42
1 Transmission Cost Reduction Sean Kelly April 2015

Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

1

Transmission Cost Reduction

Sean Kelly April 2015

Page 2: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

Chaired by Benj Sykes & Matthew Hancock

Members are all offshore developers (13),

supply chain (8), public sector (7)

2

Page 3: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

Sources: For FID in 2014 and earlier – data from ORE Catapult cost reduction monitoring report; LCoE values are averages for projects with FIDs approximately in the date ranges

shown. For 2016 LCoE is calculated from published CfD strike prices for NNG and EA-1 (first 15 years) and 2017 forward price (10 years), 9% discount rate.

Out-turn

Out-turn

Expected

From bid prices Target

Page 4: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

4

Page 5: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

Offshore

Transmission

Capex £/kW

Year in

Service Source: OFTO transfer value as published by Ofgem. Overall transmission costs closely track this

Page 6: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

6

Page 7: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

7

Size of each picture indicates relative cost

(average over all projects for which an

OFTO transfer value has been calculated)

Page 8: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

8

Page 9: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

9 Onshore sub 1km of Cable

Offshore sub

Capex £/MW

years

Note: some data points removed due to missing /

non-comparable data or to ensure anonymity

Page 10: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

10 Onshore sub

Offshore sub

?

1km of Cable

Capex £/MW

years

Note: some data points removed due to missing /

non-comparable data or to ensure anonymity

Slight rise, could

be statistical

fluke?

Page 11: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

11 Onshore sub

Offshore sub

?

?

1km of Cable

Capex £/MW

years

Note: some data points removed due to missing /

non-comparable data or to ensure anonymity

Slight rise, could

be statistical

fluke?

Slight fall, could

be statistical

fluke?

Page 12: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

12 Onshore sub

Offshore sub

?

?

1km of Cable

Capex £/MW

years

Note: some data points removed due to missing /

non-comparable data or to ensure anonymity

Slight rise, could

be statistical

fluke?

Slight fall, could

be statistical

fluke?

Clear rise due to

need for 400kV

connection and

equipment for

“grid code

compliance”

Page 13: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

13

Page 14: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

Offshore

Transmission

Capex £/kW

Page 15: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

15

Page 16: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

Cost Reduction

Improve Implementation

(“Do it Better”)

Lower priority

Improve Design

(“Don’t do it at all”)

Fewer and larger

Offshore Substation Onshore substation Cables

Mount offshore

transformers on

turbines

Harmonic filters

SVCs (reactive power)

Lower priority

Page 17: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

17

Page 18: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

18

Cable capex

per km

Cable capacity

Based on GB offshore wind projects to date, the cost of cable seems

independent of cable capacity…

Benchmarking study by Ofgem only identified cable length as a cost driver.

Page 19: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

If cost of cable was really independent of capacity it would imply huge

cost savings are possible by using larger cables.

200MW 200MW

400MW

= 2x200MW cables – same capacity as 1x400MW

But if cost is independent of rating it implies that

1x400MW option costs half as much as

2x200MW!

Page 20: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

20

Cable capex

per km

Cable capacity

Cable capacity is a cost driver if the change in capacity is large enough

This graph shows cable cost over a much wider range of capacities

Suggests that 1 double-size cable costs ~40% less than 2 smaller cables

Page 21: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

Largest wind farm

cable in Denmark

today is twice the

capacity of the largest

cable in Britain

Yes: Denmark (Energienet) is doing it already.

Page 22: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

…and Britain is catching up

All designed by either

DONG or Energinet

Page 23: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

Larger Conductors (physically bigger cables)

Higher Voltage (physically bigger cables)

Dynamic Ratings (more power through the same size of cable)

Largest Danish export

cable (400MW, 220kV,

270mm).

Relative to the GB’s

largest cable, this uses

all 3 techniques to

increase capacity

Largest in-service GB

export cable (circa

200MW, 150kV,

234mm diameter)

400MW cable

is physically

larger than

200MW cable

… but not that

much larger.

Page 24: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

Dynamic Ratings – operate cables beyond their normal (continuous) rating

Makes use of the fact that wind power is usually only at maximum output for

short periods

Cable

tem

pera

ture

Time (weeks)

90°C

(maximum

allowed)

Pow

er

Normal

(continuous)

rating of

cable

Cable doesn’t overheat

because power is reduced Cable would have overheated

if power hadn’t been reduced

Page 25: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

Temperature of a wind farm cable.

Power is greater than continuous rating on several occasions – but never

for long enough for the cable to overheat

And actual temperature lower than expected: even more capacity possible

1 week

Page 26: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

26

Page 27: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

Pie indicates total

installed cost of

offshore substation

Page 28: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

Pie indicates total

installed cost of

offshore substation

Page 29: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

Pie indicates total

installed cost of

offshore substation

Page 30: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

1 Transformer.

2 220kV switchgear.

3 33kV switchgear,

protection, etc.

4 Standard wind

turbine (tower goes

through hole in deck

and attaches to

foundation).

5 Foundation

installed using wind

turbine installation

vessel.

6 Deck and all

equipment lifted

onto foundation by

wind turbine

installation vessel.

Then the turbine

itself is installed.

Source: Siemens

Page 31: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

Source: Siemens

Page 32: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

32

Page 33: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

33

Page 34: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

34

Onshore substation cost

Page 35: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

35

Onshore substation cost

Page 36: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values
Page 37: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values
Page 38: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

38

Page 39: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

Cost savings for a far offshore Round-3 project.

Relative to Round-2 technology

Typical far-offshore project: 170km

Page 40: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

Cost savings for a far offshore Round-3 project.

Relative to Round-2 technology

Typical far-offshore project: 170km Note that these are

best-case values.

OWPB has set

lower targets since

not all cost

reduction

opportunities will

work on all projects

Page 41: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

41

Page 42: Transmission Cost Reduction · Cost savings for a far offshore Round-3 project. Relative to Round-2 technology Typical far-offshore project: 170km Note that these are best-case values

42

For further information:

Sean Kelly +44 7767 298 983