Pla de Transformació del Barri de La Mina
Transformation Plan for the Neighbourhood of
La Minaa a
Pla de Transformació del Barri de La Mina
AIM
To transform the La Mina neighbourhood and to agree on and establish an integrated and global proposal for intervention to improve housing conditions, community life and coexistence, with the goal of strengthening the community in the short and long term and for it to become a fully integrated part of Sant Adrià de Besòs and g pCatalonia.
2
Pla de Transformació del Barri de La Mina
1 9 9 03
Pla de Transformació del Barri de La Mina
4
Pla de Transformació del Barri de La Mina
5
Pla de Transformació del Barri de La Mina
The La Mina neighbourhood of Sant Adrià de Besòs.Photo from the late 90s, prior to the Consorci’s intervention.
6
Pla de Transformació del Barri de La Mina
Background
The neighbourhood of La Mina belongs to the town of Sant Adrià de Besòs on the outskirts of the city of Barcelona.It was built at the beginning of the seventies as part of a slum g g pclearance project to rehouse the population from different urban slums in Barcelona.2,700 houses were built with official protection under a social housing project.By 1975 there were already 15,133 people living in the neighbourhood.In the 1975 census, the figures were:
M i i l f S t Ad ià d B ò 33 473 lMunicipal area of Sant Adrià de Besòs: 33,473 people.Neighbourhood of La Mina: 11,848 people (2,222 families).
Surface area of the neighbourhood of La Mina: 0,59 km2Surface Sant Adrià de Besòs: 3,87 Km2
7
Pla de Transformació del Barri de La Mina
8
Pla de Transformació del Barri de La Mina
9
Pla de Transformació del Barri de La Mina
10
Pla de Transformació del Barri de La Mina
11
Pla de Transformació del Barri de La Mina
1 9 7 2
1 9 7 312
Pla de Transformació del Barri de La Mina
1970s
The population was mostly made up of immigrants coming from other parts of the Spanish state.The population that came to live in the neighbourhood lacked social and educational skills. The population also had a very low level of income.Twenty percent of the population was ethnically gypsy.
First years of the neighbourhoodThere was a high level of unemployment and of precarious employment.Physical isolation.High level of heroin consumption.Appearance of organised criminal groups selling drugs.High levels of anti-social behaviour.
Strong deterioration of public spaces and housing.13
Pla de Transformació del Barri de La Mina
14
Pla de Transformació del Barri de La Mina
1980s and 1990s
Public intervention was unable to produce an improvement in the
social situation.
Each public administration (state, autonomous and local) had their
own intervention plan in accordance with their competencies.
The intervention plans were not co-ordinated.
There were yearly interventions without any long-term planning.
In some cases the intervention plans did not have sufficient resources.
There were action plans without the sufficient capacity to provide anThere were action plans without the sufficient capacity to provide an
in-depth and long term answer to the problems of the neighbourhood.
15
Pla de Transformació del Barri de La Mina
2000
An institutional agreement was reached between Generalitat de Catalunya (Catalan Government) and the local council in Sant Adrià de Besòs to set up a global intervention plan, co-ordinate all the public bodies involved and supply the sufficient resources.
The Catalan Government and the Sant Adrià Council together with Barcelona City Council and the Diputació de Barcelona (Provincial Government) set up in June of 2000 the Consorci del barri de La Mina (La Mina Neighbourhood Partnership) as a legally sanctioned entity.
16
Pla de Transformació del Barri de La Mina
Area of Action
The Consorci del barri de la Mina (administration partnership) set up a Transformation Plan with a lifetime of ten years and with various areas to be acted upon:
SocialSocialEducationalCulturalSocio Labour InsertionHousingHousingPublic spacesCrime prevention and securityEconomic developmentUrban developmentUrban development
The four partner administrations provided the Transformation Plan with an unprecedented initial sum of 55 million euros to finance the project
17
Pla de Transformació del Barri de La Mina
The aim of the La Mina transformation plan was - and continues to be - to provide responses and solutions to the following deficiencies
and problems that exist in the neighbourhood
Significant educationalPhysical isolation of the area
Nonexistent or low professionalSocial
Significant educational deficits
among the populationImply a high level of unemployment
professional qualifications
Soc aisolation
Informal and illicit activities
Aim of the PTBM
respond to:Degradation of urban and
environmental surroundings
Lack of civic-mindedness
Weakness of social networks
g
18
Pla de Transformació del Barri de La Mina
HOW WE HAVE TACKLED THE SHORTAGES
Rehabilitate housing and improve access
to buildings
Social, educational, cultural and sports
Cooperation in improving personal safetyp
facilitiespersonal safety
Social action plan
Urban development of public spaces
Replotting project;New housing
19
Pla de Transformació del Barri de La Mina
20
Pla de Transformació del Barri de La Mina
21
Pla de Transformació del Barri de La Mina
PROPERTY CONTRIBUTED RESULTING PROPERTY
22
Pla de Transformació del Barri de La Mina
23
Pla de Transformació del Barri de La Mina
2000-2010 CONSORCI DEL BARRI DE LA MINAData is shown in millions of euros
Actions-Expenses BUDGET 2000-2010
EXECUTED 2000-2007
% EXECUTION2000-2007
Amount % Amount %
20.95 16.2%
20.14 15.5%
7.45 5.8%
26.77 15.4%
19.33 11.1%
10.20 5.9%
78.8%
103.5%
73.5%
Social
Social, educational, cultural and sports facilities
Improving access to housing and renovations
22.46 17.3%
0.7 0.5%
30.12 23.2%
21.83 12.6%
48.46 27.9%
40.31 23.2%
105.1%
2.2%
74.6%
Urban development of public spaces and connectivity
New protected housing and demolitions undertaken
Replotting project
22.59 17.4
5.5 4.0%
0.00 0.0
6.80 3.9%
---
75.0%
TOTAL 129.56 100.0% 173.70 100.0% 75.1%
Value of land ceded by administrations
Structure
24
Pla de Transformació del Barri de La Mina
SOCIAL ACTION PLAN
1. Training and occupational integration
7. Public space andcivic-mindedness
3 million euros annually
(average 2000-2007)
C f ti 6 Social and2 Balancing family Courses of action 6. Social andeducational support
2. Balancing family and professional lives
3. Development of the local economy
5. Improving coexistence and
civic-mindedness
4. Community participation and development
25
Pla de Transformació del Barri de La Mina
SOCIAL ACTION PLAN
Create opportunities
1. Training and
opportunities for training and
insertion in an integrated way
1. Training and occupational integration
Create possibilitiespossibilities
for accessing the job market
26
Pla de Transformació del Barri de La Mina
1. Training and occupational integrationSOCIAL ACTION PLAN
OBJECTIVES
ACTIONSCreate opportunities for training and insertion in an integrated way
• Integrated itineraries for insertion. (Project in operation)
-Young people, women, adults.• To train and empower people professionally.
• To make people better prepared to find work.
•To improve core competencies for obtaining and keeping a job
•To incorporate the various local community
ou g peop e, o e , adu ts-The mentally ill, those with disabilities, individuals with substance abuse problems.
• Application of social clauses.(Project in operation)• Carrying out occupational plans.
ACTIONS
p ygroups in the La Mina neighbourhood in the training processes
• To foster opportunities for occupational integration
(Project in operation)• School project (Polydor workshop).
(Project completed)
OBJECTIVES
• To facilitate access to information and orientation services
• To run the neighbourhood’s Information and JobOrientation Service. Job Club(Project in operation)
• Creation of the New Technologies Classroom(P j t l t d)
Create possibilities for accessing the job market
orientation services.
•To foster access to training and the use of new technologies.
(Project completed)
•Recycling of active professionals(Project completed)
27
Pla de Transformació del Barri de La Mina
28
Pla de Transformació del Barri de La Mina
29
Pla de Transformació del Barri de La Mina
SOCIAL ACTION PLAN
To create opportunities to access the job market free of
discrimination based on gender and
personal situation2. Balancingfamily and
To release the school-age adolescent
family and professional
livesadolescent
population from family
obligations
30
Pla de Transformació del Barri de La Mina
2 Balancing family and professional lives
SOCIAL ACTION PLAN
2. Balancing family and professional lives
Create possibilities for accessing the job market, free of discrimination based on gender or personal situation. To release the school-age adolescent population from f il bli ti
OBJECTIVES
ACTIONS
- Morning child-minding service – CEIP Mediterrània.
family obligations.
- To provide early childhood services.
- To offer a space for families and children for purposes of education and socialisation.
- To prevent situations of social exclusion.
- Children’s play centre and summer recreational centre for children from 3 to 5.
- Educational space for children up to the age of 3.
- Family recreational space “La Capsa dels Jocs”. (The Toys Box)p (The Toys Box)
(All of these projects are in operation)
31
Pla de Transformació del Barri de La Mina
32
Pla de Transformació del Barri de La Mina
SOCIAL ACTION PLAN
To give new energy to the commercial
infrastructure
3 D l t fTo regulate street trade3. Development of
the local economystreet trade
To encourage new creative activities
33
Pla de Transformació del Barri de La Mina
SOCIAL ACTION PLAN3 Development of the local economy3. Development of the local economy
To give new energy to the commercial infrastructure by encouraging new creative activities
• To provide support to the commercial • Project to energise commerce.
St t t d j t
OBJECTIVESACTIONS
infrastructure.
• To regulate street trade and make it sustainable.
• To study labour market research in depth.
• To strengthen and foster new economic activities
• Street trade project.• Project to support self-employment.
(administratively assigned to the corresponding
institution) • Project to do research.
economic activities.(All of these projects are in operation)
34
Pla de Transformació del Barri de La Mina
35
Pla de Transformació del Barri de La Mina
SOCIAL ACTION PLAN
To establish a process for community development
4. Community ti i ti d
pbetween the residents,
and various social work and institutional
services participation and
development
To reclaim and strengthen the
local infrastructure
36
Pla de Transformació del Barri de La Mina
4. Community participation and developmentSOCIAL ACTION PLAN
T l i d h h l l i f
• To reinforce local organisations and institutional projects.
OBJECTIVES• Project to support organisations in the district:
• Technical and economic support.• Technical support project to the community groups Platform
ACTIONS
To reclaim and strengthen the local infrastructure
• To foster a favourable atmosphere for spaces for exchange and social interaction between people and community groups.
• To establish systematic and pedagogical ways of providing information to the district
To overcome the district’s stigmatisation
• Technical support project to the community groups Platform.• Technical support project to the Neighbourhood Association. • Workspaces for local organisations.•Magazine articles, brochures, an edition of the bulletin, and so forth.•Support for organisations' initiatives in cultural activities.• To overcome the district’s stigmatisation.
• To bring athletic activities back to the district.
pp g•Support for community groups' athletic activities.
(All of these projects are in operation)
To establish a process for community development at the local, technical and institutional levels
• To establish social monitoring of the PTBM.•To involve and establish the social workers, services and residents of the district in the PTBM
• Creation of a Participation Council for monitoring the PTBM.
•Creation of committees with all of the stable services and local organisations in the district to carry out work as a network
OBJECTIVES ACTIONS
and residents of the district in the PTBM.•To promote resident participation in common uses
of public spaces and housing.
work as a network.•Plan for Community Communication.•European Roma’in Network. (Completed)•European Regenera Network. (Completed)
(All of these projects are in operation) 37
Pla de Transformació del Barri de La Mina
38
Pla de Transformació del Barri de La Mina
SOCIAL ACTION PLAN
To formulate a better approach to
5 Improving
combating antisocial attitudes and
behaviour
5. Improving coexistence and civic-mindedness
To strengthen the local and social
infrastructure of the Neighbourhood
Associations
Plan for welcoming new neighboursnew neighbours
39
Pla de Transformació del Barri de La Mina
SOCIAL ACTION PLAN5. Improving coexistence and civic-mindedness
To formulate a better approach to combating antisocial attitudes and behaviour
OBJECTIVES ACTIONS
pp g
•To develop measures for promoting civic-mindedness at home, in the street and in common spaces.•To create positive civic-minded attitudes among the population in social and community interactions
• All of the programmes were developed by the PTBM to foster and encourage respect, responsibility and autonomy.
To strengthen the local and social infrastructure of the local communities
population in social and community interactions
•To encourage residents to take responsibility for common spaces
OBJECTIVES ACTIONS•To encourage residents to take responsibility for common spaces.•To support and strengthen the neighbourhood organisations.•To provide socio-educational support in the process of
relocating the families affected by the PERI (Special Plan for Redesigning the Interior)
• Support project for the neighbourhood associations.• Resident data gathering project to help rehousing.
(Both of these projects are in operation)
W l lWelcome plan
•To identify new neighbours in the district and establish initial contact to identify possible needs. •To provide necessary information to new neighbours about the location, history, venues, services and cultural and
•To inform residents, organisations, services and associations in the district about the project and its development and get them involved.•To prepare and present the Welcome Plan with the
OBJECTIVES ACTIONS
, y, ,recreational activities in the district.•To encourage all residents in the district to make use of the services and venues, as well as participate in cultural and recreational activities.
p p phighest possible active participation from people in the area.•To support the people who take on this challenge in making welcoming newcomers more effective. 40
Pla de Transformació del Barri de La Mina
41
Pla de Transformació del Barri de La Mina
SOCIAL ACTION PLAN
Formal andFormal and informal education
6. Social and educational support
Consolidation ofConsolidation of the community
projects of the stable services in the
district
42
Pla de Transformació del Barri de La Mina
6. Social and educational supportSOCIAL ACTION PLAN
Formal and informal educationFormal and informal education
•To ensure that obligatory schooling is taken advantage of.
•Revitalisation project with parents (PTA). (administratively assigned to the corresponding institution) •Parental educational stimulation.•Support projects in school classrooms and reinforcement.•Support programmes for recreational activities
OBJECTIVESACTIONS
•To encourage parents to take on responsibilities.•To increase intervention with young people.•To expand the recreational education on offer.
•Support programmes for recreational activities.•Support programme specifically for youths from the gypsy community.•Support system and monitoring of socio-economic organisations' activities.•District Educational Project. (administratively assigned to the corresponding institution)
(All of these projects are in operation)
Consolidation of the projects of the stable services in the district
(All of these projects are in operation)
• Open Centre for children. (administratively assigned to the corresponding institution)
ACTIONS
•To achieve unity of criteria, quality and efficiency in the work carried out by the different services.•To stabilise the services' resources.•To tackle substance abuse in a
l b l
(administratively assigned to the corresponding institution)•Sport Programme for all ages. (administratively assigned to the corresponding institution) •Youth Centre.•Damage reduction and prevention programme.•Support to the Day Centre for persons in substance abuse (El Local).• Project to give immediate attention to school absenteeism
OBJECTIVES
global way.•To expand the athletic activities on offer.
• Project to give immediate attention to school absenteeism. (administratively assigned to the corresponding institution) •Project to support the step from primary to secondary school. (administratively assigned to the corresponding institution) (All of these projects are in operation) 43
Pla de Transformació del Barri de La Mina
44
Pla de Transformació del Barri de La Mina
SOCIAL ACTION PLAN
Promoting improvement of the urban environment
7. Public space and civic-mindedness
Retaking public spaces by the
residents
45
Pla de Transformació del Barri de La Mina
SOCIAL ACTION PLAN
7 Public space and civic-mindedness
Promoting improvement of the urban environment
7. Public space and civic-mindedness
Street Maintenance ProjectOBJECTIVES
ACTIONS
•To design a sustainable model for the district with social and participatory urban planning.•To improve waste management.
•Street Maintenance Project.•Public Art Competition. (Project completed)•District action plan: Making infrastructural spaces suitable and improving them. •Environmental Orientation Centre.•Environmental Managers.
Appropriation of the space by the residents
Environmental Managers.(All of these projects are in operation)
OBJECTIVESACTIONS
•To promote awareness of the district and overcome regional barriers.•To improve the quality of the public space.
• Campaign to increase awareness of civic-mindedness.•Actions to recover, preserve and revitalise the public space.•District action plan: Creation, design and
OBJECTIVES
public space.improvement of vacant space.•Civic agents.(All of these projects are in operation)
46
Pla de Transformació del Barri de La Mina
47
Pla de Transformació del Barri de La Mina
FACILITIES 2000-2010(Cost in millions of euros)
Childhood and Elementary Education Centre:
Secondary School: 5.1 Completed
4.9 Completed
Headquarters Mossos d’Esquadra: Executed by Generalitat de Catalunya
Seco da y Sc oo
Library and cultural centre:
Sports facility and multi-purpose
5.1 Under construction
4.6 Completed
5.1 Completed
function hall:
Evangelical Church:
Parish church and building for socio-educational activities: 1.6 Completed
0 7 Preliminary studies carried out.
Primary care centre:
Evangelical Church:
Renovation of the public administration
0.7
To be execute by Generalitat de Catalunya
yPending changes in planning
Renovation of the public administration centres in the district and new public facilities
to be defined according to future needs:No forecast
48
Pla de Transformació del Barri de La Mina
49
Pla de Transformació del Barri de La Mina
50
Pla de Transformació del Barri de La Mina
51
Pla de Transformació del Barri de La Mina
52
Pla de Transformació del Barri de La Mina
53
Pla de Transformació del Barri de La Mina
54
Pla de Transformació del Barri de La Mina
55
Pla de Transformació del Barri de La Mina
Improvement in accessibility to housing and renovations 2000-2010(amounts in millions of euros)
Providing lifts to 300 apartments in La Mina Vella:
Providing lift stops on the plans did not have it
4.8First phase completed.Second phase completed.Third phase being executed.
Providing lift stops on the plans did not have it originally in a 200 apartment building:
Improving and creating new access to 31 apartments (1,241 apartments) in the district: 1.7
0.4 Completed
Completed
Renovation of 40 apartments formerly belonging to the police department:
0 3
2.5 Completed
C ti i ti f th h i
Cross-section for 3 apartments :
0.3
Pending project
Renovation of an apartment façade on Occident street:
Completed
1.8
Continuing renovation of the housing in the district:
Begun in the block of flats on C/Occident
56
Pla de Transformació del Barri de La Mina
57
Pla de Transformació del Barri de La Mina
58
Pla de Transformació del Barri de La Mina
59
Pla de Transformació del Barri de La Mina
Urban development of public spaces 2000-2010
Rambla de la Mina. Central avenue will allows the Trambesòs tram to travel
through the centre of the district
First, second and third phases completed.Coloured paving of central avenue completed
Reorganising the neighbourhood streetsand interior mobility.
New urban development on existing streets. Completed
Creation of new squares and green areas
Creation and urban development of new streets.
Carried out in part (85%).
Taking advantage of groundwater for the upkeep of public spaces
Completed
TOTAL 21.8 million euros
60
Pla de Transformació del Barri de La Mina
61
Pla de Transformació del Barri de La Mina
62
Pla de Transformació del Barri de La Mina
63
Pla de Transformació del Barri de La Mina
64
Pla de Transformació del Barri de La Mina
65
Pla de Transformació del Barri de La Mina
Replotting project. New housing (2000-2010)(cost in millions of euros)
Recovery of industrial land in new plots for housing, public and
commercial facilities and green areas39.9 Completed
700 new private market apartments (300 owned by
422 new social houses (350 due to relocating caused by affected housing) 53
First plots under
Construction projects in open invitation to tender
700 new private market apartments (300 owned by the administration)
initial situation final situation
First plots under construction by private property developers
Final SituationSocial housing 2,750 100% 2,800 80%Private housing 0 0% 700 20%
TOTAL HOUSING 2,750 100% 3,500 100%
Final Situation
Protected Housing
Free market Housing
20%
80%
66
Pla de Transformació del Barri de La Mina
67
Pla de Transformació del Barri de La Mina
68
Pla de Transformació del Barri de La Mina
69
Pla de Transformació del Barri de La Mina
70
Pla de Transformació del Barri de La Mina
71
Pla de Transformació del Barri de La Mina
Collaboration in improving community safety
OBJECTIVESACTIONS
- Deployment of Mossos d’Esquadra (Catalan Police)- To increase knowledge of the
population about what constitutes dangerous behaviour.
- To put forward an effective communitypolicing model.
- Deployment of Mossos d Esquadra (Catalan Police).
- Local Safety Committee. Coordinating Boardoperation with the different police corps.
- Substance dependency prevention project.
Project to reach out to young people in the district
- To reduce risks and contribute to community safety.
- Project to reach out to young people in the district (administratively assigned to the corresponding institution)
(All of these projects are in operation)
72