Track-O
Jib Crane
INSTALLATION / UNINSTALLATION
PROCEDURE
REV. 02/2014
Page 2 of 10
TABLE OF CONTENTS
INSTALLATION PROCEDURE ............................................................. 3 - 6
UNINSTALLATION PROCEDURE ....................................................... 7 - 10
Page 3 of 10
INSTALLATION PROCEDURE
1. Position the Track-O backwards to the base of the jib crane.
2. Remove the drawer from the Track-O
and put the jib crane breaker to
« OFF » position.
3. Connect the wiring extensions
control/power to the red and black
connectors of Track-O and of Jib
crane.
Page 4 of 10
INSTALLATION PROCEDURE
4. Put the jib crane breaker to "ON"
position and then put the Track-O
drawer in place.
5. Back off the Track-O until the back lower studs get completely through the base of the jib
crane.
The pedestal height can be changed with a lifting device or horizontal mast of the jib crane.
6. Retract the vertical mast cylinder.
It moves the jib crane base towards
the Track-O, pass through the studs
to get a perfect seating.
Page 5 of 10
INSTALLATION PROCEDURE
7. Set the rear part with 8 nuts ½-13, 8
lock washers and 8 washers.
8. Set the upper part with 8 bolts ½ -
13 x 1 ¼ and 8 lock washers.
9. Move the jib crane in order to remove the lifting device.
Page 6 of 10
10. Remove the drawer from the
Track-O and put the jib crane breaker to « OFF » position.
11. Unplug the wiring extensions
control/power and plug the red and
black control/power connectors of the
jib crane to the Track-O.
12. Replace the jib crane breaker to "ON"
position and then put the Track-O
drawer in place.
13. The jib crane can now be used with the Track-O.
Page 7 of 10
UNINSTALLATION PROCEDURE
1. Locate a beam or any other lifting system (chain fall, etc.) with a 500 kg or more lifting
capacity and having a minimum height of 7 feet.
2. Move the Track-O with jib crane installed to this area.
3. Remove the drawer from the
Track-O and put the jib crane breaker to « OFF » position.
4. Unplug the red and black connectors
« control/power » from jib crane.
Page 8 of 10
UNINSTALLATION PROCEDURE
5. Connect the wiring extensions
control/power to the red and black
connectors of Track-O and of Jib crane.
6. Put the jib crane breaker to "ON"
position and then put the Track-O
drawer in place.
7. Position the crane so that the 2
masts make a 90 degrees angle.
Page 9 of 10
UNINSTALLATION PROCEDURE
8. Attach a sling just behind the
horizontal mast cylinder pivot.
Attach this sling to lifting device or
selected beam.
The lifting device or beam must have
a 500 kg or more lifting capacity with
a minimum height of 7 feet.
9. Remove the 8 nuts behind the base
and the 8 bolts on top.
10. Deploy the vertical mast cylinder.
It releases the jib crane base from the rear upper studs.
Page 10 of 10
UNINSTALLATION PROCEDURE
11. Move the Track-O forward until
complete removal of jib crane base
from the Track-O.
The jib crane is completely removed
and is in balance.
12. Put the jib crane breaker to « OFF »
position and unplug the
“control/power” wiring extensions.
13. The Track-O can be used without the jib crane.