105
TIME AT LARGE AND REASONABLE TIME FOR COMPLETION ONG RUI YING UNIVERSITI TEKNOLOGI MALAYSIA

Time at Large and Reasonable Time for Completion

Embed Size (px)

Citation preview

Page 1: Time at Large and Reasonable Time for Completion

TIME AT LARGE AND REASONABLE TIME FOR COMPLETION

ONG RUI YING

UNIVERSITI TEKNOLOGI MALAYSIA

Page 2: Time at Large and Reasonable Time for Completion
Page 3: Time at Large and Reasonable Time for Completion
Page 4: Time at Large and Reasonable Time for Completion

TIME AT LARGE AND REASONABLE TIME FOR COMPLETION

ONG RUI YING

A project report submitted in partial fulfillment of the

requirement for the award of the degree of

Master of Science (Construction Contract Management)

Faculty of Built Environment

Universiti Teknologi Malaysia

JUNE 2007

Page 5: Time at Large and Reasonable Time for Completion
Page 6: Time at Large and Reasonable Time for Completion

iii

Dedicated to my personal Lord and Saviour Jesus Christ

and to my beloved parents and siblings.

Page 7: Time at Large and Reasonable Time for Completion

iv

ACKNOWLEDGEMENTS

First of all, I would like to express my gratitude to my supervisor, Assoc.

Prof. Dr Rosli Abdul Rashid for his guidance and advice in order to complete this

master project. A special thanks to all the lecturers for the course of Master of

Science (Construction Contract Management), for their patience and kind advice

during the process of completing the master project.

A debt of gratitude is owed to many individuals who have also given me

support, help and tolerance in writing and completing this master project. Not

forgetting my dearest parents and siblings for their unconditional love and support.

Lastly, I would like to express my thanks to my fellow course mates, who have in

their own way helped me a great deal throughout the preparation and production

stages of this master project. Care and concern from my house mates are also

greatly appreciated.

Page 8: Time at Large and Reasonable Time for Completion

v

ABSTRACT

Time is an extremely important issue in construction. Timely completion of the

construction works by the contractor is of great importance to the employer.

Therefore, most construction contracts specify time for performance in achieving

completion of the works. However, during the execution of the contract,

circumstances may arise which render that completion date unenforceable. At

common law, the contractor’s obligation to complete the works by the specified date

is removed if the employer delays the contractor in the execution of the works. When

the specified completion date no longer applies, time is said to be “at large”, and the

contractor’s obligation is merely to complete the works within a reasonable time.

What does it mean by reasonable time? It is most certainly not “as and when the

contractor sees fit”. The study is aimed at determining the meaning of “reasonable

time” when time is at large. Findings of this study will assist contractors to assess a

reasonable time to complete the works when time at large occurs. The approach

adopted in this research is case law based. There are no limitations as for the court

cases referred to in this study in terms of type of projects as long as the case is

related to reasonable time. A total of ten cases centered on what is a reasonable time

were studied. Through the analysis of courts’ judgments, the meaning of “reasonable

time” when time at large occurs was determined. “Reasonable time” means

reasonable under the existing circumstances, assuming that those circumstances, in

so far as they involve delay, are not caused or attributed to by him and excluding

circumstances which were under the control of the contractor, considering what in

ordinary circumstances was a reasonable time for performance and then considering

to what extent the time for performance of the contractor was in fact extended by

extraordinary circumstances outside his control.

Page 9: Time at Large and Reasonable Time for Completion

vi

ABSTRAK

Masa merupakan satu isu yang penting di dalam pembinaan. Kerja

pembinaan yang disiapkan oleh kontraktor tepat pada masanya adalah satu aspek

yang amat penting kepada majikan. Oleh itu, kebanyakan kontrak pembinaan

menetapkan masa untuk penyiapan kerja. Bagaimanapun, ketika perlaksanaan

kontrak, keadaan-keadaan yang tertentu mungkin timbul dan menyebabkan tarikh

penyiapan tidak boleh dikuatkuasakan. Di dalam ‘common law’ kewajipan

kontraktor untuk menyiapkan kerja pada masa yang ditetapkan akan dibatalkan

sekiranya majikan melambatkan kontraktor dalam perlaksanaan kerja. Apabila masa

penyiapan kerja yang ditetapkan tidak dapat dikuatkuasakan lagi, situasi ‘time at

large’ akan berlaku dan tanggungjawab kontraktor hanyalah menyiapkan kerja dalam

masa yang wajar. Apakah makna masa yang wajar? Pastilah bukan “sebagaimana

dan apabila kontraktor rasa sesuai”. Kajian ini adalah untuk menentukan makna

“masa yang wajar” apabila keadaan ‘time at large’ berlaku. Dapatan kajian ini akan

membantu kontraktor untuk menilai apakah masa yang wajar untuk penyiapan kerja

apabila situasi ini berlaku. Pendekatan yang digunakan dalam kajian ini adalah

berdasarkan kes undang-undang. Kes mahkamah yang dirujuk di dalam kajian ini

tidak dibataskan dari segi jenis projek, asalkan kes-kes tersebut berkaitan dengan

masa yang wajar. Sebanyak sepuluh kes yang berkaitan dengan masa yang wajar

telah dikaji. Melalui analisis keputusan mahkamah, makna “masa yang wajar” dapat

ditentukan. “Masa yang wajar” bermakna wajar di bawah keadaan yang wujud,

mengandaikan bahawa keadaan yang berkaitan dengan kelewatan tersebut bukan

disebabkan olehnya dan tidak termasuk keadaan yang di bawah kawalan kontraktor,

mempertimbangkan apa yang di bawah keadaan biasa merupakan masa yang wajar

untuk penyiapan kerja dan seterusnya mempertimbangkan sejauh mana masa untuk

menyiapkan kerja adalah dilengahkan oleh keadaan luar biasa di luar kawalannya.

Page 10: Time at Large and Reasonable Time for Completion

vii

TABLE OF CONTENTS

CHAPTER TITLE PAGE

DECLARATION ii

DEDICATION iii

ACKNOWLEDGEMENTS iv

ABSTRACT v

ABSTRAK vi

TABLE OF CONTENTS vii

LIST OF TABLES x

LIST OF CASES xi

LIST OF ABBREVIATIONS xv

1.0 INTRODUCTION

1.1 Background Studies 1

1.2 Problem Statement 5

1.3 Objective of the Research 6

1.4 Scope of the Research 6

1.5 Significance of the Research 7

1.6 Research Methodology 7

Page 11: Time at Large and Reasonable Time for Completion

viii

2.0 TIME AT LARGE

2.1 Introduction 9

2.2 Standard Form Provisions 10

2.2.1 Public Works Department (P.W.D)

Form 203A (Rev. 10/83) 10

2.2.2 Pertubuhan Arkitek Malaysia (PAM)

(2nd Edition, 1998) 12

2.2.3 Federation Internationale des Ingenieurs

Conseils (FIDIC) Construction Contract (1999) 14

2.3 Time for Completion 15

2.3.1 Time of the Essence 16

2.4 Damages for Late Completion 19

2.4.1 Liquidated Damages 20

2.5 Extension of Time 22

2.5.1 Purposes of Extension Provisions 22

2.5.2 Grounds for Extension of Time 24

2.5.2.1 Force Majeure 24

2.5.2.2 Variations and Extra Works 26

2.5.2.3 Exceptionally Adverse Weather

Conditions 27

2.5.2.4 Late Possession of Site 28

2.5.2.5 Sub-contractors 29

2.5.2.6 Delay in Approvals and Instructions 29

2.5.2.7 Other Commonly Stipulated Grounds 30

2.5.2.8 Causes beyond the Contractor’s Control 31

2.6 Time at Large 31

2.6.1 Events Giving Rise to Time at Large 32

2.6.1.1 No Time or Date Fixed in the Contract 35

2.6.1.2 Time or Date Ceases to Apply by Acts

of Prevention 36

2.6.1.3 Waiver 43

2.6.1.4 Failure of Contractual Machinery 44

2.7 Conclusion 45

Page 12: Time at Large and Reasonable Time for Completion

ix

3.0 REASONABLE TIME

3.1 Introduction 47

3.2 Reasonable Time 49

3.3 Statutory Provisions that Apply the term

“Reasonable Time” 54

3.3.1 Sale of Goods Act 1957 (Revised 1989) 54

3.3.2 Supply of Goods and Services Act 1982 (UK) 55

3.3.3 International Sales 56

3.4 Conclusion 57

4.0 REASONABLE TIME WHEN TIME IS AT LARGE

4.1 Introduction 59

4.2 Reasonable Time when Time is at Large 60

4.2.1 Reasonable Time Where No Time for

Completion is specified in the Contract/

Contract is Silent as to Time 60

4.2.2 Reasonable Time where the Stipulated Date

Has ceased to be Applicable by Reason of

Prevention or Breach 68

4.3 Conclusion 78

5.0 CONCLUSION AND RECOMMENDATIONS

5.1 Introduction 80

5.2 Summary of Research Findings 80

5.3 Problems Encountered during Research 82

5.4 Conclusion 82

REFERENCE 83

BIBLIOGRAPHY 85

Page 13: Time at Large and Reasonable Time for Completion

x

LIST OF TABLES

TABLE NO TITLE PAGE

4.1 Reasonable time where no time for completion is specified

in the contract/contract is silent as to time 73

4.2 Reasonable time where the stipulated date has ceased to be

applicable by reason of prevention or breach 76

Page 14: Time at Large and Reasonable Time for Completion

xi

LIST OF CASES

CASES PAGE

A Bell & Son (Paddington) Ltd v CBF Residential Care and

Housing Association. (1989) 46 BLR 105

11

Abdul Rahim bin Syed Mohd v Ramakrishnan Kandasamy &

Anor. [1996] 3 MLJ 385, HC

17

Afovos Shipping Co v Pagnan [1983] 1 WLR 195 at 201 (HL) 10

Amalgamated Building Contractors Ltd v Waltham Holy Cross

Urban District Council [1952] 2All ER452 at 452 (CA).

36

Amherst v James Walker [1983] Ch 305 at 315 (CA) 48

Arab Malaysian Corpn Builders Sdn Bhd v ASM Development

Sdn Bhd. [1998] 6 MLJ 136

20

Astea (UK) Limited v Time Group Limited [2003] EWHC 725

(TCC)

43

Attwood v Emery (1856), 1 CB (NS) 110; 26 LJCP 73 54

Ayadurai v Lim Hye [1959] MLJ 143 17

Balfour Beatty Building Ltd v Chestermount Properties Ltd 62

Build LR 1

45

Barque Quilpue Ltd v Bryant (1904) 36

Bernhard’s Rugby Landscapes Ltd v Stockley Park

Consortium (No 2) [1998]

44

BFI Group of Companies Ltd v DCB Integration Systems Ltd

[1987] CILL 328

11

Bilton v Greater London Council (1982) 20 BLR 1, HL 23, 42

Page 15: Time at Large and Reasonable Time for Completion

xii

CASES PAGE

British and Commonwealth Holdings plc v Quadrex Holdings Inc.

[1989] QB 842; [1989] 3 All ER 492, CA

16

British Steel Corporation v Cleveland Bridge & Engineering Co

Ltd [1984] 1 All ER 504, 24 Build LR 94.

64

Bruno Zornow (Builders) Ltd v Beechcroft Developments Ltd

(1989) 51 BLR 16

2

CCECC (HK) Ltd v Might Foundate Developement Ltd & Ors

[2001] HKCU 916

69

Chaffer and Tassie v Richards (1905) 26 NLR 20. 27

Charles Rickards Ltd v Oppenheim [1950] 1 KB 616. 43

Charnock v Liverpool Corporation [1968] 1 WLR 1498 (CA) 48

Chye Fook & Anor v Teh Teng Seng Realty Sdn Bhd

[1989] 1 MLJ 308, HC.

18

Dodd v Churton [1897] 1 QB 562 (CA). 42

Earth & General Contractors Ltd v Manchester Corporation

(1958) 108 LJ 665

28

Etablissements Chainbaux S.A.R.L. v Harbormaster Ltd

[1955] 1 Lloyd’s Rep. 303

69

Fairclough v Rhuddlan Borough Council (1985). 29

Felton v Wharrie (1906) 28

Fisher v Ford (1840), 12 Ad. & El. 654 59

Ganam d/o Rajamany v Somoo s/o Sinnah [1984] 2 MLJ 290. 18

Gaymark Investments Pty Ltd v Walter Construction Group

(1999) NTSC 143, (1999) 16 BCL 449; (2005) 21 Const LJ 70

33

Greater London Corporation v Cleveland Bridge and

Engineering (1984) 34 BLR 57

48

Hock Huat Iron Foundry v Naga Tembaga Sdn Bhd

[1999] 1 MLJ 65.

19

Holme v Guppy (1838) 3 M&W 387 4, 22, 28, 36

Hydraulic Engineering Co Ltd v McHaffie, Goslett & Co.

(1878) 4 QBD 670

52, 54

Ismail bin Haji Embong v Lau Kong Han [1970] 2 MLJ 213 17

Page 16: Time at Large and Reasonable Time for Completion

xiii

CASES PAGE

J and J Fee Ltd v The Express Lift Company Ltd

[1993] 34 ConLR 147.

36

Jamshed Khodaram Irani v Burjorni Dunjibhai

(1915) LR 43 IA 26

17

Kenny and Hingles’ Trustee v Union Government (1928) TD 272 27

Lai Yew Seong v Wong Chieu Gook (1913) 1 FMSLR 12 17

LeBaupin v Crispin [1920] 2 KB 714. 25

Linggi Plantations Ltd v Jagatheesan [1972] 1 MLJ 89 21

Lombard plc v Butterworth [1987] Q.B. 27 at 535 (C.A.) 20

Lyle Shipping Co. v Cardiff Corporation [1900] 2 QB 638 54

Maniam v The State of Perak [1975] MLJ 75 21

Meyer v Gilmer (1899) 18 NZLR 129 42

Mohamed Habidullah v Bird & Co. AIR 1922 PC 178 17

Murdoch v Lockie (1897) 15 NZLR 296 42

Neodox Ltd v Swinton and Pendlebury Borough Council (1958) 5

BLR 34

53

North West Metropolitan Regional Hospital Board v Bickerton

(1970)

29

Panamena Europea Navigacion (Compania Limitada) v

Frederick Leyland & Co Ltd [1947] AC 428 (HL).

32, 45

Pantland Hick v Raymond & Reid [1893] AC 22. 60

Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd

(1970) 1 BLR 111

13, 29, 39

Percy Bilton v Greater London Council [1982] 1 WLR 794 29, 38

Raineri v Miles [1981] AC 1050 (HL) 48

Rapid Building Group v Ealing Family Housing Association Ltd

(1984) 29 BLR 5

4, 13, 22, 28, 39

Rickards v Oppenheim [1950] 1 KB 616 69

Russell v Viscount Sa da Bandeira (1862) 13 CB (NS) 149 42

Sim Chio Huat v Wong Ted Fui [1983] 1 MLJ 151. 17, 21

Sims & Co. v Midland Railway Co. [1913] 1 KB 103 63

Page 17: Time at Large and Reasonable Time for Completion

xiv

CASES PAGE

Shawton Engineering Ltd v DGP International Ltd

[2005] EWCA Civ 1359.

70

SMK Cabinets v Hili Modern Electrics Pty Ltd [1984] VR 391;

(1984) 1 Const LJ 159

36, 42

Startup v Macdonald (1843), 6 Man. & G. 593 59

Tan Ah Kian v Haji Hasnan [1962] MLJ 400, HC;

[1963] MLJ 175, FC.

18

Taylor v The Great Northern Railway Company [LR] 1 CP 385. 62

Temloc Ltd v Enrill Properties Ltd (1987) 39 BLR 30 12

Tew v Newbold-on Avon School Board (1884) 1 C&E 260 42

Thamesa Designs Sdn Bhd v Kuching Hotels Sdn Bhd

[1993] 3 MLJ 25

21

The Lyle Shipping Company Ltd v The Corporation of Cardiff

[1900] 2 QB 638.

62

Thornhill v Neats (1860) 8 CB (ns) 149 42

Trollope & Colls Ltd v NW Metropolitan Regional Hospital

[1973] 1 WLR 601 (HL)

42

United Scientific Holdings Ltd v Burnley Borough Council

[1977] 2 All ER 62, HL, [1978] AC 1050 (HL)

3, 16

Yeoh Kim Pong Realty Ltd v Ng Kim Pong [1962] MLJ 118 17, 18

Walter Lawrence v Commercial Union Properties

(1984) 4 ConLR 37.

27

Wells v Army and Navy Cooperative Society (1902) 86 LT 764 41

Westwood v Secretary of State for India (1863) 7 LT 736 42

Page 18: Time at Large and Reasonable Time for Completion

xv

LIST OF ABBREVIATIONS

AC Law Reports Appeal Case

All ER All England Law Reports

ALJ Australian Law Journal

ALR Australian Law Reports

ALJR Australian Law Journal Reports

App Cas Appeal Cases

B Beavan

B & S Best and Smith’s Reports

Build LR Building Law Reports

CA Court of Appeal

CB Common Bench Reports

Ch Chancery

Ch App Chancery Appeal

Ch D The Law Reports, Chancery Division

CIDB Construction Industry Development Board

CLD Construction Law Digest

DC Divisional Court, England

Const LJ Construction Law Journal

Const LR Construction Law Reports

CP Law Reports, Common Pleas

CPD Law Reports, Common Pleas Division

DLR Dominion Law Reports

Exch Exchequer Reports

Eq Equity Case

EWHC High Court of England anf Wales Decisions

Page 19: Time at Large and Reasonable Time for Completion

xvi

FC Federal Court

F & F Foster & Finlayson’s Reports

H & N Hurlstone & Norman’s Exchequer Reports

HL House of Lords

HKC Hong Kong Cases

HKLR Hong Kong Law Reports

IR Irish Reports

JKR Jabatan Kerja Raya

KB King Bench

LGR Local Government Reports

LJKB (QB) Law Journal Reports, King’s (Queen’s) Bench

Lloyd’s Rep Lloyd’s List Reports

LR Law Reports

LT Law Times Reports

JP Justice of the Peace / Justice of the Peace Reports

MLJ Malayan Law Journal

NZLR New Zealand Law Reports

PAM Pertubuhan Arkitek Malaysia

PWD Public Work Department

PD Probate, Divorce and Admiralty Division of High Court

QB Queen Bench

TCC Technology and Construction Court

SLR Singapore Law Reports

WLR Weekly Law Reports

WR Weekly Reports

Page 20: Time at Large and Reasonable Time for Completion

CHAPTER 1

INTRODUCTION

1.1 Background Studies

Time is an extremely important issue in construction. Together with cost and

quality, it is a primary objective of project management, and a major criterion by

which the success of a project is judged. The scope of this subject includes three

basic time-related issues which are commencement, progress and completion

(Murdoch and Hughes, 2000). This may be seen from clause 21.1 of PAM 98:

On the Date of Commencement stated in the Appendix, possession of

the site shall be given to the Contractor who shall thereupon begin the

Works, and regularly and diligently proceed with the same and

complete the same on or before the Date for Completion stated in the

Appendix subject to any extension of time in accordance with Clause

23.0 and/or sub-clause 32.1(iii).

clause 38(b) of PWD 203A which states:

Page 21: Time at Large and Reasonable Time for Completion

2

Unless the Contract Documents shall otherwise provide, possession of

the Site as complete as may reasonably be possible but not so as to

constitute a tenancy, shall be given on or before the “Date of

Possession” stated in the Letter of Acceptance of Tender to the

Contractor who shall thereupon and forthwith commence the Works

(but subject to sub-clause (a) hereof) and regularly and diligently

proceed with and complete the Works on or before the Date of

Completion as stated in the Appendix.

and clause 23.1 of JCT 98, which states:

On the Date of Possession possession of the site shall be given to the

contractor who shall thereupon begin the Works, regularly and

diligently proceed with the same and shall complete the same on or

before the Completion Date.

Contracts of all kinds commonly specify a date for the performance of some

obligation (Wallace, 1995). Where it comes to building contracts, stipulated periods

are provided within which the buildings have to be delivered became an essential

condition of the agreement (Guest, 1975). It is usual to name the date by which

completion is required, as can be seen in Clause 39 of PWD 203A. Even where no

precise date has been included in the contract itself, a court may be persuaded to

imply a term for completion by a certain date, on the ground that the parties must

have intended this, as seen in Bruno Zornow (Builders) Ltd v Beechcroft

Developments Ltd1 . The contractor’s obligation to complete the works by the

completion date is, like all such obligations, backed up by legal sanctions. Under

certain types of contract (for example contracts for the sale of perishable goods), time

is expressly or impliedly “of the essence”. Consequently, the employer’s remedy for

any lateness in performance or completion will be an award for damages for breach of

contract (Murdoch and Hughes, 2000).

1 (1989) 51 BLR 16.

Page 22: Time at Large and Reasonable Time for Completion

3

Under what circumstances can time be held to be of the essence of a contract?

According to Chow (2004), in United Scientific Holdings Ltd v Burnley Borough

Council2, the House of Lords, citing with approval a statement on the position in

Halsbury’s Laws of England (4th Ed), ruled that time should not be held to be of the

essence unless the following conditions are present:

1. The parties must have expressly stipulated in the contract that conditions as to

time should be strictly complied with

2. The nature of the subject-matter of the contract and the surrounding

circumstances demonstrate that time should be considered to be of the essence

3. The party who has been subjected to unreasonable delay gives notice to the

party in default making time of the essence

Section 56 (3) of Contract Act 1950 states the effect of acceptance of

performance at time other than agreed (the completion date which is also the essence

of the contract) upon, which reads:

If, in case of a contract voidable on account of the promisor’s failure

to perform his promise at the time agreed, the promisee accepts

performance of the promise at any time other than that agreed, the

promisee cannot claim compensation for any loss occasioned by the

non-performance of the promise at the time agreed, unless, at the time

of the acceptance, he gives notice to the promisor of his intention to

do so.

The position in the rules contained in section 56 (3) of the Contracts Act 1950

is that: if in a contract in which time is of the essence, a party fails to perform it by

the stipulated time, the innocent party has the right either to rescind the contract, or

to treat it as still subsisting. If he treats it either expressly or by conduct as still 2 [1977] 2 All ER 62, HL, [1978] AC 1050 (HL),

Page 23: Time at Large and Reasonable Time for Completion

4

continuing, the contract exists but time ceases to be of the essence and become at

large. Consequently he cannot claim liquidated damages under the contract unless

there is a provision as to the extension of time. However, this cessation can be

revived and so time can be restored to be the essence by the innocent party serving a

notice to the party in default giving a new date of completion. If this is done, there

would be a date from which liquidated damages could be calculated (Sinnadurai,

1987).

At common law, the contractor’s obligation to complete the works by the

specified date is removed if the employer delays the contractor in the execution of

the works. When the specified completion date no longer applies, time is said to be

“at large”, and the contractor’s obligation is merely to complete the works within a

reasonable time. A fundamental point is that the time for completion can only be

extended where the contract permits, and strictly in accordance with the contract

provisions (Murdoch and Hughes, 2000). It is a common belief in the construction

industry that extensions of time are solely for the benefit of the contractor. At face

value by giving the contractor more time to complete the works and by reducing his

liability for liquidated damages they do appear to be one-sided. It is not the

contractor who has most need of extension of time provisions, it is the employer. A

string of well documented cases from Holme v Guppy3 to Rapid Building v Ealing4

confirm that the courts will not uphold liquidated damages where the employer has

prevented completion on time unless there is express provision in the contract to

extend time for the employer’s default (Eggleston, 1992).

The ultimate dispute on a construction contract is for an employer to assert

that time is of the essence and to determine without paying whilst the contractor is

claiming time to be at large and determining for non-payment (Eggleston, 1992).

3 (1838) 3 M&W 387. 4 (1984) 29 BLR 5.

Page 24: Time at Large and Reasonable Time for Completion

5

Problem also arises in the wording employed by many of the standard forms

of contract as there was a shortcoming in that some of them did not fully cater in the

extension of time clause for all delays caused by the employer. General sweep-up

wording in an extension of time clause (such as “or other unavoidable

circumstances”) has been held by the English courts not to cover employer defaults.

Similarly in Malaysia, only PAM 98 Clause 23.7(xi) allows the Architect to grant an

extension of time for “any act of prevention or breach of contract by the Employer.”

This is designed to be a “catch-all” provision so that time does not inadvertently

become at large. Other forms like IEM, PWD 203A and CIDB do not have such

similar provision (Martin, 2005). Thus, time will be at large when the employer

causes delay to the contractor e.g. by ordering extra work and there is no provision

for extension of time for the contractor.

1.2 Problem Statement

The phrase “time at large” is much loved by contractors, the suggestion that

the contractor has as much time as he wants to finish the works. This is not what it

means. Time becomes at large when the obligation to complete within the specified

time for completion of a contract is lost. The obligation then becomes to complete

within a reasonable time. It is most certainly not “as and when the contractor sees

fit”. The question then is what is a reasonable time? What is generally at stake in the

matter of whether or not time is at large is the employer’s right to deduct liquidated

damages for late completion. The right is lost completely if time becomes at large –

the employer can still sue for general or unliquidated damages for late completion –

but regard will then had to be the contractor’s entitlement to a reasonable time

(Eggleston, 1992).

Page 25: Time at Large and Reasonable Time for Completion

6

Time being “at large” does not mean that the Contractor has no obligation to

complete the work. He has to complete in a “reasonable time”. What is reasonable

will depend on all the circumstances at the time (Murdoch and Hughes, 1992).

Calculating a reasonable time is not an easy matter and, as Emden’s Building

Contracts, puts it:

When a reasonable time for completion becomes substituted for a

time specified in the contract ….then in order to ascertain what

reasonable time is, the whole circumstances must be taken into

consideration and not merely those existing at the time of the making

of the contract.

1.3 Objective of the Research

The objective of this study is to determine the meaning of “reasonable time”

when time is at large.

1.4 Scope of the Research

The approach adopted in this research is case law based. There are no

limitations as for the court cases referred to in this study in terms of type of projects

as long as the case is related to time at large and reasonable time. The standard

forms of contract that will be referred to are:

1. Pertubuhan Arkitek Malaysia (PAM) (2nd Edition, 1998)

Page 26: Time at Large and Reasonable Time for Completion

7

2. Public Works Department (P.W.D) Form 203A (Rev. 10/83)

3. Construction Industry Development Board (CIDB) Standard Form of

Contract for Building Works (2000 Edition)

4. International Federation of Consulting Engineers / Federation

Internationale des Ingenieurs Conseils (FIDIC) Construction Contract

(1999)

1.5 Significance of the Research

This research should give a review to contractor and employer as to what is

time at large and when does it apply. When the parties in the industry are equipped

with the knowledge of time at large and its implications on both contractor and

employer, this situation can be avoided as much as possible. Suggestion on what is a

reasonable time to complete the works in the event of time at large is also provided

for through this research.

1.6 Research Methodology

This research involved literature review on time-related matters in the

construction industry. Initial study will be carried out involving extensive reading

and understanding of the concepts involved.

Then data and information collecting will be carried out. Primary source will

be law cases found in Malayan Law Journal through the access of Lexis Nexis

Page 27: Time at Large and Reasonable Time for Completion

8

available in the university’s online database. Secondary sources such as articles,

journals, textbooks and related websites will also be studied and referred to in the

course of the whole research.

Analysis will be done on collected information and will be arranged in an

orderly manner. Finally, writing up will be carried out, followed by checking and

correction of writing.

Page 28: Time at Large and Reasonable Time for Completion

CHAPTER 2

TIME AT LARGE

2.1 Introduction

Most construction contracts specify time for performance in achieving

completion of the whole of the works and many have additional requirements for

phased or sectional handovers. Time may be fixed either by reference to specified

dates or by reference to a construction period. If the latter method is used it is

essential that a precise completion date can be established. This means that there

must be an identifiable commencement date from which time runs and there must be

no uncertainty on whether the construction period takes in or excludes holiday

periods. These may seem obvious matters but it is extraordinary how often in

construction industry disputes it is found that the intentions of the parties in respect

of time have not been clearly expressed or have been misapplied. (Eggleston, 1992).

Similarly, according to Chow (2004), a date is fixed from which the time for

completion begins to run. Frequently, this is the date on which the contractor takes

possession of the site, but this is by no means the rule. In large and elaborate

Page 29: Time at Large and Reasonable Time for Completion

10

projects, it is not always possible for the owner to afford the contractor

unencumbered possession of the whole site and it is quite common in these situations

for the contract to provide that time for completion begins to run from some

stipulated date in lieu of the date of site possession. As an alternative to stipulating

the period within which the works have to be completed, a contract may provide that

the contractor’s obligation is to complete the works on or before a particular date.

Thus, instead of stipulating that the works shall be completed within 24 months from

1 January 2003, a construction contract may merely provide that the works shall be

completed on or before 31 December 2004. In this case, the contractor has the whole

of the period up to the end of the stipulated day of completion to perform his

obligation.5

2.2 Standard Form Provisions

Construction contracts usually contain elaborate provisions stipulating the

time within which the contractor is required to complete the construction of the

works, as well as the conditions under which such time may be extended. Standard

form provisions related to commencement and completion of works, damages for

non-completion and extension of time is looked into.

2.2.1 Public Works Department (P.W.D) Form 203A (Rev. 10/83)

Subject to any requirement for completion in parts or sections in the Contract,

clause 39(a) basically reiterates the obligation of the Contractor to complete the

5 Afovos Shipping Co v Pagnan [1983] 1 WLR 195 at 201 (HL).

Page 30: Time at Large and Reasonable Time for Completion

11

whole of the Works by the Date for Completion as stated in the Appendix or such

extended time as granted by the Superintending Officer (Lim, 2004).

Clause 40 provides the machinery whereby the Government and the

Contractor can agree in advance the damages to be payable by the Contractor if the

Contractor fails to complete by the Date for Completion or within any extended time

granted by the Superintending Officer. This agreed damages expressed as

Liquidated and Ascertained Damages is provided in the Contract to negate the

necessity of the Government having to prove the actual loss suffered in the event of

the Contractor’s breach for delayed completion.6 In other words, it is designed to

allow the Government to sue for or deduct the Liquidated and ascertained Damages

simpliciter from the money due to the Contractor. The enforceability of this

provision is subject to section 75 of the Contracts Act 1950 which reads:

When a contract is broken, if a sum is named in the contract as to the

amount to be paid in case of such breach, or if the contract contains

any other stipulation by way of penalty, the party complaining of the

breach is entitled, whether or not actual damage or loss is proved to

have been caused thereby, to receive from the other party who has

broken the contract reasonable compensation not exceeding the

amount so named or, as the case may be, the penalty stipulated for.

Lim (2004) also noted that although not specifically stated in clause 40, it is

implicit that the Superintending Officer should only issue the Certificate of Non-

completion after he has fully evaluated and granted the appropriate extension of time

(if any) to the Contractor pursuant to clause 43.7 In addition, it is essential that the

rate for Liquidated and Ascertained Damages is clearly inserted in the Appendix.

The clause is not enforceable and no amount can be recovered by the Government if

6 See BFI Group of Companies Ltd v DCB Integration Systems Ltd [1987] CILL 328. 7 See A Bell & Son (Paddington) Ltd v CBF Residential Care and Housing Association (1989) 46 BLR 105. If a new completion date is fixed and the contractor has not completed by that date, it is implicit that a non completion certificate to that effect must be issued by the architect whether or not a certificate had been issued in relation to an earlier and superseded completion date.

Page 31: Time at Large and Reasonable Time for Completion

12

it is omitted. In this case, the Government would have to resort to claim general

damages against the Contractor for delayed completion. However, if “NIL” is

inserted as the rate, it would be construed to constitute an agreement by the parties

that no damages would be payable by the Contractor and the Government would be

precluded from even claiming general damages against the Contractor for delayed

completion.8

Clause 43 provides for the Superintending Officer to grant an extension of

time on specified grounds and an extension of time is grantable on those grounds and

no other. The Superintending Officer has no inherent power to extend the time for

completion and in the absence of an express provision such as this clause he would

have no power to do so. This clause is an improvement over the extension of time

clause in the PAM (1969 edition) form of contract which contained limited grounds

for extending time and did not cover many common delaying events, such as failure

to give possession of site on the due date.

2.2.2 Pertubuhan Arkitek Malaysia (PAM) (2nd Edition, 1998)

According to Rajoo (1999), clause 21 of PAM 1998 Form is one of the most

important clauses in the contract. It provides for the employer to give site possession

in whole or parts by appropriately designating the Date of Commencement or Dates

of Commencement. This enables the contractor to be given site possession in one go

or alternatively by defined sections based on the needs of the employer. The

contractor’s primary obligation is to complete the Works by the contractual date for

completion. As his secondary obligation, the contractor is then to begin the Works

and proceed ‘regularly and diligently’ so as to complete the Works ‘on or before’ the

completion date set out in the Appendix of the PAM1998 Form.9 He has the whole

8 Temloc Ltd v Enrill Properties Ltd (1987) 39 BLR 30. 9 Clauses 21.1 and 21.2 of the PAM Contract.

Page 32: Time at Large and Reasonable Time for Completion

13

period between the Dates of Commencement and Completion to carry out and

complete the Works in a manner he considers best.10 The Dates of Commencement

and Completion must be specified in the Appendix and, subject to the grant of any

extension of time under clauses 23 or 32.1(iii) of the PAM 1998 Form (the latter

clause permits an extension of time for reinstatement of war damage), the contractor

is bound to complete the work by the specified Date for Completion. Clauses 21.2

and 21.3 go on to cure the inadequacy of the PAM 1969 Form in dealing with

commencement and completion in phases. If the employer requires the work to be

completed in parts, these two clauses set out the mechanics of how the contractor can

be obligated to complete the Works in part. Clause 21.4 empowers the architect to

issue instructions requiring the postponement of any work to be executed under the

contract. The employer or the architect may be forced by circumstances to call for

delay in the whole or part of the Works. Without this express power, the architect

would have no power to control the contractor’s order of working.

Clause 22 on damages for non-completion provides machinery whereby the

parties can agree in advance the damages payable by the contractor and recoverable

by the employer if he fails to complete the Works by the Date/s for Completion

stated in the Appendix, or within any extended period certified by the Architect

under clauses 23 or 32.1 (iii). Both liquidated damages and extension of time clauses

will be construed strictly contra proferentem against employer if there is any doubt

as to the construction of the provision11 (Rajoo, 1999).

Clause 23 on extension of time of the PAM 1998 Form is aimed at allocating

the risks of non-completion between the parties. It reduces the contractor’s risk in

relation to delays by entitling him to an extension of time for practical completion on

account of delay based on various circumstances, putting back the date on which

liquidated damages will start to apply. It is the main provision under which any

alteration to the Date for Completion can be made and refers to an extension of time

10 Supra note 4. 11 See Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd (1970) 1 BLR 111.

Page 33: Time at Large and Reasonable Time for Completion

14

meaning a lengthening of the period within which the Works have to be completed

(Rajoo, 1999).

2.2.3 Federation Internationale des Ingenieurs Conseils (FIDIC) Construction

Contract (1999)

Clause 8 of the FIDIC Construction Contract includes provisions for

commencement and completion of works, delay damages and extension of time, all

in one clause. The engineer shall give the Contractor not less than 7 days’ notice of

the Commencement Date. Unless otherwise stated in the Particular Conditions, the

Commencement Date shall be within 42 days after the Contractor receives the Letter

of Acceptance.12 The Contractor then has the obligation to complete the whole of the

Works and each Section, if any, within the Time for Completion including achieving

the passing of the Tests on Completion and completing all work which is stated in

the Contract as being required for the Works or Section to be considered to be

completed.13

If the Contractor fails to comply with the Time for Completion, the

Contractor is subject to pay delay damages to the Employer for this default. These

delay damages shall be the sum stated in the Appendix to Tender, and payment is

provided to be made on daily basis. However, the total amount due cannot exceed

the maximum amount of delay damages (if any) stated in the Appendix to Tender.

The delay damages do not relieve the Contractor from his obligation to complete the

Works, or from any other duties, obligations or responsibilities which he may have

under the contract.14

12 Clause 8.1 of the FIDIC Form. 13 Clauses 8.2(a) and 8.2(b) of the FIDIC Form. 14 Clause 8.7 of the FIDIC Form.

Page 34: Time at Large and Reasonable Time for Completion

15

FIDIC Form has a provision in clause 19 which elaborates on force majeure,

such as the definition of force majeure, notice of force majeure, its consequences and

release from performance under the law. Such a provision is not found in other

standard forms of building contract such as PWD 203A, PAM 1998 and CIDB 2000.

2.3 Time for Completion

According to Eggleston (1992), building forms usually specify a date for

completion in the appendix whereas civil engineering forms usually specify a time

for completion. The date for completion is therefore calculated from a date for

commencement given by the engineer. In both cases, procedural variations are often

introduced and the objective of establishing a precise date for completion can be lost.

For example, tenderers are commonly allowed to give their own preferred times for

completion or to offer an alternative to that specified in the tender documents.

However, if the contractor is allowed to fix his own time, it is necessary that this

time is linked in the contract documentation to either a start date or a completion

date. Without one or the other there will be no firm date for completion. Similar

problems in fixing the date for completion with certainty can arise when extensions

of time are granted. Differences of approach in various standard forms of contract

may be in part responsible. The danger of granting periods of time instead of fixing

new dates is that uncertainty can be created as to whether such periods, particularly

where they are expressed in days, cover working days only or include weekends and

holidays.

Page 35: Time at Large and Reasonable Time for Completion

16

2.3.1 Time of the Essence

Section 56(1) of the Contracts Act provides that failure to perform within a

fixed time in a contract, where time is essential, would render the contract voidable.

When time is of the essence in a contract, failure to complete by the specified date is

a breach of a condition entitling the innocent party to treat the contract as repudiated.

If the contract is a supply contract and the goods are offered late, acceptance of the

goods can be refused. If the contract is a construction contract and the contractor

fails to finish on time, the employer is entitled to dismiss the contractor from the site

and has no liability for payment for the unfinished work. However, this is not the

usual position in a construction contract. Finishing late does not normally entitle the

employer to dismiss the contractor from the site; it is a breach of warranty and

damages are the employer’s remedy. Nor does finishing late normally excuse the

employer from payment for unfinished work. The question then is what governs

whether or not time is of the essence in contracts. (Eggleston, 1992).

Sinnadurai (2003) noted as well that difficulties remain in determining when

time would be regarded as of the essence of the contract. At common law, time was

always regarded as of the essence of the contract in the sale of land. However,

equity did not take such a strict view. This attitude of equity towards time, did not

apply in cases when the parties had expressly agreed that time should be of the

essence. The exceptions to the common law rule that ‘time is always of the essence

of the contract’ were discussed by the House of Lords in United Scientific Holdings v

Burnley Borough Council15 and by the Court of Appeal in British and

Commonwealth Holdings plc v Quadrex Holdings Inc.16 The common law rule has

been assimilated by equity so that a court will examine the whole scope of the

transaction to decide whether the parties really meant the time stipulated to be of the

essence of the contract. Section 56 of the Contracts Act appears to follow the

English law whereby the rules contained in the section are not different from the

15 Supra note 2. 16 [1989] QB 842; [1989] 3 All ER 492, CA.

Page 36: Time at Large and Reasonable Time for Completion

17

position arrived at in common law.17 Section 56 is the most invoked provision of the

Contracts Act dealing with time and the scope of this section has been considered in

a number of cases.18 The position is if in a contract in which time is of the essence, a

party fails to perform it by the stipulated time, the innocent party has the right either

to rescind the contract, or to treat is as still subsisting. If he treats it either expressly

or by conduct as still continuing, the contract exists but time ceases to be of the

essence and becomes at large. Consequently he cannot claim the liquidated damages

under the contract unless there is a provision as to the extension of time. However,

this cessation can be revived and so time can be restored to be of the essence by the

innocent party serving a notice to the party in default giving a new date of

completion.19

The law relating to time for performance under the Contracts Act was dealt

with exhaustively by Visu Sinnadurai J in Abdul Rahim bin Syed Mohd v

Ramakrishnan Kandasamy & Anor.20 Time, in a contract for the sale of land, is of

the essence in two main situations; firstly where the intention of the parties was such

that the time was of the essence of the contract for the fulfillment of their respective

obligations and secondly, where the nature of the subject matter or the surrounding

circumstances are such that the time specified for the performance is of the essence.

There is little difficulty in considering whether time is of the essence of a contract if

there is an express provision in the contract itself stating that it is so. In contracts

where the phrase ‘time is of the essence’ is employed, it is generally accepted that

the parties in these cases have clearly intended that the provision dealing with time is

an essential term of the contract. In such cases, both parties must perform their

respective obligations within the time stipulated. Where there is no express

provision in the contract making time of the essence, the courts will then have to

consider the nature of the property, the surrounding circumstances and the nature of

the contract to determine whether time was intended by the parties to be the essence 17 Yeoh Kim Pong Realty Ltd v Ng Kim Pong [1962] MLJ 118. See also Jamshed Khodaram Irani v Burjorni Dunjibhai (1915) LR 43 IA 26 (section 55 of the Indian Contract Act is similar to section 56 of the Malaysian Act). 18 See Lai Yew Seong v Wong Chieu Gook (1913) 1 FMSLR 12; Ismail bin Haji Embong v Lau Kong Han [1970] 2 MLJ 213; Ayadurai v Lim Hye [1959] MLJ 143. See also the Privy Council decision of Mohamed Habidullah v Bird & Co. AIR 1922 PC 178. 19 Sim Chio Huat v Wong Ted Fui [1983] 1 MLJ 151. 20 [1996] 3 MLJ 385, HC.

Page 37: Time at Large and Reasonable Time for Completion

18

of the contract. In Yeoh Kim Pong Realty Ltd v Ng Kim Pong21 time was not

expressly stated to be of the essence. It was held that considering the intention of the

parties, and on an ‘examination amongst other things of attendant circumstances’,

time was of the essence of the contract in question. It was also pointed out by the

judge, as seen in the case of Ganam d/o Rajamany v Somoo s/o Sinnah22 that the

mere stipulation of a date fixed for completion in a contract does not, by itself, make

time to be of the essence of the contract. The nature of the property and the

surrounding circumstances would still have to be considered in such cases.

The general principles regarding time were also spelt out by Gill J in the case

of Tan Ah Kian v Haji Hasnan.23 There are three situations whereby time is of the

essence of the contract: (i) where the parties have expressly stipulated in the contract

that it shall be so; (ii) where it was not originally stated to be but had been made so

by giving reasonable notice to the other, who had failed to perform the contract with

sufficient promptitude; and (iii) where from the nature of the contract or of its subject

matter, time must be taken to be of the essence of the agreement.

In building contracts, time of the essence of the contract is an interesting

stipulation encountered frequently. This stipulation is usually inserted by quantity

surveyors or engineers in the preliminaries section of the bill of quantities or in some

portion of the contract specification. There are occasions where such stipulations in

a contract document are intended to be literally construed. Thus, in a contract to

construct facilities for a particular event such as a games village for a major sports

event, it is clear that the owner will be left with very benefit if the project is delivered

after the dates set for the games. (Chow, 2004).

Chye Fook & Anor v Teh Teng Seng Realty Sdn Bhd24 is a case dealing with

late completion of a building, where time was of the essence of the contract. The

21 [1962] MLJ 118. 22 [1984] 2 MLJ 290. 23 [1962] MLJ 400, HC; [1963] MLJ 175, FC. 24 [1989] 1 MLJ 308, HC.

Page 38: Time at Large and Reasonable Time for Completion

19

specific question before the High Court was whether the purchaser ‘could sue for

rescission on the agreement [that] … as the house was not completed … [on] the

completion date’. In a detailed judgment, Abdul Malek J dealt with relevant case

law and statutory law on the subject, particularly, sections 56 and 76 of the Contracts

Act. In Hock Huat Iron Foundry v Naga Tembaga Sdn Bhd25 the Court of Appeal

also considered the subject in relation to the provisions of Contracts Act 1950. The

position, as a result of the operation of section 56(1) of this Act and as set out in the

earlier decision of Loke Yuen Cheng & Anor v Vintex Sdn Bhd26, is that where the

parties to a contract clearly intends that time is to be of the essence of the contract,

then the occurrence of any delay in performance would render the contract voidable

at the option of the innocent party. If the innocent party elects to exercise the option,

the effect is that the contract is annulled so that the situation is as though it had never

existed. In the circumstances, the employer forfeits whatever recourse under the

contract, including an action for damages, and can only seek redress through

restitution.

2.4 Damages for Late Completion

The contractor’s obligation to complete the works by the completion date is

backed up by legal sanctions. Under certain types of contract such as contracts for

the sale of perishable goods, where time is expressly or impliedly of the essence, any

lateness in performance entitles the other party to determine the contract. However,

construction contracts very rarely fall into this category. Thus, the employer’s

remedy for late completion will be an award of damages for breach of contract. It is

standard practice in building and civil engineering contracts to state in advance what

the damages shall be for delay, and this is usually done by specifying a fixed sum of

money to be due for every day, week or month by which the contractor fails to meet

25 [1999] 1 MLJ 65. 26 [1998] 4 MLJ 169.

Page 39: Time at Large and Reasonable Time for Completion

20

the prescribed completion date. Such sums are called liquidated and ascertained

damages or LADs (Murdoch and Hughes, 2000).

Halsbury’s Laws of Malaysia (Building and Construction) also stated that

generally, contracts for construction works usually provide that in the event of the

contractor’s failure to complete by the date specified for completion, the contractor is

to pay a specified sum or that the employer may deduct a specified sum from money

due to the contractor.27

2.4.1 Liquidated Damages

Delay in performance is treated as going to the root of the contract without

regard to the magnitude of the breach.28 Damages for a contractor’s failure in breach

of contract to complete on time are often subject of a provision for liquidated

damages (Furst and Ramsey, 1991).

According to Murdoch and Hughes (2000), a claim for liquidated damages

can only succeed where the contract makes express provision for it. Most building

contracts contain such a clause. Liquidated damages provisions are in principle

perfectly acceptable and they are to be encouraged as they enable the parties to know

from the start as much as possible about the risks they bear.

When the LAD are agreed, the employer’s only remedy for late completion

by the contractor is a sum not exceeding the specified amount. He does not have an

27 See PAM Conditions of Contract (1998) cl 22; IEM Conditions of Contract cl 40; PWD Conditions of Contract Forms 203/203A cl 40. See also Arab Malaysian Corpn Builders Sdn Bhd v ASM Development Sdn Bhd [1998] 6 MLJ 136. 28 Lombard plc v Butterworth [1987] Q.B. 27 at 535 (C.A.).

Page 40: Time at Large and Reasonable Time for Completion

21

option of claiming unliquidated damages. Should no date for Completion be inserted

in the Appendix, then no liquidated damages will be payable since there is then no

date from which liquidated damages can run. There must be a definite date to act as

a starting point and if the completion date has passed due to the default of the

employer for which no extension of time is given by the architect, the employer’s

right to liquidated damages will be lost.29 (Rajoo, 1999).

Section 75 of the Contracts Act 1950 deals with the effect of a sum named in

a contract which is payable in cases of breach of contract, and in Malaysia ‘there is

no difference between penalty and liquidated damages’.30 Section 75 of the Act

provides:

When a contract has been broken, if a sum is named in the contract as

the amount to be paid in case of such breach, or if the contract contains

any other stipulation by way of penalty, the party complaining of the

breach is entitled, whether or not actual damage or loss is proved to

have been caused thereby, to receive from the party who has broken

the contract reasonable compensation not exceeding the amount so

named or, as the case may be, the penalty stipulated for.

29 See Sim Chio Huat v Wong Ted Fui [1983] 1 MLJ 151; Thamesa Designs Sdn Bhd v Kuching Hotels Sdn Bhd [1993] 3 MLJ 25. 30 Maniam v The State of Perak [1975] MLJ 75; Linggi Plantations Ltd v Jagatheesan [1972] 1 MLJ 89.

Page 41: Time at Large and Reasonable Time for Completion

22

2.5 Extension of Time

2.5.1 Purposes of Extension Provisions

According to Eggleston (1992), a contractor is under a strict duty to complete

on time except to the extent that he is prevented from doing so by the employer or is

given relief by the express provisions of the contract. The effect of extending time is

to maintain the contractor’s obligation to complete within a defined time and failure

by the contractor to do so leaves him liable to damages, either liquidated or general,

according to the terms of the contract. In the absence of extension provisions, time is

put at large by prevention and the contractor’s obligation is to complete within a

reasonable time. The contractor’s liability can then only be for general damages but

first it must be proved that he has failed to complete within a reasonable time.

Therefore, extension of time clauses have various purposes which are:

1. to retain a defined time for completion

2. to preserve the employer’s right to liquidated damages against acts of

prevention

3. to give the contractor relief from his strict duty to complete on time in respect

of delays caused by designated neutral events

It is a common belief in the construction industry that extensions of time are

solely for the benefit of the contractor. At face value by giving the contractor more

time to complete the works and by reducing his liability for liquidated damages they

do appear to be one-sided. It is not the contractor who has most need of extension of

time provisions, it is the employer. A string of well documented cases from Holme v

Guppy31 to Rapid Building v Ealing32 confirm that the courts will not uphold

liquidated damages where the employer has prevented completion on time unless

31 Supra note 3. 32 Supra note 4.

Page 42: Time at Large and Reasonable Time for Completion

23

there is express provision in the contract to extend time for the employer’s default.

Lord Fraser’s comment in Bilton v GLC33 sums it up:

‘… The general rule is that the main contractor is bound to complete

the work by the date for completion stated in the contract. If he fails to

do so, he will be liable for liquidated damages to the employer. That is

subject to the exception that the employer is not entitled to liquidated

damages if by his acts or omissions he has prevented the main

contractor from completing his work by the completion date: see, for

example, Holme v Guppy (1838) and Wells v Army and Navy Co-

operative Society (1902). These general rules may be amended by the

express terms of the contract…’

Extension of time clauses are commonly entered into construction contracts

essentially for the benefit of the employer, since in the event of prevention or breach

by the employer a contractual date for completion may be maintained and the

liquidated damages provisions preserved. For an extension of time provision to be

effective in such circumstances it must clearly give the means to extend the period for

completion (Brewer Consulting, 2005). Chow (2004) also pointed out that under

English common law, time extension provisions are regarded as being inserted for the

benefit of the employer since they operate to keep alive the liquidated damages

provisions in the event of delay caused by the employer’s acts of prevention. The

courts have consequently ruled that they are to be interpreted contra proferentum

against the employer.

33 (1982) 20 BLR 1, HL.

Page 43: Time at Large and Reasonable Time for Completion

24

2.5.2 Grounds for Extension of Time

According to Chow (2004), construction contract provisions may either

stipulate a list of events in respect of which extensions of time may be granted or,

alternatively, adopt a more general formulation. Both approaches should take into

account the attitude of the courts in construing time extension clauses. From the

employer’s standpoint, it is crucial that the provisions should expressly allow for

extensions in respect of delays arising from a breach or act of prevention caused by

the employer. The formulation adopted in the major standard forms such as the JCT

Contract (1998), ICE Conditions of Contract (7th Ed, 1999) and PAM 1998 is a

combination of both approaches. The time extension provision typically lists the

common causes of delay in respect of which the employer accepts that time

extensions may be granted, followed by a general “catch all” paragraph which is

intended to bring within the ambit of the provisions events of delay which have not

been specifically stated in the clause. Thus, under clause 44(1) of the ICE Conditions

of Contract (1999 Ed), paragraphs (e) and (f) extend the power for extending time to

cover “any delay, impediment, prevention or default by the employer” and “other

special circumstances of any kind whatsoever which may occur”. A similar approach

is used in clause 8.4(e) of the FIDIC Contract (1999).

2.5.2.1 Force Majeure

The expression ‘force majeure’ is of French origin. Under the French Civil

Code force majeure is a defence to a claim for damages for breach of contract. It

needs to be shown that the event made performance impossible, was unforeseeable

and was unavoidable in occurrence and effects (Eggleston, 1992).

According to Chow (2004), the expression force majeure was first used in

clause 23(a) of the JCT 63 Form and has since been retained in successive editions of

that standard form. In the 1998 edition of the JCT Contract, it is specified as a

Page 44: Time at Large and Reasonable Time for Completion

25

“relevant event” for the purpose of time extensions under clause 25. The term itself is

a curious French expression which is usually considered to cover a host of highly

unusual and superhuman events. In the classic case of LeBaupin v Crispin34, the

court accepted that the “term is used with reference to all circumstances independent

of the will of man, and which it is not in his power to control…” It was held to

include wars, epidemics and strikes, but a cautionary note was struck in the judgment

of that case on the interpretation of a force majeure clause:

… [The force majeure clause] should be construed in each case with

close attention to the words which precede or follow it with due regard

to the nature and general terms of the contract. The effect of the

clause may vary with each instrument…35

Chow (2004) further noted that at first instance, it may be difficult to

appreciate the need for the JCT Contract to expressly include force majeure as a

ground for time extension. Events such as wars, strikes and inclement weather are

already separately listed in the time extension provisions, so that it could be suggested

that the expression as used in the JCT form must have been intended to provide for

something else. There is no direct authority on this point, but it is highly arguable

that the original objective may have been as a general premise to cover any event,

other than those specifically mentioned, which resides beyond human anticipation. If

so, the conceivable range of events must be a very narrow one and it is not surprising

that there has been no reported case on the JCT contract where this ground for time

extension has been considered.

Clause 19.1 of the FIDIC conditions provided a more elaborate definition of

this expression and defines force majeure as an “exceptional event or circumstance”

which satisfies the following criteria:

1. It must be beyond the control of the relying party.

34 [1920] 2 KB 714. 35 Ibid.

Page 45: Time at Large and Reasonable Time for Completion

26

2. The relying party could not have reasonably provided for the event or

circumstances before entering into the contract.

3. Having arisen, the relying party could not have reasonably avoided or

overcome the said event or circumstance.

4. It must not be substantially attributable to the other party.

A force majeure event under the FIDIC Contract must therefore satisfy all the

four conditions prescribed here. In the context of a construction claim advanced by

the contractor, the “other party” refers to the employer. Chow (2004) therefore noted

that the paragraph appears to envisage that where the claim arises from, say a breach

by the employer, it is considered that the contractor will in most cases elect to sue for

breach of contract, rather than invoke the force majeure clause since this reduces the

onus of proof and is likely to provide him with a more extensive range of reliefs.

Clause 19.1 also specifically lists down a number of situations which are deemed to

be treated as force majeure which include wars, terrorism, strikes and lockouts and

natural catastrophes.

2.5.2.2 Variations and Extra Works

Eggleston (1992) stated that when variations or extra works cause delay to

completion, the contractor will have a clear case for extension of time, or if there is

no express provision to extend time, the employer will have lost his right to liquidated

damages. It is the following types of questions which give rise to arguments. For

example, have the variations actually caused delay to completion? Are the extra

works really extra? Could the contractor have accommodated them in his

programme? Some of these matters have been considered previously and others are

considered under particular forms but it is worth just noting here that extra quantities

are not necessarily the same as extra works and in some forms of contract, it is the

contractor and not the employer who takes the risks on quantities.

Page 46: Time at Large and Reasonable Time for Completion

27

The particular situation where omissions of work may be a premise for a time

extension should be noted. Such a situation may arise, for instance, where plant and

equipment have already been bought on site and these have been prepared to support

the execution of a particular item of work. This item of work is then subsequently

omitted, thereby necessitating a new and possibly less productive sequence of work.

There is no direct English case authority on this point, but in the South African case

of Kenny and Hingles’ Trustee v Union Government36, it was held that where the

language of a time extension provision empowered the engineer to assess the period

of delay consequent upon the ordering of extras, it would be reasonable for the

engineer to “take into account in deciding as to allowances for such delay the effect

of other orders requiring omissions.” (Chow, 2004).

2.5.2.3 Exceptionally Adverse Weather Conditions

This ground of time extension is found in the provisions of most of the major

standard forms. The general formulation is that time may be extended only when the

contractor can demonstrate that the weather conditions encountered could be properly

described as exceptional”. In construing the term “exceptional”, consideration should

be given as to whether the weather itself was exceptionally adverse or inclement, so

as to give rise to the delay and not whether the magnitude of the delay itself was

exceptional.37 It is suggested that this construction is consistent with the intent of this

provision in the other standard forms as well.

In Malaysia, the predominant issue with weather conditions, in so far as

construction operations are concerned, is the intensity of rainfall. To formulate a case

for extension of time on the basis of exceptional rainfall, a contractor has to show,

from site records, the number of days in a particular month in which the actual

rainfall actually encountered exceeds a prescribed level and this is commonly referred

36 (1928) TD 272 at 289. See also another South African case, Chaffer and Tassie v Richards (1905) 26 NLR 20. 37 Walter Lawrence v Commercial Union Properties (1984) 4 ConLR 37.

Page 47: Time at Large and Reasonable Time for Completion

28

to as the number of “wet days”. Next, the contractor compares the number of wet

days encountered with the number of wet days which are indicated by statistical

averages in meteorological records. Exceptional rainfall conditions for a particular

month are then established when the number of wet days actually encountered exceed

the number of wet days recorded in these meteorological averages. However, it is not

sufficient for an applicant for time extension to merely show the incidence of wet

days and hence, adverse weather conditions. It is necessary to establish the link

between the conditions and the progress of works, and in particular, the contractor has

to show that the nature of the construction operations being undertaken during the

period of “wet days” in a particular month are indeed operations which are

susceptible to the effects of these exceptional rainfall conditions (Chow, 2004).

2.5.2.4 Late Possession of Site

Under common law, an employer is treated to have committed a breach of

contract if he fails to give timely possession of site.38 Consequently, to ensure that

time will not be set at large in the event of a late handover of site to the contractor,

most standard forms expressly includes this event as one of the grounds for time to be

extended (Chow, 2004). Eggleston (1992) brought up the issue that whether or not

failure by the employer to give possession of site at a time convenient to the

contractor is an act of prevention will depend on the wording of the contract. If the

contract simply states a date of possession of the site, the contractor is entitled to the

whole of the site from the outset; but if the contract specifies phased release of the

site, the contractor is obliged to accommodate the restrictions that will impose.

38 See Felton v Wharrie (1906) Hudson’s Building and Engineering Contracts (4th Ed) Vol 2, p 398; Earth & General Contractors Ltd v Manchester Corporation (1958) 108 LJ 665; Rapid Building v Ealing Family Housing (1984) 29 BLR 5; Holme v Guppy (1838) 3 M&W 387.

Page 48: Time at Large and Reasonable Time for Completion

29

2.5.2.5 Sub-contractors

According to Eggleston (1992), on basic principles delays caused by domestic

sub-contractors do not give grounds for extensions of time. Unless there are express

provisions in the contract to cover delays so caused or there are other provisions for

extensions that can be interpreted to cover sub-contractors, the problems of sub-

contractor default will rest between the main contractor and sub-contractor. If the

contractor is required by the terms of the contract to obtain approval to his sub-

contractors from the contract administrator and the approval is unreasonably delayed,

that could be a breach of contract with the potential to defeat the liquidated damages

provisions unless there are extension clauses covering employer’s act of prevention.

Nominated sub-contractors are the cause of many complex disputes, and

however much forms of contract attempt to place responsibility for such sub-

contractors on main contractors, it is very difficult for the employers to avoid sharing

some of the responsibility for their delays and defaults. The burden of renomination

after default is a heavy one, with the employer bound to avoid delay in renominating

and to allow time for rectification of faulty work.39

2.5.2.6 Delay in Approvals and Instructions

The drawings and technical documents provided at the time of contract are

frequently insufficient to enable the contractor to carry out all aspects of the works

required under the contract. To enable the works to proceed properly, it is usually

necessary for the architect or engineer to issue instructions or additional drawings

during the course of the works. Most time extension provisions provide for time to be

extended where the architect or engineer fails to issue these instructions or drawings

in a timely manner. An issue which is closely related to time extensions granted for

39 See North West Metropolitan Regional Hospital Board v Bickerton (1970), Peak v McKinney (1970), Percy Bilton v GLC (1982) and Fairclough v Rhuddlan Borough Council (1985).

Page 49: Time at Large and Reasonable Time for Completion

30

delays in instructions is the date when the contractor should have contacted or applied

to the architect or engineer for these instructions. Most contracts require that the

contractor should apply for the relevant approval or instruction at an appropriate

juncture during the course of the works.

2.5.2.7 Other Commonly Stipulated Grounds

The major standard forms of contract also allow for the time to be extended in

respect of the following events:

1. Strikes and civil commotion which affect the works or affect the manufacture

or transportation of goods for use in the works40

2. Disruption arising from actions or policy changes of a government body or

statutory organisation41

3. Unexpected market conditions which affect the contractor’s ability to procure

labour or materials for the works such as a sudden shortage of aggregates or

cement42

4. Opening up for inspection any work covered up or the testing of any work,

materials or goods43

40 Clause 25.4.4 of JCT Contract (1998 Ed); clause 23.7(iv) of PAM Form (2nd Ed) (1998); Clause 43(h) of PWD 203A and clause 24.1(c) of CIDB 2000. 41 Clause 25.4.9 of JCT Contract (1998 Ed); Clause 8.5 of the FIDIC Contract (1999 Ed). In the case of the FIDIC Contract, clause 8.5 describes the condition under which this event may qualify for an extension of time under clause 8.4(b). 42 Clause 25.4.10 of JCT Contract (1998 Ed); clause 8.4(d) of FIDIC Contract (1999 Ed). 43 Clause 23.7(x) of PAM Form (2nd Ed) (1998); clause 24.1(h) of CIDB 2000.

Page 50: Time at Large and Reasonable Time for Completion

31

2.5.2.8 Causes beyond the Contractor’s Control

A final remark should be made on the general category of events which comes

frequently under a supposedly “catch all” or “umbrella” ground typically formulated

as “any cause beyond the control of the contractor.” Such a provision is not intended

to cover delays arising from events which are reasonably foreseeable by the

contractor at the time of contract and which could be avoided by reasonable action on

the part of the contractor. Thus, it would not cover, for example, delay caused by the

contractor’s financial stringency, where this is triggered by the actions of a third party

on whom the contractor depends for financial support. There should also be no basis

for time to be extended in respect of delays arising from events which are caused by

the contractor’s want of competence or judgment. These events include ineffective

supervision, insufficient manpower and a failure to plan the work properly (Chow,

2004).

From the authorities that a general expression like “causes beyond the

contractor’s control” would not be sufficiently embracing to cover delays associated

with some breach or act of prevention by the employer. For this purpose, a separate

provision has to be inserted in the time extension clause to cater specifically to these

delay events.44

2.6 Time at Large

The standard form building and civil engineering contracts deal with the

specification of time to complete in two different ways. On the one hand, the

building contracts tend to invite the insertion (in the appendix to the building

44 Clause 44(1)(e) of the ICE Conditions of Contract (7th Ed); clause 8.4(e) of the FIDIC Contract (1999); clause 23.7(xi) of the PAM Form (2nd Ed) (1998).

Page 51: Time at Large and Reasonable Time for Completion

32

contract) of a fixed calendar date for the handover of possession of the site to the

contractor coupled with a fixed completion date by which the contract must be

practically completed. There, the period between the two dates is described as the

contract period which the contractor must carry out and complete the work. On the

other hand, the engineering contracts tend to stipulate that the work shall be

completed within a specified number of days or weeks from the notice to proceed.

The date on which the notice to proceed may be given is then left open for a limited

period of time. It is only once the notice to proceed has been given that the contract

period can commence and the date for completion can be calculated.

During the execution of the contract, circumstances may arise which render

that completion date unenforceable. Of itself, the failure competently to put into

effect the contractual machinery to extend the time for completion by the contract

administrator is not sufficient to render the completion date unenforceable and time

at large. The effect must be that the parties to the contract do not truly know their

position. If the true position can be established by other contractual means then the

breakdown is likely to be immaterial. Provided always that the true position can be

restored by the operation of other contractual machinery, for example reference to an

adjudicator, arbitrator or the court to open up and review the decision or absence of a

decision, the failure of the contract administrator during the course of the contract

will not set time at large.45 (Pickavance, 2005).

2.6.1 Events Giving Rise to Time at Large

According to Pickavance (2005), in principle, there are at least three

possibilities as to how time may have become “at large”:

45 Panamena Europea Navigacion (Compania Limitada) v Frederick Leyland & Co Ltd [1947] AC 428.

Page 52: Time at Large and Reasonable Time for Completion

33

1. There may be a contract together with a number of employer’s risk events for

which the contract makes provision to extend time but which cannot be

applied because the draftsman has failed to specify the contract completion

date or time for performance in the contract.

2. There may be a contract completion date together with a number of

employer’s risk events for which the contract makes provision to extend time

but which have either become inoperable or do not apply to the event causing

the delay to completion so that, in the circumstances, the employer has in fact

no power to extend time.46

3. There may not be a contract completion date simply because there was no

contract.

The first two possibilities as to how time might have become at large require,

as a starting point, the assessment of a reasonable period for the works for which the

contractor has contracted and, while it is normally the case that the date for the

completion is stipulated by the terms of the contract, its proper revision under the

contract or by collateral agreement, that may not always be so.

Eggleston (1992) had the view that the circumstances of time becoming at

large are usually where an act of prevention by the employer creates delay and that

delay is not covered by an extension of time provision; and to a lesser extent:

1. Where the provisions for extension of time have not been properly

administered or have been misapplied

2. Where there has been waiver of the original time requirements

3. Where there has been interference by the employer in the certifying process

46 See, for example, Gaymark Investments Pty Ltd v Walter Construction Group (1999) NTSC 143, (1999) 16 BCL 449; (2005) 21 Const LJ 70.

Page 53: Time at Large and Reasonable Time for Completion

34

What is generally at stake in the matter of whether or not time is at large is

the employer’s right to deduct liquidated damages for late completion. This right is

lost completely if time becomes at large – the employer can still sue for general or

unliquidated damages for late completion but regard will then be had to the

contractor’s entitlement to a reasonable time.

Atkinson (2007) stated that the term “time at large” is usually used in

construction contracts in the situation where liquidated damages are an issue. If time

is “at large” then it is argued that liquidated damages cannot be applied, because

there is no date fixed from which the liquidated damages can be calculated. In some

situations the date for completion may be relevant to termination and the issue

whether or not there has been a breach of contract by failure to complete. Time is

made at large in four situations:

1. No time or date is fixed by the terms of the contract by which performance

must take place or be completed.

2. The time for performance has been fixed under the contract, but has ceased to

apply either by agreement or by an act of prevention (which includes

instructed additional work) or breach of contract by the Employer with no

corresponding entitlement to extension of time.

3. The Employer has waived the obligation to complete by the specified time or

date. An alternative situation is that the Employer is faced with a breach of

contract by the contractor which would entitle to Employer to terminate the

employment of the contractor and/or to bring to an end the primary

obligations of the parties to perform, but instead elects to continue with the

performance of the contract.

4. The Employer has interfered in the certification process to prevent proper

administration of the contract.

Page 54: Time at Large and Reasonable Time for Completion

35

2.6.1.1 No Time or Date Fixed in the Contract

As mentioned, many construction contracts and standard forms of contract

usually place an obligation on the contractor to complete the works by a specified

completion date or within a specified period. If no date or period is fixed by the

contract then the objective intention of the parties must be ascertained. In the case of

a contract under the Supply of Goods and Services Act 1982, if the date is not fixed

by a course of dealing between the parties, a term will be implied that the

contractor’s obligation is to complete within a reasonable time (Section 14(1)). In J

and J Fee Ltd v The Express Lift Company Ltd47 there had been correspondence

between the parties on the date of commencement and completion. The last

correspondence from Express Lift stated that it could see little possibility of

improvement on the dates previously given, but suggested that the situation be

monitored and if it became possible to review the situation. It was held that as a

matter of construction of its express terms Express Lift made a contractual offer of

the completion date which it consistently offered before and that offer was accepted.

The last letter was not written in plain “take it or leave it” terms but held out the

possibility of bettering the completion date. Nonetheless there were dates for

commencement and completion as express terms of the contract. His Honour Judge

Peter Bowsher QC stated that if he was wrong on that issue, then there was a term

implied that Express Lift would complete within a reasonable time. He gave a

provisional view, without deciding, that based on the documents before him that it

would be impossible for Express Lift to contend that a reasonable time for

completion of the works would be any later than the date they had consistently put

forward. (Atkinson, 2007).

47 [1993] 34 ConLR 147.

Page 55: Time at Large and Reasonable Time for Completion

36

2.6.1.2 Time or Date Ceases to Apply by Acts of Prevention

The prevention principle comes from a generally stated legal principle that a

party cannot benefit from its own wrong. The prevention principle has a very long

history in the common law. As long ago as 1838 the court held in the case of Holme

v Guppy48 that where the contractor had been prevented from starting the works

because of the activities of the employer's other workmen, a fresh contract could not

be found and liquidated damages could not be applied (Brewer Consulting, 2005).

Eggleston (1992) also mentioned that the principle of prevention is of general

application in contracts and is to the effect that one party cannot impose a contractual

obligation on the other party where he has impeded the other in the performance of

that obligation. In other words of Lord Justice Denning in Amalgamated Building

Contractors Ltd v Waltham Holy Cross Urban District Council49, ‘the building owner

cannot insist on a condition if it is his own fault that the condition has not been

fulfilled’. “There is an implied contract by each party that he will not do anything to

prevent the other party from performing a contract or to delay him in performing it.

Generally such a term is by law imported into every contract.”50

An act of prevention may vary from an omission on the part of the employer,

a fault, or even the ordering of variations and extras which might be fully

contemplated by the contract. In SMK Cabinets v Hili Modern Electrics Pty Ltd51 Mr.

Justice Brooking summarized the law as follows:

A wide variety of expressions have been used to describe the act of

prevention which will excuse performance. At times the words are

employed which suggest that any act or omission preventing

performance will suffice: Dodd v Churton (1897), where all three

48 Supra note 3. 49 [1952] 2All ER452 at 452 (CA). 50 Barque Quilpue Ltd v Bryant (1904), per Lord Justice Vaughan Williams. 51 [1984] VR 391; (1984) 1 Const LJ 159 at p. 396.

Page 56: Time at Large and Reasonable Time for Completion

37

members of the Court speak of an act: Bruce v The Queen (1866),

where the Court refers simply to prevention: Percy Bilton Ltd v

Greater London Council (1982). Hudson Building and Engineering

Contracts (10th ed.) p. 631 (acts or omissions) speaks of acts, whether

authorized by or breaches of the contract but at p. 700 refers to

wrongful acts. In Perini v Greater Vancouver Sewerage and Drainage

District (1966) Bull J A with whose judgment Lord J A agreed, spoke

of a wrongful act. The expressions used by Salmon L J and Phillimore

L R in Peak Construction (Liverpool) Ltd v McKinney Foundations

Ltd (1970) are “fault” and “fault or breach of contract”. Another

phrase to be found is “act or default” in Amalgamated Building

Contractors Ltd v Waltham Holy Cross Urban District Council

(1952). Words used by Lord Denning (“his conduct – it may be quite

legitimate conduct, such as ordering extra work”) appear in a passage

cited with approval in the leading speech in the House of Lords:

Trollope & Colls Ltd v North West Metropolitan Regional Hospital

Board (1973). I interpolate the observation that any formulation must

accommodate the case of the ordering of extras, whether or not in the

exercise of a power conferred by the contract. In the well know case

of Roberts v Bury Improvement Commissioners (1870) two different

statements appear. Blackburn and Mellor J J, say that no person can

take advantage of the non-fulfillment of a condition the of which has

been hindered by himself, while Kelly C B and Channell B would ask

whether performance has been prevented by a wrongful act; both

statements are cited by Lord Thankerton in delivering the principal

speech in Panamena Europa Navigacion (Compania Limitada) v

Frederick Leyland & Co Ltd (1947). It is worth noting the formulation

of Davis J of the Supreme Court of Canada in Ottawa Northern and

Western Railway Co v Dominion Bridge Co (1905).

Page 57: Time at Large and Reasonable Time for Completion

38

The editors of Building Law Reports when commenting on the Court of

Appeal decision in Percy Bilton v Greater London Council52 expressed the matter in

more general terms:

“Act of Prevention” is not easy to define but historically it has come to

mean virtually any event not expressly contemplated by the Contract

and not within the Contractor’s sphere of responsibility. From the

cases illustrated it may be seen that it is generally first necessary to

determine whether there has been a breach of contract on the part of

the employer or some other positive act or omission thereby

preventing the contractor from completing the contract work by the

due date and secondly, whether the contract did not make any express

provision for extending time in such circumstances.

The older cases were largely decided in relation to contract

where little or no provision was made for extending the time for

completion so as to keep alive the Contract Completion Date and thus

preserve the right to liquidated damages. Contract nowadays generally

contain extensions of time clauses drafted so as to cover the

eventualities likely to constitute “acts of prevention” and are in many

cases meticulous in their definition of the risks and responsibilities

assumed by each party.

It is submitted that in a modern contract such as the Standard

Form of Building Contract the correct analysis of events which may

delay completion should not be between “acts of prevention” and

“other acts” but rather between matters for which the contractor in law

assumes the risk and matters for which does not assume the risk. Such

an approach is based upon the proposition that by undertaking to

complete the work within the time stated a contractor assumes the

responsibility of surmounting all risks other than those constituting

breaches of contract or fault by the employer. It is sometimes useful to

consider this apportionment of risk in terms of the “fault” of one party

or the other, although “fault” is an emotive word.

52 [1982] 1 WLR 794.

Page 58: Time at Large and Reasonable Time for Completion

39

An example of the prevention principle operating within the construction

industry is where the contract provides a date for completion of the works but the

employer, through its acts or omissions, prevents the contractor from achieving that

date. Except to the extent that the contract provides otherwise, in such a situation the

employer will no longer be entitled to demand completion by the contractual date,

time becomes at large and the employer will not be entitled to claim liquidated and

ascertained damages for the late completion.

According to Pickavance (2005), under most standard forms of contract, the

employer is provided with the power to extend the time for completion in the event

of the occurrence of one or more of the events listed as grounds of extension of time

in the contract. However, in Rapid Building Group v Ealing Family Housing53 heard

before the Court of Appeal in 1984 (involving a development under JCT 63) there

was no applicable clause permitting the employer to grant an extension of time. In

that case, owing to the presence of squatters, the employer was unable to give

possession of site to the contractor on the due date. There is no provision in JCT 63

for extension of time for late possession. The contractor was therefore able

successfully to argue that time was at large. The contractor’s obligation was

therefore altered from one of completing by the contract completion date to one of

completing within a reasonable time and the employer lost its right to levy liquidated

damages. Therefore, in the event that, for reasons within the employer’s control, the

contractor is prevented from completing by the contract completion date, the

employer can no longer insist upon completion by that date and the contractor is then

left without a firm date by which to complete. Time is then said to be “at large” as a

result of the effect of what is known as the prevention principle as described earlier.

The application of the prevention principle is also famously illustrated by the

case of Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd.54 This was

an action by the contractor against a nominated subcontractor in which the contractor

was employed the local authority (employer) for the erection of high-rise buildings

53 Supra note 4. 54 (1970) 1 BLR 111.

Page 59: Time at Large and Reasonable Time for Completion

40

for which the nominated subcontractor was required to carry out the piling. In the

contract between the contractor and the employer, time was said to be “of the

essence” without any provision for the contract period to be extended for acts or

omissions of the employer that might interfere with the works. During the course of

the works, serious faults were discovered in the piles and the work was suspended

pending investigation and repair. However, because of delay on the employer’s part,

an expert was not engaged until some six months later. His recommendations were

eventually put into effect some ten months after the faults had first been discovered

and the piling was not completed until 58 weeks after the work had been suspended.

As a result of the subsequent delay to completion, the employer claimed liquidated

damages from the contractor who, in turn, claimed the same liquidated damages from

the nominated subcontractor.

The Court of Appeal found that, because part of the period of delay to

completion had been caused by the employer itself and there was no clause in the

contract between the contractor and the employer that enabled the employer to extend

time for the effect of its own failures, there was then no date by which the contractor

was obliged to complete and hence there was no enforceable completion date from

which liquidated damages could be calculated. In explaining the application of the

prevention principle in this case Salmon LJ said:

A clause giving the employer liquidated damages as so much a week

or month which elapses between the date fixed for completion is

usually coupled, as in the present case, with an extension of time

clause…If the failure to complete on time is due to the failure of both

the employer and the contractor, in my view, the clause does not bite.

I cannot see how, in the ordinary cause, the employer can insist on

compliance with the condition if it is partly his own fault that it cannot

be fulfilled.

If the employer wishes to recover liquidated damages for

failure by the contractor to complete on time in spite of the fact that

some of the delay is due to the employer’s fault or breach of contract,

an extension of time clause should provide, expressly or by necessary

Page 60: Time at Large and Reasonable Time for Completion

41

interference, for an extension on account of such fault or breach on the

part of the employer.

In Wells v Army and Navy Cooperative Society55 the contractors undertook to

complete a building contract within a year, unless the works were delayed by

variations, sub-contractors, “or other causes beyond the contractor’s control”. The

contract conditions provide that the decisions of the employer as to time extensions

and the determination of delays were to be final. As it turned out, there was a delay

in completion by one year. The employer granted a three-month extension in respect

of that part of the delay which was attributable to sub-contractors. The contractors

were able to show that the delays were also caused by late site possession, delay on

the part of the employer in furnishing drawings and additional works. The court

ruled that while the time extension provisions were able to deal with delays

generated by sub-contractors, the expression “or other causes beyond the contractor’s

control” did not extend to include the employer’s failure to afford timely site

possession nor his failure to furnish drawings at the appropriate time. Consequently,

the time extension provision could not be held to cover these acts of prevention and,

hence, could not operate to retain the operability of the liquidated damages provision.

This decision was cited with approval by the Court of Appeal of British

Columbia in Perini Pacific Ltd v Greater Vancouver Sewerage and Drainage Board

(1966), where it was decided that an extension of time clause which provided for

time to be extended on account of “extras or delays occasioned by strikes, lockouts,

force majeure or other cause beyond the control of the contractor” similarly would

not cover delays caused by the employer’s delivery of certain machinery in a

defective condition. Again, no liquidated damages could be recovered, although it

was forcefully argued on behalf of the employer that the effect of the employer’s act

of prevention only accounted for 45 days out of the total delay of 99 days.

55 (1902) 86 LT 764.

Page 61: Time at Large and Reasonable Time for Completion

42

The operation of prevention principle was also clearly demonstrated in the

classic case of Dodd v Churton.56 In that case, a building contract permitted extra

work to be ordered during the course of the contract. There were the usual

provisions for the imposition of liquidated damages in the event of delay in

completion, but there was no express provision to enable time to be extended.

Additional work was ordered which had the effect of delaying completion. The

employer attempted to impose liquidated damages on the period of delay after an

allowance of a fortnight had been made for what he considered was the appropriate

portion of the delay caused by the additional work. The court ruled that the

employer was not entitled to claim any liquidated damages. The delay was attributed

in part to his act of ordering additional work but there was no operative time

extension provision in the contract which would have permitted for the completion

time to be extended, thereby enabling the liquidated damages clause to be kept alive.

In his judgment Lord Esher MR stated the position under common law as follows:

The principle is ... that, when one party to a contract is prevented from

performing it by the act of the other, he is not liable in law for that

default; and accordingly a well established rule has been established in

cases of this kind ... to die effect that if the building owner has ordered

extra work beyond that specified by the original contract which has

necessarily increased the time requisite for finishing the work, he is

thereby disentitled to claim the penalties for non-completion provided

for by the contract. The reason for that rule is that otherwise a most

unreasonable burden would be imposed on the contractor. 57

56 [1897] 1 QB 562 (CA). 57 [1897] 1 QB 562, 566. See also Thornhill v Neats (1860) 8 CB (ns) 149; Russell v Viscount Sa da Bandeira (1862) 13 CB (NS) 149; Westwood v Secretary of State for India (1863) 7 LT 736; Murdoch v Lockie (1897) 15 NZLR 296; Meyer v Gilmer (1899) 18 NZLR 129; Cf Tew v Newbold-on Avon School Board (1884) 1 C&E 260; Trollope & Colls Ltd v NW Metropolitan Regional Hospital [1973] 1 WLR 601 (HL); Bilton v Greater London Council (1982) 20 BLR 1, HL; SMK Cabinets v Hili Modern Electrics [1984] VR 391 (Victoria Full Court).

Page 62: Time at Large and Reasonable Time for Completion

43

2.6.1.3 Waiver

Pickavance (2005) asserted that apart from the circumstances in which there

is no specified time, or in which, whilst there may be a specified time, there is no

power to vary it, there is one other situation in which the contractor may not have a

fixed date by which it must complete. That is the circumstance in which the

employer has waived the obligation to complete by the specified time or date or,

where the employer, faced with a breach of contract by the contractor which would

entitle the employer to terminate the employment of the contractor and/or to bring to

an end the primary obligations of the parties to perform, instead elects to continue

with the performance of the contract. For example, in Charles Rickards Ltd v

Oppenheim,58 the plaintiff agreed to supply a Rolls Royce motor car chassis and to

build a body on it within seven months. It failed to complete the work by the agreed

delivery date, but the defendant waived the original delivery date and new dates were

promised and agreed. Eventually, the defendant gave written notice to the plaintiff

stating that, unless he received the car by a firm date, four weeks away, he would not

accept it. The car was not delivered within the time specified and was not completed

until some months later when the defendant refused to accept it. The Court of

Appeal held that he was justified in doing so. After waiving the initial stipulation as

to time, the defendant was entitled to give reasonable notice making time of the

essence again, and on the facts the notice was reasonable.

Where a new date is not stipulated, then performance must be achieved

within a reasonable time, whatever that happens to be in the circumstances. So, for

example, in the case of Astea (UK) Limited v Time Group Limited,59 Astea was a

provider of software to Time Group, which was a manufacturer and retailer of

personal computers. Astea had agreed to complete performance of its services by the

end of October 2000 or by 6 November 2000 (the facts seemed unclear). The dates

passed, no new completion date was set and, in March 2001, Time Group

58 [1950] 1 KB 616. 59 [2003] EWHC 725 (TCC).

Page 63: Time at Large and Reasonable Time for Completion

44

subsequently claimed the contract had been repudiated and terminated the contract.60

It was common ground that strict compliance with an agreement to complete by the

end of October 2000 or by 6 November 2000 had been waived by failure to treat

such failure as repudiatory and that Astea’s obligation thereafter was to complete

within a reasonable time.

2.6.1.4 Failure of Contractual Machinery

According to Atkinson (2007), if the time or date for completion is effected

by events which entitle the contractor to an extension of time, but the contractual

machinery can no longer operate, then time is at large. The circumstances will be

rare.

In Bernhard’s Rugby Landscapes Ltd v Stockley Park Consortium (No 2)

[1998], BRL was awarded the contract for the construction of a new golf course on a

reclaimed landfill site under an amended ICE 5th Edition. One issue was whether

the contractual machinery had broken down and if so the effect. It was held that a

breakdown of the contractual machinery occurs when, without material default or

interference by a party to the contract, the machinery is not followed by the person

appointed to administer and operate it and, as a result, its purpose is not achieved,

and is either no longer capable of being achieved or is not likely to be achieved. His

Honour Judge Humphrey Lloyd stated that this could for most practical purposes be

equated to interference by a contracting party in the process whereby the other is

deprived of a right or benefit. Examples were the failure of an employer to re-

appoint an administrator or certifier on the resignation of the previously appointed

person or where that person fails or is unwilling to do his duty and the Employer will

not take steps to rectify the position. Reference was made to the decision in

60 It was not contended that it had been expressly agreed that Astea would do anything by a date proximate to March 2001, nor that any notice had been given making time of the essence of the contract in relation to Astea doing something by a date proximate to March 2001, it was just the date when Time Group’s patience expired.

Page 64: Time at Large and Reasonable Time for Completion

45

Panamena Europea Navigacion v Frederick Leyland Ltd61. It was held that non-

compliance with the machinery by the administrator was not in itself sufficient: the

effect must be that either or both of the parties to the contract do not in consequence

of the breakdown truly know their position or cannot or are unlikely to know it. If

the true position is or can be established by other contractual means then the

breakdown is likely to be immaterial even when the result of the breakdown is that

one party does not obtain the contractual right or benefit which would or might

otherwise have been established by the machinery, provided that the true position can

be restored by the operation of other contractual machinery.

2.7 Conclusion

Colman J stated in the case of Balfour Beatty Building Ltd v Chestermount

Properties Ltd62 that:

In the absence of an express provision, the consequence of the

occurrence of an act of prevention (in this case the giving of a

variation instruction after the most recently fixed completion date) was

that the entire extension of time, completion date and liquidated and

ascertained damages code was displaced by a general contractual duty

to complete the works within what in all the circumstances was a

reasonable time from the date of the act of prevention failing which the

contractors would be liable for unliquidated damages for breach of

contract in failing to complete within a reasonable time.

In the absence of any agreed contractual mechanism for fixing a new date for

completion, no such new date can be fixed and the contractor’s duty then is to 61 [1947] AC 428. 62 62 Build LR 1.

Page 65: Time at Large and Reasonable Time for Completion

46

complete the works within a reasonable time. Provided that a contractor has not

acted unreasonably or negligently, he will complete within a reasonable time despite

a protracted delay if the delay is due to causes outside his control. In such

circumstances, time is said to be at large (Chappell, 2005). The question of time

being at large and the relationship between the time for completion, liquidated

damages and extension of time clause are concluded below:

1. The general rule is that the main contractor is bound to complete the work by

the date for completion stated in the contract. If he fails to do so, he will be

liable for liquidated damages to the employer.

2. That is subject to the exception that the employer is not entitled to liquidated

damages if by his acts or omissions he has prevented the main contractor

from completing his work by the completion date

3. These general rules may be amended by the express terms of the contract,

such as extension of time clauses.

Page 66: Time at Large and Reasonable Time for Completion

CHAPTER 3

REASONABLE TIME

3.1 Introduction

The Concise Oxford Dictionary (10th edition) by the Oxford University Press

defines the word “reasonable” as fair and sensible, and as much as is appropriate or

fair. In the nineteenth century and earlier, the courts imposed implied terms on the

parties to all contracts of certain types, such as sale of goods and bills of exchange,

by way of judicial legislation. Such implied terms have been consolidated by statute

and, as Judge Peter Bowsher QC remarked in Barratt Southampton Ltd v Fairclough

Building Ltd (1988):

These terms now have the status of standard terms of contract upon

which everyone is deemed to contract unless express terms are agreed

to the contrary. There is little to be learned from them when

considering what terms should be implied into a modern commercial

contract falling outside those old cases or the consolidating statutes

into which they have been incorporated.

A straightforward instance of this type of term is to be found in the field of

sale of goods. Where there is a contract for the sale of goods, the Sale of Goods Act

Page 67: Time at Large and Reasonable Time for Completion

48

1979 implies various terms into the contract, for example that the goods will be

reasonably fit for any purpose made known to the seller. A similar term will be

implied in contracts for the supply of a service or contracts for work and materials by

section 4 of the Supply of Goods and Services Act 1982. (Powell-Smith et al., 1999)

In Barque Quilpue Ltd v Brown [1904] 2 KB 264, Vaughan Williams LJ said:

“... in this contract, as in every other, there is an implied contract by

each party that he will not do anything to prevent the other party from

performing the contract or to delay him in performing it. I agree that

generally such a term is by law imported into every contract, in the

same way as you import into every contract a stipulation that the

various things which are to be done by the one party or the other are, if

no time is specified, to be done within a reasonable time. In each of

these cases that may be called an implied contract.”

Where the construction contract does not expressly prescribe the time within

which the works are to be completed, the court may be prepared to infer that the

parties intended the works to be completed within a reasonable time.63 However,

before the court arrives at this inference, it must consider the contract as a whole and

the circumstances surrounding it. Where a completion date is clearly specified in the

contract, the contractor is expected to complete the works by the “due date”.64 In

such a situation, a contractor cannot maintain that he is entitled to complete the

works within a reasonable period after the date fixed65 (Chow, 2004).

The principles of reasonable time apply not only to contracts where time for

completion has not been specified in the first place, but also to contracts where

specified time has been lost and reasonable time substituted. Contracts whereby time

63 See: Charnock v Liverpool Corporation [1968] 1 WLR 1498 (CA). 64 See: Greater London Corporation v Cleveland Bridge and Engineering (1984) 34 BLR 57. 65 See: Raineri v Miles [1981] AC 1050 (HL), cf Amherst v James Walker [1983] Ch 305 at 315 (CA).

Page 68: Time at Large and Reasonable Time for Completion

49

for completion is not specified are very common in construction and may indeed

form the majority. This is because when the average householder employs a builder

to fit new windows, erect a porch or decorate the bedrooms, he pays most attention to

the price and the written quotation but beyond that the contractual details are

frequently left open. Where there is a formal contract and time is at large the defunct

extension of time provisions may serve well as some guide as to what is reasonable

time. Thus, extra works, exceptional weather, strikes etc., might all be taken into

account. With or without a formal contract it might be appropriate to look at the

production capability of the contractor, his management and financial resources, and

his other contractual commitments, particularly if known to both parties (Eggleston,

1992).

3.2 Reasonable Time

It has been seen that an obligation to complete within a reasonable time

sounding in damages arises either because the contract is silent as to time, or because

the specified time has ceased to be applicable by reason of some matter for which the

employer is responsible. It remains to consider what is a reasonable time (Wallace,

1995).

According to Davies (1989), at the turn of the century the general rule of law

as it then stood was that any act necessary to be done by either party in order to carry

out a contract must be done within a reasonable time. The principle was interpreted

that except where time was of the essence of the stipulation, a breach of contract was

only committed in the case of unreasonable delay in the performance of any act

agreed to be done. For example, where time was not essential, a party failing to

complete a sale of land on the day fixed by the agreement did not commit a breach of

contract either in equity or at law; it was only on failure to complete within a

reasonable time after that day that the contract was broken.

Page 69: Time at Large and Reasonable Time for Completion

50

However, by the middle of the century it was found that whether or not time

was of the essence, anyone who was actually injured by the breach of a time

stipulation could recover damages. In other words, a breach of a contractual

stipulation as to time which is not of the essence of a contract would not be treated as

a breach of a condition precedent to the contract, that is as a breach which would

entitle the innocent party to treat the contract as terminated or which would prevent

the defaulting party from suing the specific performance. Nevertheless, it was a

breach of the contract and entitled the injured party to damages if he had suffered

damage.

The current view of the law with regard to time within all contracts may be

summarized as follows. Time will not be considered to be of the essence unless:

1. The parties expressly stipulate that conditions as to time must be strictly

complied with

2. The nature of the subject matter of the contract or the surrounding

circumstances show that time should be considered to be of the essence

3. A party that has been subjected to unreasonable delay gives notice to the

party in default making time of the essence

In mercantile contracts, that is contracts which deal with commercial matters,

building contracts being analogous to them, time will be considered of the essence

out of practical necessity. Time is of the essence in building contracts because, for

example, the landowner has some use for the building on a specific date.

What then is the effect of the term ‘reasonable time’? According to Davies

(1989), what is a reasonable time may not depend solely upon the convenience and

financial interests of the contractors. No doubt, it is in their interest to have every

detail ‘cut and dried’ on the day a contract is signed, but a contract may not

Page 70: Time at Large and Reasonable Time for Completion

51

contemplate that. Rather, it may contemplate further drawings and details being

provided. The architect or engineer is to have time to provide them which is

reasonable having regard to the point of view of him and his staff and the point of

view of the client as well, as the point of view of the contractor.

Where the time for completion is not given in the contract documents, the

Supply of Goods and Services Act 1982, Part 2, section 14(1), provides for a term to

be implied that the work will be carried out within a reasonable time. However, if

parties to a contract were told by the client the contract completion date because it

had been left out of the contract documents, such evidence may not be admitted,

particularly where to put in the date would lead to a severe liquidated damages clause

being brought into operation. In other words, as a general principle, where a

complete blank is left in a material part of the contract evidence is not admissible to

fill it.

According to Wallace (1995), it has been seen that an obligation to complete

within a reasonable time sounding in damages arises either because the contract is

silent as to time, or because the specified time has ceased to be applicable by reason

of some matter for which the owner is responsible. It remains to consider what a

reasonable time is. Reasonable time is primarily a question of fact and must depend

on all the circumstances which might be expected to affect the progress of the works.

There are few, if any reported cases in England directly involving a typical building

or engineering contract, but it is suggested that certain questions require to be

answered before a reasonable time can be properly assessed.

Wallace (1995) further elaborated that in the first place, when arriving at a

reasonable time in “ordinary circumstances”, the parties may or may not have

contracted with the particular resources and capacity of the particular builder in

mind. Thus, an owner may have deliberately chosen a small local or jobbing builder,

with limited resources of capital, plant and labour, to build his house, in the hope of

getting a cheaper or better quality job while sacrificing speedy completion. On the

Page 71: Time at Large and Reasonable Time for Completion

52

other hand, a builder with limited resources might tender for a large contract in

competition with more substantial contractors and give no indication of his inability

to carry out the work as rapidly as them. In the former case the test might well be

subjective, and in the latter objective.66 A party may have expressly or impliedly

warranted or discounted his ability or capacity to maintain progress in a particular

situation or at a particular speed.

While it may be that most factors beyond the builder’s control will excuse

him, it is possible that expressly or impliedly the parties will have contracted with a

particular factor in mind. Thus, whereas there is little doubt that allowance would be

made for delay due to an unexpected strike, it would not, it is suggested, follow that a

contractor’s inability to obtain sufficient labour in competition with other contractors

in the district would excuse him. In the case of subcontractors of all kinds, whether

nominated or otherwise, it is submitted that the tendency of the courts should be not

to excuse the main contractor from meeting his main contract obligation in any case

where delay is caused by some act or omission within the subcontractor’s control,

though for that reason outside the main contractor’s direct personal control, since, in

such a case, the contractor will or should have his remedy against the subcontractor,

who in law is the contractor’s agent for the purpose of carrying out the works,

whether nominated or not. Any tendency to excuse the main contractor would in

effect be an invitation to subcontractors to default on their obligations, and might

well result in the owner failing to recover his own loss whereas the contractor might

still be able to recover any loss he personally might have suffered at the hands of the

subcontractor. Again, it may be a question whether the parties contracted with a

builder’s other commitments in mind. In approaching this question, it should be

borne in mind that with the increasing degree of specialist and sub-contracted work

in the building industry, the direct responsibilities of the main contractor have

become correspondingly limited to the provision of a site-organisation, a non-

specialised labour force, and materials and plant, so that in most cases the builder,

by entering into the contract, is, in effect, warranting that he has or will have at least

these available in sufficient quantity for due performance of his obligations. All

66 See Hydraulic Engineering Co Ltd v McHaffie, Goslett & Co. (1878) 4 QBD 670.

Page 72: Time at Large and Reasonable Time for Completion

53

these are matters which will, no doubt, be taken into consideration when making the

initial “ordinary circumstances” assessment, before considering the actual post-

contract circumstances (Wallace, 1995).

According to Chow (2004), the test of “reasonableness” is sometimes

construed as being synonymous with the convenience and economic interest of the

contractor. In Neodox Ltd v Swinton and Pendlebury Borough Council67 the

contractor alleged that there was an implied obligation on the part of the employer to

provide all necessary instructions and details “in sufficient time to enable the

contractor to execute and complete the works in an expeditious and economic

manner and/or in sufficient time to prevent the contractor being delayed in such

execution and completion”. Diplock J ruled that what was a reasonable time did not

depend solely on the convenience and financial interests of the contractor. He

observed that while it may appear to the contractor that it is in his interest “to have

every detail cut and dried on the day the contract is signed”, such a state of affairs

could not have been contemplated at the time of the contract. He then proceeded to

hold that what was a reasonable time was a question of fact to be determined with

reference to all the circumstances of the case. These include:

1. Considerations of the employer’s engineer and his staff

2. The order by which the works were to be carried out and approved by the

engineer

3. The contractor’s requests for particular details

4. Whether the details requested relate to variations

5. The length of the contract period

Admittedly, the list of factors tendered by Diplock J in his judgment cannot, on any

stretch of imagination, be considered to be exhaustive. However, it does serve to

indicate the wide range of factors which have to be considered when determining the

question of “reasonableness” with respect to the timing of instructions, additional

drawings and information.

67 (1958) 5 BLR 34.

Page 73: Time at Large and Reasonable Time for Completion

54

In calculation of reasonable time, Gill (1969) stated that all the circumstances

of the case should be taken into consideration, such as the nature of the works to be

done, the time necessary to do the work, the ability of the contractor to perform68, the

proper use of customary appliances69, and the time which a reasonably diligent

producer of the same class as the contractor would take.70

3.3 Statutory Provisions that Apply the Term “Reasonable Time”

3.3.1 Sale of Goods Act 1957 (Revised 1989)

According to Vohrah and Wu (2003), the statute applicable to sale of goods

in Peninsular Malaysia is the Sale of Goods Act 1957 (Revised 1989). There is no

equivalent statute for the states of Sabah and Sarawak and the law in these two states

is governed by section 5(2) of the Civil Law Act 1956 which provides, among others,

that ‘the law to be administered shall be the same as would be administered in

England in the like case at the corresponding period’. Consequently, these two states

are bound by statute to continue to apply principles of English law relating to the sale

of goods. The model of the local Sale of Goods Act (SGA) was the English Sale of

Goods Act of 1893 which is re-enacted almost in its entirety with some minor

modifications such as the numbering of the provisions.

Chapter IV of the SGA deals with the performance of the terms of the

contract, including the delivery of goods. Where under the contract of sale, the seller

is bound to send the goods to the buyer but no time for sending them is fixed, the

seller is bound to send them within a reasonable time (36(2)). Demand or tender of

68 Attwood v Emery (1856), 1 CB (NS) 110; 26 LJCP 73. 69 Lyle Shipping Co. v Cardiff Corporation [1900] 2 QB 638. 70 Supra note 66.

Page 74: Time at Large and Reasonable Time for Completion

55

delivery may be treated as ineffectual unless made at a reasonable hour. What is a

reasonable hour is a question of fact (36(4)). Assuming that a seller is bound to

make delivery under the contract and he requests the buyer to take delivery, and the

buyer does not respond within a reasonable time after such request. The buyer is

liable to the seller for any loss occasioned by his neglect or refusal to take delivery,

and to pay a reasonable charge for the care and custody of the goods. This does not

affect the seller’s right for damages under the contract where the neglect or refusal of

the buyer to take delivery amounts to a repudiation of the contract (s.44). Where

delivery is delayed through the fault of either seller or buyer, the goods are at risk of

the party at fault as regards any loss which might not have occurred but for such fault

(s.26).

3.3.2 Supply of Goods and Services Act 1982 (UK)

In Singapore, Malacca, Penang, Sabah and Sarawak, the (UK) Supply of

Goods and Services Act 1982 is applicable and gives statutory status to rule that

largely existed in common law, mirroring the Sale of Goods Acts (in Singapore,

except for Part II). The 1982 Act extends the general philosophy of implied

warranties as to standard of performance to contracts for services and to the transfer

of goods under other contractual arrangements such as building contracts. Section 14

of the Act mentioned that where the time for performance has not been fixed, a term

is implied for performance ‘within a reasonable time’. What is a reasonable time is

stated in section 14(2) to be a question of fact (Robinson et al., 1996).

Page 75: Time at Large and Reasonable Time for Completion

56

3.3.3 International Sales

Two international conventions referred to as the Hague Conventions 1964

governs contracts for the sale of goods between parties residing in different

countries. The United Nations Commission on International Trade Law

(UNCITRAL) has drafted a convention to replace the Hague Conventions and it

adopted at a conference in Vienna in 1980 as the Convention on Contracts for the

International Sale of Goods. It comes into operation only when the necessary

number of ratifications has been received (Vohrah and Wu, 2003).

Andersen (1998) presented a paper that focused on the meaning of the term

"reasonable time" as understood by Article 39(1) of the 1980 United Nations

Convention on Contracts for the International Sale of Goods (referred to as the CISG

or the Convention). This provision provides that a buyer notify the seller “within

reasonable time” after he discovers or ought to have discovered that the goods do not

conform to the contract. The objectivity of a term is especially important where the

CISG is concerned, as this is a uniform law which must be interpreted and practised

uniformly. The aim of the determination of "reasonable time" in Article 39(1) will

be to establish a pattern to the application of the provision, and assess whether the

term is an autonomous term applied uniformly.

Article 38 prescribes a duty for the buyer to inspect the goods delivered to

him within a short period. Since Article 39(1) relies not only on the time of

discovery of non-conformity but also on the time a buyer “ought to have discovered

it”, these two provisions are closely entwined. Indeed, Article 38 is prefatory to

Article 39. This relationship with Article 38 usually determines precisely from when

the reasonable time period is to be measured: as the time-frame of reasonable time

pertains to the period after the non-conformity is discovered (or ought to have been

discovered), it is only related to the time of delivery via Article 38. The Article 38

examination need not be carried out immediately after the delivery of the goods

Page 76: Time at Large and Reasonable Time for Completion

57

(although this is recommendable to avoid all doubts) nor within a set time-frame, but

hurriedly according to the objective circumstances of the case.

While the purpose of the provision would seem to imply that the time-frame

should be reasonable for the seller whose interests it protects, the fact that it

represents a flexible compromise in the interests of the buyer would outweigh this

consideration. By taking “a wide range of factors” into account, and thus the

reasonableness of the time-frame in both the seller's and the buyer's point of view, a

more subjective and fair solution can be reached in each individual case. But when

applying this interpretation to a particular case, the practitioner should be aware that

a wide range of factors does not mean all factors. Not all factors are suitable for

influencing the time-frame in question. The influence of some aspects must be

considered legal misapprehensions in international trade rather than factors of

reasonableness. For instance, what if these factors include purely domestic aspects?

Many determinations of reasonable time glean their identity from the international

practice of Courts and Tribunals when determining “reasonable time” and it is

certainly here that the key is to be found. It is the actual application of the provision

which ultimately defines it.

3.4 Conclusion

The word “reasonable time” is found in, among others, Supply of Goods and

Services Act 1982, Sales of Goods Act 1957, United Nations Convention on

Contracts for the International Sale of Goods and Landlord and Tenant Act 1988.

This term is also found in construction contracts, contracts of sale and purchase of

land and charterparty.

Page 77: Time at Large and Reasonable Time for Completion

58

According to the Law Dictionary, reasonable time is a subjective standard

based on the facts and circumstances within a particular case, with applicability in a

variety of contexts. Within commercial law, the term applies to the amount of time

in which to accept an offer, to inspect goods prior to payment or acceptance, to await

performance by a party who repudiates a contract or the time in which a seller may

substitute conforming goods for goods rejected by a buyer as non-conforming. If not

governed by statute, the term may also refer to the time allowed to set aside a default

judgment, to inform an insurance company of an accident, to file certain claims, and

to make various motions. Despite its subjectivity, it can be seen that this term is

widely used and should therefore be studied in depth.

Page 78: Time at Large and Reasonable Time for Completion

CHAPTER 4

REASONABLE TIME WHEN TIME IS AT LARGE

4.1 Introduction

The preceding chapter elaborated on reasonable time and as Gill (1969) puts

it, in a building contract to perform a work where no particular time is specified

within which the work is to be completed, an agreement to complete within a

reasonable time will be implied and a reasonable time for completion will be

allowed.68 The question as to what is a reasonable time is one of fact69 and will be

addressed in the discussion below.

Hence, this chapter will identify and determine the meaning of “reasonable

time” when time is at large. Those meanings are based on decided court cases,

which mainly were held under England law and laws in other Commonwealth

countries.

68 Startup v Macdonald (1843), 6 Man. & G. 593, per Rolfe, B. 69 Fisher v Ford (1840), 12 Ad. & El. 654, per Lord Denman, C. J.

Page 79: Time at Large and Reasonable Time for Completion

60

A total number of ten cases centered on what is a reasonable time were

studied, three of them were involving construction, two involving shipping, two on

carriage of goods through railway and the remaining were contracts of sales of

goods, and supply of goods and services.

4.2 Reasonable Time when Time is at Large

As have been reviewed, time at large occurs when no time of completion is

specified in the contract/where the contract is silent as to time and where the

stipulated date has ceased to be applicable by reason of prevention or breach. The

obligation is then to complete the works within a reasonable time. Therefore,

through the analysis of courts’ judgments, the meaning as to “reasonable time” can

be divided to reasonable time where no time for completion is specified in the

contract and reasonable time where the stipulated date has ceased to be applicable by

reason of prevention or breach.

4.2.1 Reasonable Time Where No Time for Completion is specified in the

Contract/Contract is Silent as to Time

Six of the ten cases are cases whereby the time for completion is not

stipulated in the contract. These cases are discussed in detail to give a background of

the cases and then what the judges say about reasonable time in such cases. One

well-known case is Pantland Hick v Raymond & Reid70. In this case, a consignee,

upon whom rested the contractual obligation to unload the appellant’s vessel, and

70 [1893] AC 22.

Page 80: Time at Large and Reasonable Time for Completion

61

where no time for discharge was stipulated, argued that it had discharged a vessel

within a reasonable time having regard to the fact that there had been a single cause

of delay, being a strike of dock workers over which the consignee had no control and

which prevented performance of the contract.

The appellant contended that the test is what time would have been required

for the discharge of the vessel in ordinary circumstances, and to the extent that the

respondents had to provide labour, they must be responsible if the discharge is

delayed this point. The respondents argued that the test to be applied is what was

reasonable under existing circumstances assuming that, in so far as the circumstances

were extraordinary, they were not due to any act or default on the part of the

respondents.

Lord Herschell LC stated:

The only sound principle is that the ‘reasonable time’ should depend

on the circumstances which actually exist. If the cargo has been taken

with all reasonable dispatch under those circumstances I think the

obligation of the consignee has been fulfilled. When I say the

circumstances that actually exist, I, of course, imply that in those

circumstances, in so far as they involve delay, have not been caused or

contributed to by the consignee.

In the same case Lord Watson said:

When the language of a contract does not expressly, or by necessary

implication, fix any time for the performance of a contractual

obligation, the law implies that it shall be performed within a

reasonable time. The rule is of general application, and is not confined

to contracts for the carriage of goods by sea. In the case of other

contracts the condition of reasonable time has been frequently

Page 81: Time at Large and Reasonable Time for Completion

62

interpreted; and has invariably been held to mean that the party upon

whom it is incumbent duly fulfils his obligation, not withstanding

protracted delay, so long as such delay is attributable to causes beyond

his control, and he has neither acted negligently nor unreasonably.

A common carrier of goods is not, in the absence of a special contract, bound

to carry within any given time, but only within a time which is reasonable, looking at

all the circumstances of the case; and he is not responsible for the consequences of

delay arising from causes beyond his control. The defendants, a railway company,

were prevented, by an unavoidable obstruction on their line, from carrying the

plaintiff's goods within the usual (a reasonable) time. The obstruction was caused by

an accident resulting solely from the negligence of another company who had, under

an agreement with the defendants, sanctioned by act of parliament, running powers

over their line. It was held in this case of Taylor v The Great Northern Railway

Company71 that the defendants were not liable to the plaintiff for damage to his

goods caused by the delay.

In the case of The Lyle Shipping Company Ltd v The Corporation of Cardiff72,

by a charter a cargo was to be “discharged with all reasonable dispatch as

customary”. The custom at the port was to discharge into the railway wagons.

Without any negligence on the part of the charterers, but owing to the stress of work,

and a consequent deficiency in the number of wagons available, the ship was delayed.

It was held by the Court of Appeal, that the charterers, having done their best to

procure the appliances that were customarily used for discharging such a ship, and

having used them with proper dispatch, were not liable for delay.

Smith LJ stated:

Now, the contract which the plaintiffs have in this case with the

defendants for the discharge of the cargo, as will be seen from the 71 [LR] 1 CP 385. 72 [1900] 2 QB 638.

Page 82: Time at Large and Reasonable Time for Completion

63

latest authority upon the subject in the House of Lords - no fixed time

being stipulated for the discharge - is that the plaintiffs will discharge

the cargo within a reasonable time under existing circumstances, or, in

other words, with all due diligence having regard to all the existing

circumstances, and, in my opinion, there is no limit as to what are

existing circumstances, as argued by the plaintiff - namely, the limit of

the user of the port appliances. The case to which I allude is that of

Hick v. Raymond in the House of Lords, and when what is therein laid

down is understood it will be seen that the defendants' contract is what

I have said it is.

In the case of Sims & Co. v Midland Railway Co.73, perishable goods were

consigned by the defendants' railway for delivery to the plaintiffs, no time being

specified within which the goods were to be delivered. During the transit a general

strike of railway servants, including the defendants' servants, broke out, and the

defendants were unable to forward the goods to their destination. There was no

evidence that the strike was caused or contributed to by the defendants. The goods

becoming deteriorated the defendants sold them. In an action to recover damages for

breach of contract, to deliver the goods, it was held that in calculating what was a

reasonable time for delivery in accordance with the principle laid down in Hick v

Raymond & Reid74, the strike of the defendants' servants must be taken into

consideration as one of the circumstances existing at the time of the carriage, and that

therefore the defendants were not liable for the delay.

In the course of his judgment Ridley, J., having cited the passages from Lord

Herschell's judgment in Hick v. Raymond & Reid:

It is not right to say that, because a strike of the servants of the

defendants, who are under a duty to deliver the goods, causes the

delay, it follows that the cause of delay is one within the defendants'

73 [1913] 1 KB 103. 74 Supra note 70.

Page 83: Time at Large and Reasonable Time for Completion

64

control, and that they are liable for it. I can imagine a case in which it

might be said that the happening of the strike was within the control of

the railway company; but there ought to be evidence of it. Apart from

such evidence the mere fact that there was a strike among the railway

company's servants causing the delay would not make the company

liable; but the strike would be an existing circumstance in the

ascertainment of a reasonable time. I do not say how the matter would

have stood if there had been evidence that the strike was brought about

by some unreasonable demand on the part of the railway company.

There was no such evidence.

In British Steel Corporation v Cleveland Bridge & Engineering Co Ltd75 the

defendants successfully tendered for the fabrication of steel work in the construction

of a building. The design required steel beams to be joined to a steel frame by means

of steel nodes. The plaintiffs, who were iron and steel manufacturers, were

approached by the defendants to produce a variety of cast-steel nodes for the project.

Two main areas of dispute developed between the parties. First, was there any

binding contract between the parties at all, under which the nodes were delivered?

Cleveland Bridge & Engineering (CBE) contended that there was such a contract,

which was to be found in certain documents (including a letter of intent issued by

CBE) and the conduct of British Steel Corporation (BSC) in proceeding with the

manufacture of the nodes. BSC's primary contention was that no binding contract

was ever entered into, and that they were entitled to be paid a reasonable sum for the

nodes on a quantum meruit, a claim sounding not in contract but in quasi contract.

The motives of the parties in putting their cases in these different ways lay primarily

in the fact that, unless there was a binding contract between the parties there was no

legal basis for CBE's counterclaim for damages in respect of late delivery or delivery

out of sequence. So far as delivery was concerned, CBE's submission was that BSC's

obligations, under the contract alleged by them to have come into existence, was to

deliver the goods in the requested sequence and within a reasonable time.

75 [1984] 1 All ER 504, 24 Build LR 94.

Page 84: Time at Large and Reasonable Time for Completion

65

The first issue is concerned therefore with an analysis of the legal relationship

between the parties. The second issue is whether, if CBE are right in their

submission that there was a binding contract as alleged by them, BSC were in breach

of that contract in delivering the goods late and out of sequence. This latter issue is

concerned primarily with consideration of the various events and difficulties which

occurred in production of the nodes by BSC, and deciding whether, in the light of

these events, BSC failed to deliver the goods within a reasonable time as alleged by

CBE.

It was held that the parties had ultimately been unable to reach final

agreement on the price or other essential terms, thus, the contract was eventually not

entered into and therefore the work performed in anticipation of it was not referable

to any contractual terms as to payment or performance. On the question of delivery

within a reasonable time, Goff J stated that:

The question of what constituted a reasonable time had to be

considered in relation to the circumstances which existed at the time

when the contractual services were performed, but excluding

circumstances which were under the control of the party performing

those services. As I understand it, I have first to consider what would,

in ordinary circumstances, be a reasonable time for the performance of

the relevant services and I have then to consider to what extent the

time for performance by BSC was in fact extended by extraordinary

circumstances outside their control.

His Lordship then considered the evidence and concluded that a reasonable

period for the manufacture of the 137 nodes, which were at the request of CBE, was

55 weeks and that since such a period would have gone well beyond 11 April 1980

when the last node was in fact delivered it followed that if, contrary to his Lordship's

previously expressed opinion, BSC had been bound to complete the work within a

reasonable time they would not have been in breach of that obligation. (All but one

Page 85: Time at Large and Reasonable Time for Completion

66

of the nodes had been delivered, delivery of the remaining node being held up until

11 April 1980 due to an industrial dispute at the plaintiffs' plant.)

The case of Astea (UK) Limited v Time Group Limited76 warns of the dangers

of entering into a contract without setting express deadlines for completion - in

particular when attempting to rely on the law which says that performance must be

carried out “within a reasonable time”. In July 2000, Astea entered into a contract

with Time Group, a computer retailer, to supply Time with software for its customer

call centre. Owing to delays on both sides, the integration and testing of the new

software was delayed and Time withheld payment to Astea on the basis that it was in

breach of section 14(1) of the Supply of Goods and Services Act 1982 because it had

not performed the software contract within “a reasonable time” and had repudiated

the contract by failing to complete the work by 6 March 2001. Time argued that

“reasonable time” meant that Astea had to complete the services as fast as was

humanly or technically possible, subject only to delays that it could not control.

However, the Technology and Construction Court ruled there was no express term to

complete the work by 6 March 2001 and the implied term under s14(1) of the

Services Act applied. Therefore Astea had not exceeded a reasonable time for

performance and Time was ordered to pay. In order for Time's argument to have

some credibility, it needed to issue Astea with a written notice setting out a new

deadline for performance and making "time of the essence", which it did not do.

Both counsel for the defendant and plaintiff endeavoured to seek support for their

respective emphases from the well-known decision of the House of Lords in

Pantland Hick v. Raymond & Reid77.

From the six cases discussed above, the considerations of what is a

reasonable time are given below:

- A reasonable time looking at all the circumstances of the case.

76 Supra note 59. 77 Supra note 70.

Page 86: Time at Large and Reasonable Time for Completion

67

- Reasonable under the existing circumstances, assuming that those circumstances,

in so far as they involve delay, are not caused or attributed to by him.

- The condition of reasonable time has been frequently interpreted; and has

invariably been held to mean that the party upon whom it is incumbent duly fulfils

his obligation, not withstanding protracted delay, so long as such delay is

attributable to causes beyond his control, and he has neither acted negligently nor

unreasonably.

- Perform with all due diligence having regard to all the existing circumstances, and

there is no limit as to what are existing circumstances.

- What constitutes a reasonable time has to be considered in relation to

circumstances which existed at the time when the contract obligations are

performed, but excluding circumstances which were under the control of the

contractor. What in ordinary circumstances was a reasonable time for

performance and then considering to what extent the time for performance of the

contractor was in fact extended by extraordinary circumstances outside his control.

- Consideration of a reasonable time for performance is likely to include taking into

account any estimate given by the performing party of how long it would take him

to perform.

- The focus of attention in considering reasonable time is likely to be upon the

allocation of resources to performance of the relevant contractual obligations.

A common consideration as to what constitutes a reasonable time in all the

cases stated is a reasonable time looking at all the circumstances of the case. Lord

Ashbourne said in the case of Pantland Hick v. Raymond & Reid78:

78 Supra note 70.

Page 87: Time at Large and Reasonable Time for Completion

68

What is the meaning of this expression “reasonable time”? It is

obvious that “reasonable” cannot mean a definite and fixed time. It

would not be “reasonable” if it was not sufficiently elastic to allow the

consideration of circumstances, which all reason would require to be

taken into account. The appellant accordingly admits that the

consignee has a right to have all ordinary circumstances taken into

account, but insists that all extraordinary circumstances are to be

excluded from consideration. Is this distinction sound, and does it rest

upon any real principle? If the consignee does all he can, is not his

conduct reasonable? If by circumstances absolutely outside his control

he can do nothing, is his inaction unreasonable? If it is reasonable to

consider some circumstances outside his control in favour of the

consignee, why are not all circumstances in the events which actually

happen, and which he cannot control, also to be taken into account? In

considering how to ascertain “reasonable time”, must not the question

come in, whether the consignee in the circumstances which eventuated

acted unreasonably? If throughout the consignee acted reasonably, if

he did all he could, if he omitted nothing that he should have done,

why should all the circumstances be arbitrarily divided into ordinary

and extraordinary for the purpose of putting a narrow and artificial

meaning upon the words “reasonable time”?

4.2.2 Reasonable Time where the Stipulated Date has ceased to be Applicable

by Reason of Prevention or Breach

The remaining four cases are cases whereby the stipulated date for completion

in the contract has ceased to be applicable by reason of acts of prevention or breach.

Where, as a condition of its performance, time is of the essence of a contract for the

sale of goods and, on the lapse of the stipulated time, the buyer continues to press for

delivery, thus waiving his right to cancel the contract, he has a right to give notice

Page 88: Time at Large and Reasonable Time for Completion

69

fixing a reasonable time for delivery, thus making time again of the essence of the

contract, which, if not fulfilled by the new time stipulated, he will then have the right

to cancel. The reasonableness of the time fixed by the notice must be judged as at the

date when it is given. In similar circumstances, in the case of a contract for work and

labour done, the person who has ordered the work can give a valid notice to the

contractor making, time again of the essence of a contract. A reasonable time meant,

in accordance with well-known authorities, a reasonable time in the circumstances as

they actually existed, that is, that the plaintiffs would not exceed a reasonable time if

they were prevented from delivering by causes outside their control, such as strikes or

the impossibility of getting parts, and events of that kind; and that on the evidence in

this case it could not be said that a reasonable time was in that sense exceeded.79

Reasonable time has to be considered in the light of the circumstances which

prevailed after the contract. One has to consider what is the reasonable time provided

for. There were two things that the buyers had to do in this case. First, they had to

provide some sterling. They might have made an arrangement that they were merely

to pay in sterling. In that case they would merely have had to provide themselves

with the foreign currency; but they made an arrangement that they were to pay by

letter of credit. So that they had two things to do, the letter of credit being in sterling:

they had to get the sterling and they had to arrange for a letter of credit. The sterling

is the currency in which they are buying and that is what they had first to provide.

What the time provided for, the few weeks or the reasonable time, was for the

machinery of getting the letter of credit. It was not provided for, or intended to be

used for, obtaining the sterling.80

In CCECC (HK) Ltd v Might Foundate Developement Ltd & Ors81 it was

stated that in order to establish a time at large argument, it requires two-stages, that

are establishing that there was an act of prevention by the Respondent which caused

delay and that the delay is not covered by the extension of time provision. The

79 Rickards v Oppenheim [1950] 1 KB 616 80 Etablissements Chainbaux S.A.R.L. v Harbormaster Ltd [1955] 1 Lloyd’s Rep. 303 81 [2001] HKCU 916.

Page 89: Time at Large and Reasonable Time for Completion

70

Respondent has admitted it was in breach of Contract in delaying of payment of the

Interim Certificates (Nos. 12 to 17). The Claimant says that Clause 23 of the

Contract does not cover such default by the Employer.

In this time at large issue, it was found that the Claimant was delayed by the

Respondent’s lack of payment as they depended very heavily on these interim

payments. There were admitted late payments running into millions of dollars. An

act of prevention by the Respondent sets time at large and that the Respondent is not

entitled to deduct liquidated damages and it now has a reasonable period in which to

finish the Works. A reasonable time for the completion of the Works is calculated.

In calculating this time, the Claimant is entitled to rely on the effects of non-payment

and late payment of interim payments.

In the case of Shawton Engineering Ltd v DGP International Ltd 82, the

appellant, Shawton Engineering Ltd, was the sub-contractor to a joint venture, KAT

Nuclear for the design and manufacture of a number of packages as part of the

construction of premises and process plant at Sellafield for handling nuclear waste.

The appellant sub-contracted the design work of five of these packages (numbered

S468, S469, S511, S512 and S514) to the respondent, DGP International Ltd. The

sub-contract for each package originally had a fixed completion date. In the event, in

one of the contracts, there were variations instructed before and after the original

completion date. On the other four contracts, the variations were all instructed after

the original completion dates. By October 2000, the respondent was being asked to

explain the reason for the delay. By letter dated 7 November 2000, the appellant said

that it had to insist that within seven days the respondent provide it with an acceptable

timeframe for completion of all contract works. Eventually, the respondent had not

completed its work on any of the packages and the appellant terminated or purported

to terminate the contracts. The appellant claimed against the respondent for breach of

contract. There was no contractual mechanism for extending time on account of the

variations. The parties agreed and HHJ Gilliland QC accepted that the effect of the

82 [2005] EWCA Civ 1359.

Page 90: Time at Large and Reasonable Time for Completion

71

variations was that the respondent became obliged to complete its work within a

reasonable time.

It was held that what was a reasonable time had to be judged as at the time

when the question arose in the light of all relevant circumstances. One such

circumstance was that the respondent had originally agreed fixed time periods

(although upon a misapprehension as to the work content); another was the true work

content. These worked in opposite directions. The mere instruction of a variation

after the original date for completion would not by itself necessarily mean that a

reasonable time had to be assessed afresh by reference only to the variation and

whatever work happened to remain at the date of the variation (which is what the

judge appeared to say); it was possible that a modest variation instruction given after

an original completion date had passed could, depending on all the circumstances,

result in an obligation to complete by a date in the past. However, the question was a

composite one, and the circumstances here included that the variations were

significant in scope and that the appellant was not insisting on, nor particularly

concerned about, early completion of the respondent's work. The original completion

dates and periods had cased to be of any relevance. This overlaid to extinction any

question of calculating time periods by reference to the original dates for completion

and the work content of variations. The judge was right to hold that the appellant had

not established what was a reasonable time for completion; and that, on 7 November

2000, the reasonable time for completion was to be assessed afresh, mainly with

reference to the outstanding work content including variations. Therefore, the

respondent was not in breach for delay on 7 November 2000 and the appeal failed.

From the four cases discussed above, the considerations of what is a

reasonable time are given below:

- A reasonable time meant, a reasonable time in the circumstances as they actually

existed

Page 91: Time at Large and Reasonable Time for Completion

72

- Effects of acts of prevention by Employer can be considered in calculating a

reasonable time for completion

- The fact that the experts had agreed what was an appropriate extension of time

together with the originally agreed period was a fair indication of what should be

regarded as a reasonable time for completion of the work, but that is in effect to

treat the originally agreed period as being a reasonable period

The following tables (Table 4.1 and Table 4.2) summarize all the cases

discussed above and give a clearer view on the explanation and meaning of

“reasonable time” for each case and as well as the type of contracts involved.

Page 92: Time at Large and Reasonable Time for Completion

73

Table 4.1: Reasonable time where no time for completion is specified in the contract/contract is silent as to time

No

Cases

Explanation and Meaning of “Reasonable Time”

Type of Contract/ Contractual Relationship

1 Taylor v The Great Northern Railway Company [LR] 1 CP 385

- Reasonable time means a reasonable time looking at all the circumstances of the case.

- Circumstance in the case: carrying goods on the railway company’s line within the usual (a reasonable) time was unavoidably obstructed.

Carriage of goods/ Owner of Goods

and Railway Company

2 Pantland Hick v Raymond & Reid [1893] AC 22

- Lord Watson said that when the language of a contract does not expressly, or by necessary implication, fix any time for the performance of a contractual obligation, the law implies that it shall be performed within a reasonable time. The rule is of general application, and is not confined to contracts for the carriage of goods by sea. In the case of other contracts the condition of reasonable time has been frequently interpreted; and has invariably been held to mean that the party upon whom it is incumbent duly fulfils his obligation, not withstanding protracted delay, so long as such delay is attributable to causes beyond his control, and he has neither acted negligently nor unreasonably.

- Within a time which is reasonable under the existing circumstances, assuming that those circumstances, in so far as they involve delay, are not caused or attributed to by him.

- Circumstance in the case: unloading of cargo was interrupted by a strike of the dock labourers which delayed the discharge.

Shipping/ Shipowner and

Consignee

Page 93: Time at Large and Reasonable Time for Completion

74

Table 4.1: Reasonable time where no time for completion is specified in the contract/contract is silent as to time (cont’d)

No

Cases

Explanation and Meaning of “Reasonable Time”

Type of Contract/ Contractual Relationship

3 The Lyle Shipping Company Ltd v The Corporation of Cardiff [1900] 2 QB 638

- No fixed time being stipulated for the discharge - is that the plaintiffs will discharge the cargo within a reasonable time under existing circumstances, or, in other words, with all due diligence having regard to all the existing circumstances, and there is no limit as to what are existing circumstances - namely, the limit of the user of the port appliances.

Shipping/ Shipowner and

Charterer

4 Sims & Co. v Midland Railway Co. [1913] 1 KB 103

- Reasonable time under the existing circumstances - Circumstance in the case: a general strike of railway servants,

including the defendants' servants, broke out, and the defendants were unable to forward the goods to their destination.

Carriage of goods/ Purchaser of goods

and Railway Company

Page 94: Time at Large and Reasonable Time for Completion

75

Table 4.1: Reasonable time where no time for completion is specified in the contract/contract is silent as to time (cont’d)

No

Cases

Explanation and Meaning of “Reasonable Time”

Type of Contract/ Contractual Relationship

5 British Steel Corporation v Cleveland Bridge & Engineering Co Ltd [1984] 1 All ER 504, 24 Build LR 94.

- What constitutes a reasonable time has to be considered in relation to circumstances which existed at the time when the contract obligations are performed, but excluding circumstances which were under the control of the contractor.

- These principles are applied by first considering what in ordinary circumstances was a reasonable time for performance and then considering to what extent the time for performance of the contractor was in fact extended by extraordinary circumstances outside his control. Whether a reasonable time has been taken to do the works cannot be decided in advance, but only after the work has been done.

Supply of Material in Construction/

Steel manufacturer and Contractor

6 Astea (UK) Limited v Time Group Limited [2003] EWHC 725 (TCC)

- His Honour Judge Seymour thinks that consideration of a reasonable time for performance “... is likely to include taking into account any estimate given by the performing party of how long it would take him to perform…”

- The focus of attention is likely to be upon the allocation of resources to performance of the relevant contractual obligations. In any sphere of commercial or personal life it is necessary for decisions to be made as to the relative priority of matters which need to be dealt with and as to the resources which it is appropriate to allocate to such matters.

- It would be wrong in principle to proceed that an obligation to do something within a reasonable time was equivalent to an obligation to do it as soon as was practicably possible, subject only to not being held responsible for causes of delay without one’s control.

Supply of Goods and Services/ Provider of

Software and Manufacturer and

Retailer of Computers

Page 95: Time at Large and Reasonable Time for Completion

76

Table 4.2: Reasonable time where the stipulated date has ceased to be applicable by reason of prevention or breach

No

Cases

Explanation and Meaning of “Reasonable Time”

Type of Contract/ Contractual Relationship

1 Rickards v Oppenheim [1950] 1 KB 616

- A reasonable time meant, a reasonable time in the circumstances as they actually existed, that is, that the plaintiffs would not exceed a reasonable time if they were prevented from delivering by causes outside their control, such as strikes or the impossibility of getting parts, and events of that kind; and that on the evidence in this case it could not be said that a reasonable time was in that sense exceeded.

Sales of Goods/ Motor trader and

Purchaser

2 Etablissements Chainbaux S.A.R.L. v Harbormaster Ltd [1955] 1 Lloyd’s Rep. 303

- Reasonable time has to be considered in the light of the circumstances which prevailed after the contract. One has to consider what is the reasonable time provided for.

Sales of Goods/ Buyer and Seller of

marine engines

Page 96: Time at Large and Reasonable Time for Completion

77

Table 4.2: Reasonable time where the stipulated date has ceased to be applicable by reason of prevention or breach (cont’d)

No

Cases

Explanation and Meaning of “Reasonable Time”

Type of Contract/ Contractual Relationship

3 CCECC (HK) Ltd v Might Foundate Developement Ltd & Ors [2001] HKCU 916.

- A reasonable time for the completion of the Works is calculated. In calculating this time the Claimant was entitled to rely on the effects of non-payment and late payment of interim payments (Acts of prevention by Employer).

Construction Contract/

Contractor and Employer

4 Shawton Engineering Ltd v DGP International Ltd [2005] EWCA Civ 1359

- It was submitted that the fact that the experts had agreed what was an appropriate extension of time together with the originally agreed period was a fair indication of what should be regarded as a reasonable time for completion of the work, but that is in effect to treat the originally agreed period as being a reasonable period, notwithstanding that that period was agreed to under misapprehension

- Assessing a reasonable time meant having regard to all the circumstances, one of which was that the true work content which the respondent undertook was far greater than it had anticipated. What was a reasonable time had to be judged as at the time when the question arose in the light of all relevant circumstances. One such circumstance was that the respondent had originally agreed fixed time periods (although upon a misapprehension as to the work content)

Construction Contract/

Subcontractor and Sub subcontractor

Page 97: Time at Large and Reasonable Time for Completion

78

4.3 Conclusion

From the findings, it can be concluded that in the absence of a stipulated

period, calculating what would be a reasonable time for performance of the relevant

services can take into consideration the allocation of resources to performance of the

relevant contractual obligations. Different sized contractors can be expected to have

different resources at their disposal and it is reasonable to suppose that resources and

productivity will be essential factors to be considered. As in the case of Astea (UK)

Limited v Time Group Limited83 Judge Seymour accepted that the plaintiff’s

resources were an important concept, saying:

The focus of attention is likely to be upon the allocation of resources

to performance of the relevant contractual obligations. In any sphere

of commercial or personal life it is necessary for decisions to be made

as to the relative priority of matters which need to be dealt with and as

to the resources which it is appropriate to allocate to such matters. It

would be wrong in principle to proceed that an obligation to do

something within a reasonable time was equivalent to an obligation to

do it as soon as was practicably possible, subject only to not being held

responsible for causes of delay without one’s control.

Judge Seymour also seemed to think that consideration for a reasonable time

for performance “…is likely to include taking into account any estimate given by the

performing party of how long it would take him to perform…”. Such estimated

completion period would be a reasonable point from which to assess reasonable time

for performance.

83 Supra note 59.

Page 98: Time at Large and Reasonable Time for Completion

79

In circumstances where the stipulated date has ceased to be applicable due to

prevention or breach, the original contract completion date will tend to be accepted as

a basis of reasonable time in ordinary circumstance so that the new reasonable time

for completion will be arrived at by adding such additional periods of delay as can be

shown to have been caused by the prevention as seen in CCECC (HK) Ltd v Might

Foundate Developement Ltd & Ors84. However, the problem arises when the original

completion date was not itself reasonable as stated in the case of Shawton

Engineering Ltd v DGP International Ltd85. It was submitted that the fact that the

experts had agreed what was an appropriate extension of time together with the

originally agreed period was a fair indication of what should be regarded as a

reasonable time for completion of the work, but that is in effect to treat the originally

agreed period as being a reasonable period. There was a misapprehension to the

defendant’s true work content. It is clear that DGP seriously underestimated both the

number of drawings which would be required and how long the work would take.

84 Supra note 81. 85 Supra note 82.

Page 99: Time at Large and Reasonable Time for Completion

CHAPTER 5

CONCLUSION AND RECOMMENDATIONS

5.1 Introduction

Previous chapters presented the literature review on time at large and

reasonable time, as well as the analysis of the caselaws leading to findings on what is

meant my “reasonable time”. This chapter concludes the findings of the research

according to the research objective. Problems encountered during the research and

the recommendations for future researches are also stated in this chapter.

5.2 Summary of Research Findings

In summary, examination of the ten caselaws leads to the following findings

on the meaning of “reasonable time”:

- Reasonable under the existing circumstances, assuming that those circumstances,

in so far as they involve delay, are not caused or attributed to by him and

excluding circumstances which were under the control of the contractor,

Page 100: Time at Large and Reasonable Time for Completion

81

considering what in ordinary circumstances was a reasonable time for

performance and then considering to what extent the time for performance of the

contractor was in fact extended by extraordinary circumstances outside his control.

- The condition of reasonable time has been frequently interpreted; and has

invariably been held to mean that the party upon whom it is incumbent duly fulfils

his obligation, not withstanding protracted delay, so long as such delay is

attributable to causes beyond his control, and he has neither acted negligently nor

unreasonably.

- Performance is done with all due diligence having regard to all the existing

circumstances, and there is no limit as to what are existing circumstances.

- Consideration of a reasonable time for performance is likely to include taking into

account any estimate given by the performing party of how long it would take him

to perform.

- The focus of attention in considering reasonable time is likely to be upon the

allocation of resources to performance of the relevant contractual obligations.

- Effects of acts of prevention by Employer can be considered in calculating a

reasonable time for completion

- The fact that the experts had agreed what was an appropriate extension of time

together with the originally agreed period was a fair indication of what should be

regarded as a reasonable time for completion of the work, but that is in effect to

treat the originally agreed period as being a reasonable period

Page 101: Time at Large and Reasonable Time for Completion

82

5.3 Problem Encountered During Research

The main constraint is insufficiency of time as only eight weeks is available

for carrying out this research. This caused insufficient time to search and retrieve

relevant caselaws for analysis. This limitation led to less cases being found to

support the findings. With more cases, the meaning of reasonable time can be

presented more comprehensively. Initial plans were also to search for more cases

related to construction contracts but due to time limitations, this was not possible.

5.4 Conclusion

Time at large occurs when no time of completion is specified in the contract

and where the stipulated date has ceased to be applicable by reason of prevention or

breach. The contractor’s obligation is then to complete the works within a

reasonable time. The meaning of reasonable time was presented.

As Lord Ashbourne puts it in the case of Pantland Hick v. Raymond & Reid86:

What is the meaning of this expression “reasonable time”? It is

obvious that “reasonable” cannot mean a definite and fixed time. It

would not be “reasonable” if it was not sufficiently elastic to allow the

consideration of circumstances, which all reason would require to be

taken into account.

86 Supra note 70.

Page 102: Time at Large and Reasonable Time for Completion

83

Therefore, it is probably a question that can be determined by reference to all

the factual information available that can be provided by the various project

consultants involved, the contractor, its subcontractors and suppliers and statutory

undertakings. Given that the entire scope of the contractor’s works needs to be

considered, the full ambit of those factual matters is likely to be wide and the scope

of expertise, in identifying the activity durations applicable, will depend in some

measure upon usual practice and market conditions then prevailing in the place in

which the works were built. (Pickavance, 2005).

Page 103: Time at Large and Reasonable Time for Completion

REFERENCES

Andersen, C. B. (1998). Reasonable Time in Article 39(1) of the CISG – Is Article

39(1) Truly a Uniform Provision? University of Copenhagen.

http://cisgw3.law.pace.edu/cisg/biblio/andersen.html

Chappell, D., Powell-Smith, V. and Sims, J. (2005). Building Contract Claims. 4th ed.

Oxford: Blackwell Publishing.

Chow K. F. (2004). Law and Practice of Construction Contracts. 3rd ed. Singapore:

Sweet & Maxwell Asia.

Davies, M. C. (1989). Avoiding Claims: A Practical Guide for the Construction

Industry. London: E & FN Spon.

Eggleston, B. (1992). Liquidated Damages and Extension of Time in Construction

Contracts. Oxford: Blackwell Scientific Publications.

Furst, S. and Ramsey, V. (1991). Keating on Building Contracts. 5th ed. London:

Sweet & Maxwell.

Gill, W. H. (1969). Emden and Gill’s Building Contracts and Practice. 7th ed.

London: Butterworths.

Guest, A.G. and M.A. (1975). Anson’s Law of Contract (24th Edition). London:

Clarendon Press Oxford.

Lim C. F. (2004). The Malaysian PWD Form of Construction Contract. Petaling

Jaya: Sweet & Maxwell Asia.

Malaysia Contracts Act 1950, Act 136 (1984). Kuala Lumpur: Malaysian Law

Publisher Sdn Bhd.

Martin, R. (2005). 52 Construction Issues Relevant to Malaysia and Their Resolution.

Malaysia: James R Knowles Sdn Bhd.

Murdoch J. and Hughes W. (2000). Construction Contracts Law and Management.

3rd ed. London: Spon Press.

Page 104: Time at Large and Reasonable Time for Completion

84

Pickavence, K. (2005). Delay and Disruption in Construction Contracts. 3rd edition.

London: Informa Professional.

Powell-Smith, V., Stephenson, D. and Redmond, J. (1999). Civil Engineering Claims.

3rd ed. Great Britain: Blackwell Science.

Rajoo, S. (1999). The Malaysian Standard Form of Building Contract (The PAM

1998 Form). 2nd ed. Kuala Lumpur: Butterworths Asia.

Robinson, N. M. et al. (1996). Construction Law in Singapore and Malaysia. 2nd ed.

Singapore: Butterworths Asia.

Sinnadurai, V. (1987). The Law of Contract in Malaysia and Singapore: Cases and

Commentary. Singapore: The Butterworth Group of Companies.

Sinnadurai, V. (2003). Law of Contract. 3rd ed. Kuala Lumpur: Butterworths.

Vohrah, B. and Wu, M. A. (2003). The Commercial Law of Malaysia. Petaling Jaya:

Longman.

Wallace, D. (1995). Hudson’s Building and Engineering Contracts. 11th ed. London:

Sweet & Maxwell.

Page 105: Time at Large and Reasonable Time for Completion

BIBLIOGRAPHY

Ashworth, A. (2001). Contractual Procedures in the Construction Industry. 4th

edition. Harlow: Pearson Education Ltd.

Bramble, B.B. (1987). Construction Delay Claims. New York: John Wiley & Sons

Inc.

Carnell, N.J. (2005). Causation and Delay in Construction Disputes. 2nd edition.

Oxford: Blackwell Publishing.

Knowles, R. (2005). 150 Contractual Problems and Their Solutions. 2nd ed. London:

Blackwell Publishing.

Turner, D. (1989). Building Contract Dispute: Their Avoidance and Resolution.

Essex: Longman Scientific & Technical.