2
Discrimination Cur Image Source: Amtech P By Steven McFadyen on November 3rd, 2014 Carrying out a protection system discrimination study is critical to ensure the correct functioning of the electrical system in the event of faults. The IEC defines discrimination as: overcurrent discrimination coordination of the operating characteristics of two or more overcurrent protective devices such that, on the incidence of overcurrents within stated limits, the device intended to operate within these limits does so, whil the other(s) does (do) not Note – Distinction is made between series discrimination, involving different overcurrent protective devices passing substantially the same overcurrent, and network discrimination involving identical protective devices passing different proportions of the overcurrent. Electrical engineers are called upon to produce a discrimination study at various stages within a project. If you are looking to have a protection discrimination study carried out or have been tasked with doing one, here are a few tips to help ensure you have a better than average study: 1. Do IT Early 2. The earlier in the project a study is carried out, the better. Ideally the initial study should be carried out in the design phase and then refined during construction and as equipment selection becomes finalized. Leaving the study till the end of the installation, will make any necessary changes more costly to implement. Carrying out a study earlier, will not only lead to a betterdesigned system, but can influence equipment selection and drive the cost of the system down. 3. Short Circuit and Earth Faults Ensure the study covers both short circuit and earth faults. In practice, both the short circuit and earth fault currents can be different and could affect the overall functioning of the protection systems. In additio relay and protective devices often have different settings for short circuit and earth faults. 4. More Than Curves [Current Limiting Breakers] Often discrimination studies finish once the curves have been drawn. IEC 60947 is clear that for current limiting breakers and high levels of short circuit, discrimination can only be verified by tests. All manufacturers have carried out these tests, and reviewing their literature to ensure discrimination in this re in addition to producing discrimination curves for lower fault levels makes for a complete study. 5. No Source and Load End Discrimination

Tips LV Coordination

Embed Size (px)

DESCRIPTION

Low Voltage Protection coordination

Citation preview

  • DiscriminationCurvesImageSource:AmtechPower

    ByStevenMcFadyenonNovember3rd,2014

    Carryingoutaprotectionsystemdiscriminationstudyiscriticaltoensurethecorrectfunctioningoftheelectricalsystemintheeventoffaults.TheIECdefinesdiscriminationas:

    overcurrentdiscrimination

    coordinationoftheoperatingcharacteristicsoftwoormoreovercurrentprotectivedevicessuchthat,ontheincidenceofovercurrentswithinstatedlimits,thedeviceintendedtooperatewithintheselimitsdoesso,whiletheother(s)does(do)not

    NoteDistinctionismadebetweenseriesdiscrimination,involvingdifferentovercurrentprotectivedevicespassingsubstantiallythesameovercurrent,andnetworkdiscriminationinvolvingidenticalprotectivedevicespassingdifferentproportionsoftheovercurrent.

    Electricalengineersarecalledupontoproduceadiscriminationstudyatvariousstageswithinaproject.Ifyouarelookingtohaveaprotectiondiscriminationstudycarriedoutorhavebeentaskedwithdoingone,hereareafewtipstohelpensureyouhaveabetterthanaveragestudy:

    1. DoITEarly2. Theearlierintheprojectastudyiscarriedout,the

    better.Ideallytheinitialstudyshouldbecarriedoutinthedesignphaseandthenrefinedduringconstructionandasequipmentselectionbecomesfinalized.Leavingthestudytilltheendoftheinstallation,willmakeanynecessarychangesmorecostlytoimplement.Carryingoutastudyearlier,willnotonlyleadtoabetterdesignedsystem,butcaninfluenceequipmentselectionanddrivethecostofthesystemdown.

    3. ShortCircuitandEarthFaultsEnsurethestudycoversbothshortcircuitandearthfaults.Inpractice,boththeshortcircuitandearthfaultcurrentscanbedifferentandcouldaffecttheoverallfunctioningoftheprotectionsystems.Inaddition,relayandprotectivedevicesoftenhavedifferentsettingsforshortcircuitandearthfaults.

    4. MoreThanCurves[CurrentLimitingBreakers]Oftendiscriminationstudiesfinishoncethecurveshavebeendrawn.IEC60947isclearthatforcurrentlimitingbreakersandhighlevelsofshortcircuit,discriminationcanonlybeverifiedbytests.Allmanufacturershavecarriedoutthesetests,andreviewingtheirliteraturetoensurediscriminationinthisregioninadditiontoproducingdiscriminationcurvesforlowerfaultlevelsmakesforacompletestudy.

    5. NoSourceandLoadEndDiscrimination

  • Incomplexsystems,achievingfulldiscriminationbecomesalmostimpossible.Avoidtryingtodiscriminatebetweenthesourceandloadendofcables(ifbothhaveprotectivedevices).Bothdevicesisolatethesamesectionoftheelectricalsystem,makingnodifferenceifeitheronetrips.Anypotentialbenefitsoftryingtonarrowthefaultlocationtowithinthecableisgoingtobelostinmoretimerequiredforupstreamdevicestotripandlongerfaultdurations.

    6. NotEverythingNeedsToDiscriminateThereisnorulethateverythingneedstodiscriminateandoftenitisimpossibleorcostlytotryandachievethis.Byunderstandingthesystem,it'soperationandtheeffectsonthebusinessofpowerloss,amoreengineereddiscriminationschemecanbeachieved.

    7. UseSoftwareInallbutthesimplestinstances,youshouldusesoftwaretocarryoutboththefaultcalculationsandsettingoftheprotectivedevices(discriminationcurves).Tryingtodothingsbyhand,willleadtomistakesandcompromiseinsimplifyingtheamountofwork.Softwarealsoallowsthetestingofwhatiftypescenariostoimprovesystemdesign,installation,andoverallcost.

    8. ABetterReportTheresultofanystudyisusuallytheprotectiondiscriminationreport.Spendtimeandeffortonthis.Considerthereaderandfocusthereportonthem.Keepitsimpleandavoidthetemptationtoexpanditwithwaffle.Identitywhythestudyisbeingcarriedout,anymajorissuesandtheoveralloutcome.Keepssettings,curves,supportingdata,etc.inappendices.

    9. FullyDocumentTheStudyFullydocumentthestudyinareport.Includeonlyappropriateinformationinthemainbodyandusetheappendicesforfullydocumentingthestudy.Includeallnecessaryinformationsupplyauthoritytechnicalinformation,shortcircuitandearthfaultcalculations,discriminationcurvesandcurrentlimitingchecks,recommendsettingsand/orsettingchanges,problemsandrequiredsystemmodifications/changesandanyothertechnicalinformationwhichisrequiredaspartofthestudyscope.

    Hopefully,theabovetipsshouldhelpinachievingabetterprotectiondiscriminationstudy.Thetipsaregenericandapplytonearlyalldiscriminationstudies.However,bearinmindthateachstudyisdifferent,protectionsystemscanbecomplex,focusedaroundaparticulartechnologyorwithaspecificenduserrequirementinmind.Itisuptotheelectricalengineertobringeverythingtogetherandtodelivertotheclientaprotectiondiscriminationstudywhichdeliversresults.