CONTENTS1 INTRODUCTION
LOAD-OUT PROJECTS
LOR BARGELANDING CRAFT LOADOUT AND FLOATOFFLEIGHTON STEALTHTURKMENISTANSUDANLOADOUTS OF CONTAINER CRANESBETWEEN TWO BRIDGESMAQTA BRIDGE
INTRODUCTION
Green Palm Marine Consultancy Joint Ventures withTTS to bring together resources to offer engineeringsolutions, support and project management to theoperators in the offshore sector. The combined efforthas made it possible to provide clients with costeffective solutions in a timely manner.
Client: NDSQ
Project: LOR BargeDimensions cargo: 6,500 TYear of Operation: 2012
Notes : New-built LOR barge was loaded onto barge using hydraulic skids
and a push-pull system.
Upon completion of load-out, the LOR was floated off after submerging of
load-out barge.
Client: Al Fattan Shipyard
Project: Landing craft loadout and floatoffDimensions cargo: 1,500 TYear of Operation: 2011
Notes : New-built landing craft was loaded out onto barge utilising
hydraulic skids.
In Mina Zayed Free Port the landing craft was floated off.
Client: Leighton Offshore
Project: Leighton StealthDimensions cargo: 650 TYear of Operation: 2009
Notes : Skidding of accommodation unit onto the Leighton Stealth.
Client: SBM
Project: TurkmenistanDimensions cargo: 2,900 TYear of Operation: 2007
Notes : Load-out of an FSO and two more floating units onto barge via
SPMT’s.
Float-off in Mina Khalid and Jebel Ali Port
Client: Jan de Nul
Project: SudanDimensions cargo: 1,750 TYear of Operation: 2006
Notes : Loading by means of float-over of dredger Jerommeke and
associated tugboat. Sail to Sudan and offload by means of submerging
barge.
Upon completion of the jog, reverse the operation.
Client: Various
Project: Loadouts of container cranesDimensions cargo: VariousYear of Operation: 1986 - 2014
Notes : Load-out, sea transport and load-ins of various STS cranes and
RTG’s from the UAE to various destinations
Client: Noell Imac
Project: Between Two BridgesDimensions cargo: 800 TYear of Operation: 2003
Notes : Load-out of bridge onto barge at Musafah via skid system. Sail
to bridge location.
Bridge lowered onto bearings via ballasting of barge