12
Time Management Mock Exam Lab for PMP Exam Prep Course Part 1 #346 Instructor: Neal L. Rowland, PMP

Time Management Mock Exam - GogoTraininggogotraining.com/media/gogogh_courses_downloads/115/Time... · 2010. 8. 9. · Time Management Mock Exam Lab for PMP Exam Prep Course Part

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Time Management Mock Exam - GogoTraininggogotraining.com/media/gogogh_courses_downloads/115/Time... · 2010. 8. 9. · Time Management Mock Exam Lab for PMP Exam Prep Course Part

Time Management Mock Exam

Lab for PMP Exam Prep Course Part 1

#346

Instructor: Neal L. Rowland, PMP

Page 2: Time Management Mock Exam - GogoTraininggogotraining.com/media/gogogh_courses_downloads/115/Time... · 2010. 8. 9. · Time Management Mock Exam Lab for PMP Exam Prep Course Part

10 Practice Questions

Move at Your Own Pace

Page 3: Time Management Mock Exam - GogoTraininggogotraining.com/media/gogogh_courses_downloads/115/Time... · 2010. 8. 9. · Time Management Mock Exam Lab for PMP Exam Prep Course Part

Question 1

• Based on project activity dependencies, scheduled activities will be arranged in the Schedule Network Diagram. In which of the following processes will you identify and document these dependencies among scheduled activities?

©2010 Neal Rowland 3

A. Sequence Activities

B. Define Activities

C. Develop Schedule

D. Estimate Activity Durations

Page 4: Time Management Mock Exam - GogoTraininggogotraining.com/media/gogogh_courses_downloads/115/Time... · 2010. 8. 9. · Time Management Mock Exam Lab for PMP Exam Prep Course Part

Question 2 • A project you are working on has received

duration estimates from the engineering department. Which is your next best action?

©2010 Neal Rowland 4

A. Determine what resources are needed

and revise activity resource estimates

B. Schedule the activity

C. Analyze the estimates using PERT

or comparable technique

D. Communicate the estimates to the

customer and acquire formal acceptance

Page 5: Time Management Mock Exam - GogoTraininggogotraining.com/media/gogogh_courses_downloads/115/Time... · 2010. 8. 9. · Time Management Mock Exam Lab for PMP Exam Prep Course Part

Question 3 • You have learned that two technical architects have

been rolled off another project, and you can use them for your project. You must figure out the best use of these scarce resources. What is your best action?

©2010 Neal Rowland 5

A. Network with functional managers to acquire the team members for the length of the project

B. Place the resources on activities with free float to give them time to learn the project objectives and work required

C. Allocate the resources to critical path activities first

D. File proper change control forms to acquire the resources

Page 6: Time Management Mock Exam - GogoTraininggogotraining.com/media/gogogh_courses_downloads/115/Time... · 2010. 8. 9. · Time Management Mock Exam Lab for PMP Exam Prep Course Part

Question 4

• The schedule compression technique includes fast tracking and crashing. The main purpose of applying the schedule compression technique is to:

©2010 Neal Rowland 6

A. Shorten the schedule without increasing the risk

B. Shorten the schedule by changing the Critical Path work

packages

C. Shorten the schedule without

increasing the cost

D. Shorten the schedule without

changing the Scope

Page 7: Time Management Mock Exam - GogoTraininggogotraining.com/media/gogogh_courses_downloads/115/Time... · 2010. 8. 9. · Time Management Mock Exam Lab for PMP Exam Prep Course Part

Question 5

• Activity, ‘UAT,’ has an early start (ES) of day 6, a late start (LS) of day 10, an early finish (EF) on day 12, and a late finish (LF) on day 16. Based on this information, which of the following statements accurately describes activity ‘UAT’ in the Network Diagram?

©2010 Neal Rowland 7

A. It is a dummy Node

B. It is not on the Critical Path

C. It is on the Critical Path

D. It has a LAG of 4 days

Page 8: Time Management Mock Exam - GogoTraininggogotraining.com/media/gogogh_courses_downloads/115/Time... · 2010. 8. 9. · Time Management Mock Exam Lab for PMP Exam Prep Course Part

Question 6

• Which of the following techniques uses a weighted average to estimate project costs?

©2010 Neal Rowland 8

A. Three-Point Estimate

B. Critical Path Method

C. Precedence Diagramming

Technique

D. Graphical Evaluation and

Review Technique

Page 9: Time Management Mock Exam - GogoTraininggogotraining.com/media/gogogh_courses_downloads/115/Time... · 2010. 8. 9. · Time Management Mock Exam Lab for PMP Exam Prep Course Part

Question 7

• The output of Develop Schedule process includes all EXECPT:

©2010 Neal Rowland 9

A. Project Calendar B. Schedule

Network Diagrams

C. Project Schedule D. Time

Management Plan

Page 10: Time Management Mock Exam - GogoTraininggogotraining.com/media/gogogh_courses_downloads/115/Time... · 2010. 8. 9. · Time Management Mock Exam Lab for PMP Exam Prep Course Part

Question 8 • The Ethical Committee meeting is scheduled for Friday.

As of today, Tuesday, Activity ACT is 45 days into its 50 day scheduled duration time. Activity EC is the next scheduled activity on the schedule. ACT and EC have a finish to start dependency. EC has a scheduled duration of 3 days. When is the earliest your team can start on Activity EC?

©2010 Neal Rowland 10

A. After the Ethical Committee meeting

B. Thursday

C. Day 48

D. Today: Tuesday

Page 11: Time Management Mock Exam - GogoTraininggogotraining.com/media/gogogh_courses_downloads/115/Time... · 2010. 8. 9. · Time Management Mock Exam Lab for PMP Exam Prep Course Part

Question 9 • The project is 4 months into production. Market

conditions require different materials to be used. This approved change requires more preparation steps prior to application. How does this affect the project’s WBS?

©2010 Neal Rowland 11

A. No changes are needed, the steps are added to the project schedule

B. Planning is complete, the steps are added during execution

C. Work packages are altered or added to the WBS

D. The changes are noted in the Configuration Management System, the Scope Baseline remains unchanged

Page 12: Time Management Mock Exam - GogoTraininggogotraining.com/media/gogogh_courses_downloads/115/Time... · 2010. 8. 9. · Time Management Mock Exam Lab for PMP Exam Prep Course Part

Question 10

• The Project Scope has been clearly defined, and the Project Team has decided to use the activity list and WBS to estimate the project cost/duration. This approach is called?

©2010 Neal Rowland 12

A. Bottom-up Estimation

B. Top-down Estimation

C. Analogous Estimation

D. Expert Judgment