Timeline for the oneM2M Partnership Project

Timeline and Milestones

[Joachim Koss, ETSI] Contribution to oneM2M plenary, 05 Mar 2012

Doc:Source: ETSIAgenda item: 7

Editors note:[Text in red within square brackets: To be deleted]Text in blue: New inserted textbased on version of 20 Jan 2012 (input to CoU V1a)

Page 2: Timeline for the oneM2M Partnership Project Timeline and Milestones [Joachim Koss, ETSI] Contribution to oneM2M plenary, 05 Mar 2012 Doc: Source: ETSI

Introduction

Summary of timeline discussion at Washington meeting:• [M2MCons02_31 Draft Meeting Report.doc]

“Mr. Foote presented a table that captures a summary of the SDO positions along with a list of consensus items [M2MCons02_26]. There is agreement that the launch of the consolidated group should take place no later than 1Q2012, with the understanding that milestones will be met along the way to meet the established threshold criteria.”

• [M2MCons02_26 - Summary of SDO proposals on M2M Consolidation 4.4.pptx]“Launch of consolidated group no later than 1Q2012, with milestones to be met along the way to meet the threshold criteria.”

In order to keep the envisaged date for launch of the M2M consolidation (Q1/2012) a more detailed time schedule with well defined milestones is necessary.The next pages propose a timeline including milestones and definition of milestones.

2

Page 3: Timeline for the oneM2M Partnership Project Timeline and Milestones [Joachim Koss, ETSI] Contribution to oneM2M plenary, 05 Mar 2012 Doc: Source: ETSI

JUL AUG SEP OCT DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT

M6:WG start prepared

Virtual meetings

2011 2012

Timeline

3

SDO Meeting#01,Seoul, 21 Jul

SDO Meeting#02,Washington,17-18 Aug

SDO Meeting#03,Berlin, 15-16 Dec

Reach out to verticals

M1: “Soft Launch”

M2: Final Consensus

M4: Official Signing

Technical Plenary Meeting#1

Virtual SDO meetings

SDO Meeting#04,Tokyo, 28-29 Mar

M3: Final Draft

Virtual meetings

Steering Committee Meeting#1

Steering Committee Meeting#2

M5:TP start prepared

Page 4: Timeline for the oneM2M Partnership Project Timeline and Milestones [Joachim Koss, ETSI] Contribution to oneM2M plenary, 05 Mar 2012 Doc: Source: ETSI

Milestones (1) Milestone M1 – “Soft Launch”

• IPR regime agreed• Communiqué released• Material for communication with verticals updated to include Berlin meeting

results• Target date: 18 Jan 2012, completed

Milestone M2 – Final Consensus• Feedback from vertical reach outs incorporated into major principles• Final Consensus reached and documented on all major principles (scope,

partnership and participation principles, structure, legal status, participation rules, rights and responsibilities, level of secretariat services, funding)

• Initial Organizations identified and start work on drafting the founding documents

• Target date: [17 Feb] 14 Mar 2012

4

Page 5: Timeline for the oneM2M Partnership Project Timeline and Milestones [Joachim Koss, ETSI] Contribution to oneM2M plenary, 05 Mar 2012 Doc: Source: ETSI

Milestones (2) Milestone M3 – Final Draft

• Final review of feedback from vertical reach outs • Final draft of founding documents available

(Participation rules, procedures, IPR policy and anti-trust policy, membership fee structure and initial resources agreed upon

• Secretariat support activities identified(online web presence, on-site meeting support, document editing, document management, branding/publicity)

• Convenor of Steering Committee nominated• Target date: [9 Mar] 30 Mar 2012

Milestone M4 – Official Signing• Founding agreement signed• Provision of secretariat function agreed upon• Members of Steering Committee identified• Preliminary list of members of the initiative identified• Target date: [30 Mar] 04 May? 2012

5

Page 6: Timeline for the oneM2M Partnership Project Timeline and Milestones [Joachim Koss, ETSI] Contribution to oneM2M plenary, 05 Mar 2012 Doc: Source: ETSI

Milestones (3) Milestone M5 – TP start prepared

• Convenor of Technical Plenary nominated• Participants of Technical Plenary identified• Working Procedures approved• List of standards/specifications to be transferred into GI agreed • Target date: [19 Jun] 24 Jul 2012

Milestone M6 – WG start prepared• Initial Work Plan defined• Initial Working Groups defined• Convenors of Working Groups nominated• Meeting schedule defined• Target date: [31 Jul] 04 Sep 2012