19
WTP Commercial Grade Dedication of Complex Items Chris Hartz Bechtel National Inc. Procurement Engineering Manager Bechtel National, Inc.

Track 2 WTP Commercial Grade Dedication of Complex Items.Purpose Of Presentation The WTP Project CGD: NRC vs. DOE projects – Safety Related (NRC) – Safety Class (DOE) – Safety

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Track 2 WTP Commercial Grade Dedication of Complex Items.Purpose Of Presentation The WTP Project CGD: NRC vs. DOE projects – Safety Related (NRC) – Safety Class (DOE) – Safety

WTP Commercial Grade Dedication of Complex Items Chris Hartz Bechtel National Inc. Procurement Engineering Manager

Bechtel National, Inc.

Page 2: Track 2 WTP Commercial Grade Dedication of Complex Items.Purpose Of Presentation The WTP Project CGD: NRC vs. DOE projects – Safety Related (NRC) – Safety Class (DOE) – Safety

Waste Treatment Plant Project

Purpose Of Presentation

The WTP Project CGD: NRC vs. DOE projects

– Safety Related (NRC) – Safety Class (DOE) – Safety Significant (DOE) – Air Permit (State of Washington and DOE)

Application of NQA-1, EPRI 5652, 6406, to large new nuclear construction (EPC) To discuss CGD of complex pieces of equipment

Page 3: Track 2 WTP Commercial Grade Dedication of Complex Items.Purpose Of Presentation The WTP Project CGD: NRC vs. DOE projects – Safety Related (NRC) – Safety Class (DOE) – Safety

Waste Treatment Plant Project

3

New Nuclear Construction EQ versus CGD

New nuclear construction projects

– Design and/or licensing activities may not be complete (e.g., ash-fall) Risk analysis

– EQ and CGD may be in different sequences – CGD can start prior to or in concert with EQ, but is not complete until

EQ is complete Risk analysis

– Reconciliation of EQ with CGD required before item is dedicated as Q – Unique WTP EQ requirements – CGD ≠ Design Verification

Page 4: Track 2 WTP Commercial Grade Dedication of Complex Items.Purpose Of Presentation The WTP Project CGD: NRC vs. DOE projects – Safety Related (NRC) – Safety Class (DOE) – Safety

Waste Treatment Plant Project

4

Commercial Grade Dedication vs. Equipment Qualification

Equipment Qualification: Suitability Evaluation (Criterion III) – NQA-1 Section 3, IEEE 344/323 – Validation that SSC will perform their respective safety functions

during and/or DBE – Prototype testing – EQ via testing: Destructive (item unfit for use after testing) – EQ via analysis or experience: Nondestructive (item fit for use)

CGD Acceptance Process (Criterion VII) – NQA-1 Section 700, EPRI NP 5652/6406 – Technical evaluation – Verification 4 Acceptance Methods = reasonable assurance the item

will perform its intended safety function – Dedication at normal conditions, not upset or accident (e.g., seismic) – Not directly related to design verification

Page 5: Track 2 WTP Commercial Grade Dedication of Complex Items.Purpose Of Presentation The WTP Project CGD: NRC vs. DOE projects – Safety Related (NRC) – Safety Class (DOE) – Safety

Waste Treatment Plant Project

5

BNI CGD Process -Supply Chain-

Procurement Engineering (PE) is involved with both nuclear (Q) and commercial (CM) suppliers PE conducts assist visits to mitigate rework (cost savings) PE conducts performance based CGD surveys of

commercial suppliers PE participates as CGD experts on NQA-1 supplier audits PE reviews and accepts all NQA-1 suppliers CGD programs

and CGD plans

Page 6: Track 2 WTP Commercial Grade Dedication of Complex Items.Purpose Of Presentation The WTP Project CGD: NRC vs. DOE projects – Safety Related (NRC) – Safety Class (DOE) – Safety

Waste Treatment Plant Project

WTP Examples of Complex Dedication

Thermal Catalytic Oxidizers Active valves Low Activity Waste Exhauster Pumps Emergency Turbine Generators

6

Page 7: Track 2 WTP Commercial Grade Dedication of Complex Items.Purpose Of Presentation The WTP Project CGD: NRC vs. DOE projects – Safety Related (NRC) – Safety Class (DOE) – Safety

Waste Treatment Plant Project

7

WTP Commercial Grade Dedication

-Challenges- Technical Evaluations

Depth of evaluation –What is being dedicated (equipment vs. components vs. parts) –Design function –Safety function

FMEA –Depth –Level of detail

Use of proprietary data Access to sub-supplier resources and other information Suitability evaluation not complete Seismic and Environmental Qualification not complete Configuration control

Page 8: Track 2 WTP Commercial Grade Dedication of Complex Items.Purpose Of Presentation The WTP Project CGD: NRC vs. DOE projects – Safety Related (NRC) – Safety Class (DOE) – Safety

Waste Treatment Plant Project

Low Activity Waste Exhauster

8

Page 9: Track 2 WTP Commercial Grade Dedication of Complex Items.Purpose Of Presentation The WTP Project CGD: NRC vs. DOE projects – Safety Related (NRC) – Safety Class (DOE) – Safety

Waste Treatment Plant Project

Pumps

9

Page 10: Track 2 WTP Commercial Grade Dedication of Complex Items.Purpose Of Presentation The WTP Project CGD: NRC vs. DOE projects – Safety Related (NRC) – Safety Class (DOE) – Safety

Waste Treatment Plant Project

WTP Emergency Turbine Generators: Case Study

10

Page 11: Track 2 WTP Commercial Grade Dedication of Complex Items.Purpose Of Presentation The WTP Project CGD: NRC vs. DOE projects – Safety Related (NRC) – Safety Class (DOE) – Safety

Waste Treatment Plant Project

Emergency Turbine Generator CGD Challenges

NQA-1 (2004) and EPRI 5652/6406 as written for spare parts

programs, not new construction Seismic/Environmental Qualification not complete Identification of item being dedicated: complete assembly vs. module

vs. part vs sub-parts How many critical characteristics

– Equipment/component/part/material Level of detail in technical evaluations

– Subpart safety classifications Software “Reasonable Assurance” vs “Absolute Assurance” Level of detail in CGD Plans and reports

11

Page 12: Track 2 WTP Commercial Grade Dedication of Complex Items.Purpose Of Presentation The WTP Project CGD: NRC vs. DOE projects – Safety Related (NRC) – Safety Class (DOE) – Safety

Waste Treatment Plant Project

12

Bechtel National Inc.

**On Power Inc. Design

Fabrication

Rolls Royce (complete)

Turbine Design

Fabrication

Hyundai-Ideal Generator

Design Fabrication

Allen Gears Gear Box Design

Fabrication

*Seismic Dynamic Analysis

TBD

Third Party Reviews

Mesa Sequoyah

Woodward Controller

Design Fabrication

ATCO Silencer Design

JR Capital Silencer

Fabrication

Seismic Qualification Static Analysis

NQA-1 *Sub-contract to BNI

CM **ETG Prime Contractor

Page 13: Track 2 WTP Commercial Grade Dedication of Complex Items.Purpose Of Presentation The WTP Project CGD: NRC vs. DOE projects – Safety Related (NRC) – Safety Class (DOE) – Safety

Waste Treatment Plant Project

Rolls Royce Turbine Engine 501KB7S CGD Strategy (Technical Evaluation)

BNI Challenges: – Develop an effective dedication strategy for a complex

mechanical system comprised of over 600 highly engineered engine sub-components

– Proprietary data – First of a kind dedication – Use of Rolls Royce product history – Use of Rolls Royce FMECA – Access to Rolls Royce SMEs – Access to Rolls Royce supply chain – Level of detail in CGD plans

13

Page 14: Track 2 WTP Commercial Grade Dedication of Complex Items.Purpose Of Presentation The WTP Project CGD: NRC vs. DOE projects – Safety Related (NRC) – Safety Class (DOE) – Safety

Waste Treatment Plant Project

Rolls Royce Turbine Engine 501KB7S CGD Strategy (Technical Evaluation)

Technical Evaluation:

– Series of ongoing technical meetings at Rolls Royce – Detailed technical review: Part drawings Production Travelers QA Program documents (AS 9100 quality program)

– Interface w/ Rolls Royce SME’s Design Engineers Manufacturing Engineers Supplier Quality

– Toured plant, focused on areas specific to the 501KB7S

14

Page 15: Track 2 WTP Commercial Grade Dedication of Complex Items.Purpose Of Presentation The WTP Project CGD: NRC vs. DOE projects – Safety Related (NRC) – Safety Class (DOE) – Safety

Waste Treatment Plant Project

501-KB7S Turbine Detail

4th-Stage Blade Vane

3rd-Stage Blade Vane

2nd-Stage Blade Vane

1st-Stage Blade Vane

Cast Front Turbine Bearing

Support Rear Turbine Bearing

Support

Wheel 1st, 2nd 3rd, 4th

Vane Case

Inlet Case

Page 16: Track 2 WTP Commercial Grade Dedication of Complex Items.Purpose Of Presentation The WTP Project CGD: NRC vs. DOE projects – Safety Related (NRC) – Safety Class (DOE) – Safety

Waste Treatment Plant Project

Rolls Royce Turbine Engine 501KB7S CGD Strategy (Critical Characteristics)

Critical Characteristics: – Engine Assembly Performance Requirements

– Start time – Power Output

Item Markings – Representative Characteristics from Sub-Assemblies/ Items Markings Dimensional Chemical Properties Physical Properties Performance Properties

16

Page 17: Track 2 WTP Commercial Grade Dedication of Complex Items.Purpose Of Presentation The WTP Project CGD: NRC vs. DOE projects – Safety Related (NRC) – Safety Class (DOE) – Safety

Waste Treatment Plant Project

Rolls Royce Turbine Engine 501KB7S CGD Strategy (Acceptance Methods)

Method 2 – Identification of required QA program attributes – Identified attributes required to control selected CC’s – Verification QA program attributes on selected sub-set of CC’s

bounding of engine safety related components Method 3

– Witness factory acceptance test at Rolls Royce – Witness factory acceptance testing at OPI

Method 4 – Document extensive product history in similar applications. Power generation Stand-by power Navy marine applications

17

Page 18: Track 2 WTP Commercial Grade Dedication of Complex Items.Purpose Of Presentation The WTP Project CGD: NRC vs. DOE projects – Safety Related (NRC) – Safety Class (DOE) – Safety

Waste Treatment Plant Project

Turbine CGD Process: Lessons Learned Need for Project Execution Plan

– Technical requirements – Tailoring of IEEE 387 requirements – Equipment qualification – CGD

Early engagement of key stakeholders – Senior management – Quality Assurance – Customer representatives

Linkage between CGD Plans and Execution Plan Use of Method 4 Formal PEER review process

– Mesa Associates: 2013 – Sequoia: 2014 – Future assessments planned

18

Page 19: Track 2 WTP Commercial Grade Dedication of Complex Items.Purpose Of Presentation The WTP Project CGD: NRC vs. DOE projects – Safety Related (NRC) – Safety Class (DOE) – Safety

Waste Treatment Plant Project WTP Complex Items

CGD Process

QUESTIONS

19