71
M/s. MMP BRICKS (KALBEABBAS PANJVANI) Block No. 113, Village – Chuli, Tal – Dediapada, Dist.- Narmada-393040. (M) 9624160117, Email: [email protected] MMPB/DEAC/EC/01/2019 Date: 22/06/2019 To, District Level Expert Appraisal Committee (DEAC), The Geologist, Department of Geology & Mining, Collectorate Compound, Bharuch. Subject: Application for Environmental Clearance for the Ordinary (Ordinary Bricks) Clay Mines Admeasuring 01.64.35 Ha. At Block No: 113, Village-Chuli, Tal.: Dediapada, Dist.: Narmada-393040. Respected Sir, With reference to the above subject and circular form MoEF “In case of mining activity at any less than 5 ha lease areas require Environmental Clearance form DEIAA as per MoEF Circular Dated – 15/01/2016”. We require obtaining the Environmental Clearance. We herewith apply (in Form-1M) for environmental clearance with the Form – 1M, prefeasibility study report, Project details and other supporting documents. We request your good selves to kindly consider our case in earliest committee meeting and grant us the recommendation / Environmental Clearance. Thanking You, Sincerely Yours, For MMP BRICKS. Authorised Signature Kalbeabbas Panjvani Proprietor

To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

  • Upload
    others

  • View
    2

  • Download
    1

Embed Size (px)

Citation preview

Page 1: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

M/s. MMP BRICKS (KALBEABBAS PANJVANI) Block No. 113, Village – Chuli,

Tal – Dediapada, Dist.- Narmada-393040. (M) 9624160117, Email: [email protected]

MMPB/DEAC/EC/01/2019 Date: 22/06/2019 To, District Level Expert Appraisal Committee (DEAC), The Geologist, Department of Geology & Mining, Collectorate Compound, Bharuch.

Subject: Application for Environmental Clearance for the Ordinary (Ordinary Bricks) Clay Mines Admeasuring 01.64.35 Ha. At Block No: 113, Village-Chuli, Tal.: Dediapada, Dist.: Narmada-393040.

Respected Sir, With reference to the above subject and circular form MoEF “In case of mining activity at any

less than 5 ha lease areas require Environmental Clearance form DEIAA as per MoEF Circular

Dated – 15/01/2016”. We require obtaining the Environmental Clearance. We herewith apply (in Form-1M) for environmental clearance with the Form – 1M,

prefeasibility study report, Project details and other supporting documents. We request your good selves to kindly consider our case in earliest committee meeting and

grant us the recommendation / Environmental Clearance. Thanking You, Sincerely Yours,

For MMP BRICKS.

Authorised Signature Kalbeabbas Panjvani Proprietor

Page 2: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

FORM-1M

APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY ‘B2’ FOR LESS THAN TO FIVE HECTARE

Basic information

Sr. No. Item Details

M/S. MMP BRICKS

1 Name of the Project (01.64.35 ha)

Ordinary Clay Mining at Block No.–113,

Village- Chuli,

TaL: Dediapada , Dist: Narmada-393040.

1 21°31'05.73"N 73°31'30.22"E

2 21°34'08.31"N 73° 31'36.21"E

3 21°34'01.06"N 73° 31'29.94"E

4 21°34'02.81"N 73° 31'30.82"E

2 Location / site (GPS Co-

ordinates):

3 Size of the Mining Lease 01.64.35 ha

(Hectare):

4 Capacity of Mining Lease (TPA): 35000 TPA

5 Period of Mining Lease: 5 Years

6 Expected cost of the Project: 7.5 Lacs

7 Contact Information: Mr. Kalbeabbas Panjvani (Proprietor)

Ordinary Bricks Mining Clay

Village: Chuli ,Tal: Dediapada, Dist: Narmada-393040.

Page 3: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

Environment Sensitivity SI No Areas Distance in Kilometer

1 Distance of project site from nearest rail or road bridge

Karjan River – 0.19 KM

over the concerned River, Rivulet, Nallah etc.

Distance from infrastructural facilities Chuli – 0.42 km.

Railway line Ankleshwar railway station 54.7km.

National Highway NH-08 – 54.1 km

State Highway SH-13 (Bedakampni-Dediapada)-4.7km

2 Major District Road No

Any other Road Chuli village road – 0.32 KM

Electric transmission line pole or tower Not Applicable

Canal or check dam or reservoirs or lake or ponds NO

In-take for drinking water pump house Not Applicable

Intake for Irrigation canal pumps Not Applicable

Areas protected under international conventions, national Not Such area available within 15

3 or local legislation for their ecological, landscape, cultural

km.

or other related value

Areas which are important or sensitive for ecological Not Such area available within 15

4 reasons - Wetlands, watercourses or other water bodies,

km.

coastal zone, biospheres, mountains, forests

Areas used by protected, important or sensitive species of Not Such area available within 15

5 flora or fauna for breeding, nesting, foraging, resting, over

km.

wintering, migration

6 Inland, coastal, marine or underground waters Not Applicable

7 State, National boundaries Not Such area available within 15

km.

8 Routes or facilities used by the public for access to Not Applicable

recreation or other tourist, pilgrim areas

9 Defence installations Not Applicable

10 Densely populated or built-up area, distance from nearest

Chuli – 0.42 km.

human habitation

11 Areas occupied by sensitive man-made land uses

Chuli Primary School:0.42 km.

(hospitals, schools, places of worship, community acilities)

Areas containing important, high quality or scarce

12 resources (ground water resources, surface resources, Not Applicable

forestry, agriculture, fisheries, tourism, minerals)

Areas already subjected to pollution or environmental

13 damage. (those where existing legal environmental Not Applicable

standards are exceeded)

Areas susceptible to natural hazard which could cause the

14 project to present environmental problems (earthquakes,

Not Applicable

subsidence, landslides, erosion, flooding or extreme or

adverse climatic conditions)

Page 4: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

15 Is proposed mining site located over or near fissure / No. Not Applicable

fracture for ground water recharge

Whether the proposal involves approval or clearance

under the following Regulations

or Acts, namely:-

(a) The Forest (Conservation) Act, 1980;

16 Not Applicable

(b) The Wildlife (Protection) Act, 1972;

(c) The Coastal Regulation Zone Notification, 2011.

If yes, details of the same and their status to be given.

17 Forest land involved (hectares) Not Applicable

Whether there is any litigation pending against the project

and/or land in which the project is propose to be set up?

(a) Name of the Court

18 (b) Case No. Not Applicable

(c) Orders or directions of the Court, if any, and its

relevance with the proposed

project.

“I hereby given undertaking that the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance give, if any to the project will be revoked at our risk and cost.”

Date: 22-06-2019 Place: Dediapada, Narmada.

M/S. MMP BRICKS Mr. Kalbeabbas Panjvani

Village: Chuli, Tal.: Dediapada, Dist: Narmada.

Signature of the applicant With Name and Full Address

(Project Proponent/Authorized Signatory)

Page 5: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

PROJECT DETAILS – ORDINARY CLAY MINING PROJECTS

Sr. Details Particulars

No.

1 Name of Lease Holder M/S. MMP BRICKS

Mr. Kalbeabbas Panjvani

2 Location address

Block. No. 113,

Village- Chuli, Tal: Dediapada,

Dist: Narmada-393040.

1.64.35 hectare

Northing Easting

21°31'05.73"N 73°31'30.22"E

3 Lease Area (Hectares) 21°34'08.31"N 73° 31'36.21"E

Co-ordinates of the lease area 21°34'03.72"N 73° 31'37.98"E

21°34'01.06"N 73° 31'29.94"E

21°34'02.15"N 73° 31'29.58"E

21°34'02.81"N 73° 31'30.82"E

Please refer for coordinates map.

4 Ownership of Land Private land

(Govt. / Private Land)

Status of Operation (New Project or

5 Existing project operating since New Project

2011 )

Status of Lease (Lease no., date of Registration for excavation of mining clay

(bricks manufacturing) as per the

6 issues / renewal, lease period, date of existing rules of mining has been done at geology

application for lease renewal, etc.) and mining department.

7 Name of Mineral Ordinary Clay

8 Ordinary Clay Reserve (MT) 512000 MT

Page 6: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

9 Rate of Mining of Ordinary Clay

35000 MT/Year

(MT/Year)

10 Life of Mine 5 years

11 Weather project involves forest land, No, This project does not involve any forest land.

If yes, status of diversion of forest land

12 Applicability of CRZ notification,2011 Not applicable

ENVIRONMENTAL SETTING

13 If located within 15 km, aerial distance --

of the lease area from the nearest:

i. National Park / Wildlife None

Sanctuary / Biosphere Reserve

ii. Reserve Forest / Protected None

Forest:

iii. Human Habitation: Chuli Village – 0.42 km

iv. Railway Line: Ankleshwar Railway Station :- 54.7 Km

v. Road: SH-13 (Bedakampni-Dediapada)–4.7 km

vi. Notified / Protected None

Archaeological sites:

vii. Social infrastructures, e.g. School(Chuli) - 0.42 km

School, hospital, historic / Temple(Chuli) – 0.58 km

cultural / religious places etc.: Hospital(Didiapada) –9.27 km

Presently there is no land use for any activities.

After grant of lease and EC. proponent will start land

14 Present land use of lease area. use for mining activities. The mining method will be

open cast mining and there will be permanent

change in land pattern.

As observed from nearby wells water table level in

the area is at around 30-40 mts. Mining will not

15 Geo-Hydrological features reach up to that depth. Further There is no nallah

existing near the clay area. The rain water

collected in pit, which recharge the area

16 Predominant wind direction It was observed that wind direction is

predominantly from North & North East direction

Flora:

Details on riparian vegetation, Baval

17 endemic / endangered species of flora Fauna:

/ fauna in the area Cow, Buffalo, sheep, Goat, Camel

No endangered species of flora / fauna in the area.

18 Width and condition of access road ( 3.0 to 4.0 m aces road

pucca) to the lease area.

Page 7: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

DETAILS ON MINING / EXCAVATION ACTIVITIES

19 Requirement of Power supply and its No power requirement

source

20 Requirement of Water supply and its Requirement of water will be 18 KLD. and source is

source

bore well or local body nearby project area

21 Type of mining (Manual / Semi – Semi - mechanized

mechanized / Mechanized)

Equipment to be used (bulldozers, List of the equipment to be used.

22 hydraulic excavators, JCB, scrapers, 1. hydraulic excavators

loaders, diesel pumps, etc) 2. trolley mounted tractor

As it is open cast mining, manual as well as semi

mechanized methods will be used.

Ordinary Clay mining will be an open cast mining

Details of method of working with activity; in the first phase top soil will be removed

23 phasing of activates (sequence of and stacked for plantation purpose. Than

mining operations) overburden will be removed and stacked at

earmarked place.

24 Explosives, detonators to be used It is open cast mining project and there is no need to

use explosives and detonators.

25 Details of drilling, blasting No drilling, blasting is required.

Safety measures at the time of

26 blasting N.A

Over burden in lease area will be in the form loose

Details of Over Burden (OB) removal

top soil and weathered upper layer of rocks. The soil

27 excavated will be dumped & preserved in the area

and stacking ear marked for soil dump & the dumping will be

carried out in the phase banner upto the height of

3m. This preserved soil will be used for plantation.

Height and width of benches and its

28 slop Bench of height 1 mt will be prepared

Data of the CGWB (Central Ground Water Board) for

29 Depth of ground water table (Meters) ground water table is mentioned is about 40 to 100

mts.

30 Maximum depth of working (Meters) Maximum depth of working will be 3mts. No ground

weather it will intersect ground water water intersection will be made.

table

31 Land use pattern of the lease area Non agriculture area for clay mining

32 Man power Requirement 8 to 9 person

Page 8: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

33 No. of working days in year 250 days

34 Time of working hours in a day 6.00 AM. to 6.00 PM. / Sunrise to Sunset

ENVIRONMENTAL MANAGEMENT PLAN AND C.S.R. ACTIVITES

Measures proposed for protection of

35 environmental attributes like , riparian Please refer in prefeasibility report for proposed

vegetation, water, air , human health impacts and mitigation.

etc.

Measures for control of noise,

36 vibration and fly rock problems due to Blasting is not required

blasting

Mitigation:

Details on transportation route & • Water is sprayed periodically to wet the road.

37 measures proposed for control of • Plantation of trees along the roads to help reduce

fugitive emission during the impact of dust in the nearby villages.

transportation • PUC certified heavy vehicles will be used for

transportation.

Plan for tree plantation in riparian As per attached Environment Management Plan.

38 area / road sides in at least 20% of

lease area, numbers & types of species

and budgetary outlay for the same.

As per current mining plan there is no need for

39 Plan, if any, for restoration / restoration or reclamation of mine, however at the

reclamation end of entire mine of life, area mined out will be

reused for agriculture purpose.

The proposed project will generate employment

opportunity for the local inhabitants. As a part of

40 Proposed CSR Activities and budgetary CSR activity, the proponent will expend approx.

outlay for the same. Rs.9000.00 annually for medical checkup camp,

scholarship to school students, drinking water

cooler etc.

41 Provision of fencing the pits in case of NA

use as water reservoir

Plan for green belt development, area No green belt proposed. However plantation in

of green belt, no & types of species to lease area will be carried out as per attached

42 be planted and budgetary outlay for Environment Management Plan

the same

Date: 22/06/2019 Place: Dediapada, Narmada.

Signature of the Applicant (Kalbeabbas Panjvani)

Page 9: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With
Page 10: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

1

PREFEASIBILITY STUDY REPORT

For

ORDINARY CLAY MINING PROJECT

(MANUFACTURING OF BRICKS)

BY

M/S. MMP BRICKS

LOCATED AT

NARMADA

AT

Block No.113,

VILLAGE: CHULI,

TALUKA: DEDIAPADA,

DIST.:NARMADA-393040

JUNE 2019

Page 11: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

2

Sr. No.

INDEX

Section Details

Page No.

1 Details of Proposed Project 3 1.1 Need of the Project 3 1.2 Screening Category 3 1.3 Location of the Proposed Project 4 1.4 Process Technology 7 1.5 Product Details 8 1.6 Cost of Proposed Project 8 1.7 Permission from Authorities 8 1.8 Resources Requirement 8 1.8.1 Raw Material 8 1.8.2 Electricity 9 1.8.3 Water 9 1.8.4 Fuel 9 1.8.5 Man Power 9 1.8.6 Land 9 1.8.7 Equipment / Machinery / Vessel / Reactor 9 1.9 Pollution Potential 9 2 Anticipated impact based on project operations on receiving Environment 10 2.1 Population 10 2.2 Flora and Fauna 10 2.3 Water 10 2.4 Air 11 3 Mitigation Measures 13 3.1 Wastewater Treatment and Disposal 13 3.2 Air Pollution Control Measures 13 3.3 Noise Control Measures 14 3.4 Solid /Hazardous Wastes Management System 14 3.5 Greenbelt Development 15 3.6 Hazards and Safety Measures 15 3.6.1 Mining safety guide 16 3.6.2 Excavation 17 3.6.3 Transportation Safety 18 3.6.4 Haulage (Pulling & Shifting) 19 3.6.5 The key points to ensure safety 19 3.6.6 Good Housekeeping 19 4 Environment Management Plan 20

Page 12: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

3

1. Details of Proposed Project:

1.1. Need of the Project

The proposed mining project falls in the Narmada District of South Gujarat in the Gujarat State.

Gujarat is the one of the largest contributors of Industrial Growth in the nation.

The mining project will be done on Non–Agricultural land. For such type of mining project, the

survey is being carried out by Geology Department of government to evaluate the probable

reserve.

This natural clay from India are generally used in flooring, wall cladding, vanity tops and to pave

the floors of large commercial complexes, hospitals, airports, shopping malls, railway station, parks

etc.

1.2. Screening Category:

The mining of Bricks earth was not covered under environmental laws, since most of the bricks

earth extraction work in the country is having mining activities in area less than 5 hectares and

Ministry of Environment and Forests (MoEF), New Delhi had exempted areas less than 5 hectares

for obtain environmental clearance. Now as per MoEF office memorandum dated 18th May, 2012,

all the mining activities irrespective of the mining area are required to get Environmental

Clearance form them before starting any mining activity and as per Office memorandum dated

24th June, 2013 and No. J-13012/12/2013-IA-II (I) dated 24th December, 2013 the acitvityies of

borrowing/excavation of ordinary earth up to an area less than 5 hectares, comes under category

‘B2”. And Ministry of Environment and Forest and Climate change in pursuance of amendment

dated 15-01-2016 has issued a notification no. S.O. 190 (E) dated 20-01-2016 Annexure ‘II’

constitutes the District Level Environment Impact Assessment Authority (DEIAA), for grant of

Page 13: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

4

Environmental clearance for Category ‘B2’ Projects for mining of minor minerals, for all the

districts in the country.

As per EIA Notification 14th September, 2006 & O.M. No-L-11011/47/2011-IA.II (M) dated 24 th

June 2013 the proposed project falls under Schedule 1(a) & Category “B-2”.

As per MoEF office Memorandum no. L-11011/47/2011-IA.II (M) dated 24th

The activity associated with burrowing/excavation of brick earth and ordinary earth for

purposed of brick manufacturing, construction of road, embankments etc. shall not involve

blasting.

June 2013 following

conditions shall be followed during the mining activity:

The burrowing /excavation activity shall be restricted to a maximum depth of 2 M below

general ground level at the site.

The burrowing/excavation activity shall be restricted to 2 M above the ground water table

at the site.

A minimum distance of 15 m form any civil structure shall be dept form the periphery of

any excavation area.

1.3 Location of the Proposed Project:

Project location is at Block No. 113, Village-Chuli, Tal.: Dediapada, Dist.: Narmada-393040. The break-up of proposed Mining clay lease area is given as table no.1

Sr.No. Block No. Address of Mining location Area (Hectares)

Area (Sq.meter)

1 113 Village-Chuli, Tal.: Dediapada, Dist.: Narmada-393040.

1.64.35 16435

Page 14: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

5

The mining area is 01.64.35 Hectare Latitude 21.34’05.18” N & Longitude 73.31’32.93” E.

India

Gujarat

Narmada Location Site

Page 15: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

6

Location site:

Page 16: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

7

1.4 Process Technology (Manufacturing Process)

• Thorny bushes will be removed. Top soil should be removed and stored at boundary of the Mines. Remaining soil will be dig out and stored at the Mines site for refilling at the closer time.

• Earth-moving equipment such as scrapers and mechanical shovels are used to extract the clay. This clay is blending after transported from the pit by truck. The materials are stockpiled to enable blending of the various types of clay. The clays are fed separately by manually into mixing of clays follows to water addition.

• Than material is mixed in high-speed rollers which complete the grinding process. Bricks are hand formed, pressed or extruded into their final shape. The method used to shape the bricks affects their final appearance and texture, and sets certain limitations on the handling methods employed during manufacture. Wet clay bricks then pass though drying process.

• In the brick-making process, the clay is refined and water is added in order to mould the brick. Before the bricks can be fired, they must be dried properly in sun light to minimize the moisture up to 8% of volume for the clamp kiln. This wet bricks are fired in

conventional kiln process. Lignite is used as fuel. After complete the process, cool it & remove the finished bricks from the kiln. Generally next batch will be start after first batch.

• All around the excavated mines pit the Proper wire fencing is required to avoid falling of kids, cattle etc.

• Regular servicing of equipments/machineries will be carried-out to reduce Noise level.

Restoration Plan:

Including landscaping proposals, phasing and proposal for reuse of the area after quarrying or will be used as water reservoir and supply the water those who require.

Ancillary Work:

Transportation route will be marked for traffic regulation. Office building, stores for newly purchased spare parts as well as for used oil and tyre-tubes.

Page 17: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

8

1.5 Product Details:

Mining of Ordinary Clay area

SR NO.

.

NAME OF PRODUCTS QUANTITY

1 MINING OF ORDINARY CLAY

(ORDINARY BRIKCS)

35000 MT/YEAR

2916.6 MT/MONTHLY

1.6 Cost of Project

The approx cost of the proposed project will be Rs. 7.5 Lac.

The details of the cost of the project is given delow:

Land & Building and

Plant & Machinery Rs. 7.5 Lcas

1.7 Permission from Authorities: Details are given in attached documents.

1.8 Resources:

As the proposed project will be required resource for production. The details of the resources given hereunder,

1.8.1 Raw Material requirement

1.8.2 Electricity

1.8.3 Water

1.8.4 Fuel requirement

1.8.5 Manpower

1.8.6 Land

1.8.7 Equipment / Machinery

1.8.1 Raw Material requirement

The project under consideration is project for Ordinary (Ordinary Bricks) Clay Mines for excavation of soil clay so need of raw material will use like Natural clay, Water, Agro waste & fly ash. The final product will be Bricks which shall be marketed directly by road to various destinations.

Page 18: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

9

1.8.2 Electricity

Source of Power supply: 5 HP, Dakshin Gujarat Vij company Limited (DGVCL).

1.8.3 Water

Fresh water requirement will be 18000 Lit/Day for the proposed project. Out of this 2000 L/Day will be used for domestic purpose, 16000 Lit./Day for Manufactruing Process and Dust Control Sprinkling System and greenbelt development purpose.

1.8.4 Fuel Requirement

LIGNITE – 5 MT/day used as a fuel.

1.8.5 Man power

The proposed mining activity will provide employment of 6-9 full time person approximately.

1.8.6 Land

Project land is Private Land.

1.8.7 Equipment/ Machinery:

1. Wagon drill machine

2. Dozzer

3. JCB/Poclain

4. Crusher with conveyor belt

5. Water sprinkler system

6. Trucks for transportation of material

1.9 Pollution Potential:

1.9.1 Air Emission: Dust Emission during Mining, Transportation & which will be controlled by water sprinkling and development of Greenbelt area. Bricks kilan stack height is 30 meter and air pollution control system is Grevitational setteling chamber to collect the dust and fule gas emission well within permisible limit by GPCB standard.

1.9.2 Industrial Water Pollution: Nil.

1.9.3 Hazardous Wastes Generation: Nil.

Page 19: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

10

2. Anticipated impact based on project operations on receiving Environment

2.1 Population:

The project is micro level enterprise. Hence, the magnitude of impact is negligible. No influx of population is anticipated as only local labor shall be deployed.

2.2 Flora and Fauna:

No endangered Spp. Or forest within 10 KM radius. Surrounding land is wasteland. No farming in the surrounding. Very negligible impact on flora & fauna.

2.3 Water:

2.3.1 Water Consumption

2.3.2 Wastewater Generation

2.3.3 Rain Water Harvesting

2.3.1 Water Consumption:

2.3.2 Waste Water Generation:

Fresh water requirement will be 18000 Lit./Day for the proposed project. Out of this 2000 Lit./Day will be used for domestic purpose, 16000 Lit./Day for Manufacturing proces and Dust Control Water Sprinkler and Greenbelt Development purpose. The detail breakup of the water consumption is given hereunder in Table:

The water consumption & waste water generation details:

Sr. No.

Category Water Cosumption kl/day Waste water generation kl/day

1 Domestic 2.0 1.0

2 Industrial

a. Processing 16.0 NIL

Total - INDUSTRIAL 16.0 NIL

Total – DOMESTIC + INDUSTRIAL

18.0

1.0

Page 20: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

11

1. There shall be no generation of industrial effluent from the Brick manufacturing and other ancillary industrial operations.

2. The quantity of the domestic waste water (sewage) shall not exceed 1000 lits/day.

3. Sewage shall be disposed in to the soak pit/septic tank system.

2.3.3 Rain Water Harvesting:

As the water is the basic natural resources and towards the step to resource conservation, rain water harvesting system is integrated in the project. Rain water will be percolate from the sides and the balance collected rain water will be lifted out and stored at storage tank for water sprinkling and greenbelt development.

2.4 Air:

The Impact on the air quality is divided in to two categories:

A. Impact on air quality during Mining phase

B. Impact on air quality during Transportation phase.

A. Impact on Air Quality during Construction Phase:

Minimum amount of air pollution will occur due to fly dust during Mining Phase.

B. Impact on Air Quality during Operation Phase:

Sources of Air Pollution

Dust generation during Mining, Transportation and Crushing/Screen of Minerals.

Impact on Environment

Minor increase of particulate matters in local environment.

Page 21: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

12

1. The flue gas emission through stack shall conform to the GPCB Standards.

AIR EMISSION (Flue gas stacks as well as process stacks):

SR.NO. STACK ATTCH. STACK

HEIGHT

IN METER

AIR POLLUTION CONTROL

MEASURES

FUEL USED PARAMETER

LIMIT

1. Brick Kiln 30

Meter.

Gravitational Settling

Chamber

LIGNITE –

5 MT/day

SPM < 150 mg/NM3

SO2 < 100 ppm

NOx < 50 ppm

2. There shall be no process emission from the manufacturing process of any other ancillary

operation.

Page 22: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

13

3. Mitigation Measures:

Mitigation Measures

The proposed unit will provide adequate Environmental Management Plan to assure the regular and efficient working / operation of the same. The details of Environment Plan are described here under:

Objectives:

Regular and efficient working of the Operation with acceptable minimum Environmental Impact.

• To conserve the environment.

• To check and maintain the record of the environmental parameters for the further improvement of the process and environment.

• To comply with the Act, Rules, Notifications directly applicable to the Environment Management.

3.1 Wastewater Treatment System and Disposal:

A) Domestic Wastewater:

The generated 1000 Lit./Day of domestic waste water will be drained in to the Soak pit through septic tank.

B) Industrial Wastewater:

No industrial waste water will be generated from process as well as ancillary operations.

3.2 Air Pollution Control Measures:

A. Air pollution Control Measures during Construction Phases:

Minimum amount of air pollution will occur due to fly dust during construction of buildings which will be controlled by water sprinkling. Impact is Temporary and Short Term in nature.

B. Air pollution Control Measures during operation Phases:

Sources of Air Pollution

Dust generation during Mining, Transportation etc.

Page 23: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

14

Impact on Environment:

Minor increase of particulate matters in local environment.

Control Measures:

• Sprinkling of water at Mining Area, Transportation etc.

• Adequate plantation will be provide to prevent dust dispersion.

Haul roads:

• All the haul and service roads shall be mettled and well maintained.

• Un-mettled haul roads shall be free of ruts and pot holes.

• All haul roads and surface roads shall be regularly sprayed with water.

• Plantation alongside haul roads (avenue plantation) shall be carried out done.

• Mined material receiving pits are shall be located close to the quarry to reduce the haul length of the dumper.

Overburden:

• Non-operative dumps shall be subjected to technical and biological reclamation.

• Plantation over and around over burden dumps shall be carried out to ensure stability of slopes, prevention of dust by wind action and soil erosion during the run off.

• Wetting of surface of O. B. dump shall be regularly practiced.

3.3 Noise Control Measures:

There are few potential sources such as Pump Operation, Vehicular Movement, etc. which would generate noise. Proper maintenance of all the equipments will be taken. Adequate encloser of stone crushing machine will be provided as well as personal protective equipment (PPE) like: ear muffs/ earplugs shall be given to workers during working.

3.4 Solid/Hazardous Wastes Management System

No hazardous waste generation

Page 24: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

15

3.5. Greenbelt Development

In order to mitigate the air pollutants and to attenuate the noise generated by the plant and Also improving the ecology and aesthetics of the area, the unit will develop greenbelt area on the periphery of lease area.

3.6 Hazards and Safety Measures:

• All the personnel at the plant will be made aware about the operation hazards and risk associated with them.

• Safe work practices will be adopted to ensure the control of hazards during operation and maintenance.

• The workers will be made aware about the hazards associated with manual handling and operation.

• Safety measures in the form of ‘DO’ and ‘Don’t Do’ will be displayed at strategic locations especially in local language.

• Good housekeeping will be maintained in the Mining area.

• The required PPEs for each area/operation should be identified and the necessary PPEs, like, helmets, goggles, hand gloves, mask, suit, safety belts, ear muff and plug, etc. will be provided to the personnel.

• The plant will check and ensure that all instruments provided in the plant are in good condition and documented.

• First Aid box will be provided within the plant.

• List of important telephone numbers will be displayed at prominent location in the plant. Lease Holder Machine Operator Helper/ Labour

• All the accidents and incidents if any will be recorded, investigated and analysed in the proposed plant.

• Safety awareness program and trainings of the worker will be carried out to motivate the workers to increase the safety level at personal level.

Occupational Health Aspect: As per govt. standard all facilities will be provided.

Safety Precautions:

• Adequate fencing would be provided against protection of human beings and animals in deep pit of mine.

Page 25: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

16

3.6.1 Mining Safety Guide:

Company will follow the below guidelines during Mining Activity:

Area wise hazards:

• Bulk storage of raw material – Hazard of dust

• Crusher/Screen plant- Dust emission, Noise generation

• Mixtures and drives – Crush injuries

• Loading and unloading – Dust

• Transportation – Air pollution because of fossil fuel combustion and dust emission too.

• Drilling- Dust emission

General Considerations:

1. Adequate lighting,

2. Ventilation to supply fresh air,

3. Electricity,

4. Dust control i.e. Controlling dust within safe limits,

a) Rock dust containing silica and quartz may cause silicosis.

b) It is advisable to use Electrostatic filters to reduce air pollution.

5. Continuous safety of people at work,

6. Survey of hazards of fall of persons, soil, material, etc.

7. Warning signs and notices,

8. Safe means of access,

9. Emergency generators,

10. Sufficient lighting will be provided for night work,

11. Means of escape and ladder from bottom to top will be provided in addition to any mechanical means of ingress and egress,

12. Employment of trained workers and further training to them,

Page 26: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

17

13. Safe guarding of dangerous parts of machinery,

14. Proper drainage and de-watering system (if require),

15. Wet drilling for dust control,

16. Separate transport vehicles for explosives and detonators, separate storage facility beyond 100m from lease area and their separate magazines,

17. Lubricating oils, grease and rope dressings will be kept in closed metal containers,

18. Lighting arresters will be provided on the surface,

19. Emergency lighting to function for a long time (to escape safely) will be provided,

20. To avoid any damage or accident during natural calamities like cyclone, flood, cloud bursting, earthquake, etc. sound construction of housing facility will be provided to workers,

21. Medical center with first-aid facilities will be provided,

22. Important telephone numbers (Police, Ambulance, Fire, nearest Primary Health Center)

Personal Protection Equipments:

1. Helmets

2. Gum-boots

3. Face shield

4. Hand gloves

5. Safety goggles

6. Full body harness

3.6.2 Excavation:

General precautions for any excavation or underground work are:

1. Stability of ground

2. Position of public utility services such as electric or telephone cables, water, sewers line, etc. (Relocation, isolation or protection of underground utilities should be done with due permission.)

Page 27: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

18

3. Effect on adjoining building, structure, roadways, bridges, etc.

4. No load or vehicles should be moved or stacked near the edge of excavation to prevent the side-collapsing.

5. All sides will be fenced by barrier at least up to 1m and danger notice, red signal and light will be provided. Sides of all excavation must be sloped to a safe angle not steeper than the angle of repose of a particular soil/rock.

6. Cutting will be done from top to bottom. No undercutting of side will be allowed.

7. Road barrier at a distance will be provided if road is to be blocked.

3.6.3 Transportation Safety:

1. Vehicles must be checked for:

a) Warning sirens,

b) Horns (loud and clear),

c) Lights (head-lights, tail-lights),

d) Signals,

e) Reverse alarm,

f) Vehicles will not run overloading and over speeding

g) Smokeless locomotives will be used.

2. Other important considerations:

a) Rules for driving will be enforced

b) Cabins of excavators in quarries will be partially closed and drivers should be supplied air mask

c) Water spray to dusty processes and to conveyor belts including their drives and transfer points.

Page 28: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

19

3.6.4 Haulage (pulling and shifting):

• Material carried out mechanically.

• Workers will not be transported along with the material.

• Speedy removal of derbies, refuse and trash.

• Safe and adequate walkways.

3.6.5 The key points to ensure safety are:

a) Clearing employees from the mining area,

b) Effective access control,

c) Efficient communications,

d) Training

3.6.6 Good Housekeeping:

The term Good Housekeeping is often loosely understood as simple floor cleaning or broom stick operation. But it has even wider meaning including up keeping of all industrial activities in orderly manner to minimize the accidents due to improper planning, placement, arrangement, handling, etc. everywhere in industrial premises. “Place for everything and everything on proper place”. So, Good housekeeping at quarry site will greatly reduce unsafe conditions and so risk of accidents.

Page 29: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

20

4.Environment Management Plan: The proposed unit will provide/prepare an adequate Environmental Management Cell to assure the regular

and efficient working /operation as given here below:

• The Environment Management Plan (EMP) is required to ensure sustainable development in the area

of the proposed project. Hence it needs to be all encompassive plans for which the industry,

Government, Regulating agencies like Pollution Control Board working in the region and more

importantly the population of the area need to extend their co-operation and contribution.

• Mitigation measures for each of the activities causing the environmental impact.

• Monitoring plans for checking activities and environmental parameters and monitoring

responsibilities.

• Role responsibilities and resource allocation for monitoring.

• Following sections describes the environment management plan proposed for site clearing and Mining

phases.

MITIGATION MEASURES:- • Each of the activities during production phase is critically Reviewed for suggestion of mitigation

measures. Based on This the Table 1 to 6 gives the mitigation measures for the Activities

considered being causing significant Environmental impacts during production phase of every

Year.

Page 30: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

21

Table: - 1 Environment Management Plan:- Activity Environmental

Impacts Mitigation Remarks

Mining process

Air

Water spraying by sprinkle to control micro particles of mineral and dust. Ensure uses of personal protective equipments. (PPE's)

Implementation responsibility: Project

Proponent

Water

No waste water management. Install proper facilities to prevent rain / storm water.

Land

Ensure uses of personal protective equipments (PPE's). Manage proper storage of bricks

Noise

Ensure proper maintenance of machinery to reduce noise level

Page 31: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

22

Table: - 2 Environment Management Plan:-

Activity Environmental

Impacts Mitigation Remarks

Storage of all the Waste materials

and products.

Air Water Land

To be stored in accordance with

the rules and regulation of the

As per Department. Separate storage area for products.

Install proper facilities to prevent rain / storm water

contamination during the storage of solid prepared

products. Trained / approved transports will be given work for the transportation of

the products.

Implementation responsibility:

Project Proponent

Land Well maintained vehicles will be

used. Metalled Road for vehicle movement.

Top soil will be conserved and be

utilized for greenbelt on area.

Page 32: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

23

Table: - 3 Environment Management Plan:-Other Facilities:-

Activity Environmental Impacts

Mitigation Remarks

Toilets Water Ensure proper

sewage disposal. Implementation responsibility:

Project Proponent

Development and

maintenance of green belt

Air. Land

Ensure development and maintenance of

proper green belt as proposed.

Direct / Indirect Employment

Socio- economic issue

Continue policy of local employment according to the

skill and availability

Environmental Monitoring Plan:-

Environment monitoring plan is given in table 5 as follows: Table No. 4

Sr.No. Activity Schedule Air Pollution Monitoring

1 Ambient air monitoring of parameters specified by GPCB in their air consents from time to time within the Proposed premises

Once every Calendar Year

Water Pollution Monitoring

1 No waste water Produced N.A. Solid Waste Generation Monitoring / Record Keeping

1 No Solid Waste Generation. N.A.

Page 33: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

Expenditure on Environmental Matters:-

The following table gives the expenditure to be incurred by Proponent on environmental matters. Table No. 5

Sr. No.

Description Approximate Recurring cost per annum (Rs. In Lacs)

Approximate Capital Cost (Rs. In Lacs)

1 Air pollution control 0.30 0.40

2 Water pollution control 0.20 ---

3 Environment monitoring and management

0.30 0.40

4 Noise pollution control 0.10 0.20

5 Occupational health 1.10 1.20

6 Green belt 0.50 0.70

Total 2.50 2.90

24

Page 34: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

Table No. 6: Vegetation

Name of the trees

Sensitive / tolerant to

air pollution

Height No. of Threes to be plant

Amount to be Spent

Neem Tolerant 10-15 m

10 0.50 Lacs

Asopalav Tolerant 10-15 m 10

Peepal Tolerant 10-15 m 10

Local species Tolerant 5-10 m 10

Total

40 0.50 Lacs

25

Page 35: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

M/s. MMP BRICKS (KALBEABBAS PANJVANI) Block No. 113, Village – Chuli,

Tal – Dediapada, Dist.- Narmada-393040. (M) 9624160117, Email: [email protected]

Environmental Impact Assessment: We are applied for Ordinary Clay Mining project which lease area is 01.64.35 ha (which is < 25 ha) and under B2 Category. So, TOR (Terms of Reference), Public Hearing, and EIA is not applicable.

Page 36: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

M/s. MMP BRICKS (KALBEABBAS PANJVANI) Block No. 113, Village – Chuli,

Tal – Dediapada, Dist.- Narmada-393040. (M) 9624160117, Email: [email protected]

1. KALBEABBAS NISHARHUSEN PANJVANI

LIST OF PROPRIETOR:

PANJVANI NISHARJUSEN, ARAB CHALI PARSI TEKARA, TAL.- DEDIAPADA, DIST.- NARMADA-393040, GUJARAT.

(M) 9624160117

Page 37: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

M/s. MMP BRICKS (KALBEABBAS PANJVANI) Block No. 113, Village – Chuli,

Tal – Dediapada, Dist.- Narmada-393040. (M) 9624160117, Email: [email protected]

MINING PLANT IS NOT APPLICABLE.... For MMP BRICKS.

Authorised Signature Kalbeabbas Panjvani Proprietor

Page 38: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With
Page 39: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With
Page 40: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

DISTRICT SURVEY REPORT

NARMADA DISTRICT

Page 41: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

DISTRICT SURVEY REPORT NARMADA DISTRICT, GUJARAT

INTRODUCTION

Narmada district is situated in the southern part of Gujarat State. The district lies between north latitudes 21°23’ and 22°05’ and east longitudes 73°17’ and 73°59’. The geographical area of the district is 2755 sq.km. Narmada district is bounded in the North by Vadodara district, in the south by Surat district, in the west by Bharuch district and in east by Maharashtra State (Fig.1). This district was carved out on October 2, 1997. The newly formed district consist of Tilakwada taluka of erstwhile Vadodara district and 3 talukas viz., Nandod, Dediyapada and Sagbara of erstwhile Bharuch district. and consists of 609 villages. Total population of the district as per 2011 census is 5,90,379.

Fig-1

STUDIES/ACTIVITIES

This district was carved out on October 2, 1997. The newly formed district consist of Tilakwada taluka of erstwhile Vadodara district and 3 talukas viz., Nandod, Dediyapada and Sagbara of erstwhile Bharuch district. Therefore most of

Page 42: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

the previous work done in the Bharuch district and Varodara district is now covered in Narmada district.

A. R. Pandey of Central Ground Water Board (1977-78) carried out detailed

hydrogeological investigation in parts of Bharuch distrlict. Sporadic hydrogeological survey work in connection with drilling and construction of tube wells in parts of Bharuch district was carried out by J. S. Auden (1951), Murthy (1967-68), Channabasappa (1962) of Geological Survey of India. Detailed exploratory work has been carried out under Narmada River Basin Project by the Central Ground Water Board between the years 1971 and 1978. Systematic hydrogeological survey carried out by Saleem Romani (1970-73) in parts of Narmada Basin, Naswadi, Tilakwada area of Vadodara district.

Groundwater exploration by test drilling in the district commenced in fifties

and is continuing till 2008. A. K. Jain (1986-87) carried out groundwater exploration in Tilakwada Taluka. Apart from the exploratory wells Piezometers have also been constructed in the district under the Hydrology project. Representative dug wells and piezometers are monitored periodically for the ground water regime studies and quality changes in the district and is continued till date.

RAINFALL AND CLIMATE

The district has semi arid climate. Extreme temperatures, erratic rainfall and

high evaporation are the characteristic features ( Fig. 2). The average annual normal rainfall is 924.8 mm for the 30 years. Bharuch IMD station is falling close to the newly formed Narmada district Therefore, climatological data of Bharuch IMD station (1951-1980) is ustilised for this district and is given in Table 1.

Table 1: Climatological data of Bharuch IMD station

Max Mini Wind Solar Wind Temp Temp Humidity Spd. Sunshine Rad. Eto Rainfall Spd. Month (Deg.C) (Deg.C) (%) Kmpd (Hours) (MJ/m2/d) (mm/d) (mm) Kmph January 31.3 11.9 51.5 105.9 9.0 17.3 3.7 1.2 5.9 February 33.8 14.4 45.0 111.3 9.2 19.6 4.5 1.0 6.2 March 37.6 19.0 44.0 125.7 9.8 22.7 5.8 0.8 7 April 40.0 23.3 45.0 158.0 10.4 25.2 7.2 1.0 8.8 May 39.6 26.2 55.5 222.6 10.8 26.2 8.0 12.5 12.4 June 35.6 26.5 69.5 263.9 7.6 21.3 6.3 121.0 14.7 July 32.0 25.5 81.0 237.0 4.4 16.5 4.3 307.6 13.2 August 31.2 25.0 83.5 206.4 4.2 15.9 3.9 243.1 11.5 September 32.6 24.4 76.0 154.4 6.3 18.1 4.4 197.6 8.6 October 35.9 22.0 59.5 102.3 7.9 18.5 4.5 35.2 5.7 November 34.8 16.9 52.5 84.4 8.0 16.5 3.7 3.7 4.7 December 32.2 13.2 53.5 93.3 8.9 16.5 3.4 0.1 5.2

Total - - - - - - - 924.8 Average 34.7 20.7 59.7 155.4 8.0 19.5 5.0 -

Page 43: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

Fig. 2

GEOMORPHOLOGY AND SOIL TYPE

Physiography

Narmada district has a varied landscape and may be divided into four topographic units:

The hilly area with high relief: Area is known as Rajpipla hills marks the merging of Satpura and Shyadri ranges. It has got a prominent ridge and valley topography oriented in almost East -West direction.

Piedmont zone: Periphery of hilly area is characterized by an outward sloping accumulation of loose, coarse material which has been deeply dissected.

Alluvial plain: The alluvial plain, which is nearly flat, constitutes a huge pile of alluvium, deposited during the Holocene and Pleistocene times. Narmada flood plain has conspicuous recent disposition of its own. Narmada has got an entrenched meandering course which has cut terraces and deposited flood load on both sides.

Page 44: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

Drainage

District is drained from east to west mainly by three rivers namely the Narmada, the Kim and the Tapi The river Narmada after entering the low level of Gujarat plains near Markai, flows westward to the Gulf of Khambat in Bharuch district. Narmada moves through a rich flat plain, between high rough banks of hard clay and sand deposits located mostly in Tilakwada taluka. In its course through the district, the Narmada receives important tributaries namely the Karjan, the Orsang, the Heran, the Aswan, and the Men. Rising in the Rajpipla hills, the Kim, for the first part of its course passes through the Nandod taluka and Valia Mahal territory. The south eastern extremity of the district touches the Tapi, the second important river of south Gujarat.

SOILS

The soils found in Narmada district are as follows.

Black cotton soil : These soils have their origin in trap. They are varies from 60 cm to as high as a few meters. black soils formed due to decomposition of trap parent material transported through flow of rivers. The soils are dark brown to very dark grayish brown in colour, containing 40-70% clay , are poor in drainage and neutral to alkaline reaction.

Gorat soil : It is a sandy alluvial type of soil with contain 40% clay and grater sand particle that’s why it do not retain moisture.

Bhatha soil : It is lateritic type of soil, containing lot of pebbles with water observation capacity is low.

Stony soil :The stony soil, covers only forest areas and no cultivation is done on these soils.

The soil all over the district contain low Nitrogen , Phosparus( medium in

Tilakwada taluka) and high Potash.

Page 45: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

GROUND WATER SCENARIO

Hydrogeology

The river Narmada, which flows in almost East –West direction through northern part of the district which is predominantly underlain by unconsolidated alluvial sand, gravel and boulders. Most part of the district is covered by basaltic rocks of the Cretaceous age. The Mesozoic formations are exposed under a small area mostly in Tilakwada taluka.

Groundwater occurs under unconfined conditions in all the rock formations in most of the area of the district. Weathered zone below water table acts as good repository for storage of groundwater in Deccan Trap areas. In the Infratrapean rocks (Bagh beds- sandstone, marls and limestone), apart from occurrence of water in the pore spaces between sand grains, the principal joints, fissures and other planes of structural weakness play an important role in the movement of groundwater. In the alluvium, groundwater occupies the open spaces between particles of sand, gravel and boulder.

Hydrogeological conditions in the different geological formations are

presented in the Fig. 3 and are described below.

Semi-consolidated Lower Cretaceous formation The Bagh beds

Groundwater occurs under unconfined conditions in the limestone and

sandstone aquifers. Occurrences and movement of groundwater is restricted mainly to the fractures and joints in the limestones and sandstones. Due to the cherty nature of limestone aquifers and calcareous nature of the sandstones, the primary porosity as well as development of solution cavities is very poor. The Basal conglomerate beds are poorly permeable on account of calcareous cement. However, these conglomerates when exposed to surface, give rise to good aquifers which support shallow wells. The discharge in dug wells varies from 30 to 50 m3

/day. In highly weathered conglomerates and sandstones, the yield of wells ranges up to 700 lpm for drawdown of 1 to 2 m and recuperation is fast.

The Bagh beds overlain by Deccan Trap are likely to yield groundwater under

confined condition.

Page 46: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

Fig. 3

Page 47: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

Consolidated upper Cretaceous formation The Deccan traps

The Deccan Traps, being the extrusive volcanics, where individuals flows

were laid down at specific time intervals, have given rise to multi layered stratified aquifers. Each individual flow comprises of two distinct units, namely the upper vesicular basalt and the lower massive basalt. The massive basalt is hard and compact with no primary porosity but the vesicular basalts exhibit porosity. Movement of groundwater is controlled by secondary porosity developed by the presence of fractures and joints.

The vesicular basalt forms a good aquifer where the fractures and joints

interconnect the vesicles, thereby rendering the rock more porous. Similarly, the paleo-weathering which is invariably observed at depth near the top of every flow, has good aquifers at depth. This paleo-weathering is responsible for the occurrence of groundwater under confined conditions in the Deccan Trap and has given rise to multi-aquifer system down to the depth of several hundred meters.

The yields of dug wells in Deccan Traps, which range in depth from 5 to 25m

below ground level, sustain pumping from half an hour to ten hours with discharge varying from 200 to 1200 lpm for drawdowns of 4 to 7 meters. Bore wells tapping deeper zones down to explored depths of 200 m, have yielded 100 to 1500 lpm for drawdown of 12 to 16m.

The dolerite and trachyte dykes intruding the Deccan Traps do not support

good yield of well. These dykes, on the contrary, restrict the movement of groundwater and thus gives rise to storage of groundwater on one side of the dyke and dry aquifers on the other side.

Un-consolidated Quaternary formations Alluvium

Area close to either side of the Narmada river constitute highly potential belt.

However, a large amount of water percolating through the loose alluvium is drained into the nullahs through seepages, thereby deepening the water levels.

Depth to water level

Pre monsoon water levels as shown in the map for the period May. 2012 (Fig.

5) ranges mostly 5 to 10 m bgl in the largest part of the district. Shallow water levels are mostly experienced in Dendiapada taluka. Water level more than 20 m bgl is observed in Nandod taluka.

A perusal of the map for the period of Nov 2012 ( Fig.4 ) reveal that in the

major part of the district, the depth to water level ranges from 2 to 5 m bgl and most of the area falls in Dendiapada and Sagbara talukas. The area is covered by the water level between 5 and 10 m bgl in central part of the district. Deep water levels range from 10 to 40 mbgl are observed mostly in Nandod taluka

Page 48: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

Fig - 4

Page 49: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

Fig - 5

Page 50: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

Annual fluctuation of water levels

Map showing water level fluctuation between May 2012 and November 2012 (Fig. 6) shows mostly rise in water level in the district. About 50% of the area covered in rise of 2 to 4 m. Fall in the water levels are mostly confined to Nandod taluka in the range of 0 to 2 m and 2 to 4m in patches.

Fig - 6

Page 51: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

Groundwater Quality:

The chemical quality of groundwater in shallow aquifer has been studied based on the water samples collected from 10 monitoring stations (NHS) during the year May 2011. The ground water is in general alkaline in nature. A perusal of map shows the electrical conductivity (EC) and chloride concentration increasing towards northwest direction. Groundwater quality in Basaltic formation is generally fresh and electrical conductivity is mostly less than 1000 µS/cm and chloride concentration is less than 250 mg/l. Quality in alluvium and Bagh beds are poor as compared to basaltic rocks and EC is observed to be in the range of 2000 to 5000 µS/cm in northwest portion of the district.

GROUND WATER DEVELOPMENT POTENTIAL OF NARMADA DISTRICT ( 2011)

Ground Water Resources

The ground water resources of the district as per GWRE 2011 are presented in Table 2. All the talukas in Narmada district are categorised as safe.

TABLE 2- Groundwater development potential of Narmada district (2011)

Sr. Assessment Net Ground Existing Existing Allocation Net Ground Stage of No. Unit/ Taluka Available Water Gross Gross for domestic Water Ground

Ground Draft for Ground Ground and Availability Water Water irrigation Water Water industrial for future Development Recharge (Hac.m/Yr) Draft for Draft for requirement irrigation {(6/3)*100} (Hac.m/Yr) domestic All uses supply upto development (%) and (4+5) next 25 (3-4-7) (in ha m) industrial (in ha m) years (in ha m) water (in ha m) supply (in ha m)

1 2 3 4 5 6 7 8 9 1 Nandod 10407.06 3523.40 699.00 4222.40 938.00 5945.66 40.57 2 Dendiapada 3085.34 321.00 433.00 754.00 581.00 2183.34 24.44 3 Sagbara 5011.17 438.80 253.00 691.80 339.00 4233.37 13.81 4 Tilakwada 2990.50 542.60 169.00 711.60 227.00 2220.90 23.80

TOTAL 21494.07 4825.80 1554.00 6503.80 2085.00 14583.27 29.68

Status of Ground Water Development ( Taluka wise)

The alluvial aquifers in the district are exploited with the help of dug wells, dug-cum-bored wells and tube wells for irrigation. The yield of wells in alluvial formation vary from 400 to 700 litre per minute (lpm) for drawdowns varying from a few meters to as much as 21 m. There are 2872 wells of all types in the district are in use as per the MI Census 2000-2001 and the total annual draft is computed to of

Page 52: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

the order of 6503 ha. m (GEC 2011). Groundwater development in Nandod taluka is highest (40.57%). The wells in hard rocks generally have low to moderate recuperation. The development of groundwater in Dendiapada taluka is low (16.61%) as the taluka is entirely occupied by hard rocks which have low to medium potentialities. The Taluka - wise groundwater structures are furnished in Table3. The wells in hard rocks generally have low to moderate recuperation.

Table: 3- Taluka wise groundwater structure in use.

Sl. No. Name of taluka Dug well Tube well Total

1 Dendiapada 656 11 667 2 Nandod 896 317 1213 3 Segwara 567 5 572 4 Tilakwada 291 129 420

Total 2410 462 2872

NA -Data not available

Irrigation scenario from ground water sources Dugwells

As per MI census 2000-01 there are 2772 dugwells out of which 2410 are in

use. Irrigation potential created through these dugwells is 5417 ha. m and potential utilized is 5407 ha. m area.

Tubewells:

As per MI census 2000-01 there are 560 deep tubewells in the district out of which 461 are in use. The irrigation potential created is 2646 ha.m are and potential utilized is 1643 ha.m.

The Taluka-wise details of irrigation potential for ground water sources

presented in Table-4.

Table: 4- Potential created by groundwater abstraction structures Dugwells Tubewells

Taluka Potential Potential Potential Potential created utilized created utilized Dendiapada 1450 1449 112 11 Nandod 1971 1970 1750 944 Segwara 1388 1384 73 0 Tilakwada 608 604 715 693 Total 5417 5407 2650 1648

(NA- Data not available, Source: M I Census 2000-01, area in ha.)

Page 53: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

Ground Water Management Strategy

All talukas in the district are categorised as safe in the GEC 2011 report and district as a whole has 29.68% of development. Hence, there is further scope for development of the ground water resources in the district. The irrigated area in the district forms is 406 Sq. Km cultivable area (Table 5 ). The area irrigated by wells form about 97% of the total irrigated area. This indicates that irrigation in the district depends on groundwater to very great extent. The district is quite rich in surface water resources. The available surface water in Narmada should be properly utilized after the completion of canal networks. None of the talulkas has been notified either by Central Ground Water Authority (CGWA) or State Water Authority (SGWA).

The suitable recharge structures feasible in the district are Percolation tanks/ponds, Recharge wells, Recharge shaft, Check dams, nalla bunds and gully plugs etc depending on the terrain conditions.

In the desaturated phreatic aquifers with deep water levels, spreading channels, recharge pits, recharge ponds etc wherever suitable to utilize surplus runoff and tail end releases from the canals.

Various rainwater harvesting schemes depending on the suitable hydrogeological conditions have been constructed in the district viz. Check dams, Recharge tube wells , deepening the of the village ponds etc and have shown good impact on the groundwater scenario.

Table: 5 Agricultural land and source irrigation

Sl. Name of Geographical Cultvable Net Net area irrigated through

No. taluka area area area Major/medium Surface

sown scheme Groundwater water Total

1 Dendiapada 93981 8270 8003 0 1999 0 1999

2 Nandod 69508 39122 37569 0 3073 0 3073

3 Segwara 35223 10833 9613 205 1572 0 1777

4 Tilakwada 21645 10938 10572 0 1197 0 1197

5 Total 220357 69163 65757 205 7841 0 8046

Ground Water Related Issues and Problems

The farmers don’t have control over power supply, therefore they irrigate the crops by groundwater when power supply is available rather than waiting for the wilting to start.

Flood irrigation technique which is practised in the area is also the major

cause of wastage of ground water as there is no control on the watering depth.

Page 54: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With

The Narmada is indeed shifting its course and causing erosion of the land

over the past years. The phenomenon is more pronounced since 1994 flood of Narmada river.

Lack of awareness among the people regarding rainwater harvesting and

artificial recharge.

Recommendations

There is an urgent need for management of resources for sustainable development.

Suitable ground water legislation may be enforced and all future ground water exploitation by deep tube wells can be restricted.

Creating awareness among the farmers regarding water conservation through judicious use of water and adoption of efficient irrigation techniques like drip/sprinkler irrigation.

The land holding of the group of farmers under public tubewell irrigation should be brought under the provision of the change in crops, irrigation practices and installation of drip/sprinkler irrigation technique.

Soft term institutional finances to the farmers and liberal subsidies in equipments are suggested.

Resorting to artificial recharge practices by diverting surplus run-off during monsoon into ponds, percolation tanks,. Spreading basins, abandoned dugwells etc.

Taking up artificial recharge on large scale through appropriate techniques on a regional scale with active community participation.

Institutional finance and appropriate technology should be freely made available to any individual or cooperative group of farmers that undertake resource augmentation and management measures.

The level of groundwater development is low in all talukas and there is good scope of groundwater development.

The area in the vicinity of Narmada river may be developed by constructing groundwater structures to utilise the subsurface groundwater flow to river.

Page 55: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With
Page 56: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With
Page 57: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With
Page 58: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With
Page 59: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With
Page 60: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With
Page 61: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With
Page 62: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With
Page 63: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With
Page 64: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With
Page 65: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With
Page 66: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With
Page 67: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With
Page 68: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With
Page 69: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With
Page 70: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With
Page 71: To, District Level Expert Appraisal Committee (DEAC), The …environmentclearance.nic.in/writereaddata/District/pfr/... · 2019. 6. 22. · Dist.: Narmada-393040. Respected Sir, With