Experience of Migration to State of the Art Analysis for
Eddy Current Data
Mr. Shun-Tung-Ching Shih – Taiwan Power CompanyMr. Sou-See Lee – Taiwan Power CompanyPresented by Tom Bipes – Zetec
EPRI SG WorkshopJuly 18-20, 2016
History of ISI in Taiwan• Power plants serviced
CHINSHAN
MAANSHAN(PWR -- 951 MWe × 2)
(BWR4 -- 636 MWe × 2)
KUOSHENG(BWR6 -- 985 MWe × 2)
LUNGMEN(ABWR – 1350 MWe x 2#1 Mothballed #2 under construction)
3
History of ISI in Taiwan• Typical techniques employed
Occasion Works Remark
Usual
NDT for Maintenance requirements
All NPPMaintain ISO 9001 Quality System and NDT Laboratory Accreditation(by TAF)
Other Design Change Works
PSI/ISI
PSI / ISI Program Preparation
All NPP
Piping and Vessel shell Thickness measurement (UT)
Heat Exchanger tubing eddy current testingWelds Radiographic Test (RT)VT-1, PT/MT, MUT and AUT for ISI ScopeSteam Generator tubing eddy current testing
MS NPP onlyNeutron Thimble guide tube eddy current testingReactor Core Control rod Assembly (RCCA) eddy current testing
4
Plant Types of degradation Response
CS
Austenitic (TP304)welds were found IGSCC in recirculation piping system.
Replace 10 riser pipes (SS TP316)
Austenitic (TP304)welds were found IGSCC in non-replaced recirculation piping system after 2nd interval.
Weld Overlaid
Condenser Cu-Ni tube with corrosion Replace all tubes w/Ti
KS
Austenitic (TP304)welds were found IGSCC in recirculation piping system.
Weld Overlaid
Condenser Cu-Ni tube with corrosion Plugged & Replace some tubes
MS AVB Wear, scale blockage, loose parts wear, tube end SCC in SG Plugged, Chemical cleaning
All Vessel / Piping wall thinning Reinforce / replace
5
Technology & Integration
Heat Exchanger tubes ECT and data Evaluation
Piping AUT S/G mockup, data Evaluation and Management
7
Business Need• Need for migration to PC software
• Old legacy HPUX hardware• Obsolete systems not supporting new inspection products and technologies
• Increase in Productivity• Reduction in process costs• Compatibility with other PC products
8
• Needs in selection process• Widely accepted and commercially available software
• Familiarity for existing operators• Presenting best technologies• Validation of transition
Migration Plan
9
Migration Plan
• Replace Eddynet CDS with RevospECT• Incorporate RevospECT Basic• Customized version of RevospECT PRO• Tuned to specific requirements and specification• Effective Transition Plan
10
Implementation Plan
• Eddynet AQ/AN/DM Implementation• Full PC Based Networked System Integration
• Retired aging HPUX Hardware
• Phased in over several Years• AQ & DM (2013)• AN & DQV (2014)• RevospECT Basic – Current Configuration (2015)
11
• RevospECT Commercial Software• Basic Vs. Pro Version
• Customized for Customer Needs• Noise Measurement not required• Final Acceptance logic not implemented• HDC (Historic Data Compare) not included
Implementation Plan
14
• RevospECT Basic• Replicated Previous CDS Parameters• Simple User Adjustable Parameters• Increased User Capabilities over CDS
• Productivity – Multiple Cal Groups Simultaneously• Landmarking improvements• Regions Of Interest – no missed overlap• Enhanced Calibration/Validation• Expanded Analyzer Methodology• Simultaneous Reporting of Results (flaws, sludge, dent)
Implementation Plan
15
AUTO AN – Dashboard ScreenImplementation Plan
17
Multiple cal groups simultaneously
Individual cal group interacation
• RevospECT Pro• User Modifiable• Full Functionality
• Final Acceptance• Noise Measurement and Monitoring• Historic Data Compare• Other Enhancements and features
Future Possibilities
19
Additional New Capabilities
• RevospECT Pro – Other Applicability• Maanshan RCCA Inspection
• Fully Automated Analysis (Insertion & Retraction)
• Kousheng Condenser Inspections• Large Quantities of Data (60k+ Tube Files)• Automate challenging Analysis Tasks• Consistency of Results
20
New Capabilities
• RevospECT Pro – Other Applicability• Maanshan RCCA Inspection
• Fully Automated Analysis (Insertion & Retraction)
• Kousheng Condenser Inspections• Large Quantities of Data (60k+ Tube Files)• Automate challenging Analysis Tasks• Consistency of Results
• BOP applications at other plants worldwide!
21
Taiwan Power Quote• “With the implementation of Zetec PC products and RevospECT Basic, Taiwan Power was able to smoothly transition from legacy Unix products to state‐of‐the‐art PC products and technology. Realizing this new potential, this technology was also applied to our RCCA and Condenser inspections with great success. We will look for other opportunities to apply Zetec advanced technology.”
22
Summary
• Need for SG Equipment/Process Upgrade• PC Based Acquisition and Data Management• RevospECT Basic Custom Auto Analysis Product• Functionality beyond expectations
• Need for Special ECT Projects• RCCA Inspection Automated• BOP Condenser Inspection Automated• Customization to Utility needs• Reduction in cost, increase in POD and Productivity• Utility Needs exceeded
23