Upload
richard-j
View
214
Download
0
Embed Size (px)
Citation preview
Towards improvedconstruction wasteminimisation: a need forimproved supply chainintegration?
Andrew R.J. Dainty and
Richard J. Brooke
The authors
Andrew R.J. Dainty and Richard J. Brooke are based at the
Department of Civil and Building Engineering, Loughborough
University, Loughborough, Leicestershire, UK.
Keywords
Waste management, Waste minimisation,
Supply chain management
Abstract
In recent years, economic, political and social pressures to
adopt sustainable work practices have led to a renewed
emphasis on developing effective waste minimisation
measures for major construction projects. This research
explored the efficacy of measures used for minimising waste
in high profile UK-based projects. The case studies revealed a
diverse range of waste strategies, the broader applicability of
which was then explored via a questionnaire survey of waste
minimisation specialists. The most effective measures were
deemed to be those that fostered “waste minimisation
partnerships” throughout the supply chain. Questions
remain, however, as to whether the industry is culturally
prepared for the collaborative relationships necessary to
engender radical improvements in waste minimisation
performance.
Electronic access
The Emerald Research Register for this journal is
available at
www.emeraldinsight.com/researchregister
The current issue and full text archive of this journal is
available at
www.emeraldinsight.com/0263-080X.htm
Introduction
The construction industry is heavily reliant on
natural resources for virtually all of its core
materials (Treloar et al., 2003). A degree of
material loss is however, all too often seen as an
inevitable by-product of major construction
projects. Typical wastage rates within the
industry are as high as 10-15 per cent (McGrath
and Anderson, 2000) and within the UK, total
construction wastage is estimated at around
70 million tonnes per annum (DETR, 2000a).
This makes the industry the second largest
producer of controlled waste (CIRIA, 1995),
the vast majority of which is lost to landfill sites,
the industry’s most common waste disposal
technique (Mills et al., 1999). Ferguson et al.
(1995) suggest that over 50 per cent of all
landfill in the UK could comprise construction
waste.
The industry’s lamentable waste
management performance and its reliance on
landfill is of particular concern given that most
could either be exploited for its residual value or
avoided in the first place (Pinto and Agopyan,
1994; Teo and Loosemore, 2001). In response
to this, the Government has prioritised the
reduction of landfill through sustainable waste
management measures and “green” taxation
measures (Lawson et al., 2001). Such measures
are made cost-effective by reducing purchase
and removal costs and increasing income
through trading in secondary markets for
materials (Coventry et al., 2001). Some
companies have begun to find that they can gain
a competitive advantage from adopting effective
waste minimisation strategies on site (Graham
and Smithers, 1996). Indeed, there is a
developing argument to suggest that waste
management can act as a profit centre in its own
right ( Johnston and Mincks, 1995). Regardless
of whether this is the case or not, economic,
social and political pressures are likely to
continue to drive up the costs of waste disposal
over the next few years which will increase the
Structural Survey
Volume 22 · Number 1 · 2004 · pp. 20–29
q Emerald Group Publishing Limited · ISSN 0263-080X
DOI 10.1108/02630800410533285
The authors would like to express their thanks to the
participating organisations involved in the five case
study projects for providing access to relevant
participants and to the interview and questionnaire
respondents themselves for participating in this
research project.
20
importance of waste minimisation strategies in
the UK (Turner and Powell, 1991).
This paper set out to explore the waste
minimisation strategies utilised in high profile
construction projects and to refine transferable
framework measures capable of being
transferred to other major projects. The paper
begins with a review of the key requirements of
waste minimisation strategies within the
industry, before examining those utilised in five
high profile construction projects. Their general
applicability and effectiveness are then
established via a questionnaire survey of waste
management specialists and the results used to
identify those strategies likely to have a
significant impact on other construction
projects.
The attitudinal and legislative context forconstruction waste minimisation
There are two principal ways in which
construction landfill can be reduced; by
minimising the amount of waste generated
through source reduction, or by improving the
management of the waste produced on site
(McDonald and Smithers, 1998). In the 1990s,
a number of research studies explored how work
practices, processes and technologies contribute
to the generation of waste (Bossink and
Brouwers, 1996; McDonald and Smithers,
1998; Poon, 1997). More recently however,
attention has focused on the role that human
behaviour has to play in waste causation and
minimisation in the industry (Lingard et al.,
2000; Teo and Loosemore, 2001). These
studies have demonstrated that careful
consideration of waste issues, supported by
effective education of the workforce and robust
audit procedures, can result in radical
improvements to waste minimisation
performance. However, industry scepticism
towards the value of such measures remains,
with many contractors feeling that waste
management falls outside of their core
responsibilities (DETR, 2000b).
The reluctance to implement effective waste
management measures has prompted
governments to take an increasingly hard-line
on regulating the industry’s materials usage.
Legislation is currently a key driver in ensuring
sustainable waste management in many
countries (McGrath and Anderson, 2000;
Teo and Loosemore, 2001). The Environmental
Protection Act (EPA) (1990) Part II is the
primary legislativemeasure for controlling waste
regulation in the UK. Notably, the Duty of Care
legislation, introduced in April 1992, places the
responsibility for final and safe disposal of waste
materials on the waste producer (CIRIA, 1999).
This means that any person who imports,
produces, carries, keeps, treats or disposes of
controlled waste has responsibility for its correct
and legal disposal. Allied to this are the EU
Landfill Directive (99/31/EC) and the landfill
tax. These regulations aim to reduce the volume
of waste and increase recycling rates. The tax
provides an incentive to reduce the waste sent to
landfill sites and to increase the proportion of
waste that is managed and recycled more
effectively (McGrath and Anderson, 2000).
These provide clear financial drivers for
construction firms to adopt more effective waste
management techniques. Direct costs include
the financial implications of the landfill tax and
the expense of transporting wasted materials
away from sites, and the environmental costs
associated with waste disposal. Indirect costs are
often hidden in the production or transport of
the material, as well as those incurred during
their storage on site. Up to 25 per cent of the
waste produced on construction sites could be
minimised relatively easily, which could increase
profits by up to 2 per cent (DETR, 2000b).
Given the relatively low margins typically
achieved by the industry, environmentally
friendly building practices can therefore provide
competitive advantage for the firms that
embrace them (Ngowi, 2001).
The requirements of construction industrywaste minimisation strategies
Previous research on waste causality reveals that
it can arise at any stage of the process, from
inception, through to the design, construction
and operation of the built facility (Craven et al.,
1994; Faniran and Caban, 1998; Gavilan and
Bernold, 1994; Spivey, 1974). These studies
have also shown that the most significant
sources of construction waste relate to design
changes (usually stemming from
Towards improved construction waste minimisation
Andrew R.J. Dainty and Richard J. Brooke
Structural Survey
Volume 22 · Number 1 · 2004 · 20–29
21
over-specification, poor detailing, late
variations, changing materials previously
ordered and alterations to complete work),
leftover materials, waste from packaging and
non-reclaimable consumables, design/detailing
errors, poor storage and handling of materials
and insufficient protection of the completed
works. Pressures on cost and programme
delivery also lead to working practices that are
not conducive to conserving materials and
avoiding damage (Coventry et al., 2001).
It would seem that waste minimisation is often
considered a low priority in the strategic
planning of projects. Indeed, by the time that
construction commences, many of the
opportunities for waste reduction have already
elapsed, with the management team only being
able to control waste through reactive
minimisation measures.
Waste levels are clearly dependent upon the
attitudes of key individuals engaged with the
project (Faniran and Caban, 1998). Of all
supply chain participants, clients arguably have
the greatest influence over waste issues as they
have the authority to set the environmental
standards to which the project team must
comply. However, efforts to influence waste
management will be of little value if those
further down the supply chain do not buy-in to
more effective waste management practices
(Teo and Loosemore, 2001). Given the
fragmented nature of the construction value
chain, embedding a culture of waste
minimisation throughout the supply chain is
likely to represent a significant barrier to
integrated waste minimisation solutions.
Developing an understanding of how this is
being achieved on large and complex projects
should provide insights into the measures that
could be adopted to embed a culture of
sustainable working throughout the industry.
Methodology
In order to identify effective waste minimisation
strategies for major construction projects,
two distinct sets of research activities were
undertaken. First, a series of interviews were
held with key stakeholders engaged on five large
and complex construction projects based
throughout the UK. The projects ranged from
£25m to over £100m in value and included
commercial, healthcare, education, retail and
leisure-based schemes. All of the projects
aimed to achieve high building research
establishment’s environmental assessment
method (BREEAM) ratings. BREEAM uses
environmental weightings to analyse a
building’s performance, accounting for all
the environmental impacts of a building’s
materials, design, operation management and
use (BRE, 2001). Exploring the waste
minimisation methods used on projects seeking
to achieve high BREEAM scores ensured that
the techniques were at the leading edge of
industry attempts to manage waste more
effectively.
The informants were asked to describe the
policies that they were responsible for
implementing and who has responsibility for
their operation and performance. They were
asked to comment on their effectiveness and
how they could be improved in future projects.
A set of 16 waste minimisation measures were
eventually refined as part of this exercise. These
were incorporated into a postal questionnaire
survey designed to elicit broader industry
opinion on the waste practices identified and
to discern the efficacy of those identified.
Respondents were asked to score each waste
measures based on their “ease of
implementation” and “impact” against a
five-point Likert scale. Aggregating the
implementation and impact scores allowed the
various waste measures to be ranked in order of
effectiveness. Of 45 questionnaires distributed
to waste management specialists, 27 were
returned (a response rate of 60 per cent).
The respondents comprised a relatively
well-stratified sample of specialist waste
management practitioners with direct
responsibility for the implementation of
minimisation measures throughout the supply
chain.
Results
The study results are presented below. First, the
overt waste strategies adopted on the case study
projects are discussed, followed by an analysis of
the questionnaire responses from experts asked
to assess the efficacy of these techniques.
Towards improved construction waste minimisation
Andrew R.J. Dainty and Richard J. Brooke
Structural Survey
Volume 22 · Number 1 · 2004 · 20–29
22
Waste minimisation measures adopted on
the case study projects
The interviews revealed a wide range of policies
and practices that had been initiated in an
attempt to reduce wastage levels on the five case
study projects. These are summarised as
follows.
Standardisation of design to improve buildability
and reduce the quantity of off-cuts
Standardisation has the potential to
dramatically reduce the current production of
construction waste. By designing room areas
and ceiling heights in multiples of standard
material sizes a substantial reduction in off-cuts
had been achieved.
Stock control measures to avoid the over ordering of
materials
Over-ordering of materials emerged as a
particularly significant area of site management
control leading to materials wastage. Tighter
stock control measures coupled to the careful
monitoring of on-site progress had helped to
reduce the amount of unnecessary waste.
Merely raising awareness of this issue amongst
site managers had demonstrably shown to
reduce waste levels in several of the case study
projects.
Improved education of the workforce
All of the informants agreed that the attitudes of
operatives accounted for a significant
proportion of on-site wastage. “Toolbox talks”
were a strategy used on most of the case study
projects to educate operatives in the benefits of
waste minimisation.
Supply chain alliances with suppliers/recycling
companies
This measure aimed at dealing with waste in the
most effective manner to reduce the impact
produced. Partnerships with suppliers had led
to excess materials being removed, reprocessed
and in some cases, reused. Such practices were
supported with financial incentives for waste
minimisation.
Provision of waste skips for specific materials
Centrally controlling skips for materials had
helped to promote a culture of material
segregation and recycling. Retaining
responsibility for waste management also
allowed the principal contractor to maintain
control over removal of waste and recovering
costs through recycling.
Just-in-time delivery strategy
Reducing the time that materials were stored on
site reduced the potential for damage from poor
handling and elements. Adopting a just-in-time
delivery strategy had eliminated long-term site
storage as well as reducing the potential for
over-ordering materials on several projects.
Dedicated specialist sub-contract package for on-site
waste management
On one project, logistics contractors had been
appointed to provide a waste management
service. Under this scheme, the specialist firm
then removed waste from these designated
areas, with timber, precious metals and organic
materials being separated for reuse. This
significantly reduced the waste sent to landfill,
provided the principal contractor with more
control over waste processes and devolved some
of the responsibility for managing waste to trade
contractors.
Contractual clauses to penalise poor waste
performance
All interviewees agreed that contractual
penalties were a good idea in principle. The
contracts included measurement benchmarks
linked to specific financial penalties for wasteful
work practices. By requiring each trade
contractor to provide monthly data on waste
disposal, this provided a transparent audit of
where waste was being generated in order that it
could be avoided on future projects.
Design management to prevent the over specification
of materials
Avoiding over specification was identified as
offering considerable scope for financial savings
on all of the case study projects. The
appointment of dedicated design managers with
a brief to minimise waste was seen as a proactive
and effective step in ensuring waste reduction.
Allowing more time for value engineering
design solutions was also seen as important for
more complex projects.
Additional tender premiums where waste initiatives
are to be implemented
Many construction companies cited initial
set-up costs as the main reason for not
implementing comprehensive waste
Towards improved construction waste minimisation
Andrew R.J. Dainty and Richard J. Brooke
Structural Survey
Volume 22 · Number 1 · 2004 · 20–29
23
minimisation system. More companies may be
willing to invest in waste initiatives if financial
subsidies were provided as an incentive. One
client had invited tendering contractors to build
in a transparent sum to cover the costs of waste
minimisation strategies.
Waste auditing to monitor and record environmental
performance on-site
Information collected through auditing and
monitoring had been used both to monitor the
performance of on-site practices and to educate
the workforce on the benefits of waste
minimisation practices. Several case study
projects audited waste internally, and one had
adopted the BRE’s “site methodology to audit,
reduce and target waste” (SMARTWaste)
management system. This provided a detailed
reporting tool, and included actions to reduce
waste and establish the potential for cost savings
(BRE, 2004).
Increased use of off-site prefabrication to control
waste and damage
Prefabrication uses the factory environment to
provide greater control over construction
processes. This has shown to provide benefits in
work quality and this ideology can be
introduced to control waste and provide
tangible reductions in waste levels.
Prefabrication reduces the amount of on-site
damage, reducing re-work and waste. The
increased use of prefabricated components
demands the careful modularisation of the
building design, which had been successfully
applied to aspects of the case study projects.
On-site materials compactors
A study by one of the case study companies had
found that 60-70 per cent of full skips actually
comprised air voids. Although there is little
improvement in environmental performance
(as the same amount of material was still being
wasted), reducing the volume had led to
considerable savings in transport costs.
A materials compactor was therefore being
used for material to be sent to landfill.
Educate clients about measures to reduce waste levels
Most case study participants agreed that many
clients remain under informed about the
severity of construction waste or the potential
for the reuse and recycling of materials.
Education programmes were being used on
some projects to ensure that the client
understood the need for process and attitudinal
change and that would encourage them to
influence waste conscious design and
construction practices from the inception of
projects.
Supplier flexibility in providing smaller quantities of
materials
Providing smaller quantities of materials
reduced the needs for on-site storage and the
opportunities for damage to occur on-site.
Encouraging supplier flexibility in producing
materials to project specifications had led to
considerable savings on two of the case study
projects. The informants generally believed that
supplier flexibility was integral to waste
minimisation.
Environmental impact assessments of the scheme
during the design phase
One case study had shown the benefit of
conducting regular design and production
reviews where the waste minimisation strategies
were considered as a primary performance
criterion. This had been incorporated as part of
the design development process that ensured
that the building met the client’s criteria.
Questionnaire results
The questionnaire commenced with questions
on the respondents’ perceptions of the severity
and causality of construction waste, before the
respondents were asked to score the waste
minimisation measures identified from the
case study projects outlined earlier. The postal
questionnaire results are summarised below.
The severity and causality of construction
waste
Every respondent believed that construction
industry waste is currently excessive.
Although this finding underscores the
importance of developing new and more robust
waste minimisation strategies, only 11 per cent
of respondents believed that projects commit
sufficient resources to managing waste
minimisation. In addition, over 60 per cent
believed that more needed to be done to
improve waste minimisation across the industry
as a whole. In terms of the principal causes of
Towards improved construction waste minimisation
Andrew R.J. Dainty and Richard J. Brooke
Structural Survey
Volume 22 · Number 1 · 2004 · 20–29
24
waste, over 80 per cent of respondents
suggested that poor site management was a
primary cause of construction waste.
Materials management, quality control, and
co-ordination of works were areas cited as
particularly significant. This suggests that a high
proportion of waste is caused by inadequate
measures by management compared to direct
on-site operations. Opinions were more varied
in terms of who should take responsibility for
minimising construction waste within the
construction supply chain. All stakeholders
were seen as having a role to play, including
clients, principal contractors, trade/specialist
subcontractors, suppliers and delivery firms.
This points to a need for supply chain solutions
to the industry’s waste problems.
Effectiveness of waste minimisation
measures
The respondents were asked to score a range of
waste minimisation measures against a five-
point Likert scale. Table I shows the mean
scores for both their ease of implementation and
their likely impact, along with an aggregated
total score for each measure. The results show
that all of the measures could have a positive
impact (indicated by a mean score of over 2.5 on
the Likert scale). This suggests that all have
merit in addressing waste issues in the
design/production processes and should yield
benefits as part of an overall waste minimisation
framework. However, there was a significant
distinction between the various measures when
viewed in relation to the mean scores given to
each measure. Figure 1 shows the distribution
of waste measures according to their scores on
the impact and ease of implementation
measures. Those above the higher line were seen
as being effective and relatively easy to
implement. They represent the favoured waste
minimisation solutions and comprise those
most likely to be utilised as part of a robust
waste minimisation strategy. Those below the
lower line were seen as more problematic to
utilise and having a lower overall impact.
The highest ranked strategy was “Supply
chain alliances with suppliers/recycling
companies”. Alliances do not necessarily reduce
the volume of waste, but should reduce the
amounts being sent to landfill. The second
and third ranked solutions were “Increased
off-site prefabrication to control waste and
damage” and “Standardisation of design to
improve buildability and reduce the quantity of
off-cuts”. These are examples of practices that
can have a direct impact on the levels of waste
produced. Specification of standard sizes
prevents waste from being created and therefore
remedial measures would be unnecessary.
The fourth ranked measure was “Stock control
measures to avoid the over ordering of
materials”. This suggestion incorporated the
use of more just in time and lean production
methods in order to reduce storage and excess
materials. At the other end of the scale, the
lowest ranked waste measure was surprisingly
the introduction of a Environmental impact
assessments of the scheme during the design phase.
The interviewees suggested that designers
would be unlikely to consider waste a high
enough priority to fundamentally alter design
concepts.
Discussion: the need for supply chainsolutions to waste management
Although these results are based on a small
sample of projects and industry opinion, they
reveal the types of techniques and solutions to
waste that are being utilised by the industry on
major, high profile projects. The sample of case
study projects provided a mixed picture as
regards current waste practices and
performance. Some projects were excellent in
their waste prevention and removal strategies,
whilst others had failed to make considerable
inroads to reduce the amounts of waste.
Nevertheless, the case studies showed that
where waste minimisation systems were
introduced, these were generally successful
providing that adequate financial and logistical
support was provided and that all participants
were committed to the project.
It was interesting to note that, contrary to the
inference within much of the waste
management literature, the case study projects
had well-developed strategies for dealing with
waste at all stages of the project lifecycle.
Indeed, the results suggest that a wide range of
minimisation techniques are currently utilised
in combination by large construction
organizations. The range and diversity of the
strategies demonstrate a high level of innovation
Towards improved construction waste minimisation
Andrew R.J. Dainty and Richard J. Brooke
Structural Survey
Volume 22 · Number 1 · 2004 · 20–29
25
in attempting to reduce unnecessary wastage
from high profile projects. The questionnaire
results reveal that the measures used are
effective and generally easy to implement.
Case study projects also recorded a positive link
between good site waste management and
productivity, site safety and ultimately profit
margins.
The three most effective waste management
solutions are interesting insofar as they present
Table I Ranking of waste measures identified
Rank Potential waste measure Implementation Impact Average
1 Supply chain alliances with suppliers/recycling companies 3.6 3.9 3.8
2 Increased off-site prefabrication to control waste
and damage
3.5 3.9 3.7
3 Standardisation of design to improve buildability
and reduce the quantity of off-cuts
3.3 4.0 3.7
4 Stock control measures to avoid the
over ordering of materials
3.6 3.4 3.5
5 Improved education of the workforce 3.4 3.5 3.5
6 Provision of waste skips for specific
materials
3.4 3.5 3.5
7 Just-in-time delivery strategy 3.2 3.6 3.4
8 Dedicated site team or specialist sub-contract
package for on-site waste management
2.9 3.7 3.3
9 Contractual clauses to penalise for poor
waste performance
3.0 3.3 3.2
10 Design management to prevent the over
specification of materials
3.2 3.1 3.2
11 Additional tender premiums where waste initiatives
are to be implemented
3.3 3.0 3.2
12 Waste auditing to monitor and record
environmental performance on-site
3.3 2.9 3.1
13 On-site materials compactors 3.2 2.9 3.1
14 Educate clients about measures to reduce
waste levels
2.7 2.9 2.8
15 Supplier flexibility in providing small quantities
of materials
2.5 2.9 2.7
16 Environmental impact assessments of the scheme
during the design phase
2.8 2.5 2.7
Figure 1 Expert assessment of the waste management measures identified
Towards improved construction waste minimisation
Andrew R.J. Dainty and Richard J. Brooke
Structural Survey
Volume 22 · Number 1 · 2004 · 20–29
26
supply chain solutions for managing
construction waste. The development of
alliances with suppliers and recycling companies
accords well with the current emphasis on
forming partnerships to improve performance.
Extending this to suppliers and secondary users
of waste materials seems logical and mutually
beneficial for all involved and represents a
relational attempt to minimise wastage. The
increased use of off-site fabrication to control
waste and damage represents a fundamental
shift towards bringing about an end to some
traditional on-site working practices. Again, it
seems logical that manufacturing in an off-site
environment should reduce the waste lost
on-site, and this represents a business process-
related attempt to minimise wastage. Finally,
the use of standardisation to improve
buildability and reduce the quantity of off-cuts
represents a product-oriented attempt to
address the waste issue. This is complementary
to the increased use of off-site fabrication in that
it involves designing out wasteful activities
within the construction process. It is interesting
to note that these measures were ranked more
highly than the espoused fundamental issue of
client involvement and workforce education.
Reasons as to why these issues were not more
prominent remain speculative, although they
may relate to the fact that main contractors,
designers and clients would rather mediate
waste through the sphere of influence provided
by their contractual control of their supply
chains.
It is noticeable that the three most popular
waste minimisation strategies attempted to
remove waste at source and deal with waste as it
is produced on-site. This reflects the fact that
there is scope to remove the waste throughout
the design and specification phases of a project
within what could be termed “waste
minimisation partnerships”. By working
together to integrate waste minimisation
strategies, project stakeholders could generate
considerable improvements in waste reduction.
Questions remain, however, as to whether the
industry is culturally prepared for the
collaborative relationships necessary to
engender radical improvements in waste
minimisation performance. It demands that all
stakeholders recognise the crucial importance of
reducing the industry’s contribution to landfill
and integrate their work practices to address the
situation.
Conclusions
The aim of this study was to evaluate a range of
waste minimisation practices currently being
used within large, technically complex
construction projects and to identify those with
the potential to be applied to other similarly
complex schemes. Contrary to expectations,
participants revealed the use of a fairly
sophisticated range of supply chain measures
for managing waste levels. Waste is being
reduced through the careful consideration of
the need for minimisation and better reuse of
materials in both the design and construction
phases. Whilst every project is different in
terms of volumes of waste produced, types of
waste, management of waste, and responsibility
for waste, there remain underlying principles of
effective waste management which can lead to
more appropriate solutions in most projects.
The findings reveal that the most effective
measures are those which seek to develop
alliances with suppliers and recycling
companies to remove materials from site more
efficiently, the increased use of off-site
fabrication to control waste and damage and
the greater standardisation of design to
improve buildability and reduce the quantity of
off-cuts.
Together, the solutions identified provided a
range of practical solutions to address the
challenges of reducing landfill disposal.
However, it is important to note that every
project is different in terms of the volumes of
waste produced, the types of waste generated,
the management practices used and the
apportionment of responsibility for waste
control. Thus, the research suggests that for
waste minimisation to be effective, each project
needs to consider these systems individually;
not all 16 waste measures will be practicable on
every project. Notwithstanding this, the waste
measures identified break down the complex
issue of waste management into a set of more
manageable generic processes, where
responsibility can be designated and parties
made accountable for implementing aspects of
the waste strategy.
Towards improved construction waste minimisation
Andrew R.J. Dainty and Richard J. Brooke
Structural Survey
Volume 22 · Number 1 · 2004 · 20–29
27
Finally, it is important to note that any waste
strategy requires adequate management
resources to oversee and enforce its
implementation, which in turn requires that
contractors see the reduction of waste as a core
priority with tangible benefits for their business.
The challenge to the industry is how to embed
the types of waste minimisation schemes from
high profile projects such as those investigated
to the wider construction environment, where
waste minimisation may not be given such a
high priority. The main concern is to overcome
the widely held perception that waste is
inevitable, and to embed the importance of
waste reduction as a key performance criterion
throughout the supply chain. The solutions
identified are unlikely to be effective unless
implemented as part of an integrated
minimisation strategy. Each project stakeholder
must be involved and committed to waste
minimisation as part of an integrated supply
chain. Clients must demand better waste
performance from their principal contractors
who should communicate this to their
subcontractors and suppliers. Specialist trade
contractors must take on responsibility for
implementing trade waste measures suited to
their particular package in a way that integrates
them with other measures undertaken by other
project participants. It is clear that the more
specific the measures (and transparent the
accountability for their implementation), the
more significant the improvements are likely
to be.
References
Bossink, B.A.G. and Brouwers, H.J.H. (1996), “Constructionwaste: quantification and source evaluation”, Journalof Construction Engineering andManagement, Vol. 122No. 1, pp. 55-60.
BRE (2001), BREEAM Offices 2003: Design and ProcurementAssessment Checklist, available at: http://products.bre.co.uk/breeam/BREEAM_May2003/pdf%20documents/DPPredictionChecklist2003.pdf (viewed May 2003).
Building Research Establishment (2004), THE SMARTWasteeSYSTEM, available at: http://www.smartwaste.co.uk/(viewed January 2004).
Construction Industry Research and Information Association(1995), Waste Minimisation and Recycling inConstruction – A Review, CIRIA Special Publication122, London.
Construction Industry Research and Information Association(1999), Waste Minimisation and Recycling in
Construction – Boardroom Handbook, CIRIA SpecialPublication 135, 0-86017-320-8, London.
Coventry, S. et al. (2001), Demonstrating Waste MinimisationBenefits in Construction, CIRIA Publication C536,0-86017-536-7, London.
Craven, D.J., Okraglik, H.M. and Eilenberg, I.M. (1994),“Construction waste and a new design methodology”,in Kibert, C.J. (Ed.), Sustainable Construction, Centerfor Construction and Environment, Gainesville, FL,pp. 89-98.
Department of the Environment, Transport and theRegions (2000a), Building a Better Quality of Life –A Strategy for More Sustainable Construction, DETR,London.
Department of the Environment, Transport and the Regions(2000b), Guide to Waste Reduction on ConstructionSites, DETR, M0007184NP, London.
Faniran, O.O. and Caban, G. (1998), “Minimising waste onconstruction project sites”, Engineering Constructionand Architectural Management 5, Vol. 2, p. 183.
Ferguson, J., Kermode, N., Nash, C.L., Sketch, W.A.J. andHuxford, R.P. (1995), Managing and MinimisingConstruction Waste – A Practical Guide, Institution ofCivil Engineers, London.
Gavilan, R.M. and Bernold, L.E. (1994), “Source evaluation ofsolid waste in building construction”, Journal ofConstruction Engineering and Management, Vol. 120No. 3, pp. 536-55.
Graham, P.M. and Smithers, G. (1996), “Construction wasteminimisation for Australian residential development”,Asia Pacific Construction Management Journal, Vol. 2,pp. 14-19.
Johnston, H. and Mincks, W.R. (1995), “Cost effective wasteminimization for construction managers”, CostEngineering, Vol. 37 No. 1, pp. 31-40.
Lawson, N., Douglas, I., Garvin, S., McGrath, C., Manning, D.and Vetterlein, J. (2001), “Recycling construction anddemolition wastes – a UK perspective”, EnvironmentalManagement and Health, Vol. 12 No. 2, pp. 146-57.
Lingard, H., Graham, P. and Smithers, G. (2000), “Employeeperceptions of the solid waste management systemoperating in a large Australian contractingorganization: implications for company policyimplementation”, Construction Management andEconomics, Vol. 18 No. 4, pp. 383-93.
McDonald, B. and Smithers, M. (1998), “Implementing awaste management plan during the construction phaseof a project: a case study”, Construction Managementand Economics, Vol. 16, pp. 71-8.
McGrath, C. and Anderson, M. (2000), “Waste minimisationon a construction site”, Building ResearchEstablishment Digest no. 447.
Mills, T.H., Showalter, E. and Jarman, D. (1999), “A costeffective waste management plan”, Cost Engineering,Vol. 41 No. 3, pp. 35-43.
Ngowi, A.B. (2001), “Creating competitive advantage byusing environmental-friendly building processes”,Building and Environment, Vol. 36 No. 3, pp. 291-8.
Pinto, T. and Agopyan, V. (1994), “Construction wastes asraw materials for low cost construction products”,in Kibert, C.J. (Ed.), Sustainable Construction, Centre
Towards improved construction waste minimisation
Andrew R.J. Dainty and Richard J. Brooke
Structural Survey
Volume 22 · Number 1 · 2004 · 20–29
28
for Construction and Environment, Gainesville, FL,pp. 335-42.
Poon, C.S. (1997), “Management and recycling of demolitionwaste in Hong Kong”, Waste Management andResearch, Vol. 15, pp. 561-72.
Spivey, D.A. (1974), “Construction solid waste”, ASCE Journalof the Construction Division, Vol. 100, pp. 501-6.
Teo, M.M.M. and Loosemore, M. (2001), “A theory of wastebehaviour in the construction industry”, ConstructionManagement and Economics, Vol. 19 No. 7, pp. 741-51.
Treloar, G.J., Guptar, H., Love, P.E.D. and Nguyen, B.(2003), “An analysis of factors influencingwaste minimisation and use of recycledmaterials for the construction of residentialbuildings”, Management of EnvironmentalQuality: An International Journal, Vol. 14 No. 1,pp. 134-45.
Turner, R.K. and Powell, J. (1991), “Towards an integratedwaste management strategy”, EnvironmentalManagement and Health, Vol. 2 No. 1.
Towards improved construction waste minimisation
Andrew R.J. Dainty and Richard J. Brooke
Structural Survey
Volume 22 · Number 1 · 2004 · 20–29
29