Upload
diane-jennings
View
214
Download
0
Tags:
Embed Size (px)
Citation preview
TRAINING ON WORLD BANK SAFEGUARD POLICIES
Agi Kiss, Regional Safeguards Coordinator, Europe and Central Asia Tashkent, November 2013
Introduction and Overview
Presentation Outline
Overview of the WB Safeguard Policies (10+1): Scope and Principles
Roles and Responsibilities of World Bank, Financial Intermediary, Project Implementation Unit, project sponsor/implementer
Who are the Stakeholders?
WB BoardWB
Board
Project Beneficiaries
Project Beneficiaries
CivilSocietyCivil
Society
NGOsNGOs Affected Persons
Affected Persons
BorrowersBorrowers
MediaMedia
Private Investors
Private Investors
WB Management
WB Management
International Financial Institutions
International Financial Institutions
Overview of Safeguard Policies
Overall scope and principles
All SG Policies: objectives and triggers
OP 4.01
OP 4.04
OP 4.12
OP 4.37
Closer Look (also separate presentation
later)
6
Cross-cutting Principles of SG Policies
OBJECTIVES:
Avoid negative impacts where possible; otherwise minimize, reduce, mitigate, compensate (in that order)
Identify and support sustainable approaches / env & social benefits
Match level of review, mitigation and oversight to level of risk and impacts
Inform the public and enable people to participate in decisions which effect them
Integrate environmental and social issues into project identification, design and implementation
Strengthen Borrower / implementer capacity
Application: • to all WB-financed investment operations (including TA)• To all activities under any project receiving funding from
WB, even if financed from another source
Legal Policies• OP 7.50 International Waterways• OP 7.60 Disputed Areas
Environmental Policies• OP 4.01 Environmental Assessment• OP 4.04 Natural Habitats• OP 4.09 Pest Management• OP 4.11 Physical Cultural Resources• OP 4.36 Forests• OP 4.37 Safety of Dams
Social Policies• OP 4.12 Involuntary Resettlement• OP 4.10 Indigenous Peoples
WB “Safeguard” Policies (10+1)
+ Access to Information Policy
Some environmental and social issues of concern are not covered by specific Safeguard OPs (e.g.: climate change, gender, child labor, poverty alleviation…). Where relevant these should be covered in the ESIA (OP 4.01)
- Use of Country Systems for Safeguard Policies......
OP 4.01 (Environmental Assessment): Ensure potential negative env/social issues are identified, understood and avoided or mitigated ; support environmentally sustainable options
Triggers: direct or indirect physical investments (civil works; provision of goods with “issues”); TA linked to physical investments; any other OP triggered
OP 4.04 (Natural Habitats): Maintain biodiversity and natural ecosystems ; involve local communities in management of Protected Areas and biodiversity
Triggers: investments in, near or likely to affect natural ecosystems (terrestrial, riverine, coastal, marine, aerial); Protected Areas
Safeguard Operational Policies: Objectives, Triggers, Documentation
Documentation: SEA, E(S)IA / E(S)A, EMF, EMP, Env. Guidelines, Env. Audit, etc.
Documentation: Usually incorporated in EA/EMP
Project Categories by Environmental Risk Category A
• significant adverse impacts that are sensitive, diverse, or unprecedented, or that affect an area broader than the sites or facilities subject to physical works
• conversion/alteration of natural habitats
• significant quantities of hazardous materials
• major resettlement
Category B(Compared with Category A):
• potential impacts less adverse & more limited, fewer, site-specific, likely reversible • Mitigation measures can be more easily designed/implemented
Category Cexpected to have no adverse environmental impacts, or only minimal impacts easily and fully mitigated through routine measures Category FI:
To be discussed later
OP 4.09 (Pest Management): Reduce human & environment exposure to hazardous pesticides; promote Integrated Pest Management
Triggers: financing purchase of pesticides; investments likely to introduce or increase pesticide use (expansion or diversification of agricultural production)
Documentation: Pest Management Plan (free standing or section in EA)
OP 4.10 (Indigenous Peoples): Protect livelihoods and cultures, support economic and social integration on peoples’ own preferred terms
Triggers: investment within an area occupied or used for economic purposes (presently or traditionally) by a group which falls within definition of IP (in ECA, only northern Russia)
Document: Indigenous Peoples Framework or Plan
OP 4.11 (Physical Cultural Resources): Preserve cultural heritage
Triggers: civil works on historical buildings or in historic areas or areas with rich cultural history)
OP 4.12 (Involuntary Resettlement): Protect people from economic & social impacts of losing land or access to land-based resources
Triggers: potentially any case where land is required for investment (privately owned or publicly owned). Residence or economic use; legal title or not. New construction: presume triggered unless clearly demonstrated otherwise.
Documentation: Resettlement (or Land Acquisition) Policy Framework; Resettlement (or LA) Action Plan
Documentation: Physical Cultural
Protection Framework and/or Plan or section in EA/EMP
The many faces of land acquisition/involuntary resettlement
OP 4.36 (Forestry): Promote sustainable forest management; rural poverty reduction Triggers: investments in/near/upstream of forest areas (esp. natural forest) which are likely to result in forest loss/encroachment; enterprises involving wood or non-timber forest products
OP 4.37 (Safety of dams): Protect people and investments from dam failure
Triggers: dam construction/rehabilitation; water or power projects dependent on dams
Documentation: Dam safety analysis, emergency plan, etc.
Documentation: section in EA/EMP
OP 7.50 (International Waters): riparian States are notified of and have opportunity to question/comment on projects affecting shared water bodies
Triggers: ANY investment involving water abstraction, release of water or materials into water, or hydrological impacts (regardless of scale) , which is connected with a water body shared by 2 or more countries (aquifers, open seas excluded; exception available for rehabilitation of existing schemes)
OP 7.60 (Disputed Areas): Ensure disputing States agree to
proposed project
Trigger: investments in area which is under dispute between countries (e.g. disagreement on precise border)
Access to Information: Transparency, stakeholder participation, better projects
Trigger: all operations
Documentation: notification letter (or exemption memo)
Documentation: Process described and meeting minutes included in EIA
Documentation: legal agreements
Important points to remember:Application of OP 4.04 is not limited to Protected Areas. It applies to all natural habitats (including terrestrial, aquatic, marine, aerial).
EIA should indicate whether the proposed investment has the potential to impact critical and/or non-critical natural habitats. Often this will require field work covering multiple seasons (not just literature review and consultation with experts).
If EA indicates a project would significantly impact a (non-critical) NH, it may be financed but must include mitigation measures acceptable to the WB
(Remember the “Mitigation Hierarchy”)
When OP 4.04 is triggered, often calls for involvement of a Panel of Experts in project preparation / assessment / design
Projects affecting natural forests trigger both the Natural Habitats policy and the Forests policy
More information in separate presentation on “screening and
classification”
World Bank Screens and Sets Project
EA Category
Advises Borrower on the Bank’s EA requirements
Reviews and gives “No Objection” for EA reports (Due Diligence instruments)
Makes report available in Info shop
Supervises implementation of EA/EMP
Makes mutually agreeable changes during implementation
Borrower Prepares and Implements
EA/EMP/EMF in accordance with national laws and WB OPs
Consults project-affected groups and local NGOs
Discloses draft/final documents in country
Responds to Bank and public
Monitors implementation of EMP
Ensures compliance under national laws
Roles and Responsibilities: Direct Investment Projects
Roles & Responsibilities: “Indirect investment” Projects
World BankAssigns SG Category to the overall Project (FI, A, B, C)
Assesses FI capacity to implement SG
Advises FI on SGs and on Framework Documents; gives No Objection to Framework Documents
Discloses all SG documents in Infoshop and sends to Board as required
Prior and/or Post-review of EAs/EMPs/RAPs
Supervises implementation together with FI
FI (or other Intermediary)
Prepares Framework Documents for the overall Project (Environmental Management Framework; Resettlement Policy Framework)
Disclosure and public consultation on Framework Documents
Screens, categorizes, evaluates, approves and monitors Sub-projects based on Framework documents (including ensuring preparation of acceptable
EAs/EMPs; RAPs*)(Sub) BorrowerPrepares EA/EMP, RAP* based on guidance from FI
Disclosure & public consultation of EMP/RAP
Implementation of EMP/RAP* (including selection of contractors; incorporating EMP in contracts; ensuring compliance)
*Preparation and/or implementation of RAP might be responsibility of a separate Government agency
Contractual relationship
WB Safeguard Policies and National Legislation/Regulations
Principles:
Where requirements or standards differ, the more stringent requirements prevail (might be national, might be WB)
Where WB policies and national laws conflict, WB policies prevail for projects with WB financing (even for project components financed by Govt. or others)
Legal basis: Loan Agreement with WB has standing of international treaty, superseding national law
Result: ideally national policy reform, but may be “ring-fencing” of project (can lead to situation of different standards applied in different cases)
Some flexibility in implementation as long as consistent with fundamental principles of Safeguard policies
Screening methodology and outcomes (when is EIA required)
Alternative EA documents (e.g. EMP) Contents of EIA One integrated EIA vs. separate EIAs for
different project components Timing (at what stage of project
preparation) Consultation (timing, frequency, scope,
reporting)
Common Gaps and Conflicts Between OP 4.01 and National Laws
TIME FOR A COFFEE BREAK!