Roll No. ...................... TotalNo. of Questions: 09] - . [Total No. of Pages: 03 B.Tech. -(Sem. - 7th/8th) , MATERIAL HANDLING & PLANT LAYOUT SUBJECT CODE: DE/PE - 2.9 (Elective) , Paper ID : IA0236] - [Note: Please fill subject code and paper" ID on OMR] Time: 03 Hours Instruction to Candidates: ! Maximum Marks: 60 QJ) . a) 1) 2) 3) Section - A is Compulsory. Attempt any Four questions from Section - B. Attempt any Two questions from Section - C" Section - A (10 x2 = 20) Describe briefly the guiding fundamentals of plant layout? b) , Enumerate the three fundamental requirements of Line Production systems. ' List four characteristic features of the following material handling equipmellt: Gantry Crane. >. Explain briefly the considerations affecting plant location decision in an organization. c) d) e) f) How material handling activity is related to plant layout? Enumerate the safeguards required for ensuring the safety of waiting materials. g) Describe the criterion for designing and providing optimum storage area in the plant layout. Enumerate the situations under which the, fixed path material handling equipments are preferred over the variable path floor operated systems. h) i) j) Explain briefly various fas;tors affecting scheduling, Enumerate the situations under which the overhead material handling equipments are preferred over the conventional floor operated systems. ~f-957 [1859/ P.T.O.

Total No. of Questions: 09] B. Tech. -(Sem. 7th/8th ...librarian/Question Papers/Q-PAPERS 2009/B.TEC... · MATERIAL HANDLING & PLANT LAYOUT SUBJECT CODE: DE/PE-2.9, (Elective)

  • Upload
    dodang

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

Roll No. ......................

TotalNo.of Questions: 09] -. [Total No. of Pages: 03

B.Tech. -(Sem. - 7th/8th) ,

MATERIAL HANDLING & PLANT LAYOUT

SUBJECT CODE: DE/PE - 2.9 (Elective),

Paper ID : IA0236] -

[Note: Please fill subject code and paper" ID on OMR]

Time: 03 Hours

Instruction to Candidates: !

Maximum Marks: 60

QJ)

. a)

1)

2)

3)

Section -A is Compulsory.

Attempt any Four questions from Section - B.

Attempt any Two questions from Section - C"

Section - A

(10 x 2 =20)

Describe briefly the guiding fundamentals of plant layout?

b),

Enumerate the three fundamental requirements of Line Productionsystems.'

List four characteristic features of the following material handlingequipmellt:Gantry Crane. >.

Explain briefly the considerations affecting plant location decision in anorganization.

c)

d)

e)

f)

How materialhandling activity is related to plant layout?

Enumerate the safeguards required for ensuring the safety of waitingmaterials.

g) Describe the criterion for designing and providing optimum storage areain the plant layout.

Enumerate the situations under which the, fixed path material handling

equipments are preferred over the variable path floor operated systems.h)

i)

j)

Explain briefly various fas;tors affecting scheduling,

Enumerate the situations under which the overhead material handling

equipments are preferred over the conventional floor operated systems.

~f-957 [1859/ P.T.O.

Section - B(4 X 5 =20)

Q2) Explain briefly the principlesof materials handling.Also explain the symptomsof inefficient material flows in a facility & causes of poor material flows in afacility. .

Q3) Describe the characteristicfeatures, advantagesand limitationsof the followingtypes of layouts:

(a) Process Layout,

(b) Product Layout,

(c) CellularLayout.

Q4) Given the followinginfonnation for a plant layout. Evaluate the existing layout.and suggest a proposed layout with minimummaterials handling.

I~90'

T60'

1~I

Q5) Explain the need'for a new plant location and factors affecting choice of plantlocation. Discuss briefly the different approaches for making the plant locationdecision.

Q6) What is the need for production planning and control in an organization?Differentiate between Centralized and decentralized production planning andcontrol.

i~f-957 2

Trips between Departments

Department 1 2 3 4 5 6

I. Butt and grind. 20 20 80

2. NCequipment . 10 75

3. Shippingand receiving. 15 90

4. Lathes and drills w- 70

5.Toolcrib -

6. Inpection-

2 4 3

6 5 1

Section - C(2 X 10 =20)

Q 7) A manufacturing company wants to design a repetitive production system toproduce one of its products. The production process requires (14) tasks thatare listed in the table given below, along-with estimated task times &predecessors for each task. The company wants to produce at least 270 unitsof product per day. It expects the produc.tion lin.eto operate 450 minutes peJ~y .

(a) Draw a precedence diagram for the tasks & compute maximum cycletime, theoretical minimum number of workstations, balance efficiency &smoothness index using Rank Positional Weight Heuristic.

(b) Compute the actual output per day that would occur with the line balancethus achieved & work out the efficiency of the production line.

(c) Can you suggest any further improvement?

..

Q8) (a) Explainthe working and construction of any two of the following materialhandling equipme11ts:Belt conveyor, Fork Lift trucks, Crawler cranes.

(b) Describe brieflythe variousvisualization aids commonlyused in planningthe plant layout showing the relative comparison between the variousvisualizationaids.

Q9) (a) Give a brief account of various scheduling heuristics used for jobsequencing in job shop scheduling. Why does SPT (Shortest ProcessingTime) rule perfonn so well for a job shop where jobs are arriving randomlyover time? Is there any limitation of using SPT rule?

(b) Explain the various methods for comparing alternative layouts in planningthe plant layout. Explain briefly the role of various qualitative parameters

in obtaining the optimiz~d layout.

~~~

~J-957 3

Task A B C D E F G H I J K L M N

Task Time (Seconds) 10 25 10 35 65 35 30 20 45 50 20 40 30 70

Predecessor Task -- -- -- A B,CA,E -- D,G A -- -- J,KA,LF,H,I,M