109
TOYOTA 180L SPIRAL RADIATOR HOSE DESIGN TO SIX SIGMA GOAL A Thesis Presented to the Faculty of the College of Science and Technology Morehead State University In Partial Fulfillment of the Requirements for the Degree Master of Science by Tay-Shing Chen December 2, 2005 CAMDEN-CARROLL LIBRARY MOREHEAD, KY 40351

Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

TOYOTA 180L SPIRAL RADIATOR HOSE DESIGN TO SIX SIGMA GOAL

A Thesis

Presented to

the Faculty of the College of Science and Technology

Morehead State University

In Partial Fulfillment

of the Requirements for the Degree

Master of Science

by

Tay-Shing Chen

December 2, 2005

CAMDEN-CARROLL LIBRARY MOREHEAD, KY 40351

Page 2: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Accepted by the faculty of the College of Science and Technology, Morehead State University, in partial fulfillment of the requirements for the Master of Science.

Director of Thesis

Master's Committee: -------------'' Chair

Date

rnrl/ t/fGSFS

GS-2. 51,:;. C5!Jl

Page 3: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

TOYOTA 180L SPIRAL RADIATOR HOSE DESIGN TO SIX SIGMA GOAL

Director of Thesis:

Tay Shing Chen, M.S.I.T Morehead State University, 2005

--------

Six Sigma is a systematically strategic management approach for product

design and production improvement in preventing scrap, defect and rework. The

rationale of Six Sigma measurement standard levels are the values of capability

indices that must conform to C~2 and Cplel.5. Here, the implementation ofDFSS

methodology at Cooper Standard Automotive guided the project team to clarify all

the questions that existed between customers and suppliers in designing Toyota 180L

radiator hoses to achieve a goal of Six Sigma measurement standard levels. It was

demonstrated that Cooper Standard in Mt. Sterling, Kentucky is prepared and is

performing at a high level of satisfaction in manufacturing safe, low cost and high

quality rubber radiator hoses for Toyota Motor Manufacturing Indiana (TMMI).

It was concluded as a result of this research that:

I. The result of a Design of Experiment (DOE) trial indicated that the average of

insertion force of34. l libs was higher than the benchmarking Toyoda Gosie

22.73lbs. Three out of seven selected factors had significant effect on

insertion force: Yam Angle, Yam Denier and Yam Package.

Page 4: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

2. The valid construction for producing Toyota 33mm and 37mm radiator hoses

is completed in this research by utilizing DOE and Response Surface Design

(RSD) methodologies to ensure the product meets customer's dimensional,

functional and esthetical requirements.

3. The result of process capability trials demonstrated the process capability

indices of manufacturing radiator hoses on Inside Diameter, Wall Thickness

and Wall Thickness Variation achieved .Six Sigma measurement standard

levels.

Overal~ this research found that the Bulge defect issue could be optimized by

adjusting Pre-form cut length. The Non-Fills defect issue raised but can be solved by

extending the length on the Caps and having an automation robot to trim off the

exceed material on the both ends ofradiator hoses.

Accepted by: __________ __, Chair

Page 5: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Table of Contents

Chapter I ....................................................................................................................... 1

Introduction ....................................................................................... 1

Research Statement ........................................................................... 2

Research Objectives ........................................................................... 3

Significance of the Study ..................................................................... 3

Assumptions .................................................................................. .4

Limitations ..................................................................................... .4

Definition of Terms .......................................................................... 6

Chapter II ....................................................................................... 14

Review of Literature ......................................................................... 14

Literatures Review ................................ : .......................................... 14

Background of Cooper Standard at Mt. Sterling, Kentucky ........................... 20

Review of Radiator Hoses .................................................................. 21

Production Line Process at Cooper Standard ........................................... 23

Chapter ill ....................................................................................... 27

Restatement of Research Objectives ...................................................... 27

Methodology for Research Objective One ............................................... 27

Methodology for Research Objective Two ............................................... 32

Design of Experiment (DOE) for Insertion Force Study ............................ .32

1st Response Surface Design (RSD) for Improving Bulges Problems .............. 35

Page 6: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

2nd Response Surface Design (RSD) for Improving Bulges & Non-Fills

Problems ............................................................................................................... 37

Methodology for Research Objective Three ............................................. .40

Chapter 1V ...................................................................................... .41

Data Analysis and Discussion .............................................................. .41

Research Objective Two Data Analysis and Discussion .............................. .41

Insertion DOE Data Analysis and Discussion ......................................... .41

1st Response Surface Design (RSD) Data Analysis and Discussion ............... .46

2nd

Response Surface Design (RSD) Data Analysis and Discussion ................ 51

Research Objective Three Data Analysis and Discussion ................................ 55

Chapter V ....................................................................................... 64

Conclusions .................................................................................... 64

Research Objective One ..................................................................... 64

Research Objective Two .................................................................... 65

Research Objective Three ................................................................... 66

Implications ................................................................................... 67

References ....................................................................................... 69

APPENDIX A ................................................................................... 70

APPENDIX Bl ................................................................................. 72

APPENDIX B2 .............................. . : ........ ......................................... 74

APPENDIX B3: ............................................................................... 76

Page 7: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

APPENDIX B4: ............................................................................... 78

APPENDIX BS: ............................................................................... 80

APPENDIX B6: ................................................................................ 82

APPENDIX Cl: ................................................................................ 84

APPENDIX C2: ................................................................................ 86

APPENDIX C3: ................................................................................ 88

APPENDIX C4: ................................................................................ 90

APPENDIX D: .................................................................................. 92

APPENDIX E: .................................................................................. 94

APPENDIX F: .................................................................................. 96

APPENDIX G ................................................................................... 98

APPENDIX H:.: ............. .' .... '. ............................................................ 100

Page 8: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

ACKNOWLEDGMENTS

I would like to acknowledge the people that have helped and supported me on

this research project.

First of all, I would like to thank the members of my thesis committee, Dr.

Ahmad Zargari, Dr. Lloyd Jaisingh and Dr. Farouq Alhourani for their professional

assistance on this research, and to Dr. Zachary Bortolot with IRAPP for his editorial

suggestions.

Secondly, I gratefully acknowledge my research supervisor, Mr. Steve

Defazio, for his professional directing on this research project and for sharing his

invaluable life experience. Next, I would like to thank the project team members,

Chris Snarr (Program Engineer), Kathryn Laporte (Quality Engineer), Jodie Jent

(Extrusion Engineer), Bob Trimble (Forming Tech), Chris Massaro (Lean Champion)

and Steve Defazio (DFSS Black-Belt), from Cooper Standard Automotive at Mt.

Sterling, Kentucky, and the employees who were involved in this research project

development.

Finally, I would like to thank both my parents, Yung Ze and Zhang Jiu Chen.

Their full understanding of my desire to pursue a master degree has enhanced my

strength to complete this research.

Page 9: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

CHAPTER I

In trod uctiou

Design for Six Sigma is an excellent management strategy and methodology

tool, and most companies have received great benefit by implementing its philosophy

and have become more successful in the competitive business marketplace such as

General Electric and Honeywell (Adams, Gupta and Wilson, 2003). Cooper Standard

Automotive in Mt. Sterling, Kentucky, is a high performance company that produces

rubber hoses and fluid systems. Currently, they are running trials and prototypes for

new businesses associated with a high reputation customer, Toyota Motor

Manufacturing Indiana (TMMI). The business relates to the upcoming 2007 Tundra.

For this business opportunity associated with Toyota Automobile, Cooper

Standard believed that putting their best effort forward would allow them to provide

outstanding quality performance in the production process and in material control,

thereby meeting Toyota's requirements. In achieving its satisfaction goals, Cooper

Standard has adopted a Design for Six Sigma (DFSS) management approach and

established a capable project team to focus on developing DFSS management and to

utilize the strategies to ensure the quality ofa particular product, Toyota 180L Spiral

Radiator Hoses. Their goal is to meet all specification requirements while maintaining

excellent service.

I

Page 10: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Research Statement:

As Cooper Standard Automotive prepared to begin their relationship with

Toyota Automobile, some critical questions were asked relating to the business

relationship being established.

1. What are the expectations of quality performance that Toyota Automobile

expects to see from Cooper Standard Automotive products?

2. How could Cooper Standard Automotive identify qualitative aspects of the

products performance from the new customer based on the existing production

process?

3. What are the methodologies that Cooper Standard Automotive could utilize to

improve the new products and meet the customer demands?

Based on these three general questions, Mr. Steve Defazio, a

Finishing/ Assembly Manager (DFSS Blackbelt) at Copper Standard Automotive,

adapted the Design for Six Sigma (DFSS) management system approach to discover

strategic solutions for answering these questions in detail. This proactive approach

was a necessary step and ml!inly impacted the launching of this new and unfamiliar

product. It is well known that quality is critical to Cooper's business operation, so at

this point the Design for Six Sigma management was implemented immediately in

investigating all possible design aspects of radiator hoses to prevent the cost on

rework, scrap and defective products before beginning production at Cooper

Standard.

2

Page 11: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Research Objectives:

The research objectives were developed and addressed in this research in

associaticm with Cooper Standard Automotive and they are listed next:

I. Develop the Design for Six Sigma (DFSS) and implement it on Toyota 180L

Spiral Radiator Hoses at Cooper Standard Automotive in Mt. Sterling,

Kentucky.

2. Conduct Design of Experiment (DOE) and Response Surface Design (RSD) to

develop and complete the valid construction value settings in manufacturing

process for spiral radiator hoses in meeting its Inside Diameter (I.D.), Wall

Thickness, Wall Thickness Variation, Functional and Aesthetics requirements.

3. Conduct process capability validation experiments for Toyota 33mm and

37mm spiral radiators hoses.

The effort of utilizing the DFSS methodology assisted the DFSS project team

identified and understood their oriented goals clearly; the objectives of the project

were then developed and implemented into the development phases. Following the

structure ofthe.DFSS methodology, the project team carefully utilized the strategies

ofDFSS step by step to increase quality assurance levels and productivity.

·-Significance of the Study:

Technically, the findings of the Design of Experiment (DOE) and Response

Surface Design (RSD) trials could optimize radiator hoses production process.

However, the manufacturing process capability analysis is a follow up study

regarding the uses of statistical methodology in DFSS management that measuring

3

Page 12: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

the design and to evaluate Cooper Standard production process compare with Six

Sigma measurement standard levels which the capability indices of Cp2:2 and

Cpkcl.5.

Assumptions:

According to the concept of Motorola's Six Sigma, it ensures the production

process capability has only a 3.4 ppm (parts per million) defect rate (Adams, W. C.,

Gupta P., and Wilson E. C., 2003). Hence, this research assumed the DFSS

management system would direct the team to accomplish this goal and pass customer

approval on Toyota spiral radiator hose requirements. Another assumption was that

the research assumed that by using the validation of the 33mm spiral radiator hose

construction, the value setting is compatible with other dimension spiral radiator

hoses since there are six different Toyota radiator hose jobs.

Limitations:

The first limitation that needs to be recognized was that Cooper Standard has

an existing manufacturing process for radiator hose products that has been

implemented for several years. Although improvement opportunities exist, the entire

process did not make any changes to produce this specific Toyota job during the

duration of this research.

The second limitation was the benchmarking target selection. The limitation

was the Cooper hoses which were tested and compared with Toyoda Gosei (TG) V8

Spiral Radiator Hoses on insertion force, since they are one of the competitive

suppliers associated with Toyota Automobile. No other suppliers' products were

4

Page 13: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

taken into the consideration as a benchmarking target. In other worlds, Cooper's

radiator hoses were compared only with Toyoda Gosei (TG) hose products to ensure

the capability and functional performance are comparable in the marketplace.

The third-limitation was that a complete radiator hose product needs to be

tested on several quality standard levels, such I.D., Wall Thickness, Wall Thickness

Variation, Insertion Force Test, Hoses Appearance, Leakage and Burst Test.

However, this research focus on the particular factors that mostly affect to hose's

I.D., Wall Thickness, Wall Thickness Variation, Appearance Qualification and

Insertion Force aspects. Design of Experience (DOE) process was the experimental

methodology that used to study the constructing factors that have most effect on the

hose's Insertion Force and Response Surface Design (RSD) was another experimental

methodology used to optimize the hoses' I.D., Wall Thickness, Wall Thickness

Variation and Appearance qualification.

5

Page 14: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Definition of Terms

• I.D.: Inner diameter of spiral radiator hose.

• Wall Thickness: The overall difference between hose's outside diameter and

inside diameter.

• Wall Thickness Variation: The difference between hose's maximum and

minimum wall thickness points.

• Yarn Denier: The weight in grams of9000 meters of fiber. Denier is a direct

numbering system in which lower numbers represents the finer yarn sizes~.,

840, 1000, and 1100).

• Pre-form Interference: Dimensional interference between uncured hose I.D.

and mandrel diameter.

Example: A value of Pre-form Interference for an I.D. 1.299" hose is 0.018"

in. then the actual hose I.D. need to be made at Extrusion Line by:

1.299" - 0.018" = 1.281"

• Yarn Package: Amount of fabric reinforcement used in the construction of the

radiator hoses.

• EPDM (ethylene-propylene diolefin monomer) Rubber:

Synthetic rubber; a polymer of ethylene and propylene with a small amount of

diolefin monomer added to permit vulcanization with sulfur. Possesses

excellent resistance to ozone, sunlight and weathering, has good flexibility at

6

Page 15: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

low temperatures and good electrical insulation properties (Motorcraft.com,

2005).

• Insertion Force (lbs): Amount of force required for the operator to load the

radiator hoses onto joint fitting between engine and radiator.

• Cap-End Process: A process done during the steam curing process for meeting

customer' s definitional requirements. It results in better control of a hose' s

I.D., Wall Thickness and WaU Thickness Variation; it also prevents potential

rubber shrinkage movement during the steam curing process.

Figure 1. Cap-End on the end of a Radiator Hose

• Bulges: A defect that normally occurs on the bend areas of the hoses after the

steam curing process.

Figure 2. Bulges Issue

7

Page 16: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

• Non-Fills: A defect in which the material is not fully filled within a 2mm

profile tolerance. It normally occurs on both ends of the hoses after the steam

curing process.

Nonfdl exceeds 2mm

Figure 3: Non-Fills Issue

• MINIT AB Statistical Software: An industry standard comprehensive

statistical and graphical analysis software package. It is the primary package

used in Six Sigma and other quality improvement projects, and is widely

known for its comprehensive collection of methods, reliability, and ease-of-

use.

• Capability Jndjces: Cp and Cpk indices that calculate the ratio of the voice of

the customer vs. the voice of the product or process. Cp is a measure of

capability based on short-term or small samples of data, usually what is

available during product development. The speciation limits span ±6 standard

deviation, the system has a Cp of 2, shown in the following equation.

Cp= USL - LSL 6a

12a = 2 6a

Equation-1

8

Page 17: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Cpk is a measure of long term or large samples of data that include not only

variation also the shifting of the mean itself-usually available during steady

state production. The system has a Cpk of 1.5, shown in the following

equation.

Cpk= min (USL-X, X -LSLJ= min(6a-l.5a, l.5a-(-6a)J= 1.5 3a 3a 3a 3a

Equation-2

Thus, a design that yields 6 sigma performance (Cp=2) in the short term can

be expected to produce a Cpk of 1.5 in .the long term when in production

(Antis, D., Creveling, C. and Slutsky, J. 2003, p. 511-513).

• Design ofEXJJerience (DOE)-A pro~ess for generating data that uses a

mathematically derived matrix to methodically gather and evaluate the effect

of numerous parameters on a response variable. Design ofExperiment, when

properly used, produce useful data for model building or engineering

optimization activities (Antis, D., Creveling, C. and Slutsky, J., 2003).

• Fractional Factorial Design-A family of two-and three-level orthogonal arrays

that greatly aid in experimental efficiency. Depending on how a Fractional

Factorial design is loaded with control factors, it can be used to study

interactions or it can be manipulated to promote evaluation of additively in a

design or process (Antis, D., Creveling, C. and Slutsky, J., 2003).

9

Page 18: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

The equation for Fractional Factorial Design is given in the textbook

(Besterfield, H. D., C., H G., and M., 1999). "Total Quality Management".

The number of treatment conditions is determined by:

TC= 11

Where:

TC= number of treatment conditions

I = number oflevels

f = number of factors

Equation-3

To minimize time and cost, this design excludes some of the factor level

combinations. Factorial designs in which one or more level combinations are

excluded are called fractional factorial designs.

Table I summarizes an example of a two-level default design and the base

designs for designs in which to specify generators for additional factors. Table

cells with entries show available run/factor combinations. The first number in

a cell is the resolution of the unblocked design. The lower number in a cell is

the maximum number of blocks you can use.

10

Page 19: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Table 1

Summary of Two-Level Default Design for the Research Experimental Design

Reference

Number of factors

Number of 2 3

runs 4 5 6 7 8 9 10 11 12 13 14 15

full m 4

2 1

full 8

IV m m m 4 4 2 2 1

16 full V IV IV IV m m m m m m m 8 8 8 8 8 4 4 4 4 2 2 1

32 full VI IV IV IV IV IV IV IV IV IV

16 16 8 8 8 8 8 8 8 8 8

64 full V11 V IV IV IV IV IV IV IV

32 16 16 16 16 16 16 16 16 16

128 full YID VI V V IV

64 32 16 16 16 16

• Design Resolution-For fractional factorial designs, indicates which effects are

aliased with one another. When you run a fractional factorial design, one or

more of the effects are confounded. That is, the effects cannot be estimated

independently and therefore, these effects cannot unambiguously be attributed

to a single factor or interaction. Generally, you want to use fractional designs

11

Page 20: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

that have the highest possible resolution consistent with degree of

fractionation required. Resolution III, IV, and V designs are particularly

important (Minitab Inc., 2004).

• Blocks: Blocking is a technique used to increase the precision of the

experiment. Blocks are portions of the experimental unit that are more similar

to one another than to the entire set of data. Although every measurement

should be taken under identical experimental conditions ( other than those that

are being varied as part of the experiment), this is not always possible. Factors

that affect the experiment which can be measured, but are not controlled, can

be accounted for using a blocked design (Minitab 14 Software). For example,

an experiment may be carried out over several days with large variations in

temperature and humidity, or data may be collected in different plants, or by

different technicians. Observations collected under the same experimental

conditions are said to be in the same block (Minitab Inc., 2004).

• Response Surface Design: A response surface, in general, is curved and

bumpy. In order to model this surface, it needs a transfer function with

quadratic or higher terms in it. A two-level design is not capable of estimating

quadratic effects. It needs to have an experiment with at least three levels.

This can get very large. There is, however, an economical design that gives

the needed information. It is called a central composite design (CCD). The

12

Page 21: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

CCD is a composite of a Full Factorial with a center point and additional

points called star or axial points (Antis, D., Creveling, C. and Slutsky, J. 2003).

13

Page 22: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

CHAPTER IT

REVIEW OF LITERATURE

This section reviews the literature related to this research. Then, the

background of the company and the concept of production processes are explained

and interpreted.

Literatures Review

Folaron and Morgan,

(2003) presented a historical table

of the contribution to Six Sigma in

the article "The Evolution of Six

Sigma" as shown in the Figure 4

(p.38). Eli Whitney was a great

contributor in the quality field. In

1798, he received a mass

production contract to make

muskets for the government. He

proved the possibly of using

methods to produce

interchangeable parts by using a

capable machine to replicate different

parts (Folaron and Morgan, 2003, p.

17N: a_....,.-. ......... 1111111••111110.._,._ .. • Need forcorlllistency. • klenllficatlon of dewcts.

192-4: .... ..._Mft

• Proce5s orientlld thlnkln&, • Conirol c:h•tt. (~lo and common c:ilUISe).

i.4-5: n.. , __ ~ llov•-•t ...... • StlttletJcat methods and uw of stallgticiar,a. • Continuous lrnllfowment (~act)

nwt.tlodoqy. • ~ttw anc1e11mont of m~ and Involvement of-,one.

• Dlac,"lostk and remedial Jou~

1•72: TIM ·--.... ffMlt llllove • Quick r"5llOl'lCe to charelll& ~ needs.

1980: PIiia. CfOlllly Mtl Qlrllll!CY ,_ ,,,..

• ~ I:> ac::hklw com~ qualty 1mprov--..

• 1rr1ProW IJJOduct. proc.ess and sen/loe. SUWe for perfection.

Ha7: an.rna11on■1 0r.,_u11oa,., .._._.utio■ • Wldegpreact ah~ of basic elomenls of M>Und

qualt.y systems. • Orvanlmllonal ralb' cry for lmprCM111'181'1t.

HST: llalcolt■ ....... ......_alQll■llty Mar•

• Shar1nc ~ t i::,rac:tlceg.

• Strorw focug on cu&tomars and resul&.

1ea7: lloterola Mtl Sia --• • Focus on cU5tomer ,-ct• and ~son Cit proceu

perlonnance to 1hoM ,-ds. • StrUdllrvcl mathodok>cY wtttl dlsclplne and Pl'OWII

bualnffs results.

leeG-1995: Olltef 1_...UV_

• Tool& to be usod ti,- -yic,ne In the orpnc.adon.

Figure 4. Each Era's Contributions to Six

Sigma ( Folaron and Morgan, 2003)

14

Page 23: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

38). Later in mid-1800s, he created and put into practice the use of the go and no go

gage as a measuring tool that can assure dimensional consistency and detect the over

limits defect parts. It was the earliest quality inspection technique applied to the

industry. (Folaron and Morgan, 2003, p. 38).

Around 1920, Walter Shewhart was a colleague with the most famous quality

leaders of the time, Joseph M. Juran and W. Edward Deming in the Western Electric

manufacturing plant. On May 16, 1924 the new version of a data collection, display

and analysis form was introduced by Shewhart and it was known as a process control

chart and statistical quality control. They are excellent quality techniques that have

widely been used in today's industry (Folaron and Morgan, 2003, p. 39). The rational

of Six Sigma as a measurement standard in product variation was a statistical strategy

contributed by Shewhart; he indicated that three (3) sigma from the mean is the point

where a process requires correction. Later on, 1988, Bill Smith, a statistical engineer

at Motorola introduced the Six Sigma and credit for the term with many measurement

standards (Cp, Cpk, Zero Defects, etc.) (isixsigma.com, 2005).

The Japanese realized that the study and utilization of statistical rational was a

factor in losing the war to the Allies in 1945. However, since Shewhart was unable to

travel due to his illness in 1950; a friend of his, Deming, went to Japan and educated

them on the theory of statistics for continuous improvement; meanwhile, Juran

implemented his principles of quality management throughout Japanese organizations

and addressed solving quality issues. Later, in 1951, his "Quality Control Handbook"

was created (Folaron and Morgan, 2003, p. 40).Over the next twenty years, the

15

Page 24: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Japanese adapted the methodology of using statistics with quality management and

widely applied it to the automobile industry, resulting in successfully designing high

quality, performance automc:,biles, at low cost.

As a matter of fact, losing market share to foreign competitors had a great

impact on American automobile manufacturers. They started seeking better quality

management and strategies because of the stimulation brought from Japan which

made them more aware of this importance. The insufficient knowledge of quality

control in the United States was improved after Deming began helping American

managers to comprehend the concepts of variation and the benefit of using statistical

study for preventing the defect issues and improving the production process (Folaron

and Morgan, 2003, p. 41 ). The great quality improvement works done by Deming and

other quality philosophies has enhanced the industrial activities in America.

Corporations such as Motorola, IBM and General Electric are the most famous and

successful companies that are still unbeatable and fast growing in the extremely

competitive marketplace. Their organizational systems were enhanced and they

benefited by implementing the philosophy and strategy of the Six Sigma management

approach.

In 1988, Bill Smith, a Communication Sector Quality Manager at Motorola,

dedicated the conceptual use of Six Sigma program from a traditional statistic

methodology application to a business improvement strategy approach and it was the

critical key for Motorola to meet their success as a winner of the Malcolm Baldrige

National Quality Award (Harburg. F., 2004). The objective of the program was the

16

Page 25: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

reduction of the variation in every process under a six (6) sigma specification limits.

He decided to have one point five (1.5) sigma shift for the process and assumed it

could behave normally and fit Walter Shewhart's control chart theory (Adams, W. C.,

Gupta P., and Wilson E. C. 2003). This sigma shift for the process was clearly

interpreted and defined from (lwintl.com, 2004)

"The sigma rating is based on the distribution of a process output as related to

a customer requirement. This diagram shows the short-term process output

. .

(solid blue) which is centered in the specification. The short term variability

of the process output is such that the upper specification limit (USL) and the

lower specification limit (LSL) are both six standard deviations ( called cr, or

sigma in statistical parlance) away from the center. Recognizing that most

processes shift somewhat over a long period of time, an arbitrary change of

plus or-1.Scr is expected to happen, leaving 4.5cr between the shifted average

and the specification limit. This means that a process running at a six sigma

level in the short term can tolerate a relatively large amount of drift and still

make only 3 .4 PPM nonconforming over the long term with the dashed blue

line".

17

Page 26: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

LSL U L .--shift--+

Figure 5. Process Shift within Customer Specification

Indeed, the 1. 5 sigma shift means the value of process index (Cpk) I. 5 with a

nonconformance rate 3.4 parts per million were defined throughout a number of years

of production process experiments at Motorola as a standard reference point. Upon

this significant theory, project management phases (DMAIC) were added into Six

Sigma toolkit by Mikel Harry and others (1990) and adapted by other organizations

such as Allied Signal (I 993) and General Electric (1995) to approach a lowest cost

and highest value product and steering to a successful business result

(sixsigmainstitute.com, 2004).

Figure 6 is a clearly DFSS management process phases illustrated by Lean

Sigma Institute for improving existing processes.

18

Page 27: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

CTOs

Chartwr GRR Critical x s Demonstrawd control Basel,,. ldentttled Improvement Plan Capablltty

•Charters •QFD •Process •Mult:1-vari •Project Mgt •MSA Map •FMEA •VOC •C&E •Cpk •Pareto

•DOE •FMEA •Pilots

Lean Sigma Institute - -

•Control Charts •Control Plan •Sigma studies

Figure 6. DFSS Design Phases and Key Tools (Adapted from Lean Sigma Institute)

The management phases of Design of Six Sigma process are: Define, Measure,

Analyze, Improvement and Control (DMAIC) which they used to achieve the 3.4

defects per million opportunities in a project work. In the meaning of those terms,

they are utilized to emphasize any possibility perspectives that associate a particular

product and service via interaction between the internal and external customers.

In the "Define" phase, the team is established and the purpose of the project is

validated and the key tools such as Team Charters and VOC are quickly created and

reviewed in this phase (McCarty, Daniels, Bremer and Gupta, 2005, p. 363). The

development then steps into the "Measuring" phase after the project and product

defined. In this phase, the critical process map needs to be created and so as the

measurement system for providing the valid data (McCarty, Daniels, Bremer and

19

Page 28: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Gupta, 2005, p. 392). Therefore, the valuable data can be defined and colleted by a

reliable data collection process. Next, in the "Analyze" phase, the team determines

the root causes of the problems of the process that it identified in the Define and

Measure phases of the project and the helpful tools are FEMA and Pareto charts

(McCarty, Daniels, Bremer and Gupta, 2005, p. 428). Once the team has validated the

causes of the problems in the process, the new ideas for changing the process are

generated in next phase called "Improve" for improving the process (McCarty,

Daniels, Bremer and Gupta, 2005, p. 455). The powerful tools for accomplishing this

phase are Pilot, FEAM and DOE. Finally, in the "Control" phase, the team should

develop a plan to implement the solutions selected in the Improve phase and also

conduct the control charts to monitor the process (McCarty, Daniels, Bremer and

Gupta, 2005, p. 472). Yet, the project does not finish up at the Control phases.

Instead the team still needs to look out for any continuous process improvement

opportunities.

However, it is understandable that the Six Sigma management approach is

valuable for any size organizations which in implementing this process to avoid

rework, scrap and defect product which usually waste time and money. Furthermore,

the Six Sigma management approach increases the profitability and productivity

under a standard process monitoring.

Background of Cooper Standard at Mt. Sterling, Kentucky

Cooper Standard Automotive, Fluid Division, in Mt. Sterling produces rubber

hose and hose assemblies for the automobile manufacturing market in the United

20

Page 29: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

States, and the facility has been operating since 1996. They originally intended to

only employ 400 people but today they employ over 575 people and are considered to

be a high quality performance organization, yet they still strive to improve quality.

The manufactured rubber hoses are assembled and provided to customers such as

Ford, Chrysler and Nissan, and they frequently add new customers. With their

customer services, Cooper Standard always focuses on the customers' desires and

needs.

Review of Radiator Hoses

The upper and lower radiator hoses are all flexible connections between the

engine and radiator as shown in Figure 7.

Lower Hose

Thermostat

Transmission cooling lines

Figure 7. Diagram of a Cooling System (Adapted from HowStuffWorks.com, 2005)

Because of engine vibration, flexible connections are mandatory between these areas.

Also these hoses must be able to withstand the extreme heat environment under the

hood of a vehicle as well as up to 20 pounds of internal pressure (Century

21

Page 30: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Performance Center, 2005). Because of the wide temperature range of the coolant,

they must also be compatible with below zero to over 250° F temperatures without

failing (Century Performance Center, 2005). Rubber radiator hoses are typically made

ofEPDM (ethylene-propylene diolefin monomer). As shown in figure 8, there are

three layers consisting of a rubber radiator hose: the tube, reinforcement, and cover.

Reinforcement Tube

Figure 8. Three Layers of a Rubber Radiator Hose

As the innermost layer, the "tube" has two functions: to contain the fluid

being conveyed and to resist being broken down by that fluid (rlhudson.com, 2005).

If the fluid to be contained undergoes any sudden increases in pressure, the tube may

need to be reinforced by fabric or wire (rlhudson.com, 2005). This "reinforcement" is

the second layer of most rubber hoses. Reinforcement helps protect the tube from

internal pressure and outside forces. Reinforcing fabric or wire is applied by braiding,

knitting, spiraling, wrapping, or weaving. The third (and outermost) layer is the

"cover." The cover further protects the tube from external damage and environmental

deterioration (rlhudson.com, 2005).

22

Page 31: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Production Line Processes at Cooper Standard

The entire process of producing rubber hoses flows through several process

stations. The first process begins with the raw rubber material that is transformed into

formed rubber hose that Cooper defines as Extrusion Line. Once the raw material has

been received from the suppliers, the operator feeds it into the extrusion machines on

the Extrusion Line Stations. The extruded tube hose is formed to meet the I.D.

specification which is controlled by tube (pin and die) tooling selection. In the next

step, the fabric yam is applied on the surface of the tube depending on the different

number of packages and angle settings; the purpose for applying the· yam is to

reinforce the strength of the hoses. Next, the tube continues to feed into a second

extrusion machine to form the cover and meet its O.D. specification which is

controlled by cover (pin and die) tooling selection. The hoses are then_inkjet printed

with a customer's logo and part identified number after they passed through a laser

inkjet head. Finally, the hoses were cut off with a specific length by a blade cutter.

The hoses samples then are randomly selected to inspect on Inner diameter (I.D. ),

Outer diameter (O.D.), Wall Thickness Average and Wall Thickness Variation by a

non-contact laser measuring machine (QC-20, see Appendix A for instrument

description) to obtain the measurements.

The cut off hoses are then sent to forming stations to be steam cured with

different shape hoses based on customer functional and dimensional design. The

operators at forming stations take the perform hoses and loads them onto the shaped

mandrel bars and puts it into an autoclave with three hundred twenty five (3 25)

23

Page 32: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

degree heat for twenty five (25) minutes. After the forming process, the hoses are

then washed with mixed soap and water. After being washed, the hoses are air dry

and sent to the assembling line. The assembling lines they are sent to depend on their

functional purposes. A similar rubber radiator hose production process is shown in

Figure 9.

• lt.. p,0< .. , ..,, wlth dot •llffllsloftof •,wbof Nbt •.

"

.. .,.

I

• Theho,. ,,,._, cvcin10'""91l>• •. .,

0 •. ~hltHt """'UV,.,. N•

... n.1.-.. ,-.. ~-li•nli .•.

0

., lo,11M"'cwwiilu,._Low ... tot..• .. thtdllph ... .,

• • Cur ........... ,_. N.w,d lri--4 l>efon"'"' ,._,.,.,.,~., ... "°"41fo,,hi~

0 CD

Figure 9. Formed Rubber Hoses (Adapted from RL Hudson & Company)

It is notable that every single detail of the production process could have a

critical effect on the radiator hoses failing. Possibilities include a wrong yarn and

pattern or over high limit/ under low limit of O.D/1.D. specifications. Here, the causes

24

Page 33: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

of errors in the process and the results of potential defects ·need to be comprehended

while manufacturing a reliable and high quality performance radiator hose.

The error of wrong yarn and pattern in the process are usually caused by:

a) Wrong thread pattern

b) Wrong bushing

c) Incorrect pitch setting on continuous lines

d) Incorrect yarn type used

Potential Defects Resulting:

a) Burst failure from too little yarn

b) Installation efforts too great from too much yarn

c) Wrong yarn will not meet heat requirements

d) Wrong yarn will be chemically deteriorated by incompatible rubber,

causing hoses failure

The error ofO.D/I.D. over high limit/under low limit in the process usually

cause by:

a) Inaccurate measurement by operator

b) Improper or no pin placed in I.D. to measure O.D.

c) I.D. of extrusion larger than measure over pin causing thin wall and O.D.

ULL with potential ofl.D. OHL on the finished part

d) Extreme stretch on hose causing excessive shrinkage and resulting in

incorrect dimensional results

e) Starving of extruder causing uneven rubber flow

25

Page 34: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

26

Potential Defects Resulting:

a) Installation effort increase

b) Inability to crimp hose

c) Potential burst failures

d) Age failures on long term performance of hose

Page 35: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Chapter-ill

METHODOLOGY

Restatement of Research Objectives:

The areas of consideration were determined based on the strategic

development and mathematical aspects studied in implementing the DFSS on Toyota

spiral radiator hoses. However, the research objectives conducted and addressed in

this research are guided by the general concerns listed below:

I. Develop the DFSS and implement it on Toyota 180L Spiral Radiator Hose at

Cooper Standard Automotive in Mt. Sterling, Kentucky.

2. Conduct Design of Experiment (DOE) and Response Surface Design (RSD) to

develop and complete the valid construction for manufacturing spiral radiator

hoses in meeting its I.D., Wall Thickness, Wall Thickness Variation,

Functional and Aesthetics requirements.

3. Conduct process capability validation experiments for 33mm and 37mm spiral

radiators hoses.

Methodology for Research Objective One:

In this DFSS development for Toyota spiral radiator hoses, all the strategies

are implemented by following the DFSS model created by Uniworld Consulting Inc.

In their "Concept Engineering Tool Illustration", the process begins with "Value

Chain" and end with ''Process FMEA''. The process toolkit consists in DFSS

management are listed below:

27

Page 36: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

• Value Chain

• Customer Matrix

• Discussion Guide and Interview

• ImageKJ

• Voice Reduction

• Translations

• Requirements KJ

• KANO Diagram

• Functional Requirements

• Quality Function Deployment (QFD)

• PUGH

• Critical Parameter Map

• Design FMEA

• Process Map

• Process FMEA

"Value Chain" is the earliest stage in the DFSS management. It is utilized to

focus on external and internal customers' identification that are associated with the

project and primary is to understand the customers' needs and identify cost on time,

effort, space, and money. The steps to a Value Chain Map are listed below:

• Give the Value Chain a Name

28

Page 37: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

• For one Market Segment, Identify the Output or Products, End Users, and End

. User Expected Benefits.

• Identify Company and Market or Product Segments

• Identify Suppliers and their Inputs

• Identify customers between Cooper's suppliers and project's end user.

• Identify benefits and costs for each entity

• Identify Suppliers of Similar Products to Customers

• Identify Influencers and their expected benefits

• Within each of the Companies/Organizations list the names of all the

Functions/Customers who experience benefits or costs related to the

product/service offering

• List any of the potential ways for the project to increase benefits or decrease

cost that will increase the value of your offering.

The session result of the defining "Value Chain" is presented in Appendix B 1.

"Customer Matrix" is a stage to identify who are the customers (Internal and

External) that the project team must visit in order to gather the information related to

the product. In this stage, the abstract segment is to distinguish who are the relevant

customers for the current/potential product/process or service area that Cooper is

exploring and what are the different types of consumer, collaborator and influencer.

The session result of defining the "Customer Matrix" is presented in Appendix B2.

29

Page 38: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

"Discussion Guide and Interview'' is a stage that uses the interview method to

gather the information from customers. The customers are defined as well in the

second stage, "Customer Matrix" development, which included internal and external

aspects of the customers. A questionnaire was conducted to obtain information

regarding observations on the radiator hoses made by the manufacturing operator,

supplier, end user etc. The feedback on the questionnaire told us what the customer's

perspectives on the product are. In decoding these valuable feedbacks it leads the

project team to identify the factors that influence the product and the production

process which must be taken into consideration during project development. A

sample of the "Discussion Guide and Interview" is presented in Appendix B3.

The "Image and Voice KJ'' method, named after the Japanese anthropologist

Jiro Kawakita, is used to process the Voice of Customer (VOC) data into rational

groups based on common themes. It employs higher levels of categorizing the many

details of expressed or observed/imaged need (Antis, D., Creveling, C. & Slutsky, J.,

2003, p. 122). Here, the team used the KJ method to investigate the definition of a

quality radiator hose in the customers' eyes. Based on the customers' feedback, the

team members wrote down the images of a quality radiator on the note and post them

on the wall. Then the draft image notes were grouped into different categories by

similarity on a process called the "red level process". The "blue level process" is the

next step in ranking the importance of categories for 1st, 2nd and 3rd place. The

session result of the "Image and Voice KJ'' is summarized in Appendix B4.

30

Page 39: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

"Quality Function Deployment (QFD)" and the resulting "House of Quality"

chart is a method that is used to balance the conflicting requirements. Multifunctional

trams are used in the development, and the resulting matrix can serve as an important

communications tool. The Customer's Critical Criteria were listed by the project team

at Cooper Standard Automotive and taken to the customer Toyota Automobile who

ranked the importance. Engineering requirements that are needed to meet the voice of

the customer are complied. The relationships between customer requirements and the

"engineering know-how" are shown in a relationship matrix (Adams, W. C., Gupta P.,

and Wilson E. C., 2003 p. 221). The session result of the creating "House of Quality"

chart is presented in Appendix BS.

The "PUGE" method is a structured concept selection process used by

multidisciplinary teams to converge on superio~ concepts. The process uses a matrix

consisting of criteria based on the voice of the customer and its relationship to

specific, candidate design concepts (Antis, D., Creveling, C. & Slutsky, J., 2003, p ..

744). The session result of the "PUGE" concept selection is presented in Appendix

B6.

As the project went through those key tools of the DFSS development, The

DFSS team discussed and determined that a Design of Experiment (DOE) was

required to determine contrasts and comparisons of comparable concepts to decide

which was more effective for manufacturing Toyota Spiral Radiator Hoses.

31

Page 40: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Methodology for Research Objective Two:

Research objective two was focusing on the strategy of using Design of

Experiment (DOE) and Response Surface Design (RSD) to improve the production

process and product qualification. As has been mentioned in the literature review

section of this research, the DOE and RSD experimental methodologies are powerful

key tools in the improvement phase of the Design for Six Sigma to improve

manufacturing process and quality. As well as its efficient performance, the project

team decided to conduct DOE and RSD to optimize the reduction of the detective

products and proving the production ability to customer.

Design of Experiment (DOE) for Insertion Force:

The DOE technique was utilized to capture the factors that have a significant

effect on the amount of force needed to insert the hose onto the joint fitting. In this

DOE trial, the factors and levels were determined based on the session result of

"PUGE Concept Selection" and it was attempting to achieve the target of the

insertion force of fifteen (15) lb according to Toyota's requirements. The experiment

result was also compared with benchmark target Toyoda Gosei (TG) hoses. The

seven factors (Rubber Hardness, Yam Angle, Pre-form Interference, Yam Packages,

Tube/Cover Split, Yarn Denier and Hose Cleanness) with two levels (High & Low)

are listed in the table 2. The value settings oflevels were informed according to the

radiator hoses compound studies done by the laboratory department at the Cooper

Standard facility.

32

Page 41: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Table 2

Insertion DOE Factors and Levels Setting

Factors Level-I (Low) Level-2 (High)

Rubber Hardness 60 70

Yam Angel 49° 59°

Pre-fonn Interference 0.01" 0.1"

Yam Packages 16 24

Tube/Cover Split 40/60 60/40

Yam Denier Cooper (I 680) TG(840)

Hose Cleanliness Dirty Clean

Insertion DOE Design Procedures by Minitab 14:

I . First is to pull down the menu options from the top of the menu bar then

following by >Stat >DOE>Factorial > Create Factorial Design as shown in

Figurel0

33

Page 42: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

~l'I IAH Untlrlf"11 - ~~ - -

-- 7/13!.

Vele.-.. to llln1 U ""'1d0wts ' ~Ma:,e O)Jlay Took > 1f11,n

•1 '0 .,-F-Oolit,> .. , T

• Pi

~ • l~ ~

1 r

Tlle1,,ltos

1-~

f!o,owandS..,.Slm.

4 C, CZ O D O CS Cl Cl C9 C1I a, Ct2

Figure 10. Minitab Manipulation for Generating Insertion DOE Trial

2. Select 2-level factorial (default generators) when a design dialog-box pops up

and then and select the number of factors to "7'' since there are seven (7) factors

has been selected and decided by the project team.

3. Select "Design" option from "Create Factorial Design" dialog-Box then selects

the"½ factorial 64" due to the time and cost concerning. Next, click "OK" when

done.

4. Select ' 'Factors" option from "Create Factorial Design" djalog-Box then type

in the factors with their Levels values. Click "OK" to return page.

5. Click "OK" in "Create Factorial Design" dialog-box when finishing the setting.

The created insertion DOE trial runs in a worksheet indicated a total of sixty

four (64) samples were needed and the individual insertion force measurements were

recorded as in Appendix C.

34

Page 43: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

1st Response Surface Design (RSD) for Improving Bulges Problems:

In the findings of the "Insertion Force DOE" experiment, the team observed

that a majority of the hoses had Bulges problems at the bend area of the hose. The

team obtained information regarding priority factors that possibly caused this problem

to be happened. It was concluded that the overall Cut Length has the most significant

effect on the causes which it was not considered into the effective factors in the DOE

study. In addition, the "Pre-form Interference" value in manufacturing hose's I.D.

was another factor that the team assumed could affect the Bulges problems. During

the rubber curing process, the rubber will expand because the heat force from the

mandrel and once the hose cools it will shrink back to mandrel; this can cause the

hose to bulge in places. Due to this rubber characteristic, the project team conducted

this experiment to improve the hose's aesthetic aspect by eliminating the Bulges

problems using different "Pre-form Interference."

The factors and levels were determined based on the solution of Bulges issues

discussion and the standard finished length of the hoses 29.125" with a± 0.25"

tolerance was obtained from Toyota. Two factors (Cut length & Interference) with

two levels (High & Low) are decided and listed in the table 3 for this experiment.

35

Page 44: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Table 3

Jst RSD Factors and levels Setting

Factors Level-1 (Low) Level-2 (High)

Pre-fonn Cut Length 28 7/8" 29 3/8"

Pre-form Interference 0.015" 0.035"

1st

(RSD) Design Procedures by Minitabl4:

1. First is to pull down the menu options from the top of the menu bar then move

the pointer following by >Stat >DOE>Response Surface> Cl ick Create Response

Surface Factorial Design as shown in Figure I 1

'1l~IT AB Unhlled

J Efle~DAt4~:ibt!ir.-i£i,orI901s~~ - - - -- -

IS liil a l!MIC !otl5tla • ~ t •

Ptetroa Int:etfere Pretroa Ini:ei:rue

Effects Plot for Ir

Effects Pareto ro

• 1101'! • There 1~

I RHldull Plots fo

◄ I I

B.eqe.ssD'I .._ _______________ _

{ontrol Owts

~Tads

Retel,ayf.uvjval

~«In

Tino Serles

rates !P1JS51111bics

fadmal ► I ·- · • f'l&b,n • 1 •. !l.efine Cu!tnm Response Sllface Omlgn •••

• Iacp:hi • • ~ OptiMI Oesli,l .•. ► lo --

- ~lle591... &ll(yz,eResponseSllfaceOesli,l •••

► ~ !l_,spay ~ ... • __,__.._._ __ _. .... rn'. Cb/:IDIJ'/'nfa Plots ...

~ Qwtlald Cam, Pb; ••.

IP"

f:owa"nlSall'cileSize ►

~~~---

Figure 11 . Minitab Manipulation for Generating 1st RSD Trial

36

Page 45: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

2. Choose "Central composite" when a design dialog-box pops up and then and

select the number of factors to "2" since there are two (2) factors has been

selected and decided by the project team.

3. Select "Design" option from "Create Response Surface Design" dialog-Box

then chooses the "Full with Runs 13" and change the "Number ofreplicates" to

"2". Choose "Face Centered" for "Value of Alpha" then click "OK" when done.

4. Select "Factors" option from "Create Response Surface Design" dialog-Box

then type in the factors with their levels' values. Click "OK" to return page.

5. Click "OK" in "Create Response Surface Design" dialog-box when finishing

the setting.

The creation ofRSD trial runs in a worksheet indicated a total of twenty six

(26) samples were needed and the individual measur~ments were recorded as in

AppendixD

2nd Response Surface Design <RSD) for Improving Bulges & Non-Fills Issues:

In the result of the 1st Response Surface Design experiment, the team has

concluded that the contour plot has unknown curvature areas to the left side which

means the factor "Pre-form Interference" value settings in the first model did not

cover the desired ranges in gathering enough data for drawing a valid conclusion,

therefore, this experiment was conducted to supplement the 1st Response Surface

Design model. Furthermore, "Non-Fills" issue was another unacceptable problem.

Since the team was concerned with a high percent of rejection possibility from the

37

Page 46: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

customer. The study of Non-Fills was included in this experiment due to this critical

rejection issue. The factors and levels were determined based on the adjustment of

first Response Surface levels setting in discovering the unknown curvature areas. The

adjusted two factors (Cut length & Pre-form Interference) with two levels (Low &

High) are listed in the table 4.

Table4

2nd RSD Factors and Levels Setting

Factors Level-I (Low) Level-2 (High)

Pre-form Cut Length 29 1/8" 301/8"

Pre-form Interference 0.005" 0.030"

2nd (RSD) Design Procedures by Minitabl4:

I. First is to pull down the menu options from the top of the menu bar then move

the pointer following by >Stat >DOE>Response Surface> Click Create Response

Surface Factorial Design as shown in Figurel2

38

Page 47: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

fJe ~dl Otta t_ac :ital !i~ ElJor !ods ~ ~

~ g st y. ~ ~ statistics • " • (S) , ~ ~ - ©~ ii ti li'l a e1m ~ 1-------------------

T8Dl lnqle"T8Dl f 49 16 59 16 Qrirolehw 49 24 ~Toms 59 24

T8Dl Angle'Tube/C RefdyJSl,rmal 49 40/ 60 ~wta 59 40/ 60 49 60/ 40 Tne~

59 60/ 40 !alies Tam lnqle"Tam t

fi:q>arametrits 49 Cooper S9 Cooper fDA

I ...... I ~e I · • Qen'e Cu!11:m Re5p(n,e Soo!ICII DesrJi ...

!~ I • :ieled()pJnaiOesr,Ji ...

I lo liiil _ l!Plfy Oesr,Ji... l!fl ~ Re5p<n,e Slrlace De51g, ...

I~ ~De5ig, ... 11-------' ~ u,pu,oofacel'bts ...

.79 I . 97

0. 6403 1.1273

~ Qfflal Ccrim Pd ...

i.:~O!tml!l!r.,,

Figure 12. Minitab Manipulation for Generating 2nd RSD Trial

2. Choose "Central composite" when a design dialog-box pops up and then and

select the number of factors to 2 since there are two (2) factors has been selected

and decided by the project team

3. Select "Design" option from "Create Response Surface Design" dialog-Box

then chooses the default setting "Full with 14 Runs" and enter "2" for the

''Number ofreplicates." Choose "Face Centered" for "Value of Alpha" then click

"OK" when done.

4. Select "Factors" option from "Create Response Surface Design" dialog-Box

then type in the factors with their Levels' values. Click "OK" to return.

5. Click "OK" in "Create Response Surface Design" dialog-box when finishing

setting.

The RSD trial runs that were created in a work.sheet indicated a total of twenty

eight (28) samples were needed and the individual measurements were recorded in

Appendix E .

39

Page 48: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Methodology for Research Objective Three:

The study of process capability (Cp and Cpk) was the goal of the measuring

stage in this objective. It was to confirm the factors' value settings found in the

objective two could ensure the hose's I.D., Wall Thickness and Wall Thickness

Variation be manufactured at Six Sigma measurement standard levels. In doing so, it

was decided to run a total forty eight (48) samples trail on Toyota 33mm radiator

hoses with the Pre-form Interference 0.018". The three different populations of the

Pre-form Cut Length are: Maxima: 29.375", Nominal: 29.25" and Minima: 29.125", a

sixteen (16) sample size is consisted in each population to complete the trial. In

addition, the team also conducted a total of thirty six samples trial with the same Pre­

form Interference 0.018"on Toyota 37mm radiator hoses. The three different

populations of Cut Lengths are: 29.1875", 29.25" and 29.3125" and a twelve (12)

sample size is consisted in each population to examine whether the result of this trial

could also achieve Six Sigma measurement standard levels.

40

Page 49: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

CHAPTERN

Data Analysis and Discussion

The intention of this paper is to develop the Design of Six Sigma strategies

and complete the validation on constructing Toyota 180L 33mm and 37mm spiral

radiators hoses. The measurement data that needed to be analyzed were the

experiments conducted for research objective two and three for observational study

and decision making perspectives.

The trail samples were manufactured from the extrusion production line and

then shaped at forming production pools. The individual measurements of the

insertion force were taken from the samples that were tested on the tensometer

machine. The recorded data consisting of the hoses' I.D., Wall Thickness and Wall

Thickness Variation were gathered from the samples scanned on the quality

inspection machine (QC-20) and then entered into Minitab software to analyze the

trial results by generating statistical and graphical results.

Research Objective Two Data Analysis and Discussion

The statistical analysis of a Design of Experiment (DOE) trial and two

Response Surface Design (RSD) tria\s were completed in this objective to determine

a valid construction for manufacturing Toyota 180L 33mm spiral radiators hoses.

Insertion DOE Data Analysis and Discussion:

The recorded data of the Insertion Force was entered into Minitab software by

following procedures for analyzing the trial result:

41

Page 50: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

1. First is to pull down the menu options from the top of the menu bar then

follows by >Stat >DOE>Factorial > Analyze Factorial Design

2. Select "Insertion" to be the responses when an "Analyze Factorial Design"

dialog-box pops up and click "OK" to end up the dialog.

3. The data analysis graphs were presented as Figure 13 and 14:

Normal Probability Plotafthe Standardized Effects (response is Insertion-A, Alpha = .05)

99,----,----------r----- -----,

95

90

-.i

70 1!! 60

~ SI t. «>

30

20

1.0

5

■B

■ B

■F

1. ........ --~-'--- ~--.....---'----,.---..-' -5.0 ~ 5 ~0 ~ 5 ~0 7.5

SUndardized Effect

EffectType

• Not Significant

■ Significant

FaclDr Name A Rubber Hardness B Yam Angle C Prwrom I nteden,na, D Yam Packages E Tube,ICovorSplt F Yam Denier G Hose C leanill!"'

Figure 13. Normal Probability Plot of the Standardized Effects on Insertion Force

42

Page 51: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

8D

~ 85 at AD AF A

8G DG

~ 8~~ ~ A~

ACE CE BE G

xh CG ,CD DE AG

ACG

. . . .

'

t=t ~

~ ,_

t? ' 0 1

ParelD Chart of the Standardized Effects (response is Insertion-A, Alpha = .OS)

2080

T

' '

'

7 7 . . 2 3 4 5 6

Standard"ized Effect

' Factor Name A Rubber Hardness a Yam Angle C Prefrom Interference D Yam Packages E Tube/Cover Split F Yam Denier G Hose Cleaniness

. 7 8

Figure 14. Pareto Chart of the Standardized Effects on Insertion Force

Insertion DOE Data Analysis:

The red square dots in the ''Normal Probability of the Standardized Effects"

graph demonstrated the most significant effective factors; however, the factors term E

(Tube/Cover Split) & G (Hose Cleanliness) should be removed from the model in

order to observe the remaining effective factors since they both did not appear in the

plot and their pavalues were greater than significant p-value 0.05 (see Appendix C2

for calculated p-values). The updated graphs were presented in Figure 15 and 16 after

insignificant factors were removed. The Pareto Chart pointed out the most significant

factors is on the right side of the red line.

43

Page 52: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

9!1

95

90

80

70

~ 60 • u 511 .. l. 10

JO

20

10

5 ■F

-5.0

Nornal Probability Plot of the Standarclzed Effects (response is Insertion-A, Alpha= .OS)

■BF

■BC

■AF ■A ■ o

■c ■AO

-2.5 0.0 2.5 5.0 standardiad Effect

Effect Type • Not Sig nillcant

■ B ■ Slgnllcant

■BO Fac:tor Name A Rubber Hardness B Yam Angle C Pmrom I ntelfelenc,e 0 YamP~ges F Yam Denier

7.5

Figure 15. Updated ofNormal Probability Plot of the Standardized Effects on Insertion Force

B

BO F

BC

AF A

! D ~ II'

C

AO

AC

AB CF

CD ~ 0 1

Pareto Chart of the Standardized Effects (response is Insertion-A, Alpha = .05)

2.032

I Factor Name A RubberHa«h!ss

I B YamAngle

I I

C Prehomlnb!rference D Yam Plldage,; F Yam DrrRr

I I

I

I

2 3 4 5 6 7 8 Standarcmed Bfect

Figure 16. Updated Pareto Chart of the Standardized Effects on Insertion Force

44

Page 53: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Discussion of Insertion DOE:

1. The average insertion force was 34 .11 lbs in this experiment and the

individual measurements can be found in Appendix C.

2. By the Descriptive Statistical Analysis, R2 is the percentage of total variation

in the response that is explained by predictors or factors in the model. In

general, the higher the R2, the better the model fits the data. The calculated

value ofR2

in this experiment was 85.38% which implies the model fits the

data well. The value ofR2 can be found in Appendix C2.

3. The factor terms E (Tube/Cover Split) & G (Hose Cleanliness) were removed

from the model because they were insignificant effects on insertion force.

4. Adjusted R2 is useful for comparing models with different numbers of

pn,dictors or factors. By removing three insignificant terms, the interactions

R2

(adj) increased from 81.25% to 85.78% which accounts for the number of

predictors in the model by eliminating the insignificant factors and focus on

significant ones (see Appendix C2 and CJ for R2 (adj) values).

5 .. It was determined that the factors Yarn Angle, Yarn Packages and Yarn

Denier are significant due to their high percentage values of epsilon2 and the

calculated epsilon2 values are presented in Appendix C4. Therefore, a follow

up DOE needs to be conducted only using these three factors in order to study

their interaction on reduction of the insertion force.

6. The majority of hoses in this experiment had the Bulges condition occurred on

the bend area; a Response Surface Design (RSD) experiment was needed to

45

Page 54: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

discover the causes of potential phenomena and minimize the chance of the

Bulges issue occurred on the hoses.

1st

Response Surface Design (RSD) Data Analysis and Discussion:

The levels of the Bulges condition were classified via the visual observation

technique before analyzing this experiment result.

Bulges Ranking Technique:

The judging ranges of the Bulges condition were determined and classified

before to analyze the data; these ranges were assigned based on customer interviews

(VOC). The team determined the classification one (1 : No Bulges) & three (3 : Slight

Bulges) are the acceptable ranges to the customer and six (6: Bulges) & nine (9:

Serious Bulges) are the unacceptable ranges. The visual Bulges ranges are also

presented in Figures 17, 18, 19 and 20 with their classification.

Figure 17. Classification I= No Bulges Figure 18. Classification 3= Slight Bulges

46

Page 55: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Figure 19. Classification 6= Bulges

1st RSD Data Analysis by Minitab 14:

Figure 20. Classification 9= Serious Bulges

The recorded data of 1st RSD were entered into Minitab software by following

procedures for analyzing the trial result:

1. First is to pu.U down the menu options from the top of the menu bar then

move the pointer following by >Stat >DOE>Response Surface>

Counter/Surface Plots as shown in Figure 21

47

Page 56: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

)'-a ~ale I :[tat !i~ Egtor !ods ~ ~

j ~ ~ ftasic~ -,98276 1 ,98276 1 .48276 1 ,98276 1 ,20690 C . 20690 C ,20690 C .20690 C ,20690 C

I Plots to

&e9°esSIOf'I

Contrd Charts

Q.ualyTods

R8'dY/Sl-'Yival ~ariate ► ~

► 14236) A?~I:\

♦ Qeate Respcnse SLrf ace Desql ...

► Ile ~CustunRespinseSufcDesqi.,,

► • ~ OptiMI DesiO'I ...

► 1-Moify Desql,,' ~ ~Desigl .. , ~

I& ►~------~

line~

~ametrlcs ►] ~ ~C!Jtoo'Pklt ...

fJ)A ► ~ 8,e5'X)l'1Se Oitilizer "'

~ cnl Sanl)le Size ►

Figure 21 . Minitab Manipulation for Analyzing 1081 RSD Trial

2. Check the "Contour Plot" and click "Setup".

3. Choose ' 'Bulges" to be "Response" in the set up dialog-box and click "OK"

to return.

4. The data analysis contour plot was generated as Figure 22:

48

Page 57: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

(ontour Plot of Bulqes vs [ut length, lntcrfc,ence lll[iiJ EJ

.c E, C _gi .. :I t.1

Contot.r Plot of Bulges vs Cut length, Interference

29.3

29.2

29.1

29.0

28.9

0.015 0.020 0.025 Interference

0.03'.) 0.035

Figure 22. Contour Plot of 1st RSD Trial Result

5. Right click on the mouse to pull up secondly options.

Bulga < 2.0

■ 2.0 • 3.2 ■ 3.2 . 4.,4

■ 4.4 · 5.£ ■ 5.6 · 6.8 ■ > 6.8

6. Use ' 'Plant Flag" function to locate the specific values with the bottom-line

acceptable Bulges condition three (3) as shown in Figure 23

49

Page 58: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Conto..- Plot of Wges vs Cut length, Interference

29.3

29.2 .c

i .. a 29.1

.0 lntl!m!rence = 0.0Zl68B3 Cut length = '1filfm. Bulges = 3.lm53

0.015 0.020 0.025 Nerference

0.030 0.035

Bulges < 2.0

■ 2.0 • 3.2 ■ 3.2 · 4.4

■ "·" · 5.6 ■ 5.6 • 6.8 • > 6.8

Figure 23 . Contour Plot of 1st RSD Trial Result with Planted Flags

1st RSD Data Analysis:

This experiment was attempting to improve the hose aesthetic by minimizing

the chance of Bulges occurring on the hoses. This is possibly most affected by the

pre-form Interference and Cut length factors. In the graphics shown in Figure 23, the

tow flags were planted on the "contour plot" in order to determine the optimal value

settings for the factors based on the Bulges ranking classification number one (1) and

three (3) are acceptable from the customer. The upper left flags was planted due to the

Bulges classification did not exceed the acceptable limit three (3) and so was the

lower right flag. The two flags' readings pointed out the Cut Length should fall in the

range value between 28.8722" to 29.1018" with Pre-form Interference value between

0.0151" and 0.0236" to ensure the Bulges problems could be controlled in customer

acceptable levels.

50

Page 59: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Discussion of 1st (RSD) for Improving Bulges Issues:

1. The optimal range was in the lower left quadrant of the contour plot thereby a

second Response Surface Design was needed to discover the unknown

curvature in first RSD model.

2. The Non-Fills issues on the both ends of the radiator hoses were observed in

this experiment and that was definitely not acceptable in the customers' eyes.

The team assumed that the short of the cut length has a significant effect

causes this problem.

2nd Response Surface Design (RSD} Data Analysis and Discussion:

The recorded data of the 2nd RSD were entered into Minitab software by

following procedures for analyzing the trial result:

1. The first step is to pull down the menu options from the top of the menu bar

then move the pointer following by >Stat >DOE>Response Surface> Overlaid

Contour Plot as shown in Figure 24

51

Page 60: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Op ~ale :it& ~ai,i, Edtor Iools ~ !:!e1P

') llR Slatisti:s • II ~ ,j' I {I ~ ~ (D ~ ii '\l lfI 8 lffl II II ~~ ~

' Plot oft.

t Contou1

t Contou1

Refdy/S1nival

~«late

nne~ [ables

~

tDA

♦ ueate Re:spoose Si.face Desq, ...

~ ► •c ~Custon lle:spoose Sllface Oesql .. .

Iagucti ► fJ :ielect QJltlNI DesilJl. .. ~-- -------• 'o Iii) _ l!ldY Oesl!JI... ~ er,a1vze Re:spoose Sllf ace Oe5Ql ...

• , ~ ~Dmr,Ji... ---• .--------~ CD;j;Ollf.uface l'td:s ...

• s (mm) •

~and~Sze.

Figure 24. Minitab Manipulation for Analyzing 2nd RSD Trial

2. Choose "Bulges" and ''Non-Fills" to be responses and then click "Contours"

options.

3. Enter the factors value settings for responses and click "OK" to return.

4. The data analysis contour plot was generated as Figure25 and using the "Plant

Flag" option to locate the acceptable value settings for minimizing "Bulges" and

' 'Non-Fills" conditions.

52

Page 61: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

OlataidOmuActdlljgl!s, ~lls(rmt :n1 :n1 29.9"

29.8

fi 29] t JI 29.1 a

29:

~ =O.CXBm.' a.tli!!¢ =293'2 B,95=.ll4rn Norfls(rrnt = 1m3

,,,., .. --.... , .. , ' .... ~

~ =O.~ a.t 11!1¢ = 2!lllS1 B,95=2'm11 taffs (rrnt = U5II •

I l

~ = llOllfil'.X)

at 11!1¢ = 2!1.1137 B,95=1rmt l'b&(rrnt = l.3fiBl

\ '·

Q~ Q~ Q~ Q~ Q~ Q~ A1!fannltafaaD

B,95 - 1

··-- 3 Norfls (rrnt

- o ., ., 2

Figure 25. Contour Plot of 2nd RSD Trial Result with Planted Flags

2nd (RSD) Data Analysis:

The two contour areas were separated based on the Bulges classification

range. This means the white contour area contained acceptable hose with different

factors value settings. The three flags were planted on the overlaid contour plot for

determining desired factors value settings to optimize the hose aesthetic and reduce

the Non-Fills value. The bottom flag in the middle was planted to determine the

nominal interference and minimum cut length settings with acceptable Bulges

classification three (3) which it indicated the value 0.0185" pre-form interference

with the value 29.1287" cut length held hoses with a 1.34 Bulges classification and

1. 13mm Non-Fills. The flag on the left side was planted to decide the minimum

53

Page 62: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

interference and maximum cut length settings with acceptable Bulges classification

three (3) which it indicated the value 0.0084" pre-form interference with the value

29.3752" cut length held hoses with a 3.14 Bulges classification and 1.26mm Non­

Fill. The flag on the right side was planted to determine the maximum pre-form

interference and cut length settings with acceptable Bulges classification three (3)

nominal setting and it indicated the value 0.028" pre-form interference with the value

29.3751" cut length held the hoses with a 1.32 Bulges classification and 1.13mm

Non-Fills.

Discussion of 2nd (RSD) for Improving Bulges and Non-Fills Problems:

The final determination on hoses overall Cut length and Pre-form Interference

setting was based on this experiment result. The validated construction for

manufacturing 33mm radiator hoses should conform to these settings as summarized

in table 5 in order to prevent the Bulges and Non-Fills problems:

Table 5

33mm Construction Setting Determination of 2nd RSD Result

Construction Item Minima Nominal Maxima

Pre-form Interference 0.008" 0.018" 0.028"

Cut Length 29.375" 29.25" 29.125"

54

Page 63: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Research Objective Three Data Analysis and Discussion

The intention of this objective was to determine whether the Pre-form

Interference 0.018" is an adequate construction setting in producing radiator hoses tci

achieve at a six sigma measurement standard levels for both 33mm and 37mm. To

achieve the philosophy ofMotorola's Six Sigma, the measurement standard value of

Cp must be at least 2.0 and Cpk_must meet_ 1,5 rates. Furthermore, the conditions of

Bulges. and Non-Fills issues were evaluated by using the Pie-Chart to illustrate the

proportion of each data category relative to the Whoie data set ,

The trial individual measurements of the hoses' I.D., Wall Thicknesses and

Wall Thickness Variations were entered into Minitab to analyze the trial data for

process capability based on the dimensional specifications. The dimensional

specifications of33mm and 37mm are listed in table 6 as for Cp and Cpk calculation

reference values, and trial individual measurements can be found in Appendix F and

G.

Table 6

Radiator Hoses Specifications

Radiator Hoses I.D.

33mm 33±0.5mm

37mm 37±0.5mm

Wall Thickness Wall Thickness Variation

4.5 ± 0.5mm 0-0.8mm

5 ± 0.5mm 0-0.44mm

55

Page 64: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

The process capability of the 33mm I.D. is shown graphically in Figure 26. It

indicated the response appears to be normally distributed and the average of the

samples was 32.8992mm with a standard deviation 0.0614756mm. The value ofCp=

2.97 and Cpk= 2.37 both passed the Six Sigma measurement standard levels and there

were no out-of - spec values for every million opportunities found in the result.

Process capability d 33nm LD.

LSL Tar-Qd USL Process Data

,-- Within lSL 32.5

" - - Over.ii Taroet 33 t' USL 33.5 Poll!ntlal {Within) Capability

Sample Mean 32.8992 Cp 2.'ifl

Sample N 47 CPL 2.37

StOev(v.thln) 0.05(,0985 CPU 3.57

StDev(Overall) 0.0614765 Cpk 2.37 CCpk 2.'ifl

Overal Capabllty

Pp 2.71 PPL 2.16 PPU 3.26 Ppk 2.16 Cpm 1.'10

I ' \. I

32.55 32.70 32.85 33.00 33.15 33.30 33.45

Observed Penonnance Exp. Wllhi1 Perfamance EllP, OveraN Perfamance PPM < lSL 0.00 PPM < lSL 0.00 PPM < LSL 0.00 PPM > USL 0.00 PPM > USL 0.00 PPM > USL 0.00 PPM Total 0.00 PPM Total 0.00 PPM Total 0.00

Figure 26. Process Capability Analysis of 33mm I.D.

The process capability of the 33mm Wall Thickness is shown graphically in

Figure 27. It indicated the response appears to be normally distributed and the

average of the samples was 4.47926mm with a standard deviation 0.022798mm. The

value of Cp= 7.7 and Cpk= 7.38 both passed the Six Sigma measurement standard

56

Page 65: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

levels and there were no out-of - spec values for every million opportunities found in

the result.

Process capability m 33nm wan Thickness

Process Data ISL 4 Target 4.5 USL 5 Sample Mean 4.47926 Sample N 47 StDev (Within) 0.0216366 StDev (Overall) 0.022798

0 bselv ed Performance PPM < ISL 0.00 PPM > USL 0.00 PPM Taal 0.00

LSL Tar

4.06 4.20 4.34 4.48 4.62 4.76 4.90

Exp. 'Mthil Performance Exp. Overall Perfonnance PPM < ISL 0.00 PPM < ISL 0.00 PPM > USL 0.00 PPM > USL 0.00 PPM Tooil 0.00 PPM Tooil 0.00

USL ,-1 :::::::::-w-ith-in­- - Overall

Potential (Within) Capability Cp 7.70 CPL 7.38 CPU 8.02

Cplc 7.38 cc pie 7.70

Overall Capablity

Pp 7.31 PPL 7.01 PPU 7.61 Pplc 7.01 Cpm 5.40

Figure 27. Process Capability Analysis of33mmWalJ Thickness

The process capability of the 33mm Wall Thickness Variation is shown

graphically in Figure 28. It indicated the response appears to be normally distributed

and the average of the samples was 0.260161mm with a standard deviation

0.0612175mm. The value ofCp= 2.26 and Cpk= 1.47 both passed the Six Sigma

measurement standard levels. However, there were 10.7 out-of-low specification

values for every mill ion opportunities found in the result which is not a critical issue

since it is impossible to have the value beyond 0mm.

57

Page 66: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Process capability of 33mm Wall Thickness Variation

-------~ LSL Pnx:esas Data lSL 0 I Target • I USl 0.8

I Sample Mean 0.260161

USL

'

-- Within

- - Overall

P\'.ltential (Within) Capability

Cp 2.26

Sample N 47 I CPL 1.47

StC>e-.<Wrthin) 0.0500356 I ~ StOell(Overall) 0.0612175

I I

' I I

CPU 3.05 Cpk 1.47 CCpk 2.26

Overall Capability

Pp 2.18

PPl 1.42 PPU 2.94

I Ppk 1.42

I Cpm

I

j ~J

I ~'-I ~ I

I Obsetved l'l!rfomuince Exp. Within l'l!rfonnance Exp. Overall l'l!rformance 0.72

PPM< LSL 0.00 PPM< LSL 5.24 PPM< LSL 10.70 PPM> USl 0.00 PPM> USl 0.00 PPM> USl 0.00 PPM Total 0.00 PPM Totai 5.24 PPM Total 10.70

Figure 28. Process Capability Analysis of 33m.mWall Thickness Variation

The conditions of 33mm Bulges and Non-Fills issues were clearly illustrated

in Figure 29. It was observed that the Bulges condition was minimized with the Cut

Length 29.12511 since no serious Bulges (classification: 9) appeared, and in 46.7% of

No Bulges (classification: I) occurred; besides the Non-Fills existed in these three

different Cut Lengths, especially the shorter Cut Length created a larger Non-Fills

value.

58

Page 67: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Pie Chart of Bulges, Non-fills

Non-fills, Cut Leng ht 29 3/8

Panel variable: Cut Length

Bulges, C If Length 29 1/4

63'lo "63¥.

1 50.0%

Category

I If> !h ip

■ 3 OipB~

■ 6 ~ 1 □ 9 IDwB.Jp

.7% -----

Category lCo-U DIIII)

■ JlO J-lllllll)

■ 6PA.JDIIII)

□ g(>lJ-.j

Figure 29. Multi Pie-Charts of33mm Bulges & Non-Fills Conditions

The process capability of the 37mm I.D. is shown graphically in Figure 30. It

indicated the response appears to be normally distributed and the average of the

samples was 36.6169mm with a standard deviation 0.051291mm. The value of Cp=

3.2 passed the Six Sigma measurement standard levels but Cpk= 0.75 did not due to

the size of the mandrel was manufactured with the old measurement technique;

therefore, the out-of-spec values for every million opportunities found in the result

was due to this matter.

59

Page 68: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Process C,apability cl 37nmLD.

LSL Taract USl Precess Data I 1- Wilhin

lSL 36.5 I -- Overall

Target 37 USL 37.5 I Polenlial (Wthln) Capabllky

Sample Mean 36.6169 I Cp 3.20

Sample N 36 I CPL 0.75

SIOev(V-,tilln) 0.0520481 CPU 5.66

StDev (Overall) 0.051291 I Cpk 0.75

I CCpk 3.20

I Overal Capabllty

I Pp 3.25

I PPL 0.76 PPU 5.74

I Ppk 0.76

I Cpm 0.43

' \ I I

36.60 36,75 36.90 37.05 37.20 37.35 37.50

Obsetv ed Petformanoe E.llp. Wttlil Performance E.llp. Overan Perfonnanoe

PPM < lSL 0.00 PPM < lSL 12338.39 PPM < lSL 11316.20

PPM > USL 0.00 PPM > USL 0.00 PPM > USL 0.00 PPMTOllll 0.00 PPM TOllll 12338.39 PPM Tmal 11316.20

Figure 30. Process Capability Analysis of 37mm I.D.

The process capability of the 37mm Wall Thickness is shown graphically in

Figure 31. It indicated the response appears to be normally distributed and the

average of the samples was 5.04881mm with a standard deviation 0.0173679mm. The

value of Cp= 10.12 and Cpk= 9.13 both passed the Six Sigma measurement standard

levels and there were no out-of-spec values for every million opportunities found in

the result.

60

Page 69: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Process capability of 37nm Wall Thickness

Process Data

LSL 4.5 Target 5 USL 5.5 Sample Mean 5.04881 Sample'il'I 36 StOev(Wlthln) 0.0164701 StOev(Overal) 0.0173679

Observed Perfonnance

PPM?<ilSL 0.00 PPM?>a!SL 0.00 PPM?fotal 0.00

LSL Target USL

4.48 4.62 4.76 4.90 5.04 5.18 5.32 5.46

EJ<P. Within Perfonnance EJ<P. Overall Perfonnance

PPM?<ilSL 0.00 PPM?<ilSL 0.00 PPM?> a!SL 0.00 PPM ?>a!SL 0.00 PPM?fotal 0.00 PPM?fotal 0.00

- Within I - - Overall

Potential (Within) CapabRlty

Cp 10.U CPL 11.11 CPU 9.13 Cpk 9.13 CCpk 10.12

Overall Capability

Pp 9.60 PPL 10.53 PPU 8.66 Ppk 8.66 Cpm 3.18

Figure 31. Process Capability Analysis of37mrnWall Thickness

The process capability of the 37mm Wall Thickness Variation is shown

graphically in Figure 32. It indicated the response appears to be normally distributed

and the average of the samples was 0.171591 mm with a standard deviation

0.0246245mm. The value of Cp= 2.86 and Cpk= 2.23 both passed the Six Sigma

measurement standard levels and there were no out-of- spec values for every million

opportunities found in the result.

61

Page 70: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Process capability of 37nm Wall Thickness Variation

Process Data ISL 0 Target • USL 0.44

Sample Mean 0.171591 Sample N 36 StOev (Within) 0.02.56702 StDev(Overal) 0.0246245

Observed Performance PPM < ISL 0.00 PPM > USL 0.00 PPM Total 0.00

LSL

I I I I I I I I I I I I I I ~ I I

-0.00 0.06 0.12

Exp. Within Perfonnance PPM < ISL 0.00 PPM > USL 0.00 PPM Total 0.00

USL I With' := Over:. Potential (Within) CapabiMty

Cp 2.86 CPL 2.23 CPU 3.49

Cpk 2.23 CC pk 2.86

Overal Capability

Pp 2.98

' PPL 2.32 PPU 3.63 Ppk 2.32 Cpm •

1'111,.. I . 0.18 0.24 0.30 0.36 0.42

Exp. Ov eraa Perfonnance PPM < ISL 0.00 PPM > USL 0.00 PPM Total 0.00

Figure 32. Process Capability Analysis of 37mmWall Thickness Variation

The conditions of 37mm Bulges and Non-Fills issues were clearly illustrated

in Figure 33. It was observed that the Bulges condition was minimized with the Cut

Length 29.25" since there was no serious Bulges (classification: 9) appeared and a

58.3% ofNo Bulges (classification: 1) occurred. However, the Non-Fills existed in

these three different Cut Lengths, especially the shorter Cut Length created a larger

Non-Fills value.

62

Page 71: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Pie Chart of 37nm Bulges & Non-fills Condition Analysis

Bulges, Cut Length 29 1/4

Panel variable: Cut Length

Bulges, Cut Length 29 5/ 16

I 11,B>lp

• 3 SliptB-.!p

1 ■ 6 Jl,rJit 1 L7% 0 9 Sa~B-.. 50.0%

Non-fills, Cut Length 29 3/16 Non-fils, Cut Length 29 5/ 16 9

16J% ,_--r.-,o.._

3 33.3%

Cat~ory 1 (9-8.ha)

■ J (O M -.)

■ 6C1•1J~ D 9<>1J~

Figure 33. Multi Pie-Charts of 37mm Bulges & Non-Fills Conditions

63

Page 72: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Chapter V

Conclusions

This chapter discusses the findings of research objectives and it gives possible

further study.

Research Objective One

The first research objective was to develop and implement the strategies of the

Design of Six Sigma to guide the project team for ensuring that the radiator hoses can

be manufactured to Toyota's expectations. In completing this project, the team leader

demonstrated outstanding leadership in leading the project team to concentrate on the

parameter of design aspects in order to accomplish this project.

The selected team members responded professionally in their supporting the

project being processed. Because of strong leadership, the project team members

followed this lead in fulfilling their responsibilities in achieving the project objectives

and making the right decision precisely in each of development phases.

The powerful key tools in the DFSS phases such as Value Chain, Customer

Interview, KJ method, QFD and PUGH assisted the team in investigating the critical

parameter setting for manufacturing a high quality with a low cost radiator hose. The

DOE and RSD were the methodologies that were utilized for analytical study to

improve and complete the design of the spiral radiator hoses. Finally, the process

capability study proved that the production of Cooper Standard Automotive is

capable to produce Toyota 1801,, spiral radiator hoses.

64

Page 73: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Research Objective Two

The second objective was to develop and complete the valid construction for

the 3 3 mm spiral radiator hoses in meeting the dimensional, functional and esthetics

requirements. As the result of the DOE trial, it indicated the average of the insertion

force 34.11 lb was higher than the benchmark (Toyoda Gosie) 22.731b and three

critical factors, Yam Angel, Yam Package and Yam Denier had the most significant

effects on insertion force. According to the analytical study of the DOE trial result,

the team decided the Yam Angle 54 degree was adapted from the middle value of the

trial factor range (Low:49°, High:59°). The Yam Package (24) was determined based

on the less yarn (Package12) could cause potential failure issues. The Yam Denier

840 was selected since it does not show the yarn pattern on the hose's appearance and

it assists in lowering the insertion force.

In the stage of eliminating the Bulges and Non-Fills conditions that occurred

in the Insertion DOE trial, the team assumed that two factors, Cut Length and Pre­

form Interference, have potential effect to the problems. The first RSD experiment

was set up to solve the problems but unexpectedly the value setting of the factor Pre­

form Interference was insufficient to discover the desire response. Hence, the second

RSD experiment was conducted to supplement the first RSD model and the trial

result provided an adequate value 0.018" of the Pre-form Interference that could

reduce the Bulges and Non-Fills conditions to a lowest probability. The completed

construction of the 33mm spiral radiator was validated according to these trial results

and the detail of the construction also can be found in Appendix H.

65

Page 74: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Research Objective Three

The third research objective sought to investigate and confirm whether the

Pre-form Interference 0.018" could ensure the production process performing at Six

Sigma measurement standard levels on 33mm and 37mm radiator hoses to meet the

requirements. However, the result of process capability validation experiments

proved that the production process was performing at Six Sigma measurement

standard levels on I.D., Wall Thickness and Wall Thickness Variation and these

results were summarized in table 7. Technically, the Cpk value of the 37mm I. D. was

obviously lower than Six Sigma measurement standard levels due to the size of the

shaped mandrels which were manufactured with less than the I.D. specification target.

Table 7

33 mm and 37 mm Radiator Hoses Process Capability Summary

33mm Radiator Hose Specification

Item Capability Value Process Capability Acceptance

I.D. Cp=2.97, Cpk.=2.37 Capable Acceptable

W. Thickness Cp=7.70, Cpk=7.38 Capable Acceptable

W. Variation Cp=2.26, Cpk=l.47 Capable Acceptable

Bulges Issue Capable Acceptable

Non-Fills Issue Incapable Unacceptable

66

Page 75: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

37mm Radiator Hose Specification Capability Value Process Capability Acceptance

I.D. Cp=3.2, Cpk=0.75 Capable Acceptable

W. Thickness Cp=l0.12, Cpk=9.13 Capable Acceptable

W. Variation Cp=2.86, Cpk=2.23 Capable Acceptable

Bulges Issue Capable Acceptable

Non-Fills Issue Incapable Unacceptable

The overall outcomes of numerous ~xperiments in this project indicated the

Bulges issues could be minimized by adjusting the Cut Length to be controlled on the

hoses. However, it then creates a Non-Fills condition that is severe and unacceptable

to customer. Because of this critical defect issue, the project team decided to extend

the length on both cap ends of the radiator hoses then apply a trimming process to cut

off excess martial and meeting the overall length specifications.

Implications

Given the findings of this research, it is important to examine the implications

of this study. The study has implications for future practice such as:

1. A study of potential burst failures for Toyota 180L 33mm and 37mm radiator

hoses is needed since dimensional variation could cause this occurred.

2. Control plans must be conducted before the regular mass production is

launched and the Six Sigma process capability study should be maintain

continuously to control the production variation.

67

Page 76: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

3. In the design of the radiator hoses, there is an extend length added on both

ends of the hose and it was determined that this was required to eliminate the

' 'Non-Fills" issue. Therefore, a Cap-End trim.ming process needs to be

designed to trim off the excess material as shown in Figure 34. In the function

of this operation design, instead of setting up six trimming process ceIJs for

different dimension radiator hoses, it needs only one operator to manipulate a

capable robot to trim and stamp the labels on both ends of radiator hoses in

one processing cell.

Figure 34. Cap-End Trimming Process Prototype

68

Page 77: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

References

Antis, D., Creveling, C. & Slutsky, J. (2003). Design for six sigma: In technology

and product development. New Jersey: Prentice Hall PTR.

Adams, W. C., GuptaP., and Wilson E. C. (2003). Six sigma deployment. M.A:

Butterworth-Heinemam.

Bhote, R. K. (2003). The ultimate six sigma: Beyond quality excellence to total

business excellence. New York: AMACOM.

Bremer, M., Daniels, L.,Gupta, P. and McMcarty, T. (2005). The six sigma black belt

handbook. New York: McGraw-Hill. · ·· r •

Besterfield, H. D., C., H. G., and M. (1999). Total quality management (2nd ed.). New

Jersey: Prentice Hall.

Folaron, J., & Morgan, J. (2003, August). The evolution of six sigma. p. 38-44.

Retrieved May 7, 2005

http://www.asq.org/pub/sixsigma/past/vol2_issue4/ssfmv2i4folaron.pdf

Harburg. F. (2004). Next-generation six sigma. Retrieved February 17, 2005

http//www.clomedia.com/content/anmviewer.asp

iSix Sigma. (2005). The history of six sigma. Retrieved March 4, 2005

http://www.isixsigma.com/library/content/c0208l5a.asp

Minitab Inc. (2004). Statistical software (Version 14.0) [Computer software].

State College, PA

69

Page 78: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

70

Appendix A

Description ofQC-20 Hose Instrument

Page 79: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

QC-20 Hose Instrumentation

The LOTIS Model QC-20 is a laser-based, non­contact hose measurement system. It simultaneously measures inside diameter, outside diameter, average wall thickness, and wall thickness variation. It is specifically designed to measure a hose's compliant surface where accurate and repeatable contact measurements are difficult to obtain. The QC-20 is designed for both in-process gaging and final parts inspection. Users can validate production processes by comparing actual measurements to user-defined measurement tolerances. Parts are automatically identified as passed or failed depending on measurement results. Part measurements are also accumulated in a database for statistical process control (SPC) requirements. The QC-20 comes complete with a PC compatible support computer and software. Standard hose sizes and measurement parameters are entered into the computer and stored. During operation, a hose part number is keyed in by the operator. The system automatically reconfigures itself to accurately position and measures that particular hose. Batch measurements require a single setup. A foot switch triggered by the operator initiates the measurement cycle.

71

Page 80: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

72

Appendix Bl

DFSS Session Result of Value Chain Map Development

Page 81: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

M r-

Suppliers: Auburn, IN

(Compound)

Beaver

(Yarn)

Input: Rubber Yam

Customer Needs: Quality Cost

Delivery

Value Cooper Cooper

Extrudes Forms Hose Hose Key Key Activities:

Activities: Plaoe hose onto

Extrude Tube mandrels

Cool Tube Plaoe ca~ on h06e

Apply Yam Cure hose In autoclave ApplyTactffier

Remove ca~ Extrude Cover Add Priri Code Pull hoses off of

mandrels Cool Hose Cut to Lel'Qlh Customer Customer Needs

Needs Hose that meets Correct Hose correct contour dimensions Host that meets

Consistent wa11 comet print Thickness dimensions

Part to correct length Volume:

Parts that have High straight out Ergonomics Margins:

Safety Medium Law cost

Volume: Benefits:

Quality High Cost

Margins: Medium

Benefits: Foot In

Japanese Markets

Meet customer expectations

Chain Map Outputs:

Cooper OEM Dealership Finishes Assem Sells End User:

Hose bles Vehicle Complete Automobile

Vehicle Key Compo Key Requirements: Activities nents Activities: Quality Stamp hose Sales Relia~llty

Place correct ¢f Key Service Cost in container Customer

Label container Actlvltl Needs: Conduct final es: lnspeotion Quality

Assembles Cost Customer hose to Service

Rad/ENG Needs Volume: High

Quality Custo Margins: Cos! mer Law

Delivery Needs: Benefits:

Volume: Quality Quality

Cost Price High

Delive,y Margins:

Medium Volume

Benefits: : High

Ccsls Margin QUIity s:

Medium

Benefit S:Cos! Quality

Page 82: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

74

AppendixB2

DFSS Session Result of Customer Matrix Development

Page 83: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

75

Customer Matrix

MATRIX Cooper Auburn Extnaion Forming Anlshlng Toyota

External SUppliers Auburn Lab

Extrusion Forming

~ and Finishing 0pera1Drs Internal Supplers &pefvlsor

Operators & & Supervisor

BG Engineering Supervisor

TMMI Opera1X>rs TMMIQuollty

External Customer TMMI Group Leaders

TMMI Warranty

Forming Finishing Operators Internal Customers 0peN1tors &

Supervisor & Supervisor

lnlluencers

Page 84: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

76

AppendixB3

DFSS Project Interview Questionnaire

Page 85: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

1) Describe some issues you have seen with hoses in the past.

2) Describe any current issues you have with the current hose?

3) Describe what you don't like about the current hose?

4) Describe what you do like about the current hose?

5) What would you like to see happen in the next generation of hoses?

6) Tell me what is most important about a hose to your job?

7) What is most critical to the hose?

8) What are some cosmetic concerns of the hose?

9) What expectations do you have of a new hose supplier?

10) In your experience what issues with hose have been the most troublesome?

11) Describe some durability' problems that have been documented concerning spiral radiator hoses?

12) What serviceability issues have been encountered with spiral hoses?

13) What characteristic of a hose is most important to you & why?

14) What one question did I not ask that I should have?

77

Page 86: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

78

AppendixB4

DFSS Session Result ofKJ Development

Page 87: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

KJ Summary

What are the most important requirements for a Spiral Rad

hose?

• ID/OD/Wall of hose must be to print. •Cut length from extrusion must be held with +/-1/16" to minimize cosmetic issues. •Hose design must meet guidelines in order to cap hoses successfully.

Image

What are the key images that define a quality spiral rad hose in the eyes of the customer.

•Nonfills are not acceptable. These are created by the cut length not being correct

from extrusion. •Bulges and ridges are not acceptable, which

is are result of poor cut length and loading technique in forming

•Must develop process that has a fast line speed with low scrap.

Conclusion: We must develop a process to ensure that our hose

dimensions and cut length is capability from extrusion.

Conclusion: Concept Generation must include and focus on ways to improve

extrusion cut length, standar,ding techniques and ensure that ~r rusion

process is efficient and eff I

Page 88: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

80

Appendix BS

DFSS Session Result of Quality Function Deployment (QFD) Development

Page 89: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

OlJ __ /,l~ .,,.,..

" • I

• " I II

• ' • ' • ., .. ~ ; :, :, 1 J ~ :a J l'i-' I 'i-' j ................

DIY.l..tllc1M~N:>l,'03,aClBl'OJ&o:J

( ~ I I ~ 'E f '

! ! s I ! -M-" --" .. . !t

~ . • ;a . -...,

I C I

' ' ' ' • ' ' I

' • a __, __ , ....... Mllolc

a

' I I

' ' I

' ' ' ' I

' ' • ---

,, ' •

I

' I

' ' C

' C

' • I

" _...,. .. I I ' ' • ' • ' •

I •

I • " -· " ' '

I • •

I • '

I I •

I I II II

I I I •

I • • ' •

I • ' ' •

---" • I

' I

• • • ' I I I

• ' II __ .. _ II

I ' ' • I I

• ' I

' I

' ' I 111-...-... " I

' ' ' ' ' ' ' ' I I

• • H _,. ___ ,.. H

' I

' ' ' ' ' ' ' • ' • • " --" ' C

' I I I

' ' ' ' I I

• I ..

-· " ' ' ' • ( I . I

• I

• I I

• --·

" I I '

I •

I • ' ' ' '

I '

I

--..

' I I

' ' I I

' C I I I I II _,,..,. __ .., .. •

• I I I

' ' I

' • • I I I II

---""""""'-I

' . I '

I I I '

I I '

I • • .... I ,.,.. .. _.. __ ~-- • ' '

I

' I

' I

' • I

• I I

_,.... .......... -.-:I • I I • • I

• I I

• ' • I

' " • I I • •

I I •

I I '

I I I

" ---• ' ' • ' • ' • ' • • •

I '

I ID-' I

' I

' I I I

' I I

• I I

• ----~ I

·f u ,11 f

If I I ( Ii !I I ! r

......... ,._MIi)

1 I •

'Ii I

I • . l I a •1 I l

l r i

f • r .. J I

I t I i' I I I

I • I ~

1-I

a:Jb 00 ......

Page 90: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

82

AppendixB6

DFSS Session Result of Pugh Concept Selection Development

Page 91: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

M 00

Oi:ent

Qf0 -R~ San

Fwtmv•mesal!llbtes:inl'I I :lllnii., M ~ be Clplllie,

l '/.916'

IDml!!bltaplllilo11>M0>110' 3 -ea,a,'/.OII

Wlllllido!eulll!Cbt-• • 01d~•~mD ~-.-- l 00-lllllllOOk ICC'lllli~.l,n 9Nd I

aa.. .. --.... -- ~--r,1--..i 7 l'lllm111myllll<lllilllnolells

I ··---·-No ·--Pro'1t ti 2mll'I • ?l't-----to-- \0

Ps11111•btd«mtt 11 -... RLl>w""""""ml!!mt«

.,.;11-(SIMJ,ogi ""

"'' 12

Polt im11110'yrrUllbt.,_ .. ···- - ~ -· ~ ·-' u

Qmd-. Elmlct'O Qund'·

24Yn DATI.M Pacbg11

n

0 0

r 0 0

~ 0 ~ . t " ~i ~ :: • J:~ o.!, 0 ~ ~

n

• 0 i -"' 0 ~ Q.

~ 0

2 ,. '

Pugh Matrix Pugh Concept Selection

~ .. t.tJa.aoond

1ftxed cme!lrll

El<!MO' Clp -IIYn .Oll'BOR ZJJv [Ml- !Win; Fb.ed

5dij lraoaod -.... Cop """'° ..

Pacbp laof«mo ClpOlly Cc>'fr,n ITIIIMlll 1/Drao media Cln!anng I.I/bl

b,od.,~, .. 01,. c:o&i,grn CUl!in9., .. fade lloN ...... ., cop ... 1/&'lnell

"°"' ... oo -1tto1 .....

ClftO'fli_l!!II

n 0 n n 0 n 0 0 0 0 0 0 ~ .____L

0 0 0 + . 0 0 0 C -0 0 0 0 0 ~ 0 0 0 0 0 0 .____L .:! 0 0 0 0 0 0

0 . 0 . 0 en -. . 0 . n . . ... .......,:._ .. N

0 0 0 0 0 -~ 0 0 . .......,:._ 0 • • • • 0 0 0 0 0 0 0 ... .____L

0 0 0 0 0 0 0 n n + n 0 0 L+-n 0 • 0 ♦ . + . ♦ • ♦ -• 0 0 0 0 0 + 0 . ,-.......:.._ 0 0 0 0 0 0 n n 0 0 0 • ~ 0 0 0 .

n n 0 • • 0 .____L 0 0 0 0 0 0 0 0 0 0 0 0 0 l I 0 l ◄ l ! ◄ ◄ l ,,..,, .,..... ....,-10 ' jl 10 ' I " ' 9 • - ~ ' ' 0 0 0 0 0 0 0 0 , . ., • 1

Gr

Page 92: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

84

Appendix Cl

DOE Trial Matrix and Sample Measurement for Insertion Force

Page 93: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

"' 00

_ std Order DOE RUN Rub. Hard. Yam~. Pre. Inter. Yam P!ll, Tube Yarn Denier Hose Cle:in. lnsertl.on ~b) 1.D. (mm~ Wallthlel<ness !mm) Wan Vmiatlon (mm) 1 2 60 .. 0.01 " <o.<O TO "''"' 33.0733 4.47546 0.13208 2 4 70 49 0.01 " <o.so Cocper ,,,, 32.6 32.4231 4.5974 0.48008 3 • eo 59 0.01 " ... , Cooper . ., 38.1 32.7685 -1.6647 0.87564 4 • 70 59 0.01 " , .. o TO c,,., 25.8 32.ana 4.47294 0.33528

' " 60 49 0.1 18 , .. o Coop~ Clo~ . . ' .. 70 49 0.1 18 ,.., TO . ., 30,7 32.7889 4.5593 0.22088 7 " 60 " 0.1 18 '"60 TO ""' 211,9 32.6568 4.83042 0.&5118

' " 70 59 0,1 18 , .. o Coop~ c,,., 32.1445 4.ST708 0.48006 • 18 60 49 0.01 24 '"" -~ Dirty 2U 32.8422 4.58184 0.38322 10 20 70 49 0.01 24 ,.., TO Cl= 26.5 32.7738 4.52882 0.25148

" " 60 " 0.01 24 ''"" TO CIOM 31.4 32.8879 ...... 0,.,.. 12 24 70 59 0.01 24 '"'° -~ Dirty 50 33.2943 •. 62374 o.m1e 13 58 60 49 0.1 24 ... , TO Dlrty

" eo 70 " 0.1 24 - -~ Clo~ ,,. 32.6593 4.4831 0.381

" 82 60 59 0.1 24 '"" -~ Cleari 49.5 33.4747 4.4-4248 0.70812

" " 70 59 0.1 24 - TO . ., 42.8 33.5204 4.49834 0,76882 17 10 60 49 0.01 " 60/40 TG ""' 28 32.7767 4.62882 0.44704 18 12 70 49 0.01 " 60/40 Coop~ Clom 32,7 32.4587 4.60246 0.25654

" " 60 " 0.01 " 60/40 -~ c,,., 36,3 32.8397 4.61612 0.28182 20 " 70 " 0.01 18 60/40 TO Orty 27.7 32.827 4.47548 0.53086 21 60 60 49 0,1 18 "'" -~ o•y 28.4 32.4688 4.83804 0.284111

" 82 70 49 0.1 " 80l40 TO Clo~ 33.11 32.887 -4.411532 0.60038 23 " " " 0.1 " 60140 TG Clos, 27,5 32.8498 4.59894 0,381 24 .. 70 59 0.1 18 8Dl40 Cooper . ., 25 " 60 " 0.01 24 t!0/40 Coop~ e1, .. 29,3 32.7809· 4.54914 0,28702 28 28 70 " 0,01 24 80/40 TO O,rty 30.8 32.9108 4.49072 0.3937 27 30 60 " 0,01 24 00/40 TO ""' 35.4 32.8244 4.55878 0.21844 • 28 32 70 " 0.01 24 60/40 Coop« Cl,., 41,4 32.8727 4.5847 0.111468 29 "

., 49 0.1 24 60/40 TG c,,., 33.11753 4.55876 0.28194· 30 " 70 49 0.1 24 60/40 Coop~ D"1y 30,9 32.8187 4.51812 0.4W84 31 70 60 59 0.1 24 60/40 Coop~ o•y 33.1972 4.42722 0.27178', 32 72 70 " 0.1 24 80/40 TO Clo~ 33.8652 4,55188 0.45974 33 2 " .. 0.01 " '"" TG c,,., . 32.8468 4.58692 0.34798

" 4 70 49 0.01 " , .. o Coop« .,, 28.6 32.827. 4.55422 0.32512 , , 35 • eo " 0.01 " , .. o Coop~ ""' 40,3 33.De83 4.48818 0.1®22

" • 70 " 0.01 18 , .. o TG Clos, 27.3 32.4485 4.84312 0,311322 37 " 60 " 0,1 18 , .. o Cooptlll' Clt1an 38.8 32.B085 4.5212 0.74188 36 .. 70 49 0.1 " ... , TO Dirty 300 32.893 4.57708 0,3175

" .. 60 " 0.1 " ,.., TG D"1y 30.7 32.8371 4.52828 0.21082 .. 48 70 " 0.1 18 , .. o -~ ao., 32.8819 4.5974 0,22608

" " .,

" 0.01 24 , .. o -~ . ., 28.9 32.5658 -4.73964 0.63848

" 20 70 .. 0.01 24 - TO Cl= 33.2 329403 ◄.57454 0.3883

" " 60 " 0.01 24 40/00 TO Clom

" 24 70 " 0.01 24 ◄0180 Cooper . ., 4◄.7 33.2481 ,4,41708 0.98268

" " 80 49 0,1 24 , .. o TO ""' .. 60 70 48 0.1 24 , .. o -~ Clos, 30.1 32.5857 ◄.49320 0.33782

" " 60 " 0.1 24 ,.., Coop« CIOM 48 " 70 " 0.1 24 ... , TO Dirty 60.5 33.7541 4.48058 0.55628 49 10 80 " 0.01 18 60/40 TO """ 29.7 32.8088 4.50068 0.35814 60 12 70 49 0.01 " ..-o Coop« Clos, 33.4 32.6222 ◄.54152 0.54356

" " 60 " 0.01 " 80/40 Coop« Clo~ 33.7 32.6438 4.53898 0.2413

" 18 70 " 0.01 " 80140 TG . ., 25,6 32.S068 4.597◄ 0,2921

" 50 " " 0.1 " 80/,40 -· . ., " 52 70 " 0,1 18 80/40 TO Clo~ 32.2 32.8295 ◄.57982 0.3937 55 " 80 " 0,1 " 60/40 TO ,Clei!II 27.4 32.Ba51 4,48818 0.62832 58 .. 70 " 0.1 " SOHO Coop« Dirty " 32.9235 4.84058 0.23878 57 28 60 " 0.01 24 .., .. Coop« a,., 28.8 32.8771 ◄.58724 0.3048 59 28 70 .. 0.01 24 60/<0 TG D"1 35.8 32.8143 4.6339 0.◄1858 59 30 60 " 0.01 24 ..-o TO D"1 33.2 32.8371 '·""" 0.3327◄ 60 32 70 " 0.01 24 80l40 -~ a,., 42.7 33.1343 4.54814 0.52832

" " 80 49 0.1 24 50/40 TO Clos,

" " 70 " 0.1 24 80/40 Coop« . ., 31.4 32,8822 4.682111 0.67858

" 70 " " 0,1 24 80140 Coop~ O,rty 51.3 33.6028 4.◄323 0.69182

" 72 70 " 0,1 24 80/◄0 TO Clom ◄8,4 33.7e.41 ◄.48024 0.6842

Page 94: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

86

Appendix C2

Estimated Effects and P-Values for Insertion Force

Page 95: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

87

Results for: INSERTION DOE RUNS & RESULT.MTW

Factorial Fit Insertion-A versus Rubber Hardness, Yam Angle, ...

Estimated Effects and Coefficients fo:c Inse:ction-A (coded units)

Te:cm Effect Coef SE Coef T p Constant 34.116 0.6403 53.28 0.000 Rubber Hardness 2.819 1.409 0.6715 2.10 0.048 Yai:n Angle 8.444 4.222 0.6482 6.51 0.000 P:cefo:cm Inte:cfe:cence 2.3Ei2 1.181 0.4413 2.68 0.014 Ya.Dl Packages 3.981 1.991 o. 6482 3.07 0.006 Tube/Cover Split -0.919 -o. 459 0.4528 -1.01 0.322 Yam Denie:c -5.525 -2.762 0.6639 -4.16 0.000 Hose Cleaniness -0.594 -0.297 0.6074 -0;49 0.630 Rubbe:c Ha:cdness•Ya:cn Angle -0.506 -0.253 0.6158 -0.41 0.685 Rubbe:c Ha:cdness•P:cefo:an. Inte:cfe:cence 1.400 0.700 0.6322 1.11 0.281 Rubbe:c Ha:cdness*Yarn Packages 2.219 1.109 0.4639 2.39 0.026 Rubbe:c Hai::dnesst'fube/Cove:c Split 1.706 0.853 0.4528 l.88 0.073 Rubbe:c Ha:cdness•Yarn Denie:c 2.875 1.437 0.6639 2.17 0.042 Rubbe:c Ha:cdness•Hose Cleaniness -0.081 -0.041 0.4526 -0.09 0.929 Yarn Angle•P:cefom Inte:cfe:cence 3.950 1.975 0.6074 3.25 0.004 Yai:n Angle~Ya,:n Packages 6.581 3.291 0.4528 7.27 0.000 Ya,:n Angle~e/Covet Split 0.519 0.259 0.4639 0.56 0.582 Ya.z:n Angle·~Yam Denier.: -3.738 -1.869 o. 6715 -2.78 0.011 Yarn Angle"t'Hose Cleaniness .-L90.6 -0.953 o. 4639 -2.05 0.053 P:cefo:cm Inte:cfe:cence•Ya:cn Packages 0.500 0.250 0.6715 0.37 o. 713 P:cefo:cm Inte:cfe:cence• -0.550 -0.275 0.4413 -0.62 0.540

Tube/Covet Split P:cefo:cm Inte:cfe:cence*Ya:cn Denie:c -0.544 -0. 27Z 0.6403 -0.42 0.675 P:cefo:cm. Inte:cfe:cence*Hose Cleaniness 0.362 0.181 0.4413 0.41 0.685 Yarn Packages~e/Cover Split 0.269 0.134 0.6158 0.22 0.829 Ya.z:n Packages~Hose Cleaniness -1.769 -0.884 0.4639 -1.91 0.070 Rubbe:c Ha:cdness• 1.175 0.587 0.6322 0.93 0.363

P:cefo:cm Interference* Tube/Covet Split

Rubber: Haz:dness* 0.000 0.000 0.4413 o.oo 1.000 Ptefom Interference* Hose Cleaniness

Yam Angle*Prefonn. Intetfetencew 1.538 0.769 0.6074 1.27 0.220 Tube/Covet Split

S = 2.29077 R-Sq = 85.38% R-Sq(adj) 81.25%

Analysis of Variance for Insertion-A (coded units)

Sour:ce DF Seq SS Adj SS Adj HS F p Hain Effects 7 1311. 72 741. 557 105.937 20.19 0.000 2-1Jay Interactions 17 953.74 895.339 52.667 10.04 0.000 3-1Jay Interactions 3 9.32 9.317 3.106 0.59 0.627 Residual E:c:co:c 21 110.20 110.200 5.248

Pur:e En:o:r: 21 110.20 110.200 5.248 Total 48 2384.98

Page 96: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

Appendix C3:

Estimated Effects and P-Values for Insertion Force after Removing Insignificant

Factors

88

Page 97: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

89

Factorial Fit: Insertion-A versus Rubber Hardness, Yarn Angle, ...

Estimated Effects and Coefficients foz: Insez:tion-A (coded units)

Tem Effect Coef SE Coef T p Constant 33.931 0.5254 64.59 0.000 Rubber Hardness 3.654 1.827 0.6066 3.01 0.005 Yam Angle 9.400 4.700 0.5913 7.95 0.000 Pref:c:om Inte:c:fe:c:ence 2.242 1.121 0.5075 2.21 0.034 Yam Packages 3.525 1.763 0.5990 2.94 0.006 Yam Denier -6.350 -3.175 0.5990 -5.30 0.000 Rubber Haz:dness~Yam Angle -0.996 -0.498 0.5075 -0.98 0.334 Rubber Ha:cdness~P:cefrom Interference 1.987 0.994 0.5913 1.68 0.102 Rubber Ha:cdness*Ya:cn Packages 2.229 1.115 0.5340 2.09 0.044 Rubbez: Haz:dness~Yam Deniez: 3.254 1.627 0. 5340 3.05 0.004 Yam AngleTPz:efz:om Intez:fez:ence 4.417 2.208 0.5593 3.95 0.000 Yam AngleTYam Packages 6.712 3.356 0.5165 6.50 0.000 Yam AngleTYaz:n Deniez: -3.238 -1.619 0.5675 -2.85 0.007 Pz:efz:om InterferenceTYaz:n Packages -0. 446 -0.223 0.6290 -0.35 0.725 Pref:c:om Inte:cfe:c:ence*Yam Denier -1.121 -0.560 0.5834 -0.96 0.344

S 2.65814 R-Sq = 89.93% R-Sq(adj) 85.78%

Analysis of Variance foz: ~nsez:tion-A (coded units)

Sow::ce DF Seq SS Adj SS Adj !IS F p !lain Effects 5 1294.l 1211. 7 242.332 34.30 0.000 2-Way Interactions 9 850.6 850.6 94.511 13.38 0.000 Residual E:cro:c: 34 240.2 240.2 7.066

Pui:e E:cto:c 34 240.2 240.2. 7.066 Total 48 2385.0

Page 98: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

90

Appendix C4:

Epsilon2 Table for Comparing the Relative Strength of Each Factor on the Response

Page 99: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

91

Factors Sum of Squares Epsilon•2 % Epsilon•2

Rubber Hardness 22.69 22.69/2384.98 0.95 Yarn Angle 539.04 539.04/2384.98 22.60 Preform Interference 77.6 77.6/2384.98 3.25 Yam Packages 413.66 413.66/2384.98 17.34 Yam Denier 241.16 241.16/2384.98 10.11 Total 2384.98

Page 100: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

92

AppendixD

1st RSD Trial Matrix and Samples Measurement for Bulges Issues

Page 101: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

93

RunOrder PtType Blocks Interference Cut Length (inch) Bulges 1 1 1 0.015 28.875 1 2 1 1 0.035 28.875 9 3 1 1 0.015 29.375 3 4 1 1 0.035 29.375 6 5 -1 1 0.015 29.125 6 6 -1 1 0.035 29.125 6 7 -1 1 0.025 28.875 3 8 -1 1 0.025 29.375 3 9 0 1 0.025 29.125 3

10 0 1 0.025 29.125 6 11 0 1 0.025 29.125 3 12 0 1 0.025 29.125 3 13 0 1 0.025 29.125 1 14 1 1 0.015 28.875 1 15 1 1 0.035 28.875 9 16 1 1 0.015 29.375 6 17 1 1 0.035 29.375 9 18 -1 1 0.015 29.125 1 19 -1 1 0.035 29.125 3 20 -1 1 0.025 28.875 1 21 -1 1 0.025 29.375 6 22 0 1 0.025 29.125 9 23 0 1 0.025 29.12~ 3 24 0 1 0.025': 29,125 6 25 0 1 0.025 29.125 6 26 0 1 0.025 29.125 6

Page 102: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

94

AppendixE

2nd RSD Trial Matrix and Samples Measurement for Bulges and Non-Fills Issues

Page 103: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

95

RunOrder PITt11e Blocks Interference Cut Leng!h (inch) Non-Fills (mm) Bulges 1 1 . 1 0.005 29.125 2 3 2 1 1 0.03 29.125 2.8 3 3 1 1 0.005 30.125 0.7 9 4 1 1 0.03 30.125 1.9 6 5 0 1 0.0175 29.625 0.4 3 6 0 1 0.0175 29.625 1.4 3 7 0 1 0.0175 29.625 1.66 1 8 -1 2 0.005 29.625 1.4 3 9 -1 2 0.03 29.625 · 0.7 1 10 -1 2 0.0175 29.125 0.5 1 11 -1 2 0.0175 30.125 0.2 3 12 0 2 0.0175 -29.625 1.9 3 13 0 2 0.0175 29.625 1.2 3 14 0 2 ·0.0115 29.625 0.1 1 15 1 1 0;005 29.125 1.2 6 16 1 1 0.03 29.125 · ·0.9 3 17 1 1 0.005 ,_3Q.125 ·, 1.9 9 18 1 1 0.03 '30.125 · 0.5 9 19 0 1 0.0175 29.625 2.4 6 20 0 1 0.0175 29.625 2.4 6 21 0 1 0.0175 :29.625 ·0,3 3 22 -1 2 0.005 29.625 0.2 3 23 -1 2 0.03 29.625 0.5 6 24 -1 2 0.0175 29.125 1.5 1 25 -1 2 0.0175 30.125 0.03 1 26 0 2 0.0175 29.625 1.7 1 27 0 2 0.0175 29.625 0.3 1 28 0 2 0.0175 29.625 0.4 1

Page 104: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

96

AppendixF:

33mm Process Capability Trial Matrix and Samples Measurement

Page 105: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

97

Trial Run Cut lena!!! {inch} I.D. (mm) Wall Thickness {mm} Wall Thickness Variation {mm} Non-Fills {mm) Bulges 1 293/8 32.93618 4.47802 0.31496 0.7 3 2 293/8 32.97428 4.51612 0.28194 1.1 3 3 293/8 32.92602 4.51612 0.34798 0.3 3 4 293/8 33.0073 4.45262 0.1143 0.7 9 5 293/8 32.91332 4.52882 0.381 0.8 1 6 293/8 32.9057 4.49072 0.20828 1.2 6 7 293/8 32.85998 4.47294 0.33528 1.5 3 8 293/8 32.85998 4.4958 0.37338 1 1 9 293/8 32.84474 4.48056 0.32512 1.18 6 10 293/8 32.85744 4.49834 0.28702 0.11 3 11 293/8 32.83458 4.4704 0.21336 0.4 1 12 293/8 33.0073 4.4577 0.2413 0.6 9 13 293/8 32.88538 4.4577 0.32512 0.7 3 14 293/8 33.0073 4.48818 0.20574 0.5 1 15 293/8 32.90062 4.47548 0.25908 1.4 3 16 293/8 32.88538 4.45008 o.1n8 0.9 3 18 291/8 32.9184 4.4704 0.2413 1.1 3 19 291/8 32.91078 4.49072 0.25146 1.4 3 20 291/8 32.88284 4.50088 0.1397 0.7 3 21 291/8 32.86506 4.49326 0.18288 1.1 1 22 291/8 32.97428 4.47294 0.16256 0.25 6 23 291/8 32.8422 4.46024 0.18796 0.6 1 24 291/8 32.78632 4.4831 0.23876 0.6 1 25 291/8 32.95904 4.45262 0.19812 1.4 1 26 291/8 33.00984 4.53898 0.2794 2.8 1 27 291/8 32.9311 4.4577 0.27432 1.3 3 28 291/8 32.88538 4.46532 0.3556 0.2 3 29 291/8 32.9438 4.47802 0.28448 2.8 6 30 291/8 32.9565 4.48056 0.20828 1 1 31 291/8 32.92602 4.47802 0254 0.7 1 32 291/8 32.85998 4.4958 0.34544 0.9 3 33 291/4 32.99714 · 4.445 0.22606 2.4 3 34 291/4 32.8803 4.46532 0.24638 0.8 3 35 291/4 32.93872 4.445 0.2288 1.5 9 36 291/4 32.91078 4.48056 0.24892 0.91 3 37 291/4 32.8422 4.4831 0.3302 1 1 38 291/4 32.79394 4.47802 0.27686 0.2 1 39 291/4 32.92856 4.45262 0.21082 0.9 3 40 291/4 32.83458 4.4704 ·o.34798 0.75 3 41 291/4 32.83204 4.47294 0.28702 0.3 1 42 291/4 32.89554 4.47294 0.23368 0.63 3 43 291/4 32.80156 4.49834 0.28702 0.8 1 44 291/4 32.81934 4.53898 0.26162 0.15 1 45 291/4 32.n616 4.4704 0.27686 0.6 1 46 291/4 32.90824 4.46278 0.26416 0.2 6 47 291/4 32.94126 4.45262 0.2413 0.4 1 48 291/4 32.9057 4.48818 0.26416 0.6 1

Page 106: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

98

AppendixG

37mm Process Capability Trial Matrix and Samples Measurement

Page 107: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

99

Trial Run Cut le~ ~nch} I.D. (mm) Wall Thickness (mm} Wall Thickness Variation (mm} Non-Fills (mm} Bul~s 1 29 3116 36.59632 5.01142 0,1524 0,8 3 2 29 3/16 36.59378 5.08508 0.21644 0.26 1 3 29 3/16 36.55314 5.0546 0,13462 1.24 1 4 29 3116 36.61156 5.04698 0.21336 2.04 3 5 29 3116 36.70046 5.03428 0.16034 0.6 3 6 29 3/16 36.60394 5.03936 0.16764 0.29 6 7 29 3/16 36.61156 5.0546 0.16002 0.99 1 8 29 3/16 36.6649 5.0292 0.12954 2.15 3 9 29 3/16 36.59886 5.04698 0.20828 1.5 6 10 29 3/16 36.66998 5.03428 0.17018 2 1 11 29 3116 36.61664 5.0419 0.1651 1.5 1 12 29 3116 36.576 5.05206 0.1651 0.2 1 13 29 1/4 36.70554 5.02412 0.16764 1.28 6 14 29 1/4 36.59378 5.0546 0.13462 0.6 1 15 29 1/4 36.54044 5.06476 0.21082 0.54 1 16 29 1/4 36.63188 5.0292 0.1524 0,93 1 17 29 1/4 36.64712 5.04444 0.14986 0.94 1 18 29 1/4 36.64966 5.02866 0,1651 1.27 3 19 29 1/4 36.63442 5.0546 0.16256 0.73 6 20 29 1/4 36.50234 5.0673 0.1651 0.98 1 21 29 1/4 36.6141 5,04698 0.1524 0.46 1 22 29 1/4 36.63696 5.04698 0.16256 0.14 6 23 29 1/4 36.54606 5.09TT8 0.22352 0.81 1 24 29 1/4 36.53028 5.03936 0.16002 0.3 3 25 29 5/16 36.61664 5.06984 0.17018 0.52 6 26 29 5/16 36.68522 5.07238 0.20574 0.42 1 27 29 5/16 36.64712 5.06222 0.22098 0,55 6 28 29 5/16 36.6141 5.0673 0.16764 024 1 29 29 5/16 36.66014 5.03936 0.14732 1.6 3 30 29 5/16 36.51758 5.04698 ·0.1778 1.04 1 31 29 5/16 36.5633 5.03936 0.15494 0.45 1 32 29 5/16 36.64458 5.03936 ·0.1778 1.09 3 33 29 5/16 36.65728 5.~8 0.16764 0.63 3 34 29 5/16 36.63442 5.0546, 0.17272 1.8 6 35 29 5/16 36.67252 5.0546 0.16764 0.48 6 36 29 5/16 36.64458 5.03682 0.17526 0.55 1

Page 108: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

100

AppendixH

Valid Construction Detail of Toyota 180L Spiral Radiator Hoses

Page 109: Toyota 180L Spiral Radiator Hose Design to Six Sigma Goal

101

Table 8

Valid Construction Detail of Toyota 180L Spiral Radiator Hoses

Component Code/Value

Tube Rubber Material 3745

Cover Rubber Material 3762

Pre-form Interference 0.018"

Yam Packages 24

Yam Angle 54°

Yam Denier 840

Tube/Cover Split 60/40