22

Transportation Master Plan - crgov.com

  • Upload
    others

  • View
    12

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Transportation Master Plan - crgov.com

    

Page 2: Transportation Master Plan - crgov.com

 

    

September, 2011

  

Transportation Master Plan  

 

 

Prepared for: 

Town of Castle Rock 

100 N. Wilcox Street 

Castle Rock, CO 80104 

 

 

 

 

 

 

 

 

Prepared By: 

 

  

In association with 

 

   

Page 3: Transportation Master Plan - crgov.com
Page 4: Transportation Master Plan - crgov.com

 

   

Executive Summary ES1

Executive Summary Introduction This  Transportation  Master  Plan  (TMP)  emphasizes  improvements  to  the  existing  street  system, enhanced bicycle  routes, and upgrades  to pedestrian  facilities along  the primary  street  system.     The TMP  also  includes  long  range  forecasts  of  the  Town’s  transportation  system  to  assess  the  ability  of future  transportation projects  to meet 2020 and 2030  travel demand.         Since  the Town Council has designated  the North Meadows Extension  to US 85 and  I‐25 project as  the Town’s  top  transportation priority, it was included in the street network used in the 2020 and 2030 traffic models.   

The following text and figures provide a summary of the reasons for the master plan, an assessment of existing  transportation  conditions,  and  the  recommendations  that  were  developed  during  the  TMP process. 

Reason for Updating the TMP     

The primary purpose of  the TMP  is  to help guide  transportation decisions  to best address  the  future needs and visions of the Town.  The plan provides the Town guidance in the allocation of its funding to meet the transportation needs of the community.  

The previous TMP was completed in 2003 and revised in 2004 and 2007.    Although the existing plan is still  a  very  usable  document,  a  number  of  conditions  have  changed  that make  an  update  advisable.   Several of  the major projects  identified  in  the 2003 TMP have been completed and others have been partially  completed.      Figure  ES‐1  shows  the  19 major  transportation projects  that have  either been completed, or partially completed, since 2003. These projects have helped address the effects of recent traffic growth.   The Town, the Colorado Department of Transportation and private developers have all contributed to these  improvements. The “ring road” around the town, which was first proposed  in the Town’s  original  Transportation Master  Plan,  has  now  been  completed.  These  projects  address  the following issues identified in the previous Transportation Master Plans: 

Improve the regional facilities serving the Town   Improve the Town’s I‐25 interchanges  Improve east‐west access across I‐25, the Burlington Northern Santa Fe Railroad (BNSF RR), the 

Union Pacific Railroad (UP RR), and East Plum Creek  Improve streets serving the downtown area   

 

A Pedestrian and Bicycle Friendly Community 

In addition to developing a safe and efficient roadway system, the Town wishes to be a pedestrian and bicycle‐friendly  community.    To  do  this,  an  integrated  plan  was  prepared  that  will  lead  to  the development of a system of “on” and “off” street bike routes, multi‐use trails and multi‐use sidepaths (8‐10 ft. wide paths that are located along major streets) throughout the Town.  In the past, people have primarily viewed walking and bicycling as forms of exercise and recreation.  The Town wants these forms of transportation to also be used  in commuting to/from work, for shopping trips and for other day‐to‐day errands.  This TMP gives a much greater emphasis to achieving this goal. 

Page 5: Transportation Master Plan - crgov.com

 

   

Executive Summary ES2

 

Figure ES‐1: Major Transportation Projects Undertaken Since 2003 

Page 6: Transportation Master Plan - crgov.com

 

   

Executive Summary ES3

Growth and Development of the Town  

Since 2003, Castle Rock has experienced tremendous growth, with the Town’s population increasing by more than 60%.  However, the recent economic downturn has made it necessary to significantly revise the population and employment forecasts used in the previous plan.  During the last 30 years, most of the  growth  has  been  in  single‐family  residential  developments  located  away  from  the  Town  center. Population has outgrown employment by nearly two to one, creating a large disparity between housing and  jobs.    This  disparity  has  resulted  in  increased  commuting  to  areas  outside  Castle  Rock  for employment.   The Town Master Plan calls  for  future growth  to have a higher density, and  include an increased  amount  of mixed‐use  development, which will  have  a  higher  proportion  of  employment.  Future  growth  projections  provided  by  the  Town’s  Development  Services  Department  are  shown  in Table ES‐1.  Over the next 20 years, approximately 8,000 households are expected to be built in Castle Rock along with 4,000,000  square  feet of commercial and office development.   Table ES‐2  shows  the projected change in population and employment as a result of household and commercial development.   

Table ES‐1: Projected Land Use Changes  

Land Use 2010‐2020 Change 

2020‐2030 Change 

Single Family Homes (units) 

3,325  4,650 

Retail Square Footage (Sq Ft) 

656,000  407,000 

Industrial Office Space (Sq Ft) 

265,000  165,000 

Office Square Footage (Sq Ft) 

1,604,000  994,000 

Source: Castle Rock Development Services Department 

 

Table  ES‐2:  Projected  Population  and Employment Change 

   2010  2030  % Increase 

Population  46,000  64,100  39.3% 

Employment  18,500  31,700  71.4% Source:  Castle  Rock  Development  Services  Department  / Muller Engineering Company 

 

 

 

EXISTING CONDITIONS Street System Performance  The major  street  system was  analyzed  to  assess  its  operational  performance  during  periods  of  peak traffic  flow.   Street  segments  are  generally described  as having  light, moderate or heavy  congestion.  Figure ES‐2 shows the congestion levels that are found on the Town’s street network during the evening (PM)  peak  hour,  which  typically  has  the  heaviest  congestion  of  the  day.    Roadways  with  heavy congestion include:  

Founders / Meadows Parkway through the I‐25 interchange area   Crowfoot Valley Road north of Founders Pkwy.  Wilcox Street from 5th St. to Wolfensberger Rd.  Ridge Road south of SH 86/5th Street   SH 86 east of Founders Parkway  SH 85, north of the Town limits 

 The congestion on Wilcox Street  is  likely due to traffic from the Douglas County School District offices, the Douglas County administrative offices and Town Hall.    

Page 7: Transportation Master Plan - crgov.com

 

   

Executive Summary ES4

 Figure ES‐2: Existing PM Peak Hour Congestion Levels 

 For  the most  part,  the  street  system  is  shown  as  operating  acceptably.   Even  though  there will  be periods  of  time  during  the  peak  hours when  traffic  builds  up  and  creates  “stop  and  go”  conditions, especially within the Founders / I‐25 interchange area, these are generally of a short duration.   

Page 8: Transportation Master Plan - crgov.com

 

   

Executive Summary ES5

Several  intersections  also  experience  heavy  congestion  during  the morning  and  evening  peak  hours.  These intersections are mostly clustered along the Founders/Meadows corridor and also on 5th Street in downtown Castle Rock as noted below. 

Founders Parkway /I‐25 NB and SB Ramps   Founders Parkway /Allen Way  Founders Parkway / Crowfoot Valley Road   Founders Parkway /5th St./SH 86 

Meadows Parkway/SH 85  Meadows Parkway/Prairie Hawk   5th Street/Wilcox Street  5th Street/Perry Street 

 The last three intersections are controlled by the Town.  The others fall under the jurisdiction of the Colorado Department of Transportation.  Pedestrian and Bicycle System Many of the 110 miles of bicycle and pedestrian facilities that presently exist within the Town have been completed within  the past 10 years.   These  facilities  include both paved and unpaved multi‐use trails, on‐street bikes lanes and 8 ft. wide multi‐use sidewalks alongside many major streets. The Town’s trail system  connects  neighborhoods with  parks  and  open  space  areas. Multi‐use  sidepaths  along many major streets connect to, and complement, this trail network.    Two branches of the Colorado Front Range Trail meet within the Town.   This “crossroads” is formed by the East Plum Creek Trail that will connect to Chatfield State Park and the McMurdo Gulch Trail that will connect to the Cherry Creek Trail that leads to Cherry Creek State Park.  A major part of the East Plum Creek Trail has been completed within the Town  limits and was dedicated  in 2009. This portion of the trail extends from south of Plum Creek Parkway to almost a mile north of Meadows Boulevard.  It is the major north‐south multi‐use trail through Town.  The McMurdo Gulch Trail,  is presently under design, with portions of it planned for construction in 2012/2013.   

Throughout the year, numerous activities are held  in the downtown  area.    Fairs,  farmer’s markets,  parades  and special  events  are  common.    In  order  to  encourage pedestrian  activity,  a  number  of  amenities,  such  as pedestrian  lighting,  enhanced  crosswalks  and  signing, have also been constructed within the downtown area to create a more “walkable” environment.  It  is  the  goal  of  the  TMP  is  to  develop  a bicycle/pedestrian  system  that  meets  the  collective needs  of  pedestrians  as  well  as  those  of  recreational, commuter, and sport cyclists alike.    

 

RECOMMENDATIONS The recommended transportation plan provides for  improved mobility for automobile, pedestrian and bicycle travel modes.  Due to the discontinuation of the Town’s bus system, transit improvements were not addressed in this TMP. 

Page 9: Transportation Master Plan - crgov.com

 

   

Executive Summary ES6

Roadway Plan The 2030 Roadway Plan was based upon an analysis of the Town’s anticipated growth in households and employment over  the next 20 years.   A  traffic model was prepared and utilized, previous studies and regional planning efforts were reviewed, and public input was taken.  Comments and suggestions were solicited  from  other  Town  Departments  that  rely  upon  the  transportation  system  to  fulfill  their responsibilities.   

In general, the roadway plan closely conforms to the plan included in the 2003 TMP, with the following exceptions: 

The easterly limit of the North Meadows Extension has been extended from US 85 to I‐25.    A  new  two  lane  road,  roughly  paralleling  East  Plum  Creek,  from Meadows  Parkway  to  the 

Liggett Road extension has been added to the plan.      Coachline Road, from Wolfensberger Road to Meadows Boulevard, is now being shown as a two 

lane arterial instead of a 4 lane arterial.  Projected future traffic volumes are not large enough to require the additional 2 lanes. 

Red  Hawk  Drive,  Butterfield  Crossing  Drive,  Foothills  Drive,  Diamond  Ridge  Parkway,  and Sapphire Pointe Boulevard are being shown as residential collector roadways.   

Prairie Hawk  from Meadows  Blvd.  to  Plum  Creek  Parkway  has  been  changed  from  a  4  lane arterial  to a 2  lane arterial.   The majority of development along Prairie Hawk  is  located along only one side (the west side) of the street.  There will be no development along the east side of the street south of  the commercial area  in  the southeast quadrant of Meadows Parkway and Prairie Hawk Dr.  This will limit the congestion problems from turning traffic that often require a wider street cross‐section.   

Figure  ES‐3  shows  the  proposed  2030  roadway  plan,  the  roadway  classifications  and  the  number  of travel  lanes of each  facility.   Figure ES‐4 shows  the  locations and  type of roadway projects needed  to implement the recommended plan. 

Project Evaluation and Comparison The projects  shown  in  Figure  ES‐4 were  evaluated using  a  variety of  criteria  in order  to  assess  their relative  importance  to  the Town’s  transportation  system.   Seven of  the criteria are very  subjective  in nature.   Because of this, a “Yes/No” rating system, rather than a numerical one, was used.   Table ES‐3 shows the results of the evaluation.      Input related to several of the criteria was provided by the Town’s Fire and Police Departments and the Development Services Department.  The Castle Rock Economic Development Council also provided input on  the  potential  economic  impact  of  certain  projects.    Project  costs were  developed  by  the  Town’s Public Works Department and were based on 2010 construction costs.   After completing the criteria ratings  for each project, the projects were then classified as being either first or second “tier” projects.   As with  the  individual criteria,  this was also a subjective process.   The projects weren’t “ranked”, only put into “tiers” that reflect the general importance of the project to the Town.  These criteria relate only to vehicle travel, and do not reflect how well the project would support bicycle and pedestrian travel.   Bicycle and pedestrian facilities, that meet the recommendations of the Bicycle and Pedestrian elements of this TMP, will be incorporated into each project.   

Page 10: Transportation Master Plan - crgov.com

 

   

Executive Summary ES7

 

Figure ES‐3: Recommended 2030 Roadway Plan 

 

Page 11: Transportation Master Plan - crgov.com

 

   

Executive Summary ES8

 

Figure ES‐4: Recommended Roadway Projects 

  

Page 12: Transportation Master Plan - crgov.com

 

   

Executive Summary ES9

 

Table ES‐3: Roadway Project Prioritization 

(Note: While “Yes” indicates a positive attribute, in the case of the “Environmental Mitigation Required” criteria, it 

is just the opposite.  For this criteria, a “No” response would be the most desirable.) 

First Tier Roadway Projects As  seen  from  Table  ES‐3,  the  “First  Tier”  projects  had  the  highest  percentage  of  “yes”  responses; although  the  I‐25/Crystal Valley/Dawson Ridge  interchange met  all but one of  the  criteria  it was  still classified as a “Second Tier” project.  In deciding upon the groupings, the amount of developer funding that would be used  in a project was often the deciding criteria.   The  I‐25/Crystal Valley/Dawson Ridge interchange  project  will  certainly  be  of  value  to  the  Town,  but  it  is  a  project  that  will  be  almost completely funded by the adjacent developments and not by the Town.  Of this group of projects, the Town Council has established the North Meadows Extension project as the Town’s top priority.     This project provides the greatest positive  impact  from the standpoint of easing traffic congestion, improving emergency access and supporting economic development.  Since the Town will dedicate most of its transportation funding to this project, completion of the remaining “First Tier” projects will be primarily dependent upon the development of adjacent properties.  One of the Town’s primary responsibilities  is to provide emergency services.    In order to do that most efficiently  there  should  a  number  of  routes  available  to  a  responder  in  case  their  primary  route  is blocked  or  unusable.   All  six  of  the  “First  Tier”  projects  either  construct  a missing  portion  of  street (Projects  #2,  6),  extend  an  existing  street  so  that  it  connects  to  other  streets  (Projects  #1,  3,  4),  or relocate a road away from a serious barrier that could block the ability of emergency units to respond (Project  #5).    Not  only  do  these  projects  improve  police  and  fire  response,  they  will  also  increase economic development opportunities, serve future development areas and reduce roadway congestion.  

Project ID 

Number Project

Planning Level 

Cost Estimate 

(millions)

Developer 

Participation

Improves 

Police 

Response

Improves 

Fire 

Response

Supports 

Economic 

Development 

Improves 

Traffic Flow

Environmental 

Mitigation 

Required

1 North Meadows Extension  $66.5 Yes Yes Yes Yes Yes Yes

2 Woodlands Blvd Connection $5.2 Yes Yes Yes Yes Yes No

3 Liggett Rd ‐ Extension to Caprice St $3.8 No Yes Yes Yes Yes Yes

4 Prairie Hawk Dr ‐ Extension (Wolfensberger  to Plum Creek Pkwy) $2.5 Yes Yes Yes Yes Yes No

5Prairie Hawk (West Frontage Rd) ‐ Relocation (Plum Creek Pkwy to 

Dawson Ridge) $15.8 Yes Yes Yes Yes Yes No

6 Perry St. ‐ Connection to East Frontage Rd $5.7 Yes Yes Yes Yes Yes Yes

7 Crowfoot Valley Rd Widening  $3.5 Yes No No No Yes No

8 Castle Oaks Drive  Construction $9.5 Yes No Yes No Yes No

9 Meadows Blvd Widening (Prairie Hawk to Coachline) $2.6 Yes No No No Yes No

10 Prairie Hawk Dr ‐ Improvements (Meadows Blvd to Wolfensberger) $2.6 Yes No No No Yes No

11 New Roadway Between Meadows Blvd to Liggett Rd $6.0 Yes No No Yes No Yes

12 Liggett Rd ‐ Widening (south of Blackfeather) $4.4 Yes No No No Yes No

13 Wolfensberger ‐ Widening (Prairie Hawk to Coachline) $5.9 No No No No Yes No

14 5th St improvements (Gilbert to Founders Blvd) $4.3 No No No No Yes No

15 Ridge Rd ‐ Widening (SH 86 to Plum Creek Pkwy) $2.3 No No No No Yes No

16 Plum Creek Pkwy  ‐ Widening (I‐25 to Wolfensberger) $3.8 No No No No Yes No

17 Valley Dr Completion (Hover to Hudson Ln) $3.2 No Yes Yes No Yes No

18 Plum Creek Pkwy ‐ Widening (Gilbert to Ridge Rd) $4.4 No No No No Yes No

19 Crystal Valley/Dawson Ridge/I‐25 Interchange $38.5 Yes Yes Yes Yes Yes Yes

20 Crystal Valley Pkwy ‐ Widening (I‐25 to Lake Gulch Road)  $9.3 Yes No No No Yes No

21 East Frontage Rd ‐  Improvements  $4.0 Yes No No No No No

SECOND TIER PROJECTS

FIRST TIER PROJECTS

Page 13: Transportation Master Plan - crgov.com

 

   

Executive Summary ES10

While the  initial phases of each of these projects may not build the roadways to their ultimate width, they do help “complete” the basic roadway network.      With the Town’s commitment to the completion of the North Meadows Extension, the Town’s ability to fund an additional project within the next 10 years may be  limited.   So  it  is  important that,  if possible, the “First Tier” projects not be reliant upon Town funding.  Funding for five of these projects will include developer participation.  Only one project, the Liggett Road extension, is expected to be entirely funded by the Town.    

Second Tier Roadway Projects Most of  these projects  involve either widening or  improving an existing street or  roadway,  instead of building a completely new one.   Although  the projects  in  this grouping are classified as “Second Tier” Projects,  they  are  still  important  and  will  significantly  improve  the  operation  of  the  Town’s transportation system.  This classification simply refers to the fact that it is the Town’s intention that the “First Tier” be finished before work on this group is started.  Since some of these “Second Tier” projects will be constructed as part of the development of adjacent properties, and are not being funded by the Town, they may actually be completed prior to some of the “First Tier” projects.    Second Tier projects that provide the most improvement to traffic flow include:  

#7: Crowfoot Valley Road Widening – construction of an additional 2  lanes between Founders Parkway and Sapphire Pointe Boulevard  

#9: Meadows Boulevard Widening – construction of an additional 2 lanes between Prairie Hawk Drive and Coachline Road 

#14: 5th Street  Improvements – widening, construction of turn  lanes and other  improvements between Gilbert Street and Founders Parkway 

#15: Ridge Road Widening – construction of an additional 2 lanes between Plum Creek Parkway and SH 86 

Both 5th Street and Ridge Road are on DRCOG’s 2035 Regional Transportation Plan and may be eligible to compete for operational funding through their Transportation Improvement Program (TIP).   Detailed descriptions of each of the 21 roadway projects are provided in Chapter 4 of the TMP.  

Bicycle Plan The goal of the Bike Plan is to provide safe and efficient bicycle routes between Castle Rock’s residential areas, the downtown area, the interchange overlay districts, schools and shopping areas.    Bicycling can play  an  important  role  in  meeting  the  Town’s  transportation  needs  as  well  as  being  a  popular recreational activity.   Additionally, a well‐planned and utilized bicycle system can encourage people to use  their  bicycles  instead  of  their  automobiles  for  commuting,  shopping  and  other  trips.    This  can improve air quality and promote a healthy  lifestyle.   Figure ES‐5  shows  the  framework of  the Bicycle Plan.    

Page 14: Transportation Master Plan - crgov.com

 

   

Executive Summary ES11

 

 Figure ES‐5: Recommended Bicycle Plan 

Page 15: Transportation Master Plan - crgov.com

 

   

Executive Summary ES12

The proposed bicycle system has a series of facilities that perform specific functions:   Loops – these seven routes serve the residential areas and don’t extend beyond the limits of the 

individual neighborhood. They serve as “collector” routes within neighborhoods and tend to be located along collector streets.  They provide access to neighborhood amenities such as schools, parks and the open space trail system.   

Runs  ‐  there  are  six  “runs”  that  provide  direct  connections  between  the  neighborhoods  and downtown Castle Rock.  These routes follow collector and arterial streets leading generally into the downtown area.  These routes cross several major barriers such as I‐25, the UPRR and BNSF RR and East Plum Creek.   Being major streets, they also are typically  less “hilly” than the  local street system 

Connectors –  there are 10 “connector”  routes  throughout Town.   As  their name  implies  they help connect the “loop” routes, the “runs”, the “ring route” and the regional trail system to one another.   These  routes help  fill  in gaps between  the other  routes and  take bicyclists  into  the downtown area.   

Circumferential Route –  this  route  (“ring  route”)  surrounds  the Town and connects all of  the routes together 

Regional Trails – the regional trail system follows major geographic features and runs through Town connecting neighborhoods to open space areas and parks.  It also connects to portions of the statewide trail system 

 Appendix D provides additional details of each of the proposed routes.   

 

Pedestrian Plan Pedestrian activity is important to a community’s vitality and quality of life.  The best way to encourage people  to walk  is  to  provide  them with  a  continuous, well  designed  sidewalk  or  trail  network.    The network needs to connect residential areas with places of work, shopping, dining and recreation.    While  the  sidewalks  found  along  the  residential  streets  are  a  part  of  the  overall  network,  the  only sidewalks and “multi‐use sidepaths”  identified  in the TMP are those along the major street system, as these are  the  facilities  that  lead  to primary destinations and activity centers.   Sidewalks  in  residential areas are  typically 4‐5  ft.  in width; multi‐use  sidepaths are basically  sidewalks  that are 8‐10  ft. wide.  They are wide enough to accommodate a variety of users, such as pedestrians, bicyclists, skaters, etc.    The  recreational  trails  that  have  been  constructed through  the  Town’s  open  space  areas  are  also considered to be “multi‐use”, as they are typically 8‐10 ft. wide  and  used  by  both  bicyclists  and  pedestrians.  One of the goals of this TMP is to connect the multi‐use sidepaths,  along  the  major  street  system,  with  the multi‐use  trails  through  the open space areas  in order to expand  the overall path system.   Figure ES‐6 shows the recommended multi‐use sidepath/trail system.     

Page 16: Transportation Master Plan - crgov.com

 

   

Executive Summary ES13

There  are  numerous  missing  sections  of  multi‐use  sidepaths  and  multi‐use  trails  that  need  to  be completed.    In  selecting projects  for construction,  there are many criteria  that  should be considered.  Among them are: 

The posted speed and traffic volumes of the adjacent street  The distance to alternate facilities  Locations of schools and the ages of the children who attend  Commercial centers  Employment centers  Whether the project eliminates a “missing link” in a facility  Project cost  Connection to the downtown area  Support of the adopted pedestrian and bicycle plan 

Table  ES‐4  shows  the  missing  sections  of  sidepaths  and  sidewalks  that  should  be  given  special consideration  during  the  prioritization  of  construction  projects.    Some  are  along  streets  that  serve schools  and  recreation  areas;  others  are  along major  roads  and  streets where  pedestrians  have  no alternative routes.   

 

Page 17: Transportation Master Plan - crgov.com

 

   

Executive Summary ES14

 

Figure ES‐6: Recommended Pedestrian Plan and Project Priorities (The side paths shown in the bicycle 

plan are the same as those in the pedestrian plan.  For more detail on the side path system refer to the 

sectional Bicycle Plan maps in Appendix D.) 

Page 18: Transportation Master Plan - crgov.com

 

   

Executive Summary ES15

 

TABLE ES‐4: Sidepath and Sidewalk Projects 

Project locations are shown in Figure ES‐6. 

 

  

Project ID 

NumberProject Name  Project Description 

Length 

(Ft)

Width 

(Ft)

Planning 

Level Cost 

Estimate

Safe route 

to school

Connection for 

traffic 

generators 

Near 

alternative 

facility

Support 

biking/walking  

Downtown 

Estimated 

Developer 

Contribution

FIRST TIER PROJECTS

1Crowfoot Valley Road ‐                            

Founders Pkwy to Sapphire Pointe 

Blvd 

8 foot multi‐use sidepath ‐ 

northwest side;                                             5,100  8 $400,000 No Yes No No 25%

2 Founders Parkway  ‐                                 

Crowfoot Valley Road to Beechnut Pl. 

 8 foot multi‐use sidepath on east 

side of Founders Pkwy        1,700  8 $175,000 No Yes No No 0%

3Founders Parkway ‐                                  

Crowfoot Valley Rd to Woodlands 

Blvd 

8 foot multi‐use sidepath ‐ south 

side        2,800  8 $125,000 No Yes No Yes 0%

4Heritage Ave ‐                                            

School Boundary to Sundance5 foot sidewalk ‐ south side

          750  5 $100,000 Yes Yes Yes** No 50%

5Oman Road  ‐                                             

North of  Gilbert St.                                  5 foot sidewalk ‐ east side 

      1,000  5 $100,000 Yes Yes No No 0%

6Fifth St. ‐                                                     

Woodlands to Valley Drive

8 foot. multi‐use sidepath ‐south 

side 2,100 8 $500,000 No Yes No No 0%

7Mikelson Boulevard ‐                               

Suffolk Ave to Sovereign St. 5 foot sidewalk ‐ inside of loop 

      5,800  5 $300,000 Yes No Yes* No 0%

8Praire Hawk Drive  ‐                                 

Wolfensberger Rd  to Meadows Pkwy

8 foot multi‐use sidepath‐ west side ‐

(from south of New Hope Rd. to the 

end of existing 5' sidewalk);          3,550  8 $240,000 No Yes No Yes 0%

9Ridge Road ‐                                               

Plum Creek Parkway to Mikelson 

Blvd. 8 foot multi‐use sidepath ‐ east side 

      2,800  8 $300,000 No Yes No Yes 0%

10Wolfensberger Road ‐                              

Coachline to Red Hawk Drive 8 foot multi‐use sidepath ‐south 

side        5,100  8 $700,000 No Yes No Yes 25%

11 Coachline Road ‐                                       

Wolfensberger Rd to Park Entrance 8 foot multi‐use sidepath ‐ west side 

      2,300  8 $300,000 No No No No 75%

12 Founders  Parkway ‐                                 

Beechnut Place to Crimson Sky Drive   8 foot multi‐use sidepath‐ east side 

       7,100  8 $500,000 No Yes No No 50%

SECOND TIER PROJECTS

13 Founders Parkway ‐                                  

5th St. to Castle Oaks Right of Way 8 foot multi‐use sidepath ‐ east side  

      1,800  8 $300,000 No Yes Yes* No 100%

14Fifth St. ‐                                                     

Valley Drive to Founders Pkwy  8 foot multi‐use path 2,800 8 $600,000 No Yes No No 0%

15South St. ‐                                                   

Gilbert to Oman5 foot sidewalk

      1,000  5 $100,000 Yes Yes No No 0%

16Enderud Boulevard ‐                                

Mikelson Blvd. To Heritage Ave.5 foot sidewalk ‐  east side  

          500  5 $70,000 Yes No Yes* No 0%

17Mikelson Boulevard ‐                               

Willow St. to Enderud Boulevard  5 foot sidewalk ‐ east side 

          500  5 $70,000 No Yes Yes* Yes 0%

18 Crystal Valley Parkway‐                           

East of Lions Paw St. to West Loop Rd 

8 foot multi‐use sidepath ‐ south 

side        2,800  8 $350,000 No No Yes No 100%

19Front Street ‐                                             

Cantrill St to 5th Street  8 foot multi‐use sidepath ‐ east side 

      1,100  8 $150,000 No Yes No Yes 0%

20Park Street ‐                                               

Jason St. to North of 8th St. 5 foot sidewalk ‐ west side  

      1,000  5 $150,000 No Yes Yes No 0%

21Perry Street ‐                                             

South Street to Plum Creek Pkwy8 foot multi‐use sidepath ‐ west side 

      2,000  8 $300,000 No Yes Yes Yes* 0%

22Emerald Drive‐ Plum Creek Blvd. to 

Emerald Court8 foot multi‐use sidepath

          450  8 $70,000 No Yes Yes Yes 0%

23Plum Creek Blvd. ‐ Mount Royal Drive 

to Emerald Drive 8 foot multi‐use sidepath        1,100  8 $150,000 No Yes Yes* Yes 0%

* Must cross multi‐lane or divided roadway** Temporary sidewalk in place

Total

Unit Price Sources: CDOT Cost Data 2009,2010 ‐ Castle Rock PMP 2010, 2011 ‐ Castle Rock Opinion of Costs for Roadway Construction 2010

Page 19: Transportation Master Plan - crgov.com

 

    

i September, 2011

  

Transportation Master Plan  

 

 

Prepared for: 

Town of Castle Rock 

100 N. Wilcox Street 

Castle Rock, CO 80104 

 

 

 

 

 

 

 

 

Prepared By: 

 

  

In association with 

 

   

Page 20: Transportation Master Plan - crgov.com

 

    

ii September, 2011

Acknowledgements 

Town of Castle Rock 

Town Council 

Paul Donahue, Mayor, Council District 1 Brian Logan, Council District 2 Jennifer Green, Council District 3 Chip Wilson, Council District 4 Renee Valentine, Council District 5 Clark Hammelman, Mayor Pro Tem, Council District 6 Joe Procopio, Council District 7  

Public Works Commission 

Joe Procopio, Town Council Liaison JoBeth McFadden, Chair Richard Morton, Vice‐Chair Ken Brink Donna Hawk Mike Riedmuller Bob Washburn  Robert Wells  

Planning Commission 

Joe Procopio, Town Council Liaison Leslie Lee, Chair  Barbara Dash, Vice Chair  Ryan Christensen  Michael Fronczak  Andrew Hauss  Chris Pace  Rick Wood  

 

Castle Rock Staff 

Robert Goebel, Director of Public Works  Bob Watts, Transportation Planning Manager Ann Skinner, Transportation Planning Analyst Dan Sailer, Traffic Engineer Manager Martin Hudson, Development Services, Long Range Planning Jeff Smullen, Superintendent of Parks Rich Havel, Trails Planner Jason Reynolds, Development Services, Project Manager  

   

Page 21: Transportation Master Plan - crgov.com

 

    

iii September, 2011

Table of Contents 

1.0 Introduction ............................................................................................................ 1 

Purpose and Basis for Updating the TMP ................................................................................................. 1 

Previously Completed Transportation Projects ........................................................................................ 2 

Guiding Principles and Policies ................................................................................................................. 4 

Relationship to Community and Regional Planning .................................................................................. 6 

2.0 Existing Conditions ............................................................................................... 8 

Bicycle System ......................................................................................................................................... 17 

Pedestrian System ................................................................................................................................... 22 

3.0 Future Conditions ............................................................................................... 26 

Travel Demand Model ............................................................................................................................ 26 

Year 2020 ‐ Future Conditions ................................................................................................................ 28 

Year 2030 ‐ Future Conditions ................................................................................................................ 37 

4.0 Recommended Transportation Plan ............................................................ 47 

Roadway Plan .......................................................................................................................................... 47 

Major Roadway Project Descriptions ...................................................................................................... 52 

Intersection Improvement Projects ........................................................................................................ 58 

Downtown Street System ....................................................................................................................... 61 

Pedestrian Plan ....................................................................................................................................... 62 

Bicycle Plan ............................................................................................................................................. 65 

Appendices A – Household and Employment Forecast Data 

B – Summary of Public Comments 

C – Travel Demand Forecasting Technical Memorandum 

  D – Bicycle Plan    

Page 22: Transportation Master Plan - crgov.com

 

    

iv September, 2011

List of Figures  Figure 1‐1: Major Transportation Projects Undertaken Since 2003…………………………………………………….. . 3 

Figure 2‐1: Existing Functional Street Classification and Number of Lanes…………………………………………….9 

Figure 2‐2: Daily Traffic Volumes……………………………………………………………………………………………... .......... 11 

Figure 2‐3: Existing PM Peak Hour Congestion Levels …………………………………………………. ....................... 13 

Figure 2‐4: 2010 Fifteen Highest Accident Rate Locations………………………………………………………………….. 14 

Figure 2‐5: Projects That Will Help Complete the Basic Roadway System ………………………………………….. 16 

Figure 2‐6: Existing Multi‐Use Sidepaths and Trails…….……………………………………………………………………… 19 

Figure 2‐7: Existing On‐Street Bicycle System…………………………………………………………………………………….. 20 

Figure 2‐8: Barriers to Bicycle Travel…………………………………………………………………………………….. ............. 21 

Figure 2‐9: Inventory of Multi‐Use Sidepath System………………………………………………………………………….. 23 

Figure 3‐1: Household and Population Growth in the Castle Rock Travel Demand Area…………………….. 26 

Figure 3‐2: Castle Rock Traffic Analysis Zones (TAZ)…………………………………………………………………………… 27 

Figure 3‐3: Household Growth by Traffic Analysis Zone (2010‐2020) ..................................................... 28 

Figure 3‐4: Employment Growth by Traffic Analysis Zone (2010‐2020)………………………………………………. 29 

Figure 3‐5: Estimated Year 2020 Traffic Volumes using the Base Condition Street Network ................. 31 Figure 3‐6: Estimated 2020 PM Peak Hour Congestion using the Base Condition Street Network  ....... 32 

Figure 3‐7: Estimated 2020 Traffic Volumes when Selected Projects are Added to the 2020 Base Street 

Network ................................................................................................................................................... 35 

Figure 3‐8: Estimated 2020 PM Peak Hour Congestion Levels when Selected Projects are Added to the 

2020 Base Street Network….. .................................................................................................................. 36 

Figure 3‐9: Estimated 2030 Traffic Volumes when the Interchange and the Selected Projects are Added 

to the Base Street Network ..................................................................................................................... 38 

Figure 3‐10: Estimated 2030 PM Peak Hour Congestion Levels when the Interchange and the Selected 

Projects are Added to the Base Street Network ...................................................................................... 39 

Figure 3‐11: Estimated 2030 Traffic Volumes – Base Roadway Network + Selected Projects ................ 45 

Figure 3‐12: 2030 PM Peak Hour Congestion Levels – Base Roadway Network + Selected Projects ...... 46 

Figure 4‐1: Recommended 2030 Roadway Plan…………………………………………………………………………………. 50 

Figure 4‐2: Recommended Roadway Projects……………………………………………………………………………………. 51 

Figure 4‐3: Recommended Intersection Improvements……………………………………………………………………… 61 

Figure 4‐4: Recommended Pedestrian Plan and Project Priorities……………………………………………………... 64 

Figure 4‐5: Recommended Bicycle Plan……………………………………………………………………………………………… 67 

Figure 4‐6: Bicycle Facility Types………………………………………………………………………………………………………… 68 

 

List of Tables Table 4‐1: Roadway Projects .................................................................................................................... 49 

Table 4‐2: Sidepath and Sidewalk Projects .............................................................................................. 63