Manila Water Plans & Programs Updates
May Quinto
Strategic Asset Planning
2 2
2
The MWSS-Manila Water PPP
East Zone
West Zone
The Concessionaires
3 3
Before Aug. 1, 1997
PUBLIC
MWSS
Concession Framework
Since Aug. 1, 1997
PUBLIC
Concession
Agreement Reimbursement
Cost + ADR Service
Obligations
MWSS
Agents and
Contractors
Regulatory Framework
4 4
Service Obligations
Sewerage and
Sanitation
Customer
Service
Water Supply
5 5
The Manila Water Concession Area
BalaraBalara
Marikina
CubaoCubao
San Juan/
MandaluyongMandaluyong
Pasig
MakatiMakati
Taguig/
AntipoloBalaraBalara
Marikina
CubaoCubao
San Juan/
MandaluyongMandaluyong
Pasig
MakatiMakati
Taguig/
Antipolo
Profile of Manila Water Company
The East Zone covers 23 cities and
municipalities
Covers all new business centers in
Metro Manila and is the center of
population growth
Spans 1,400 square kilometers
Population of 5.9 million
6 6
“Spaghetti” & Illegal Connections
Leaks
Lower water pressure to no water
Poor service
3.13.1 MILLION CUSTOMERSMILLION CUSTOMERS
1997
24 hours 13-23 hours 0-12 hours
26%26% 99%99%
1Q 2009
5.65.6 MILLION CUSTOMERSMILLION CUSTOMERS
Water Supply Availability
Public – Private Partnership
Conditions Before Privatization
Sanitation low!
7 7
Water Supply Accomplishment
8 8
3.1 MILLION CUSTOMERS
1997
24 hours 13-23 hours 0-12 hours
26% 99%
2012 (Q1)
6.2 MILLION CUSTOMERS
24/7 Water Availability
Water Supply : Accomplishment
9 9
Reduction of Water Losses
10%
15%
20%
25%
30%
35%
40%
45%
50%
55%
60%
65%
19971998
19992000
20012002
20032004
20052006
20072008
20092010
20112012
in % Non-Revenue Water (NRW)
63%
11%
Water Supply : Accomplishment
10 10
Water Supply Plans & Programs
11 11
Water Supply Master Plan
Covered Population
11
2017 2012 2037 EZ
89%
EZ
94% EZ
99%
Covered
Population : 6.2M Covered
Population : 6.8M
Covered
Population : 8.2M
Rizal
Towns
27%
Rizal
Towns
60%
Rizal
Towns
98%
13 13
Rodriguez Water
System
Balara
Water
System
East Source
Water
System
Water System Master plan
13 • Future Plans subject to MWSS approval of 2013 Business Plan
14 14
Natural Calamities and
Environmental
Challenges
SERVICE CONTINUITY
Ensure that existing customers
continue to receive high-quality
service
Water Supply Masterplan
14
Natural Calamities and
Environmental
Challenges
SERVICE CONTINUITY
Network Efficiency projects
Tubig Para sa Brgy
Meter management
Coverage Expansion to
farther and higher areas
SERVICE ACCESSIBILITY
Laying of Transmission &
Distribution lines
One source of water
supply
WATER SECURITY
Development of new water
resources
Raw water Aqueduct
• Future Plans subject to MWSS approval of 2013
Business Plan
16 16
Wastewater Services
18 18
WASTEWATER SERVICES
SANITATION SEWERAGE
Septage
19 19
1. Sanitation Services
2 . Separate System
3. Combined Sewer-Drainage
with Sanitation Services
Wastewater Services Approaches
20 20
Septage Treatment
Plant
Septage
Hauled by vacuum tankers to
Septage Treatment Plants
Sanitation Services
21 21
DRAINAGE
Sewage Treatment
Plant SEWER LINE
treated effluent
storm water
Sewage Management Separate System
22 22
Sewage Treatment
Plant
COMBINED SEWER-DRAINAGE LINE
treated effluent
overflow during heavy rains INTERCEPTOR SYSTEM
Septage Treatment
Plant
Sewage management
Combined Sewer – Drainage and Septage Management
23 23
Sanitation
2 Septage treatment plants
77 tankers
North SpTP
South SpTP (FTI)
North SpTP (San Mateo)
Existing Facilities of Manila Water
24 24
number of households served thru desludging of septic tanks
Accomplishments in Manila Water Sanitation Services
25 25
SEWERAGE
Number of STP: 37
Total Capacity : 131 MLD
Sewerage Services Accomplishments in Manila Water
26 26
Olandes Wastewater System
Project Name Capacity, MLD Location Beneficiaries Status
Olandes 10 FVR Road, Marikina City
Sitio Olandes, Cinco Hermanos, Industrial Valley, St. Ignatius, Blue Ridge A&B;
11,000 Population served.
Operational
Pinagsama
Sewerage Services : Completed Projects
27 27
Pineda Wastewater System
Project Name Capacity, MLD Location Beneficiaries Status
Pineda 4 MRR. Road, Barangay Pineda, Pasig City
Barangay Pineda and Capitolyo, Pasig City
18,000 population served Operational
Sewerage Services : Completed Projects
28 28
Makati Poblacion
Project Name Capacity, MLD Location Beneficiaries Status
Makati Poblacion 11 S. Osmeña Street Barangay Poblacion, Makati City
Barangay Poblacion, Olympia, and Valenzuela, Makati
40,000 population served
Operational
Sewerage Services : Completed Projects
29 29
Pinagsama Project Name Capacity, MLD Location Beneficiaries Status
Pinagsama 8
Ipil-ipil St. Barangay Signal Village, Taguig City
Pinagsama, Ph1, Ph2, AFP/PNP vill Ph2 and Signal Village;
42,000 population served
Completed
Sewerage Services : Completed Projects
30 30
Road 5
Project Name Capacity, MLD Location Beneficiaries Status
Road 5 4 Road 5, Project 6, Quezon City.
Project 6
10,714 Population served Completed
M A P
Project Site
CST 20 Road 5
Sewerage Services : Completed Projects
31 31
East Avenue
Project Name Capacity, MLD Location Beneficiaries Status
East Avenue 16 DENR forestry Compund, East Avenue Quezon City
Barangay Central, Teacher’s Village and portions of Kamias, Quezon City.
Operational
M A P
STP
Other CSTs
Force Mains
Sewerage Services : Completed Projects
32 32
Ongoing WasteWater Projects
33 33
Marikina North Project Name Capacity, MLD Location Beneficiaries Status
Marikina North 100 Balubad, Marikina City
Northern barangays of Marikina city and portion of San Mateo Rizal
On-going Construction
Sewerage Services : Ongoing Projects
34 34
Taguig North (Libingan ng mga Bayani)
Project Name Capacity, MLD Location Beneficiaries Status
Taguig North (LNMB)
75 Bayani Road, Taguig
Barangay Bel-Air, Forbes, AFPOVAI, BNS, Western Bicutan, San Lorenzo Vill.;
On-going Construction
Sewerage Services : Ongoing Projects
35 35
Project Name Capacity (MLD) Location Beneficiaries Status
Pasig North &
South (Ilugin)
100 MLD
expandable to
120MLD
Pinagsama, Pasig
City
Pasig, portions of Quezon City,
Mandaluyong, Cainta and
Taytay
STP for construction
& network for
detailed design
North & South Pasig
Sewerage Services : Ongoing Projects
36 36
FutureWasteWater Projects
38 38
Makati Manila
Mandaluyong West
San Mateo Rodrguez
Sewerage Services : Proposed Projects
Taguig Central
• Future Plans subject to MWSS approval of 2013
Business Plan
QC West
39 39
SJ South
Antipolo
East of Manggahan
QC South
Sewerage Services : Proposed Projects
QC North
Qc East
Marikina South
• Future Plans subject to MWSS approval of 2013
Business Plan
40 40
North SpTP
South SpTP
Sanitation Programs
For area not covered by separate
system
Desludging cycle every 5 -7
years
7-10 years desludging tanker
replacement program
42 42
Call for Cooperation
Government support
- Land/ ROW acquisition
- Permit acquisition
- Local Ordinances
- Cooperation in the maintenance of drainage system
- Enforcement of policies / ordinances
Regular Desludging ( 5-7 years cycle)
Connection to Existing Sewer Network
Solid Waste Management