36

Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

Embed Size (px)

Citation preview

Page 1: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008
Page 2: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

Transmission Expansion

Kansas Wind and Renewable Energy Conference

Topeka, KSSeptember 23, 2008

Page 3: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

3

Overview

• SPP Background• SPP Transmission Expansion Plan• 2008 EHV Overlay Study • Joint Coordinated System Plan• Cost Allocations in SPP

Page 4: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

4

SPP System: 230 kV and above

Page 5: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

5

Transmission Expansion

Amount of Transmission

Co

st

Congestion Management Cost

Transmission Expansion

Reliability

SPP Today

Infinite Bus

Minimum Transmission

Need for More Transmission

Page 6: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

6

Quote from MISO RECB Order Issued July 23, 2007

“We need a true nationwide transmission version of our interstate highway system; a grid of extra-high voltage backbone transmission lines reaching out to remote resources and overlaying, reinforcing, and tying together the existing grid in each interconnection to an extent never before seen. . . . Indeed I would tend to assume that a large multi-state 500 or 765 kV transmission line would not have much difficulty showing net benefits over a very broad region. . .”

• Suedeen Kelly, FERC Commissioner

Page 7: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org 7

STEPWhat Is It?

Page 8: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

8

SPP Transmission Expansion Plan

• SPP Transmission Expansion Plan (STEP)• “Everything pertaining to transmission

development”

1. Generation Interconnection Upgrades

2. Transmission Service Upgrades

3. Reliability Standards Upgrades

4. Economic / Sponsored Upgrades

5. Planned Upgrades

6. EHV Overlay / JCSP +

Page 9: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

9

Page 10: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

10

Page 11: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

11

Page 12: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

12

SPP Generation Interconnections (KS)

SPP Wind Farm statistics based on nameplate capacities (KS data)• 1,800 MWs in-service (350 MW)• 2,100 MWs under construction (1,405 MW)• 1,600 MWs with signed IAs on suspension (549 MW)• 4,800 MWs with IAs pending/Facility Studies (1,555 MW)• 6,300 MWs with Impact/Feasibility Studies in process (2,953 MW)• Almost 32,000 MW with Feasibility Studies requested (7,702 MW)

Explosion of Generation Interconnection Requests • 161 active requests (14,639 MW of Wind in KS)• Significantly more wind than SPP peak demand

Generation Queuing Task Force (GQTF) • Limit queue• ID project milestones• Possible GI clustering

Target MOPC/BOD October meetings for recommendations

Page 13: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

13

Transmission Service Issues

FERC 890 compliance.

3rd party impacts, seams issues are problematic.

Aggregate Study Improvement Task Force (ASITF) recommendations approved by MOPC in April to expedite and improve the Aggregate Study process.

Proposing to pair AG studies to allow SPP to catch up in processing past and future requests.

Page 14: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

14

Reliability Standards Planning

NERC Reliability Standards match SPP Criteria. Projects needed for reliability are base plan funded with revenue requirement cost allocations of 33% to all loads and 67% to project benefactors as measured by MW-MI impacts.

Some members have stricter standards for load pockets. Projects to meet higher standards for TOs are eligible for zonal cost recovery.

Appropriate definition of reliability is being discussed to consider probabilistic metrics

Page 15: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

15

Economic Planning

Reliability and Economics are Inseparable

Economic Upgrades – sponsored under existing tariff but eligible for credits based on new service sold

Balanced Portfolio • Postage stamp cost allocations for a portfolio of

Economic Upgrades which benefit SPP as a whole, and for which each zone realizes benefits in excess of their costs

• Tariff language has been approved and filed at FERC• Balanced Portfolio in final stages of development

Page 16: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

1616

Portfolio 3Portfolio 3

Page 17: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

17

Portfolio 3-APortfolio 3-AIatan

Nashua

Seminole

Muskogee

El Dorado

Longwood

Chesapeake

Tolk

Reno CoSpearville

Wichita

ClevelandSooner

Anadarko XF

Swissvale – Stilwel Tap

SummitKnoll

Axtell

Potter

Substation UpgradeNew Transmission Circuit

Page 18: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

18

Portfolio 3-BPortfolio 3-BIatan

Nashua

El Dorado

Longwood

Chesapeake

Reno CoSpearville

Wichita

ClevelandSooner

Anadarko XF

Swissvale – Stilwel Tap

SummitKnoll

Axtell

Seminole

Muskogee

Substation UpgradeNew Transmission Circuit

Page 19: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

19

Adjusted Production Cost Results

• Results shown for both 345 kV and 765 kV construction (with 345 kV operation)

• 765 kV includes• Spearville – Knoll 765 kV• Seminole – Muskogee 765 kV

• Wind modeled at 2,600 MW (year end, 2008 levels)

2012Project Cost ($M)

Proj 10 Year SPP Benefit ($M) SPP B/C

Portfolio 3-A $585 $776 1.33 Portfolio 3-B $545 $693 1.27

Portfolio 3-A $761 $776 1.02 Portfolio 3-B $721 $693 0.96

345 kV Construction

765 kV Construction

Page 20: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

20

B/C Per Zone

(1.00)

(0.50)

-

0.50

1.00

1.50

2.00

2.50

3.00

3.50

4.00

AEPWEM

DE

GRDA

KCPL

MID

WM

IPU

OKGE

SPCIUT

SUNC

SWPS

WEFA

WEPL

WERE

Zone

B/C

(10

yr)

Portfolio 3a

Portfolio 3b

Portfolio Balance

1.0 = Balanced

Page 21: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

21

Next Steps on Balanced Portfolio• CAWG meeting tomorrow in Dallas• SPP Staff recommends that Portfolio 3 and 3-A be

used for future analysis• Future (2017, 2023) analyses • Scenarios

1. Higher Wind

2. Carbon Regulation• Impact on reliability plan (negative and

positive)• Leading portfolio moved forward to

construction

Page 22: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

2222

2008-2017 STEP

• 2008-2017 SPP Transmission Expansion Plan (STEP) approved by BOD in January 2008

• $2.2 B of transmission projects over 10 year horizon with almost $800M of transmission projects requiring financial commitments in 2008-2011 and $465M of major economic upgrades primarily in KS (costed at 345 kV)

Page 23: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

23

Page 24: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

2424

Updated EHV Overlay Study

• Quanta Technology Report posted at http://www.spp.org/section.asp?group=1216&pageID=27

• Analysis of Alternative 5 from original study does not support continued grid build out at 345 kV, but demonstrates that 765 kV solution is appropriate when wind penetration exceeds 4,600 MW

• Soliciting input from stakeholders on results to date, issues, concerns at [email protected]

Page 25: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

2525

New Wind in Updated EHV Overlay Study

Kansas 6,600 MW 31.9%

Missouri 750 MW 3.6%

New Mexico 300 MW 1.4%

Oklahoma 8,550 MW* 41.3%

Texas 4,500 MW 21.7%

TOTAL 20,700 MW 100% * Includes 4,450 MW in Oklahoma Panhandle

Page 26: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

2626

Potential EHV Overlay Mid-Point Design for 13.5 GW Wind

Potential EHV Overlay Mid-Point Design for 13.5 GW

Wind

Page 27: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

2727

Updated EHV Overlay Study Findings

Focus on midpoint designs to collect / deliver 13.5 GW of new wind in SPP• 5.5 GW to SPP• 3 GW to WECC via HVDC• 2.5 GW to northeast• 2.5 GW to southeast

$8 billion at $2 million / mile engineering and construction costs + $65,000 / mile for Rights-of-Way• 2,250 miles of 765 and 500 kV in SPP• Almost 600 miles of 765 kV in new

interconnections and connectivity in neighboring systems

Page 28: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

2828

2008 EHV Overlay Next Steps

• SPP Transmission Working Group supports further work• Scope being finalized to identify alternative plans and

sensitivities for economic analyses to be concluded in 4th Quarter 2008

• Review and incorporate new data, objectives, etc. as appropriate into concurrent plans• e.g., see DOE’s “20% Wind Energy by 2030” report released

May 12th at www.20percentwind.org. • Nebraska entities integration into SPP• Must be robust, flexible and coordinate with neighbors’ plans.

• Must demonstrate incremental value and merits of 765 vs. 345 kV overlay in SPP

Page 29: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

29

Page 30: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

30

Page 31: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

31

JCSP Next Steps

• Evaluate existing RPS baselines, as well as a 20% National RPS as part of 2008 NREL/DOE Eastern Wind Integration Transmission Study (EWITS)

• Next Meeting October 2 in Carmel, IN

• Studies will be used to demonstrate the value of bulk power transmission to harvest best wind resources in central plains, rather than build local wind to met local requirements.

• Check out www.jcspstudy.org

Page 32: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

32

Wind Integration Issues

• Operational issues / reliability concerns warrant further investigation to address wind integration challenges• Developing scopes of wind integration and penetration

studies

• Further dynamics and reactive compensation analyses required

• SPP staff / members involved in numerous industry initiatives on wind integration

• EHV build out, regardless of drivers, will require changes to power system planning and operations

Page 33: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

3333

Cost Allocations Are Key

• Cost allocations can be a barrier to effective transmission expansion planning, but need not be. Witness EHV expansion by South Central Electric Companies in the 1960s.

• FERC Order 890 is forcing industry to address this topic

• SPP Cost Allocation Working Group in process of finalizing recommendations on Balanced Economic Portfolio of 345 kV transmission expansion projects, primarily, with associated postage stamp cost recovery.

• Power industry can not afford to undervalue transmission anymore.

Page 34: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

3434

Reliability

Base Plan Funding

33% / 67%

Criteria or

Designated Resource

Transmission

2005

Economic

Balanced Portfolio

Postage Stamp

Benefits / Cost ≥ 1

345 kV and above

Filed on 08/15/08

EHV

Postage Stamp

765 kV

Work in Progress

Page 35: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org

35

Questions?

Page 36: Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008

www.spp.org 36

Jay Caspary Director, [email protected]