduceoreliminateconflictsbetweentrainsandvehiclesand/orpedestrians.Continuetorejectandopposeriverdraw‐downsbelowcurrentoperatinglevelsandremovalorbreachingofanydamsonthelowerSnakeRiverorColumbiaRiversystems.TheMinimumOperatingPool(MOP)shouldbemaintainedbytheCorpsofEngineerstoensurethepreservationofthe14footfederalnavigationchannel.SupporttheUSArmyCorpsofEngineersintheirongoingeffortstodredgetheColumbiaRiver/SnakeRiversystem.SupportandencouragetheCorpsofEngineerstocontinueSnakeRiverdredgingasneededtopreservetheviabilityofportfacilitiesatClarkston,Washington,andLewiston,Idaho.Policy16‐FreightMovementItisthepolicyoftheBFCGtoencouragesafeandefficientfreightmovement;supportinter‐modalfreightfacilities;andensurethatanyharmfuleffectsoffreightmovementaremitigatedwiththeusersofthesystem.ActionStrategiesGatherandmaintainfreightinformationforallappropriatemodes.Coordinatewithlocaljurisdictions.PeriodicallyreviewandupdatetheregionalportionofthestatewideFreightandGoodsTransportationSystem.Evaluatefreightmovementneeds,restrictions,opportunities,andconstraintswithintheregion.Examinehazardscreatedbyfreightmovementtolocalcommunitiesandsearchforsolutionstomitigateinequitiesorhazards.Encouragelocalcomprehensiveplanstoaddresstheissueoffreightmovementwithintheirboundariesandaddresstheimpactsassociatedwithlanduseandfreightmovement.Supportprivatesectorinvestmentsinadvancedtechnologiesandmanagementsystemsthatsupportregionalgoalsandpolicies.

Page 36: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page30 Benton‐FranklinCouncilofGovernments

ApplytherecommendationsfromtheEasternWashingtonInter‐modalTransportationStudy(EWITS)andtheStrategicFreightTransportationAnalysis,bothbyWashingtonStateUniversity,toapplicablepoliciesandstrategies.Promoteandencourageall‐weathersurfacingoffarm‐to‐marketroadssubjecttoheavytruckusageandseasonalclosuresorweightrestrictions.Encouragefreightaccessimprovementstoagriculturalprocessing,industrialfacilities,ports,railterminalsandothershippingfacilities.Encouragethelocationoffreightfacilitiesadjacenttoappropriateexistingarterialsandtransportationhubsandencouragetheconsolidationoffreightfacilitieswhereverfeasible.SupporteffortsbytheCorpsofEngineersandthestatesofWashington,Oregon,andIdahotorestoreandupgradetheColumbia/SnakeRivernavigationsystemtostrengthenourpositionintheinternationaltrademarket.ContinuesupportoftheWSDOTintheireffortstofindsolutionstothechallengesassociatedwithI‐90overSnoqualmiePass.SupportWSDOT in efforts to secure funding for the completion of the I‐90 improvements overSnoqualmiePass.Policy17–IntermodalismItisthepolicyoftheBFCGtoencourageandmaintainanaccessibleintermodalpassengerandfreightnetworkwithtransportationhubstofacilitateaccesstourbanandruraldestinationswhilemaintaininganefficientandbalancedtransportationsystem.ActionStrategiesIdentifymajortransportationterminals,facilities,routes,andcorridorsthatconnectpassengerandfreightmovementswithotherintermodalfacilities.Developanintermodalplanoutliningtheregion’sstrategiestodealwithanyconstraintstoincreasingintermodalism.Recognizetheabilityofeachmodetoenhancetheefficiencyofothermodes.Explorethepossibilityofothermodescontributingtotheoverallefficiencyofthenetworksuchaswaterwaysandrail.Encouragethedevelopmentorexpansionofefficientfreightandpassengerintermodalfacilitiesthatexpeditetransfersbetweenmodes,routes,andcarriers.Workwithlocaljurisdictionstodevelopandpromoteregionalintermodalfacilitiestoavoidduplicationofservices.Policy18–TransportationandEconomicsItisthepolicyofBFCGtoacknowledgeandpromotetransportationashavingafundamentalroleingrowingandmaintainingahealthyandstrongregionaleconomy.

Page 37: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page31

ActionStrategiesSupporttransportationprojectsthatprovideservicefornew,expandingorexistingindustry/businessesintheregion.Acknowledgetheextensivediversityofcommercewithintheregion.Encourageandsupporttransportationinfrastructureimprovementsandexpansionprojectsthateliminatecongestionpointsandsupportastrongeconomythroughpromotionofeconomicdevelopmentandincreasedemploymentopportunities.Supportimprovementstofreightroutesinordertomoveproductsandcommoditiesinandoutoftheregionforeconomicgrowthaswellastheemploymentstabilitycreatedbytheactivity.Supporttransiteffortstoserveemploymentcentersanddeveloppark&ridelots.Recognizehowprojectsmayimpacttherecreationandtourismtrade.ContinuesupportforthedevelopmentandfundingofastatewideAllWeatherRoad(AWR)systemthatallowsfortheyear‐roundmovementofagriculturalproducts,consequentlystrengtheningtheruraleconomy.Policy19–MaintenanceandPreservationItisthepolicyoftheBFCGtopromotethemaintenanceandpreservationoftheexistingregionalmulti‐modaltransportationsystem.ActionStrategiesRecognize both a federal and state emphasis onmaintaining a safe and efficient existing systemratherthanbuildingadditionalcapacity.Encourageschedulingofmaintenanceandpreservationthatwillachievelowestlife‐cyclecosts.Promotedetailed inventoriesandanalysisof transportationsystems;understanding thisexercisecantakeavarietyofformsthatmayormaynotincludeadvancedcomputertechnologies.Encourage discussions regarding the funding challenges for preservation of the existing multi‐modalsystem.(FromtheBFCG2011‐2032RegionalTransportationPlan,ChapterThree)

Page 38: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page32 Benton‐FranklinCouncilofGovernments

CHAPTERSEVEN–MODELRESULTSANDMETROPLITANTRANSPORTATIONSYSTEMEVALUATION

MODELRESULTS&TRANSPORTATIONSYSTEMEVALUATION

INTRODUCTIONAfterthemodeliscalibratedtoexistingtrafficvolumes,itisthenpossibletoevaluatewhateffectsplannedroadprojectsandgrowthpatternswillhaveupontheroadnetwork.Thisisachievedbyusingprojectedlandusedatacoupledwithroadimprovementsplannedbylocaljurisdictions.Aswithallmodels,theyareatooltoevaluatetheimpactsoffuturechange.Itisimportanttorecognizethestrengthofaregionalmodelisintheevaluationofcorridor‐basedvolumesandregionaltrends.Attentionshouldbegiventothosecorridorsthatshowmultiplepointsofcongestion,ratherthansinglesegments.Specificspotforecastsandevaluationarebetterlefttomicro‐levelevaluationthroughothermeans.ThemodelreplicatestrafficpatternsduringatypicalweekdayPMpeak‐houroftravelforthescenarioyear.Forecastvolumesaremeanttoillustratetrendsandnotabsoluteflows.Itisimportanttorememberthatwhilethemodeliscalibratedwelltoregionalvolumes,theremaybesomeareasofcongestionwhichmaynotappearinmodelresults.Conversely,theremaybesomelocationswherethemodelmayreflectcongestedconditionswherenoneexist.Additionally,theremaybeareaswherecongestionisprominentduringadifferentperiodofday,thanthePMpeak‐hour.Intheseinstances,BFCGstaffandlocaljurisdictionshavereviewedresultsandhaveseparatelylistedknownareasofconcernthatmaynototherwiseappearintheevaluation.PORTRAYINGCONGESTION/LEVELOFSERVICEThemodelingpackagecanportrayresultsinavarietyofmeasures‐somelendingthemselveswelltowrittendiscussionsregardingcongestion,andothersthatdonot.Onemeasurewidelyunderstoodthatlendsitselfwelltovisualportrayalofresultsisusingprojectedvolumesagainstthecapacityofaroadway.ThischapterwillrelyonVolumetoCapacity(V/C)ratiosforthepurposesofdiscussionregardingpotentialcongestion.Inthesimplestterms,aroadsegmentwithlittleornovolumewouldhaveaV/Crationearzero,whileasegmentoperatingatits’statedcapacitywouldhaveaV/Cratioequaltoone.Asageneralrule,V/Cratiosinexcessof.85indicatecongestionislikelyuponthatsegment.V/Cratiosareshownthrougharangeofcolors,beginningwithgreentonesnearzeroescalatingtoyellowtonesuptoaV/Cequalto.85.SegmentswithaV/Cinexcessof.85areconsideredcongestedandshadedinpinkforemphasis.ProjectedPMpeak‐hourvolumesuponeachroadsegmentareshownbothbyagraduatedlinethicknessandalsonumericallyabovetheroadways.Figure7‐1belowprovidesamodelimageportrayingV/Cratios,withvolumesreflectedbythicknessoflineandlabelsuponeachsegment.This(2010calibration)exampleshowsSR395BlueBridgesouthboundhavingaV/Cinthe.75‐1.00range,withthenorthboundV/Cratiointhe.50‐.75range.V/Cratiosinexcessof.85areevidentuponsegmentsofYelmandBentonStreetsinKennewick.LevelofService(LOS)isawidelyusedterminevaluationoftransportationfacilities.LevelofServicecanbemeasuredatintersectionsandalongroadwaysegments,withascalesimilartoareportcardwhereAisfavorableandFisundesirable.Withintheurbanarea,memberjurisdictionshaveadoptedLOSDasbeingacceptable.LOScalculationsatintersectionsvarydependinguponthetypeofintersectioncontrol(stoporsignal),whetherallapproachesarecontrolled,andthedelaysassociatedwiththosecontrols.LOScalculationsuponroadsegmentsvaryaswell,dependentuponavarietyoffactorsincluding:roadwayclass,segmentspeed,frequencyofaccesspoints,presence

Page 39: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page33

ofpedestrians/bicyclists,turnlanes,andterrain.WhileneitherintersectionnorroadwayLOScalculationsarefeasibletocompleteattheregionallevel,V/Cratiosdoprovideacontextthatcanbecomparable.Forinstance,aV/Cequalto.85orabovewouldbeindicativeofanLOSEorF.2010BASE‐YEARRESULTSThebaseyearforthemodelwas2010andcloselyreflectsthetrafficvolumes,astheyexistedduringthePMpeak‐hourofatypicalweekdaythatyear.Thebase‐yearscenarioistypicallyusedasacontroltoensurethemodeliscalibratedtoactualtrafficcounts–ascongestionisevidenttoalldriverswhoexperienceconditionsuponthelocalroadways.AreasthatresultinV/Cratiosinexcessof.85(indicatingcongestion)duringthebase‐yearwere:

SR240eastboundbetweenRoute10andStevensDrive GeorgeWashingtonWaynearI‐182 SR240eastboundtoI‐182westbound(nearAaronheadedtowardQueensgate) GageBlvdeastbound,eastofSteptoe YelmStreetatIntersectionswithSR395andKennewickAve SR395southboundrampmovementsbetweenSR397I/CandCourtStI/C I‐182eastboundramptoRd100 Road100betweenSandifurandI‐182I/C Road68northboundnorthofI‐182I/C

ThegreatestvolumestravelupontheSR240,I‐182,andSR395corridorsthatstretchthroughouttheTri‐Cityarea.Congestionismostlylimitedtoareassurroundingthesestateroutesandtheirconnectiontolocalarterials.Delaysatsignalizedintersectionsresultinthepredominanceofdelaysupontheseroutes.OTHEROPERATIONALCONCERNSNOTIDENTIFIEDBYMODELThereinvariablyarelocationsinallmodelswhoseactualconditionsarenotreflectedwellwithinthemodel.BFCGstaffandlocaljurisdictionshavereviewedthemodelfindings,andhaveidentifiedlocationswherevolumesarehigherthanportrayedbythemodel,orotherwiserealizedasbeingcongestedbaseduponotherconditions.Identificationoftheselocationsisimportantwhenconsideringthebase‐yearmodel,becauselocationsthatappearlowwithinthecalibratedmodelarelikelytomodelsimilarlyinfuturescenarios.Thefollowinglocationshavebeenidentifiedasareasofcongestionwherethemodelresultsdonotadequatelyportrayexistingconditions:

SR240“Bypass”–delaysatsixsignalizedintersectionsonroute SR395,HildebrandttoYelm–delaysatsevensignalizedintersectionsalongroute I‐182InterchangesatRoad100andRoad68‐rampdelaysaccessinglocalarterials ClearwaterBlvd.‐EdisonSt.toSR395 SR397(AinsworthAve)‐4thAveto10thAvewestbound

OPERATIONALCONCERNSFORAMPEAK‐HOURThereareseverallocationsinthemodelareathathaveoperationsproblemsduringthemorningcommute,orotherperiodsoutsidethePMpeak‐hour.WiththemodelfocusuponthePMpeak‐hour,andthepredominanttravelpatternsinthearea,theselocationsarelikelytonotappearwithinthemodelresults.BFCGstaff,withthehelpofWSDOTandthelocaljurisdictions,hascompiledthefollowinglisttoidentifytheselocations.

SR240westboundramptoI‐182westbound SR240“Bypass”–delaysatsixsignalizedintersectiononroute

Page 40: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page34 Benton‐FranklinCouncilofGovernments

Queensgate–eastboundaccesstoI‐182eastbound ColumbiaCenterBlvd–northboundaccesstoSR240westbound Burden/Road68accessingI‐182westbound I‐182eastboundofframptoSR240northbound At‐graderailroadcrossingsonLeslie,Edison,WashingtonSt./Fruitland,SR397

(FromtheBFCG2011‐2032RegionalTransportationPlan,Chapter7,pages7‐1to7‐4)

Page 41: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page35

CHAPTERTEN‐PLANIMPLEMENTATIONPERFORMANCEMEASUREMENTMonitoringtheperformanceoftheregionaltransportationsysteminvolvesthemeasurementofchangesinspecificfactorsovertime.“TransportationTrendsandKeyFacts”releasedbyBFCGin2010summarizesdataonmultipleaspectsofboththemetropolitanandregionaltransportationsystemsovertime.ThereportpresentsdataintheareasofGrowingTravelDemand,TransportationSystemandTransportationImpacts.TheTransportationTrendsreportisavailableontheBFCGwebsiteat:http://www.bfcog.us/transportation.html.Trackingchangesregion‐wideprovidesinformationtolocalandregionalpolicymakersandeducatesinterestedcitizens.Feedbackfromperformancemonitoringcanleadtoprogramandgoalmodification,moreintensiveevaluationofspecificfactors,changesinthetypesofdatacollected,orimprovementstothetransportationsystem.PerformanceMeasuresTwopotentialhighwaysystemperformancemeasuresarereviewedbelow.Additionalaspectsoftheregionaltransportationsystemtopicsormodesthatmaybetrackedarealsodiscussed.SystemperformancemeasureswillbeevaluatedandincorporatedintosubsequentRTPupdates.TheperformancemonitoringoftheRTPwillbecompletedandreportedasapartofthebiennialRTPreview.HighwayPerformanceMeasuresThesedataaregenerallyusedtoassessstreetcapacitydeficiencies.Nosinglemeasurecanprovideacompleteassessmentofthetransportationsystem.Eachanalyticaltechniquemeasuresadifferentperformancelevel.Astreetsegmentorintersectionthatisperformingpoorlyusingonemeasuremayfunctionadequatelyaccordingtoothercriteria.Eachmeasureindicatesadifferentrangeofresponsesthatcouldaddresstroubleareasidentifiedintheanalysis.Currently,dataavailablefortrackingroadsystemperformanceincludes:TrafficVolumesTrafficvolumesareprimarilyusefulforensuringthatroadwayimprovementsareadequatetoaddressthedemandsofpeaktravelperiods.Trafficvolumesareoneofmanydatainputsoftheregionaltransportationmodelandareusedtoprojecttheregion’stravelbehaviorandtheefficiencyofroadwaysegments.VehicleMilesTraveledThenumberofvehiclemilestraveled(VMT)inaregionrevealsarelationshipbetweenlanduseandthetransportationsystem.AverageVMTpervehicletripisoftenusedtocalculategenerallyhowfarmotoristscommutebetweenhomeandwork.The2010Tri‐Citiestrafficmodelprovidestheabilitytoextractvehiclemilestraveledoncriticalsegmentsofthemetropolitanstreetandhighwaysystem.RevisionofthemetropolitanareamodeleveryfiveyearsforRegionalTransportationPlanupdatesaffordstheopportunitytotrackchangesinvehiclemilestraveledinthemodelarea.

Page 42: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page36 Benton‐FranklinCouncilofGovernments

Level‐of‐ServiceTypically,performancestandardsthatmeasuretrafficcongestionarepresentedinthecontextoflevel‐of‐service(LOS)measures.Thesearemeasuresofobservedtrafficvolumecomparedwithcapacityalongroadwaysegmentsandameasureofdelayatintersectionsandramps.DatarequirementsforcalculatingtheLOSofarterialsincludeexistingstreetcapacity,trafficvolumes,andtraveltime.JurisdictionstypicallyadoptLOSCinruralareasandLOSDinurbanareas.AdditionalTransportationSystemMeasurementsStreetsandhighwaysareasignificantcomponentofthetransportationsystemintheRTPO,butadditionalelementscouldbemeasured.Someofthesearelistedbelow.SeasonalWeightRestrictionsSeasonalweightrestrictionsonruralcountyfreightandgoodsroutesarediscussedinChapterTwoasaregionaltransportationissueorconcern.Duringspringfreeze/thawcyclesthosefreightandgoodsroutesnotadequatelysurfacedcansufferdamageifweightrestrictionsarenotimposed.Trackingprogresstowardall‐weathersurfacingthoseroutesisaneasilyattainableperformancemeasure.PublicTransportationThedatarequiredtomeasuretheeffectivenessofpublictransportationincludesridershiptrendsandtheprovisionofservicetotransitdependentcitizens.Thesedatarequirementsshouldbeequaltoorexceedbaselinecalculations.BenFranklinTransitandValleyTransitmaintainrecordsonridershiptrendsandprovisionofservices.FreightTransportationPerformanceMeasuresFreighttransportationisveryimportanttotheeconomicvitalityofthisagriculturalregion.Aneffectivefreightsystemrequiresswiftandeconomicaltransport.Thedatarequiredtomeasuretheneedsandeffectivenessofthefreighttransportationsystemincludesanestimateoftheamountoffreighttransportedandadeterminationofdeficienciestoincludetravelroutes,frequencyoftransport,timeoftransports,andotherconstraints.FreighttonnagewascollectedfortheFreightandGoodsTransportationSystem(FGTS),whichcategorizedroadwaysbasedonthelevelofannualfreighttonnageinordertoidentifyroadsegments,whichplayasignificantroleinmovementofgoodsinthestate.Otherdatawillneedtobecollectedtoestablishbaselinerecords.AirTransportationPerformanceMeasuresTheRTPencouragesairtransportationofpeopleandfreightbyminimizingtheimpactofsurroundingdevelopmentonairportoperations.Datarequiredtomeasureairtransportationincludetheamountoffreightandpassengerstransportedandadeterminationofdeficienciestoincludeprovisionofservicedemandandfrequency.Aperformancestandardforthesedatacouldbetonotdecreasebelowthebaselinelevel.BoththePortofPasco(Tri‐CitiesAirport)andthePortofWallaWalla(WallaWallaRegionalAirport)collectannualfreightandpassengerstatistics.RailTransportationPerformanceMeasuresRailservicesintheRTPOregionareveryimportanttothetransportoffreightandpassengers.Datarequirementsformeasuringtheeffectivenessoftherailsystemincludetheamountoffreighttransportedandthenumberofpassengersserved.Dataonraildeficienciesshouldalsoincludethenumberofcrossings,theamountoflinetrackageincompliancewithstandards,andfrequencyofservice.Theperformancestandardsforthedatarequiredareitsbaselinemeasurements.Baselinedatawillneedtobegathered.

Page 43: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page37

Non‐MotorizedTransportationPerformanceMeasuresThenon‐motorizedtransportationsystemcomponentincludescommuterandrecreationalbikeroutesandpedestriansidewalksandpathways.Emphasisisgiveninourcitiesandtownstoprovidingsidewalksalongallarterialsandschoolroutesandtoconnectingparksandresidentialareaswithbicycleandpedestrianpathswheneverpossible.Thedatarequiredtomeasurethenon‐motorizedsystemmayincludepedestrianandbicycleusageoftheexistingtrailsystem,non‐motorizedtravelpatterns,theexistingconnectionsbetweenpathsandparksorresidentialareas,sidewalklocations,andthenumberofimprovementsmadetotheexistingpedestriansystemtomeetADArequirements.Theperformancestandardsforthesefacilitiescouldbetoexceedbaselinelevels.Thebaselinemeasurementforsidewalksincludeslocatingthemonallarterialsandschoolroutes.Baselinedataisnotavailableandwouldhavetobegatheredforthissystemcomponent.Multi‐ModalTransportationSystemIncreasedintegrationoftransportationmodesintheregionaltransportationsystemcanresultinmoreefficientuseofexistinginfrastructureandprograms.Multi‐modalperformancemeasurescouldbedeterminedbyhouseholdtravelsurveysindicatingthepercentageoftripstakenbyalternativetransportationmodestothesingle‐occupantvehicle.IntermodalTransportationschemeThenumberofinter‐modalconnectionsintheregion,andthemodesplitbetweenthetransportationoffreightbytruck,rail,barge,orair.Theperformancestandardforthenumberofinter‐modalconnectionsandmodalsplitbetweentruck,barge,andrailintheregioncouldbetoremainatorexceedthebaselinecalculation.CoordinationTheeffectivenessofcoordinationeffortsbetweenRTPOmembers,systemstakeholders,andotherinterestgroupsandcitizensisdifficulttoevaluate.However,qualitativedatacanbegatheredbysurveyingpersonstoassessopinionsandevaluatecoordinationrelatedaccomplishments.Theperformancestandardcouldbeanoveralladequacyratingofregionaltransportationplanningcoordination.Thereiscurrentlynobaselinemeasurementofthisrating.(FromtheBFCG2011‐2032RegionalTransportationPlan,Chapter10,pages10‐4to10‐6)

Page 44: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page38 Benton‐FranklinCouncilofGovernments

CHAPTERTEN‐REGIONALTRANSPORTATIONSTRATEGIES

Regionaltransportationstrategiesareusedtoimplementtheregionalgrowthstrategydiscussedabove.Thestrategiesidentifyandaddressalternativetransportationmodeswithintheregion,enhanceindividualtransportationmodesaswellasinter‐modalconnectionsand,asappropriate,promotetransportationdemandmanagement.Countywideplanningpoliciesandpoliciesfromlocalcomprehensiveplansthatareregionalinscopeandregionallyconsistentprovidethebasisfortheregionaltransportationstrategies. Meetthetransportationinfrastructureneedsoftheregion’smajorsourcesofeconomic

growthandvitality.Projectsthatmeetthisconditionareimprovementsthatdirectlyfacilitatethemovementofgoodsorpeopleinamannerthatprovidesanetbenefittotheregionasawhole.Thiswouldincludetheimprovementoftherecreationalroadwaysystemtoattractvisitorsfromoutsidetheregion;theimprovementoftheportionsofthehaulroadsystemandaccesstowaterports,railheads,andairports.Developmentofthesecomponentsoftheroadwaysystemfacilitatesmovementthatgeneratesincomefortheregion’sprincipalindustriesandcontributestoregionaldevelopment.

Supportthecoordinationoflanduseandtransportationdecisions.

Thereareportionsoftheregionwhichareundergoingsignificantdevelopmentwithregardtolanduse.ChaptersSixandSevenhavedescribedtheseinsomedetail.Projectsthatsupportoraccommodatelandusedevelopmentintheseareasmeetthiscondition.

Improvemulti‐jurisdictionalcoordinationtoavoidtransportationsystemdeficiencies.

Thisappliestosituationswhereaprojectrequiresinvolvementofeithermorethanonelevelofgovernment,adjacentgovernmentaljurisdictions,oragreementsbetweenpublicandprivatesectorentities.Inthecaseofallthesepartnerships,theadministrativeoversight,financing,andotheraspectsofprojectdevelopmentcanbesharedandmakeaproductiveoutcomemorelikely.

Promoteefficientmultimodaltransportationsystemsandconnections.

Projectsshouldevaluateandaddresstheneedsofallformsoftransportation,includingpublictransit,pedestriansandbicyclists.Multimodalconnectionsshouldbereadilyaccessible,convenientandprovidesmoothtransitionsbetweenmodes.

Promoteeffectiveintermodaltransportationsystemsandconnections.Opportunitiesforintermodalfacilitiesarefew.Existingfacilitiesshouldbemaintainedandthedevelopmentofnewintermodalfacilitiesencouraged.RailexandthePortofPascoBigPascofacilityareexamples.

EnsuresufficientrailandroadaccesstotheSnakeandColumbiaRiverportfacilities

andensuresufficientinfrastructure(i.e.bargeslips,docks,andstoragefacilities)atthoseports.BargetransportationontheSnake/ColumbiaRiversystemisvitaltotheeconomyoftheregion,thestate,andtheentirenorthwest.Withoutthatcompetitiveoption,thecostsoftransportingbyrailortruckwouldsurelyincrease.Furthermore,massiverailandroadcapacityimprovementswouldbeneededtomovethosecommoditiesnowshippedbybarge.

Page 45: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page39

ActivelysupporttheUSArmyCorpsofEngineers(COE)intheireffortstomaintain

adequatedepthinthelowerColumbiaRivershipchannelAlso,supporttheCOE’songoingeffortstodredgeandmaintainsufficientclearanceforbargetrafficontheSnakeRiverfromtheLewiston/ClarkstonareatotheColumbiaRiverneartheTri‐Cities.Asstatedabove,shipmentoffreightbybargeisasignificantcomponentoftotalfreighttrafficforgoodstravelingfromtheRTPOtothecoast.InternationalshippingisvitaltoWashington’scontinuedeconomicgrowth.Continuedviabilityoftheriversthemselvesiscriticaltosuccessfulmaintenanceofthisfreightmode.

Promoteinnovativefinancingstrategies.Decreasedtransportationrevenuesmakeitimperativethatinnovativefinancingstrategiesbeutilizedtogetthemostpossiblebenefitfromavailablefunds.Innovativefinancingstrategiescaninvolvepartneringbetweenjurisdictionsandmayalsoincludetheprivatesector.

(FromtheBFCG2011‐2032RegionalTransportationPlan,Chapter10,pages10‐2to10‐4)

Page 46: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page40 Benton‐FranklinCouncilofGovernments

Page 47: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page41

APPENDIXCCMPCorridorTrackingMatrix

Page 48: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page42 Benton‐FranklinCouncilofGovernments

InSeptember2013,FHWAstaffmetwithBFCGstafftoreviewthestatusofTMAimplementation.At themeeting,aCorridorTrackingMatrixwasdescribed. Its importanceasa trackingtool tobeusedtopresentachronologyoftheprogressoftheCMPimplementationwasemphasized.FHWAstaffsuggestedinclusionofanexistingimprovementtouseasanexampleofimplementingthematrix.RichlandandKennewickhaveprovidedexamplesforthatpurpose.

Page 49: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page43

CORRIDOR DATA PERFORMANCEMEASURE STRATEGIES

KeeneRoadWidening

RegionalModelprojectedtrafficvolumesgreaterthanexistingtrafficlanescouldaccommodate

TrafficCounts;RegionalModelupdates AdditionalLanes;SignalizedIntersections;AccessControl

ColumbiaCenterBoulevard‐ClearwaterAvenuetoWillametteAvenue

Counts(onSteptoeStreetandColumbiaCenter),RegionalModelprojectionsshowingneedforcapacityimprovement

LOS,TravelTimeandTravelTimeReliability,Counts(todeterminetrafficreductionsasaresultofSteptoeStreet)

Signalphasingandcrosswalkchanges.Lanereconfigurationsandlaneadditions.Constructionofalternateparallelroute(SteptoeStreet).Removalofat‐graderailcrossingbetweenClearwater&Deschutes

QueensgateDrive:KeeneRoadtoDuportailStreetTrafficcountsandtraveltimedatawillbecollectedandanalyzed.

GeorgeWashingtonWay:ColumbiaPointDrivetoHornRapidsRoad

Asegmentofthiscorridorwasidentifiedinthe2011MTPashavingav/cgreaterthan.85.

Trafficcountsandtraveltimedatawillbecollectedandanalyzed.

StevensDrive:SR240toHornRapidsRoadTrafficcountsandtraveltimedatawillbecollectedandanalyzed.

ColumbiaCenterBoulevard(CCB):ClearwaterAvenuetoWillametteAvenue

Trafficcountsandtraveltimedatawillbecollectedandanalyzed.

ClearwaterAvenue:US395toKelloggStreetTrafficcountsandtraveltimedatawillbecollectedandanalyzed.

Road68:ChapelHillBoulevardtoSandifurParkwayAsegmentofthiscorridorwasidentifiedinthe2011MTPashavingav/cgreaterthan.85.

Trafficcountsandtraveltimedatawillbecollectedandanalyzed.

Road100:ChapelHillBlvd.toSandifurParkwayAsegmentofthiscorridorwasidentifiedinthe2011MTPashavingav/cgreaterthan.85.

Trafficcountsandtraveltimedatawillbecollectedandanalyzed.

CourtStreet:Road40to20thAvenueTrafficcountsandtraveltimedatawillbecollectedandanalyzed.

20thAvenue:LewisStreettoArgentRoadTrafficcountsandtraveltimedatawillbecollectedandanalyzed.

SR240:Milepost20.48(Route10)toMilepost28.84(StevensDrive)

Asegmentofthiscorridorwasidentifiedinthe2011MTPashavingav/cgreaterthan.85.

Trafficcountsandtraveltimedatawillbecollectedandanalyzed.

SR240:Milepost30.63(JadwinAvenue)toMilepost34.57(SR182offramp)

Trafficcountsandtraveltimedatawillbecollectedandanalyzed.

SR182:Milepost.87(DallasRd)toMilepost4.40(I‐182westboundon‐rampfromGeorgeWashingtonWaysouthbound)

Asegmentofthiscorridorwasidentifiedinthe2011MTPashavingav/cgreaterthan.85.

Trafficcountsandtraveltimedatawillbecollectedandanalyzed.

HistoricalProjectExample:CityofRichland

HistoricalProjectExample:CityofKennewick

Page 50: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page44 Benton‐FranklinCouncilofGovernments

CORRIDOR SOLUTION IMPLEMENTATION ASSESSMENT

KeeneRoadWidening

Addedadditionallaneseachdirection;Installedsignalizedintersections;establishedaccesscontrollimitingtheamountofdriveways

Corridorwaswidenedin3phaseswiththefinalphasecompletedin2012.

Currenttrafficcountsandmodelingindicatethiscorridorisoperatingwithanacceptablelevelofservice

ColumbiaCenterBoulevard‐ClearwaterAvenuetoWillametteAvenue

Allitemsin"Strategies"between2004andpresent.

At‐graderailcrossingremovalandaddedtravellanesbetweenClearwaterandDeschutesin2004‐2005,FlashingYellowArrow,allowingoptimalphasingandcoordinationsolutionsin2005‐2006.LanechangesatQuinault&Grandridgein2006and2011respectively.Crosswalkchangesin2012.AdditionofSteptoeStreetparallelroutein2013.

Increasedtraveltimereliabilityduetoremovalofat‐graderailcrossing.Reducedtraveltimesasaresultofimprovedphasingandsignalcoordination.Reduceddelayonsidestreetsatsomelocationsduetolaneconfigurationchangesandphasingefficiencies.13%reductioninAverageDailyTrafficonColumbiaCenterBoulevardbetweenDeschutesandClearwaterwithanticipatedreducedtraveltimesandcongestionthatgoalongwithit.

QueensgateDrive:KeeneRoadtoDuportailStreet

GeorgeWashingtonWay:ColumbiaPointDrivetoHornRapidsRoad

StevensDrive:SR240toHornRapidsRoad

ColumbiaCenterBoulevard(CCB):ClearwaterAvenuetoWillametteAvenue

ClearwaterAvenue:US395toKelloggStreet

Road68:ChapelHillBoulevardtoSandifurParkway

Road100:ChapelHillBlvd.toSandifurParkway

CourtStreet:Road40to20thAvenue

20thAvenue:LewisStreettoArgentRoad

SR240:Milepost20.48(Route10)toMilepost28.84(StevensDrive)

SR240:Milepost30.63(JadwinAvenue)toMilepost34.57(SR182offramp)

SR182:Milepost.87(DallasRd)toMilepost4.40(I‐182westboundon‐rampfromGeorgeWashingtonWaysouthbound)

HistoricalProjectExample:CityofRichland

HistoricalProjectExample:CityofKennewick

Page 51: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page45

APPENDIXDCongestedCorridorData

Page 52: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page46 Benton‐FranklinCouncilofGovernments

This appendixwill be comprisedof separate sectionson each corridor.Each sectionwill containmaps(collisionsandinjuries,signalization, landuse,etc.)anddataspecific toeachcorridor. Thelevelofdetailofinformationoneachcorridorwillbeaugmentedovertime.

CMPCONGESTEDCORRIDORS

RICHLANDCONGESTEDCORRIDORSQueensgateDrive:KeeneRoadtoDuportailStreetGeorgeWashingtonWay:ColumbiaPointDrivetoHornRapidsRoadStevensDrive:SR240toHornRapidsRoad

KENNEWICKCONGESTEDCORRIDORSColumbiaCenterBoulevard(CCB):ClearwaterAvenuetoWillametteAvenueClearwaterAvenue:US395toKelloggStreet

PASCOCONGESTEDCORRIDORSRoad68:ChapelHillBoulevardtoSandifurParkwayRoad100:ChapelHillBoulevardtoSandifurParkwayCourtStreet:Road40to20thAvenue20thAvenue:LewisStreettoArgentRoad

WSDOTCONGESTEDCORRIDORSSR240:Milepost20.48(Route10)toMilepost28.84(StevensDrive)SR240:Milepost30.63(JadwinAvenue)toMilepost34.57(SR182offramp)SR182:Milepost.87(DallasRd)toMilepost4.40(I‐182westboundon‐rampfromGeorge

Washington Way southbound)

Page 53: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page47

QueensgateDriveCharacteristicsoftheCorridorExtent:KeeneRoadtoDuportailStreetLength:0.84milesFunctionalClassification:MinorArterialTransitRoutes:39K,39HW,110

Page 54: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page48 Benton‐FranklinCouncilofGovernments

Page 55: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page49

Page 56: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page50 Benton‐FranklinCouncilofGovernments

QueensgateDriveCollisionData

I/SMid‐Block TOTAL I/S

Mid‐Block TOTAL I/S

Mid‐Block TOTAL

2010 2010 2010 2011 2011 2011 2012 2012 2012

Injuries&FatalitiesSummary

TotalFatalities 0 0 0 0 0 0 0 0 0

TotalInjuries 0 1 1 4 6 10 5 0 5

PedestrianInjuries 0 0 0 0 0 0 0 0 0

PedestrianFatalities 0 0 0 0 0 0 0 0 0

BicyclistInjuries 0 0 0 0 0 0 0 0 0

BicyclistFatalities 0 0 0 0 0 0 0 0 0

NatureofCollisions

Rear‐End 0 2 2 2 2 4 0 0 0

TurningMovement 1 0 1 1 1 2 5 1 6

AngleorSideSwipe 0 0 0 0 2 2 0 4 4

FixedObject 0 0 0 2 1 3 0 0 0

BackingUp 0 0 0 0 0 0 0 0 0

Bicyclist 0 0 0 0 0 0 0 0 0

Pedestrian 0 0 0 0 0 0 0 0 0

ParkedMotorVehicle 0 0 0 0 0 0 0 0 0

Overturn 0 0 0 0 0 0 0 0 0

Total 1 2 3 5 6 11 5 5 10Source:WSDOTStatewideTravelandCollisionDataOffice

Page 57: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page51

GeorgeWashingtonWayCharacteristicsoftheCorridorExtent:ColumbiaPointDrivetoHornRapidsRoadLength:6.07milesFunctionalClassification:PrincipalArterialTransitRoutes:23,26,27,120,225

Page 58: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page52 Benton‐FranklinCouncilofGovernments

Page 59: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page53

Page 60: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page54 Benton‐FranklinCouncilofGovernments

GeorgeWashingtonWayCollisionData I/S Mid‐Block TOTAL I/S Mid‐Block TOTAL I/S Mid‐Block TOTAL

2010 2010 2010 2011 2011 2011 2012 2012 2012

Injuries&FatalitiesSummary

TotalFatalities 0 0 0 0 0 0 0 0 0

TotalInjuries 29 18 47 35 18 53 23 9 32

PedestrianInjuries 0 0 0 1 1 1 0 1

PedestrianFatalities 0 0 0 0 0 0 0 0 0

BicyclistInjuries 4 1 5 4 0 4 2 1 3

BicyclistFatalities 0 0 0 0 0 0 0 0 0

NatureofCrashes

Rear‐End 26 33 59 21 19 40 29 18 47

TurningMovement 11 3 14 15 4 19 15 4 19

AngleorSideSwipe 24 9 33 20 9 29 15 8 23

FixedObject 1 1 2 2 3 5 2 0 2

BackingUp 0 0 0 0 0 0 0 0 0

Bicyclist 1 1 2 4 0 4 1 1 2

Pedestrian 4 0 4 1 0 1 1 0 1

ParkedMotorVehicle 0 0 0 0 0 0 0 0 0

Overturn 0 0 0 0 0 0 0 0 0

Miscellaneous 0 0 0 0 0 0 0 1 1

Total 67 47 63 35 63 32 Source:WSDOTStatewideTravelandCollisionDataOffice

Page 61: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page55

StevensDriveCharacteristicsoftheCorridorExtent:SR240toHornRapidsRoadLength:2.93milesFunctionalClassification:PrincipalArterialTransitRoutes:23,27

Page 62: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page56 Benton‐FranklinCouncilofGovernments

Page 63: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page57

Page 64: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page58 Benton‐FranklinCouncilofGovernments

StevensDriveCollisionData

I/SMid‐Block TOTAL I/S

Mid‐Block TOTAL I/S

Mid‐Block TOTAL

2010 2010 2010 2011 2011 2011 2012 2012 2012

Injuries&FatalitiesSummary

TotalFatalities 0 0 0 0 0 0 0 0 0

TotalInjuries 1 3 4 8 3 11 0 2 2

PedestrianInjuries 0 0 0 0 0 0 0 0 0

PedestrianFatalities 0 0 0 0 0 0 0 0 0

BicyclistInjuries 0 0 0 0 0 0 0 1 1

BicyclistFatalities 0 0 0 0 0 0 0 0 0

NatureofCollisions

Rear‐End 2 1 3 6 1 7 0 0 0

TurningMovement 0 0 0 2 0 2 0 0 0

AngleorSideSwipe 1 1 2 2 4 6 1 1 2

FixedObject 1 4 5 0 2 2 0 3 3

BackingUp 0 0 0 0 0 0 0 0 0

Bicyclist 0 0 0 0 0 0 0 1 1

Pedestrian 0 0 0 0 0 0 0 0 0

ParkedMotorVehicle 0 0 0 0 0 0 0 0 0

Overturn 0 0 0 0 1 1 0 0 0

Miscellaneous 0 1 1 0 1 18 0

Total 4 7 11 10 9 36 1 5 6Source:WSDOTStatewideTravelandCollisionDataOffice

Page 65: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page59

ColumbiaCenterBoulevardCharacteristicsoftheCorridorExtent:ClearwaterAvenuetoWillametteAvenueLength:1.26milesFunctionalClassification:PrincipalArterialTransitRoutes:110,39,39K,42,48,50

Page 66: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page60 Benton‐FranklinCouncilofGovernments

Page 67: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page61

Page 68: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page62 Benton‐FranklinCouncilofGovernments

ColumbiaCenterBoulevardCollisionData

I/SMid‐Block TOTAL I/S

Mid‐Block TOTAL I/S

Mid‐Block TOTAL

2010 2010 2010 2011 2011 2011 2012 2012 2012

Injuries&FatalitiesSummary

TotalFatalities 0 0 0 0 0 0 0 0 0

TotalInjuries 30 6 36 31 11 42 26 8 34

PedestrianInjuries 0 0 0 0 1 1 3 0 3

PedestrianFatalities 0 0 0 0 0 0 0 0 0

BicyclistInjuries 0 0 0 0 0 0 0 0 0

BicyclistFatalities 0 0 0 0 0 0 0 0 0

NatureofCollisions

Rear‐End 13 14 27 18 8 26 15 11 26

TurningMovement 30 2 32 27 5 32 29 2 31

AngleorSideSwipe 15 4 19 24 10 34 17 7 24

FixedObject 0 2 2 1 1 2 2 0 2

BackingUp 0 1 1 0 0 0 0 0 0

Bicyclist 0 0 0 0 0 0 0 0 0

Pedestrian 0 0 0 0 1 1 2 0 2ParkedMotorVehicle 0 0 0 0 0 0 0 0 0

Overturn 0 0 0 1 1 2 0 0 0

Miscellaneous 0 0 0 0 0 0 0 1 1

Total 58 23 81 71 26 97 65 21 86Source:WSDOTStatewideTravelandCollisionDataOffice

Page 69: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page63

ClearwaterAvenueCharacteristicsoftheCorridorExtent:US395toKelloggStreetLength:2.01milesFunctionalClassification:PrincipalArterialTransitRoutes:41,42,47,120,160

Page 70: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page64 Benton‐FranklinCouncilofGovernments

Page 71: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page65

Page 72: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page66 Benton‐FranklinCouncilofGovernments

Page 73: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page67

ClearwaterAvenueCollisionData

I/SMid‐Block TOTAL I/S

Mid‐Block TOTAL I/S

Mid‐Block TOTAL

2010 2010 2010 2011 2011 2011 2012 2012 2012

Injuries&FatalitiesSummary

TotalFatalities 0  0 0 0 0 0 0  0 0

TotalInjuries 25  35 60 17 24 41 25  30 55

PedestrianInjuries 2  1 3 2 1 3 1  1 2

PedestrianFatalities 0  0 0 0 0 0 0  0 0

BicyclistInjuries 0  0 0 1 0 1 1  2 3

BicyclistFatalities 0  0 0 0 0 0 0  0 0

NatureofCollisions

Rear‐End 16  25 41 13 28 41 19  31 50

TurningMovement 15  5 20 11 8 19 8  8 16

AngleorSideSwipe 22  20 42 22 21 43 18  16 34

FixedObject 4  2 6 0 2 2 2  3 5

BackingUp 0  0 0 0 0 0 0  0 0

Bicyclist 0  0 0 1 0 1 0  2 2

Pedestrian 1  1 2 1 1 2 0  0 0

ParkedMotorVehicle 0  0 0 0 0 0 0  0 0

Overturn 0  2 2 1 0 1 0  2 2

Miscellaneous 0  0 0 1 0 1 0  0 0

Total 58  55 113 50 60 110 47  62 109Source:WSDOTStatewideTravelandCollisionDataOffice

Page 74: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page68 Benton‐FranklinCouncilofGovernments

Road68CharacteristicsoftheCorridorExtent:ChapelHillBoulevardtoSandifurParkwayLength:1.17milesFunctionalClassification:MinorArterialTransitRoutes:67

Page 75: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page69

Page 76: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page70 Benton‐FranklinCouncilofGovernments

Page 77: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page71

Road68CollisionData I/S Mid‐Block TOTAL I/S Mid‐Block TOTAL I/S Mid‐Block TOTAL

2010 2010 2010 2011 2011 2011 2012 2012 2012

Injuries&Fatalities

TotalFatalities 0 0 0 0 0 0 0 0 0

TotalInjuries 14 4 18 23 5 28 30 5 35

PedestrianInjuries 0 0 0 0 0 0 0 0 0

PedestrianFatalities 0 0 0 0 0 0 0 0 0

BicyclistInjuries 0 0 0 0 0 0 0 0 0BicyclistFatalities 0 0 0 0 0 0 0 0 0

NatureofCollisions

Rear‐End 13 8 21 15 4 19 13 10 23

TurningMovement 7 2 9 11 6 17 9 3 12

AngleorSideSwipe 9 5 14 10 6 16 6 10 16

FixedObject 1 1 2 0 0 0 2 0 2

BackingUp 0 0 0 0 0 0 0 0 0

Bicyclist 0 0 0 0 0 0 0 0 0

Pedestrian 0 0 0 0 0 0 0 0 0

ParkedMotorVehicle 0 0 0 0 0 0 0 0 0

Overturn 0 0 0 0 0 0 0 0 0

Miscellaneous 0 0 0 0 0 0 0 0 0Source:WSDOTStatewideTravelandCollisionDataOffice

Page 78: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page72 Benton‐FranklinCouncilofGovernments

Road100CharacteristicsoftheCorridorExtent:ChapelHillBoulevardtoSandifurParkwayLength:0.57milesFunctionalClassification:MinorArterialTransitRoutes:66,67,225

Page 79: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page73

Page 80: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page74 Benton‐FranklinCouncilofGovernments

Page 81: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page75

Road100CollisionData

I/SMid‐Block TOTAL I/S

Mid‐Block TOTAL I/S

Mid‐Block TOTAL

2010 2010 2010 2011 2011 2011 2012 2012 2012

Injuries&Fatalities

TotalFatalities 0 0 0 0 0 0 0 0 0

TotalInjuries 1 0 1 4 1 5 4 0 4

PedestrianInjuries 0 0 0 2 0 2 0 0 0

PedestrianFatalities 0 0 0 0 0 0 0 0 0

BicyclistInjuries 0 0 0 0 0 0 0 0 0

BicyclistFatalities 0 0 0 0 0 0 0 0 0

NatureofCollisions

Rear‐End 0 0 0 0 1 1 1 1 2

TurningMovement 5 0 5 1 0 1 2 0 2

AngleorSideSwipe 2 0 2 1 0 1 0 1 1

FixedObject 0 0 0 1 0 1 2 0 2

BackingUp 0 0 0 0 0 0 0 0 0

Bicyclist 0 0 0 0 0 0 0 0 0

Pedestrian 0 0 0 1 0 1 0 0 0

ParkedMotorVehicle 0 0 0 0 0 0 0 0 0

Overturn 0 0 0 0 0 0 0 0 0

Miscellaneous 0 0 0 0 0 0 0 0 0

Total 7 0 7 4 1 5 5 2 7Source:WSDOTStatewideTravelandCollisionDataOffice

Page 82: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page76 Benton‐FranklinCouncilofGovernments

CourtStreet

CharacteristicsoftheCorridorExtent:Road40to20thAvenueLength:1.25milesFunctionalClassification:PrincipalArterialTransitRoutes:60,62,67,225

Page 83: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page77

Page 84: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page78 Benton‐FranklinCouncilofGovernments

Page 85: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page79

Page 86: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page80 Benton‐FranklinCouncilofGovernments

CourtStreetCollisionData

I/SMid‐Block TOTAL I/S

Mid‐Block TOTAL I/S

Mid‐Block TOTAL

2010 2010 2010 2011 2011 2011 2012 2012 2012

Injuries&Fatalities

TotalFatalities 0 0 0 0 0 0 0 0 0

TotalInjuries 18 10 28 18 3 21 23 7 30

PedestrianInjuries 0 0 0 0 0 0 2 5 7

PedestrianFatalities 0 0 0 0 0 0 0 0 0

BicyclistInjuries 0 0 0 1 0 1 0 0 0

BicyclistFatalities 0 0 0 0 0 0 0 0 0

NatureofCollisions

Rear‐End 8 7 15 9 6 15 14 2 16

TurningMovement 6 3 9 6 2 8 6 0 6

AngleorSideSwipe 10 11 21 11 7 18 18 10 28

FixedObject 1 6 7 2 2 4 2 3 5

BackingUp 0 0 0 0 0 0 0 0 0

Bicyclist 0 0 0 1 0 1 0 0 0

Pedestrian 0 0 0 0 0 0 2 4 6

ParkedMotorVehicle 0 0 0 0 0 0 0 0 0

Overturn 0 0 0 0 0 0 0 0 0

Miscellaneous 0 0 0 0 0 0 0 1 1

Total 25 27 52 29 17 46 42 20 62Source:WSDOTStatewideTravelandCollisionDataOffice

Page 87: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page81

20thAvenueCharacteristicsoftheCorridorExtent:LewisStreettoArgentRoadLength:1.83milesFunctionalClassification:PrincipalArterialTransitRoutes:60,62,64,65,160,225

Page 88: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page82 Benton‐FranklinCouncilofGovernments

Page 89: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page83

Page 90: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page84 Benton‐FranklinCouncilofGovernments

North20thAvenueCollisionData

I/SMid‐Block TOTAL I/S

Mid‐Block TOTAL I/S

Mid‐Block TOTAL

2010 2010 2010 2011 2011 2011 2012 2012 2012

Injuries&Fatalities

TotalFatalities 0 0 0 0 0 0 0 0 0

TotalInjuries 14 6 20 17 1 18 6 5 11

PedestrianInjuries 0 0 0 0 0 0 1 0 1

PedestrianFatalities 0 0 0 0 0 0 0 0 0

BicyclistInjuries 0 1 1 1 0 1 0 0 0

BicyclistFatalities 0 0 0 0 0 0 0 0 0

NatureofCollisions

Rear‐End 8 9 17 6 5 11 4 6 10

TurningMovement 8 0 8 5 0 5 3 3 6

AngleorSideSwipe 7 3 10 12 2 14 12 12 24

FixedObject 2 0 2 1 0 1 0 0 0

BackingUp 0 0 0 0 0 0 0 0 0

Bicyclist 0 1 1 1 0 1 0 0 0

Pedestrian 0 0 0 0 0 0 1 0 1

ParkedMotorVehicle 0 0 0 0 0 0 0 0 0

Overturn 0 0 0 1 0 1 1 0 1

Miscellaneous 0 0 0 0 0 0 0 0 0

Total 25 13 38 26 7 33 21 21 42Source:WSDOTStatewideTravelandCollisionDataOffice

Page 91: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page85

SR240

CharacteristicsoftheCorridorExtent:Milepost20.48(Route10)toMilepost28.84(StevensDrive)Length:8.34milesFunctionalClassification:Freeway/Expressway

Page 92: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page86 Benton‐FranklinCouncilofGovernments

Page 93: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page87

Page 94: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page88 Benton‐FranklinCouncilofGovernments

SR240:Route10toStevensDrive 2010 2011 2012

Injuries&Fatalities

TotalFatalities 0 0 0

TotalInjuries 0 12 4

PedestrianFatalities 0 0 0

BicyclistInjuries 0 0 0

BicyclistFatalities 0 0 0

NatureofCollisions

Rear‐End 1 4 1

TurningMovement 0 0 0

AngleorSideSwipe 3 3 3

FixedObject 1 2 0

BackingUp 0 0 0

Bicyclist 0 0 0

Pedestrian 0 0 0

ParkedMotorVehicle 0 0 0

Overturn 0 0 0

Miscellaneous 2 1 5

Total 7 10 9Source:WSDOTStatewideTravelandCollisionDataOffice

Page 95: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page89

SR240BypassCharacteristicsoftheCorridorExtent:Milepost30.63(JadwinAvenue)toMilepost34.57(SR182offramp)Length:4.12milesFunctionalClassification:Freeway/Expressway

Page 96: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page90 Benton‐FranklinCouncilofGovernments

Page 97: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page91

Page 98: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page92 Benton‐FranklinCouncilofGovernments

SR240:JadwinAvenuetoI‐182 2010 2011 2012

Injuries&Fatalities

TotalFatalities 0 0 1

TotalInjuries 34 23 39

PedestrianFatalities 0 0 0

BicyclistInjuries 0 0 0

BicyclistFatalities 0 0 0

NatureofCollisions

Rear‐End 39 32 31

TurningMovement 0 1 2

AngleorSideSwipe 8 14 14

FixedObject 8 3 1

BackingUp 0 0 0

Bicyclist 0 0 0

Pedestrian 0 0 0

ParkedMotorVehicle 0 0 0

Overturn 2 3 0

Miscellaneous 1 5 3

Total 58 58 51Source:WSDOTStatewideTravelandCollisionDataOffice

Page 99: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page93

SR182CharacteristicsoftheCorridorExtent:Milepost.87(DallasRd)toMilepost4.40(I‐182westboundon‐rampfromGeorgeWashingtonWaysouthbound)Length:3.92milesFunctionalClassification:Interstate

Page 100: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page94 Benton‐FranklinCouncilofGovernments

Page 101: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page95

Page 102: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page96 Benton‐FranklinCouncilofGovernments

I‐182:DallasRoadtoI‐182 2010 2011 2012

Injuries&Fatalities

TotalFatalities 0 0 0

TotalInjuries 4 10 10

PedestrianFatalities 0 0 0

BicyclistInjuries 0 0 0

BicyclistFatalities 0 0 0

NatureofCollisions

Rear‐End 5 7 4

TurningMovement 0 0 0

AngleorSideSwipe 6 2 9

FixedObject 5 2 11

Overturn 1 2 1

Miscellaneous 1 4 4

Total 18 17 29Source:WSDOTStatewideTravelandCollisionDataOffice

Page 103: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page97

APPENDIXETravelTimeDataCollection

Page 104: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page98 Benton‐FranklinCouncilofGovernments

Page 105: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page99

CMPTRAVELTIMEDATACOLLECTIONTheprocessdescribedbelowhasnotbeentestedinactualpractice.Itmayremainessentiallyasoutlinedorevolvethroughimplementation.Ifthatisthecase,changeswillbeidentifiedinsubsequentiterationsoftheCMP.DataCollectionTechniquesAvehicleisequippedwithaGPSreceiverandrecordingdevice.Thisdeviceisconnectedbeforetherunsonthecorridorarestartedandunpluggedoncetherunsarecompleted.Corridorshavebeendefinedelsewhereinthisdocument.Inaddition,thedefinitionisfluid;theextentofeachcorridorwillberevisitedtodeterminewhetheritisstillappropriate.DrivingForthepurposeofthesestudies,driversareinstructedtodriveataspeedthatapproximatestheflowoftraffic.Theyweretonotpurposelygetstuckbehindslow‐movingtraffic,ormatchspeedswiththefastestdrivers.Onmulti‐laneroadswithorwithoutacenterturnlane,itwassuggestedthatthelanenexttothecenterbeusedfortravel.RepetitionIfpossible,driversareinstructedtocompleteasmanycircuitsaspossibleduringtheallottedtimeperiod(see“TimePeriods”below).Forsomecorridorsasmanyas8or9circuitsmaybepossible;forothers,eventhreecircuitsmaynotbepossibleduetocongestionand/orlength.SpecialCircumstancesIntheeventofextremeweathersuchasheavyrain,snow,orice,ormajortrafficeventssuchasaccidentsorconstruction,datagatheringalongacorridorwouldbepostponed.Thecorridorwouldbeswitchedwithanothercorridor,iftrafficeventswerethecause,orscheduledforalaterdate,ifweatheristhereason.TimePeriodsInconsideringmeasurementoftraveltime,oneconcernthatsurfaced,andmustbeaddressedasthetraveltimecollectionprocessevolves,isthelengthofpeakperiodcongestionandmeasurementissuesthatpresents.AlthoughacorridorisconsideredcongestedbasedonthenatureoftrafficintheTri‐Cities,thecongestionmayhavea15‐or20‐minutepeakperiod,ratherthanamoreconventionalone‐hourpeak.Thispresentsmeasurementfrequencychallengesthatneedtobeaddressed.TheseincludethenumberofGPSrunsthatcanbeaccomplishedinsuchashorttime,andthenumberofrunsthatconstituteasufficientdataset.Thisemphasizestheimportanceofcoordinatedplanningwitheachjurisdictionpriortothecorridordrives.ThereissomeskepticismastotheefficacyoftheGPSmethodologygeneratingconsistentdataoncorridorswithaveryshortwindowofcongestion.Thedatacollectiontimeframeswillbe“morningcommute”and“eveningcommute”incontrastto“AMpeak”or“PMpeak”.CooperationandconsultationamongjurisdictionsandBFCGwillbeneededtoestablishbothwhenandhowfrequentlytraveltimemeasurementsaremadeandtheschedulemaytakeafewiterationstofinalize.Conventionally,threetimeperiodsaredefinedasimportantinprovidinginformationonhowtheregion’sroadsareoperating.Thesetimeperiodsaredefinedbasedonwhenthe‘peak’traveloccurs.Thesetimeperiodswillbeadjustedasneededinthefuturetotakeintoconsiderationnewinformationthatsuggeststhepeakperiodsareshifting.

Page 106: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page100 Benton‐FranklinCouncilofGovernments

Asitstandstoday,thetimingoftraveltimeGPSrunshasyettobedetermined.Decisionswillvarybyjurisdictionandbyindividualcorridor.DecisionswillbebasedonconversationsamongjurisdictionstaffandBFCGstaff.

Page 107: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page101

APPENDIXFTransitSystemData

Page 108: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page102 Benton‐FranklinCouncilofGovernments

TRANSITDATABenFranklinTransit(BFT)currentlydoesnotcapturepassengerdatainamannerapplicabletotheCMPneeds.However,theagencyisintegraltotwoprogramsthatmateriallyaffectcongestioninthemetropolitanareaandaregermanetotheCMPprocess.ThoseprogramsareBFTVanpoolProgramandthemetropolitanareaparkandridesystem.Muchofthetextandallofthetablesandfiguresarefromthe2011‐2032MTP.Ifappropriate,theywillbeupdated.

Page 109: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page103

BenFranklinTransitVanpoolProgramAsdiscussedearlier,theBFTVanpoolprogrambeganinthe1980sandhasbeenevolvingsince.BenFranklinTransitcurrentlyhas260Vanpoolvansontheroad,theirprimarydestinationistheHanfordArea,andtheirvanpoolserviceranksfourthinthestateinnumberofvansinservice.BasedonBFTdataasofSeptember2013,theprogramaveraged2,352,381passengermilespermonthwhilecarryinganaverageof73,975passengerspermonthsofarthisyear.TableXandFigureXandXpresentdatashowingthegrowthoftheBFTvanpoolprogramovertime.Thesearefromthe2011MTPandwillbeupdated.

TABLE4:BENFRANKLINTRANSITVANPOOLOPERATIONSDATA1995‐2010

BenFranklinTransitVanpoolOperationsData1995‐2010

YearAverage#

VansOperatedTotalMiles

TotalPassengers

PassengerIncrease

MileageIncrease

%RidershipIncrease

%MileageIncrease

1995 921,563,423 466,862 237,134 756,951 51% 48%

2000 1411,998,723 574,055 107,193 435,300 19% 22%

2005 1882,716,309 733,443 159,388 717,586 22% 26%

2010 3124,962,773 1,261,396 527,953 2,246,464 42% 45%

Source:BenFranklinTransitVanpoolProgram 

 

FIGURE2:BENFRANKLINTRANSITVANPOOLRIDERSHIP–1990TO2010

200,000

400,000

600,000

800,000

1,000,000

1,200,000

1,400,000

1990 1995 2000 2005 2010

TotalPassengers

TotalPassengers

Page 110: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page104 Benton‐FranklinCouncilofGovernments

FIGURE3:BENFRANKLINTRANSITVANPOOLMILES–1990TO2010

SourceforFigures:BenFranklinTransitVanpoolProgram

MetropolitanAreaParkandRideSystemTheexistingparkandridesystembegandevelopmentintheearly1980’s.Currentlyitiscomprisedof15formalparkandridelotsinBentonandFranklinCountiesandanumberofinformallots.Thissectionwillreviewdataconcerningtheformalparkandridelots.OccupancydatapresentedinthissectionhasbeencollectedbytheWSDOTSouthCentralRegionalofficeinYakima.Thetwo‐countyareainventoryofparkandridelotsincludesbothparkandrideandparkandpoolfacilities,whileownershipofmostformalmetropolitanareaparkandridelotsissplitbetweentheWSDOTandBFT.BFTalsoleasesafewparkandridesites.Distinguishingbetweenthetwo,WSDOTfacilitiesareprimarilyparkandpoollotsadjacenttomajorroadwayintersectionssuchasSR240/SR224orI‐182/Queensgateandaresitedtocapturethevanpoolandcarpooluser.BFT‐ownedparkandridefacilitiesarelocatedattransitcentersintheirrespectivecommunities.Thefocusofthesefacilitiesisonthetransituserratherthanthecommuter,thoughcommutersmayusethem.Also,developmentoftheWSDOTfacilitiesgenerallyprecededthatoftheBFTlots.AcriticaldistinctiontonotebetweentheTri‐CityareaparkandridesystemandthegreatmajorityofparkandridesystemsisthatthecentralpurposeoftheTri‐Citiesparkandridesystemwas/istoprovideconvenientparkingfacilitiesforvanpoolsandcarpools.Inmanymetropolitanareas,parkandridelotsprimarilyprovideparkingfortransfertoexpressbusesoramasstransitsystem.BenFranklinTransit’sserviceandroutesystemarenotdesignedtoprovidetransportationfromthesefacilitiestoworksites,thoughpeopleusetransittogettoworklocationsservedbythefixedroutesystem.Table5identifiesfacilityownership,facilitytype,andshows2010occupancydatafortheformalparkandridelotsystemintheTri‐Citiesarea.Evaluatedcollectively,theaverageannualmonthlyoccupancyrate,andutilizationoftheTri‐Citiesparkandridesystemisincreasing.Systemcapacityhasrisenfrom657stallsin2001to1,555stallsin2010,anincreaseofmorethan130percent.ParkandRidelotusage,basedonaveragemonthlysystemoccupancy,decreasedfrom2001,with42percentofcapacitybeingutilized,until2006with28percentofcapacitybeingutilized.Usagehasbeenincreasingsince,withthedatashowingaveragesystemmonthlyoccupancytobeat54percentin2010.

1,000,000

2,000,000

3,000,000

4,000,000

5,000,000

6,000,000

1990 1995 2000 2005 2010

TotalMiles

TotalMiles

Page 111: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page105

Table5alsoindexestheParkandRidelotsinMap3andcontains2010occupancydataforeachsite.ParkandRidelotsintheTri‐CitiesmetropolitanareaareshowninMap3.

TABLE5:PARKANDRIDELOTSINBENTONANDFRANKLINCOUNTIES

PARK&RIDEFACILITIESBENTONANDFRANKLINCOUNTIES

SiteID# Facility FacilityOwner

FacilityType Capacity

2010AvgMonthlyOccupancy

2010AvgMonthly%Occupancy

1 StacyAvenueStation Prosser/BFT Park&Ride 28 10 48%

2 SR225&DaleAvenueBentonCity/BFT Park&Ride 37 31 83%

3 I‐82&SR224Interchange WSDOT Park&Pool 30 24 81%

4 WestRichlandTransitCenter WRichland/BFT Park&Ride 27 19 69%

5 FlatTopParkParkingLot WestRichland Park&Ride 127 62 49%

6 SR224&SR240Intersection WSDOT Park&Pool 89 68 76%

7 I‐182&QueensgateInterchange WSDOT Park&Pool 139 6 5%

8 KnightStreet&GoethalsDrive BFT Park&Ride 33 7 20%

9 WSDOT‐ColumbiaParkTrail WSDOT Park&Pool 249 196 79%

10 West27thAvenue&SouthUnionStreet Kennewick Park&Pool 50 40 81%

11WestClearwaterAve&NorthHuntingtonSt BFT Park&Ride 135 35 26%

12 ParkStreet&22ndAvenue BFT Park&Ride 50 19 38%

13 StevensDrive&SpenglerRoad PortofBenton Park&Pool 350 253 72%

14 TRAC TRAC Park&Pool 172 70 40%

15 US395&YelmStreet Kennewick Park&Pool 39 17 43%

Source:2007Tri‐CitiesMetropolitanAreaParkandRideLotReport;WSDOTSouthCentralRegionMonthlyParkandRideInventory

Page 112: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page106 Benton‐FranklinCouncilofGovernments

Map3:Park

andRideLotsin

Benton

andFran

klinCou

nties

Page 113: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page107

APPENDIXGTransportationSystemComponentsintheCMPStudyArea

Page 114: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page108 Benton‐FranklinCouncilofGovernments

ThisappendixcontainsmapsshowingvariouselementsofthemetropolitantransportationsystemandintheCMPstudyarea.Theyinclude:The2013FederalFunctionalClasssystem,the2013BFTfixedroutebusroutes,the2011WSDOTFreightandGoodsSystemandbikepathsfromthe2009BFCGbikemap.

Page 115: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page109

MAP4:CMPStudyAreaandthe2013FederalFunctionalClassSystem

Page 116: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page110 Benton‐FranklinCouncilofGovernments

MAP5:CM

PStu

dyA

reaandthe2

011WSDOTFreigh

tandGood

sTran

sportation

System

Page 117: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page111

MAP6:CMPStudyAreaandthe2013BFTTransitRoutes

Page 118: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page112 Benton‐FranklinCouncilofGovernments

MAP7:CM

PStu

dyA

reaand2009BFCG

BikeM

apRoutes

Page 119: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page113

APPENDIXHPublicComment

Page 120: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page114 Benton‐FranklinCouncilofGovernments

Notice of availability of the CMP for review online was mailed to more than 240 agencies andindividuals on the BFCGTransportation Section Public OutreachMailing List. One commentwasreceived.ThatcommentandtheBFCGreplyarebelow.

Page 121: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page115

Page 122: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page116 Benton‐FranklinCouncilofGovernments

Page 123: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Benton‐FranklinCouncilofGovernments Page117

Page 124: TRI‐CITY METROPOLITAN AREA TRANSPORTATION STUDYbfcog.us/.../05/2013-Congestion-Management-Process.pdf · 2013 Tri‐MATS Congestion Management Process Page 2 Benton‐Franklin Council

2013Tri‐MATSCongestionManagementProcess

Page118 Benton‐FranklinCouncilofGovernments

Benton‐FranklinCouncilofGovernments1622TERMINALDRIVE RICHLAND,WASHINGTON99352

______________________________________________________________________________________________

November26,2013Ms.LisaAndersonTri‐CityRailroadCompany2579StevensDrivePOBox1700Richland,Washington99354Re:Tri–CityRailroadCommentonthe2013CongestionManagementProcessDearMs.Anderson:ThankyouverymuchfortakingthetimetocommentoncongestionmanagementintheTri‐Cities,specificallythepotentialeffectsofincreasedrailtrafficonthePortofBentonraillinewestofRichland.The2013CongestionManagementProcess(CMP)doesnotaddresstherailloopprojectyoureference.Timeconstraints–theCMPhasaduedateofJanuary18thfordeliverytofederaltransportationagencies–andtherecentemergenceoftheloopprojecthavenotallowedsufficienttimetoaddresstheissue.DevelopmentoftheCMPisongoing.CurrentlyagencydiscussionshavescheduledtheCMPforanupdateintwoyears.TheCouncilofGovernmentsisawareoftheissueoftheeffectsofrailonstreetcongestionandthetopicwillbeapartoftheupdate.IfyouhaveanyfurtherquestionsImaybereachedat(509)943‐[email protected],LenPavelka,TransportationPlannerBentonFranklinCouncilofGovernments