8
transport planning practice 30827/D/014a February 2020 1 Transport Planning Practice| 70 Cowcross Street | London | EC1M 6EL| Tel: 020 7608 0008 | [email protected] Residential Sites, Wye Transport response to Local Authority Introduction 1. Transport Planning Practice (TPP) has been commissioned by Telereal Trillium to provide transport planning advice with regard to their development proposals for the Land to the north of Occupation Road, referred to as Site 8 in the WYE3 Masterplan area. 2. This note has been prepared to respond to transport related comments made by Kent County Council Highways & Transportation (KCC) and Ashford Borough Council (ABC) planners on the planning application. ABC’s comments are contained in Appendix A and KCC’s comments are contained within Appendix B. Responses to comments 3. We have provided the relevant transport comments raised by ABC and KCC in blue italics with our comments / recommendations below them. ABC’s comments 4. Street parking and the potential for parking on the proposed streets associated with the adjoining school use. Is this something you have thought about? It’s been suggested that a condition could be added limiting parking between certain hours to prevent people leaving their car for the entire day. 5. The Wye Free School Transport Assessment Addendum Note contained within Appendix C provides supporting text on how student and staff parking can be accommodated within the school site. Under the heading Proposed Parking Provision the note sets out the rationale behind the number of staff and student parking spaces, and drop off / pick up spaces that will be provided, all of which exceed the demand. The school has a successful Travel Plan which could provide further management on staff and pupil parking, and drop off / pick up activities. 6. Therefore, it is considered that the school has sufficient staff and student parking to supply the demand. However, double yellow lines would be extended into the site as far as the Unit 1’s driveway entrance on the northern side of Occupation Road and up to the visitor parking lay-by on the southern side of Occupation Road. See drawing 30827/AC/072_C. 7. I note you were asked to provide more 4-unit terraces, which you have done. This necessarily results in more remote parking and you are now showing two parking courts. The parking court in the northern corner of the site is very large (we would hope to limit courts to 6 cars). Is there scope to break up the hard surface in this area? 8. A significant amount of adjustment has already been made to the original site layout to accommodate the requests of ABC planners. Then to address comments made by KCC on the resultant site layout, a great deal of work was undertaken by the design team. Reducing the size of the parking courts would result in the need to find parking

transport planning practice...Transport Planning Practice . 30827/D/014a February 2020 2 elsewhere which would significantly impact on the layout of the site, particularly if tandem

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

  • transport planning practice

    30827/D/014a February 2020

    1

    Transport Planning Practice| 70 Cowcross Street | London | EC1M 6EL| Tel: 020 7608 0008 | [email protected]

    Residential Sites, Wye

    Transport response to Local Authority

    Introduction

    1. Transport Planning Practice (TPP) has been commissioned by Telereal Trillium to provide

    transport planning advice with regard to their development proposals for the Land to the

    north of Occupation Road, referred to as Site 8 in the WYE3 Masterplan area.

    2. This note has been prepared to respond to transport related comments made by Kent

    County Council Highways & Transportation (KCC) and Ashford Borough Council (ABC)

    planners on the planning application. ABC’s comments are contained in Appendix A and

    KCC’s comments are contained within Appendix B.

    Responses to comments

    3. We have provided the relevant transport comments raised by ABC and KCC in blue italics

    with our comments / recommendations below them.

    ABC’s comments

    4. Street parking and the potential for parking on the proposed streets associated with the

    adjoining school use. Is this something you have thought about? It’s been suggested

    that a condition could be added limiting parking between certain hours to prevent people

    leaving their car for the entire day.

    5. The Wye Free School Transport Assessment Addendum Note contained within Appendix

    C provides supporting text on how student and staff parking can be accommodated

    within the school site. Under the heading Proposed Parking Provision the note sets out

    the rationale behind the number of staff and student parking spaces, and drop off / pick

    up spaces that will be provided, all of which exceed the demand. The school has a

    successful Travel Plan which could provide further management on staff and pupil

    parking, and drop off / pick up activities.

    6. Therefore, it is considered that the school has sufficient staff and student parking to

    supply the demand. However, double yellow lines would be extended into the site as far

    as the Unit 1’s driveway entrance on the northern side of Occupation Road and up to the

    visitor parking lay-by on the southern side of Occupation Road. See drawing

    30827/AC/072_C.

    7. I note you were asked to provide more 4-unit terraces, which you have done. This

    necessarily results in more remote parking and you are now showing two parking courts.

    The parking court in the northern corner of the site is very large (we would hope to limit

    courts to 6 cars). Is there scope to break up the hard surface in this area?

    8. A significant amount of adjustment has already been made to the original site layout to

    accommodate the requests of ABC planners. Then to address comments made by KCC on

    the resultant site layout, a great deal of work was undertaken by the design team.

    Reducing the size of the parking courts would result in the need to find parking

  • Transport Planning Practice

    . 30827/D/014a February 2020

    2

    elsewhere which would significantly impact on the layout of the site, particularly if

    tandem parking was provided and therefore more visitor parking was required. Whilst

    KCC state that the use of parking courts is not best practice, they have not raised any

    objections to the layout with regards to the parking.

    9. Suburban footpaths on side of street need to be set behind a verge to avoid looking

    suburban. A series of street trees is essential. The AONB Unit has identified a need for

    more street trees (specifically on highway land) to filter views.

    10. The road and footway are supposed to form a shared surface with no kerbs. The

    currently proposed 1.2m wide footways will not be acceptable if they are set behind a

    verge. If the footways are to be set behind a verge they will need to be widened to 1.8m

    in order to be adoptable. The current shared surface arrangement has been agreed with

    KCC.

    11. In places the smaller lanes are too wide and regular and needs to be less formal with

    varied width to help naturally restrict speeds. KCC H&T have asked for raised table to

    restrict speeds but this approach is suburban and inappropriate on this rural site. Playing

    with street widths / alignment is a more responsive approach to reducing speeds in a

    rural setting.

    12. See response in paragraphs 17 and 18 below to KCC on this matter.

    KCC’s comments

    13. Section 4.4.6 of the Transport Assessment states:

    Covered cycle parking will be provided in garages or car barns for those units which

    have them. Sheds will be provided in the rear gardens of those units without car barns

    or garages for cycle parking.

    14. The above approach is acceptable, however this has not been fully translated onto the

    Proposed Site Plan with regard to storage/sheds in back gardens. This needs to be

    revised to show these at sufficient size to accommodate cycles to enabled them to be

    conditioned.

    15. Sheds have been shown within the rear gardens of units which do not have a garage or

    car barn. In addition, access routes to the rear of the terraced units have been provided.

    See the proposed layout contained within Appendix D.

    16. The highway layout is indicated as a shared surface to be used by both pedestrians and

    vehicles. This is acceptable as a layout to be adopted by the highway authority, however

    both east/west roads are in excess of 100m long and are effectively straight in

    alignment. To maintain low driven speeds, particularly important for a shared surface,

    these will require some form of traffic calming to maintain low speeds. Perhaps some

    form of raised table in the vicinity of the communal green space. With the above in mind,

    a minor amendment to the proposed highway layout is required.

    17. TPP discussed the above comment with KCC during a telephone conversion on 15th

    January 2020. KCC agreed that the layout and geometry of the Occupation Road site

    road has been designed to discourage high vehicle speeds and that most sections of the

    road are less than 60m long before there is a junction, bend or kink in the road. This

    helps to maintain driven speeds at 20mph or less. KCC also understand the

    environmental and noise implications of vertical (speed bumps) and horizontal (chicanes)

    speed restraint features and accept that they would be inappropriate for this

  • Transport Planning Practice

    . 30827/D/014a February 2020

    3

    development given the geometry of the proposed road and the residential site use i.e.

    vehicles braking and accelerating outside of residential properties. This is particularly

    pertinent for the southern road which will be carrying traffic for the AONB car park and

    the proposed industrial uses to the south.

    18. Therefore, KCC agreed that some form of contrasting surface treatment to the north and

    south of the ‘park’ area on the carriageway section of road. This would help to identify

    the presence of the ‘park’ and encourages speed restraint by highlighting a change in

    character of the street. The proposed development layout contained within Appendix D

    shows contrasting surface treatments to the south of the ‘park’ area and on approach to

    the ‘park’ on the northern road to warn drivers to reduce their speed on the straightest

    section of carriageway.

    19. Section 7 of the Transport Assessment details the proposed off site highway

    improvements. Alterations to the Olantigh Road / Occupation Road junction are proposed

    (Drawing 308/AC/072_B) which would improve visibility when exiting Occupation Road

    and bring it up to the correct standard for the 30mph speed limit. Also proposed are a

    set of raised table traffic calming features which will reinforce the speed limit to keep

    driven speeds low in the vicinity of the school and provide improved at-grade pedestrian

    crossing points for accessing the school and North Downs Way.

    20. Two sets of road narrowing features are proposed to encourage lower driven speeds on

    Olantigh Road close to Middlefield Cottage and Middlefield Lodge (drawings

    30827/AC/053_A and 30827/AC/048_A).

    21. A revision of the speed limit to reduce from 60mph down to 40mph with village gateway

    on Olantigh Road on approach to the ADAS site is proposed. The proposed alteration to

    the 40mph limit on Olantigh Road will need to be accompanied by an ATC speed survey

    to demonstrate current driven speeds. This would also be required at a later date as part

    of the consultation process with Kent Police in the processing of any future traffic

    regulation order to enable a change to the speed limit.

    22. Although the above proposed highway revisions appear to be acceptable, they need to

    be fully supported by a road safety audit. This is to demonstrate their acceptability and

    will need to provided with the supporting planning documents to demonstrate as part of

    the planning consultation that they are deliverable.

    23. An Automatic Traffic Counter (ATC) survey including speed surveys was undertaken on

    Olantigh Road within for a period of seven days between the 7th January to 13th January

    2020. The ATC was located just to the north of the ADAS site access, being secured to

    the first telegraph pole in that location. The results of the speed survey are summarised

    in Table 1. The survey data is contained within Appendix E.

  • Transport Planning Practice

    . 30827/D/014a February 2020

    4

    Table 1: Speed survey summary

    Time

    Northbound Southbound

    7 day average 5 day average 7 day average 5 day average

    85%ile

    (mph)

    Ave.

    (mph)

    85%ile

    (mph)

    Ave.

    (mph)

    85%ile

    (mph)

    Ave.

    (mph)

    85%ile

    (mph)

    Ave.

    (mph)

    0700 54.3 45.5 54.2 45.4 51.7 44.5 51.8 44.5

    0800 52.6 44.3 52.3 44.5 52.1 44.3 51.9 44.2

    0900 52.9 44.4 53.8 44.7 53 44.5 53.4 46.4

    1000 52.2 43.9 52.7 44.4 53.5 45.2 54.3 45.6

    1100 52.1 41.9 54.1 42.5 52 42.7 52.5 43.1

    1200 50.8 42.2 52.3 43.7 51.9 45.1 51.3 45.6

    1300 53.5 44.6 54.3 45.4 54.4 45.6 54.7 46.2

    1400 53.2 43.5 55.7 43.9 53 45 53.4 45.2

    1500 49.7 42.4 49.7 42.7 51.4 43.2 51.1 42.7

    1600 48.9 41.6 48.8 41.5 51.1 43.4 49.8 42.6

    1700 51.7 43.7 51.6 43.9 50.5 41.4 50.7 41.5

    1800 55.5 45.1 55.5 44.7 51.8 44.7 51.9 44.5

    12hr Ave.

    52.3 43.6 52.9 43.9 52.2 44.1 52.2 44.3

    24. As can be seen from Table 1, the 7-day two-way 85%ile average speed was 52.2mph

    and the 5-day two-way 85%ile average speed was 52.6mph which is approximately

    7.5mph below the current speed limit of 60mph. The 7-day two-way average speed was

    43.9mph and the 5-day two-way average speed was 44.1mph which is approximately

    16mph below the current speed limit.

    25. This demonstrates that the current driven speeds on Olantigh Road near the Site 4 ADAS

    access are already lower than the existing speed limit on what is a lightly trafficked,

    straight carriageway with good forward visibility. Therefore, with the introduction of the

    village gateway and 40mph speed limit signage, it is considered that the new 40mph

    speed limit will be adhered to by drivers.

    26. Separate Stage 1 Road Safety Audits (RSAs) have been undertaken for the proposed

    traffic calming features (village gateway and narrowing features) and the proposed

    alterations to the Olantigh Road / Occupation Road junction.

    27. The Stage 1 RSA recommendations for the traffic calming features are minor and can be

    addressed as part of the detailed design stage. These include the provision of high skid

    resistant surfaces on the southbound approaches to the carriageway narrowing features

    and that the street lighting is reviewed and upgraded if necessary at the narrowing

    features. Appendix F contains the traffic calming features Stage 1 RSA and the designer’s

    response report.

    28. The Stage 1 RSA recommendation for the Olantigh Road / Occupation Road junction is

    that the proposed junction geometry should be modified, in order to accommodate the

    types and sizes of vehicle anticipated to utilise the junction, thus mitigating the potential

    collision scenarios of head on, side impact or nose to tail shunt type vehicular collisions.

    29. The geometry of this junction was discussed with KCC early in the preparation of the

    WYE3 Masterplan Transport Assessment. This resulted in a 6.0m carriageway for

    Olantigh Road and a 5.5m carriageway for Occupation Road. The geometry was decided

    upon to slow down turning vehicles and provide better facilities for pedestrians. The

    junction has not been designed for constant HGV access but rather occasional access.

    Whilst it is accepted that the swept paths of delivery and refuse collection vehicles cross

  • Transport Planning Practice

    . 30827/D/014a February 2020

    5

    the centre lines of Olantigh Road and Occupation Road, such movements will be minimal

    and unlikely to be opposing on what is and will continue to be a lightly trafficked

    junction. It is worth noting that refuse collection vehicle movements will generally occur

    outside of the peak hours and one vehicle will be collecting for the surrounding area.

    Therefore it is unlikely there will be opposing movements of similar vehicles.

    30. With regards to the school coach movements, these will be tidal and therefore no

    opposing movements should be experienced. Coach movements would need to be

    managed by the school so that the first coach to arrive does not leave until the last

    coach has arrived and vice versa in the afternoon/evening. This is standard practice to

    reduce heavy vehicle movements in areas where school children are alighting and

    boarding. Appendix G contains the Stage 1 RSA and the designer’s response report.

    31. In terms of pedestrian connectivity, section 3.2 of the Transport Assessment discusses

    walking connections from the site. 3.2.1. details the existing footway of approximately

    1m in width on the eastern side of Occupation Road. This is sub-standard in width for

    existing purposes, even without the proposed 40 dwellings and potential for further

    dwellings on the nearby ADAS site.

    32. The drawing showing alterations to the Olantigh Road / Occupation Road junction

    (Drawing 308/AC/072_B) shows a widened footway on the western side of Olantigh Road

    (currently grassed area adjacent to existing buildings).

    33. Through the master planning process, it was always the intention of the developer to

    provide an improved footway in this location. This footway however is not detailed within

    the list of highway proposals nor the Transport Assessment.

    34. Although I do not doubt the intention to provide such a facility and in terms of delivery it

    would no doubt be easier to leave this until the adjacent site is developed. There is

    however the danger that should this proposal be granted, the site adjacent to this

    footway link may be dormant for years or even not be developed. As such in terms of it's

    importance locally, to provide safe access from the proposed site to the village centre, an

    improved footway link on the western side of Olantigh Road needs to be attached to this

    tabled planning application. Details to this effect should be provided for assessment.

    Having said this, subject to my other requirements outlined above being satisfied, then I

    would not object to this issue being settled by way of a planning condition.

    35. Drawing 30827/AC/081 shows the proposed footway connections to be brought forward

    as part of the proposed Olantigh Road / Occupation Road junction improvements.

  • Drawings

  • +48.30

    +49.93

    +49.93

    +49.00 EXT

    1312

    1110

    98

    76

    54

    32

    1

    50.45

    49.77

    49.99

    TP

    CL 49.44IC

    50.29

    51.49

    51.49

    VP

    VP

    48.5

    0RE

    G49.39

    G48.46

    G48.48

    GATE

    ER

    48.6

    6

    50.4

    5

    50.6

    4

    48.4

    5

    RWP

    RWP

    48.50

    47.91

    48.49

    LC

    LC

    LC

    LCLC

    LC

    LC

    LC

    LC

    LC

    G48.43

    G48.44

    G48.41

    G48.32

    GATEGATE

    GATE TP

    G48.47

    G48.56G48.47

    PP

    P

    ER

    ER

    RE

    ER

    D=0.95m

    D=2

    .50m

    D=2.5

    0m

    EP

    50.49

    50.44

    50.42

    50.51

    50.92

    50.6

    9

    51.5

    0

    51.1

    151

    .30

    50.51

    50.47 50.

    62

    50.74

    50.91

    VP

    GATE

    ST

    G50.89

    D=0.95m

    D=0.80m

    150Ø

    150Ø

    100Ø

    D=0

    .50m

    D=0.

    50m

    G

    D=0.95m

    SOAKAWAY

    KITCHEN

    GAS METER

    ELECTRICITYDISTRIBUTED INTOBUILDING

    ELECTRICITYDISTRIBUTED INTOBUILDING

    O

    C

    C

    U

    P

    A

    T

    IO

    N

    R

    O

    A

    D

    1 2

    3

    BASED ON ORDNANCE SURVEY MAPPING AND

    REPRODUCED BY TRANSPORT PLANNING

    PRACTICE WITH THE PERMISSION OF THE

    CONTROLLER OF HMSO © CROWN COPYRIGHT

    This drawing has been prepared for planning purposes and should not be used for construction.

    It should be read in conjunction with TPP document D014.

    T:\30000_Projects\30827 Residential Sites, W

    ye, Ashford\ACAD

    \072_C.dw

    g

    transport planning practice

    TRANSPORT PLANNING PRACTICE

    t: 020 7608 0008

    w: www.tppweb.co.uk

    70 Cowcross Street

    London, EC1M 6EL

    DRAWING NUMBER

    REV

    SCALE @ A3 DATE DRAWN BY CHECKED

    30827/AC/072 C

    RESIDENTIAL SITES, WYE, ASHFORD

    Proposed Olantigh Road / Occupation Road

    tied into site access road

    11/02/20 LD CWP

    1:250

    0 5m2.5

  • OLAN

    TIGH

    ROA

    D

    48.53

    48.16

    48.61

    48.60

    48.49

    48.50

    CL 49.44

    IC

    CL 48.35

    IC

    CL 48.49

    IC

    RWP

    RWP

    RWP

    RWP

    RWP

    50.29

    48.48

    48.47

    49.89

    48.50

    RE

    G49.39

    G48.48

    G48.46

    G48.48

    G48.60

    LC

    LC

    LC

    LC

    LC

    ER

    ER

    ER

    CL 47.21

    MH

    CL 47.18

    IC

    CL 47IC

    CL 48.48

    MH

    CL 48.48

    IC

    47.30

    47.30

    47.29

    47.35

    47.17

    47.64

    47.6547.65

    47.46

    47.45

    47.45

    47.46

    47.43

    47.42

    47.44

    47.45

    47.45

    47.45

    47.31

    47.19

    48.46

    48.66

    50.45

    50.64

    48.45

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWPRWP

    RWP

    RWP

    RWP

    RWP

    47.29

    46.99

    46.80

    47.20

    47.23

    47.2

    3

    47.24

    47.19

    47.18

    47.25

    46.31

    47.2947.30

    47.05

    48.50

    47.91

    48.49

    LC

    LC

    LC

    LC

    LC

    LC

    LC

    LC

    LC

    LC

    LC

    LC

    LC

    LC

    LC

    LC

    LC

    LC

    LC

    LC

    LC

    G46.98

    G47.05

    G47.06

    G47.02

    G47.04

    G47.04

    G47.08

    G47.21

    G47.24

    G47.24

    G47.27

    G47.23

    G47.25

    G47.23

    G48.43

    G48.44

    G48.41

    G48.32

    46.46

    46.54

    46.53

    46.42

    47.17

    47.17

    47.21

    47.20

    47.30

    NITROGEN TANKS

    47.28

    47.67

    47.15

    47.19

    47.26

    47.23

    47.23

    GATEGATE

    GATE

    GATE

    GATE

    GATE

    GATE

    GATE

    GATE

    MH

    EB

    SP

    47.17

    47.17

    47.15

    47.15

    47.14

    47.20

    AIR

    CON

    47.22

    47.12

    47.33

    47.30

    47.31

    47.31

    47.31

    47.32

    POND

    47.27

    47.28

    GS

    G

    ST

    TP

    TP

    G47.31

    G47.29

    G47.29

    G47.28

    G47.29

    G47.26

    G46.97

    G47.26

    G47.30

    G48.50

    G48.47

    G48.47

    G48.47

    G48.56

    G48.47

    47.25

    P

    P

    P

    RE

    ER

    ER

    ER

    RE

    ER

    47.00

    46.77

    46.73

    46.76

    46.77

    47.13

    47.07

    46.85

    46.88

    47.11

    47.17

    CL 47.11

    CL 47.12

    IC

    CL 47.34

    MH

    ST

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWPRWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    RWP

    G47.12

    G47.11

    G47.02

    G46.67

    47.23

    G47.10

    G47.18

    G47.17

    G47.17

    G46.84

    G47.23

    G47.19

    G47.18

    G47.17

    G47.21

    G47.12

    G47.21G

    47.16

    G47.13

    G47.18G

    47.22

    G47.19

    G47.20

    G47.17

    GS

    GATE

    GATE

    P

    P

    P

    P

    P

    P

    P

    P

    P

    P

    P

    P

    P

    P

    P

    P

    ICGASCL46.81

    RS

    G46.73

    G46.66

    G46.64

    G46.61

    VP

    TP

    P

    46.87

    46.84

    46.77

    46.70

    47.19

    47.25

    47.38

    47.46

    47.22

    47.13

    46.9746.66

    46.62

    SQUASH COURTS

    STORE

    RUSSELLLABORATORIES

    RUSSELLLABORATORIES

    G

    G

    ELEC

    THE KEMPECENTRE

    GAS PIPE

    D=0.50mD=0.50m

    100Ø

    100Ø

    D=0.40m

    D=0.40m

    D=0.4

    0m

    D=0.4

    5m

    D=0.6

    5m

    D=0.7

    5m

    D=0.3

    5m

    D=0.75m

    D=0.90mD=0.90m

    D=0.2

    5m

    D=0.5

    0m

    EOT

    D=0.4

    0m

    D=0.3

    0m

    47.06

    47.14

    D=0.20m

    D=0.8

    0m

    D=0.7

    0m

    D=0.6

    0m

    D=0.

    70m

    D=0.60m

    D=0.60m

    D=0.3

    5m

    D=1.1

    0m

    D=0.95m

    D=2.5

    0m

    D=2.5

    0m

    D=2.1

    0m

    D=0.80m

    D=0.25m

    D=0.30m

    CL 46.86

    MH

    D=0.50m

    D=0.5

    0m

    D=0.

    85m

    D=0.90m

    100ØD=1.20m

    MH BENEATH GARDEN FRAME

    100Ø

    D=0.8

    5m

    D=0.7

    5m10

    D=1.

    60m

    100Ø

    D=1.2

    5m

    D=1.2

    5m

    100Ø

    D=0.45m

    D=0.7

    5m

    D=0.9

    5m

    D=1.

    95m

    15

    SERVI

    CE TRE

    NCH 0.5

    5m

    RWP

    SUB STATION

    D=0.20m

    D=0.2

    0m

    D=0.7

    5m

    EOT

    150Ø

    EOT

    BLOC

    KED

    D=0.9

    5m

    100Ø

    D=1.2

    5m

    D=1.9

    5m

    D=1.2

    5m

    100Ø

    150ØD=1.65m

    D=1.70m

    UTR LOCKED

    D=0.30m

    D=0.90m

    D=0.70mD=0.70m

    100Ø

    100Ø

    D=0.95m

    D=0.80m

    150Ø

    150Ø100Ø

    D=0.5

    0m

    D=0.5

    0m

    D=0.75m

    63ØMDPE

    UTR

    UTR

    G

    S.ATH VEGETATION.

    SERV

    ICE

    TREN

    CH

    SERVICE TRENCH

    UTR

    D=0.95m

    UTR

    D=0.8

    5m

    D=0.85m

    D=0.2

    5m

    150Ø

    D=0.4

    0m

    150Ø

    SOAKAWAY

    SERVICE TRENCH

    GULLY SILTED

    GULLY SILTED

    ASSUMED

    ROUTE

    SILTED

    D=0

    .65m

    D=0.

    60m

    SILTED

    AR

    SILTED

    EOT BLOCKED

    SOAKAWAY

    SOAKAWAY

    COMBINED SEWER LOCATION FROM RECORDS

    SERVICE TRENCH

    D=0.

    60m

    D=1.1

    0m

    150Ø

    D=0.9

    5m

    OCCUPATION ROAD

    IMPERIAL COLLEGE

    MAIN CAMPUS

    IMPERIAL COLLEGE

    MAIN CAMPUS

    IMPERIAL COLLEGE

    MAIN CAMPUS

    IMPERIAL COLLEGE

    MAIN CAMPUS

    ASPHALT

    ASPHALT

    STORE

    UNMADE TRACK

    SHRUBS

    SHRUBS

    SHRUBS

    SHRU

    BSCO

    NCRE

    TE P

    AVIN

    G SL

    ABS

    GRASS

    GRASS

    CONCRETE PAVING SLABS

    CONC

    RETE

    PAV

    ING

    SLAB

    S

    CONCRETE PAVING SLABS

    ASPHALT

    ASPHALT

    ASPHALT

    ASPHALT

    ASPHALTCARPARK

    GRAVEL

    UP

    UP

    UP

    SHRUBS

    STORE

    UP

    UP

    UP

    UP

    CPS

    SHRUBS

    CONCRETE PAVING SLABS

    CONC

    RETE

    PAV

    ING

    SLAB

    S

    UP

    UP

    GRASS

    CPS

    SHRUBS

    SHRUBS

    CPS

    UP

    CPS

    BIKE

    SHE

    LTER

    UP

    CPS

    ASPHALT

    SPEED HUMP

    ASPHALT

    UP

    Heating

    /Gas/W

    ater/Ele

    cticity/C

    ommunic

    ations

    ASSUM

    ED PLASTIC

    WATER

    PIPE POSITIO

    N TAKEN

    FRO

    M R

    ECO

    RD

    S

    UN

    ABLE TO D

    ETECT BY G

    PR O

    N LO

    OSE,U

    NEVEN

    GR

    AVEL

    THE KEMPECENTRE

    THE KEMPECENTRE

    THE KEMPECENTRE

    RUSSELLLABORATORIES

    Heating/Gas/Water Pipes

    SOAKAWAY

    Heati

    ng/G

    as/W

    ater/E

    lectic

    ity/C

    ommu

    nicati

    ons

    RWP INTO GROUND

    RWP INTO GROUND

    SUBSTATION

    UP/DOWN

    STAIRS

    VEGETATION

    HORTIC ANNEX

    KITCHENETTEVEGETATION

    GAS SHED(TRANSCO)

    SHRUBSSHRUBS

    SHRUBS

    SHRUBS

    GAS

    METE

    R

    SINK

    SINK

    GAS METER

    VISI

    BLE

    SCAR

    VISIBLE SCAR

    VEGE

    HEDGE

    HEDGE

    VEGETATION

    FOUL ROUTE FROM

    TOILETS & COFFEE

    SHOP

    PLANT ROOM &AIR HANDLING UNITS

    FOUL ROUTEFROM SINK IN

    OLD DARK ROOM

    ELECTRICITYMETERS

    FOUL ROUTEFROM TOILETS

    INSIDE BUILDING

    MAIN PLANT ROOM

    1st FLOOR

    WATERMETER 30a

    FOUL ROUTEFROM TOILETS

    FOUL ROUTEFROM TOILETS

    FOUL ROUTEFROM 1st FLOOR

    TOILETS

    OSA

    OSA

    OSA

    SOAKAWAYASSUMED POSITION

    TAKEN FROM RECORDS

    ASSUMED POSITION

    TAKEN FROM RECORDS

    FOUL ROUTEASSSUMED FROM

    KITCHENETTE

    WATER PIPE FROM

    SERVICE TRENCHWITHIN BUILDING

    BASEMENT PLANT ROOM

    INCLUDING WATER, GAS &

    ELECTRICITYFED FROM SERVICE

    TRENCH WITHIN BUILDING

    DEPTHS???

    FOUL ROUTE FROM

    CLASSROOM SINKS

    FOUL ROUTE FROM

    CLASSROOM SINKS

    FOUL ROUTE FROM

    CLASSROOM SINKS

    FOUL ROUTEFROM TOILETS

    ASSUMED ROUTE

    ASSUMED ROUTE OF UTILITIES IN THIS AREA

    UNABLE TO SURVEY

    DUE TO NO ACCESS

    HORTIC DEPT.

    O

    C

    C

    U

    P

    A

    T

    I

    O

    N

    R

    O

    A

    D

    O

    L

    A

    N

    T

    I

    G

    H

    R

    O

    A

    D

    G:0.3S:6

    H:5

    .30

    +49.93

    +49.93

    +49.00 EXT

    +48.50 EXT

    65

    43

    21

    OLAN

    TIGH

    ROA

    D

    2

    Wye School

    36

    20

    Grid

    Bramleys

    El Sub Sta

    El Sub Sta

    Cattle

    Pool1

    47.1m

    Swimming

    BASED ON ORDNANCE SURVEY MAPPING AND

    REPRODUCED BY TRANSPORT PLANNING

    PRACTICE WITH THE PERMISSION OF THE

    CONTROLLER OF HMSO © CROWN COPYRIGHT

    Based on drawing number 50697. TPP REF - IN_23. and

    drawing Wye OS. TPP REF - IN_15

    T:\30000_Projects\30827 Residential Sites, W

    ye, Ashford\ACAD

    \081.dw

    g

    transport planning practice

    t: 020 7608 0008

    w: www.tppweb.co.uk

    70 Cowcross Street

    London, EC1M 6EL

    DRAWING NUMBER

    REV

    SCALE @ A3 DATE DRAWN BY CHECKED

    TRANSPORT PLANNING PRACTICE

    This drawing has been prepared for planning purposes and should not be used for construction.

    It should be read in conjunction with TPP document D014.

    30827/AC/081 -

    RESIDENTIAL SITES, WYE, ASHFORD

    Footway connections to be brought forwards with

    the Olangtigh Road / Occupation Road

    junction improvements

    1/500 11/02/20 LD CWP

    Key:

    - Kerbs / Channel Line

    - Back of Footway

    - Road Markings

    - Double yellow lines

    - Visibility Splay (2.4m X 43m)

    Raised table surface treatment to

    be based on KCC's pallet of

    materials. Surface will be

    contrasting from adjacent

    carriageway surface treatment.

    No.34 Olantigh

    Road driveway

    Raised table surface

    treatment to be based on

    KCC's pallet of materials.

    Surface will be contrasting

    from adjacent carriageway

    surface treatment.

    North Downs

    Way footpath

    connection

    2.0m footway connection

    to the south including

    Sites 3, 7 and 9 and the

    rest of the village

    2.0m footway

    connection to

    Site 6

    2.0m footway

    connection to the

    north including

    Site 4 ADAS

    Drawings.pdf072_C.pdfSheets and ViewsA3-L

    081.pdfSheets and Views081