36
TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN STANDARDS, CONSTRUCTION SPECIFICATIONS, AND STANDARD DRAWINGS REVISED: January 2015

TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

Embed Size (px)

Citation preview

Page 1: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

TOWN OF HIDEOUT

WATER DISTRIBUTION SYSTEM

DESIGN STANDARDS,

CONSTRUCTION SPECIFICATIONS,

AND

STANDARD DRAWINGS

REVISED: January 2015

Page 2: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

Table of Contents

550 – Facility Design and Operation: Transmission and Distribution Pipelines

550.1 – Purpose pg. 1

550.2 – Intentionally Left Blank pg. 1

550.3 – Definitions pg. 1

550.4 – General pg. 4

550.5 – Water Main Designs pg. 4

550.6 – Component Materials and Design pg. 7

550.7 – Separation of Water Mains and Transmission Lines from Sewers pg. 9

550.8 – Installation of Water Mains pg. 10

550.9 – Cross Connections and Interconnections pg. 12

550.10 – Water Hauling pg. 12

550.11 – Service Connections and Plumbing pg. 12

550.12 – Transmission Lines pg. 13

550.13 – Operation and Maintenance pg. 13

600 – Supplemental Requirements

601 – General Construction Requirement pg. 14

602 – Materials and Equipment Approvals pg. 17

Appendix – Standards Drawings

Page 3: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

1

550. Facility Design and Operation: Transmission and Distribution Pipelines.

550-1. Purpose.

The purpose of this rule is to provide specific requirements for the design and installation of

transmission and distribution pipelines within the Town of Hideout (Town) which deliver drinking water

to facilities of public drinking water systems or to consumers. It is intended to be applied in conjunction

with State of Utah Administrative rules R309-500 through R309-550. Collectively, these rules govern the

design, construction, operation, and maintenance of public drinking water system facilities. These rules

are intended to assure that facilities are reliably capable of supplying water in adequate quantities

consistently meeting applicable drinking water quality requirements, and not posing a threat to general

public health. The State of Utah Administrative rules at the time this standard was created can be found

at www.drinkingwater.utah.gov

“Guidance:” is included in the Town Standard as recommendations but they are not part of the official

standard.

550-2. INTENTIONALLY LEFT BLANK.

550-3. Definitions.

"AF" means acre foot and is the volume of water required to cover an acre to a depth of one foot (one AF is

equivalent to 325,851 gallons).

"Air gap" The unobstructed vertical distance through the free atmosphere between the lowest opening from any

pipe or faucet supplying water to a tank, catch basin, plumbing fixture or other device and the flood level rim of

the receptacle. This distance shall be two times the diameter of the effective opening for openings greater than

one inch in diameter where walls or obstructions are spaced from the nearest inside edge of the pipe opening a

distance greater than three times the diameter of the effective openings for a single wall, or a distance greater

than four times the diameter of the effective opening for two intersecting walls. This distance shall be three times

the diameter of the effective opening where walls or obstructions are closer than the distances indicated above.

"ANSI/NSF" refers to the American National Standards Institute and NSF International. NSF International has

prepared at least two health effect standards dealing with treatment chemicals added to drinking water and

system components that will come into contact with drinking water, these being Standard 60 and Standard 61. The

American National Standards Institute acts as a certifying agency, and determines which laboratories may certify

to these standards

"Approval" unless indicated otherwise, shall be taken to mean a written statement of acceptance from theTown

Engineer.

"AWWA" refers to the American Water Works Association located at 6666 West Quincy Avenue, Denver, Colorado

80235. Reference within these rules is generally to a particular Standard prepared by AWWA and which has

completed the ANSI approval process such as ANSI/AWWA Standard C651-92 (AWWA Standard for Disinfecting

Water Mains).

"Backflow" means the undesirable reversal of flow of water or mixtures of water and other liquids, gases, or other

substances into the distribution pipes of the potable water supply from any source. Also see backsiphonage,

backpressure and cross-connection.

"Backpressure" means the phenomena that occurs when the customer's pressure is higher than the supply

pressure, this could be caused by an unprotected cross connection between a drinking water supply and a

Page 4: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

2

pressurized irrigation system, a boiler, a pressurized industrial process, elevation differences, air or steam

pressure, use of booster pumps or any other source of pressure. Also see backflow, backsiphonage and cross

connection.

"Backsiphonage" means a form of backflow due to a reduction in system pressure which causes a subatmospheric

or negative pressure to exist at a site or point in the water system. Also see backflow and cross-connection.

"cfs" means cubic feet per second and is one way of expressing flowrate (one cfs is equivalent to 448.8 gpm).

"Combined distribution system" is the interconnected distribution system consisting of the distribution systems of

wholesale systems and of the consecutive systems that receive finished water.

"Contaminant" means any physical, chemical biological, or radiological substance or matter in water.

"Corrosion inhibitor" means a substance capable of reducing the corrosiveness of water toward metal plumbing

materials, especially lead and copper, by forming a protective film on the interior surface of those materials.

"Cross-Connection" means any actual or potential connection between a drinking (potable) water system and any

other source or system through which it is possible to introduce into the public drinking water system any used

water, industrial fluid, gas or substance other than the intended potable water. For example, if you have a pump

moving non-potable water and hook into the drinking water system to supply water for the pump seal, a cross-

connection or mixing may lead to contamination of the drinking water. Also see backsiphonage, backpressure and

backflow.

"Disinfection" means a process which inactivates pathogenic organisms in water by chemical oxidants or

equivalent agents (see also Primary Disinfection and Secondary Disinfection).

"Distribution System" means the use of any spring or well source, distribution pipelines, appurtenances, and

facilities which carry water for potable use to consumers through a public water supply. Systems which chlorinate

groundwater are in this discipline.

"Division" means the Utah Division of Drinking Water, who acts as staff to the Director and is also part of the Utah

Department of Environmental Quality.

"Drinking Water" means water that is fit for human consumption and meets the quality standards of State of Utah

Administrative Rule R309-200. Common usage of terms such as culinary water, potable water or finished water are

synonymous with drinking water

"Drinking Water Project" means any work or facility necessary or desirable to provide water for human

consumption and other domestic uses which has at least fifteen service connections or serves an average of

twenty-five individuals daily for at least sixty days of the year and includes collection, treatment, storage, and

distribution facilities under the control of the operator and used primarily with the system and collection,

pretreatment or storage facilities used primarily in connection with the system but not under such control.

"Engineer" means a person licensed under the Professional Engineers and Land Surveyors Licensing Act, 58-22 of

the Utah Code, as a "professional engineer" as defined therein.

"Equivalent Residential Connection" (ERC) is a term used to evaluate service connections to consumers other than

the typical residential domicile. Public water system management is expected to review annual metered drinking

water volumes delivered to non-residential connections and estimate the equivalent number of residential

connections that these represent based upon the average of annual metered drinking water volumes delivered to

true single family residential connections. This information is utilized in evaluation of the system's source and

storage capacities (refer to State of Utah Administrative Rule R309-510).

Page 5: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

3

"Finished water" is water that is introduced into the distribution system of a public water system and is intended

for distribution and consumption without further treatment, except as treatment necessary to maintain water

quality in the distribution system (e.g., booster disinfection, addition of corrosion control chemicals).

"Flowing stream" is a course of running water flowing in a definite channel.

"fps" means feet per second and is one way of expressing the velocity of water.

"Geologist" means a person licensed under the Professional Geologist Licensing Act, 58-76 of the Utah Code, as a

"professional geologist" as defined therein.

"gpd" means gallons per day and is one way of expressing average daily water demands experienced by public

water systems.

"gpm" means gallons per minute and is one way of expressing flowrate.

"gpm/sf" means gallons per minute per square foot and is one way of expressing flowrate through a surface area.

"Maximum Contaminant Level" (MCL) means the maximum permissible level of a contaminant in water which is

delivered to any user of a public water system.

"MG" means million gallons and is one way of expressing a volume of water.

"MGD" means million gallons per day and is one way of expressing average daily water demands experienced by

public water systems or the capacity of a water treatment plant.

"mg/L" means milligrams per liter and is one way of expressing the concentration of a chemical in water. At small

concentrations, mg/L is synonymous with "ppm" (parts per million).

"Nonpoint source" means any diffuse source of contaminants or pollutants not otherwise defined as a point

source.

"Peak Day Demand" means the amount of water delivered to consumers by a public water system on the day of

highest consumption, generally expressed in gpd or MGD. This peak day will likely occur during a particularly hot

spell in the summer. In contrast, some systems associated with the skiing industry may experience their "Peak Day

Demand" in the winter.

"Peak Instantaneous Demand" means calculated or estimated highest flowrate that can be expected through any

water mains of the distribution network of a public water system at any instant in time, generally expressed in gpm

or cfs (refer to section 510-9).

"Plan Approval" means written approval, by the Town Engineer, of contract plans and specifications for any public

drinking water project which have been submitted for review prior to the start of construction.

"Public Drinking Water Project" means construction, addition to, or modification of any facility of a public water

system which may affect the quality or quantity of the drinking water.

"Residual Disinfectant Concentration" ("C" in CT calculations) means the concentration of disinfectant, measured

in mg/L, in a representative sample of water.

"scfm/sf" means standard cubic foot per minute per square foot and is one way of expressing flowrate of air at

standard density through a filter or duct area.

"Service Connection" means the constructed conveyance by which a dwelling, commercial or industrial

establishment, or other water user obtains water from the supplier's distribution system. Multiple dwelling units

such as condominiums or apartments, shall be considered to have a single service connection, if fed by a single

Page 6: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

4

line, for the purpose of microbiological repeat sampling; but shall be evaluated by the supplier as multiple

"equivalent residential connections" for the purpose of source and storage capacities.

"Significant deficiencies" means defects in design, operation, or maintenance, or a failure or defects in design,

operation, or maintenance, or a failure or malfunction of the sources, treatment, storage, or distribution system

that the Director determines to be causing, or have potential for causing, the introduction of contamination into

the water delivered to consumers.

"System with a single service connection" means a system which supplies drinking water to consumers via a single

service line.

"Water Supplier" means a person who owns or operates a public drinking water system.

"Water System" means all lands, property, rights, rights-of-way, easements and related facilities owned by a single

entity, which are deemed necessary or convenient to deliver drinking water from source to the service connection

of a consumer(s). This includes all water rights acquired in connection with the system, all means of conserving,

controlling and distributing drinking water, including, but not limited to, diversion or collection works, springs,

wells, treatment plants, pumps, lift stations, service meters, mains, hydrants, reservoirs, tanks and associated

appurtenances within the property or easement boundaries under the control of or controlled by the entity

owning the system.

550-4. General.

Transmission and distribution pipelines shall be designed, constructed and operated to convey adequate

quantities of water at ample pressure, while maintaining water quality.

550-5. Water Main Design.

1. Distribution System Pressure.

a. The distribution system shall be designed to maintain minimum pressures as required in

State of Utah Administrative Rule R309-105-9 at points of connection, under all

conditions of flow.

b. When static pressure exceeds 150 psi in new distribution water lines, pressure reducing

devices shall be provided on mains in the distribution system where service connections

exist.

Guidance: The normal working pressure in the distribution system should be between 60 and

100 psi. The requirement for PRV’s to be installed when pressures exceed 150 psi only applies to

new water pipelines. Systems should implement an operation program to protect water users

from excessive pressures.

2. Design Flow Rates.

Flow rates used when designing or analyzing distribution systems shall meet the minimum

requirements in the current version of the State of Utah Administrative Rule R309-510.

3. Hydraulic Analysis.

a. All water mains shall be sized following a hydraulic analysis based on flow demands and

pressure requirements.

Page 7: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

5

b. Where improvements will upgrade more than 50% of an existing distribution system in a

given phase of a specific project, or where a new distribution system is proposed, a

hydraulic analysis of the entire system being upgraded or being installed shall be

prepared and submitted for review prior to plan approval.

c. Some projects require a hydraulic model. The Town may require submission of a

hydraulic modeling report and/ or certification in a format acceptable to the Town

Engineer, as outlined in State of Utah Administrative Rule R309-511, prior to plan

approval.

4. Minimum Water Main Size.

For water mains not connected to fire hydrants, the minimum line size shall be 4 inches in diameter,

unless they serve picnic sites, parks, semi-developed camps, primitive camps or roadway rest-stops.

Minimum water main size, serving a fire hydrant lateral, shall be 8 inches in diameter unless a

hydraulic analysis indicates that required flow and pressures can be maintained by 6-inch lines.

Guidance: Generally, velocity in water main should not exceed 5 fps for base water system demands

and not to exceed 12 fps under peak instantaneous demand or peak day demand with fire flow

imposed. Mains should be designed with sufficient excess capacity to provide for anticipated future

connections.

5. Fire Protection.

When a public water system is required to provide water for fire flow by the local fire code official,

or if the system has installed fire hydrants on existing distribution mains for that purpose:

a. The design of the distribution system shall be consistent with the fire flow requirements

as determined by the local fire code official. The fire flow requirement for residential

subdivisions is 1500 gpm.

Guidance: The State Fire Marshall’s office has stated that “The State adopted fire code

recognizes that water mains intended for firefighting need not become subject to

retroactive fire flow requirements. As such, an existing system is considered code

compliant as long as it is maintained properly and new construction does not alter the

fire flow requirement. Water companies are encouraged to make improvements

incrementally to avoid a possible moratorium on development due to lack of water, i.e.,

fire flow.”

b. The location of fire hydrants shall be consistent with the requirements of the State

adopted fire code and as determined by the local fire code official.

Guidance: Generally, individual hydrant spacing may range from 200 to 500 feet

depending on the area being served. The planning of hydrant locations should be a

cooperative effort between the water utility and local fire officials.

c. The pipe network design shall permit fire flows to be met at fire hydrant representative

locations together with “peak day” system demands while minimum pressures as

Page 8: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

6

required in State of Utah Administrative Rule R309-105-9 are maintained at all times

and at all points in the distribution system.

d. Fire hydrant laterals shall be a minimum of 6 inches in diameter.

6. Geologic Considerations.

The character of the soil through which water mains are to be laid shall be considered.

Special design and burial techniques shall be employed for Community Water Systems in areas of

geologic hazard (e.g., slide zones, fault zones, river crossings, etc.)

Guidance: Water supply conduits and major service lines crossing known fault areas should be either

designed to accommodate significant differential movement of the ground, or be valved

immediately above and below the points of the fault crossing to allow control of water flow, in case

of pipe rupture during an earthquake event.

Guidance: Water systems should be designed to provide alternative flow paths for major conduits in

regions of known geologic hazards.

7. Dead Ends.

a. To provide increased reliability of service and reduce head loss, dead ends shall be

minimized by making appropriate tie-ins whenever practical.

b. Where dead-end mains occur, they shall be provided with a fire hydrant if flow and

pressure are sufficient, or with an approved flushing hydrant or blow-off for flushing

purposes. Flushing devices shall be sized to provide flows that will give a velocity of at

least 2.5 fps in the water main being flushed. No flushing device shall be directly

connected to a sewer.

8. Isolation Valves.

Sufficient number of valves shall be provided on water mains so that inconvenience and sanitary

hazards will be minimized during repairs. Valves shall be located at not more than 500 foot intervals

in commercial districts and at not more than one block or 800 foot intervals in other districts. Where

systems serve widely scattered customers and where future development is not expected, the valve

spacing shall not exceed one mile.

9. Corrosive Soils and Waters.

Consideration shall be given to the materials to be used when corrosive soils or waters will be

encountered.

10. Special Precautions in Areas of Contamination.

Where distribution systems are installed in areas of contamination:

a. pipe and joint materials which are not susceptible to contamination, such as permeation

by organic compounds, shall be used; and,

Page 9: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

7

b. non-permeable materials shall be used for all portions of the system including water

mains, service connections, and hydrant leads.

11. Water Mains and Other Sources of Contamination.

Caution shall be exercised when locating water mains at or near certain sites such as sewage

treatment plants or industrial complexes. Individual septic tanks shall be located and avoided. The

Town Engineer shall be contacted to establish specific design requirements prior to locating water

mains near a source of contamination.

Guidance: It is recommended that utility lines are clearly identified and visually different from one

another. Consideration shall be given to providing appropriate separation between water and other

utilities for operational and contamination reasons.

550-6. Component Materials and Design.

1. ANSI/NSF Standard for Health Effects.

All materials that may come in contact with drinking water, including pipes, gaskets,

lubricants and O-Rings, shall be ANSI-certified as meeting the requirements of ANSI/NSF

Standard 61, Drinking Water System Components - Health Effects. To permit field-

verification of this certification, all components shall be appropriately stamped with the NSF

logo.

2. Asbestos and Lead.

a. The use of asbestos cement pipe shall not be allowed.

b. Pipes and pipe fittings installed shall be “lead free” in accordance with Section 1417

of the Federal Safe Drinking Water Act. They shall be certified as meeting ANSI/NSF

372 or Annex G of ANSI/NSF 61.

Guidance: The Federal Community Fire Safety Act of 2013 exempts fire hydrants from the

lead free requirements of Section 1417.

3. Standards for Mechanical Properties.

Pipe, joints, fittings, valves, and fire hydrants shall conform to ANSI/NSF Standard 61, and

applicable sections of AWWA Standards C104-A21.4-08 through C550-05 and C900-07 through

C950-07.

4. Used Materials.

Only materials that have been used previously for conveying drinking water may be reused.

Used materials shall meet the above standards, be thoroughly cleaned, and be restored to their

original condition.

5. Fire Hydrants.

Page 10: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

8

a. Hydrant drains shall not be connected to, or located within, 10 feet of sanitary

sewers. Where possible, hydrant drains shall not be located within 10 feet of storm

drains.

b. Auxiliary valves shall be installed in all hydrant leads.

c. Hydrant drains shall be installed with a gravel packet or dry well unless the natural

soils will provide adequate drainage.

6. Air Relief Valves and Blow-offs.

a. At high points in water mains where air can accumulate, provisions shall be made to

remove air by means of hydrants or air relief valves.

b. The open end of the air relief vent pipe from automatic valves shall be provided

with a #14 mesh, non-corrodible screen and a downward elbow, and where

possible, be extended to at least one foot above grade. Alternatively, the open end

of the pipe may be extended to as little as one foot above the top of the pipe if the

valve’s chamber is not subject to flooding, or if it meets the requirements of (7)

Chamber Drainage.

c. Blow-offs or air relief valves shall not be connected directly to a sewer.

d. Adequate number of hydrants or blow-offs shall be provided to allow periodic

flushing and cleaning of water lines.

e. The air relief valve shall be installed in a manner to prevent from freezing. A shut-off

valve shall be provided to permit servicing of an air relief valve.

7. Chamber Drainage.

a. Chambers, pits, or manholes containing valves, blow-offs, meters, or other such

appurtenances to a distribution system, shall not be connected directly to a storm

drain or sanitary sewer.

b. Chambers shall be provided with a drain to daylight, if possible. Where this is not

possible, underground gravel-filled absorption pits may be used if the site is not

subject to flooding and conditions will assure adequate drainage.

8. Control Valve Stations.

a. Pressure Reducing Valves (PRV’s)

i. Isolation Valves shall be installed on both sides of the pressure reducing

valve.

ii. Where variable flow conditions will be encountered, consideration shall be

given to providing parallel PRV lines to accommodate low and high flow

conditions.

b. Backflow Devices

Installation of Backflow devices shall conform to the State-adopted plumbing code.

c. Meters

Meter installation shall conform to the State-adopted plumbing code and local

jurisdictional standards.

Page 11: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

9

550-7. Separation of Water Mains and Transmission Lines from Sewers.

1. Basic Separation Standards.

a. The horizontal distance between water lines and sanitary sewer lines shall be at least 10

feet. Where a water main and a sewer line must cross, the water main shall be at least

18 inches above the sewer line. Separation distances shall be measured edge-to-edge

(i.e., from the nearest edges of the facilities).

b. Water mains and sewer lines shall not be installed in the same trench.

c. Where local conditions make it impossible to install water or sewer lines at separation

distances required by subsection (a), the sewer pipes are in good condition, and there is

not high groundwater in the area, it may be acceptable if the design includes a minimum

horizontal separation of 6 feet and a minimum vertical clearance of 18 inches with the

waterline being above. In order to determine whether the design is acceptable, the

following information shall be submitted as part of the plans for review:

i. reason for not meeting the minimum separation standard;

ii. location where the water and sewer line separation is not being met;

iii. horizontal and vertical clearance that will be achieved;

iv. sewer line information including pipe material, condition, size, age, type of

joints, thickness or pressure class, whether the pipe is pressurized or not, etc.;

v. water line information including pipe material, condition, size, age, type of

joints, thickness or pressure class, etc.;

vi. ground water and soil conditions; and,

vii. any mitigation efforts.

d. If the basic separation standards as outlined in subsections (a) though (c) above cannot

be met, an exception to the rule can be applied for with additional mitigation measures

to protect public health, in accordance with State of Utah Administrative Rule R309-105-

6(2)(b).

2. Special Provisions.

The following special provisions apply to all situations:

a. The basic separation standards are applicable under normal conditions for sewage

collection lines and water distribution mains. More stringent requirements may be

necessary if conditions such as high groundwater exist.

b. All water transmission lines that may become unpressurized shall not be installed within

20 feet of sewer lines.

c. In the installation of water mains or sewer lines, measures shall be taken to prevent or

minimize disturbances of the existing line.

d. Special consideration shall be given to the selection of pipe materials if corrosive

conditions are likely to exist or where the minimum separation distances cannot be met.

These conditions may be due to soil type, groundwater, and/or the nature of the fluid

conveyed in the conduit, such as a septic sewage which produces corrosive hydrogen

sulfide.

e. Sewer Force Mains

Page 12: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

10

i. When a new sewer force main crosses under an existing water main, all portions

of the sewer force main within 10 feet (horizontally) of the water main shall be

enclosed in a continuous sleeve.

ii. When a new water main crosses over an existing sewer force main, the water

main shall be constructed of pipe materials with a minimum rated working

pressure of 200 psi or equivalent pressure rating.

3. Water Service Laterals Crossing Sewer Mains and Laterals.

Water service laterals shall conform to all requirements given herein for the separation of water

and sewer lines.

550-8. Installation of Water Mains.

1. Standards.

The specifications shall incorporate the provisions of the manufacturer's recommended

installation procedures or the following applicable standards:

a. For ductile iron pipe, AWWA Standard C600-10, Installation of Ductile Iron Water Mains

and Their Appurtenances;

b. For PVC pipe, ASTM D2774, Recommended Practice for Underground Installation of

Thermoplastic Pressure Piping and PVC Pipe and AWWA Manual of Practice M23, 2003;

c. For HDPE pipe, ASTM D2774, Recommended Practice for Underground Installation of

Thermoplastic Pressure Piping and AWWA Manual of Practice M55, 2006; and

d. For Steel pipe, AWWA Standard C604-11, Installation of Buried Steel Water Pipe- 4 inch

and Larger.

2. Bedding.

A continuous and uniform bedding shall be provided in the trench for all buried pipe. Stones

larger than the backfill materials described below shall be removed for a depth of at least 6

inches below the bottom of the pipe.

3. Backfill.

Backfill material shall be tamped in layers around the pipe and to a sufficient height above the

pipe to adequately support and protect the pipe. The material and backfill zones shall be as

specified by the standards referenced in Subsection (1), above. As a minimum:

a. for plastic pipe, backfill material with a maximum particle size of 3/4 inch shall be used

to surround the pipe; and

b. for ductile iron pipe, backfill material shall contain no stones larger than 2 inches.

4. Dropping Pipe into Trench.

Under no circumstances shall the pipe or accessories be dropped into the trench.

5. Burial Cover.

Page 13: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

11

All water mains shall be covered with sufficient earth or other insulation to prevent freezing,

unless they are part of a non-community system that can be shut-down and drained during

winter months when temperatures are below freezing. The minimum burial depth, measured at

top of pipe, for the projects in the Town of Hideout is 6’ below 7000’ and 7’ at or above 7000’

and the maximum burial depth is 10’. Burial depths greater than 10’ would require approval

from the Town Engineer.

6. Thrust Blocking.

All tees, bends, plugs, and hydrants shall be provided with thrust blocking, anchoring, tierods, or

restraint joints designed to prevent movement. Restraints shall be sized to withstand the forces

experienced.

7. Pressure and Leakage Testing.

All types of installed pipe shall be pressure tested and leakage tested in accordance with AWWA

Standard C600-10.

8. Surface Water Crossings.

Guidance: Surface water crossings, whether over or under water, present special problems. The

Division should be consulted before final plans are prepared.

a. Above Water Crossings

The pipe shall be adequately supported and anchored, protected from damage and freezing,

and accessible for repair or replacement.

b. Underwater Crossings

i. A minimum cover of 2 feet or greater, as local conditions may dictate, shall be

provided over the pipe.

ii. When crossing water courses that are greater than 15 feet in width, the

following shall be provided:

A. Pipe with joints shall be of special construction, having restrained joints

for joints within the surface water course and flexible restrained joints

at both edges of the water course.

B. Isolation valves shall be provided on both sides of the water crossing at

locations not subject to high ground water or flooding, so that the

section can be isolated for testing or repair.

C. A means shall be provided, such as a sampling tap, not subject to

flooding, to allow for representative water quality testing on the

upstream and downstream sides of the crossing.

D. A means shall be provided to pressure test the underground water

crossing pipe.

9. Sealing Pipe Ends During Construction.

Page 14: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

12

The open ends of all pipelines under construction shall be covered and effectively sealed at the

end of the day's work.

10. Disinfecting Water Lines.

All new water mains or appurtenances shall be disinfected in accordance with AWWA Standard

C651-05. The specifications shall include detailed procedures for the adequate flushing, disinfection,

and microbiological testing of all water mains. On all new and extensive distribution system

construction, evidence of satisfactory disinfection shall be provided to the Town Engineer. Samples

for coliform analyses shall be collected after disinfection is complete and the system is refilled with

drinking water. A standard heterotrophic plate count is advisable. The use of water for public

drinking water purposes shall not commence until the bacteriologic tests indicate the water is free

from contamination.

550-9. Cross Connections and Interconnections.

1. Physical Cross Connections.

There shall be no physical cross connections between the distribution system and pipe, pumps,

hydrants, or tanks that may be contaminated from any source, including pressurized irrigation.

2. Recycled Water.

Neither steam condensate nor cooling water from engine jackets or other heat exchange devices

shall be returned to the drinking water supply.

3. INTENTIONALLY LEFT BLANK

550-10. Water Hauling.

1. Community Water Systems.

Water hauling is not an acceptable permanent source for drinking water distribution in Community

Water Systems.

2. INTENTIONALLY LEFT BLANK

3. INTENTIONALLY LEFT BLANK

550-11. Service Connections and Plumbing.

1. Service Taps.

Service taps shall not jeopardize the quality of the system's water.

2. Plumbing.

a. Water services and plumbing shall conform to the State-adopted Plumbing Code.

b. Pipes and pipe fittings installed, shall be “lead-free” in accordance with Section 1417 of

the federal Safe Drinking Water Act. They shall be certified meeting the ANSI/NSF 372 or

Annex G of ANSI/NSF 61.

3. Individual Home Booster Pumps.

Page 15: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

13

Individual booster pumps shall not be allowed for individual service from the public water supply

mains.

4. Service Lines.

a. Service lines shall be capped until connected for service.

b. The portion of the service line under the control of the water system is considered to be

part of the distribution system.

5. Service Meters and Building Service Line.

Connections between the service meter and the home shall be in accordance with the State-

adopted Plumbing Code.

550-12. Transmission Lines.

1. Unpressurized Flows.

Transmission lines shall conform to all applicable requirements in this rule. Transmission line design

shall minimize unpressurized flows.

2. Proximity to Concentrated Sources of Pollution.

A water system shall not install an unpressurized transmission line less than 50 feet from a

concentrated source of pollution (e.g., septic tanks and drain fields, garbage dumps, pit privies,

sewer lines, feed lots, etc.). Furthermore, unpressurized transmission lines shall not be placed in

boggy areas or areas subject to the ponding of water.

550-13. Operation and Maintenance.

1. Disinfection After Line Repair.

The disinfection procedures of Section 4.7, AWWA Standard C651-05 shall be followed if a water

main is cut or repaired.

2. Cross Connections.

The water system shall not allow a connection that may jeopardize water quality. Cross connections

shall be eliminated by physical separation, an air gap, or an approved and properly operating

backflow prevention assembly.

The water system shall have an ongoing cross connection control program in compliance with R309-

105-12.

3. ANSI/NSF Standards.

All pipe and fittings used in routine operation and maintenance shall be ANSI-certified as meeting

NSF Standard 61 or Standard 14.

4. INTENTIONALLY LEFT BLANK

Page 16: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

14

In addition to complying with the requirements of 550 Facility Design and Operation: Transmission and

Distribution Pipelines all construction activity related to the installation, maintenance and repair of

water distribution systems have to comply with the following 600 Supplemental requirements. The

hierarchy of compliance shall be the current State of Utah Administrative Drinking Water Rules, then the

requirements of the Section 550 and then Section 600

600 Supplemental Requirements

601 General Construction Requirements

Licenses and Permit Required:

1. All water mains and service line construction shall be done by a General Utility Contractor

licensed and bonded in Utah.

2. When construction is required within the Town’s public right-of-way, contractor shall comply

with applicable Town regulations.

Removal of Unsuitable Materials:

Wherever in excavating the trench for water mains the bottom of the trench exposes peat, soft, clay,

quicksand, organic soils, or other material which is unsuitable such material shall be removed and

disposed of by the Contractor. The material thus removed shall be replaced by suitable material as

directed by a licensed geotechnical engineer.

Trench Excavation:

The Contractor shall exercise sound engineering and construction practices in excavating the trench and

maintaining it so that no damage will occur to any foundation, structure, pole line, pipe line, or other

facilities because of slough, slopes, or from any other cause. If, as a result of the excavation, there is

disturbance of the ground such as to endanger other property, the Contractor shall immediately take

remedial action at his own expense. No act, representation or instruction of the Town or his

representatives shall in any way relieve the Contractor from liability for damages or costs that result

from trench excavation.

Care shall be taken not to excavate below the depth indicated, and excavation below that depth shall be

backfilled with selected backfill material and compacted to the satisfaction of the Engineer at the

Contractor's expense.

The bottom of trenches shall be accurately graded to provide uniform bearing and support for each

length of pipe or undisturbed or compacted soil at every point along its entire length, except at the

joints. Bell holes shall be excavated to an extent sufficient to relieve bearing pressure at the bell joint.

Work shall comply with the "Utah Occupational Safety and Health Rules and Regulations" for the Utah

State Industrial Commission.

Handling of Pipe:

Page 17: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

15

All types of pipe shall be handled in such manner as will prevent damage to the pipe, pipe lining or

coating. Damage to the pipe, pipe lining or coating shall be repaired to the satisfaction of the Engineer

or the damaged pipe shall be removed from the job and methods of handling corrected to prevent

further damage.

Threaded pipe ends shall be protected by couplings or other means until laid.

The pipe and fittings shall be inspected for defects and cast iron pipe, while suspended above grade,

shall be rung with a light hammer to detect cracks.

Dirt or other foreign material shall be prevented from entering the pipe or pipe joints during handling or

laying operations and any pipe or fitting that has been installed with dirt or foreign material in it shall be

removed, cleaned and re-laid. (At times when pipe laying is not in progress, the open ends of the pipe

shall be closed by watertight plug.)

Pipe Bedding and Backfill:

Specific Requirements. Engineer shall submit to the Town Engineer for approval a complete system of

pipe zone embedment materials and installation requirements and final backfill. Submittal shall include

pipe manufactures installation recommendations, soils engineer’s recommendations and ANSI/AWWA

codes that apply. Engineer should consider environmental impacts of trucking on its selection of

imported materials.

General Requirements. For all graded streets, including the shoulders, asphalt, and parkway strip

located in the Right-of-Way, the backfill shall be compacted to 96% of the maximum modified proctor

density at optimal moisture content as determined by the Compaction Control Tests specified in ASTM

D1557 - 12 and verified by the methods specified in ASTM D2911 – 10 or ASTM D1556 – 07. The

compaction may be reduced to 90% for areas where vehicle traffic will never occur, and/or the most

distant five (5) feet of the Right-of-Way with written approval from the Town of Hideout Engineer.

Concrete thrust blocking shall be placed at bends, tees, and crosses or as directed by the Engineer. Blocking concrete shall be Class 4000 (1 ½” minus aggregate) concrete mix placed in place. (See Standard Detail).

Concrete blocking, when placed as indicated on the Standard Drawings, shall be bearing against solid undisturbed earth at the sides and bottom of the trench excavation and shall be shaped so as not to obstruct access to the joints of the pipe or fittings.

Dewatering of Trench:

Where water is encountered in the trench, it shall be removed during pipe laying operations and the

trench so maintained until the ends of the pipe are sealed and provisions are made to prevent floating

of the pipe. Trench water shall not be allowed to enter the pipe at any time.

Connections to Existing Mains:

1. The Contractor shall notify the Town of Hideout at least 48 hours (two full working days) in

advance of such connections.

2. Existing Town of Hideout water lines can only be shut down by crews authorized by the Town of

Hideout Engineer.

Page 18: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

16

3. The Contractor shall also provide written notice giving the date of the notice, the date and time

of the shutdown, and the duration of the shutdown. Major shutdowns shall only occur as

approved by the Town.

Disruption of Services:

Where the connection of new work to old requires interruption of service and notification of customers

affected, the Town of Hideout Engineer, and the Contractor shall mutually agree upon a date for

connections which will allow ample time to assemble labor and materials, and to notify all customers

affected. The Contractor will be required to notify all affected customers, the Town of Hideout Engineer

24 hours in advance of service being interrupted.

Wet Tap Connections:

Wet tap connections shall not be made on Friday, Saturday, Sunday, Holidays, or after 12:00 Noon

subject to approval by the Town of Hideout Engineer. Where connections are made between new work

and existing pipelines, such connections shall be made in a thorough, neat manner using suitable and

proper fittings to suit the conditions encountered. Each connection with an existing water line shall be

made at a time under conditions which will least interfere with normal user consumption and as

authorized by the Town of Hideout. Suitable facilities shall be provided for proper dewatering, drainage

and disposal of all water removed from the dewatered lines and excavations without damage to

adjacent property. Air and/or water testing may be requested by the Town of Hideout Engineer.

Testing Records and Documentation:

Both the pressure tests and leakage tests shall be recorded by the Contractor with the approved inspector present. Records shall contain the length of pipe tested, size of pipe, type of pipe, rated working pressure of pipe, time and duration of test(s), pressure(s) used, complete list of test equipment used, list of personnel performing the test(s), and any comments about the test. Test records shall be submitted to the Town of Hideout Engineer before the water line will be accepted.

Disinfection of Water Lines:

Before being placed in service, all new water lines and repaired portions or extensions of existing mains shall be chlorinated and flushed in accordance with these standards. The Contractor shall review the proposed method of chlorination with the Town of Hideout Engineer prior to water line construction and shall schedule the Inspector prior to chlorination of the water line.

The Contractor shall be responsible for maintaining the disinfected condition of existing water lines when connecting to, cutting into, repairing, or tapping existing water lines. Mains shall be flushed without using hydrants, unless approved by the Town of Hideout Engineer. Taps required by the Contractor for chlorination or flushing purposes shall be provided by him as a part of the construction of water mains, unless otherwise provided.

The Contractor shall be responsible for disposal of heavily chlorinated treated water flushed from mains and shall neutralize the waste water for protection of the environment before disposal into any natural draining channel, sanitary sewer, storm drain, curb and gutter, or onto the ground.

In the process of chlorinating newly laid pipe, all valves or other appurtenances shall be operated while the pipe line is filled with the chlorinating agent and under normal operating pressure.

Page 19: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

17

Twenty four (24) hours after the line is flushed by the Contractor, the Contractor shall take three (3) bacteriological samples from the installed pipe line with the inspector present. The locations of the samples shall be at intervals along the pipe line as directed by the Engineer. The sampling bottles and methods used shall be in accordance with the Utah State Board of Health, and this. Sample results shall be sent to the Town of Hideout Engineer.

All disinfection operations shall be observed and recorded by the Inspector. Records shall contain the length of pipe disinfected, size of pipe, type of pipe, location of pipe, date, time, and duration of disinfecting operations, complete list of equipment used and personnel performing the disinfection, and any comments about the disinfection operations. These records shall be submitted to the Engineer.

Should the initial treatment result in an unsatisfactory bacterial test, the original chlorination procedure shall be repeated by the Contractor until satisfactory results are obtained. Failure to get a satisfactory test shall be considered as failure of the Contractor to keep the pipe clean during construction, or to properly chlorinate the main, and no additional payment will be made for flushing and rechlorinating.

Concrete Thrust Blocking:

Concrete thrust blocking shall be placed at bends, tees, and crosses or as directed by the Engineer. Blocking shall be Class 4000 (1 ½” minus aggregate) concrete mix placed in place. (See Standard Detail 400.16).

Concrete blocking, when placed as indicated on the Standard Drawings, shall be bearing against solid undisturbed earth at the sides and bottom of the trench excavation and shall be shaped so as not to obstruct access to the joints of the pipe or fittings. Payment for blocking will be included in the unit price for water line installed.

602 Material and Equipment Approvals

General:

Prior to starting any water system project a complete submittal package shall be submitted to the Town

of Hideout for review. The submittal shall be well organized and shall include all relevant manufactures

information. If during the project changes are made the contractor shall submit the changes for review.

Contractor shall submit a complete Material and Equipment Submittal to the Town. Contractor shall

specifically identify any part of their submittal that is not in compliance

The Town shall review the submittal for compliance with the standards set forth herein. Review shall

not constitute a waiver from the State of Utah Administrative Drinking Water Rules or Section 550

requirements and for acceptance of the type and manufacturer of the products used.

Valves for Water Mains:

Valves types and valve manufacturer are subject to approval from the Town Engineer. The valves shall be suitable for an ordinary waterworks service intended to be installed in a normal position on buried pipe lines for water distribution systems. All valves shall be Mueller or EJ or approved equal the valves shall have the name or mark of the manufacturer, year valve casting was made, size and working pressure plainly cast in raised letters on the valve body.

All valves not in a vault shall be provided with a cast iron valve box of the extension sleeve type, and the

correct adjustable height to bring the top of the valve box flush with the finished surface. The valve box

shall not be less than (five) 5 inches in diameter, and shall have a minimum thickness of 3/16 inch, and

Page 20: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

18

shall be provided with suitable base and cover. The word “Water” shall be cast on the cover. Valve

boxes shall be equal to MUELLER H-10357 with No. 6 or No. 8 round base as needed. There shall also be

furnished to the Town of Hideout, one (1) “T” handle operating wrench for each five (5) new valves

installed on the project.

All gate valves shall be inspected upon delivery in the field to insure proper working order before

installation.

Water Service Connections and Fire Lines:

The service connections will be made by the Contractor, in accordance with these Specifications and

Standard Drawings. This excludes setting the meter, which will be accomplished by Town of Hideout

personnel, only after proper inspection of the service connection at the main service line, yoke, meter

box, and lid assembly (furnished by the Contractor). All connections to the TOWN OF HIDEOUT water

system including fire lines shall be metered unless otherwise approved by the Town of Hideout

Engineer. All service connections including fire lines shall be constructed in accordance with the

provisions of this standard up to the first shut-off valve within the building.

Service connections will be activated only after inspection, testing, chlorination and flushing of all new

water line facilities.

Each culinary service connection must be pressure tested in accordance with the provisions of this

standard except that the test pressure shall not be less than 50 psi greater than the line pressure.

Meter Yoke:

Meter yokes for 1" and smaller shall be approved by Town Engineer to verify compatibility with Town

water meter; meter fittings will be standard thread. Meter yokes for 1½-inch will be shall be approved

by Town Engineer to verify compatibility with Town water meter. Please refer to the appropriate

Standard Drawing. High pressure setters shall be used.

Meter Box:

Meter boxes will be 24-inch diameter for single 1-inch meter installations; and a 48-inch diameter vault

for 1½-inch meter. Meter box shall be location is subject to approval by the Town of Hideout Engineer.

Meter boxes shall also be insulated, including the lid.

Alternative Meter Box:

Alternative meter boxes that achieve high degrees of frost protection may be submitted for review and

possible approval.

Curb Stop and Curb Box:

Mueller Oriseal curb valve and cast iron extension-type curb box with arch pattern base with cast iron

foot piece as manufactured by Mueller or approved equal

Meters:

TOWN OF HIDEOUT provides meters. A fee shall be charged. Acquisition, calibration, and distribution

will be at the Town of Hideout's discretion.

Page 21: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:

19

Unless otherwise approved by the Town of Hideout Engineer water meters, vaults/boxes, and the

associated appurtenances shall be placed in the Town Right-of-Way between 6 (six) and 10 (ten) feet

behind the curb/gutter/edge of asphalt and in a landscaped area. Proposed interior placement of water

meters must be submitted to the Town of Hideout Engineer at the time the building plans are submitted

for initial review.

The Town of Hideout will maintain water service lines to the cold side of the water meter yoke or the

edge of the Town Right-of-Way , whichever is the shorter distance. If the water meter vault/box is on

private property the Town of Hideout will maintain the water meter, yoke, and vault/box only, not the

section of line between the right-of-way and the meter box.

Hydrants shall be six (6)-inch minimum size with two (2) 2½-inch hose nozzles and one (1) 4½-inch

pumper nozzle. Hydrants shall be supplied with O-Ring seals and a six (6)-inch ASA 125 pound flanged

inlet. Each hydrant shall be supplied complete with a flanged mechanical joint auxiliary gate valve with

box. They shall be EJ Water Master or approved equal.

Page 22: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:
Page 23: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:
Page 24: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:
Page 25: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:
Page 26: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:
Page 27: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:
Page 28: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:
Page 29: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:
Page 30: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:
Page 31: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:
Page 32: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:
Page 33: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:
Page 34: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:
Page 35: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised:
Page 36: TOWN OF HIDEOUT WATER DISTRIBUTION SYSTEM DESIGN … · town of hideout . water distribution system . design standards, construction specifications, and . standard drawings . revised: