57
( p a ge ge c olor: olor: L i g h t s k y -b -b lue lue A Training report On “Damodar Valley Corporation” submitte d in partial fulfilment for the award of the Degree of Bachelor of Technology in Department of Electrical Engineering Submitted To: Submitted By: Mr. Himanshu Doraya Aditi Anand Asst. Professor, EE Enrollment No. Department of Electrical Engineering Rajasthan college of Engineering for Women Rajasthan Technical University, Kota

training_Report_Guidelines(1).doc

Embed Size (px)

Citation preview

Page 1: training_Report_Guidelines(1).doc

( ppaagege ccolor:olor: LLiigghhtt sskkyy-b-bluelue

ATraining report

On “Damodar Valley Corporation”

submittedin partial fulfilment

for the award of the Degree of

Bachelor of Technology

in Department of Electrical Engineering

Submitted To: Submitted By:Mr. Himanshu Doraya Aditi AnandAsst. Professor, EE Enrollment No.

Department of Electrical Engineering Rajasthan college of Engineering for Women

Rajasthan Technical University, Kota

May-July,2015

Page 2: training_Report_Guidelines(1).doc

CERTIFICATE

This is to certify that Ms Aditi Anand , Roll No 12ERWEE001 student of B.Tech.,

Electrical Engineering, Rajasthan College of Engineering for Women has submitted her

Training report.

Mr. Rachit Saxena Mr. Himanshu Doraya HoD,EE Asst. Professor, EE

Page 3: training_Report_Guidelines(1).doc

Contents

Certificate

Acknowledgement i

Abstract ii

List of Figures …

List of Tables …

Chapter 1: Introduction 1

1.1 Heading1 …

Chapter 2: ……………………. …

2.1 Heading1 …

Appendix …

References …

Page 4: training_Report_Guidelines(1).doc

Chapter – 1

TITLE OF THE CHAPTER SHOULD BE IN TNR 14 (ALL CAPITAL)

The paper size should strictly be A4 i.e 8.27 X 11.69 inches. Pages should be white Bond

paper 75 gsm only and printed on one side. Report must contain minimum 35 pages and

maximum 55 pages (Chapters matter should contains 30-50 pages) approx. Two copies of

report ( 1 Deptt, 1 self) to be submitted in soft sheet bind form.

Margins of each page should be preferably 1.25 inch left side, 1 inch right hand side, 1

inch top and 1 inch bottom with page no. at bottom margin. (as it is on this page).

The report pages should contain page numbers in centre of the footers in following

format:-

i) Before chapter 1 in roman like i, ii, iii ……

ii) From chapter 1 onwards in numerals like 1, 2, 3……

For each chapter at top right corner chapter no. should be written: for Bold, Times New

Roman example; for chapter 1, it should be Chapter - 1 (Font 12, bold, right justified).

Title of the chapter should be typed in Font 14 (All Capital) and should be centered.

The main contents in the Report should be typed in Times New Roman 12, regular, both

side justified font. Spacing between consecutive lines should be 1.5. Separate

successive paragraphs by 9 points.

References will be arranged in the order in which they are referred in the Thesis. Reference

no. will be put in square brackets within the text in the order in which they are cited.

Preferably, the Report should be organized as under:

i) Contents (Pg no. should be numbered in Roman as i, ii, iii… distinct to that of

starting from Abstract).

ii) Abstract (not more than 300 words. It should be precise, concise and duly

approved by the guide.)

iii) Introduction (Chapter – 1)

4

Page 5: training_Report_Guidelines(1).doc

v) Chapters 2, 3, 4….

vi) Conclusion

vii) References (IEEE Syntax), Examples are given as under:

“To refer a resea r ch p aper” –

[1] Dinesh Birla, R. P. Maheshwari, and H. O. Gupta, “A New Non-linear Directional

Overcurrent Relay Coordination Technique, and Banes and Boons of Near-end Faults

Based Approach”, IEEE Transactions on Power Delivery, vol.-21, no.-3, pp. 1176-

1182, July 2006

“To refer a book” –

[2] David E, Goldberg, “Genetic Algorithms in Search, Optimization, and Machine

Learning”, ISBN 81-7808-130-X, Pearson Education Asia Pte Ltd., 2000.

(621.381952, G47G)

“To refer a URL”

[3] Grid security infrastructure, http: //www.globus.o rg/security/ov erview.htm l

All Figures/Images/Tables should be clear, electronically drawn and should be having

good resolution.

Figures/Images/Tables and their titles should be aligned centrally to the page. Figures

should be numbered, and should be titled as under.

Fig. 1.1. RCEW Logo

Single Figure/Image/Table should not exceed the available page size (within margins).

(Tables should be given the number based on their chapters; for example; for chapter 2

they should be Table 2.1, 2.2 and so on. T h e y s h ould be written as u nder:

5

Page 6: training_Report_Guidelines(1).doc

TABLE 1.1

STYLE AND FONT SIZES

Chapter Title bold 16pt

Main section heading Bold 14pt

Sub section heading Bold 12pt

Sub sub section heading Bold and italics 12pt

Figures and table titles normal 10pt

Chapter contents Bold + italics 14pt

In between text (for emphasizing) Normal + italics 12pt

All other text normal 12pt

Page 7: training_Report_Guidelines(1).doc

Public Relation Office

IntroductionMission & VisionPhysical PerformanceGeneration ProjectAnticipated GrowthInfrastructureWater ManagementDams & BarrageReservoir OperationWelfareRural Electrification

Central Load Dispatch

IntroductionReal Time DVC Ex-Bus Generation (MW)Meter Locations in DVC Interconnected SystemUI rate & FrequencySCADATransmission

Kumardhubi SubstationRatingsCommon TermsTransmission SystemGridmapSubStation

INTRODUCTION

Page 8: training_Report_Guidelines(1).doc

DAMODAR VALLEY CORPORATION

Damodar valley corporation (dvc) is the first ever multipurpose river valley projects of independent india which came into being on july 7,1948 by an act of the consitutent assembly (act no .1948).

Dvc has its command area of approx 24,235 sq kms spreading across the Damodar basin,boundaries of which transcend the state of which transcend the state of west Bengal and Jharkhand.The upper Valley consist of two entire district (dhanbad and bokaro)and eight district partly(hazaribagh,koderma,giridih,chhatra,palumau,ranchi,Lohardaga and doomka) in the state of jhartkhand.The lower valley on the other hand consist of five districts partly (Burdwan and Hooghly,howrah,Bankura and Purulia) in the state of west Bengal.

Dvc was set up with the intent of promoting and operating the schemes which may cause social and economic uplift in the valley region.Dvc has already established its existence in discharging its obligation for more than five decades in perfect harmony.The difficult but effective water management by the corporation has already established.its existence in discharging its obligation for more than five decades in perfects harmony.The difficult but effective water management by the corporation has turned the devasting river Damodar from a ‘River of sorrow’ to a River of prospects and opportunities’.proficient management of water resources through dams,canels,and barrage,Dvc facilities irrigation as well as insustrial and domestic water supply which at a large benefited the region as a whole.it has also contributed significantly in conservation of soil and promotion of scheme of social integration in the valley area.

Dvc has been generating,transmitting,and distributing electrical energy since 1953 and has succeeded not only in meeting the expectation of the consumers but also has elevated its level of performance to a great height in the diamond jubilee year.no doubt during the course of the last 60 years,the scenario in power sector has undergone a sea change,yet dvc has maintained its lead role in the eastern region,adapting itself to the challenges of time and new technologies.

CORPORATE MISSION ,VISION AND OBJECTIVES

THE MISSION

Damodar valley corporation,the first major multipurpose integrated River valley project of the country ,conceived in line of Tennesse valley Authority(TVA) came into existance on july 7,1948 by an acts of central Legislature.

The mision at the time of its inception was:

Flood control Promotion and operation of schemes for irrigations Water supply for industrial and domestic use

Page 9: training_Report_Guidelines(1).doc

Navigation and drainage Generation ,transmission and distribution of electrical energy Promotion of a forestation and control of soil erosion in valley area Promotion of public health,agriculture,industrial,economic and general well being

i damodar valley In keeping with industrialization in the DVC command area,power generation,transmission and distribution gained priority for providing electricity to he core industries like steel,coal,railways and other railways and other industries and consumers through respective state electricity boards.however other manded objective and general also received equal importance as part of overall responsibility and commitment of dvc.

This emphasis on capacity addition programme for power generation gained a new direction when ministry of power goverment o india started advocating for setting up f a thermal power plant at or near pits head and transmit power rather than transporting coal and advised DVC to world towards adequates capacity adition during the tenth and eleventh plan order to met the power vision 2012 of government of india.

THE VISION

To established DVC as one of the largest power majors of Eastern India while discharging the responsibilites of its order objets adequately.

In order to achive this goal against the backdrop of the competitive market scenario in the

power sector,the objectives of the corporation has been redefined.

CORPORATE OBJECTIVES

• Generate more power at lowest possible cost by improving operational efficiences of the existing plants,rejuvenating old generating units through comprenhensive overhaling as well as by installing new genrating plants.

• Transmit,distribute and supply reliable and quality power at competitive tarrif.

• Improve the financial health of the coroporation by adoption of efficient industrial,commercial and human resources management practices.

• Ensure optimum utilization of available water resources through effective and efficent management and harness the remaining potential of dmador basin to the extent possible.

• Fourtify measures for enviroment protectionat a plant level and to continue with the

activites of consevation in the valley area.

PIONEERING ROLE

First multipurpose river valley projects of the government of the india. A government of india projects managing generation p[ower utilizing two sources coal

& water.

Page 10: training_Report_Guidelines(1).doc

First government of india projects managing generation transmission and distribution of electricity.

First underground hydel station in maithon. Bokaro thermal power station ,biggest thrmal power plant of the nation in the 50 of last

yr.

DVC INFRASTRUCTURE AT A GLANCE

Dvc command area 24,235 sq.kms

Power management

Total installed capacity 2796.5m.w

Thermal power station 04(four)

Thermal capacity 2570 mw

Sub station

Transmission line

At 220 kv-11

At 132 kv-33

At 220 kv-1342ckt.kms

Water management

Major dam and barrage Tilaiya,konar,maithon,panchet dams anddurgapur barrage

Irrigatation command Area(gross)

5.69 lakhs

Irrigation potential created 3.64 lakhs hectares

Flood reserve capacity 1296 millions cu.millions cu.m

Soil conservation

Forest,farm,upland,& wasteland treatment

4 lakhs hectares(approx)

Checkdams 16,000(approx)

DVC POWER PLANT AT A GLANCE

Page 11: training_Report_Guidelines(1).doc

NAME LOCATION EXISTING CAPACITY

TILAIYA

MAITHON

RIVER-BARAKAR,DIST-HAZARIBAGH,JHARKHAND

4 M.V

63.2MW(2*20MW+1*23.2MW) RIVER-BARAKAR,DIS- BURDWAN,STATE-

JHARKHAND

PANCHET RIVER-DAMODAR 80 MW

(2*40 MW)DIST-DHANBAD

JHARKHAND

TOTAL HYDEL CAPACITY=

THERMAL

BOKARO B’ DIST-BOKARO,JHARKHAND630M.W(3*210)

CHANDRAPURA DIST-BOKARO,JHARKHAND750 MW(3*130MW)+(3*120MW)

DURGAPUR DIST-BURDWAN,WEST BENGAL

350 MW(1*210 MW)

Mejia Dist-bankura,west bengal 840 mw,(4*210)

DVC TAKES INTTIATIVES FOR SOCIAL SECTOR DEVELOMENT

Damodar valley corporation has initiated a number of new activities to further the process of development.

Integrated development and utilization of DVC water resources:

WAPCOS has been entrusted with preparation of a master plan of integrated development and utilization of damodar valley water resources and

Page 12: training_Report_Guidelines(1).doc

unified operation and control of all the reservoirs,including Tenughat Dam for effective and optimum utilization of the available water resources and harness untapped potential included surface water flow during monsoon season.CWC has been entrusted with preparation of detailed projects for the proposal Balphari dam on barakar river between maithon and tilaiya on fast track basis.

AFFORESTATION SOIL CONSERVATION:

Damodar valley mission has been constituted under the chairmanship of chief secretary government of Jharkhand with member from the participating government,NEERI, Nagpur is working out action plan for pollution abatement in damodar river system.

DVC foundation for social sector development

The foundation seeks to design,manage and implement the social integration programme(sip) of dvc.IIT, Kharagpur has been entrusted with prepation of a master plan for socio-economic development of the inhabitants in the valleys areas.

DEVELOPMENT OF TOURISM:

To tap to continue prospect and opportunites,dvc has signed a MOU with preparation of a master plan for socio and IL&FS IDC to venture into development of tourism (so far untapped) jointly as commercial activity.accured economic benefit (direct and indirect)will aid the socio economic development of the region.

OTHER INFORMATION:

To provide protein food to the projects people and rehabilites the displaced villagers effected due to impoudement of their villages.serious efforts are in to review fish farming .the combined area of the four major reservoirs,which is about 25000 hectares is a huge potentials resources to be put under organized pasciculture programme

Joint venture projects:

1.maithon power limted : with tata power Ltd atmadandih,maithon

Page 13: training_Report_Guidelines(1).doc

1050 mw mega thermal projects under co

-nstruction.

2.Bokaro power supply : with bokaro steel Ltd at bokaro 500 mw

FLOOD MODERATION

ROLE OF DVC IN FLOOD MODERATION

The river damodar proverbially erratic in nature is know as for recurrence of flood for over a century .the physiography of the valley by river damodar and its tributaries and the character of the network of the other rivers in the regions are in the main conditioning factors of the flood pattern in conditioning factors of the flood pattern in the damodar valley area and beyond.

THE RIVER NETWORK

Rising from the palamau hills in bihar the river Damodar flows in a generally south easternly direction for a distance of approximately 290 kms through bihar.on entering the deltaic plains of west Bengal below ranigung and after reaching the vicinity of burdwan the river aburuptly changes its course to a southernly direction spreading its water into a many channels.though the mains channels into a an insignificant stream,ultimately joining the Hooghly near shyampur much of its water drain into rupnarayan and the combined flow reaches Hooghly further south around 49 kms below Calcutta.

Its principal tributaries in the upper reaches are maulah,bokaro,konar,jamunia,and barakar.in the lower valley two other principal rivers flowing outside the Dvc command area.the floods of damodar and trans-damodar regions recurrent in nature have invariably been accompanied by pestilence,hunger,and epidemics.the situation climaxed in 1943 when the entire region suffered terrible loss of life and properties due to

Page 14: training_Report_Guidelines(1).doc

the damodar floods which also led to worst ever famine in the region and dislocated trunk communications.hence serious efforts were undertaken to find out a permanent remedy to this chronic problem.

BIRTH OF DVC

A ten-man enquiry commited was set up which included the noted physicist dr meghanad saha and the maharaj of burdwan.this was followed by the adoption of Tennesse valley Authority model of the USA and induction of mr WL voorduin who submitted the preliminary memorandum for a compherhensive approach to tackle the flood of damodar and to harness the resources of the damodar valley region.based on these recommendation,damodar valley corporation came into being on 7th july 1948 as the first multipurpose river projects of independent india.the water management of dvc is also supported by Durgapur barrage which however does not have any flood moderation capacity but is used for temporary storage/balancing of water for irrigation industrial and domestic use.however since 1963-64 the responsibility of distribution of water from duragapur barrage through the canal have been handed over to the government of west Bengal.

Page 15: training_Report_Guidelines(1).doc

WATER RELEASE:THE METHODOLOGY

Since 1964 operation of dvc reservoirs involving release of water during monsoon and non-monson (October-june )period is controlled by the damodar valley reservoirs regulations committee(DVRRC).The DVRR committe consist of two members each representing th government of west Bengal,bihar,and DVC under chairmanship of member RM central water commission(CWC).

The DVRRC decides about the quantam of water to be realeased as per the guidelines laid down in the reserviours regulations manual which has been formulated after a close study of relevant data to guide water realease at different situations.

Page 16: training_Report_Guidelines(1).doc

PERFORMANCE OF DVC DAMS

The four Dvc dams have controlled a number of major floods in the lower damodar valley .there have been atleast 12 subsequent occasions when the peak discharge if unregulated would have been far in exess of the flow recorded in 1943,during September 26/27,1978,dvc reservoirs had a record inflow of 8.51 lakhs causes (hourly peak)of flood water.

. Performance during major flood since 1958

Date inflow outflow

16/17 september 1958 555 175

½ October 1959 623 288

27/29 september 1960 348 92

2/3 october 1961 516 161

2/3 october 1963 451 121

24/25 october 1963 465 91

16/18 july 1971 424 180

Page 17: training_Report_Guidelines(1).doc

12/13 october 1973 588 175

27/28 september 1995 613 250

.

FLOOD CONTROL CONSTRAINTS Due to the truncation of the scheme the flood storage capacity of DVC

dams and reservoirs has been reduced to one third . Non availability of land for utilization the full potential of maithon and

panchyat dams. Construction of tenughat dam with no provision for flood moderation in

place of proposed aiyar dam of DVC. Depletion in the drainage capacity of the channels below duragapur

barrage due to sedimentation and encroachment.

No provision for controlling floods caused by dwarekeshwar,silabati and other rivers in trans damodar area.

MEASURE REQUIRED FOR ENHANCHING FLOOD MODERATION CAPICITY

Page 18: training_Report_Guidelines(1).doc

Construction of balpahri dam on barakar as proposed by DVC. Acquisition of remaining land at panchyat & maithon. Unified operation of Tenughat dam with DVC dams. Improvement of the drainage channels in Lower damodar area. Steps for enhancing checks and balanced to combat silt inflow into

reservoirs and drainage channels. Implementation of integrated flood control scheme including other

rivers (such as Dwarkeshwar etc) in the lower damodar areas.

THE PLAN AND AFTERMATH The initial plan enviased construction of seven dams including two on damodar(panchet and aiyar) three on baraker (maithon,balapahri and Tilaya) and one of the konar and bokaro river with a view to moderating a deign flood of 10 lakhs causes to the levels of 2.5 lakhs cases.

TRUNCATED CAPACITYOut of these seven proposed dams only four have been constructed by dvc in the first in the phase of its construction and others could not materialize due to the reasons beyond dvc control.the four dams in the dvc system include panchyat on damodar ,maithon and tilayia on baraker and konar which cam at best moderate six lakh causes of flood water to 2.5 lakhs causes of flood water to 2.5 lakhs causes level. The four dams constructed by DVC were supposed to have a total reservoir capacity of 25 lakhs acres feet excluding dead storage.out ofthis capacity of 15 lakhs acre feetwas earnmarked for flood control but due to non –availability of full requirement of land,five lakh acre ft thus limiting the ability of dvc to one third of the original plan. Further,the position is compounded by the facts that valley iethe region below the dvc dams can itself generate a flood of 2.5 lakhs ft/sec and the original plan assumed that separate flood control

Page 19: training_Report_Guidelines(1).doc

arrangement including improved drainage system would have to be made for protection of the trans-damodar areas which is affected not only by floods of damodar but also by floods of rivers like dwarakeswar,kangsabati,silabati and others which are not part of DVC water management network. DVC OBJECTIVES

DVC is working with the following objectives since formations:

Flood control; Irrigation and watyer supply for industrial and domestic uses; Generation,transmission and distribution of electrical energy; Soil conservation and afforestion; Socoio economic uplift of the people in the valley area;

DVC VALLEY

The total valley areas covered by DVC is around 24,235 sq.kms.upper valleys covers six districts fully (hazaribagh,koderma,giridih,chatra,dhanbad,bokaro) and four districts partially(palamau,ranchi,lohardaga and dumka) in the state of Jharkhand.lower valleys fall into two districts fully(burdwan,and Hooghly)and three districts partiaaly (howrah,purliya) in he state of weste Bengal.

Page 20: training_Report_Guidelines(1).doc

l.

Page 21: training_Report_Guidelines(1).doc
Page 22: training_Report_Guidelines(1).doc

.

Page 23: training_Report_Guidelines(1).doc
Page 24: training_Report_Guidelines(1).doc
Page 25: training_Report_Guidelines(1).doc

JOINT VENTURE PROJECTS

MAITHON LIMITED

A joint venture company by dvc and Tata powers has been formed to implement 1050 mw maithon right bank thermal power projects for meeting the energy needs of power deficients regions onexport basis.

BOKARO POWER SUPPLY CORPORATION LIMITED(BPSCL) A joint venture company of dvc and SAIL has been established to operate and maintained power and steam generation plant and supply power and steam exclusively to Bokaro steel Ltd.

DVC EMTA COAL MINES LIMITED

A joint venture company formed with Eastern minerals & trading Agency for development and operation of capative coal mines blocks and supply of coal exclusively to dvc thermal power projects of 10 th and 11 th plan.

MINING & ALLIOED MACHINERY CORPORATION (MAMC)

The mining and allied machinery corporation (mamc) in Durgapur-one of the psu in india set up under the rupeerouble agreement and enjoying soviet patronage in the early sixties.bharat earth movers has a highest stake (48%) in the consortium whi;le the other two psu –dvc and coal india have 26% stake each.

Page 26: training_Report_Guidelines(1).doc

CENTRAL LOAD DISPATCH

The Load dispatch department is the nerve centre for the operation planning,monitoring and control of the power system.Electricity cannot be stored and has to be produced when it is needed.it is therefore essential that power system is planned and operated optimally & economically.the load despatch department is the nerve centre for the operation,planning,monitoring and control of power system.the objective of load despatch department are:

• Matching the power demand with system integrity ,reliability and security of generation and transmission facilities.

• Regulating the system frequency.• Optimum utilization of resources.• Quick restoration of normalcy after system disturbances.• Thus the objectives of Load despatch department is to co-ordinate

generation,transmission and distribution of electricity from moment to moment achieve maximum security and efficiency.the functions of load dispatch department are dyanamic are dyanamic in nature.while performing the functions the polices laid down by management are strictly followed.in Maharashtra state electricity that the polices of load despatch department are:

RESPONSABILITES OF STATE LOAD DESPATCH CENTRE

• Demand Estimate for operational purpose.• Scheduling for merit order despatch.• Regulating generation load balance.• Schedule for Centra sector drawl & regulted it• Maintain system frequency in 49.0 hzs to 50.5 hzs range• Outage planning and monetring.

Page 27: training_Report_Guidelines(1).doc

• Reactive power management and voltage control.• Load shedding implementation.• Coordination with RLDC and other constituents.

LOAD DISPATCH DEPARTMENT ARE

• Economy of generation ,transmission and distribution of supply of electric power to the consumers.

• Continuity and high reliability power supply.

• Safty of equipment.

FUNCTION OF THE STATE LOAD DISPATCH CENTRE

• The regional load dispatch centre shall be the apex body to ensure integrated operation of the power system in the concerned region.

• The regional load dispatch centre shall comply with such principles guidelines and methologies in respect of the wheeling and optimum schedulint and dispatch of electricity as the central commission.

• The regional load despatch centre shall-

• Be responsible for optimum scheduling and dispatch of electricity within the regions in accordance with the constracts entered into the wiyh yhe licences or the generating companies operating companies operating in the region;

• Monitors grid operation

• Keep account of the quality of electricity transmitted through then regional grid;compliance OF DIRECTION.Transmission within a state regional grid;

Page 28: training_Report_Guidelines(1).doc

• Be responsible for carrying out real time operations for grid control and despatch of electricity within the state region grid;

• The regional load despatch of electricity centre may levy and collects such fee and charges from the generating companies or licences engaged in inter state of electricity.

Page 29: training_Report_Guidelines(1).doc

TECHNICAL OVERVIEW:-

Page 30: training_Report_Guidelines(1).doc

Date of commissioning :- October 1989 e

No. of Unit: - 3 nos.

Capacity :- It comprises 3 units of 30MW (27.5MW nominally rated) each

Type of FUEL:- Presently dual fuel basis (HSD-Naphtha) but capable of conversion to gas and other liquid fuel.

Special feature: -

1.The emission meets the Ambient Air pollution norm. in terms of decibel of sound, it conforms to sound pollution norm

2. Since the units run with hazardous fuel, the fire fighting network is so designed (as per API standard) to achieve Non-combustible atmosphere in less than a minute time.

CENTRAL LOAD SYSTEM

The objective of Load Dispatch Department

1. Matching the power demand with system integrity, reliability and security of generation and transmission facilities.

2. Regulating the system frequency.

3. Optimum utilization of resources.

4.Quick restoration of normalcy after system disturbance Central Testing Center at Maithon has two distinct divisions namely

1. Central Relay and Instrument Testing Laboratory (CRITL) and

2. Central Relay and Instrument Testing Mobile (CRITM).

The above two divisions take care of commissioning and proper maintenance of the entire protection and metering system, fault analysis as well as

Page 31: training_Report_Guidelines(1).doc

periodical testing of all types of relays and meters including tariff meters of the entire DVC network including power

OVERVIEW OF MAITHON GAS TURBINE UNITS

GT units run on peak cycle that is “Brayton Cycle” with 3 storage impulse turbine and 17 stage axial compressor mounted on same shaft. It has 630 Hp starting diesel engine, 10nos. annular combustion chamber. Turbine speed, 5082 RPM is reduced to 3000 RPM with reducing gear box.

TECHNICAL OVERVIEW

Date of commissioning :- October 1989 e

No. of Unit: - 3 nos.

Capacity :- It comprises 3 units of 30MW (27.5MW nominally rated) each

Type of FUEL:- Presently dual fuel basis (HSD-Naphtha) but capable of conversion to gas and other liquid fuel.

Special feature: -

1.The emission meets the Ambient Air pollution norm. in terms of decibel of sound, it conforms to sound pollution norm

2. Since the units run with hazardous fuel, the fire fighting network is so designed (as per API standard) to achieve Non-combustible atmosphere in less than a minute time.

MAITHON GAS TURBINE

Page 32: training_Report_Guidelines(1).doc

4329 plus Rs. 57196697- Rs.4085 lacs. The main purpose of plant setup is to serve as standby & emergency source of power.

The Maithon Gas turbine has been setup by DVC in October 1989, Constructed & commissioned by m/s GE, USA on Turnkey basis with total cost of setup of $ 2702.

Page 33: training_Report_Guidelines(1).doc

. Reservoir operation

A vast hydro meteorological station with VHF/wireless facilities exists

over the Damodar catchment area. On a real time basis (hourly, 3

hourly, 6 hourly) data of river gauge, rainfall river discharge are

measured and transmitted through existing communication network to

the central flood station at Maithon. The Indian Meteorological

Department(IMD), Kolkata, transmit the rainfall forecast for the next 24

hours for the entire Damodar Valley region to Maithon. A computer

Page 34: training_Report_Guidelines(1).doc

model at the Flood Forecasting Unit(FFU) at Maithon estimates the

inflow into the reservoirs based on the real time data & rainfall forecast

of IMD.

According to detailed guidelines contained in the “Damodar Valley

Reservoir Regulation Manual”, Member Secretary of DVRRC

(Damodar Valley Reservoir Regulation Committee) after discussion

with SE, Damodar Irrigation Circle Govt. of West Bengal, Reservoir

Operation of DVC & SE, Tenughat of Govt. of Jharkhand decides day

to day release of water from Maithon Dam

Problems

People involved in power generation say that water should be filled up

as much as possible as it would be better for power generation. People

involved in flood control department says water storage should be

lowered, so that in case of excessive rain a flood like situation arises

then it will be a flood cushion. This is a conflicting nature, so water has

to be kept at an optimum level to satisfy both parties

Dead Storage Capacity of the dam during the initial years was much

more than the storage capacity now.The portion of a water storage’s

capacity that is equal to the volume of water below the level of the

lowest outlet (the minimum supply level),is known as th Dead Storage

Capacity. This, increase has been mainly due to the sedimentation

storage. Due to human & industrial activities, the storage capacity has

decreased over the years. As per the design of dam given by Mr.Voord

capacity depth should have been 500 ft (150 m). But due to non-

acquisition of land the depth is at 495 ft (151 m). The carrying capacity

of the dam as designed by Mr.Voodro was 1,000,000 cu ft/s

Page 35: training_Report_Guidelines(1).doc

(28,000 m3/s). But at the time of construction it was only

250,000 cu ft/s (7,100 m3/s) and at present it has a carrying capacity of

less than 100,000 cu ft/s (2,800 m3/s). The cost of removing deposited

silt in the dam is equal to the construction of a new dam,therefore

economically not viable. If the silt is removed and stored in the banks

of the dam, then during monsoon the silt would get washed off into the

dam.

Maithon Dam has completed 60 years.

Problems[edit]

People involved in power generation say that water should be filled up

as much as possible as it would be better for power generation. People

involved in flood control department says water storage should be

lowered, so that in case of excessive rain a flood like situation arises

then it will be a flood cushion. This is a conflicting nature, so water has

to be kept at an optimum level to satisfy both parties

Dead Storage Capacity of the dam during the initial years was much

more than the storage capacity now.The portion of a water storage’s

capacity that is equal to the volume of water below the level of the

lowest outlet (the minimum supply level),is known as th Dead Storage

Capacity. This, increase has been mainly due to the sedimentation

storage. Due to human & industrial activities, the storage capacity has

decreased over the years. As per the design of dam given by Mr.Voord

capacity depth should have been 500 ft (150 m). But due to non-

acquisition of land the depth is at 495 ft (151 m). The carrying capacity

of the dam as designed by Mr.Voodro was 1,000,000 cu ft/s

(28,000 m3/s). But at the time of construction it was only

Page 36: training_Report_Guidelines(1).doc

250,000 cu ft/s (7,100 m3/s) and at present it has a carrying capacity of

less than 100,000 cu ft/s (2,800 m3/s). The cost of removing deposited

silt in the dam is equal to the construction of a new dam,therefore

economically not viable. If the silt is removed and stored in the banks

of the dam, then during monsoon the silt would get washed off into the

dam.

Maithon Dam has completed 60 years.

Rivers

Barakar

Bokaro

Damodar

Jamunia

Konar

Mundeswari

Rupnarayan

Dams, barrages

Durgapur

Konar

Maithon

Panchet

Tenughat

Tilaiya

Damodar Valley Corporation

Geographical features

Chota Nagpur Plateau

Shikharji (Parasnath Hills)

Rajrappa

Rarh region

Usri Falls

Riparian districts Jharkhand Palamu

Page 37: training_Report_Guidelines(1).doc

Hazaribagh

Koderma

Giridih

Ramgarh

Bokaro

Dhanbad

West Bengal

Purulia

Bardhaman

Bankura

Hooghly

Howrah

Paschim Medinipur

Purba Medinipur

Languages

Bengali

Hindi

Kumarbhag Paharia

Kurukh

Magahi

Mal Paharia

Santali

Sauria Paharia

Coalfields

South Karanpura Coalfield

North Karanpura Coalfield

Ramgarh Coalfield

West Bokaro Coalfield

East Bokaro Coalfield

Raniganj Coalfield

Industries Bokaro Steel Plant

IISCO

Durgapur Steel Plant

Bokaro Thermal Power Station B

Santaldih Thermal Power Station

Durgapur Thermal Power Station

Page 38: training_Report_Guidelines(1).doc

Mejia Thermal Power Station

Transport

National Highway 2

Grand Trunk Road

National Highway 31

National Highway 33

National Highway 100

National Highway 32

National Highway 60

Grand Chord

Bardhaman-Asansol section

Asansol-Gaya section

Asansol-Tatanagar-Kharagpur line

Other basins

Godavari

Kosi

Mahanadi-Brahmani-Baitarani

Narmada

Son

FUNCTIONS OF THE CORPORATION

• THE PROMOTION AND OPERATION OF SCHEMES FOR IRRIGATION, WATER SUPPLY AND DRAINAGE

• THE PROMOTION AND OPERATION OF SCHEMES FOR THE GENERATION, TRANSMISSION AND DISTRIBUTION OF ELECTRIC ENERGY, BOTH HYDRO-ELECTRICAL AND THERMAL

• THE PROMOTION AND OPERATION OF SCHEMES FOR FLOOD CONTROL IN THE DAMODAR RIVER AND ITS TRIBUTARIES AND THE CHANNELS, IF ANY, EXCAVATED BY THE CORPORATION IN CONNECTION WITH THE SCHEME AND FOR THE IMPROVEMENT OF FLOW CONDITIONS IN THE HOOGHLY RIVER,

Page 39: training_Report_Guidelines(1).doc

• THE PROMOTION AND CONTROL OF NAVIGATION IN THE DAMODAR RIVER AND ITS TRIBUTARIES AND CHANNELS, IF ANY

• THE PROMOTION OF AFFORESTATION AND CONTROL OF SOIL EROSION IN THE DAMODAR VALLEY, AND

THE PROMOTION OF PUBLIC HEALTH AND THE AGRICULTURAL, INDUSTRIAL, ECONOMIC AND GENERAL WELL-BEING IN THE DAMODAR VALLEY

CORPORATE OBJECTIVES

• GENERATE MORE POWER AT LOWEST POSSIBLE COST

• TRANSMIT, DISTRIBUTE AND SUPPLY RELIABLE AND QUALITY POWER

• ADOPTION OF EFFICIENT INDUSTRIAL, COMMERCIAL AND HUMAN RESOURCE MANAGEMENT PRACTICES

• OPTIMUM UTILIZATION OF AVAILABLE WATER RESOURCES AND HARNESSING THE REMAINING POTENTIAL OF THE BASIN TO THE EXTENT POSSIBLE

• TO FORTIFY MEASURES FOR ENVIRONMENTAL PROTECTION AT PLANT LEVELS AND TO CONTINUE WITH THE EFFECTIVE ECO-CONSERVATION ACTIVITIES IN THE VALLEY AREA.

• STRENGTHENING OF SOCIO-ECONOMIC DEVELOPMENT FOR THE INHABITANTS OF NEIGHBORING VILLAGES OF THE MAJOR PROJECTS

THE TENNESSEE VALLEY AUTHORITY (TVA) - A PARTIAL MODEL FOR THE DAMODAR VALLEY CORPORATION (DVC)

BRIEF COMPARISON

Page 40: training_Report_Guidelines(1).doc

CATCH AREA Sq. Mile 40,200

RIVER LENGTH Miles 652

FOREST COVER Acres 13,000,000

(1930)

MEAN YEARLY R/F Inches 51

MEAN YLY RUNOFF % of rainfall 42

DAM (MAJOR) Nos. 39

POPULATION Nos. 2,800,000 (1930) 10,720,485 (1971)

14,076,399 (1991)

MUNICIPAL & INDUSTRIAL WATER SUPPLY

SUPPLYING WATER TO ABOUT 170 MUNICIPAL & INDUSTRIAL AGENCIES FROM MACKLUKXIGUANGE NEAR DALTANGUANGE IN JHARKHAND TO PANAGARH IN WB.

MAIN INDUSTRIAL CONSUMERS

• COAL INDIA

• STEEL PLANTS

• THERMAL PLANTS

• RAILWAYS

• CEMENT FACTORIES

Page 41: training_Report_Guidelines(1).doc

• HFCL, DPL, STPS ETC.

MAIN DOMESTIC CONSUMERS

• JHARIA WATER BOARD

• DHANBAD WATER WORKS

• ASANSOL RANIGUNGE & DURGAPUR MUNICIPALITIES

PUBLIC HEALTH ENGINEERING DEPARTMENTS (JHARKHAND & W. BENGAL) ETC.

MUNICIPAL AND INDUSTRIAL WATER WITHDRAWAL

Withdrawal in MCM/Day

Page 42: training_Report_Guidelines(1).doc

IRRIGATION AREA

WEST BENGAL

Kharif Irrigation potential: 9,73,000 acre (3,93,763 hectare)

Rabi irrigation potential : 55,000 acre (22,258 hectare)

JHARKHAND

Kharif Rabi Total

Hectare Hectare Hectare

Check dams (16,882) 64,748 64,748

Small Reservoirs

Jamunia 1458 1,458

Charwa 405 405

Gonda 931 931

Proposed

Konar Reservoir 47,849 14,074 61,923

Balpahari Reservoir 40,468 40,468

1,69,933

Page 43: training_Report_Guidelines(1).doc
Page 44: training_Report_Guidelines(1).doc

MAJOR ISSUES FACED BY DVC

• LAND ACQUISITION

• REHABILITATION AND RESETTLEMENT

• FLOOD OPERATION

• LOWER DAMODAR CHANNEL CAPACITIES

• OPERATION OF THE TENUGHAT RESERVOIR

• ACTIVITIES WITHOUT KNOWLEDGE OF DVC

• ENVIRONMENTAL IMPACT

• CAPITAL SHARING

Page 45: training_Report_Guidelines(1).doc

• FUND

• ILLITERACY

• POLITICAL WILL

• EMPLOYMENT

• EXTRACTION OF FULL BENEFITS (TPD ETC)

• EROSION & SEDIMENTATION

• SHARING OF WATER

• TECHNOLOGY

• LACK OF PRO-ACTIVE PARTICIPATION OF STAKE HOLDERS

STRATEGIES TO COMBAT ISSUES

• FLOOD CUSHION OF TILAIYA AND KONAR RESERVOIR MAY BE USED AS A COMBINED STORAGE FOR FLOOD AND CONSERVATION STORAGE

• IF EXTRA WATER IS MADE AVAILABLE, IRRIGATION FACILITIES MAY BE EXTENDED TO JHARKHAND STATE THROUGH KONAR AND TILAIYA RESERVOIRS

• IN CASE OF MAITHON AND PANCHET, EXISTING OPERATIONAL CONSERVATION LEVEL MAY BE INCREASED BY 1.52 MT. IN EACH RESERVOIR

• ALL M&I WATER ALLOCATIONS MAY BE REVIEWED TO LOCATE SURPLUS IN THE ALLOCATED QUANTITIES

• TO COMBAT THE FLOOD AT THE LOWER VALLEY, DOWN-STREAM FLOOD CARRYING CAPACITIES MAY BE REVIEWED AND MEASURES FOR IMPROVEMENT OF CARRYING CAPACITY MAY BE TAKEN

Page 46: training_Report_Guidelines(1).doc

• ADEQUATE AFFORESTATION AND SOIL CONSERVATION MEASURES ARE ALSO REQUIRED TO BE TAKEN UP AT THE UPPER VALLEY TO REDUCE THE EROSION RATES

• TO TAKE UP RAIN WATER HARVESTING AND GROUND WATER RECHARGING PROJECTS

• RENOVATION OF OLD IRRIGATION & WATER SUPPLY CANAL SYSTEM AND IMPLEMENTATION OF MODERN IRRIGATION TECHNIQUES FOR OPTIMUM USE OF THE RESOURCE

Page 47: training_Report_Guidelines(1).doc

6