Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
TransPennine Route Upgrade –
Value Engineering through
Geotechnical Data management
Callum Irving (TSP)
Paul Chaplin (Central Alliance)
What Could Possibly Go Wrong ?
Ground Investigation ConstructionDesign
Great Western Railway
Modernisation
Add company logo here
• 650+ (+ ???) Locations
• 5000+ samples
• 13000+ Laboratory tests Scheduled
• 74000+ Results
• Not to mention In-Situ Tests and Site Observations not included
• 16,000+ elements of the GWRM data on Project Wise in pdf/excel/word/email
• 200+ Holes lost ~£300,000 of information
After Quality Control Measures Introduced
• 440 Holes with reliable data
• GI Planned reduced (Damage Mitigation cost reduction)
• GI programme recovered (Expertise in Geology)
• Design Information available in “real time”
TRUe Project Overview
ABS 75
CP 5
DP 34
RC 11
SCP 296
TP 4
WLS 40
CSW 63
WLS + RC 13
WLS + DP 38
Total 579 locations (to
date)
No. of Shifts: Approx 150
Programme: 18 Apr – 12 Nov 2017
Cost: Approx 800k
Communication is Key• Pre-startup Meetings – Building the Relationship from the outset
• Single Point of Contact from the Investigation Supervisor and
Contractor
• Formulation and Delivery of Data Management Plan – a two-way
street
• Both Contractor and Investigation Supervisor (IS)/Data
Manager(DM) understanding the end goal to be achieved
• Clarity of what is expected of the Contractor by the IS
• Queries / Issues arise – pick up that phone
Data Management Plan (DMP)
Data Life Cycle
GI
Proposed
Access
Planning Site LaboratoryGround
InformationDesign
ConstructionVerificationLessons
LearnedStorage
Project
Feasibility
3rd Party
(BGS)
Project
Scope
Defining the Level of Detail (LOD)
Design Process Construction and Verification
Add company logo here
TSP
VMS Alliance
Central Alliance
LABSSITE
Network Rail
Investigation Supervisor
Data Manager
(DM)
Site Engineer (SE)
SE
DM
DM Role Quality Assurance and Quality Control of the data deliverables and check of suitability for design in line with UK BIM strategy
GI contractor. Contracted to gather, collect and provide data to the client in line with client remit. NOT TO APPROVE OR ASSESS FIT FOR PURPOSE
Principal Contractor + Principal Designer
CLIENT
Samples
GI Data Assurance Report
GI Reports + Progress
GI SPEC
DMP
COCSchedules
COCSchedulesDatabase transfers
Investigation Supervisor (IS)
Add company logo here
IS Expertise: • Engineering Geology
• Engineering
Geomorphology
• Hydrogeology
• Ground Investigation
o Procurement
o Planning
o Techniques
• Ground risk
• Design Knowledge
TSP Designer Representative
• Knowledge of design process
• Checking data is suitable for
design
• Ensuring that all data from
site is reported to the
designer
• Ensuring that data is retained
and passed on
How can IS
assist Site
Engineer?- Expected geology at
site
- Predicted ground
risks
- Applicability of
technique/plant
- Site access & egress
- Effects on wider
project
Implementing
changes to GI
scope from
wider GRIP
3(OS) project
Quality
control of
information
from site
TSP Data Manager
SITE CA TSP
TSP
Proposed
Locations CA
LAB
AGS COC and
Schedules Only
Closing The Loops
• Using the tools/fields available within HBSI for headline info
• Both Chains of Custody and Schedules issued in AGS Format
• Chains of Custody and Physical Sample Batches registered against Schedules
• Schedules not crossing Chains of Custody – try to maintain a 1:1 relationship
• Status of Schedule defined at outset – at any transfer point both the IS and the Contractor knows what should be
contained in their dataset
• Using the Remarks field for additional / pertinent information
• Central Alliance using the LBST tables to keep track of the Geotechnical Testing
What have been the hurdles, and
continue to be?• Non-standard approach to Testing Suites / Test Naming
across the industry / regional offices of same company
• Implementation of the AGS Guidance by Consultants /
Investigation Supervisors – hard and fast, or flexible?
• Slow speed of change within the AGS Standard – has
to be able to react quickly to industry needs
• Under appreciation of what the format can provide and
how fast it can be provided
• Limited understanding / implementation within the
industry of the use of LBST/LBSG groups
• Tools to Schedule Tests exactly as AGS guidance
incomplete
• Requirement of custom tools for automated data
validation – particularly in relation to Environmental
Testing
But in our Favour…..
• Software Providers that are wanting to push the envelope
• Investigation Supervisors making clear the Level of Detail required for their
specification to be met
• Lab Managers (Environmental and Geotechnical) that are keen to improve
data quality to create as complete a dataset as is possible
• Contractors who understand that a complete, quality assured dataset
enables the Investigation Supervisor to start making design decisions while
the GI is still being undertaken.
• A Data Format committee willing to listen to the people who are promoting
it’s use and most enthusiastic about it’s many benefits
When the dust settles….
• What have we learned?
• Post completion analysis – What worked / what didn’t?
• Liaising with Lab Managers, Software Vendors – to
improve best practice
• Identify bottlenecks / breakdowns
• Reviewing the actual use of the end data product