TRANSMISSION SYSTEM KERALA 2015-32
K ASOKANDIRECTOR
INSTITUTE FOR SUSTAINABLE DEVELOPMENT AND ENERGY STUDIES (InSDES)
NEED FOR ADEQUATE TRANSMISSION STSYEM
• Generation capacity addition – limited chances• Existing generation mainly in Central / Southern
parts of Kerala• Demand in northern parts of Kerala increasing
at faster rate• Increased import requirement to meet demand• Transport of power to load centres
TRANSMISSION TO FECILITATE
• Import of sufficient power from outside• Evacuation of power from generation projects
within state• Efficient transfer of power to load centres• Grid map
• Kerala• South India
IMPORT OF POWER
• Existing system• Total capacity
• 4500 MW (Possible 2000 MW only due to constraints)
• Constraints• Inter regional• S1 - S2 corridor congestion• Overloading of inter state lines to Kerala
IMPORT OF POWER contd
• Future import requirement• Proposals to increase import
• Sufficient to meet demand up to 2031-32• 400 KV link between Trivandrum – Tuticorin for future
EFFICIENT TRANSFER OF IMPORTED POWER
• 400 KV network within state required– Proposed works• Madakkathara - Areacode DC line by 2017 - 18• Areacode – Mylatti DC line by 2018 - 19
POWER EVACUATION FROM GENERATION PROJECTS
• Proposals for power evacuation from new generation projects
STRENGTHENING OF EXISTING NETWORK
• To overcome inadequacies– Proposals
• To meet the future demand– Projected demand– Existing substations– Future requirements• 400 KV substations• 220 KV substations
MAJOR ISSUES
• Objection from landowners• For cutting trees• For placing towers
• Delay in land acquisition• Contract failures
REMEDIES
• Narrow based towers / Monopoles• Multi voltage / multi circuit towers• EHT UG cable• Submarine cable• HVDC transmission• Higher capacity conductors / HTLS conductors• GIS / Hybrid stations• Existing ROW for new lines• Simplify LA procedure• New system for tendering / selection of
contractors• Timely decisions / Timely payments• Route/Technology options
• Discussion with political parties
ACTION REQUIRED
• Completion of ongoing projects on war footing
• Timely completion of already sanctioned lines• Follow up action with CEA / SRPC/ PGCIL• Renovation / up gradation of existing system• Adopting new technologies and new systems• Long term planning