Upload
ahmedamer1
View
217
Download
0
Embed Size (px)
Citation preview
8/12/2019 TRA Welding and Stringing 6 Pipeline
1/2
This section should be used to summarise the
key points of relevant risks identified
by the team discussion
TASK:The steps involved in
doing the job
HAZARD:What could go wrong
and what would the
effect be?
CONTROLS:How can the hazard be prevented?
Measures in placefor recovery
What action to be
taken if the control
fails
RESPONSIBILITIES:
Who is
going to take
action?
CONTROLS INPLACE?
Yes No
Review location
drawings/Maps
Lifting pipes by
crane
Hot work
(welding, grinding)
Transportation of
6x12m pipes on trailer
from storage area to
worksite
oDamage to existing
lines during
offloading activities
oDropping objects
oUncontrolled loads
oSource of ignition
(fire, explosion)
o Personal injuries
(burns/eye injuries )
Noise fron assets
oPipes movement
while being driven on
graded road causing
slipping/unsecured
load.
oClear understanding of the location and the equipment on that
location (topsides and buried).
oCertified lifting equipment (crane, shackles, wires, etc...)
oTag lines used by comptent rigger
oBalance the pipes while moving them with side boom
oOne comptent banksman only to give instructions to cranedriverwearing yellow vest
oNo personnel to stand under suspended loads
oBarrier around lifting area.
oVHF Radio communications to be available (for all steps of
the job)
oInspect All sets before use
oGas test
oUse hot work enclosure (tent) and barriers/signs where
applicable
o
Use PPE for hot work (i.e. welding mask, welding gloves)oEarthed welding sets inspected by electrical dep
oCompetent fire watcher to be appointed
oNo flammable materials at the work site
oFire watcher to inspect site 30mins after welding
oOrganize worksite (cables, machines, welding space, etc..)
oHearing protection
oFire Extinguisher
oLoad stoppers on trailer
oSecure loads by tight slings
oNo metal-to-metal contact by (wood packingoTry and park the trailer on a level surface, where possible.
oRemoval of securing devices only once by experienced one
o Fire extinguisher
shall be in place
oMedical Kit in
place
oContact Radio
Room
Procedure/Work Guideline Reference:
Welding and stringing of 6 pipeline of new Well OB AN Permit/Job Card No: 100 Risk Assessment Reference No:100
Task Risk Assessment
8/12/2019 TRA Welding and Stringing 6 Pipeline
2/2
Area: Location: Talk Leader: .Person Supervising: .Job: Date & Time:
Reviewed by (initials):
Talk leader ..
H.O.D. .
Office ...
Action required:
Update procedures
Update risk
assessments
Other
(Raise remedial action form or
change requests as necessary)
Hazard/Risk IdentificationHazard/Risk Management
If so, the work may be hazardousand care should be taken toensure the work is done safely
If the answer to any of thesequestions is NO, then the safety
of people is at risk
The talk leader should confirm the
understanding of the group by
asking open questions on the
above points
Will the work involve:
The use of lifting equipment?
(i) Is this TRIC a lifting plan
(ii) Is a separate lifting plan diagram
required/available?
Working in noisy areas?
Line breaching or potential hydrocarbon release?
Environmental impact?
Manual handlingmoving objects/loads? (If
yes obtain /complete a manual handling
assessment
Working near objects that may move?
Working in an area with poor lighting or a
tight/confined space?
Working at height?
Working near areas that could cause personnel
to slip, trip, or fall? Using portable electrical equipment?
Working with equipment or connections under
pressure?
Working with dangerous goods and substances
hazardous to health?
Personnel who are new to the area or each
other?
Equipment which is potentially dangerous?
Remember, everyone is responsible for:
Using the correct tools for the job
Being aware of the hazards around them and
remaining vigilant to change
Using the correct PPE for the job
Making themselves aware of, and working within,
the requirements of the PTW system, Procedures,Risk/MSDS/Manual Handling Assessments
Can all personnel in the group answer YES to the
following questions?
Have all the significant hazards involved
with the work been identified?
Have control measures been identified for
these hazards?
Have the people responsible for implementing
these control measures been identified and are
these controls in place?
Has the method of communication been agreed
and tested?
Is everyone aware of what is being done at the
worksite?
Are we aware of what everyone else is doing at
the worksite?
Does everyone know that any changes to the
work plan have to be communicated to everyone
involved in the work?
Does everyone know that any new people
joining the work party must be given a full and
thorough handover?
Single work party in area?
10.5
94 ..
83 ..
72 ..
6....1
Operator
Area
Attendees