Work Instruction Check the Status of PO Acknowledgement for the Buyer (ME23N)
(c) Reliance Industries Ltd. 2013 31 July 2015 3/19
Purpose
Trigger
Perform this procedure to check the status of Purchase Order (PO) Acknowledgement for the Buyer when a Vendor Acknowledges the PO.
Prerequisites
Access to Inowits for the Vendor SAP Login ID and Password for the Buyer
Menu Path
Use the following menu paths to begin this transaction:
http://qasepeq2.ril.com:50000/irj/portal SAP Menu Logistics Materials Management Purchasing Purchasing Order
ME23N
Transaction Code
ME23N
Work Instruction Check the Status of PO Acknowledgement for the Buyer (ME23N)
(c) Reliance Industries Ltd. 2013 31 July 2015 4/19
Procedure
1. Start the transaction using the menu path or transaction code.
Home - RIL eCommerce Portal - Windows Internet Explorer
2. Click the Order Processing menu.
Work Instruction Check the Status of PO Acknowledgement for the Buyer (ME23N)
(c) Reliance Industries Ltd. 2013 31 July 2015 5/19
Order Processing - RIL eCommerce Portal
3. Click the Attachment icon.
Attachments
4. Click the Digitally Signed ePO link.
Work Instruction Check the Status of PO Acknowledgement for the Buyer (ME23N)
(c) Reliance Industries Ltd. 2013 31 July 2015 6/19
http://sidcdevotarc.in.ril.com:8080/archive?get&pVersion=0045&contRep=1O&docId=00144FFACCED1ED4 - Windows Internet Explorer
5. Click the scroll-down arrow.Scroll-down to read the Vendor's PO document.
Work Instruction Check the Status of PO Acknowledgement for the Buyer (ME23N)
(c) Reliance Industries Ltd. 2013 31 July 2015 7/19
http://sidcdevotarc.in.ril.com:8080/archive?get&pVersion=0045&contRep=1O&docId=00144FFACCED1ED4 - Windows Internet Explorer
6. Click the Order Processing - RIL eCommerce Portal tab.
Work Instruction Check the Status of PO Acknowledgement for the Buyer (ME23N)
(c) Reliance Industries Ltd. 2013 31 July 2015 8/19
Order Status DashBoard
7. Click the Acknowledgement icon.
Order Acknowledgement
8. Select the first Confirm check box.
Work Instruction Check the Status of PO Acknowledgement for the Buyer (ME23N)
(c) Reliance Industries Ltd. 2013 31 July 2015 9/19
Order Acknowledgement
9. Select the second Confirm check box.
Order Acknowledgement
10. Select the third Confirm check box.
Work Instruction Check the Status of PO Acknowledgement for the Buyer (ME23N)
(c) Reliance Industries Ltd. 2013 31 July 2015 10/19
Comments :
11. As required, complete/review the following fields:Field R/O/C DescriptionComments : Required
Example:OK..Accepted
Work Instruction Check the Status of PO Acknowledgement for the Buyer (ME23N)
(c) Reliance Industries Ltd. 2013 31 July 2015 11/19
Attachment Details :
12. Click the Document Type drop-down arrow.As required, the Vendor can attach any relevant documents.
Work Instruction Check the Status of PO Acknowledgement for the Buyer (ME23N)
(c) Reliance Industries Ltd. 2013 31 July 2015 12/19
Attachment Details :
13. Select ACCEPTANCE.
Attachment Details :
14. Click the Browsefor File button.
Work Instruction Check the Status of PO Acknowledgement for the Buyer (ME23N)
(c) Reliance Industries Ltd. 2013 31 July 2015 13/19
Choose File to Upload
15. Double-click Approval note for level revision.docx.
Work Instruction Check the Status of PO Acknowledgement for the Buyer (ME23N)
(c) Reliance Industries Ltd. 2013 31 July 2015 14/19
Attachment Details :
16. As required, complete/review the following fields:Field R/O/C DescriptionTag Name: Required
Example:Acceptance Letter
Work Instruction Check the Status of PO Acknowledgement for the Buyer (ME23N)
(c) Reliance Industries Ltd. 2013 31 July 2015 15/19
Attachment Details :
17. Click the Attach button.
Work Instruction Check the Status of PO Acknowledgement for the Buyer (ME23N)
(c) Reliance Industries Ltd. 2013 31 July 2015 16/19
Attachment Details :
18. Click the Submit button.
Work Instruction Check the Status of PO Acknowledgement for the Buyer (ME23N)
(c) Reliance Industries Ltd. 2013 31 July 2015 17/19
Submit: Confirmation
19. Click the Yes button.
Work Instruction Check the Status of PO Acknowledgement for the Buyer (ME23N)
(c) Reliance Industries Ltd. 2013 31 July 2015 18/19
Order Processing - RIL Corporate Portal
20. Click the Minimize icon.The message Order has been submitted successfully is displayed.
The Buyer gets a confirmation mail after successful order submission.
Work Instruction Check the Status of PO Acknowledgement for the Buyer (ME23N)
(c) Reliance Industries Ltd. 2013 31 July 2015 19/19
Order Processing - RIL Corporate Portal
21. End of Simulation