Top Down Technique by Parag Kesalkar

Embed Size (px)

Citation preview

  • 8/9/2019 Top Down Technique by Parag Kesalkar

    1/17

    TOP

    DOWN TECHNIQUE

    IN CONSTUCTION

    Parag P.kesalkar

    M0910C04

  • 8/9/2019 Top Down Technique by Parag Kesalkar

    2/17

    INTRODUCTION

    n In this method, the underground retaining walls are firstinstalled. In most cases, these retaining walls are concretediaphragm walls. This is followed by excavation to just belowthe roof slab level of the underground structure, with the

    retaining walls and struts supporting the soil at the sides. Theroof slab is then constructed, providing a massive supportacross the excavation. Access openings on the roof slab areprovided so that works thereafter could proceed downwards tothe base slab level of the underground structure. Upon

    completion of the base slab, the side walls are constructed andthe intermediate struts are progressively removed. The accessopenings on the roof slab are then sealed and the ground issubsequently backfilled and reinstated.

  • 8/9/2019 Top Down Technique by Parag Kesalkar

    3/17

    INSTALLATION OF RETAINING

    WALLn The underground retaining wall, which is usually a concrete

    diaphragm wall, is installed before excavation commences.

  • 8/9/2019 Top Down Technique by Parag Kesalkar

    4/17

    INSTALLATION OF RETAINING

    WALL- DIAPHRAGM WALLn The following pictorial guide illustrates the construction

    sequence of a typical diaphragm wall. This type of retaining

    wall was used for the construction of underground station in

    delhi.

  • 8/9/2019 Top Down Technique by Parag Kesalkar

    5/17

    01 .Construction of Guide Wall

    n A guide wall is constructed to set out the position of the

    diaphragm wall.

  • 8/9/2019 Top Down Technique by Parag Kesalkar

    6/17

    02 .Excavation of Panel

    n The grab/trench cutter cuts and removes the soil to form the

    panel. The excavation is stabilized by filling it with bentonite

    slurry to support the wall of the excavation.

  • 8/9/2019 Top Down Technique by Parag Kesalkar

    7/17

    03 .Installation of Rebar Cage

    n The crane lifts up the reinforcement-bar cage and places it

    within the panel.

  • 8/9/2019 Top Down Technique by Parag Kesalkar

    8/17

    04 .Concreting of Panel & wall.

    n Concrete is poured into the panel to form the panel wall.n Process 2 - 4 repeats for the remaining soil in between

    the panels till the entire length of the diaphragm wall

    construction is completed.

  • 8/9/2019 Top Down Technique by Parag Kesalkar

    9/17

    Excavation & Installation of Steel Strut

    n The soil is excavated to just below the roof slab level ofthe underground structure. Struts are installed to supportthe retaining walls, which in turn support the soil at the

    sides.

  • 8/9/2019 Top Down Technique by Parag Kesalkar

    10/17

    Construction of Underground Structure

    n The roof slab is constructed, with access openings provided onthe slab for works to proceed downwards. The roof slab not onlyprovides a massive support across the excavation, it also acts asa noise barrier.

  • 8/9/2019 Top Down Technique by Parag Kesalkar

    11/17

    Construction of Underground Structure

    n The next level of slab is constructed, and this process

    progresses downwards till the base slab is completed .

  • 8/9/2019 Top Down Technique by Parag Kesalkar

    12/17

    Construction of Underground Structure

    n The side walls are constructed upwards, followed byremoval of the intermediate struts. The access openingson the roof slab are then sealed.

  • 8/9/2019 Top Down Technique by Parag Kesalkar

    13/17

    Backfilling & Reinstatement

    n After the underground structure is completed, the soil isbackfilled to the top strut level before the strut is removed. This isfollowed by completely backfilling the top of the undergroundstructure and finally reinstating the surface areas.

  • 8/9/2019 Top Down Technique by Parag Kesalkar

    14/17

    CONSTRUCTION OF ROOF SLAB

  • 8/9/2019 Top Down Technique by Parag Kesalkar

    15/17

    UNDERGROUND EXCAVATION

  • 8/9/2019 Top Down Technique by Parag Kesalkar

    16/17

  • 8/9/2019 Top Down Technique by Parag Kesalkar

    17/17

    n Thank u