TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION OF BASEMENT STRENGTHENING CUM RETROFITTING WORKS IN BASEMENT COLUMN, SLAB, RCC WALLS AND WATER PROOFING WORK AT TICEL BIO PARK II BUILDING, No.5, CSIR ROAD, TARAMANI, CHENNAI - 600113. NOTICE FOR COMPETITIVE TENDER VOLUME - I PRE-QUALIFICATION, CONDITION OF CONTRACT & TECHNICAL SPECIFICATION DUE DATE FOR SUBMISSION: ON OR BEFORE: 24.07.2019 at 03.00 PM TO BE SUBMITTED: M/s.TICEL Bio Park Ltd No.5, CSIR Road, Taramani, Chennai - 600 113. Telephone No.: +91 44 22542061/62 Fax No: 91-44-2254 2055 E-Mail: [email protected] ENGINEERING CONSULTANT: M/s.TAAMAESEK ENGINEERING CONSORTIUM Architects & Engineers No 5, 1st Floor, Bishop Wallers Avenue West, Off TTK Road, Mylapore, Chennai- 600 004. Tel No: 044-24671139 / 57 Fax No: 044-24672237 E-Mail: [email protected] TENDER SUBMITTED BY: M/s._____________________________________ Address__________________________________ _________________________________________ _________________________________________ July 2019

TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL BIO PARK LTD

RETENDER FOR “PROVIDING RECTIFICATION OF BASEMENT STRENGTHENING

CUM RETROFITTING WORKS IN BASEMENT COLUMN, SLAB, RCC WALLS AND

WATER PROOFING WORK AT TICEL BIO PARK – II BUILDING”, No.5, CSIR ROAD,

TARAMANI, CHENNAI - 600113.

NOTICE FOR COMPETITIVE TENDER

VOLUME - I

PRE-QUALIFICATION, CONDITION OF CONTRACT & TECHNICAL SPECIFICATION

DUE DATE FOR SUBMISSION: ON OR BEFORE: 24.07.2019 at 03.00 PM

TO BE SUBMITTED: M/s.TICEL Bio Park Ltd

No.5, CSIR Road, Taramani,

Chennai - 600 113. Telephone No.: +91 44 22542061/62 Fax No: 91-44-2254 2055

E-Mail: [email protected]

ENGINEERING CONSULTANT: M/s.TAAMAESEK ENGINEERING CONSORTIUM Architects & Engineers No 5, 1st Floor,

Bishop Wallers Avenue West, Off TTK Road, Mylapore, Chennai- 600 004.

Tel No: 044-24671139 / 57 Fax No: 044-24672237 E-Mail: [email protected]

TENDER SUBMITTED BY: M/s._____________________________________

Address__________________________________

_________________________________________

_________________________________________

July 2019

Page 2: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 1

TICEL BIO PARK LTD

RETENDER FOR PROVIDING RECTIFICATION OF BASEMENT STRENGTHENING

CUM RETROFITTING WORKS IN BASEMENT COLUMN, SLAB, RCC WALLS AND

WATER PROOFING WORK OF TICEL BIO PARK – II BUILDING AT No.5, CSIR

ROAD, TARAMANI, CHENNAI – 600113.

CONTENTS

S.No DESCRIPTION Pages

Notice for Competitive Tender 2

Information and Instructions to the Tenderer 3 - 4

1 General Information 5 – 8

2 Brief Description of Work 8

3 Important Conditions of Contracts 8

4 Eligible TENDERER for applying. 8-9

5 Pre - Qualification Criteria for Eligibility. 9-10

6 Site Visit 10

7 Submission of TENDER documents 10-11

8 Final Decision Making Authority 11

9 Submission of Tender 11

10 Evaluation Method 12

II. Qualification Information

1 Appendix – A : Letter of Transmittal 13 – 15

2 Format – A : Structure and Organization of Tenderer 16 – 18

3 Format – B : Key Personnel to be deployed for the project 19 – 20

4 Format – C : Financial Information 21

5 Format – D : Details of Completed works 22-23

6 Format – E : Details of Ongoing works 24-25

7 Format – F : Tools & Major Equipment 26

8 Format – G : Details of Termination of contract by previous client in the pas, if any

27

9 Format – H : Details for considered make of Raw materials 28

10 Format - 1 to 5 and Pre-qualification requirement 29-34

11 Withdrawal of conditions letter 35

12 Declaration Cum Undertaking 36

13 Annexure – 1 – Work Execution Schedule 37

14 General Conditions of Contract 38-52

15 Important Conditions of Contract 53-64

16 Concrete works specification 64-87

17 Hand Book on Health & Safety at work for contractors working in the project

88 - 121

Page 3: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 2

TICEL BIO PARK LTD

NOTICE FOR COMPETITIVE TENDER

RETENDER FOR PROVIDING RECTIFICATION OF BASEMENT STRENGTHENING

CUM RETROFITTING WORKS IN BASEMENT COLUMN, SLAB, RCC WALLS AND

WATER PROOFING WORK AT TICEL BIO PARK-II BUILDING, NO.5, CSIR ROAD,

TARAMANI, CHENNAI - 600113.

TICEL BIO PARK Ltd., Chennai is a company promoted by Tamilnadu Industrial

Development Corporation Limited (TIDCO) along with TIDEL Park Limited, Chennai.

TICEL Bio Park Ltd., constructed a state-of-the-art Bio Technology Park - II, in the TICEL

BIO Park Campus at No. 5, CSIR Road, Taramani, Chennai 600 113, invites TENDER for

Providing Rectification of Basement, Strengthening Cum Retrofitting Works in Basement

Column, Slab, RCC Walls, and Water Proofing Work of TICEL Bio Park – II Building.

TICEL invites TENDER from experienced contractors.

Page 4: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 3

Information and Instructions to the Tenderer

PRE–QUALIFICATION CRITERIA

TICEL BIO PARK LTD. Invites TENDER for Providing Rectification of Basement,

Strengthening Cum Retrofitting Works in Basement Column, Slab, RCC Walls, and Water Proofing Work from experienced and eligible contractors, who meet the following qualifying criteria;

(a) Experience of the Contractor

The TENDERER should be a well-established contractor, having experience of minimum 5 years in the field of concrete strengthening and retrofitting works. (Modification / Repairing / Correction on the existing structures with new

additional components etc). Copy of the LOA or Agreement and work completion certificate or handing over certificate has to be enclosed by the contractor. (Format – 1)

(b) Experience in Retrofitting Works

The TENDERER should have satisfactorily completed the works like

Strengthening the RCC column, slab & wall by retrofitting method in any Multi-storied Building / Industrial Building / IT Building / Hotel / institutional building (Format – 2)

Experience of having successfully completed similar (concrete strengthening and retrofitting) works during the last 5 years ending last day of month previous to the

one in which application are invited should be either of the following:

(i) One similar (concrete strengthening and retrofitting) completed works each costing not less than Rs.115 Lakhs.

OR (ii) Two similar (concrete strengthening and retrofitting) completed works

each costing not less than Rs.75 Lakhs.

OR (iii) Three similar (concrete strengthening and retrofitting) completed works

each costing not less than Rs.55 Lakhs

The TENDERER should submit LOA or Agreement and work completion certificate or handing over certificate for the above works as part of the technical

bid.

(c) Experience in Basement Water Proofing Works

The TENDERER should have satisfactorily completed the Waterproofing works minimum in one basement of any Multi-storied Building / Industrial Building / IT Building / Hotel / institutional building during the last 5 years ending last day of

month previous to the one in which application are invited. The TENDERER shall submit LOA or Agreement and work completion certificate or handing over certificate for the above works as part technical bid. (Format – 3)

Page 5: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 4

(d) Annual Turnover

Average annual financial turnover during the last 3 years, ending 31st March of the previous financial years, should be a minimum of Rs.50 Lakhs (Format – 4)

(e) Bank Solvency Certificate

The Tenderer should produce Banker’s Solvency Certificate for a value of Rs. 60 Lakhs obtained not earlier than three months from the last date of submission of tender, the certificate to be enclosed along with PQ documents. (Format – 5)

To satisfy the Pre-Qualification criteria, Tenderer has to submit Audited Balance Sheet (duly signed by practicing CA), LOA or Agreement and work completion certificate or handing over certificate as per the prescribed format enclosed Format – 1 to 5.

Page 6: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 5

1. General Information

Name of Work

Re-Tender for Providing Rectification of Basement, Strengthening Cum Retrofitting Works in basement Column,

Slab, RCC walls and Water Proofing Work at TICEL Bio Park- II, Building at No. 5, CSIR Road, Taramani, Chennai–600113.

TENDER Documents Cost

TENDER Documents can be purchased by payment of

Rs.16,800/- (Rupees Sixteen Thousand Eight Hundred only) by DD in favour of “TICEL Bio Park Limited” payable at Chennai(during office hours.)

Earnest Money Deposit

Rs.1.4 Lakhs (Rupees One Lakhs Forty Thousand only) to be paid by Demand Draft from any Nationalised Bank in favour of “TICEL Bio Park Limited, payable at Chennai.

Taxes The quoted value should be inclusive of GST (The work value and GST value should be shown separately)

Issue of Tender 04.07.2019 to 23.07.2019. During office hours

Time and date of

Pre Bid Meeting 12.07.2019 at 03.00PM at TICEL Bio Park Ltd, Office.

Last Date for Submission

24.07.2019 at 03.00 PM at TICEL Bio Park, No.5, CSIR Road, Taramani, Chennai - 600 113.

Opening of

Technical Bids

24.07.2019 at 03.30 PM in the Office of TICEL Bio Park Ltd.,

No.5, CSIR Road, Taramani, Chennai 600 113.

Tender Validity Period

90 (Ninety) days from the last date of submission of Tender.

Period for work completion

90 (Ninety) days from the date of issue of LOA.

Defect Liability

Period

One year period after 100% completion and handing over of the entire works as certified by the Engineering Consultant (EC). Retention Money 5% (Five Percent Only) of contract value. 100% of retention

money shall be released upon completion & handing over of all the works as certificate by EC

Warranty Period 5 (FIVE) Years, Including Defect Liability Period (DLP)

Performance Bank Guarantee

10% of the work order value (inclusive of GST) from any

Nationalized Bank to be given within 10 days from the date of issue of LOA and should be valid for a period of 5 years and three months.

TENDER Inviting Authority

The Managing Director, TICEL Bio Park Limited, No. 5, CSIR Road, Taramani, Chennai 600 113.

TENDER Document can be downloaded from the website viz. www.ticelbiopark.com and downloaded document should be submitted with DD for Rs.16,800/- (Rupees Sixteen

Thousand Eight Hundred only) along with the Bid submission or Tender Documents can be purchased from the Office of TICEL by payment of Rs.16,800/- by DD. The DD should be drawn in favour of “TICEL Bio Park Limited”, payable at Chennai.

Page 7: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 6

TICEL Bio Park Ltd. reserves the right to accept / reject anyone / all the TENDERs without assigning any reasons thereof.

1.01 TICEL BIO PARK Ltd., is a company promoted by Tamilnadu Industrial

Development Corporation Limited (TIDCO) along with TIDEL Park Limited, Chennai.

TICEL Bio Park Ltd., constructed a state-of-the-art Bio Park-I & II, in the TICEL BIO Park Campus at No. 5, CSIR road, Taramani, Chennai 600 113,TICEL invites TENDER for “Providing Rectification of Basement Strengthening Cum Retrofitting

Works in basement Column, Slab and RCC Walls and Water Proofing Work” at TICEL Bio Park –II Building.

1.02 DEFINITIONS

i. TENDER: Shall mean the set of TENDER Documents submitted by a

TENDERER. ii. TENDER DOCUMENT: shall mean set of documents consisting of Techno

Commercial TENDER with Drawings. iii. CLIENT: TICEL BIO PARK LTD will also be referred as Employer/ Owner.

iv. TENDERER: Shall mean firm or Company who has purchased the TENDER

documents to submit for Techno Commercial TENDER to execute the said

works. v. WORKS: Shall mean “Providing Rectification of Basement Strengthening Cum

Retrofitting Works in basement Column, Slab, RCC Walls and Water Proofing Work” at TICEL Bio Park –II Building. The works includes Defects Liability Period (DLP) of one year, after 100% successful completion / handing over of the entire

works as certified by Engineering Consultant (EC) and the warranty period of 5 (five) years including DLP.

vi. CONTRACT: Shall mean the Contract entered into between TICEL BIO PARK LTD. and the successful TENDERER on award of Contract for the works.

vii. ENGINEERING CONSULTANTS: Shall mean M/s. Taamaesek Engineering Consortium, No 5, 1st Floor, Bishop Wallers Avenue West, Off TTK Salai, Mylapore, Chennai-600 004 who is a Consultant engaged by TICEL BIO PARK

LTD., 1.03 TENDERS are invited by TICEL BIO PARK Ltd, Chennai from reputed, well

established and experienced Contractors from India for this works for TICEL Bio Park- II Building,No.5, CSIR road, Taramani, Chennai 600 113,.The notice inviting TENDER is published in leading newspapers and also available in websites:

www.ticelbiopark.com 1.04 TENDER Document can be obtained from the office of the TICEL BIO PARK Ltd,

No.5, CSIR Road, Taramani, Chennai 600 113 from 04.07.2019 to 23.07.2019 upon payment of non-refundable amount of Rs.16,800/- (Rupees Sixteen Thousand Eight Hundred only) towards the cost of one set of TENDER

documents in the form of Demand Draft in favour of “TICEL BIO PARK Ltd” payable at Chennai. TENDER documents can also be downloaded from the above

Page 8: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 7

Websites. However, drawings have to be purchased from TICEL Bio Park Ltd., Office, Chennai on payment of Rs.16,800/- in the form DD drawn in any

Nationalised bank, in favour of “TICEL BIO PARK Ltd” payable at Chennai, towards the cost of TENDER document.

1.05 TENDER Document can be downloaded from the website viz. www.ticelbiopark.com and downloaded document should be submitted with DD for Rs.16,800/- (Rupees Sixteen Thousand Eight Hundred only) along with the Bid submission or Tender

Documents can be purchased from the Office of TICEL by payment of Rs.16,800/- by DD. The DD should be drawn in favour of “TICEL Bio Park Limited”, payable at Chennai Purchased Tender documents are not transferable and will be accepted only

from the parties who have purchased the documents from TICEL BIO PARK Ltd. The TENDER documents purchased / downloaded from the website should be submitted along with TENDER Drawings. The TENDER document submissions

without duly signed drawings are considered as invalid submission.

1.06 The TENDER should be submitted in English only. Supporting documents such as

Annual Reports, Balance sheets, Client’s certifications, Testimonials etc., if attached in any other language other than English shall be accompanied by its true English translation duly signed for its correctness,

1.07 The TENDER Document shall be submitted in triplicate (Volume1, Volume – II

(BOQ)) in typewritten/handwritten form. The TENDERER’S signature and seal of the

Firm / Company shall appear on each page of the TENDER document. In volume -2, the unit rate should be written both in words and figures. In case of any discrepancy between words and figures, the rates written in words shall be taken as final for

further evaluation purposes. 1.08 TENDERER should avoid, as far as possible, corrections, overwriting, erasures or

postscripts in the bid documents. In case, however, any corrections, alterations, changes, erasures, amendments and / or additions have to be made in the tender, they should be supported by dated signatures of the same authorized person signing

the Tender documents.. All pages of the TENDER document shall be numbered, signed and submitted in a single cover along with a signed letter of transmittal.

1.09 TENDER Document details and enclosures shall be submitted in sealed envelopes and addressed to TICEL BIO PARK Ltd. No.5, CSIR road, Taramani, Chennai 600 113. Submission of the TENDER documents beyond the stipulated date and time

will be summarily rejected. All times and dates mentioned in this TENDER Notice and application are in Indian Standard Time (IST). Indian Standard Time only will be followed for communication and other purposes.

1.10 TENDERS made by telegram, fax, e-mail and those received beyond the stipulated

date and time in post / speed post / courier etc., will be summarily rejected.

1.11 Documents submitted in connection with the TENDER will be treated as Confidential

and will not be returned.

1.12 The cost incurred by TENDERERS in preparing their TENDER, in collecting

information, in providing clarifications or attending discussions, conferences or in

making presentations, site visit etc is the scope of Tenderer.

Page 9: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 8

1.13 At any time prior to the last date of submission of Tender, TICEL may, for any reason, whether on its own or in response to the clarification request by a

prospective Tenderer, modify the Tender document. All prospective Tenderers who have purchased the Tender document will be notified of the amendment in writing, and such amendments/ modifications will be binding on them. All amendments will

also be uploaded at Company’s Website (www.ticelbiopark.com) 1.14 TICEL BIO PARK Ltd reserves the right to reject any or all TENDERS or reduce the

scope without assigning any reasons whatsoever and without incurring any liability to whomsoever.

2.00 BRIEF DESCRIPTION OF PROJECT 2.01 Project:-TICEL Bio Park Ltd had constructed the Bio Park- II consists of 3

basements for vehicle parking, ground floor for common amenities and 12 upper floors. The typical floors are designed with different size modules of labs Utility corridor had been created within the floor as mezzanine floor. TICEL invites

TENDER for “Providing Rectification of Basement Strengthening Cum Retrofitting Works in Basement Column, Slab, RCC Walls and Water Proofing Work" at TICEL BIO PARK – II BUILDING.

3.0 0 IMPORTANT CONDITIONS OF CONTRACT

3.00 The Contract shall be item rate contract with unit rates to be quoted in Rupees. 3.01 Condition of Contract will be as per standard practice and duly modified for local

conditions. Performance Bank Guarantee, Retention Money, Defect Liability Period, liquidated damages, default and arbitration clause will be followed as per the conditions of contract. The contractor shall be responsible for procurement of all

quality materials required for the performance of the contract. 3.02 Since the project is to be implemented strictly on the time schedule, TICEL BIO

PARK Ltd. will lay high emphasis on the capacity of the selected contractor to deploy high tech and speedy construction techniques, high degree of planning, good procurement and quality check procedures, quality assurance Plan,

Environment and Safety Plan to meet the appropriate standards, execution, and co-ordination, ability to prepare Program Evaluation Review Technique (PERT)Chart network and adherence to it.

4.0 ELIGIBLE TENDERERS

4.01 The person signing the TENDER document should be the duly authorised representative of the firm / company, for which a certificate of authority should be submitted. The Power of Attorney /authority to authorized signatory must be

enclosed in detail.

4.02 The price tenders will be opened for those who qualify the eligibility criteria as

mentioned in the clause No 5 as below: 4.03 Any change in the legal status of a TENDERER subsequent to submission of

TENDER will be subject to approval of TICEL BIO PARK LTD with respect to Tender Documents

Page 10: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 9

4.04 TENDERERS under Joint Venture/ Consortium arrangement are not permitted.

Therefore, the TENDER shall be evaluated based only on the technical and financial strength of the applicant of their individual capacities and capabilities.

5.0 Pre-Qualification Criteria for Eligibility

5.01 The Tenderer should fulfill the following pre-qualification criteria documents for Rectification of basement strengthening cum retrofitting works in Basement column,

slab, RCC walls and water proofing works in RCC wall, other respective areas within the BOQ quoted rates.

(a) Experience of the Contractor The Tenderer should be a well-established contractor, having experience of minimum 5 years in the field of concrete strengthening and retrofitting works (Modification /

Repairing / Correction on the existing structures with new additional components etc.).Copy of the LOA or Agreement and work completion certificate has to be enclosed by the contractor.(Format – 1)

(b) Experience in Retrofitting Works

The TENDERER should have satisfactorily completed the works like Strengthening the RCC column, slab & wall by retrofitting method in any Multi-storied Building / Industrial Building / IT Building / Hotel / institutional building.

(Format – 2)

Experience of having successfully completed (Concrete strengthening and

retrofitting) works during last 5 years ending last day of month previous to the one in which application are invited should be either of the following:

(i) One similar (concrete strengthening and retrofitting) completed works

each costing not less than Rs.115 Lakhs OR

(ii) Two similar (concrete strengthening and retrofitting) completed works

each costing not less than Rs.75 Lakhs. OR

(iii) Three similar (concrete strengthening and retrofitting) completed works

each costing not less than Rs.55 Lakhs.

The TENDERER should submit LOA or Agreement and work completion certificate

or handing over certificate for the above works as part of the technical bid.

(c) Experience in Basement Water Proofing Works

The TENDERER should have satisfactorily completed the Waterproofing works

minimum in one basement of any Multi-storied Building / Industrial Building / IT Building / Hotel / institutional building during the last 5 years ending last day of month previous to the one in which application are invited. The TENDERER shall submit

Work order / LOA and Completion certificate / Handing over certificate for the above works as part technical bid. (Format – 3)

(d) Annual Turnover Average annual financial turnover during the last 3 years, ending 31st March of the previous financial year, should be minimum of Rs. 50 Lakhs (Format – 4)

Page 11: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 10

(e) Bank Solvency Certificate

The contractor produces Banker’s Solvency Certificate for a value of Rs. 60 Lakhs obtained not earlier than three months from the last date of submission of tender, the certificate to be enclosed along with PQ documents.(Format-5)

To satisfy the Pre-Qualification criteria, Tenderer has to submit Audited Balance Sheet (duly signed by practicing CA), LOA or Agreement and work completion certificate or

handing over certificate as per the prescribed format enclosed Format – 1 to 5.

6.0 SITE VISIT

The site may be inspected by the TENDERER or his representative at his own cost,

with prior intimation to TICEL BIO PARK Ltd for proper assessment of the prospective assignment before submission of TENDER. The TENDERER should refer to the Site Plan and Location Map enclosed with the drawing.

7.0 SUBMISSION OF TENDER DOCUMENTS

7.01 To be eligible for Qualification, TENDERERS shall provide evidence to suitability of

their meeting the Criteria indicated in Clause – 5.0 above and furnish details giving their full bio-data, organization, technical experience, plant and equipment’s etc. to establish their capacity and competence, and possession of adequate resources to

carry out the contracts effectively and for this, the TENDERS submitted shall include the following: (*)

a) Letter of transmittal; as in Appendix - A

b) Copies of original documents defining the legal status of the TENDERER, its

structure and organization, place of registration and principal place of business of the TENDERER in Format – A. The qualification and experience of key personnel proposed for the administration and execution of the contract, both

on and off site in the format prescribed in Format - B.

c) Details of Financial Information in Format – C

d) Details of completed works of similar nature in Format – D. Certificates in

support of suitability, technical know-how and capability for having successfully

completed the works during the last five years

e) Details of on-going works of similar nature in Format - E

f) Details of Tools & equipment in Format – F

g) Details of termination of contract by previous client, if any, in Format – G h) A detailed description on the approach methodology to the construction

technology proposed, schedule and type of equipment to be used, names and responsibilities and detailed qualifications of the proposed subcontractors, if any etc.

i) A detailed description of any method of approach specially devised by the

contractor to speed up the work.

Page 12: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 11

j) Details of cases of having been barred or blacklisted from the Tendering process, if any. Black-listed Agencies’ TENDER is liable to be rejected.

k) All governing laws and jurisdiction shall be as per laws in the State of Tamil

Nadu and Laws of India and only courts in Chennai shall have jurisdiction over

all matters arising out of or relating to this project.

Any deviation from the above said submittal procedures, shall disqualify the

TENDERER.

8.0 FINAL DECISION MAKING AUTHORITY

8.01 TICEL BIO PARK Ltd reserves the right to accept or reject any TENDER or to

reduce the scope, cancel the exercise without having to incur any cost or to assign

any reason for its decision to any party whatsoever. TICEL BIO PARK LTD., decision on prequalifying Tenderers will be final and binding on all the Tenderers.

9.0 SUBMISSION OF TENDER

Sealed TENDERs should be addressed to The Managing Director, M/s. TICEL Bio Park Ltd., No.5, CSIR Road, Taramani, Chennai 600 113, and super scribing the

name of the TENDER on the top left hand corner of the cover and the name of the TENDERER on the bottom left hand corner of the cover and sent so as to reach the TICEL Office not later than 24.07.2019, 3pm.

The TENDER shall be two cover system / Two-part TENDER system,

Cover – I Should Consist Volume 1 Technical TENDER - the Pre-qualification criteria,

conditions of contract and Technical Qualification along with EMD and Tender document fee if downloaded from the Website. Technical Tender should be submitted in Triplicate. (one original and two copies in duplicate).

Cover - II Should consist Volume 2 Price TENDER - Bill of Quantities with respective rates.

Price TENDER should be submitted in original.

All TENDER drawings obtained from TICEL should be duly signed in original and

affixed with the seal of the TENDERER along with the submission of the TENDER Documents.

TENDER, which is not accompanied by the required EMD and document fee (in case tender document downloaded from the website) should be submitted in separate sealed envelopes duly super scribed on the covers of the Envelope

viz. “Document Fee and EMD” along with Part 1. The Tenders received without EMD and Document fee, will be summarily rejected.

Page 13: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 12

10.00 Evaluation Method: The method of evaluation will consist of three stages.

First Stage: In this stage,

(a) The Part – 1 containing the EMD will be opened. If EMD is not submitted or is deficient, TICEL Bio Park Ltd., will reject the TENDER submission.

(b) If the document is downloaded from the websites and if DD for Rs.16,800/- is not

enclosed towards the cost of the TENDER document while submitting the

TENDER, TICEL Bio Park Ltd will reject the Tender.

(c) In both cases no further evaluation will be done.

Second Stage: Evaluation will be done on the Technical TENDER to assess whether substantive response has come from the TENDERERS to the basic

prequalification criteria along with the documentary evidence as called for. Any clarifications on the submitted TENDER document required for evaluation purpose will be sought from the Tenderer.

Third Stage: In the Third and final stage, the PRICE TENDER of those TENDERERS who satisfies the eligibility criteria will be opened.

The TENDERER who has complied with the TENDER conditions in full and quoted

the Lowest Rate will be choosen as Lowest TENDERER (L1) for the award of work.

TICEL Bio ark Limited reserves the right to call for clarifications and negotiations

with the Lowest TENDERER before awarding the work. TICEL BIO PARK LTD

reserves the rights to negotiate with next eligible TENDERER (next lowest quoted

Tenderer – L2) in case the price quoted by the lowest TENDERER (L1) is found to

be unreasonable or the details submitted by the L1 TENDERER are not satisfactory

to the owner. TICEL reserves the right to reject the L1 Tenderer without assigning

any reason thereof.

Page 14: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 13

APPENDIX – A

LETTER OF TRANSMITTAL Date:

To The Managing Director TICEL BIO PARK Ltd

No.5, CSIR road, Taramani, Chennai - 600 113.

Sir, Sub: Submission of TENDER for Providing Rectification of Basement,

Strengthening cum Retrofitting Works in Basement Column, Slab, RCC Walls and Waterproofing Work at TICEL BIO PARK–II Building.

1. I / We ………………………………………..having examined the details given in the Invitation to TENDERERS, we hereby submit the following information and relevant documents.

a) I/We hereby certify that all the statements, information and data provided in the

enclosed formats A to H and 1 to 5 and accompanying statements are true and

correct to the best of my / our knowledge.

b) I/We .…………………………. have read the instructions appended with the

Prequalification document and I/We understand that any contract made between ourselves and TICEL BIO PARK Ltd., on the basis of the information given by me / us is liable to be cancelled if any false information is detected at a later date.

c) I/We ……………………………..have also no objection if enquiries are made on all the

projects and works listed by me / us in the accompanying sheets or any other enquiry

on the information furnished herewith in the accompanying sheets.

d) I/We have furnished all information and details as asked for and have no further

pertinent information to provide.

e) I/We hereby submit the requisite certified solvency certificate and authorize TICEL

BIO PARK Ltd to approach the Bank issuing the solvency certificate to verify the correctness thereof. I/We also authorize TICEL BIO PARK Ltd to approach individuals, employers, companies, and corporation to verify my / our competency and

general reputation.

f) I/We hereby submit in Format – D the certificates in support of my / our suitability,

technical know-how and capability for having successfully completed the works during the last five years.

g) I/We hereby also agree that the decision of the TICEL BIO PARK Ltd in the Qualification and selection of Contractors will be final and binding upon me / us.

Page 15: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 14

h) I/We hereby agree TICEL BIO PARK Ltd reserves the right to qualify any contractor or to cancel the exercise without assigning any reason for doing so or to incur any

liability to any party whatsoever. i) I/We hereby agree not to withdraw from the contract after issue of LOA and before

signing the agreement. Incase if we withdraw before signing the agreement, we hereby agree for the forfeiture of the Earnest Money Deposit as per the tender condition

j) I/We have gone through the drawings provided to us along with the Tender document

and has considered the details in the drawings while arriving at the quoted rates.

(k) I/We hereby agree to produce performance Bank Guarantee within Ten (10) days and

execute agreement within fifteen (15) days from the date of LOA

(l) The following documents duly signed by the authorized signatory and sealed are

enclosed as enclosures to the letter of transmittal

1. Certificate of Incorporation from Registrar of Companies, if applicable.

2. Memorandum of Association, if applicable.

3. Annual Report / Audited Balance Sheet & Profit and Loss Statement for the past 5

years

4. Registration with Govt. Departments or Public Bodies.

5. Support Certificate from Bankers for Credit facilities available.

6. Copies of Acknowledgements issued by IT Department for the firms having filed Income Tax for the past five years as on 31st March 2019.

7. GST Registration certificate.

8. Testimonials from Clients / Consultants for completion of works included in Format

–D

9. LOA or Agreement and work completion certificate or handing over certificate

10. LOA / Work Order issued by the Clients for ongoing works included in Format –E

11. Organization Chart of Company showing the Officer in-Charge who will have direct link with and control of site organization and the experience of the official who will be in charge for the Implementation of the Tendered project and the detailed

profile of the team members who are going to involve in the said work. 12. Method Statement: Programming & Planning and Progress monitoring plan,

weekly and monthly; Management of direct subcontractors from selection through execution of work; Coordination with Specialist contractors like Electrical, Air conditioning, lifts etc., Quality control & quality Assurance at site; Safety Plan;

Page 16: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 15

13. Formats - ‘A’ to ‘H’ and 1 -5 with complete details and any certificates other than that listed above.

I / we hereby agree to as a TENDERER to all the terms and conditions of the Tender

Date of Submission Signature of TENDERER with

Official Seal

Page 17: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 16

FORMAT – A

STRUCTURE AND ORGANISATION OF TENDERER

S.No. Details required To be filled by the TENDERER

1 Name of the TENDERER's Company

2 Nationality of TENDERER

3 Establishment of the Company

i) Year

ii) Location

4. The TENDERER is a company (Please enclose attested copy of registration / incorporation under

appropriate laws of the TENDERER’s country)

Yes / No

Enclosed/ Not enclosed

5 Address of the TENDERER :

i) Registered Office Address

Telephone Number

Fax Number

E-mail Address

Web site

ii) Local office address:

Telephone Number

Fax Number

E-mail Address

iii) Office address through which this work will be handled and name of officer in-charge.

Telephone Number

Fax Number

E-mail Address

6 If the TENDERER is a Multinational

Company, please furnish the following :

a)

Whether the foreign company has an office in India? If so, give the following details :

Year of Establishment

Location :

Name of the Contact Person :

Telephone Nos. :

Fax No.:

Email :

Page 18: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 17

S.No. Details required To be filled by the TENDERER

b)

Please mention the nature of Indian office. If so, please provide the details whether marketing, liaison, capable of

undertaking complete project in India etc.

c) Whether company has executed / currently executing / TENDER for any project in India?

If so, please furnish the following details :

Name of the Client :

Name of the Project :

Location of the Project :

Nature of Project :

Nature of Contract :

Project Duration :

Project value :

d) The TENDERER has to furnish a detailed note on how it will handle the

project in India, if successful TENDERER, in terms of (i) Finance, (ii) Manpower, (iii)Tools & equipment,

(iv) Use of local agencies and labour, (v) Project control and management plan

7 Details of the Board of Directors

i) Name of the Director

ii) Qualification

iii) Organization

iv) Office address

v) Telephone Number

vi) Fax Number

vii) E-mail Address

8 Enclose Company's Organisation Chart showing the structure of the organisation including the names of

the Directors / Chief Executive Officer and position of Officers.

Enclosed / Not Enclosed

9 Number of years of experience and other Details.

Page 19: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 18

S.No. Details required To be filled by the TENDERER

10

Area of business activities other than construction works, if any. (If yes please furnish specific

information).

Yes / No

11

Whether registered with any

Government / Public Sector Undertaking / Local bodies like CPWD / MES / PWD or equivalent applicable

in the TENDERER's country. If yes, please furnish details class and type of Registration.

Yes / No.

1.

2.

3.

12

Please give at least three references

of Clients (Engineers, Engineering

Consultants or top Officials of

Organization) for whom you may have

executed construction works of

importance and similar nature from

whom TICEL BIO PARK LTD., can

verify

1) Name :

Designation : Company :

2) Name : Designation : Company :

3) Name : Designation : Company :

13

Any special information, which you may like to provide.

Place :

Signature of the TENDERER

Common seal of the Company

Date : Office Address

Page 20: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 19

FORMAT-B

KEY PERSONNEL TO BE DEPLOYED FOR THE PROJECT

S.No. Details required To be filled by TENDERER

A Managerial Level - General

1 Individual’s Name

2 Age

3 Qualification

4 Present position

5 Professional experience in the similar nature of works.

6 Years with the TENDERER

B Managerial Level - Technical

1 Individual’s Name

2 Age

3 Qualification

4 Present position

5 Professional experience in the similar nature of works.

6 Years with the TENDERER

C Managerial Level - Administration & Finance

1 Individual’s Name

2 Age

3 Qualification

4 Present position

5 Professional experience in the similar nature of

works.

6 Years with the TENDERER

D Managerial Level - Quality Control and Quality Assurance

1 Individual’s Name

2 Age

3 Qualification

4 Present position

5 Professional experience in the similar nature of

works.

6 Years with the TENDERER

E Managerial Level - Safety Officer & Industrial Relation Officer

1 Individual’s Name

Page 21: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 20

S.No. Details required To be filled by TENDERER

2 Age

3 Qualification

4 Present position

5 Professional experience in the similar nature of works.

6 Years with the TENDERER

F Managerial Level – Planning

1 Individual’s Name

2 Age

3 Qualification

4 Present position

5 Professional experience in the similar nature of works.

6 Years with the TENDERER

Place :

Signature of the TENDERER

Date :

Common seal of the Company

Page 22: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 21

FORMAT–C FINANCIAL INFORMATION

S.No Description Details to be filled in by

TENDERER

A Annual Turnover in the last three

financial years Only for

1 Year : 01st April 2016 - 31st March 2017

2 Year : 01st April 2017 – 31st March 2018

3 Year : 01st April 2018 – 31st March 2019

B Financial Information

I Year : 01st April 2016 - 31st March 2017

a. Total assets

b. Current assets

c. Total Liabilities

d. Current Liabilities

e. Profits before taxes

f. Profits after taxes

g. Net worth

h. Working Capital

II Year : 01st April 2017 – 31st March 2018

a. Total assets

b. Current assets

c.Total Liabilities

d. Current Liabilities

e. Profits before taxes

f. Profits after taxes

g. Net worth

h. Working Capital

III Year : 01st April 2018 – 31st March 2019

a. Total assets

b. Currents assets

c. Total Liabilities

d. Current Liabilities

e. Profits before taxes

f. Profits after taxes

g. Net worth

h. Working Capital

Place :

Signature of the TENDERER

Page 23: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 22

FORMAT-D

DETAILS OF COMPLETED WORKS

S.No. Details required To be filled by the TENDERER

1 Name of work

2 Country and location

3 Client’s name and address

Name:

Address :

4 Consultants name and address.

Name:

Address :

5 Total Tendered cost of work Agreement No.

Date

INR …………….. Agreement No:

Date :

6 Total actual cost of work after completion.

INR ……………..

7 Excess / less in percentage. ……………..%

8 Explain if Excess / less is higher by 20%

of the Tendered cost of work.

9 Date of commencement

10 Period of completion

11 Stipulated date of completion

12 Actual date of completion

13 Extended by the contractor, if any. Reason for non-completion of work in stipulated time limit / extended time limit,

if so furnish details

Yes / No

14 Extension of time granted by the Client, if any. If yes, please specify the reason for

extension of time.

Yes / No

15 Brief description of works including

principal features and quantities of main items of the work.

16 Name of Contractor’s Engineer in-charge

of the Project &Qualifications.

Name :

Qualification :

17 Details of specialized work executed under this Contract.

Page 24: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 23

S.No. Details required To be filled by the TENDERER

18 Details of specialized work executed by

their own divisions under the Contract

19 Whether the Programming and planning was followed in the form of PERT Chart

or BAR Chart?

Yes / No

20 Whether the Quality Control and Quality Assurance function was carried out? If yes, Please give details and copies of

quality formats used in anyone project

Yes / No

21 Whether the safety measures were

followed? If yes, Please give details.

Yes / No

Date:

Signature of TENDERER

Place: Official Seal

Page 25: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 24

FORMAT–E

DETAILS OF ON-GOING WORKS

S.No. Details required To Be filled by the TENDERER

1 Name of work

2 Country and location

3 Client's name and address

Name:

Address :

4 Consultants name and address.

Name:

Address :

5 Total Tendered cost of work (Agreement

No. and Date) INR ………………….

6 Brief description of works including

principal features and quantities of main items of the work.

7 i) Percentage of physical completion

ii) Amount billed for the work completed.

iii) Cost of work remaining to be executed

as on the date of submission.

iv) Stipulated date of completion

v) Anticipated date of completion

8 Name of Contractor’s Engineer in-charge of the Project &Qualifications.

Name: Qualification :

9 Details of specialised works under this Contract

10 Specialised works being executed by their own divisions

11.a. Details of the sub-contracted specialised works by the TENDERER

i) Total value of work sub-contracted. INR ………………..

ii) Trade-wise value of work sub-

contracted.

1.INR ……….....…….. 2.INR ……….....……..

3.INR ……….....……..

4. INR ………..………..

Page 26: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 25

S.No. Details required To Be filled by the TENDERER

iii) Trade-wise Name of sub-contractors

Use separate sheet for details of such sub-contractors experience, capability, testimonial.

1.

2. 3.

4.

15

i) Were there any labour strikes?

If yes, Please give details.

Yes / No

ii) Whether corrective action taken

immediately? Yes / No

16

Were there any penalties / fines / stop

notice / compensation / liquidated damages imposed?

If Yes, Please give amount, details and reason.

Yes / No Amount :

Reason :

17 Please specify the details of litigation / arbitration cases, if any, pertaining to

works ongoing.

Yes / No

18 Attach client's certificate, as may be available (Not below the rank of Director

or equivalent)

Yes / No

Place :

Signature of the TENDERER

Date :

Common seal of the Company

Page 27: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 26

FORMAT– F

TOOLS & MAJOR EQUIPMENTS

S. No.

Item of Equip-

ment

Qty

Equipment Information

Name of Manufacture

r

Make & Model Capacit

y

Year of Manufactu

re

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

Place :

Date :

Page 28: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 27

FORMAT-G

DETAILS OF TERMINATION OF CONTRACT BY PREVIOUS CLIENT IN THE PAST, IF ANY

S.No. Particulars To Be filled by the TENDERER

1 Name of works

2 Name of the Client

3 Value of Contract in INR

4 Period of Contract

5 Terminated at what stage

6 Reasons / grounds for termination

7 Approx. value of work completed at the time of termination in INR

8 Approx. value of balance work not completed in INR

9 Remarks

Place :

Signature of the TENDERER

Date :

Common seal of the Company

Page 29: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 28

FORMAT-H

DETAILS FOR CONSIDERED MAKE OF RAW MATERIALS TO BE FILLED BY VENDOR

S.No. ITEM MAKE ORIGIN SUPPLIED

FROM

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

NOTE: All Equipment / Components used in execution of work shall be preferred

make listed above subject to the approval of Owner / Engineering Consultant. The rates quoted above shall be valid for any of the makes mentioned above.

Place : Signature of the TENDERER

Page 30: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 29

FORMAT - 1

PRE-QUALIFICATION CRITERIA

DETAILS REQUIRED TO SATISFY THE ELIGIBILITY CLAUSE 5.01 a.

(a) Experience of the Contractor

The TENDERER should be a well-established contractor, having experience of

minimum 5 years in the field of concrete strengthening and retrofitting works.

(Modification / Repairing / Correction on the existing structures with new additional

components etc). Copy of the LOA or Agreement and work completion certificate or

handing over certificate has to be enclosed by the contractor.

S.No. Year Project Details

1 01.04.2014

to 31.03.2015

2 01.04.2015

to 31.03.2016

3 01.04.2016

to 31.03.2017

4 01.04.2017

to 31.03.2018

5 01.04.2018

to 31.03.2019

The following Documentary evidences required to establish the above P.Q. Criteria

Copy of Client’s Work Completion Certificate or Agreement or handing over certificate or LOA has to be enclosed by the contractor for the document proof.

Signature of Tenderer

Page 31: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 30

FORMAT– 2 DETAILS REQUIRED TO SATISFY THE ELIGIBILITY CLAUSE 5.01 b.

b) Experience in Retrofitting Works

The TENDERER should have satisfactorily completed the works like

Strengthening the RCC column, slab & wall by retrofitting method in any Multi-storied Building / Industrial Building / IT Building / Hotel / institutional building.

Experience of having successfully completed similar (concrete strengthening and retrofitting) works during the last 5 years ending last day of month previous to the one in which application are invited should be either of the following:

(i) One similar (concrete strengthening and retrofitting) completed works each costing not less than Rs.115 Lakhs.

OR

(ii) Two similar (concrete strengthening and retrofitting) completed works each costing not less than Rs.75 Lakhs.

OR

(iii) Three similar (concrete strengthening and retrofitting) completed works each costing not less than Rs.55 Lakhs

The TENDERER should submit LOA or Agreement and work completion certificate or handing over certificate for the above works as part of the technical bid.

S.No. Description 1st Project 2nd Project 3rd Project

1 Name of the Client

2 Nature and Scope of work

3 Period of Contract

4 Value of the

work

5 Year of completion

The following Documentary evidences required to establish the above P.Q. Criteria

Copy of Client’s Work Completion Certificate or handing over certificate has to be enclosed by the contractor for the document proof.

Signature of Tenderer

Page 32: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 31

FORMAT – 3

DETAILS REQUIRED TO SATISFY THE ELIGIBILITY CLAUSE 5.01 c.

c) Experience in Basement Water Proofing Works

The TENDERER should have satisfactorily completed the Waterproofing works minimum in one basement of any Multi-storied Building / Industrial Building / IT Building / Hotel / institutional building during the last 5 years. Ending last day of month

previous to the one in which application are invited The TENDERER shall submit LOA or Agreement and work completion certificate or handing over certificate for the above works as part technical bid.

S.No. Year Project Details

1

01.04.2014

To 31.03.2015

2 01.04.2015

To 31.03.2016

3 01.04.2016

To

31.03.2017

4

01.04.2017

To 31.03.2018

5 01.04.2018

To 31.03.2019

The following Documentary evidences required to establish the above P.Q. Criteria

Copy of Client’s Work Completion Certificate or handing over certificate has to be

enclosed by the contractor for the document proof.

Signature of Tenderer

Page 33: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 32

FORMAT – 4

DETAILS REQUIRED TO SATISFY THE ELIGIBILITY CLAUSE 5.01 d.

d) Annual Turnover

Average annual financial turnover during the last 3 years, ending 31st March

of the previous financial years should be a minimum of Rs. 50 lakhs. .

S.No. Financial

Year

Annual Turn Over of the Company

(Value in INR)

1 01.04.2016

to 31.03.2017

2

01.04.2017

to 31.03.2018

3

01.04.2018 to

31.03.2019

Note:

To satisfy the Pre-Qualification criteria Audited Balance Sheet (duly signed by

practicing CA), have to be submitted as per the prescribed format enclosed viz.

Signature of Tenderer

Page 34: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 33

FORMAT – 5

e) BANKER’S SOLVENCY CERTIFICATE

The Tenderer should produce Banker’s Solvency Certificate for a value of Rs. 60 Lakhs obtained not earlier than three months from the last date of submission of tender, the

certificate to be enclosed along with PQ documents.

Draft

To Date: The Managing Director TICEL Bio Park Ltd.

No.5, CSIR Road, Taramani, Chennai – 600 113

Dear Sir,

SOLVENCY CERTIFICATE

This is to certify that to the best of our knowledge and information, M/s ……………………….. …………….., (address ) …………………………., a customer of our Bank is respectable and be treated as good for an engagement upto a sum of Rs. ………( Solvency amount )……….only as on …………….(Date of certificate)

This certificate has been issued without any risk and responsibility on the part of the Bank or any of its officers.

This certificate is issued at the specific request of the customer.

Yours faithfully,

for ……………………Bank

Bank Officer with designation

Signature of Tenderer

Page 35: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 34

PRE-QUALIFICATION REQUIREMENTS

S.N

O PARTICULARS

TO BE FILLED BY

TENDERER (YES / NO)

1. Do you satisfy requirement of Clause 5.01.(a)

2. Do you satisfy requirement of Clause 5.01.(b)

3. Do you satisfy requirement of Clause 5.01.(c)

4. Do you satisfy requirement of Clause 5.01.(d)

Date of Submission Signature of TENDERER with Official

Seal

Page 36: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 35

WITHDRAWAL OF CONDITIONS LETTER

Date:

To The Managing Director, TICEL Bio Park Ltd,

No.5, CSIR Road,Taramani, Chennai – 600 113.

Dear Sir,

Sub:TENDER FOR PROVIDING RECTIFICATION OF BASEMENT STRENGTHENING CUM RETROFITTING WORKS IN BASEMENT COLUMN, SLAB, RCC WALLS AND WATER PROOFING WROKS AT

TICEL BIO PARK – II BUILDING at No.5, CSIR Road, TARAMANI, CHENNAI 600113– Withdrawal of conditions - reg.

----- We hereby confirm that our offer TENDER for providing RECTIFICATION OF

BASEMENT STRENGTHENING CUM RETROFITTING WORKS IN BASEMENT

COLUMN, SLAB, RCC WALLS AND WATER PROOFING WORKS relating to TICEL

BIO PARK –II Building at No.5, CSIR Road, Taramani, Chennai - 600113, is in complete

compliance with the TENDER documents, drawings, specifications, Bill of Quantities and

subsequent pre TENDER meeting minutes. Our offer does not deviate from any of the

Technical and Commercial requirement of the TENDER documents. We hereby agree to

withdraw all conditions/deviation in case any such conditions / deviations have been

specified by us in the technical or price TENDER which have either direct or indirect

impact on the price quoted.

Thanking and assuring you of our best services at all times.

Yours faithfully,

Page 37: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 36

On Rs.20 Stamp Paper

DECLARATION – CUM – UNDERTAKING

We, ------------------------------------------------ pursuant to our TENDER submission

on__.__.2019 for selection of TENDER for PROVIDING RECTIFICATION OF

BASEMENT STRENGTHENING CUM RETROFITTING WORKS IN BASEMENT

COLUMN, SLAB, RCC WALLS AND WATER PROOFING WORK relating to TICEL

bio park –II Building at No.5, CSIR Road, Taramani, Chennai – 600 113, hereby

declare that all the certificates, agreements, information and other details, furnished

by us in our TENDER document are true and correct.

We further declare that, in case the contract is awarded to us, and at a later date any

of the above certificates, agreements, information and other details are found to be

false or incorrect, TICEL bio park Ltd., has full rights to terminate the Contract with

immediate effect, without any notice and without assigning any reason therefore,

besides initiating actions such as forfeiting the Earnest Money Deposit, invoking the

Performance Bank Guarantee etc.

We further undertake that in the event of such termination, we would indemnify

TICEL BIO Park Ltd., against the consequential losses, damages etc., as claimed by

TICEL BIO Park Ltd., for having furnish such false/incorrect certificate, agreements,

information and other details.

Place: Signature:

Date: Name:

Designation:

Page 38: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 37

ANNEXURE - I

Tender for Providing Rectification of Basement Strengthening Cum Retrofitting works in Basement Column, Slab, RCC walls and Water Proofing work at Ticel Bio Park – II

Building

Work Execution Schedule with time frame for completion of various stages of work with milestones

S.NO. NAME OF ACTIVITY NO OF DAYS ALLOTTTED

FROM LOA

A

Deployment of Required Man Power with

Project Manager at site with all other Engineers.

Within 10 days

B Submission of Bank Guarantee & Agreement.

Within 15 days

C Completion of Wall works Within 50 days

D Completion of Column works including

water proofing works Within 60 days

E Completion of Slab and other works Within 75 days

F

Complétion and Hand Over of all Works

Within 90 days

Page 39: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 38

GENERAL CONDITIONS OF CONTRACT

1 Inspection of site: The contractor shall visit and examine the sites and satisfy as to

the nature and correct dimensions of work and facilities for obtaining material and shall obtain generally his own information on all matters affecting the execution of work. No extra charge made in consequence of any misunderstanding or incorrect

information on any of these points on the ground of insufficient description will be allowed. All expenses incurred by the contractors in connection with obtaining information for submitting this TENDER including his visit to site and efforts in compiling the TENDER shall be borne by the TENDERER ad no claims for

reimbursement thereof shall be entertained. 2 Safety Regulations: The contractor shall take all the necessary precautions while

working and to safeguard adjacent property, TICEL property, TICEL employees, employees of contractor & general public.

3 Compliance to local laws: The contractor shall conform to the provisions of any Act

of the Legislature relating to the work and to the Regulation of Bye Laws of any

prevalent authority. He shall also obtain all necessary permission / approval, NOC from the competent authorities for completion of the said work, if required under the existing rules.

4 Site cleaning: All the rates quoted are inclusive of removal of rubbish / debris

collected during the progress of work, rejected material and clearance of site before and after the work is completed.

5 Vouchers / bills: Contractor shall upon the request of the TICEL furnish bills,

invoices, accounts, receipts and other vouchers for all materials brought on site to prove that the material purchased are as mentioned in the specification.

6 Contractor’s responsibility: The work will from time to time be examined by TICEL

Architect / Engineer, but such examination shall not in any way exonerate the contractor from the obligation to remedying any defects which may be observed at any stage of the work or after the same is completed.

7 Dismissal from work: The contractor shall upon the written request of the TICEL

Architect / Engineer immediately dismiss from the work any person employed by him thereon, who may in the opinion of the authority be incompetent or misconduct himself and such person shall not be again employed on the work.

8 Order of work, etc: TICEL reserves the right to fix the order in which the various

items of work involved are to be executed. However, the contractor shall be responsible for the completion of the entire job within the item limit specified failing which liquidated damages as mentioned in clause No.48 shall be recovered from the contractor.

9 Commencement of work: The work must be started within 10 days upon accepting

the work order and the programme for carrying out the various jobs shall be drawn out in consultation with the TICEL and Engineering Consultants. Default in compliance with the programmes so finalized shall entail operation of liquidated damages as stated. Adequate labour force shall be provided to complete the work within the

Page 40: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 39

specified period. Adequate security aspects should be ensured in purview of the significance of the building. Contractor has to arrange own security to safe guard their material. TICEL will not be responsible for contractor’s materials.

10 Subletting the work: The contractor shall not directly or indirectly sublet the work to

other party without written permission from the TICEL.

11 Changes in Quantities: The Bill of quantity (BOQ) proposed to be used for

providing Rectification of basement strengthening cum retrofitting works in basement column, Slab, RCC walls and Water proofing work shall be indicated in the tender document. The Tender accepting authority may permit quantity

variation of upto + / - 25% of each BOQ line items without any change in the rates provided for BOQ line items. The final value of the work done should not exceed 15% of the overall Initial Contracted Price.

12 Distribution of work: TICEL reserve the right to distribute the work for which TENDER

have been called, among more than one parties, if found necessary. No claim in this

respect shall be considered and the contractor shall agree to cooperate with other

agencies appointed by the TICEL.

13 Third party damage: The contractor shall be responsible for all injury to persons,

animals, building, building structure, any damage to road, streets, and footpaths shall

rectify it at its own cost, during the contract period.

14 Delay & Extension of time: All the work should be completed within period specified in the TENDER. If the work is delayed due to the reasons beyond the control of the contractor, he should, immediately apply to EC with explanation. If the reasons for such delays and if the opinion of EC is justified, then EC will recommend to TICEL for the approval of extension of time to the Contractor. The quoted rate remains the same during extended period. No extra cost can be claimed by Contractor.

15 Retention money

10% of the gross value will be deducted towards retention money from each running

bill with respect to the limitation of 5% of the work done value. 100% of retention

money shall be released upon completion & handing over of all the works as

certificate by EC.

16 Defect liability period: The defects or other faults which may appear during the defect liability period which is one year period after 100% completion and handing over of the works as certified by the Engineering Consultant (EC).arising in the opinion of the TICEL due to inferior quality of material or bad workmanship not in accordance with the contract, contractor should rectify the repair or fault at his own cost within a reasonable time as fixed by TICEL. In this period any faults (includes inferior quality of material or bad workmanship, etc. not in accordance with the contract) found shall be rectified by the contractor at his own cost failing which all remedial works will be carried out by the owner and will be adjusted from the retention money. In case, if the remedial cost exceeds the retention value, the owner is entitled to invoke the Performance Bank Guarantee.

Page 41: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 40

17 Arrangement of work: The contractor shall organise the work in such a way that the office users or the nearby public area are not subjected to any hardships and the working of the office is not affected. The contractor shall take adequate care during the progress of work to protect the office property like stationery, furniture, etc. In case of any damage, the same shall be made good by the contractor and no claim in this regard shall be entertained. If Contractor agrees to work after office hours/during night, for which no extra cost shall be considered.

18 Stacking of material: The contractor is not to stack any of his material recklessly so

as to endanger the safety of the building and cause any nuisance to the occupants and the public.

19 Extra charges: It is clearly implied that all the conditions of contracts are intended to

be strictly enforced and that no extra charges in respect of extra work will be allowed unless such work shall have been ordered in writing.

20 Protection of material and work: The contractor shall be responsible for storing and watching his own material and protecting the work at his own cost. The contractor and his worker will be allowed to use service lift only after office hours. Any damage / spoiling of lift / floor / dado caused during such act will have to be made good by the contractor at his own expenditure.

21 Electric supply: Electricity will be supplied by the TICEL; the contractor shall make his own arrangement for providing points, wires lines, extension board, necessary electricians wherever it is required in the premises, in and out. Extra electrical meter will be fixed for payment as per rules.

22 Water Supply: Water consumption for Construction Activities shall be collected from

contractor by TICEL as per flow meter reading at any One Point @ Rs.200/KL

23 Approval of samples: The contractor shall furnish well in time before work commence at his own cost, colour samples, samples of material or workmanship that may be

called by Engineering Consultant for approval. Rates quoted shall cover for such preliminary work.

24 Workmanship: The work involved calls for a high standard of work man ship combined with speed. All the glass panes, door handles / hinges, electric fitting, fans, furniture records, floors etc. are to be thoroughly cleaned after work is completed. Any damage to the flooring, tiles, dado, paneling or any other part of the building, etc. Shall be made good at the cost of the contractor to the entire satisfaction of the Bank. Contractor shall make all arrangements for shifting of furniture / records and keeping the same in its original position after he finishes the work on daily basis. The contractor at his own cost shall provide brown paper, polythene, tarpaulin etc. for protecting furniture / fixtures, paneling, electrical, fittings, records, etc.

25 Interpretation of documents / drawing: Except where otherwise provided in the contract all questions and disputes relating to the meaning of the specifications, design drawings and instructions herein before mentioned and as to the quality of

workmanship or materials used for the work or as to any other question, claim, right,

Page 42: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 41

matter or thing whatsoever, in any way arising out of or relating to the contract, designs, drawings specifications, estimates, instructions, orders or these conditions or

otherwise concerning the works, or the execution or failure to execute the same whether arising during the progress of the work or after the completion or abandonment thereof shall be referred to the competent authority of the Bank whose

decision shall be final and binding on the contractor

26 Use of scaffolding: Necessary scaffolding, centering and ladder facility is the scope of contractor. No extra cost is considered.

If required any dewatering, contractor has to arrange own system at their cost with necessary machine, tools and manpower.

27 Provisional Item: If ordered by the TICEL, contractor shall be required to carry out

provisional items at the same conditions and rates as applicable for this contract. Period as per the contract.

28 Measurements of all concealed items: Measurements of all concealed items of work

and extra item if any, shall be got recorded by the TICEL Engineering Consultant before it is concealed or covered.

29 Measurements: All measurement tapes shall be of steel and all scaffolding and ladders that may be required for taking measurements shall be supplied by the contractor.

30 Cleaning during the work: The rates quoted shall include cleaning of entire site with

all fixtures &Equipment’s leaving the site neat and tidy from time to time.

31. Complying I.S. specification: Unless otherwise mentioned in the contract, the latest

Indian Standard Code for material specifications, method of work, and mode of measurements shall be followed. The payment shall be made on the basis of actual measurement of work done to be submitted along with bill

32. Rate to include: The rates quoted by the contractor shall cover for the entire

basement area (all three basements) in the site premises under this contract. The rate quoted shall be inclusive of all material cost, wastage, labour, loading, scaffolding, centering, transport, supervision, necessary dewatering system with machine and manpower, prepare the area for work anywhere, spot light arrangement and profit, taxes and GST, if any other means to complete the job.

33. Price Fluctuation: The rates quoted by the contractor shall be firm throughout the

currency of contract (including extension of time if any granted) and will not be subject

to any fluctuation due to variation in the cost of material or labour.

34. The successful TENDERER if called upon to do so, shall obtain a letter from the

approved trade manufacturer whose product is used, if found necessary by the Bank

confirming that the manufacturer shall provide all the technical assistance and

supervision during the execution of the work at all such places as directed and the

contractor shall bear the expenses, if any, for such supervision and technical

assistance supplied by the trade manufacturer. 35. Testing of materials: At any point of time during the work, if necessary, the

Page 43: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 42

contractor shall arrange for the test report has to be submitted without any extra cost.

36. The contractor shall note that they should bring the notice to EC, the defects in

building including finishes or breakage in glass window, curtain glazing, etc before starting work. However, if any defect in finishes of building or glass is found to be broken during the work, the same shall be replaced by the contractor at his own cost.

37 Conditional TENDERs: Conditional TENDERs are rejected.

38 Rates of non-Tendered items: The successful TENDERER is bound to carry out any item of work necessary for the completion of the job even though such items are not included in schedule of quantities with the prior approval of TICEL / EC.

39 Abandonment of work: If in any case the work required to be abandoned, the

contractor shall not be entitled for any claims and he will be paid as per the actual

work done till that period.

40 Deleted

41 TICEL / EC reserves the right to accept / reject the lower or any or all TENDERs in part

or in whole without assigning a reason therefore.

42 Decision of the TICEL shall be final and binding on any matter connected with the work.

Any dispute or difference between the Parties and all connected and related matters

whatsoever shall be discussed and settled amicably. In the event of any failure to

resolve the disputes or differences amicably, all such disputes or differences

whatsoever, shall be referred to the arbitrator with in the jurisdiction in Chennai. The

arbitration proceedings shall first be conducted in English and in accordance with the

provisions of Indian Arbitration and Conciliation Act 1996 or any statutory modification or

enactment thereof. The venue of arbitration shall be Chennai. All connected and related

matters shall, in all respects, be subject to the jurisdiction of Chennai. 43 Incomplete quotation: Incomplete quotations shall be summarily rejected 44 Payments: The contractor shall be paid by the TICEL from time to time under interim

payment on account of works executed and when the value of work equal to the approximate value named in the clause as ‘Value of work for Interim Certificate has been executed in accordance with this contract.

Settlement of Contractors Bills

The Contractor shall submit running bills as mentioned herein, to the engineering consultant for acceptance, due scrutiny & further approval. The engineering consultant upon acceptance of bills from contractor shall immediately recommend certification for

settlement of 60% of the amount claimed by the contractor as adhoc payment. The bill shall then be certified for full settlement by the engineering consultant not later than 15 days of acceptance of the bill.

The adhoc payment shall be effected by owners, not later than 10 days upon receiving engineering consultant’s certificate for payment. However the bills shall be settled in full

not later than 15 days from the date of submission to the engineering consultant.

Bill of Quantities

Page 44: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 43

The Bill of Quantities given in Contract Bill is provisional and is meant to indicate the intent of the work and to provide a uniform basis for Tendering. The Owner reserves the

right to increase or decrease any of the quantities or to totally omit any item of work and the Contractor shall not claim any extras or damages on these grounds. Any error in description or in quantity or omission of items from the Contract Bill shall not vitiate this

Contract but shall be treated as a variation.

The Bill of Quantities shall contain items for the construction, installation, testing, and

commissioning work to be done by the Contractor. The Bill of Quantities is used to calculate the Contract Price. The Contractor is paid for

the quantity of the work done at the rate in the Bill of Quantities for each item.

45 Terms of Payment: All payments by the Owner under this Contract will be made through

banking channel within the specified period based on detailed recorded measurements and certification of bills by the Architect All such interim / progressive payments shall be regarded as payment by way of

advances against final payment only and shall not preclude the requiring of bad, unsound and imperfect or unskilled work to be rejected, removed, taken away and reconstructed or re-erected. Any certificate given by the Architect/Owner’s engineers

relating to the work done or materials delivered forming part of such payment, may be modified or corrected by any subsequent such certificate(s) or by the final certificate and shall not by itself be conclusive evidence that any work or materials to which it relates is

/ are in accordance with the contract and specifications. Any such interim payment, or any part thereof shall not in any respect conclude, determine or affect in any way powers of the Architect/owner’s engineers under the contract or any of such payments

be treated as final settlement and adjustment of accounts or in any way vary or affect the contract or right of the Owner under the terms of the contract.

46 Payment of part rates: Payment at part rates to the extent of work done against agreement rates for certain items may be made in the running account bills at the discretion of the Engineering Consultant.

The part rate to be allowed for an item shall be as assessed and decided by the Engineering Consultant for the extent of work done and whether the item could be

completed in all respects as per specification within the balance amount available.

Full rate shall be released in subsequent bills on completion of the item of work in all

respects as per specifications and the amount paid at part rate shall be duly deducted

47 Payment terms

No mobilization advance and security advance will be paid.

48 (a) Deductions in Interim Payments:

i) 10% of the gross value of bill will be deducted towards retention money from each running bill and the retention money shall be collected upto to 5% of the contract sum

of work. ii) Any other applicable deductions as per Conditions of Contract. iii) Other applicable deductions.

The Contractor shall submit his final bill for the works within one month of completion & handing over of works. The bill shall be based only on works as measured and at

accepted agreement rates including rates for any additional or extra work which might

Page 45: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 44

have been sanctioned by the Owner. All deductions due under the contract shall be made.

49 (b) Final bill Payment

The contractor’s final bill shall be certified for settlement, within 30days upon acceptance of handover by the engineering consultant, and payments on this shall be effected within 30 days thereon.

The Owner shall make payment for the final bill within one month from the date of certification of final bill by the Engineering Consultant and validation.

50. The contractor is requested to sign each page of the quotation and put rubber stamp,

seal below his signature and seal the quotation in an envelope.

51 Liquidated damages: If the contractor fails to maintain the required progress as per the

fixed mile stones to complete the work and clear the site or before the contract with respect to the mile stones or extended date period of completion, he shall without prejudice to any other right, pay as agreed compensation amount of 0.02% of contract amount per day of delay subject to maximum of 10.0% of contract amount as liquidated damages and if the liquidated damages value exceeds 10% of contract value, the contractor will be terminated.

52 Records & measurements: Measurements shall be taken jointly by TICEL / EC and

contractor and shall without extra charges provide assistance with appliance/ Equipment; labour and other things necessary for the work and measurements will be signed and dated by both the parties on completion of measurements.

53 Safety measures: The contractor at his own cost shall provide tarpaulins on the external

side of the building at the time of breaking plaster etc. to safeguard adjacent property, TICEL property, employees, general public, etc. The contractor shall follow all the safety measures while carrying out the work. Employer that is TICEL shall not be liable for any compensation due to accident, any mishap or negligence.

54 If there is delay in commencement of work for any reason, the employer that is TICEL

shall not be liable for any compensation. 55 If at any point of time during the progress, it is observed that the contractor is not

progressing the work with due diligence, care and lagging much behind the schedule or fails to gear up the work despite instructions from TICEL / EC. The reserves the right to terminate the contract with 7 days notices. In such case, the contractor shall be liable to pay the employer any extra cost involved for the completion of the said work and will not obstruct any way in completing the work through other agency. After completion of entire work the contractor shall be paid for the actual work executed by him at the quoted rates after deducting any claims, damages. In case of such termination the security deposit held by the TICEL will be forfeited

56 Although the number of coats of paints are specified the contractor will have to additional

coats if the surface is not to the satisfaction of the TICEL / EC and there shall be no extra payment on account of such coats

57 First Aid: The contractor shall be responsible for all first aid and he shall keep the site

fully equipped to meet such emergency.

58 Supervision: The contractor is required to have on site during all working hours a

Page 46: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 45

competent supervisor who will be responsible for the conduct of worker and who has

authority to receive and act on such instructions issued by the TICEL / EC.

59 All work shall be carried out in a workman-like manner to the entire satisfaction of the

TICEL / EC.

60 Contractor shall follow all rules / regulations in force and should possess the license for employing labour and also follow all safety measures, labour bye law and shall be responsible for any lapse.

61 Transfer of TENDER Documents: Transfer of TENDER documents purchased by one

intending TENDERER to another is not permissible. 62 Safety: The contractor shall carry out the entire work in a workman like manner having

full regard for the safety of the men working at site. All safe practices shall be strictly adhered to by the workmen of the contractor like wearing helmets, safety belts when working at heights, gloves when handling sharp objects and reinforcement, eye shields during welding, safety shoes, etc. The contractor shall protect sides of openings in floor slabs, edges of slabs, stairs, stairwells etc. with barricades, warning signs / lights and educate all his workmen regarding following safe working practices. He shall provide first aid boxes at site.

In spite of following safe methods, in case of any unfortunate accident, the contractor shall indemnify the employer against any expenses or claims towards treatment or compensation under the insurance policy.

63 Nuisance: The contractor shall not any time do cause or permit anyone to do or cause

any nuisance on the site or do anything which shall cause unnecessary disturbance of inconvenience to the Employer or to the owners, tenants or occupiers of other properties near the site and to the public generally.

64 Rights, remedies and powers:

i) Termination of contract due to contractor’s default. If the contractor:

a. Abandon the contract.

b. At any time defaults in proceedings with the works with due diligence and continues to do so after a notice in writing of seven days from the TICEL / EC or Employer, or

c. Commits default in complying with any of the terms and conditions of the contract and do not remedy it within 7 days after a notice in writing is given to him in that behalf of the Engineer or TICEL / EC.

d. Persistently disregards the instructions of the Engineer, Project Architect or

contravenes any provision of the contract, e. Fails to remove materials from the site or to pull down and replace work after

receiving from the Engineer, Project Architect notice to the effect that the said materials or works have been rejected.

f. Fails to complete the works or items of work on or before the stipulated date (s) of

completion.

g. Offer or gives or agrees to give to any person in the Employer’s service or to any

Page 47: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 46

other person on this behalf, any gift or consideration of any kind as an inducement or reward for doing or forbearing to do so for having done or forborne to do any act in relation to the obtaining or execution of this or any other contract for the Employer,

h. Shall enter into a contract with the Employer in connection with which commission

has been paid or agreed to be paid by him or to his knowledge, unless the particulars of any such commission and the terms of payment thereof have previously been disclosed in writing to the Employer / Engineer,

i. Shall obtain a contract with the Employer as a result of ring Tendering or other non-

bonafide methods of competitive tendency, j. Being an individual, or if a firm, any partner thereof, shall at any time be adjudged

insolvent or have a receiving order or order for administration of his estate made against him or shall take any proceedings for liquidation or composition (other than a voluntary liquidation fir the purpose of amalgamation or reconstruction) under any Insolvency Act for the time being in force or make any conveyance or assignment of his effects or composition or arrangement for the benefit of his creditors or support so to do, or any application be made under any Insolvency Act for the time being in force for the sequestration of his estates or if a trust deed be executed by him for benefit of his creditors, or

k. Being a company, shall pass a resolution or the court shall make an order for the liquidation of its affairs, or a appointed or circumstances shall arise which entitle the court or debenture holders to appoint a receiver or manager,

l. Shall suffer an execution being levied on his goods and allow it to be continued for

a period of 21 days,

m. Assigns, transfers, sublets (engagement of labour on a piece work basis or of labour with materials not to be incorporated in the work, shall not be deemed to be sub-letting) or attempts to assign, transfer or sub-let the entire works, or any portion thereof without the prior written approval of the employer.

n. TICEL may, without prejudice to any other right or remedy which shall have accrued or shall accrue thereafter as the Employer by written notice determine the contract either as a whole or in part.

o. Upon such determination of the contract in whole or in part, the security deposit with the Employer in respect of the contract shall stand forfeited to the Employer without in any way affecting the rights of the Employer.

p. Rights of the employer after determination of the contract due to contractor’s

default.

The Engineering Consultant shall on such determination have powers to:

Take possession of the site and any materials equipment, plant, implements stores etc. Thereon, and / Carry out the incomplete work by any means at the risk and cost of the contractor.

65. Termination

Page 48: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 47

65.1The Owner or the Contractor may terminate the Contract if the other party causes a fundamental breach of the Contract.

65.2 Termination by the Owner

a) Default

If the Tenderer shall make default in any one or more of the following respects, that is

to say:-

If he without reasonable cause wholly suspends the carrying out of the works before

completion thereof, or

If he abandons the Contract, or

If he fails to proceed regularly and diligently with the works, or

If he fails to adhere to the agreed program of schedule, or

if he refuses or persistently neglects to comply with a written notice from the Engineering Consultant requiring him to remove and redo / replace at his cost defective work or

Substandard work or improper materials or goods and by such refusal or neglect the work is materially affected, or

If the progress of any particular item or items is slow, or

If he has failed to execute the work in accordance with the terms and condition of the contract, or

If he is persistently or flagrantly neglecting to carry out his obligation under the Contract, or If he fails to take steps to employ competent or additional staff and labour or to

deploy additional tools and plants and equipment’s as required for scheduled completion of work.

Then the Engineering Consultant may give him a notice by registered post or recorded delivery specifying the default, and if the Contractor either shall continue such a default for 14 days after receipt of such a notice or does not commence and

diligently to remedy such default with 14 days or shall at any time thereafter repeat such a default (whether previously repeated or not) or repudiates the Contract, then the Owner without prejudice to any other rights or remedies may within 10 days after

such continuance or repetition of default by notice by registered post or recorded delivery forthwith determine the employment of the Contractor under this Contract, provided that such notice shall not be given unreasonably or vexatiously.

b) Bankruptcy of Contractor:-

In the event of the Contractor

Becoming bankrupt or insolvent, or

Making a composition or arrangement with or assignment in favour of his creditors, or

Page 49: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 48

Agreeing to carry out the Contract under a committee of inspection of his creditors, or

Being a company, having a winding up order made or (except for purposes or reconstruction), a resolution for voluntary winding up passed, or a receiver or

manager of his business or undertaking duly appointed or possession taken by or on behalf of the holders of any debentures secured by a floating charge, of any property comprised in or subject to the floating charge, the employment of the Contractor

under this Contract shall be forthwith automatically determined but the said employment may be reinstated and continued if the Owner and the Contractor, his trustee in bankruptcy, liquidator, receiver or manager as the case may be shall so

agree. c) Corrupt Practice:-

The Owner shall be entitled to terminate the employment of the Contractor under this

Contract.If the Contractor shall have offered or given or agreed to give to any person any gift or consideration of any kind as an inducement or reward for doing or forbearing to do or for having done or forborne to do any action in relation to the

obtaining or execution of this Contract with the Owner, or For showing or forbearing to show favour or disfavor to any person in relation to this

Contract, or any other Contract with the Owner. Or if the like acts shall have been done by any person employed by the Contractor or

acting on his behalf (whether with or without the knowledge of the Contractor), or if in relation to this Contract or any other Contract with the Owner the Contractor or any person employed by him or acting on his behalf shall have committed any offence

under the prevention of corruption act, or shall have given any fee or reward the receipt of which is an offence under the Local Government Act

65.3 Consequences:-

In the event of the employment of the Contractor being terminated as aforesaid and so long as it has not been reinstated and continued, the following shall be the respective rights and duties of the Owner and Contractor.

The Retention money & Performance money shall stand forfeited in favour of the Owner.

The Contractor shall deliver to the Engineering Consultant all drawings and other documents made by or for the Contractor in connection with the Works.

The Owner may employ and pay other persons to carry out and complete the works and he or they may enter upon the Works and use all temporary buildings, plant, machinery, appliances, goods and materials intended for, delivered to and placed on or adjacent to

the works and may purchase all materials and goods necessary for the carrying out the completion of the Works.

The Contractor shall if so required by the Owner or Engineering Consultant within 14 days of the date of termination assign to the Owner without payment the benefit of any Agreement for the supply of materials or goods and/or for the execution of any works for

the purposes of this Contract but on the terms that a supplier or Sub-Contractor shall be entitled to make any reasonable objection to any further assignment thereof by the Owner. In any case the Owner may pay any supplier or Sub-Contractor for any materials

Page 50: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 49

or goods delivered or Works executed for the purpose of the Contract (whether before or after the date of determination), in so far as the price thereof has not already been

paid by the Contractor . Payments made under this paragraph may be deducted from any sum due or to become due to the Contractor.

The Contractor shall as and when required in writing by the Engineering Consultant so to do (but not before) remove from the works any temporary buildings, plant, tool, equipments, goods and materials belonging to or hired by him. If within a reasonable

time after any such requirements has been made the Contractor , has not complied therewith then the Owner may (but without being responsible for any loss or damage) remove and sell any such property of the Contractor, holding the proceeds less all costs

incurred to the credit of the Contractor. The Contractor shall not be released from any of his obligations or liabilities under the

Contract prior to the date of termination. The Contractor shall allow or pay to the Owner in the manner hereinafter appearing the

amount of any direct loss and/or damage caused to the Owner by the termination. Until after completion of the works under this Clause the Owner shall not be bound by any provisions of this Contract to make any further payment to the Contractor , but upon

such completion and the verification within a reasonable time of the accounts thereof the Engineering Consultant shall certify the amount of expense properly incurred by the Owner and the amount of any direct loss and/or damage caused to the Owner by the

determination and if such amounts when added to the monies paid to the Contractor before the date of determination exceed the total amount which would have been payable on due completion in accordance with this Contract, the difference shall be a

debt payable to the Owner by the Contractor and if the said amounts, when added to the said monies be less than the said total amount, the difference shall be a debt payable by the Owner to the Contractor.

65.4 Termination by contractor

Without prejudice to any other rights and remedies which the Contractor may possess, if the Owner does not pay to the Contractor the amount due on any certificate within the

period for honoring Certificates mentioned in these Conditions and continues such default for 15 days after receipt by registered post or recorded delivery of a notice from the Contractor stating that notice of termination under this condition will be served if

payment is not made within 15 days from receipt thereof; Or The Owner interferes with or obstructs the issuance of any certificate due under this Contract; Or The carrying out of the whole or substantially the whole of the uncompleted works (other than the

execution of work required under clause 70 of these conditions) is suspended for a continuous period of more than 3 (three) months by reason of:

Force majeure, or Loss or damage occasioned by any one or more of the contingencies referred to in clause 82 of these conditions (if applicable) Or Civil commotion or by any injunction or other order of any Court of Law, Or Engineering Consultant’s instructions

issued under clauses ( 10 ) of these conditions, Or The Contractor not having received in due time necessary instructions drawings, details or levels from the Engineering Consultant for which he specifically applied in writing on a date which having regard to

the date of completion stated in the appendix to these Conditions Or to any extension of time when fixed under clause 14 of these Conditions was neither unreasonably distant from nor unreasonably close to the date on which it was necessary for him to receive

the same, Or Delay on the part of Artists, Tradesmen or others engaged by the Owner

Page 51: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 50

in executing work not forming part of this Contract, or The opening up for inspection of any work covered up or of the testing of any of the work materials or goods (including

making good in consequence of such opening up or testing) unless the inspection or test showed that the work materials or goods were not in accordance with this Contract.

Then Contractor may thereupon by notice by registered post or recorded delivery to the Owner and the Engineering Consultant forthwith determine the employment of the Contractor under this Contract; provided to such notice shall not be given unreasonably

or vexatiously. Upon such determination, then without prejudice to the accrued rights or remedies of

either party or to any liability which may accrue either before the Contractor or any Sub-Contractor shall have removed his or their temporary buildings, plant, machinery, appliances, goods or materials or by reason of his or their so removing the same, the

respective rights and liabilities of the Contractor and the Owner shall be as follows that is to say:

The Contractor shall with all reasonable diligence dispatch in such manner and with such precautions as will prevent injury, death or damage of the classes in respect for which before the date of determination he was liable to indemnify the Owner, remove

from site all his temporary buildings, plant, machinery, appliances, goods and materials and shall give facilities for his Sub-Contractors to do the same but subject always to the provisions of this clause.

The Contractor shall deliver to the Engineering Consultant all drawings and other documents made by or for the Contractor in connection with the Works.

After taking into account amounts previously paid under this Contract the Contractor shall be paid by the Owner

The total value of the works completed at the date of termination.

The total value of work begun and executed but not completed at the date of termination the value being ascertained mutatis mutandis in accordance with of these Conditions.

The cost of materials or goods properly ordered for the works for which the Contractor shall have paid or of which the Contractor is legally bound to pay, and on such payment by the Owner materials or goods so paid for shall become the property of the Owner.

The reasonable cost of the removal under this clause.

Any direct loss and/or damage caused to the Contractor by the determination. Provided that in addition to all other remedies the Contractor upon such determination

may take possession of and shall have a lien upon all unfixed materials which may have become the property of the Owner under clause 19 until payment of all monies due to the Contractor from the Owner.

The Contractor shall not be released from any of his obligations or liabilities under the Contract prior to the date of termination.

Page 52: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 51

66. Force Majeure:

66.1 If at any time during the continuance of this Contract the performance by either party under this Contract of any of its obligations is rendered impossible by reasons of Force Majeure such as acts of God, flood, fire, earthquake, explosion, war, riots, civil

commotion etc. (here-in-after referred to as Force Majeure) then, provided written notice of the happening of the event of Force Majeure is given by the affected party to the other within 15 days, of the occurrence thereof and provided that such event of Force

Majeure has not resulted from the negligence or failure of the affected party to perform its obligations, the affected party shall not be liable for fulfillment of any of its obligations pursuant to this Contract during the continuance of the event of Force Majeure.

So soon as practicable, upon the cessation of the Force Majeure conditions, the affected party shall continue performance of its obligations under the Contract.

The affected party shall take steps to remedy and mitigate the effects of the Force Majeure event on its ability to perform its obligations under the Contract.

Time for performance of the relative obligation suspended by the Force Majeure shall then stand extended by the period for which such cause lasts.

If the Contract shall be terminated under the provision of the above clause, the Contractor shall with all reasonable diligence remove from the Site all the Contractor

Contractor’s equipment and shall give similar facilities to his Subcontractors to do so. Any extension of time granted by the Owner in terms of above clause, shall neither

entitle the Contractor to any claim for increase in prices nor shall it release him from any of the obligations under the Contract. If the performance of the Contract as a whole is delayed by reason of the Force Majeure conditions continuing to persist for a continuous

period exceeding 30 Working days, the Owner and the Contractor shall discuss the matter and decide to discontinue or to continue its execution on such terms as may be agreed upon.

The Owner shall not be held responsible or be called upon to make good any losses / costs incurred by the Contractor consequent to the happening of any of the event under

clause above.

67. Suspension of Work Partly or Wholly

67.1The Contractor shall if ordered in writing by the Owner / Engineering Consultant,

temporarily suspend the work or any part thereof for such period and such time as so ordered and shall not after receiving such written order proceed with work therein ordered to be suspended until he shall have received a written order to proceed

therewith. The Contractor shall during such suspension, properly protect and secure the work, so far as is necessary in the opinion of the Engineering Consultant.

If such suspension delays the progress of the work to such an extent as to cause additional expense or loss to the Contractor, the matter shall be mutually discussed and agreed to. As soon as the Contractor finds that such extra cost is likely to be involved on

account of suspension of such work or part thereof he shall promptly notify the Owner accordingly, giving his estimates of such cost likely to be involved. Unless the Owner is so notified he shall not be bound to entertain any subsequent or delayed claims on this

Page 53: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 52

account. However, no compensation for the first cumulative period of 30 days of suspension of work shall be payable by the Owner to the Contractor. If the cumulative

period of suspension of work exceeds 30 days, the Engineering Consultant shall settle mutually and arrive and determine on mutual agreement the amount of compensation payable to the Contractor for the period beyond the initial cumulative suspension period

of 30 days in fair and reasonable manner. An extension of time for completion corresponding with the delay caused by any such

suspension of work as aforesaid will be granted to the Contractor should he apply for the same provided that the suspension was not consequent to any default or failure on the part of the Contractor.

In case of suspension of work ordered in writing by the Owner / Engineering Consultant for a cumulative period of more than three (3) months, the Contractor shall have the

option to terminate the Contract, provided that the suspension was not consequent to any default or failure on the part of the Contractor and that the Contractor shall exercise such option forthwith.

68. Payment upon Termination

68.1 If the Contract is terminated because of a fundamental breach of Contract by the Contractor, the Owner / Engineering Consultant shall issue a certificate for the value

of the work done less advance payments received up to the date of the issue of the certificate, less other recoveries due in terms of the contract, less taxes due to be deducted at source as per applicable law and less the percentage to apply to the work

not completed as indicated in the Contract Data. Additional Liquidated Damages shall not apply. If the total amount due to the Owner exceeds any payment due to the Contractor the difference shall be a debt payable to the Owner. Further, in such an

event, the performance bond shall stand forfeited by the contractor. 68.2 If the Contract is terminated at the Owner's convenience or because of a

fundamental breach of Contract by the Owner, the Engineering Consultant shall issue

a certificate for the value of the work done, the reasonable cost of removal of Equipment, repatriation of the Contractor's personnel employed solely on the Works, and the Contractor's costs of protecting and securing the Works and less advance

payments received up to the date of the certificate, less other recoveries due in terms of the contract, and less taxes due to be deducted at source as per applicable law. In such an event the performance money held by the owner shall be returned to the

contractor, along with other settlement dues. 69. Property

All materials on the Site, Plant, Equipment, Temporary Works and Works are deemed to be the property of the Owner, if the Contract is terminated because of a Contractor’s default.

70. On determination of the contract in full or in part, the Engineer shall determine what amount, if any, is recoverable from the contractor for completion of the works or part of the works or in case the works or part of the works is not to be completed, the loss or damage suffered by the Employer. In determining the amount, credit shall be given to the contractor for the value of the work executed by him upto the time of cancellation or the value of contractor’s materials to be present so as to record the measurements in his presence. If the contractor fails to be present in response to the notice, the recording of measurements shall be preceded with ex-parte and the measurements as recorded shall be binding the contractor.

71. TICEL shall have the right to use contractor’s plant, machinery and materials on the balance work but shall not in any way be responsible for any damage or loss of the

Page 54: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 53

same and the contractor shall not be entitled to any compensation thereof.

IMPORTANT CONDITION OF CONTRACT

WATER PROOFING WORKS

1.0 GENERAL This specification is to be read in conjunction with the conditions of contract, the General Specification and all other specifications and drawings

2.0 CONTRACTOR’S RESPONSIBILITIES

2.1 The Contractor shall be completely responsible for the supply and proper installation of the specified waterproof barrier system, or its equivalent, to make the basement

structure absolutely watertight. All barrier material shall be new and shall comply with the specified material requirements. The Contractor shall produce testing certificates to verify that the barrier material meets the specification and is suitable

for the end use intended.

2.2 The Contractor shall be completely responsible for the evaluation and retrofit for the existing waterproof barrier system for the existing basement wall, to make the whole basement structure, existing and new basement wall absolutely water tight.

2.3 The Contractor shall engage a qualified waterproofing specialist as a sub-contractor

to supply, install and protect the waterproof barrier system, all in accordance with the barrier manufacturer’s recommendations. The waterproofing specialist shall be approved by the TICEL / EC and shall be selected on the basis of past track record,

technical reliability, capability and willingness to supply technical assistance, and reputation for standing behind his product and work.

2.4 The Contractor shall be responsible for the implementation and maintenance of a temporary drainage system to keep the Site dry at all times for proper installation of

the barrier system. During execution, if any additional dewatering system needs, contractor has to arrange own system at own cost.

3.0 Deleted

4.0 Deleted

5.0 Deleted

6.0 Deleted

7.0 DETAILS OF WARRANTY FOR WORK

The Contractor has to furnish warranty for a period of 5 years, after 100% completion and handing over of entire works as certified by the Engineering Consultant a) The warranty related document (Indemnity bond) has to be registered for 5 years

through legal system.

b) During the 5 years of warranty period, the Contractor has to inspect every 6

months and confirm the water tightness and corrosion condition and report should be submitted to TICEL

Page 55: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 54

c) In case of any leakage / fault / deficiency found in the Basement strengthening cum retrofitting works in Basement column, slab, RCC walls and waterproofing

works within the warranty period, it is the duty of the contractor to rectify leakage / fault / deficiency at the Contractors own’s cost without delay.

d) In case of only deficiency / default by the contractor on point ( c ) above, TICEL will invoke the Bank Guarantee as submitted by the Contractor.

7.2 The Contractor has to rectify the fault caused in plaster, paint, paneling, tiling, electrical or other installation, or other property, by water leakage or dampness; this is the duty of the contractor to rectify with his cost.

7.3 The Contractor shall submit manufacture’s product data, installation and use limits

and recommendations. The Contractor shall submit representative samples for

approval. 7.4 The Contractor shall provide the Engineer with comprehensive shop drawings

showing all details and procedures for the relevant parts of the works. At least 14 days for each submission shall be allowed for checking by the Engineer in programming the production of shop drawings. Delays caused by the late submission

of shop drawings or repeated amendments of drawings due to inadequate or inaccurate drawings will not be recognized as a reason for extension to the contract time.

7.5 The manufacturer’s standard application details shall be used only as a guide for the

preparation of shop drawings. The Contractor is deemed to have taken due

consideration of the particular requirements of this contract based on the TENDER documents. Where necessary, the Contractor is expected to improve upon the manufacturer’s standard details to suit the project requirements and such

amendments shall be shown in shop drawings for approval by the Engineer. The Contractor shall not be entitled to extra contract cost and/or time in this respect.

7.6 The contractor, in case failure to the adherence to the above class (7.1 to 7.5) the contractor’s performances bank guarantee will be invoked.

8.0 CONCRETE CONDITIONING

8.1 The barrier material shall be compatible with the surface of concrete. The use of curing compounds, release coatings on concrete forms, or admixtures in the concrete that interfere with the adhesion of the barrier material to concrete shall not be

permitted.

8.2 Curing compounds shall not be used on concrete surfaces unless the Contractor can conduct field tests to demonstrate that complete removal of the compound can be

achieved before application of the barrier. Alternatively, the Contractor may perform field tests to establish the compatibility of the compound with the barrier material and the concrete surface.

8.3 Release agents such as oil, wax, grease and silicone which transfer to the concrete

surface during placement, and contribute to poor adhesion between barrier system

and concrete, shall not be used. The use of proprietary paint systems applied to forms and formulates to prevent contamination of the concrete surface, or the use of polyethylene lined forms, may be considered.

Page 56: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 55

8.4 Special purpose admixtures, such as water-immiscible chemicals intended to retard

evaporation of water during cure, may create adhesion problems and shall not be used.

9.0 CONCRETE SURFACE PREPARATION

9.1 Removal and Repair of Defects

9.1.1 Surface defects, including tie holes, unless otherwise specified in the contract

documents, shall be repaired immediately after form removal. All honeycombed and defective concrete areas shall be removed down to sound concrete which shall then be cleaned. If chipping is necessary, the edges shall be perpendicular to the surface

or slightly undercut. No feather edges shall be permitted. 9.1.2 Unless specifically recommended by the barrier material manufacturer, normal mix

Portland cement-based patching materials shall not be used for the repair of small surface voids and rutted cracks on account of their relatively poor adhesion to cured concrete. Such repair shall be affected with suitable resin-based materials composed of the same resin found in the protective barrier material mixed with inert fillers, but

the specific recommendation of the barrier system manufacturer shall be obtained

before using such materials for patching. Coarse aggregate shall be omitted.

9.1.3 Large surface voids and rutted cracks shall be dry packed with graded aggregate

and pressure grouted with suitable non-shrink cementations mortar.

8.1.4 The quantity of mixing water shall be limited to that necessary for handling and placing. The patching material shall be thoroughly mixed to the extent that i t is the

stiffest consistency that will permit placing.

9.1.5 The area to be patched and a band at least 150 mm wide surrounding it shall be dampened to prevent adsorption of water from the patching mortar. After surface water has evaporated from the area to be patched, an approved bonding agent shall

be well brushed into the prepared surface. The premixed patching mortar shall be thoroughly consolidated into place, struck off so as to leave the patch slightly higher than the surrounding surface and left undisturbed for at least 1 hour to allow for some

initial shrinkage before being finally finished. The patched area shall be kept damp for

7 days.

9.1.6 Proprietary compounds may be used in lieu of, or in addition to, the foregoing patching procedures. Such compounds must be used strictly in accordance with the manufacturer’s recommendations. Specific approval from the barrier manufacturer

shall be obtained before proprietary compounds are used for patching. These materials shall be compatible with the barrier system and the concrete, and not

interfere with good adhesion between the two.

9.1.7 Fins, protrusions or similar irregularities projecting from the concrete surface shall be removed back to the surface by chipping, bush hammering, needle gunning, or

wire brushing. Care shall be exercised to obtain a reasonably planar surface for application of the barrier system. Sharp offsets in the surface, such as those caused by formwork misalignment, shall be mechanically abraded to provide gradual and

smooth transitions between the offset surfaces. 9.2 Stopping or Rerouting of Water

Page 57: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 56

9.2.1 The Contractor shall employ a suitable method of repair to stop any seepage or flow of water into or through the concrete structure prior to application of the barrier

system. The method of repair shall depend on the type of defects present in the concrete and the source of water.

9.2.2 Stopping or rerouting water at the source 9.2.2.1 Excavation outside the structure and installation of temporary site drainage shall

be considered. 9.2.3 Stopping water on surface not in contact with the source

8.2.3.1 Water ingress though a crack, hole or porous area may be stopped on the side

opposite the water-source

9.2.3.2 The use of cementations quick-setting materials shall be considered as temporary

water stops only until permanent surface repairs can be made. Quick-setting mixes

with a chloride ion content exceeding the limits given in the Concrete Work Specification shall not be permitted.

9.2.3.3 Epoxy injection can be either a temporary or permanent repair depending on the following conditions. If the crack is non-moving, epoxy injection can be permanent

repair. If cracks move enough to destroy adhesion between the concrete and the epoxy, the repair shall be considered temporary. The crack to be treated shall first be temporarily sealed with an epoxy resin paste to withstand injection pressures. A low

viscosity epoxy adhesive shall then be injected under pressure through ports established in the surface seal. Qualified and experienced applicators shall be used for this work.

9.2.3.4 Chemical grouts can be effective on a permanent basis if not allowed to dry out. Small grout up to 25 mm in diameter shall be drilled through the concrete wall in the

area of the leaks. The Contractor shall undertake approved precautionary measures during drilling to detect and avoid damage to embedded reinforcement. A low viscosity (2cps), 2-part plastic monomer solution shall then be pumped through

inserted pipes to saturate the soil and form a seal upon hardening. Qualified and experienced applicators shall be used for this work.

9.2.4 Rerouting water on surface not in contact with the source 9.2.4.1 Each crack through which water is flowing shall be covered with a small hollow

enclosure to form a temporary channel. A hollow enclosure may be produced from wire mesh formed in a semicircle with cementations quick-setting material as infill. Enclosures shall be connected together to route the water to a central location. Once

the flow of water has been controlled, other permanent repair methods shall be employed.

9.3 Surface Cleaning

9.3.1 Generally, surfaces shall be dry and must be newly exposed concrete, free of chemical contaminants and loose, weak or unsound materials.

9.3.2 Pre cleaning

9.3.2.1 The Engineer shall inspect the concrete surface to determine the necessity for

pre cleaning. If the surface is heavily contaminated with oil and grease, pre cleaning

Page 58: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 57

is required prior to blast cleaning. Solutions of caustic soda or trisodium phosphate or proprietary detergents specially formulated for use on concrete may be employed for

this purpose. If used, caustic soda solution shall be in a 10/90 dilution ratio. Detergents shall be heavy-duty, non-ionic type. They shall be applied by vigorous scrubbing with a brush or power broom, followed by flushing with water to remove all

traces of both the detergent and the contaminant. Litmus or pH paper shall be used on the wet surface to check the adequacy of flushing. The flushed surface shall be either neutral or slightly alkaline. Solvents are liable to dissolve the material and

spread the contamination over a larger area, and shall not be used as a cleaning agent for this reason.

9.3.3 Mechanical cleaning

9.3.3.1 Scarification by a mechanical impacting device on concrete surfaces may be used to remove thick overlays of dirt or weakened material. Aggregate weakened by scarification shall then be removed by water blast or sand blast. Grinding may be

employed when small areas are to be cleaned or when the cleaned surface must be smooth.

9.3.3.2 Blast or abrasive cleaning shall be used to remove laitance, dirt, efflorescence and weak surface material. The Contractor may select either wet sandblasting or high pressure water jetting procedures for this purpose, subject to compliance with local

building or environmental bylaws and regulations governing the use of such methods, and also to field tests to verify the effectiveness of the method for removing weak surface material. Abrasive cleaning methods other than sand-blasting may be

considered for use provided that the surface is not contaminated by the abrasive used. The compressed air used for sandblasting shall be clean and free of oil particles, and requires the air compressor to be equipped with efficient oil and water

traps. The Contractor shall ensure that clean water is used for wet blast cleaning, and shall make adequate provisions to collect and remove effluent from the Site. The surface shall be abraded to the extent that small aggregate particles are exposed. If

the surface of concrete is weak, more material shall be removed. 9.3.4 Acid etching

9.3.4.1 Acid etching shall be employed at areas where no alternative means of cleaning

are possible. The etching operation shall be performed by persons experienced in

such application.

9.3.4.2 The acid used for etching shall be a 10/90 to 20/80 dilution ration of commercial grade phosphoric acid in water solution applied at the rate of 1.0 square meter per litre. The use of hydrochloric acid shall not be permitted on account of the chloride

constituent. For large areas, low pressure automatic spray equipment shall be used to apply the acid solution. For small areas, plastic sprinkling cans can be used for dispensing the acid solution. A stiff bristle street broom, brush, or similar implement

shall be used to spread the acid solution uniformly over the surface. After the foaming action of the acid has subsided, normally in 3 to 5 minutes, the surface shall be thoroughly flushed with water while scrubbing with stiff bristle or wire brushes to

remove the salts formed by acid reaction and to dislodge loose particles. A second treatment may be necessary to ensure an absolutely clean surface.

9.3.4.3 The adequacy of the flushing system shall be checked at several points within the cleaned area by placing litmus or pH paper on the wet surface to determine whether

Page 59: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 58

the acid has been completely neutralised. If flushing is adequate, the surface shall be allowed to dry. When forced drying is necessary, heat may be applied or dry, oil-free

air may be blown over the surface. 9.4 Tests for surface Quality

9.4.1 Prior to barrier application, the adequacy of surface preparation shall be tested on

the basis of cleanliness, dryness, adhesion quality, and the effects of concrete patching compounds and form release agents. Applicable test procedures are

described below.

9.4.2 Cleanliness of surface

(a) Dusty condition: Wipe the surface with a dark cloth. If a white powder is on the cloth, the surface shall considered to be too dusty and unsatisfactory.

(b) Oily condition: Sprinkle water on the dried concrete surface. If the water spreads out immediately instead of standing as droplets, it shall be considered that the surface is not contaminated by oils or dust

(c) Acid condition: Use pH paper to determine the acidity at the concrete surface. A

pH below 4 shall be considered unacceptable. 9.4.3 Dryness of surface

9.4.3.1 Moisture content shall be considered excessive if moisture collects at the bond line between the concrete and the barrier material. Generally, a test for surface

moisture content shall be conducted before the start of each day’s operation.

9.4.3.2 Moisture content shall be evaluated qualitatively by taping a 1.2 m* 1.2 m clear,

polyethylene sheet to the concrete surface and determining the time required for moisture to collect on the underside of the polyethylene sheet. The ambient conditions, i.e. sunlight, temperature and humidity, during test shall simulate, as much

as practical, the conditions during application of the barrier. The time for moisture to collect shall be compared with the time for adhesion development is less than that required for moisture to collect, the concrete shall be considered adequately dry.

9.4.4 Strength of surface when laitance is present

9.4.4.1 The presence of laitance shall be tested by scraping the surface with a putty knife. If a lose powdery material is observed, excessive laitance is considered present

and shall be removed by mechanical means prior to laying of barrier.

9.4.4.2 Patch tests for surface strength shall be carried out to check the peel adhesion of the barrier system and to provide an indication whether surface cleanliness and

dryness are satisfactory. Patch tests shall be conducted before the start of and during barrier installation at a frequency to be determined by the Engineer. The ambient conditions, i.e. sunlight, temperature and humidity, during test shall simulate, as much

as practical, the conditions during actual application of the barrier. If the results of the tests are not satisfactory for any reason, the Engineer may order further tests to be carried out. Conversely, the Engineer may reduce the rate of sampling if consistent

high quality of workmanship has been well established.

9.4.4.3 The Contractor shall obtain from the barrier manufacturer the recommended procedure for the peel adhesion test, otherwise the following method shall be adopted. An area of clean and dry concrete, which should simulate as much as

practical the conditions existing during application, shall be selected and a 0.6m x 0.6m barrier panel applied in accordance with the manufacturer’s recommendations.

Page 60: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 59

One edge of the barrier panel shall be secured to load a application device capable of applying a uniform peeling force along the panel edge. After adhesion has been

allowed to developed, the panel shall be peeled from the concrete at a 90 degree angle, starting from panel edge. The force required to initiate peeling along the length of panel edge shall be measured for compliance with the manufacturer’s

recommendation and this specification. 10.0 WATERPROOFING UNDER BASEMENT SLABS & SLABS IN CONTACT WITH

SOIL

10.1 Material

10.1.1 HORIZONTAL AREA: The barrier material shall be 4mm the APP modified membrane of MAXIPRO or equivalent for horizontal areas and should be self-finished with mineral granules and weight 5.5 kg/sqmt. It should be reinforced with 180gsm

polyester mat to get tensile strength of minimum 850 (longitudinal) / 575 ( transverse) N5 cm laid loosely on finished pcc surface with a base coat water based emulsion with a minimum overlap of 100mm. Care should be taken to do proper welding by

heating torch.

Vertical area: All as above except mineral granules with a minimum weight of

4.5Kg/m2 with solvent based primer as adhesive @ 250gm/sqmt.

This membrane on floor shall be protected using BITUPROTECT which is a high strength

impact resistant protective board to receive raft rebar. 10.1.2 In the absence of test certificates, the Contractor shall carry out tests to verify

quality of material. Tests shall be carried out in accordance with the appropriate ASTM procedures or approved equivalent.

10.2 Method of Construction

10.2.1 Generally, the application procedures shall be consistent with the manufacturer’s recommendations.

WATER PROOFING METHODS:

1. Basement raft and Terrace water proofing method of works:

Water proofing with 4 m thick APP modified membrane “Maxipro” with 180 gsm polyester

reinforced membrane laid loosely over the base concrete with a coat of water based emulsion with a overlap of 100 mm. The overlap portion shall be torch welded.

Note: The surface to be treated should be reasonably smooth and clear of damaging objects, free from slurry and water. The base layer should be evenly plastered smooth to receive the membrane.

The base layer should be primed with emulsion to receive the membrane. After the priming coat roll of membrane shall be rolled over the flat area to the required length and

all the overlaps shall be minimum of 100 mm. All the overlaps shall be flame torched. For horizontal surfaces of treatment: A rich mix of screed concrete M25 grade 20 to 30

mm thick shall be laid over the membrane in the horizontal surfaces to protect the membrane from reinforcement during placing.

Page 61: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 60

For Vertical surfaces of treatment: Extruded polystyrene protection board 20 mm thick shall be fixed over the membrane in vertical surfaces to protect the membrane from

reinforcement during placing. In case of non – availability if extruded polystyrene protection board, bituminous protection board 3 mm thick may be used with necessary prior approval of the architect /owner.

Work shall be carried out as per the approved method of waterproofing accepted by the architect, work shall be guarantee for five years against leakage and guarantee shall be

provided in the form of guarantee bond as per the approved format. 2. Water proofing method for Lift pits, Toilet sunken slabs U.G.Sump, STP tank:

The Waterproofing to the above areas shall be carried out using Penetron slurry as per

the procedure indicated below: Since the PENETRON requires moisture to initiate the crystalline waterproofing process,

all concrete, whether fresh or old, must be saturated with water.

The concrete surface must be a minimum of 24 HOURS (ONE DAY) old before application of the PENETRON SLURRY coating treatment.

For normal surface conditions, the coverage rate for each PENETRON coat is 0.7 Kg/sqm.

1. The concrete surface to be treated must be clean and free of laitance, dirt, film, paint,

coatings or other foreign matter. 2. If surface is too smooth (where steel forms are used) or if surface is covered with

excess form oil or other foreign matter, the concrete should be cleaned thoroughly with wire brush or water jet.

3. Rout out cracks, faulty construction joints and other structural defects to a depth of 1.5 inches (37 mm) and a width of 25 mm

4. Apply a brush coat of Penetron slurry Concentrate in cavity and allow drying for 10 minutes.

5. Against a direct flow of water (leakage) or where there is excess moisture due to seepage, use PENEPLUG first and followed by a brush of PENETRON SLURRY.

PENETRON SLURRY requires a saturated substrate and a damp surface. Concrete surfaces, therefore, must be thoroughly saturated with clean water prior to the application so as to aid the proper curing of the treatment and to ensure the growth of the crystalline

formation deep within the pores of the concrete. Remove excess surface water before the application. If concrete surface dries out before application, it must be re-wetted.

Mixing of PENETRON SLURRY COAT

(i) Mix PENETRON with clean water only (water that is free of salt and other

deleterious materials).

(ii) Mix clean water into the PENETRON SLURRY powder with a paddle on a slow speed electric drill (250 RPM) or with other equipment that ensures adequate mixing. For small jobs, PENETRON SLURRY may be mixed by gloved hand.

Page 62: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 61

(iii) Be sure that the quantity mixed can be applied within 20 minutes. As the mixture thickens, stir frequently but do not add water.

(iv) Mix PENETRON SLURRY powder with clean water to a creamy consistency For

Brush Application 2.5 parts powder to 1 part water. Application of PENETRON SLURRY COATING

Apply PENETRON SLURRY with a semi-stiff nylon bristle brush. Do not apply PENETRON with a trowel, roller, paintbrush or paint sprayer.

The PENETRON coating must be uniformly applied and should be less than 1.25 mm thick. A thicker coating can cause curing difficulties, especially in warm weather.

Second coat PENETRON Concentrate should be applied after the first coat has reached an initial set but while it is still "green" (less than 48 hours). Light pre-watering between coats may be required due to drying.

In hot weather it is advisable to apply PENETRON either early in the morning or late in the day. This will prevent the PENETRON coating from drying out too quickly. Curing

shall be misty fog spray of clean water must be used for curing the PENETRON treatment. Curing should begin as soon as the PENETRON has set to the point where it will not be damaged by a fine spray of water.

3.0 Construction joint treatment:

Providing treatment to construction joints in basement raft, walls etc, to be carried out as

per the manufacturer specification and as detailed in technical specification complete.Work shall be carried out as per the approved method of waterproofing accepted by the architect, work shall be guarantee for five years against and leakage and

guarantee shall be provided in the form of guarantee bond as per the approved format. Providing and applying Penebar SW 45 Type A water stop of expansive nature at

construction joints / cold joints of the raft slab and at the junctions with the retaining walls etc.

The Penebar SW 45 Type A water stop shall be laid as per following steps: i. Clean the surface sufficiently to receive the Penebar SW Primer.

ii. Apply a coat of Penebar SW primer to the area where Penebar SW 45 Type A water stop is to be placed, at an application rate of 240 running meters per 3.78 Liters of

Penebar SW primer. iii. Placement of Penebar Water stop: The Penebar Water stopper shall be placed as per

the following guidelines: a. Up to a thickness of 150mm: exactly at the centre of the thickness of the concrete.

b. Above 150 mm thickness : Place Penebar closer to the edge of the concrete from where the water is likely to enter the construction joint, keeping the edge of Penebar

minimum 50 mm away from the edge of the concrete.

Page 63: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 62

iv. Using moderate hand pressure with the heel of the hand, press a continuous bead of Penebar Water Stop firmly into the position. Make sure that the product has bonded to

the primed area. v. Peel the protective backing from the exposed side of the water stop and tightly butt the

coil ends to form a continuous water stop. Do not overlap the water stop. vi. Follow standard concrete pouring procedures.

The proposed water stop shall be used for the following situations:

1. At all the cold construction joints

2. At the junction of Horizontal Raft and vertical retaining walls.

3. At the Junction of horizontal Roof slab and vertical Parapet walls

4. At all cold construction joints in Water retaining structures such as water tanks, swimming pools, water bodies on Podium, roof garden or Flower beds etc.

5. Construction joints in the Lift Pits. Around the Pipe penetrations, metal penetrations, any other penetrations, where there is a joint between two different surface – one of the surface being Concrete. For these

penetrations, Penebar SW 45 type B having a cross – section of 1” x 0.5” shall be used. 4.0 Method of construction

4.1 The procedure of work shall be as follows unless otherwise modified by the Engineer

to suit the site and project requirements: (a) At formation level, Lay 75 mm thick lean concrete with HDPE sheet acting as vapor

barrier. The vapor barrier shall be turned down a minimum 150 mm at edges of footings and taped down with waterproofing tape. Concrete surface shall be smooth.

(b) Lay barrier onto prepared surface from low points toward high points in shingled fashion. Each strip shall overlap a minimum of 100mm and shall be rolled down firmly and completely. The barrier manufacturer shall give detailed instructions on the method

of pressure application, especially at joins and laps, to avoid the formation of wrinkled seams, ‘fish mouths’ or trapped air pockets.

(c) At the edge or foundation, the barrier shall be carried a minimum of 25 mm into the concrete cover of Foundation and this detail shall be repeated without a break in continuity around each Foundation. Additionally, all inside and outside corners shall be

double covered with barrier material by applying an initial strip of minimum 300 mm width centred along the axis of the corner. A 25 mm cant strip shall be used on inside corners. Outside corners shall be rounded.

5.0 WATERPROOFING UNDER BASEMENT SLABS & SLABS IN CONTACT WITH SOIL

Method of Construction

Construction joints shall be double covered with barrier material in accordance with the manufacturer's recommendations.

Page 64: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 63

a. The perimeter of the barrier placed in any day’s operation and all outside edges barrier shall have trowelled bead of manufacturer's recommended mastic applied after the

barrier is placed. Protection board shall be provided when work is performed over or near installed portions of the barrier.

b. Areas around protrusions below general formation level shall have a double layer of barrier extending a minimum of 15 mm in each direction from the protrusion. Edges or barrier shall be liberally coated with mastic after the application of the barrier.

c. Immediately before covering the barrier, a careful inspection shall be made and any holes, tears, misaligned or wrinkled seams, trapped air pockets or other discontinuities

shall be remedied and patched with barrier material or mastic. 6.0 TREATMENT OF SLAB CONSTRUCTION JOINTS

a. Construction joints shall be provide in the positions shown on the drawings or

elsewhere as approved by the Engineer, and shall be of an approved shape and design. b. The face of the old concrete shall first be roughened, then scum and lose aggregate

removed there from and the face thoroughly cleaned by flushing. Immediately before placing new concrete against concrete that has already hardened, the old concrete face shall be thoroughly wetted and a coating of neat cement grout of about 2.5 mm thick laid

against it by brushing or other approved method. The new concrete shall be well rammed against the prepared face before the grout sets.

c. Should the construction joints be found leaky, or have moist patches, they are to be made watertight by the Contractor using approved chemical grouting method or equivalent. Inside face rendering will not be accepted as a method of remedy.

7.0 Contiguous Bored Piles

7.1 All joints between Contiguous bored piles shall be pressure grouted with NITTO SS chemical grout or an approved equivalent on the side of the water source.

8.0 Formwork Tiles

8.1 The Contractor shall ensure that all formwork ties for the basement wall are left -in type. After removal of the wall formwork, the sockets of the ties shall be plugged with

non-shrink cementitious grout. 9.0 FLOOD TESTING

9.1 Where required by the Engineering Consultant, flood testing shall be carried out to check the performance of horizontal membrane applications in the Terrace floor slab.

9.2 The area to be tested shall be flooded with at least 25 mm of water, but in no event shall the water be allowed to stand above the finished level of the membrane flashing. Drains shall be plugged and curbings (temporary or permanent) shall be formed to retain

the water for a period of at least 24 hr. 9.3 Any leaks found during flood testing shall be repaired in accordance with the

manufacturer's recommendations and the area shall then be retested. Before repairing the surfaces, they shall be dry.

9.4 Where it is impractical to flood test an area because the slope of the substrate would produce excessive water depths, the membrane shall be tested by allowing water to run

Page 65: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 64

continuously over the area for a period of at least 8 hr. During the 8hr period, the whole area shall be completely immersed.

9.5 Where flood testing is not possible because of job conditions, weather, location etc, a thorough inspection shall be carried out check all laps, terminations and flashings for any

evidence of ‘fish mouths’, incomplete adhesion or other conditions that may be detrimental to the watertight integrity of the membrane.

CONCRETE WORK SPECIFICATION 1.0 STANDARDS AND CODES OF PRACTICE

1.1 Unless otherwise specified herein, all concrete work shall be executed in accordance with the requirements and recommendations of the NBC 2005 together with all amendments and addends, and shall conform to the

requirements of the Indian standards: 2.0 MATERIALS

2.1 General

2.1.1 Concrete shall be made with cement, aggregate and water. No other constituent material shall be used without the approval of the Owner / Engineering Consultant.

2.1.2 All materials used in the Works shall comply in all respects with the specified standards, unless specifically excluded or modified hereafter.

2.2 Cement

2.2.1 The cement used shall be Portland cement or Portland blast furnace cement complying with Indian standards.

2.2.2 The manufacturer’s test certificates will in general be accepted as proof of soundness. If the quality of cement is suspect in any way, the Owner / Engineering Consultant will instruct the Contractor to send selected samples for testing by an

approved and accredited laboratory and will reject any cement which does not comply with specifications. All such rejected cement shall be removed from site and replaced entirely at the Contractor’s own expense. The Owner / Engineering

Consultant many, without tests being made, order that any bag of cement, a portion of the contents of which has hardened, or which appears to be defective in any other way, be removed from the site.

2.2.3 Cement shall be transported to the site in covered vehicles adequately protected

against water and weather; cement shall be stored at least 300 mm above the natural ground level, not more than 10 bags high and in a waterproof store with ample under floor ventilation, all to the approval of the Owner / Engineering

Consultant. Cement shall be used in the order of its deliver to the site.

2.2.4 All cement shall be obtained from approved sources, 2.2.5 Notwithstanding the above provisions, the Contractor may at his option receive

supplies of cement in bulk and store in silos of approved type and size. The capacity of the silos shall be such that not more than one week’s supply can be stored at any time.

Page 66: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 65

2.2.6 A record of the amount of cement used each day in the construction of the works shall be kept by the contractor. This record shall be open to inspection by the

Owner / Engineer Consultant, and copies be submitted to him upon request. 2.2.7 The use of cement other than Portland cement or Portland blast furnace cement

will not be permitted in any part of the works without the approval of the Owner / Engineering Consultant, if such approval is given, the extra cost which may be incurred by using an alternative shall be borne by the Contractor, unless the use of

the alternative has been specially instructed by the Owner / Engineering Consultant in writing. Such alternative cement shall be subject to the provisions of the relevant British Standard and to the provisions as stipulated above for Portland

cement and Portland blast furnace cement.

2.3 Aggregate

2.3.1 Coarse and fine aggregates for concrete shall comply with the standards 2.3.2 For structural concrete grade, the maximum size of coarse aggregate shall be 20

mm and the maximum size of fine aggregate shall be 7mm

2.3.3 Aggregates shall be naturally occurring and shall be obtained from a source known to produce aggregate suitable for concreting.

2.3.4 The aggregates shall be hard, durable and clean and shall not contain deleterious materials in such a form or in sufficient quantity to affect adversely the strength at any age or the durability of the concrete. Examples of such materials are clay,

particularly as an adherent coating, flaking or elongated particles, mica, shale and other laminated materials, coal and other organic impurities, iron pyrites and soluble sulphate or chloride salts such as those of calcium magnesium and

sodium. 2.3.5 Aggregates shall be stored in properly constructed open bins with hard, clean and

adequately drained floors. Each size of aggregate shall be stored in a separate bin. If bins are not provide, the different sizes of aggregate shall be separated by means to be approved by the Owner / Engineering Consultant.

2.4 Water

2.4.1 All water used in the concrete works shall be from the public mains and shall be fresh clean and free from all harmful matter in suspension or solution and in

accordance with the standards. Storage tanks of sufficient size shall be maintained on the site to ensure and abundant service under pressure at all times.

2.5 Admixtures

2.5.1 The Contractor shall propose and use only approved admixtures strictly in accordance with the manufacturer’s instructions and recommendations particularly with regards to the dosage requirements of the admixture, admixtures shall comply

with respective Indian codes. 2.5.2 Before use, the Contractor shall verify the suitability and effectiveness of any

admixture by trial mixes with the cements, aggregates and other materials to be adopted in the works. If two or more admixtures are to be used simultaneously in the same concrete mix, the contractor shall prove date to access their interaction

and to ensure their compatibility. He shall perform and bear all costs for compatibility and chloride content tests on representative samples of the admixture(s) to the satisfaction of the Owner / EC.

Page 67: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 66

2.5.3 The admixture shall not be a material, which can adversely impair the strength,

durability or appearance of the finished concrete works. It shall not combine with the ingredients of concrete to form harmful compounds nor increase the risk of corrosion of embedded reinforcement.

2.5.4 The chloride content of admixtures shall not exceed 2% by mass of the admixture

for 0.03% by mass of cement in the mix.

2.5.5 Information to be provided by the Contractor on admixtures shall include but not limited to:

(a) The typical dosage and details of the detrimental effects of under-dosage and

over-dosage

(b) The chemical names of the main active ingredients in the admixture

(c) Whether the admixture contains chlorides and, if so, the chloride iron content of the admixture expressed as a percentage mass of cement in the mix.

(d) Whether the admixture leads to the entrainment of air when used at the manufacturer’s recommended dosage.

(e) Where more than one admixture is used, the compatibility of the admixture. 2.6 Waterproof concrete

2.6.1Waterproof concrete where shown in drawings, shall mean concrete mixed with ‘water proof additive of any approved integral Waterproofing admixture

2.6.2The Contractor shall provide information on the admixture for the Owner / Engineering Consultants review as required under the sub-section headed ‘admixtures’ in this specification. The use of the admixture shall be in strict

adherence to the manufacturer’s instructions and recommendations. 3.0 Concrete Mixes

3.1 Definitions 3.1.1The terms concrete grade, maximum free water/cement ration, minimum and

maximum cement content as specified in Indian codes 3.1.2A test specimen shall mean a concrete test cube made for compressive strength

determination in accordance Indian codes. 3.1.3 The 7-day concrete strength shall mean the compressive strength of test

specimens made concrete used in the works and cured for 7 days before testing. 3.2 Designed Mixes

3.2.1Concrete mixes shall be designed by the Contractor for each grade of concrete (if no fly ash or slag is added) as shown in the table below

Concrete grade 30 35 40 45 50

Min 7 days strength N/mm² 20 24 28 32 36

MIN. CEMENT CONTENT kg/m³ 325 350 375 400 425

MAX.CEMENT CONTENT kg/m³ 550 550 550 550 550

Page 68: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 67

MAX.WATER/CEMENT RATIO 0.60 0.55 0.50 0.45 0.40

MAX. NOMINAL SIZE OF COARSE AGGREGATE mm

20 20 20 20 20

In case of using fly ash or slag than the contractor should submit a mix design for

approval and no concreting will be allowed till a trial mix is done and approved for usage in permanent structure.

3.2.2A mix design for a specified concrete grade shall conform to the foregoing requirements in all respects. In particular, the Contractor shall price his concrete rates for full compliance with the minimum cement content specified for each

concrete grade to meat durability requirements. A mix design, which does not comply with the minimum cement content shall not be approved for use in the works, notwithstanding its compressive strength results

3.3 Requirements for designed mixes

3.3.1 Prior to the use of concrete in the permanent works, the Contractor shall submit to the Owner / Engineering Consultant for approval the design mix proportions to be

used for the works and shall carry out trial mixes according to the proposed mix designs. The test procedure and rate of sampling shall be in accordance with the subsection headed ‘trial mixes’ in this specification

3.3 Requirements for designed mixes

3.3.2 The concrete mix shall be designed to have a target mean strength greater than the specified characteristic strength by at least the current margin. The current

margin for each particular type of concrete shall be determined from trial mixes, or may be taken as 1,64 times the standard deviation of cube tests obtained from at least 40 batches of concrete of nominally similar proportions of similar materials

and produced over a period not less than 5 days but not exceeding 6 months by the same plant under similar supervision, subject to a minimum of 7.50 N/mm²

3.3.3 Evidence should be submitted to the Owner / Engineering Consultant showing that at the intended workability, the proposed mix proportions for each grade of concrete of the required quality.

3.3.4 If adequate date for target mean strength is not available trail mixes shall be

prepared. The current margin for the initial mix design shall be taken as not less

than 7.50 N/mm² 3.3.5 The following information shall be provided before any designed mix is supplied

for use in the works:

(a) Nature and source of each material (b) EITHER appropriate existing date as evidence of satisfactory previous

performance for target means strength, current margin, workab8ility and water/cement ratio OR full details of test on trial mixes.

(c) Proposed quantities of each ingredient per cubic meter of fully compacted concrete

Page 69: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 68

3.3.6 Should there be any subsequent change in the sources of materials or any change in cement content, the Contractor shall submit to the Owner / Engineering

Consultant the new mix design data 3.3.7 Concrete shall not be placed in the works prior to approval by the Owner /

Engineering Consultant of test results of the proposed design mix. 3.4 Trial mixes

3.4.1The mix design shall be finalized by trail in the presence of the Owner /

Engineering Consultant or his representative well in advance of the start of concrete placement in the permanent works. Results of all trail tests shall be submitted as soon as available and before any concrete work starts on site

3.4.2 Where trial mixes are required, three separate batches of concrete shall be

prepared using materials likely to be typical of the proposed supply. Sampling and

testing should be in accordance Indian codes. 3.4.3 The workability of each trial batch shall be measured in accordance with the

subsection headed workability in this specification and recorded 3.4.4 Nine test specimens shall be made from each batch. Three specimens shall be

tested ad 7 days and three at 28 days. The remaining three specimens shall be tested as directed by the Owner / Engineering Consultant. The trial mix proportions shall be approved if all three individual cube results tested at 28 days exceed the

characteristic strength increments recorded in tests at 7. 3.4.5 If the trial mixes are required to demonstrate that the maximum free water/cement

ratio is not exceeded, two batches shall be made in laboratory using cement and surface dry aggregates known to typical from past records of the suppliers of the material. The proposed mix proportions shall not be accepted unless both batches

have the correct cement content and a free water/cement ration below the maximum specified value at the proposed degree of workability. For this purpose, existing laboratory test reports may by accept in place of trail mixes but only if the

Owner / Engineering Consultant is satisfied that the materials to be used in the structural concrete works are likely to be similar to those used in the tests.

3.5 Adjustments to mix proportions 3.5.1 Subject to the approval of the Owner / Engineering Consultant, adjustments to mix

proportions may be made during production in order to minimize variability of

strength and to achieve the target mean strength. Such adjustments are regarded as part of proper production control but the specified limits of minimum cement content and maximum water/cement ratio shall be maintained. Changes in cement

content must be declared. Such adjustments to mix proportions should not be taken to imply any change to the current margin.

4.0 READY MIXED CONCRETE

4.1 The Owner / Engineering Consultant may permit the use of ready mixed concrete from an approved source provided that the Contractor complies with the requirements for concrete mixes as previously described. Such permission shall

only be give for as long as the Owner / EC is satisfied that the concrete supplied compiles with the requirements of this specification and the recommendations relevant Indian codes.

Page 70: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 69

4.2 In order to determine compliance with these specifications, the Owner / EC may call

for tests to establish the cement content and the water/cement ration of the ready mixed concrete delivered to site, and the Contractor shall allow for such tests

4.3 Each batch of concrete delivered to the site shall be accompanied by a delivery ticket, a copy of which shall be handed to the Owner / Engineering Consultant’s representative at the time of delivery is made. The following minimum information

shall be printed, stamped or written the delivery ticket:

(a) Name or number of ready-mixed concrete depot

(b) Serial number of ticket

(c) Date

(d) Truck number

(e) Name of location of site

(f) Grade or mix description of concrete, including minimum cement content.

(g) Specified workability

(h) Type of cement

(i) Nominal maximum size of aggregate

(j) Type or name of admixture, if include, and the dosage quantity

(k) Quantity of concrete in cubic meters

(l) Time of loading, defined as the time of contact between cement and aggregates

or when these are surface dry, between cement and added water

4.4 The Contractor shall compete the following items of information on the delivery ticket after the discharge of each batch of concrete:

(a) Arrival and departure times of the truck

(b) Time of completing of discharge

(c) Details of extra water or any other materials added on site

(d) Position in the works where concrete is placed

4.5 In the case of truck mixed concrete, the water may be added either at the concrete

supplier’s plant or under the Contractor’s supervision after arrival at site, but NOT in transit

4.6 The concrete is to be agitated continuously by rotation of the mixer drum during transport to the site and which awaiting discharge. Concrete shall be discharged from the delivery vehicle within 2 hours after the time of loading

4.7 The concrete is to be compacted in its final position in as short a time as possible

after discharge from the delivery vehicle.

5.0 MEASURES TO AVOID CRACKING IN FRESH CONCRETE

5.1 Generally, the Contractor shall allow for all necessary measures to monitor and avoid cracking in fresh hydrating concrete, regardless of the size or volume of the

pour. Such measures shall be to the satisfaction of the Owner / Engineering Consultant and shall be such that the maximum surface crack width on hardened concrete measured immediately after the pour does not exceed 0.004 times the

nominal cover of the main reinforcement.

Page 71: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 70

5.2 If the surface exhibits cracking after compacting, it shall be re-tamped to close the

cracks while the concrete is still in the plastic state. 5.3 The Contractor shall allow for and provide approved instrumentation for the

measurement of internal temperature changes in large pours. The maximum concrete temperature at the point of delivery shall not in general exceed the lower of either 37 degrees C, or 6 degrees c above the prevailing shade temperature. The

limiting internal temperature differential measured across the extreme faces of the concrete mass shall not exceed 25 degrees C at any time

5.4 Curing of hardened concrete shall be executed in accordance with the subsection headed curing in this specification. Generally the element surface shall not be cooled to dissipate heat from the concrete. Curing methods such as the wetting of

heated concrete elements exposed to prolonged and direct radiation, which induce temperature gradients within the concrete mass are strictly prohibited.

5.5 For large pours, the contractor shall allow for and take precautions to reduce concrete temperature gradient and to prevent the loss of surface moisture. Such measures include but are not limited to

(a) Keeping all mix constituents shaded where possible to reduce their temperatures

in the stockpile.

(b) Cooling of mixing water and/or replacing part or whole of the added water with

ice

(c) Reducing the cement content by the use of admixtures (but not below that

required for durability)

(d) Using a cement with a lower heat of hydration

(e) Injecting liquid nitrogen after mixing a concrete. (f) Restricting the time between mixing ad placing of the concrete to not more than 2

hours. (g) Providing approved surface insulation continuously over all exposed surfaces to

prevent draughts and to maintain uniform temperature through the concrete mass (h) Initiating curing immediately after final tamping and continue until the approved

surface insulating system is fully in place. (i) Providing shade to the concrete surface to prevent heat gain from direct radiation

6.0 Formwork

6.1 General

6.1.1Before erecting formwork, the Contractor shall submit details to the Owner / Engineering Consultant of the systems of formwork he proposes to use for all main

structural members

Page 72: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 71

6.1.2If in the opinion of the Owner / Engineering Consultant, the proposed system is in any way unsatisfactory he will instruct the Contractor to have it modified and the

Contractor shall bear the cost of any such modifications. The review of the formwork design shall not relieve the Contractor in any way from his responsibility of providing a system, which is safe and adequate for the intended use.

6.1.3 No metallic part of any device used for maintaining formwork in the correct

location shall remain permanently within the specified concrete cover to

reinforcement. 6.1.4 In watertight construction methods of fixing formwork that leave openings through

the concrete section when the formwork is removed shall not be used. All wall ties shall have water baffles and wall kickers shall be cast monolithically with the

base slab. 6.1.5 Where the support of formwork is provided by the permanent structure the

adequacy of the structure of this temporary role shall be checked and approved by the Owner / Engineering Consultant before work commences

6.2 Holes, Inserts and Fixings

6.2.1 Approval for the size, type and position of any hole, insert fixing required by the Contractor or any subcontractor shall be obtained before work proceeds

6.2.2 Unless otherwise specified or approved, all holes shall be formed and all inserts cast in at the time of pouring. No part of the concrete works shall be subsequently drilled, chipped or cut way without prior approval from the Owner / Engineering

Consultant. 6.3 Release agents

6.3.1 The internal faces f formwork shall be coated with an approved release agent

6.3.2 Release agents shall be materials marketed as such, and shall be of one of the following types:

(a) Cream emulsion

(b) Neat oil with surfactant added

(c) Chemical release agent

6.3.3 The Contractor shall be responsible for ensuring that the release agent is

chemically and physically compatible with the finishes to be applied later. Where there are no applied finishes, the contractor shall be responsible for ensuring that the release agent will not stain the surface of the finished concrete.

1.3.4 Release agents shall be stored and used strictly in accordance with the

manufacturer’s printed instructions

6.4 Cambers

6.4.1 Unless otherwise directed, all formwork to suspended beams and slabs shall be constructed with the following upward cambers

Location % of span

Midspan between supports of span at center 0.3%

Page 73: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 72

Cantilever at free end of span 0.5%

6.5 Flying forms

6.5.1 Where flying forms or similar type of forms are used, they shall be designed

sufficiently rigid and stable to support the Weight of concrete and construction loads, and to maintain the finished work within the specified tolerances. The methods of moving the flying form from one floor to the next shall be carefully

planned to ensure the operation can be carried out with full assurance of safety. Before fly8ing forms are brought out into the open, they shall be cleaned of loose materials that may dislodge during transit

6.6 Formwork design

6.6.1 Formwork panels shall be rigid enough to prevent damage to the concrete surface

by excessive movements of the panel during vibration of the concrete 6.6.2 The design and construction of formwork shall be carried out by competent

personnel, taking due account of the surface finish required. The formwork shall be made sufficiently rigid ad tight at the joints by appropriate methods to prevent loss of front or mortar from the concrete during the placing and compacting of concrete.

The design & methodology of formwork shall be got approved by the Owner/Engineering Consultant.

6.6.3 Formwork (including supprots0 shall be sufficiently rigid to maintain the forms in correct positions and to correct shape and profile so that the final concrete structure is within the limits of the dimensional tolerances and deviations specified,

the supports shall be designed to withstand the worst combination of self-weight, formwork weight formwork forces, reinforcement weight, wet concrete weight and construction loads, together with all incidental dynamic effects caused by placing, vibrating and compacting the concrete

6.6.4 The formwork shall be so arranged as to be readily dismantled and removed

without causing shock, disturbance or damage to the cast concrete. Where

necessary, the arrangement should be such that the soffit form, properly supported on props, can be retained in position for such period as may be required by maturing conditions or this specification. Of the concrete member is to be

prestressed whilst still resting on the soffit form, provision shall be made to allow for elastic deformation and any variation in mass distribution

6.7 Repair of formwork

6.7.1 Damaged formwork shall not be used. Repaired formwork will be rejected if, in the opinion of Owner / Engineering Consultant, the repair may impair the surface

appearance of the finished concrete. Formwork judged by the Owner / Engineering Consultant to unsuitable for the works shall be removed forthwith from the site to prevent accidental re-use

6.8 Formwork props

6.8.1 If formwork props are to be left in place when soffit forms are removed, the props shall not be disturbed during or after the removal process without approval from

the Owner / Engineering Consultant 6.8.2 Formwork props shall be positioned between permanent supports so that all

members are supported at not more than1.00 m centers in both directions.

Page 74: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 73

Re-propping shall be supported at not more than 2.00m centers in both directions.

6.9 Prop detains 6.9.1 The contractor shall submit to the Owner / Engineering Consultant not less than

two weeks prior to the start of any concrete pour which require props, shop drawings indicating the props he proposes to use a detailed programme of the fixing and striking sequences., and an estimate of the loads to be carried by the

props 6.9.2 All propping shall be done with steel props. The use of ‘casurina’ props is not

permitted. Sawn timber prop may be used only if specifically approved in writing by the Owner / Engineering Consultant. If timber props are used, they shall be straight, clear of knots and cracks and shall not be spliced

6.10 Stability during construction 6.10.1 Temporary supports to the structure may be required to require resisting loading

conditions imposed by construction. These shall be provided at the Contractor’s own cost

6.11 Temporary works-safety precautions

6.11.1 The Contractor shall be responsible for the provision of all necessary temporary works and safety measures in accordance with the local regulations and bye-laws

6.11.2 The Contractor shall employ a professional Owner / Engineering Consultant who shall be fully responsible for the design and supervision of all temporary works to ensure complete safety for both temporary and permanent construction

7.0 Striking of formwork

7.1 General

7.1.1 Before any formwork is removed, the Contractor shall ensure that the concrete has attained sufficient strength and that the structure will be stable and not adversely affected when formwork is struck. Materials and plant shall not be placed

on any new construction in such a manner as to cause damage 7.1.2 The responsibility for the safe removal of any part of the formwork or props rests

entirely with the Contractor 7.2 Minimum forming period

7.2.1 The minimum period before removing formwork to structural members shall be as

follows

Location Period

Sides of beams, walls and columns 1 day Slab soffits (formwork props left-in-place) 3 days Formwork props to slabs 7 days

Beam soffits (formwork props left-in-place) 7 days Formwork props to beams 9 days

7.2.2 The above striking times are subject to review by the Owner / EC where accelerated curing methods or sliding forms are used.

Page 75: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 74

7.2.3 Earlier striking of forms (but not props) may be approved if the Contractor can show that this will not course damage to the concrete, especially to arise and

features, r to the structure, especially if it results in unacceptable deflection. The Contractor shall make good any such damage at his expense should it occur.

7.2.4 The making and testing of cubes to establish the period before striking shall be at the Contractor’s own expense. These cubes shall be stored and cured in a manner that simulates the curing of the concrete used in the works

7.2.5 Permission to strike formwork on the basis of the strength of specially cast cubes

shall be withdrawn if the Owner / EC is no satisfied that the strength of the cubes is

representative of the strength of the cast concrete. 7.2.6 Vertical propping to all formwork shall be carried down sufficiently far in the

structure to provide the necessary support, without damage or overstress or displacement of any part of the construction

7.2.7 Structural props shall be retained in position until new construction is sufficiently strong to be self-supporting as well as carry all other additional loads to be placed thereon during the construction period, in no case shall props provided for this

purpose be spaced at more the 1.00m center, in either direction. 7.2.8 All formwork to soffits shall be constructed such that formwork can be removed

without disturbing the structural props 8.0 CONSTRUCTION JOINTS

8.1 General

8.1.1 The locations of construction joints are normally proposed by the Contractor to suit

his preferred methods and sequence of construction joints shall be kept to the minimum necessary for the proper execution of the works. Such joints should generally be at right angles to the general direction of the member being cast and

positioned at the point of inflexion along the member span. Construction joints shall not be permitted across areas designated for wet usage, as in toilets.

8.1.2 Where construction joints are not shown on the contract but are necessary for construction purposes, the Contractor shall obtain approval from the Owner / Engineering Consultant for their locations before work commences. The Contractor

shall allow in his rates for the provision of all construction joints required by him whether or not they are shown on the contract drawings. At all construction joints the surface against which new concrete is cast shall be free from laitance and shall

be roughened so that the larger aggregate is exposed but not dislodged. 8.2 Preparation of construction joints

8.2.1 Unless otherwise instructed, the Contractor shall form and prepare construction

joints in accordance with the requirements and methods recommended he shall provide shop drawings showing all necessary joints details for approval by the Owner / Engineering Consultant.

8.2.2 Where the position of construction joints desired by the Contractor will result in

alterations to the design, the Contractor shall be responsible for providing complete

revised details for approval by the Owner / Engineering Consultant prior to commencing work.

Page 76: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 75

8.2.3 Unless other instructed, the following Owner / Engineering Consultant

considerations shall dictate the positions of construction joints: (a) The length: breadth aspect ratio of any floor or wall panel enclosed by construction

joints and formed in a single casting operation shall not exceed 2:1without the Owner / Engineering Consultant’s written approval

(b) Construction joints shall be laid along positions of least stress, which will be determined by the structural system adopted in the design.

(c) Large pours of floor or wall panel to be connected to previously cast rigid members (shear walls, etc0 shall be avoided in order to minimize cracking due to thermal and shrinkage restraint.

(d) The contractor shall be required to revise his layout of construction joints to the

satisfaction of the Owner / Engineering Consultant if surface cracks occur in

excessive amounts or if measured crack widths exceed the permissible limits given in the sub-section headed ‘measures to avoid cracking in Fresh Concrete’ in this specification

8.3 Movement joints

8.3.1 Movement joints shall be formed in accordance with the requirements.

8.3.2 Movement joints shall be left unconcerned until all expected movement of the structure has occurred.

9.0 KICKERS

9.1 Kickers shall be 150mm high unless otherwise shown. Kickers shall be cast and compacted in accordance with these specification, using concrete of the same grade as the adjacent concrete

10.0 REINFORCEMENT

10.1 Materials

10.1.1 The types of reinforcement bars will be identified on the contract drawings as a

prefix to the bar diameter. The prefixes have the following meaning: R: Round mild steel bars

T: high yield deformed type 2 bars

BRC: Steel fabric

10.1.2 The sources of supply for all materials shall be approved by the Owner / EC before these materials are delivered on the site.

10.1.3 Reinforcement shall be stored clear of working areas and supported above the surface of the ground, and shall be protected from damage and from deterioration due to exposure

10.1.4 Reinforcement hooks and beds shall comply with the requirements of Indian

standards. The Contractor shall prepare bar bending schedules, copies of which

will be made available to the Quantity Surveyor for his assistance during any re-measurement of reinforcement.

Page 77: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 76

10.1.5 Reinforcement not readily identifiable as to the required quality will be liable to rejection

10.2 Test certificates

10.2.1 The Contractor shall supply the Owner / Engineering Consultant with a test certificate from the steel manufacturer shown compliance with specified

requirements. 10.2.2 One tension test and one bend test shall be made for each incremental lot of 50

tones (bar size distinction not necessary) supplied for the works, or as frequently as required by the Owner / Engineering Consultant. In addition, one rebend test shall be conducted fro each incremental lot of 100 tones delivered to site.

10.2.3 The Owner / Engineering Consultant may consider a reduced rate of sampling

when consistent high quality of the material has been well established. Conversely,

if for any reason the Owner / Engineering Consultant is not satisfied with the quality of material, he may instruct the Contractor to further increase the rate of sampling.

10.3 Reinforcement cutting and bending 10.3.1 Reinforcement details are provided in the contract drawings. The Contractor shall

determine from these drawings the required dimensions of the bars, and shall cut and bend the reinforcement in accordance with BS 4466 to meet the requirements of cover, lap length, etc., as indicated on the drawings

10.3.2 On no account shall reinforcement be heated to facilitate bending.

10.3.3 Reinforcement shall not be re-bent unless approved by the Owner / EC. Any bar that shows signs of fracture shall be replaced. Any estimated remedial work that is consequential to bar damage and considered necessary by the Owner / EC shall

be carried out entirely at the Contractor’s cost. 10.3.4 The rates for bar and fabric reinforcement shall include checking, sorting, storing,

fabricating, wastage, cleaning, hoisting in position, and provision of all necessary spacers, hangers, stools, and chair supports, whether or not shown on the contract drawings

10.3.5 Rates for fabric reinforcement shall include minimum 250 mm overlaps between

adjacent sheet and for notching around obstructions

10.4 Reinforcement Fixing

10.4.1 All reinforcement shall be accurately placed with correct cover and securely fixed in the positions shown on the contract drawings by an approved method. Tying

wire, etc.Shall be fixed such that it does not encroach into the concrete cover. 10.4.2 The concrete cover to the reinforcement shall be within + 5 mm of that specified

10.4.3 Spacers, where used to maintain concrete cover to reinforcement may be of

either concrete or plastic construction unless otherwise specified. Plastic spacers

shall be of approved design and are not to be used to support heavy loads

Page 78: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 77

10.4.4 The Contractor shall supply and fix all chairs required to maintain the reinforcement in the correct positions

10.4.5 If not detailed in the contract drawings, the Contractor shall propose and obtain

approval for the size and spacing of chairs.

10.4.6 Spacer blocks shall be made of cement sand and fine aggregate, and shall

match the mix proportions of the surroundings concrete, being similar in strength,

durability and appearance 10.5 Rust Staining

10.5.1 Concrete surface, which will be exposed to view in the finished works, shall be

protected from the rust stains of projecting reinforcement by coating the reinforcement with cement grout or by other approved means.

11.0 Concreting

11.1 Final preparation and inspection

11.1.1 No concrete shall be poured without the Owner / Engineering Consultant’s permission. The Owner / EC shall be notified of any concrete pour 24 hours in

advance exclusive of Sundays and public holidays, for an inspection to be made of the formwork reinforcement expansion joints anchors and other items that are to be embedded in the concrete

11.1.2 The Contractor is to allow for such inspections and for making any required of

instructed corrections

11.1.3 No claims for extra costs or extension of time will be considered for delay due to

failure to give notification or to make the allowance described above. Neither inspection nor approval by the Owner / Engineering Consultant shall relieve the

Contractor of his responsibility or the proper execution of the works. 11.1.4 Immediately before the concrete is placed in any section of the formwork, the

interior of that section shall be completely cleared of all extraneous material, including water, by means of compressed air other approved method.

11.1.5 Each section of formwork for structural members shall be inspected by the Owner / Engineering Consultant immediately before concrete is placed in that section and the contractor shall carry out any adjustments to formwork,

reinforcement or levels, as instructed by the Owner / Engineering Consultant, prior to placing of any concrete

11.1.6 All reinforcement shall be free from mud, pant, oil, retarders, rust, loose, mill

scale, grease or any other substance which may adversely affect the steel or concrete chemically or reduce the bond. The Owner / Engineering Consultant may instruct the Contractor to clean off thoroughly any such substance by wire brushing other approved

method and the Contractor shall allow in his rates for any such cleaning 11.2 Mixing

11.2.1 The volume of mixed materials in each batch shall comply with the mixer manufacturer’s written recommendations

11.2.2 The quantity of cement, fine aggregate and the various sizes of coarse aggregate, shall be measured by weight

Page 79: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 78

11.2.3 A separate weighing device shall provide for weighing the cement. Alternatively,

the cement may be measured by using whole number of bags in each batch. 11.2.4 The amount of water shall be measured either by volume or by weight. The batch

weights of aggregate shall be adjusted to allow for moisture content typical of the aggregates being used

11.2.5 The accuracy of the measuring equipment shall be within +3% of the quantity of cement, water or total aggregates being measured, and within+ 5% of the quantity of any admixture being used. All measuring equipment shall be maintained in a

clean, serviceable condition 11.2.6 The accuracy of all measuring equipment over the entire range of the scale shall

be checked when set up at each site, and thereafter at least once per month. The accuracy of each scale shall be checked and adjusted daily to read zero when not loaded. Checking shall be d\done using proper certified weights.

11.2.7 The water content of each batch of concrete shall be adjusted produce a

concrete that has the workability of the trial mixes

11.3 Transporting and placing

11.3.1 Concrete shall be transported and placed by approved methods that ensure segregation or loss of material will not occur.

11.3.2 Concrete drop during vertical placement shall not exceed 2.50m. For heights

greater than 2.50m, the Contractor shall pour concrete through enclosed chutes or

access hatches, details of which shall be approved by the Owner / Engineering Consultant.

11.3.3 Concrete shall be transported as quickly as possible from mixer to its final position, and in no case shall the time interval between the addition of water and placing exceed 30 minutes.

11.3.4 All placing and compacting shall be carried out by experienced workmen and

under the direct supervision of a competent staff.

11.3.5 Gangways for concrete transporter and foot traffic shall not be permitted to bear

on the fixed reinforcement. They shall be supported clear of the reinforcement on

chairs or stools designed for the purpose. 11.3.6 Concrete shall remain in sufficiently plastic condition for adequate compaction

when placed. Concrete shall be place as near as possible to its final position, and shall be placed square against the forms. Concrete shall not be moved into position by means of vibrators.

11.3.7 In walls, the concrete shall be placed in approximately horizontal layers. The concrete shall be places in one continuous operation, rising uniformly in the formwork at the rate not less than 2.00 per hour. The concrete shall not be handled

in any manner that may cause segregation. 11.3.8 A competent steel fixer shall be in continuous attendance during concreting to

adjust and correct the position of any reinforcement, which may be displaced

Page 80: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 79

11.3.9 Concreting operation must cease during rain and the Owner / Engineering

Consultant will decide whether work can be done under light drizzle. The Contractor shall carry out concreting in such sequence as to minimize the effects on the permanent works of temporary stoppage of concreting due to rain. The

Contractor shall also provide adequate cover and protection from inclement weather for the permanent works.

11.4 Compacting 11.4.1 Unless otherwise specified, all structural concrete shall be compacted by

mechanical vibrators of an appropriate type.

11.4.2 The contractor shall submit details of the type, size and number of vibrators to be

used in the works. Whenever concrete is being vibrated, at least one spare vibrator

of each type in use shall be available in case of breakdowns 11.4.3 The minimum number of vibrators to be provided by the contractor shall be

based on the assumption that one vibrator in proper working condition can compact 5-8 m³ of concrete per hour, unless otherwise instructed

11.4.4 Compaction shall commence as soon as there is sufficient concrete within the formwork to immerse the vibrator. Vibration shall continue during the placing operation so that at no time shall there be a large volume of uncompacted concrete

in the formwork 11.5 Cleaning

11.5.1 All equipment used for mixing, transporting, placing and compacting concrete

shall be thoroughly cleaned before changing from one type of aggregate or cement to another, and whenever mixing ceases

11.6 Records of placing

11.6.1The contractor shall submit weekly a complete record of concrete work completed during the week, including details of the time and date of each pour.

11.7 Curing

11.7.1 If the surface exhibits cracking while the concrete is still plastic, it shall be re-tamped to close the cracks. Curing shall be initiated immediately after final tamping. Initial curing shall be by means of the continuous application of water to

the concrete surface. 11.7.2 The surface of all concrete shall be adequately and continuously cured for a

minimum total period of 7 days from the time to placing unless otherwise instructed.

11.7.3 For large pours or for elements with section dimensions exceeding 600 mm an approved surface insulation system shall be provided comparing jointed sheets of an impervious material which is suitably pigmented to reflect radiation. The sheets

shall be sealed and fastened at the edges to prevent draughts from removing surface moisture. If the finished surface is to be exposed to view, the sheets shall be supported away from the concrete surface.

Page 81: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 80

11.7.4 Sand or hessian layers shall not be used for curing large pours. Sands or hessian layers shall be kept wet by the continuous or frequent applications of water

for the full duration of the specified curing period. 11.7.5 Alternate wetting and drying, and the application of cold water to warm concrete

surfaces during curing shall be strictly prohibited to prevent the occurrence of

adverse temperature gradients in particular, concrete elements with section dements exceeding 600 mm shall be shaded and allowed to cool to the temperature of its surroundings before the application of water.

11.7.6 Liquid curing membranes may alter the surface appearance of concrete and shall

not be used without prior approval, where the use of a liquid curing membrane has

been allowed, the concrete surface shall be prepared and the membrane applied strictly in accordance with the manufacturer’s written instructions, Such approval will be withdrawn if the curing system is found unsatisfactory in any way

11.7.7 Any formwork made of metal, concrete or other material of high thermal capacity

shall be cooled with water before it comes in contact with poured concrete.

11.8 Treatment of cast concrete 11.8.1 Unless otherwise directed, no treatment of any kind, other than that required for

curing the concrete, shall be applied to the concrete after removal of the forms until the concrete has been inspected by the Owner / Engineering Consultant.

11.8.2 The contractor’s methods of making good any defects are subject to the approval of the Owner / Engineering Consultant in each case, and the remedial measures shall be carried out immediately after inspection by the Owner / Engineering

Consultant or when directed by the Owner / Engineering Consultant. Making good will only be permitted on the basis that, if the results are not satisfactory, demolition may be required.

12.0 PUMPED CONCRETE 12.1 Concrete may be pumped subject to the approval of the Owner / Engineering

Consultant. All pumping machinery shall be of an approved type. Complete Standby equipment shall be provided in order to maintain a continuous concrete supply in the event of breakdown. All machinery and pipes shall be kept clean and

shall be thoroughly washed out when placing is completed. All paperwork shall be laid out so that a continuous ‘wet edge’ is maintained during concrete placing. Aluminum pipes are not permitted.

13.0 CONCRETE FINISH 13.1 The concrete shall be uniformly leveled and tamped. When harder end sufficiently,

the surface shall be wood floated by hand to produce a uniform surface. 13.2 Alternatively, where required, the surface shall be steel-floated by hand or machine

to produce a dense, smooth, uniform surface free form trowel marks 14.0 PROTECTION OF FINISHED WORKS

14.1 Surfaces, which are exposed to view in the finished works shall be protected from

spillage, stains and any other damage. 15.0 SALTS IN CONCRETE

15.1 Chloride content

Page 82: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 81

15.1.1The use of calcium chloride as a constituent in reinforced, prestressed or sulpahte-resisting concrete shall be strictly prohibited.

15.1.2The total chloride content of the concrete mix arising from the aggregate together

with that from any admixtures and any other source shall not exceed 0.1% of

chloride ion by mass of cement in the mix. 15.1.3The total chloride content shall be determined either from the mix proportions and

the measured chloride contents of each of the constituents, or from compacted fresh or hardened concrete.

15.2 Sulphate content 15.2.1The total water-soluble sulphate content of the concrete mix shall not exceed 4%

SO3 by mass of the cement in the mix.

15.2.2The sulphate content shall be determined as the total measured either from the

various constituents of the mix, or from compacted fresh or hardened concrete.

16.0 ENTRAINED AIR IN FRESH COMPACTED CONCRETE 16.1 The average air content by volume of the fresh concrete at the time of placing shall

not exceed 5% 17.0 TESTING REQUIRMENTS

17.1 General

17.1.1 The contractor shall allow for and be responsible for carrying out all sampling

and testing required by these specifications. He shall arrange for copies of test results to be supplied direct to the Owner / Engineering Consultant immediately they become available.

17.1.2 The contractor will not be reimbursed for any special tests called for by the

Owner / Engineering Consultant in consequence of any failure by the contractor to

comply with these specifications 17.1.3 All tests and checks on site shall be carried out in the presence of or as directed

by the Owner / Engineering Consultant 17.1.4 For all cement and reinforcement delivered to the site, the contractor shall obtain

and keep on the site a copy of the manufacturer’s certificate of tests carried out at the frequency and using the methods specified in the relevant British Standards or equivalent Singapore standards. For reinforcement this shall include the rebend

tests and shall be accompanied by details of manufacturer’s identification marks rolled into each brand of bar supplied.

17.2 Testing facilities 17.2.1 Before concreting commences, the contractor shall engage a testing agency

approved by the Owner / Engineering consultant. The approved agency shall be

responsible for the proper conduct of all laboratory tests required by these specifications

17.2.2 In case of ready mixed concrete, the apparatus, described in (a) and (b) above may be maintained at the depot of the ready mixed concrete supplier.

Page 83: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 82

18.0 TESTING AGGREGATES 18.1 General

18.1.1 Samples of the fine and coarse aggregates approved by the Owner / Engineering Consultant shall be kept on the site and shall give a fair indication of the approved quality of the aggregates for comparison with the aggregate delivered during the

course of the works. 18.1.2 Should a sample fail to comply with any of the tests, the Owner / Engineering

Consultant may at his own discretion reject the batch from which the sample was taken, or order it to be washed and/or screened, or permit such to be used with variations in the proportions of the concrete mixes specified, all at the contractors

expense. Any batch of aggregate rejected by the Owner / Engineering Consultant shall be removed from the site forthwith and replaced entirely at the contractor’s expense

18.2 Preliminary aggregate tests 18.2.1 As soon as the sources of supply of aggregate have been approved, the

contractor shall instruct the testing agency to carry out the following tests for

compliance Indian codes

(a) Sieve analysis

(b) Tests for clay, silt and dist content

(c) Tests for organic impurities

(d) Tests for salt content (chloride and sulphate ions)

18.2.2The results of these tests shall be submitted for approval as son available

18.3 Tests sampling of Aggregates 18.3.1 The contractor shall carry out such tests on aggregate samples as are necessary

for the production of the specified concrete. The minimum incremental frequency of

tests on each type of aggregate used for the works shall be mutually agreed by the Owner / Engineering consultant and contractor.

18.3.2 If for any reason the Owner / Engineering Consultant is not satisfied with the work concrete, he may instruct the contractor to further increase the rate of sampling. Conversely, the rate of sampling may be reduced by the Owner /

Engineering Consultant when consistent high quality has been well established. 19.0 TESTING OF WORKS CONCRETE

19.1 General 19.1.1 All sampling, curing and testing of the concrete in the fresh and hardened state

shall be carried out in accordance with SS78

19.2 TEST SAMPLING 19.2.1The rate of sampling of each grade of concrete for testing shall mean the

incremental volume of concrete in cubic meters from which, on the average, one sample shall be taken.

19.2.2 For the analysis of Fresh concrete: the minimum sampling rate of freshly mixed concrete for analysis shall be one sample for every 500 m³ of concrete placed unless otherwise directed by the Owner / Engineering Consultant.

Page 84: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 83

19.2.3 if for any reason the Owner / Engineering Consultant is not satisfied with the works concrete, he may instruct the contractor to further increase the rate of

sampling. Conversely, the rate of sampling may be reduced by the Owner / Engineering Consultant when consistent high quality has been well established.

19.2.4 The samples shall be taken at the point of discharge from the mixer, or in the case of ready mixed concrete, at the point of discharge from the vehicle or the point of casting as directed by the Owner / Engineering Consultant.

19.3 Workability 19.3.1 The required workability for any part of the work shall be determined by the

contractor, subject to agreement by the Owner / Engineering Consultant. The mix design shall ensure that this workability is achievable

19.3.2 Test samples shall be taken at the rates specified in the sub-section headed ‘Test Sampling’ in this specification. Concrete workability shall check by means of a slump test. The slumps shall be within + 25 mm of the required value. If the

slump is not within these limits, or if the slump tests show likelihood of segregation, the Owner / Engineering Consultant will reject the mix.

19.4 Temperature of fresh concrete 19.4.1 Within 2 minutes of taking the sampling, a type A 100 mm immersion thermometer

having a range of – 5 degrees C to +110 degrees C, graduated at each 1 degree C

shall be inserted in the sample to a depth of at least 100 mm. When steady conditions have been maintained for 1 minute, the temperature shall be recorder to the nearest 1 degree C.

19.5 Analysis of Fresh concrete 19.5.1Test samples shall be taken at the discretion of the Owner / Engineering

Consultant either at the point of delivery or the concrete batching depot. 19.5.2 In the case of ready mixed concrete, the Owner / Engineering Consultant or his

representative shall have unrestricted access to the concrete supplier’s batching plant(s) whenever concrete is being produced for the project and shall be provided with the facility to inspect and take fresh samples for analysis.

19.6 Tests for the Assessment of Compressive Strength

19.6.1The minimum number of test specimens (concrete cubes) to be prepared from each sample

and the regime of curing prior to testing shall be as follows: Material Type

Minimum

Number of Specimens

Pre-Test Curing Period (days)

5d 7d 28d

Reinforced Concrete 4 - 2 2

Prestressed Concrete 6 2 2 2

19.6.2 On completion of the curing, the specimens shall be tested and the average

strength of two specimens shall be taken as the individual test result to judge compliance in accordance with the sub-section headed ‘compliance with characteristic compressive strength’ in this specification

Page 85: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 84

19.6.3 In the case of prestressed concrete, the specimens reserved for the 5 days test may with the consent of the Owner / Engineering Consultant, be crushed at an

agreed date after mixing to verify compliance with the specified transfer strength of the concrete.

20.0 Dimensions of completed work 20.1 The contractor shall keep records in an approved form of the dimensions of all

work as constructed. These records shall be available for inspection at any time

and shall be submitted immediately after completion of each section as directed. 21.0 Maximum allowable deviation of structural works

21.1.1 Owner / Engineering Consultant tolerances for concrete finish

21.1.1.1 Tolerances specified under this section shall be checked against the tolerances

for surface finish of structural members specified by the Owner / Engineering

consultant. The contractor shall follow the more stringent of the two requirements in the construction of the works.

21.1.2 Reference Grids

ON PLAN

21.1.2.1 At every structural level the contractor shall set out a horizontal reference grid

as detailed on the Owner / Engineering consultant’s drawings or offset from them

and in a form agreed with the Owner / Engineering consultant. 21.1.2.2 The dimensions between intersections of the reference grids shall be within + 5

mm of dimensions given or computed from the drawings

21.1.2.3 The reference grid at each level shall be:

(a) Vertically above the corresponding grid on the level immediately below, with

maximum deviation + 5 mm (b) Vertically above the corresponding grid on the lowest level, with maximum deviation + 10 mm

LEVELS 21.1.2.4 The deviation of height from floor to shall not exceed the following:

(a) Height of structural level above the datum on the level immediately below + 5mm

(b) The height deviation of any structural level from the control bench mark + 10mm

21.1.3 Foundation

21.1.3.1 Maximum deviations of concrete works in foundation shall be as follows:

(a) Position in plan – maximum deviations measured in any horizontal directions from the nearest reference grid line + 25mm

(b) Dimensions on plan- maximum deviation per 300m (except retraining wall thickness which shall be + 5 mm) + 10mm

(c) Maximum deviation in any horizontal dimension of a structure (except for retaining wall thickness which shall be + 5 mm) + 25mm

Page 86: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 85

(d) The deviation of the level of foundation surface from nearest transferred bench mark + 20mm

21.1.4 Elements or components above foundations

21.1.4.1 Maximum deviation in plan of any point measured from the nearest reference

grid line

(a) Maximum deviation in plan of any point measured from the nearest reference grid line

+ 10mm

(b) Maximum deviation in verticality plumpness in height of:

Up to and including 0.5 m + 3mm Over 0.5m up to and including 1.5m + 5mm

Over 1.5m up to and including 15m + 10mm Over 15m up to and including 150 m Over 150 m

21.1.4.2 Notwithstanding the dimension tolerance motioned above, the contractor shall

take all measures to ensure that all walls of lifts shafts are not more than 12 mm

out of verticality at any point between the top to bottom from the entire height. Failure of the contractor to maintain the required tolerance will render him liable for all rectification work that may be required by the Owner / Engineering consultant

and/or the lift sub-contractor (a) Cross section, linear dimensions and openings.

Maximum deviations from dimensions of beams slabs, columns and walls Up to and including 300mm Over 300mm up to and including 600mm

Over 600mm up to including 1.5m Over 1.5m

21.1.5 Bow or camber (other than designed camber0 21.1.5.1 Maximum deviation of any point of the surface from a straight line joining the

extremities of the surface: (a) Up to and including 3m apart (b) Over 3m up to and including 9m apart

(c) Over 9m apart 21.1.6 Twist

21.1.6.1 Maximum deviation of any one corner from the place containing the other 3 corners:

(a) For diagonal up to and including 3 m

(b) For diagonal over 3 m up to and including 8m (c) For diagonal over 8 m

21.1.7 Squareness of Corner 21.1.7.1 The longer of the two adjacent sides should be4 taken as the base line and the

maximum deviation of the shorter side from a perpendicular to the base line is toe be related to the length of the shorter side:

(a) Short side up to and including 0.5 m + 5mm

(b) Over 0.5m up to and including 2 m + 15mm

Page 87: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 86

(c) Over 2m + 20mm (max)

21.1.8 Level 21.1.8.1 Maximum deviation from the designed level with reference to the nearest

transferred bench mark (a) Length up to and including 8 m + 5mm (b) Over 8m up to and including 15 m + 15mm

(c) Over 15 m + 20mm (max) 21.1.9 Windows

The foregoing permissible deviations exclude the specific tolerance for tower

windows and floor levels, which shall be as follows

The required structural openings of the tower windows are indicated on the relative

drawings. Tolerances both vertically and horizontally, including any in-build camber and subsequent deflection is restricted to +5 mm per side as measured from the center

line of the opening. Sides, soffit and sill of openings shall be true both vertically and horizontally.

This tolerance is not progressive over the height of the tower. Hacking of undersized opening will only be permitted with the approval of the Owner / Engineering consultant in writing

21.1.10 Floor levels

The structural level on any one tower is to be + 3 mm. However, the contractor’s

attention is drawn to the under floor ducting and especially to the junction boxes where there is no tolerance

21.2 Survey of verticality

21.2.1 The contractor is to employ the same independent licensed surveyor responsible for setting the reference points to check the vertical alignment of all core walls and columns at each third floor height of the building immediately that level is

constructed. 21.2.2 The contractor shall submit the survey results to the Owner / Engineering

consultant within seven days from the date of completion of the site survey. 22.0 DEFECTIVE WORK

22.1 Where in the opinion of the Owner / Engineering Consultant any of the finished

works, of the materials or workmanship in any part of the works, do not comply with all the relevant requirements of these specifications, that part of the works shall be classified as defective work

22.2 All work classified, as defective work shall be cut out and removed from the works

and replaced to the satisfaction of the Owner / Engineering Consultant.

22.3 The extent of the work to be removed and the methods to be used in the removal

and replacement of this work shall be in accordance with Owner / Engineering

Consultant’s directions. In all cases, cutting out of defective concrete work shall be

Page 88: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 87

carried back to a satisfactory construction joint before the replacement of the defective work and any other work thereby affected is commenced.

22.4 All removal and replacement of defective work and all coasts or charges arising

from such removal of replacement shall be at the contractor’s expense and no

extension of time will be allowed on this account. 23.0 LABOUR

23.1 The description of each item of all types of concrete beds and slabs will be held to

include for laying on any type of sub-base and for preparing and leaving surfaces of concrete to receive screeds or paving.

23.2 The description of each item of all types of concrete will be held to include for cutting and/or forming grooves, chases, rebates, mortices, hoes and making good and any other sundry item of a like a nature.

23.3 The description of each item of all types of concrete will be held to include for all

construction joints, other than those shown on the shown on the drawings.

23.4 The description of each item of all types of concrete will be held to include for all

moulds, handling, lifting, hoisting and building in.

23.5 The description of each item of reinforcement will be held to include for binding

reinforcement and spacers, for cutting to lengths and forming bends, cranks, etc.

The weight of all reinforcement is exclusive of rolling margin. 23.6 The description of each item of formwork will be held to include for erection, raking

and/or circular cutting, spayed edges notchings, allowance for overlaps and waster, passing at angles, battens filleting to form chamfered edges not exceeding 50 mm wide, strutting (including strutting exceeding 3.50 m high to walls columns

etc.) bolting wedging, easing striking and removal and for all modification, re-erection easing striking etc and removal for further use

Page 89: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 88

HAND BOOK ON HEALTH AND SAFETY AT

WORK FOR

CONTRACTORS WORKING IN THE PROJECT

Page 90: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 89

TABLE OF CONTENTS

SECTION

1. INTRODUCTION

2. RULES FOR GENERAL OPERATIONS

2.1 Access

2.2 Accident Reporting

2.3 Contractors & Sub-Contractors Tools & Equipments.

2.4 Hazardous Materials

2.5 Dust and Fume Control

2.6 Fire Hazards and Precaution

2.7 Machinery Safety

2.8 House-keeping / Hygiene

2.9 Noise

2.10 Overhead Working

2.11 Working at Height

2.12 Safety Clothes and Equipment

2.13 Plant Services

2.14 Supervision

2.15 Warning signs and Notices

3. TOOLS

3.1 Electrically Driven Portable Tools

3.2 Compressed Air Tools

3.3 Percussion Cartridge Tools

3.4 Hoisting and Lifting.

3.5 Movement of Plant and Equipment

3.6 Industrial Trucks

4. CONTRACTORS GUIDELINES.

5. MODEL RULES FOR THE PROTECTION OF HEALTH AND SANITARY.

6. ISI SAFETY CODE.

7. LABOUR LAWS

Page 91: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 90

SECTION – 1

INTRODUCTION:

This document defines the operations undertaken by Contractors and sub-Contractors on

Project premises, which can give rise to hazards to those engaged in the work and others who may be working, standing or passing in the vicinity.

It is the Owner's endeavour to secure a high standard of safety at site. Therefore, Contractors and sub-Contractors must know their duties under common law, both for establishments, and their own employees and to conduct their business and methods of

work to conform to the best practices. Before the Owner, allows any contracting or sub- contracting firm to carry out work on its

premises, the Owner insists that Contractors and sub-Contractors understand their duties regarding safe practices for themselves, others and regulations covering the type of work they will be carrying out.

In furtherance to this policy, rules herein have been devised to bring to the notice of Contractors and sub-Contractors, some of the more common hazards, and appropriate

preventive measures in connection with the erection, construction, cleaning, painting, alteration or demolition of plant, machinery and buildings.

The Owner, is confident that the observance of these rules will be no hindrance to progress the work, but will assist in the avoidance of accidents.

IT IS IN A TERM OF ALL CONTRACTS BETWEEN THE CLIENT AND CONTRACTORS THAT THEY AND ANY SUB-CONTRACTORS, APPOINTED BY THEM COMPLY WITH THESE RULES AND THEIR CO-OPERATION IS THEREFORE OBLIGATORY IN

CARRYING OUT THE PRECAUTIONS LAID DOWN. Section - 2: Details general rules which are applicable to most Contractors and

sub-Contractors. Section - 3: Details specific rules which must be followed where applicable, where a

particular type of work is to be undertaken. All Contractors Supervisors will make sure that the Engineering Services / Safety Manager

on Project site are notified as and when he and others (Sub-Contractors) are reporting for work on that site.

Page 92: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 91

SECTION - 2 RULES FOR GENERAL OPERATIONS:

2.1 ACCESS : Nothing shall be done or omitted to be done by Contractors or Sub-Contractors or their

employees to render unsafe or obstruct: - Any means of access to the places at which people are required to work.

- The passage of people and / or vehicles whether on a defined gangway or

not, unless permission is obtained from the designated safety officer.

- Access for emergency apparatus, such as fire fighting equipment.

- Contractors and sub-Contractors shall nevertheless provide adequate fencing, lighting and warning signs to ensure safety at all times.

2.2 ACCIDENT AND INCIDENT REPORTING: All notifiable accidents, dangerous occurrences and potential hazard situations shall

be reported to the safety officer at site.

Injuries are to be treated by experienced medical staff available at site.

2.3 CONTRACTORS AND SUB-CONTRACTORS' TOOLS AND EQUIPMENTS: All Contractors and sub-Contractors tools and equipments must comply with

statutory regulations and approved codes of practices.

2.4 HAZARDOUS MATERIALS: The Contractor must inform the safety officer, prior to commencement of work,

procurement of materials connected with the contract work of a hazardous nature. The Contractor will have to secure storage for any such material.

2.5 DUST AND FUME CONTROL: Contractors and sub-Contractors must inform the safety officer at the Project site of

all processes producing dust or fumes, and under the conditions as laid down in the

relevant Act of Government the safety precautions are to be fulfilled. 2.6 FIRE HAZARDS AND PRECAUTIONS:

When at site, all fire regulations, as well as regulations under relevant Sections of the relevant Act of Government of must be observed at all times.

2.7 MACHINERY SAFETY: Contractors and sub-Contractors working at the Project site must not remove or

displace any guard, fencing or other safety equipment which is designed to protect

personnel or machinery or any place where safety equipment has been provided without the written permission of the safety officer or his designated representative.

On completion of any work, any guards that had to be removed must be replaced

immediately and whilst work is being carried out, machinery must not be operated. The requirement of the relevant Act must be followed:

Page 93: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 92

2.8. HOUSE-KEEPING:

The House-keeping standards employed by Contractors and sub-Contractors, must be as good as the Owner. Care must be taken by all responsible people to ensure that the standard of house-keeping for all establishments is known and understood.

2.8.1 Housekeeping and hygiene go hand in hand with safe working practices.

Contractors and sub-Contractors must leave work areas in a clean, tidy and safe

condition at the end of each working period. 2.8.2 Special attention must be paid to potential fire hazards, trip points and equipment

left in a hazardous condition. 2.8.3 Contamination of any product (by drill swarf sawdust, oil, salient, paints and

materials etc.) must be avoided at all costs, and the officers of the Owner are empowered to stop any activity which could result in contamination.

2.9. NOISE: Contractors and sub-Contractors working at the Project site must obtain permission

from the safety officer if the processes being employed to carry out that work

significantly increase the ambient noise level in that area being worked. 2.10. OVERHEAD WORKING:

No work may be carried out above the heads of people or over gangways or roads, until all precautions have been taken to ensure the safety of the persons below, and until permission is given by the safety officer. Each specific site of overhead working

will require consent from the safety officer. This will be given after satisfactory inspection.

Work may be carried out in the vicinity of power cables only when permission is obtained from the safety officer and/or Owner Project Engineer.

Work connected with overhead safety includes the movement of long metal objects, machinery, jibs, masts, arms or other elevated parts.

2.11 WORKING AT HEIGHT: All temporary structure, erected by Contractors or sub-Contractors for the purpose of

allowing their staff to work at heights of more than 2 M. above floor level, must be

constructed in accordance with the Safety Regulations laid down. Whenever possible, ladders are to be made of wood and in good condition. Metal

ladders must not be used where there is any possibility of the ladder coming into contact with an electrical conductor.

Roof working must be properly supervised. 2.12 SAFETY CLOTHES AND EQUIPMENT:

This will be supplied by Contractors and sub-Contractors who are working on sites and must be adequate for the well being of their staff engaged in the type of work contracted for.

Page 94: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 93

The equipment and its use must comply with the regulations and codes of practice as laid down, that apply to the conditions of work being undertaken.

Contractors and sub-Contractors will be responsible for the use of any tools and

equipment that is supplied by them, or their staff to the exclusion of all responsibility

of the Owner. Tools will be maintained to the highest standard of safety. Whilst in the possession of such tools, the person so using said tools is responsible for the continued maintenance of safety standards.

It is the individual's responsibility to ensure that the tools he works with are suitable

for the job, and in a safe condition prior to work commencement. All necessary tools

and equipment to complete a contract should be supplied by the Contractor. Due provision must be made during contract preparation.

2.13 PLANT SERVICES: Before using plant services such as electricity, permission to do so must be obtained

from the appropriate authority, from Owner and water, necessary (TICEL). 2.14 SUPERVISION:

Contractors working at the Project site, must ensure that their staffs are adequately

supervised.

2.15 WARNING SIGNS AND NOTICES:

Suitable warning signs are to be displayed warning of potential hazards.

SECTION – 3

TOOLS

3.1ELECTRICALLY DRIVEN PORTABLE TOOLS:

Permission is to be obtained from the nominated person before any Contractor or

sub-Contractor's electrical hand tools can be connected to the electricity supply. Connection must be by 3-core and 3-pin plugs and sockets, except when tools are

double insulated on a 2-wire supply. Where the supply is 3-phase, 4-core cable and 4-pin plugs and sockets with earth connections must be used.

Make-shift connections are prohibited. The use of extension cables is discouraged, but sometimes necessary.

Portable electric lamps must be the 'Gripper' type with caged wire protection for the bulk and precautions as laid down under relevant section of the relevant Act of Government

must be observed. In all cases, with the exception of double insulated tools, the metal work of the tools

must be effectively earthed, also any flexible metallic cable coverings must be earthed.

Page 95: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 94

3.2 COMPRESSED AIR TOOLS

Contractors and sub-Contractors must obtain permission to use any compressed air supply at the Project site.

Contractors and sub-Contractors must also provide suitable noise suppression for pneumatic hammers, drills etc.

3.3PERCUSSION CARTRIDGE TOOLS

Permission to use percussion tools must be obtained from the designated safety

representative prior to the use of these tools. Also when using percussion tools, it is the individuals duty to ensure that the charges

used in said tools are correct. These tools are to be handled as dangerous weapons, never leave tools unattended, never leave tools charged or store charged, never point tools at personnel, always lock up when finished both tool and charges.

3.4 HOISTING AND LIFTING:

Permission must be obtained prior to the use of Plant and equipment, from the Owner Project Engineer or other nominated responsible person.

Equipment must be adequate for the purpose required and anchorage approved by the site safety officer.

All equipment so used must have been examined by a competent person, and where necessary a certificate obtained in accordance with relevant sections of the relevant Act of Government.

No object is to be left unattended whilst using lifting equipment.

3.5 MOVEMENT OF PLANT AND MACHINERY Permission must be obtained prior to the movement of construction materials, plant or

equipment in and around Project site. 3.6 POWERED INDUSTRIAL TRUCKS

Permission must be obtained prior to the use of lift-trucks by Contractors or sub-Contractors at the Project site.Trucks must only be driven by competent licensed

personnel, and must comply with statutory regulations.

Page 96: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 95

SECTION – 4

CONTRACTORS AND SUB-CONTRACTORS GUIDELINES 1. Safe working practices must be observed at all times.

2. It is the responsibility of the Contractors and sub-Contractors staff to use appropriate

personal protection. It is the Contractors and sub-Contractors obligation to supply

necessary protective equipment and clothing. 3. Certain areas are designated hazardous (eg. noisy areas) and warning signs must

be obeyed. 4. Where the Contractors and sub-Contractors work presents a potential hazard,

appropriate notices must be supplied and displayed, and the area made secure as far as is reasonably possible.

5. The Owner will not provide tools, materials, lifting or access equipment, fixings or raw materials, unless by previous arrangement.

6. Any equipment brought to site by Contractors and sub-Contractors must not be used by untrained persons, and attention is drawn to the indemnity clause of the Owner orders, which states that the Contractor is liable for any consequent damage or loss

to people, equipment or buildings. 7. All welding, burning and grinding operations which could potentially cause fire must

be reported to security. 8. No alcohol is permitted at site, and anyone deemed to be under the influence of

alcohol will be required to leave the site. 9. Vehicle parking will be in designated areas only.

10. No smoking is allowed in work areas.

11. No food is to be consumed or left in work areas. 12. Warning signs and speed restrictions must be observed.

13. Place of work to be left in a tidy and safe condition at the end of each work period.

14. Care to be taken against contamination of any product of paint, oil, etc. 15. All injuries must be reported to the authorities as per law applicable.

16. A health and safety officer shall be employed on such conditions as circumstances

require.

The above has been received and read by Contractor / Sub-Contractor, we agree to comply with these Rules (See foot-note)

Page 97: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 96

Contractors .....................................

Company....................................

Date .........................................

NOTE : The Contractor will ensure that sub-Contractor receive and sign a copy of these Rules.

MODEL RULES FOR THE PROTECTION OF HEALTH AND SANITARY ARRANGEMENTS FOR WORKERS EMPLOYED BY CONTRACTORS

1. FIRST-AID-FACILITIES 1.01 The labour shed should be away from TICEL. Inside staging is not permitted At every

work place there shall be provided and maintained, so as to be easily accessible during working hours, first-aid boxes at the rate of not less than one box for 150 labourers or part thereof ordinary employed.

1.02 The first-aid box shall be distinctly marked with a red cross on white back ground and

shall contain the following equipment, :-

1.02.01 For work places in which the number of labour employed does not exceed

50, each first-aid box shall contain the following equipments:-

6 small sterilized dressings

3 medium size sterilized dressings

3 large size sterilized dressings

3 large size sterilised burn dressings

1 (30 ml.) bottle containing a two per cent alcoholic solution of iodine.

1 (30ml.) bottle containing salvolatile having the dose and mode of administration indicated on the label.

1 snakebite lancet

1 (30gms.) bottle of potassium permanganate crystals

1 pair scissors

1 copy of the first-aid leaflet issued by the Director General, Factory Advice Service and Labour Institutes, Government of India.

1 bottle containing 100 tablets (each of 5gms.) of aspirin.

Ointment for burns

A bottle of suitable surgical antiseptic solution

1.02.02 For work places in which the number of labour exceed 50. Each first-aid box shall contain the following equipments.

12 small sterilised dressings

6 medium size sterlised dressings

6 large size sterilised dressings

6 large size sterilised burn dressings

6 (15 gms.) packets sterilised cotton wool

Page 98: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 97

1 (60 ml.) bottle containing a two per cent alcoholic solution of iodine.

1 (60 ml.) bottle containing salvolatile having the dose and mode of administration indicated on the label.

1 roll of adhesive plaster

1 snakebite lancet

1 (30 gms.) bottle of potassium permanganate crystals

1 pair scissors

1 copy of the first-aid leaflet issued by the Director General, Factory Advice Service and Labour Institutes / Government of India.

A bottle containing 100 tablets (each of 5 gms.) of aspirin.

Ointment for burns

A bottle of suitable surgical antiseptic solution 1.03 Adequate arrangements shall be made for immediate recoupment of the equipment

when necessary. 1.04 Nothing except the prescribed contents shall be kept in the First-aid box.

1.05 The first-aid box shall be kept in charge of a responsible person who shall always be

readily available during the working hours of the work place.

1.06 A person in charge of the First-aid box shall be a person trained in First-aid treatment,

in the work places where the number of contract labour employed is 150 or more.

1.07 In work places where the number of contract labour employed is 750 or more and

hospital facilities are not available within easy distance from the works. First-aid posts

shall be established and run by a trained Compounder. The Compounder shall be on duty and shall be available at all hours when the workers are at work.

1.08 Where work places are situated in places which are not towns or cities, a suitable motor transport shall be kept readily available to carry injured person or person suddenly taken ill to the nearest hospital.

2.00 DRINKING WATER 2.01 In every work place, there shall be provided and maintained at suitable places, easily

accessible to labour, a sufficient supply of water fit for drinking. 2.02 Where drinking water is obtained from an intermittent public water supply, each work

place shall be provided with storage where such drinking water shall be stored. 2.03 Every water supply or storage shall be at a distance of not less than 50 feet from any

latrine drain or other source of pollution. Where water has to be drawn from an existing well which is within such proximity of latrine, drain or any other source of pollution, the well shall be properly chlorinated before water is drawn form it for

drinking. All such wells shall be entirely closed in and be provided with a trap door which shall be dust and waterproof.

2.04 A reliable pump shall be fitted to each covered well, the trap door shall be kept locked and opened only for cleaning or inspection which shall be done at least once a month.

3.0 WASHING FACILITIES 3.01 In every work place adequate and suitable facilities for washing shall be provided and

maintained for the use of labour employed and supervisory staff separately therein.

Page 99: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 98

3.02 Separate and adequate cleaning facilities shall be provided for the use of male and

female labourers and supervisory staff. 3.03 Such facilities shall be conveniently accessible and shall be kept in clean and hygienic

condition. 4.0 LATRINE AND URINALS

4.01 Latrines shall be provided in every work place on the following scale namely:-

4.01.01 Where females are employed there shall be at least one latrine for every 25

females. 4.01.02 Where males are employed, there shall be atleast one latrine for every 25 males.

Provided that where the number of males or females exceeds 100, it shall be sufficient if there is one latrine for 25 males or females as the case may be upto the

first 100, and one for every 50 thereafter.

4.02 Every latrine shall be under cover and so partitioned off as to secure privacy, and shall

have a proper door and fastenings. 4.03 Construction of latrines: the inside walls shall be constructed of masonry or some

suitable heat-resisting nonabsorbent materials and shall be cement washed inside and outside. Standard sanitary fixtures & fittings shall be provided.

4.04.01 Where workers of both sexes are employed, there shall be displayed outside each block of latrine and urinal, a notice in the language understood by the majority of the workers ”For Men only” or “For Women only” as the case may be.

4.04.02 The notice shall also bear the figure of a man or of a woman, as the case may be.

4.05 There shall be atleast one urinal for male workers upto 50 and one for female workers upto fifty employed at a time, provided where the number of male or female workmen, as the case may be exceeds 500, it shall be sufficient if there is one urinal for every 50

males or females upto the first 500 and one for every 100 or part thereafter. 4.06. a The latrine and urinals shall be adequately lighted and shall be maintained in a

clean and sanitary condition at all times.

b. Latrine and urinals other than those connected with a flush sewage system shall

comply with the requirements of the Public Health Authorities. 4.07 Water shall be provided by means of tap or otherwise so as to be conveniently

accessible in or near the latrine and urinals. 4.08 Disposal of excreta shall be arranged either by connection to a municipal sewer with

permission from the local sanitary authority, or by providing connection to a covered soak pit.

4.09 The contractor shall at his own expense, carry out all instructions issued to him by the Owner/ Engineering Consultant to effect proper disposal of night soil and other

Page 100: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 99

conservancy work in respect of the contractor’s workmen or employees on the site. The contractor shall be responsible for payment of any charges which may be levied

by Statutory Authority for execution of such on his behalf. PROVISION OF SHELTER DURING REST

At every place there shall be provided, free of cost, four suitable sheds, two for males and the other two for rest separately for the use of men and women labour. The height of each shelter shall not be less than 3 metres from the floor level to the lowest part of the

roof. These shall be kept clean and the space provided shall be on the basis of 0.6 sq.m per head.

Provided that the Owner / Engineering Consultant may permit subject to his satisfaction, a portion of the building under construction or other alternative accommodation to be used for the purpose.

CRECHES

At every work place, at which 20 or more women worker are ordinarily employed; there

shall be provided two rooms of reasonable dimensions for the use of their children under at the age of six years. One room shall be used as a play room for the children and the other as their bedroom. The rooms shall be constructed with painted masonry walls with light

weight roofing. The rooms shall be provided with suitable and sufficient openings for light and ventilation.

There shall be adequate provision of sweepers to keep the places clean. The contractor shall supply adequate number of toys and games in the play room.

The contractor shall provide one ayah to look after the children in the crèche when the number of women workers does not exceed 50 and two when the number of women workers exceeds 50.

The use of the rooms earmarked as crèches shall be restricted to children, their attendants and mothers of the children.

CANTEENS In every work place where the work regarding the employment of labour is likely to continue for six months and where in contract labour numbering one hundred or more is ordinarily

employed, an adequate canteen shall be provided by the contractor for the use of such labour.

The canteen shall be maintained by the contractor in an efficient manner.

The canteen shall consist of at least a dining hall, kitchen, pantry and washing places

separately for workers and utensils.

The canteen shall be sufficiently lighted at all times when any person has access to it.

The floor shall be made of smooth and impervious materials and inside walls shall be lime-washed or colour washed.

The premises of the canteen shall be maintained in a clean and sanitary condition.

Waste water shall be carried away in suitable covered drains and shall not be allowed to accumulate so as to cause a nuisance.

Page 101: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 100

Suitable arrangements shall be made for the collection and disposal of garbage.

The floor area of the dining hall shall be suitably provided with furniture.

Sufficient tables, stools, chair or benches shall be available for the number of diners to be accommodated.

There shall be provided and maintained sufficient utensils crockery, furniture and any other equipment’s necessary for the efficient running of the canteen.

The furniture utensils and other equipment shall be maintained in a clean and hygienic condition.

Suitable clean clothes for the employees serving in the canteen shall be provided and maintained.

A service counter, if provided, shall have top of smooth and impervious material. Suitable facilities including an adequate supply of hot water shall be provided for the

cleaning of utensils and equipments. The food stuffs and other items to be served in the canteen shall be in conformity with the

normal habits of the contract labour. The charges for food stuffs, beverages and any other items served in the canteen shall be

based on ‘No Profit, No Loss’ and shall be conspicuously displayed in the canteen.

In arriving at the price of foodstuffs, and other article served in the canteen, the following

items shall not be taken into consideration as expenditure namely:- The depreciation and maintenance charges for the building and equipments provided for

the canteen. The cost of purchase, repairs and replacement of equipments including furniture, crockery,

cutlery and utensils. The water charges and other charges incurred for lighting and ventilation.

The interest and amounts spent on the provision and maintenance of equipments provided for the canteen.

5.0 Minimum Safety Requirements (To be made a part of TENDER conditions and BOQ of works related package to address the inclusion of PPE, Scaffold, Electrical safety measures, Housekeeping as a minimum)

Prior to commencing work on Site, the Contractor must make himself aware of all the

requirements for the Works and the Site relating to Environment, Health & Safety (EH&S) matters including all relevant legislation and standard codes of practice.

Contractor shall comply with all the EH&S Requirements listed below which shall be deemed a fundamental condition of this Contract.

Page 102: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 101

Contractor must comply in full with all applicable Health & Safety (H&S) local and national legislation. (e. g. Labour Licence, Insurance Policy under Workmen Compensation Act,

etc.)

In circumstances where there is a conflict between local or national legislation and these Minimum Safety Requirements (MSR), the higher (more protective) requirement shall prevail.

Guardrails are to be provided at all working places and other locations where persons or materials could fall more than 2.0m / 6'6". Where this can physically not be achieved,

suitable and sufficient fall protection devices that do not rely on individuals should be provided and used to establish a safe place of work. (Examples include Safety Nets closely installed under height works, Stretched wire ropes installed to hook up safety

harnesses while workers move from one location to another at height, Use of full body safety harnesses with double lanyards etc.)

Full body harness with double lanyard Proper Access to work

platform

All persons working on suspended scaffolds/cradles/gondolas must wear and use appropriate fall prevention equipment so as to protect them effectively at all times when they are at risk from any failure of any part of the scaffold/cradle/gondola, including its

suspension system. Free-standing scaffold towers used externally must not be higher to the top platform level

than three times the minimum base dimension, unless secured to a permanent structure. For internal use only, the height to platform may rise to 3.5 times the minimum base dimension. Wheels must be locked when towers are in use. No person is permitted to

remain on a tower platform while a tower is being moved.

Page 103: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 102

Mobile Scaffolds

Holes, shafts and edges from or through which persons could fall a distance of more than 2 metre /6ft 6in must be clearly marked with signage or other means and be adequately

protected by covers or barriers so as to prevent falls of persons and materials.

Holes, Shafts, Floor Penetrations

All temporary electrical circuits must include a Residual Current Device, Earth Leakage Circuit Breaker or Ground Fault Circuit Interrupter at source.

Temporary Electrical System

Powered Lifts and hoists, aerial platforms and scissors lifts must have a competent driver, certified by a qualified third party. Additionally, the above items must be certified as safe to use by a local government approved third party.

Adequate lighting must be provided to enable safe access to and egress from every place on a site where persons are liable to work, this is in addition to task lighting.

Induction/Orientation

All workers shall receive site-specific safety induction/orientation, before they are involved in any activity at site. They must be made aware of site safety rules, provisions of first aid and welfare facilities such as drinking water, washing place, toilets, rest rooms,

etc.

Page 104: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 103

Task related Safety Instruction Contractor shall ensure all workers shall receive at least one specific task-related

training/skilling session per week. This may be achieved by using Toolbox talks &/or induction to Safe Work Method Statement.

Incident/Injury Reporting & Investigation Contractor shall report and record all incidents, which have potential to cause injuries

and damages and also injuries including first aid cases.

Lost Time Injury (LTI) or serious injury must be intimated immediately as soon as

possible by phone. (If an injured person doesn’t likely to report to work in his next

following shift, it is to be recorded as Lost Time Injury)

Job Safety Analysis & Safe Work Method Statement

Contractor must produce detailed Job Safety Analysis / Safe method of work for approval and use only approved work methods only. No work shall start without approved Job Safety Analysis / Safe Work Method Statement. All workers and supervisors must be

inducted to Job Safety Analysis / Safe method of work.

(iii) Oxygen / Acetylene / Fuel Gases/ Compressed or Liquefied Gases

(a) All gas cylinders shall be stored, transported and handled as per the requirements of Gas Cylinder Rules, 198.

Indian Standard Safety Codes to be followed by the Contractor during execution of work

S.No

IS No Part

No./Year Description

1. IS 3696 1 – 1987 Safety code for scaffold and ladders

2. IS 3996 2 – 1991 Safety code for ladders

3. IS 4014 2 – 1967 Code of practice for steel tubular scaffolding

4. IS 4081 1986 Safety code for blasting and related drilling

operations

5. IS 4082 1977 Recommendation on stacking and storage

materials at site (1st Revision)

6. IS 4130 1991 Safety code for demolition of buildings 2nd revision

7. IS 4138 1977 Safety code for working in compressed air

8. IS 4756 1978 Safety code for funneling work

9. IS 4912 1978 Safety requirements for floor and wall openings,

railing and toe boards

10. IS 5121 1990 Safety code for piling and other deep foundations

11. IS 5916 1990 Safety code for constructions involving use of hot

bituminous material

12. IS 7272 1974 Recommendation for labour output constants for building work

13. IS 7293 1987 Safety code for working with construction machinery

14. IS 7969 1975 Safety code for handling and storage of building

materials with amendment No.1

Page 105: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 104

15. IS 8989 1978 Safety code for erection of concrete framed structures

16. IS 10067 1982 Material constants in building works

17. IS 1029 1990 Safety code for dress divers in civil engineering works

18. IS 10302 1995 Unified nomenclature of workmen for civil

engineering

19. IS 13415 1992 Protective barriers in and around buildings - code

of safety

20. IS 13416 1 – 1992

Preventive measures against hazards at work

places - recommendations falling materials hazards prevention

21. IS 13416 2 – 1992 Preventive measures against hazards at work places - recommendations fall prevention

22. IS 13416 3 – 1994 Preventive measures against hazards at work places - recommendations disposal of debris

23. IS 13416 4 – 1994 Preventive measures against hazards at work places - recommendations timber structures

24. IS 13416 5 – 1994 Preventive measures against hazards at work places - recommendations fire protection

25. IS 13430 1992 Safety during additional construction and alteration to existing buildings - Code of practice.

7. LABOUR LAWS

1. Labour:

The TENDERER shall, unless otherwise provided in the Contract, make his own

arrangements for the engagement of all staff and labour, local or other, and for their

payment, housing, feeding and transport.

The TENDERER shall, if required by the Engineering Consultant, deliver to the

Engineering Consultant a return in detail, in such form and at such intervals as the

Engineering Consultant may prescribe, showing the staff and the numbers of the

several classes of labour from time to time employed by the TENDERER on the Site

and such other information as the Engineering Consultant may require.

2. Compliance with labour regulations:

During continuance of the contract, the TENDERER and his sub TENDERERS shall

a TENDERER at all times by all existing labour enactments and rules made there

under, regulations, notifications and bye laws of the State or Central Government or

local authority and any other labour law (including rules), regulations, bye laws that

may be passed or notification that may be issued under any labour law in future

either by the State or the Central Government or the local authority. Salient features

of some of the major labour laws that are applicable to construction industry are

given below. The TENDERER shall keep the Owner indemnified in case any action

is taken against the Owner by the competent authority on account of contravention

of any of the provisions of any Act or rules made there under, regulations or

Page 106: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 105

notifications including amendments. If the Owner is caused to pay or reimburse,

such amounts as may be necessary to cause or observe, or for non-observance of

the provisions stipulated in the notifications/bye laws/Acts/Rules/regulations

including amendments, if any, on the part of the TENDERER, the Engineering

Consultant / Owner shall have the right to deduct any money due to the TENDERER

including his amount of performance security. The Owner / Engineering Consultant

shall also have right to recover from the TENDERER any sum required or estimated

to be required for making good the loss or damage suffered by the Owner.

The employees of the TENDERER and the Sub-TENDERER in no case shall be

treated as the employees of the Owner at any point of time.

Page 107: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 106

SALIENT FEATURES OF SOME MAJOR LABOUR LAWS APPLICABLE TO ESTABLISHMENTS

ENGAGED IN BUILDING AND OTHER CONSTRUCTION WORK.

a) Workmen Compensation Act 1923: The Act provides for compensation in case of injury by accident arising out of and during the course of employment.

b) Payment of Gratuity Act 1972: Gratuity is payable to an employee under the Act on satisfaction of certain conditions on separation if an employee has completed 5 years

service or more or on death the rate of 15 days wages for every completed year of service. The Act is applicable to all establishments employing 10 or more employees.

c) Employees P.F. and Miscellaneous provision Act 195: The Act Provides for monthly contributions by the owner plus workers @ 10% or 8.33%. The benefits payable under the Act are:

(i) Pension or family pension on retirement or death as the case may be.

(ii) Deposit linked insurance on the death in harness of the worker.

(iii) Payment of P.F. accumulation on retirement/death etc. d) Maternity Benefit Act 1951:- The Act provides for leave and some other benefits to

women employees in case of confinement or miscarriage etc. e) Contract Labour (Regulation & Abolition) Act 1970: The Act provides for certain

welfare measures to be provided by the TENDERER to contract labour and in case the TENDERER fails to provide, the same are required to be provided, by the Principal Owner by Law. The principal Owner is required to take Certificate of Registration and the

TENDERER is required to take license from the designated Officer. The Act is applicable to the establishments or TENDERER of Principal Owner if they employ 20 or more contract labour.

f) Minimum Wages Act 1948: The Owner is supposed to pay not less than the Minimum Wages fixed by appropriate Government as per provisions of the Act if the employment is

a scheduled employment. Construction of Buildings, Roads, Runways are scheduled employment.

g) Payment of Wages Act 1936: It lays down as to by what date the wages are to be paid, when it will be paid and what deductions can be made from the wages of the workers.

h) Equal Remuneration Act 1979: The Act provides for payment of equal wages for work of equal nature to Male and Female workers and for not making discrimination against

Female employees in the matters of transfers, training and promotions etc. i) Payment of Bonus Act 1965: The Act is applicable to all establishments employing 20

or more workmen. The Act provides for payments of annual bonus subject to a minimum of 8.33% of wages and maximum of 20% of wages to employees drawing Rs.3500/- per month. or less. The bonus to be paid to employees getting Rs.2500/- per month or above

upto Rs.3500/- per month. shall be worked out by taking wages as Rs.2500/- per month only. The Act does not apply to certain establishments. The newly set-up establishments are exempted for five years in certain circumstances. Some of the State Governments

have reduced the employment size from 20 to 10 for the purpose of applicability of the Act.

Page 108: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 107

j) Industrial Disputes Act 1947: The Act lays down the machinery and procedure for

resolution of Industrial disputes, in what situations a strike or lock-out becomes illegal and what are the requirements for laying off or retrenching the employees or closing down the establishment.

k) Industrial Employment (Standing Orders) Act 1946: It is applicable to all establishments employing 100 or more workmen (employment size reduced by some of

the States and Central Government to 50). The Act provides for laying down rules governing the conditions of employment by the Owner on matters provided in the Act and get the same certified by the designated Authority.

l) Trade Unions Act 1926: The Act lays down the procedure per registration of trade unions of workmen and owners. The Trade Unions registered under the Act have been

given certain immunities from civil and criminal liabilities. m) Child Labour (Prohibition & Regulation) Act 1986: The Act prohibits employment of

children below 14 years of age in certain occupations and processes and provides for regulations of employment of children in all other occupations and processes. Employment of Child Labour is prohibited in Building and Construction Industry.

n) Inter-State Migrant workmen’s (Regulation of Employment & Conditions of Service) Act 1979 :- The Act is applicable to an establishment which employs 5 or more inter-state

migrant workmen through an intermediary (who has recruited workmen in one state for employment in the establishment situated in another state). The Inter-State migrant workmen, in an establishment to which this Act becomes applicable, are required to be

provided certain facilities such as Housing, Medical-Aid, Travelling expenses from home upto the establishment and back etc.

o) The Building and Other Construction workers (Regulation of Employment and Conditions of Service) Act 1996 and the Cess Act of 1996: All the establishments who carry on any building or other construction work and employs 10 or more workers are

covered under this Act. All such establishments are required to pay cess at the rate not exceeding 2% of the cost of construction as may be modified by the Government. The Owner of the establishment is required to provide safety measures at the Building or

construction work and other welfare measures, such as Canteens, First-Aid facilities, Ambulance, Housing accommodations for workers near the work place etc. The Owner to whom the Act applies has to obtain a registration certificate from the Registering

Officer appointed by the Government. p) Factories Act 1948: The Act lays down the procedure for approval at plans before

setting up a factory, health and safety provisions, welfare provisions, working hours, annual earned leave and rendering information regarding accidents or dangerous occurrences to designated authorities. It is applicable to premises employing 10 persons

or more with aid of power or 20 or more persons without the aid of power engaged in manufacturing process.

2. SUB-CONTRACTING

The TENDERER shall not be required to obtain any consent from the owner for:

a) The sub-contracting of any part of the Works for which the Sub-TENDERER is named in the contract;

b) The provision of labour; and

Page 109: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 108

c) The purchase of materials which are in accordance with the standards specified in the Contract.

Beyond this if the TENDERER proposes sub-contracting any part of the work during execution of works, because of some unforeseen circumstances to enable him to

complete the work as per terms of the contract; the Owner / Engineering Consultant will consider the following before according approval:

- The TENDERER shall not sub-contract the whole of the Works. - The TENDERER shall not sub-contract any part of the Work without prior consent of the

Owner / Engineering Consultant. Any such consent shall not relieve the TENDERER from any liability or obligations under the contract and he shall be responsible for the acts, defaults and neglects of any sub-TENDERER, his agents or workmen as fully as if

they were the acts, defaults or neglects of the TENDERER, his agents or workmen.

- The Engineering Consultant should satisfy whether (a) the circumstances warrant

such sub-contracting; and (b) the sub-TENDERERS so proposed for the Work possess the experience, qualifications and equipment necessary for the job proposed to be entrusted to them in proportion to the quantum of work to be sub-contracted.

-If payments are proposed to be made directly to that sub-TENDERER, this should be subject to specific authorization by the prime TENDERER so that this arrangement does

not alter the TENDERER's liability or obligations under the contract.)

3. Protection of Environment:

The TENDERER shall take all reasonable steps to protect the environment on and off

the Site and to avoid damage or nuisance to persons or to property of the public or others resulting from pollution, noise or other causes arising as a consequence of his methods of operation.

During continuance of the contract, the TENDERER and his sub-TENDERERS shall attend at all times by all existing enactments on environmental protection and rules made there under, regulations, notifications and bye-laws of the State or Central

Government, or local authorities and any other law, bye-law, regulations that may be passed or notification that may be issued in this respect in future by the State or Central Government or the local authority.

Salient features of some of the major laws that are applicable are given below:

The Water (Prevention and Control of Pollution) Act, 1974, This provides for the prevention and control of water pollution and the maintaining and restoring of

wholesomeness of water. 'Pollution' means such contamination of water or such alteration of the physical, chemical or biological properties of water or such discharge of any sewage or trade effluent or of any other liquid, gaseous or solid substance into

water (whether directly or indirectly) as may, or is likely to, create a nuisance or render such water harmful or injurious to public health or safety, or to domestic, commercial, industrial, agricultural or other legitimate uses, or to the life and health of animals or

plants or of aquatic organisms. The Air (Prevention and Control of Pollution) Act, 1981, This provides for prevention,

control and abatement of air pollution. 'Air Pollution' means the presence in the atmosphere of any 'air pollutant', which means any solid, liquid or gaseous substance (including noise) present in the atmosphere in such concentration as may be or tend

Page 110: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 109

to be injurious to human beings or other living creatures or plants or property or environment.

The Environment (Protection) Act, 1986, This provides for the protection and improvement of environment and for matters connected therewith, and the prevention

of hazards to human beings, other living creatures, plants and property. 'Environment' includes water, air and land and the inter-relationship which exists among and between water, air and land, and human beings, other living creatures, plants, micro-

organism and property. The Public Liability Insurance Act, 1991, This provides for public liability insurance for

the purpose of providing immediate relief to the persons affected by accident occurring while handling hazardous substances and for matters connected herewith or incidental thereto. Hazardous substance means any substance or preparation which is

defined as hazardous substance under the Environment (Protection) Act 1986, and exceeding such quantity as may be specified by notification by the Central Government.

Site Office for TENDERER

The TENDERER shall provide temporary office, stores, laboratory and workshops at the location approved by the Owner / Engineering Consultant. All temporary construction

shall be put up after prior approval from Owner & Engineering Consultant.

The TENDERER shall provide necessary approaches, fencing and other facilities

at his own cost and within the quoted rates and with the prior approval of the Owner. No other land shall be occupied by the TENDERER without the written permission of Owner. The TENDERER shall not use or allow to be used the land for any purpose other than that of executing the works. The TENDERER shall dismantle and clear all dismantle all materials and hand over the vacant possession of the area allowed to him before leaving the site after completion of the contract

SPECIFICATIONS

Section A - SCOPE The scope of work covers special execution and completion of the structural rehabilitation, retrofitting to the damaged columns and PROVIDING RECTIFICATION

OF BASEMENT STRENGTHENING CUM RETROFITTING WORKS IN BASEMENT COLUMN, SLAB, RCC WALLS AND WATER PROOFING WORK AT TICEL BIO PARK – II BUILDING TARAMANI, CHENNAI - 600113 in accordance with drawings and

specifications prepared by and under the direction and to the satisfaction of M/s TAAMAESEK ENGINEERING CONSORTIUM Architects & Engineers No 5, 1st Floor, Bishop Wallers Avenue West. Off TTK Road, Mylapore, Chennai- 600 004.

SECTION B - MATERIALS

Materials shall be of approved quality and the best of their kind available and shall generally conformed to I.S. Specifications. The Contractor shall order all the materials

required for the execution of work as early as necessary and ensure that such materials are on site well ahead of requirement for use in the work. The work involved calls for high standard of workmanship combined with speed and to the entire satisfaction of the

Consultants.

Page 111: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 110

Materials shall be of the best approved quality obtainable and they shall comply with the respective latest Indian Standard Specifications.

In case of non-availability of materials in metric sizes, the nearest size in FPS units shall be provided with the prior approval of the Consultants for which neither extra will be paid

nor any rebate shall be recovered. a. Cement:

Cement shall comply in every respect with the requirements of the latest publication of IS:269 and unless otherwise specified ordinary Portland cement shall be used.

The weight of ordinary Portland cement shall be taken as 1440 kg. Per cum (90 lbs. Percft) Cement shall be measured by weight and in whole bags, and each undisturbed and sealed 50 kg bag being considered equivalent to a 34.72 litres (1.2 cft.) in volume.

Care should be taken to see that each bag contains full quantity of cement. When part bag is required cement shall be taken by weight or measured in measuring boxes.

Cement shall be stored in weather-proof shed with raised wooden plank flooring to prevent deterioration by dampness or intrusion of foreign matter. It shall be stored in such a way as to allow the removal and use of cement in chronological order of receipt

i.e. first received being first used. Cement deteriorated and/or clouded shall not be used on work but shall be removed at once from the site. However, allowing use of warehouse set cement shall be determined by the Consultants.

b. Fine Aggregate:

Sand shall conform to IS: 383 and relevant portion of IS: 515. It shall pass through an I.S. sieve 4.75mm (3/16 B.S) test sieve, leaving a residue not more than 5%. It shall

be from natural source crushed stones, if allowed, chemically inert, clean, sharp, hard, durable, well graded and free from dust, clay, shale, large pebbles, salt, organic matter, loam mica or other deteriorating matter. The sum of percentage of all delirious materials

in sand shall not exceed 5% of weight. It shall be washed if directed or reduce the percentage of deleterious substance to acceptable limits. Sand shall not contain any trace of salt and it shall be tested and sand containing any trace of salt shall be rejected.

The fine aggregate for concrete shall be graded within limits as specified in IS: 383 and the Fineness Modulus may range between 2.60 to 3.20.

c. Coarse Aggregate: It shall consist of crushed or broken stone 95% of which shall be retained on 4.75

mm test sieve. It shall be obtained from crushing Granite, Quartzite, Basalt or similar approved stones from approved quarry and shall conform to IS: 383 and IS: 515. Coarse aggregate shall be chemically inert when mixed with cement and shall be cubical in

shape and free from soft, friable, thin porous, laminated or flaky pieces. It shall be free from dust and any other foreign matter.

Gravel / Shingle of desired grading may be permitted as a substitute in part or full in plain cement concrete if the Consultants are otherwise satisfied about the quantity of aggregate. For all RCC works the size of coarse aggregate shall be 20mm. and down

gauge.

Page 112: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 111

d. Reinforcement

Reinforcement shall be of mild steel tested quality conforming to IS: 432-1966 and any other ISS applicable or deformed bar conforming to IS: 1786 and IS:1139 or hard drawn steel wire fabric conforming to IS:1566:1967.

All finished bars shall be free from cracks, surfaces flaws, and Laminations Jagged and imperfect edges.

Mild steel bars conforming to grade 1 of IS: 432 (Part 1) - 1966.

Cold twisted high yield strength deformed bars conforming to IS: 1139-1966 or IS: 1786-1979 (Grade Fe 415). The pitch of twist shall be 10 to 12 times the diameter of bars & shall preferable bear the manufacturer's identification mark.

Welded fabric & or wire mesh conforming to IS 1566, made out of high tensile wires electrically welded together.

e. Structural Steel: All structural steels used shall conform to IS: 226-1975 before fabrication. Bolts &

Nuts shall conform to IS:1363-1967, IS-1364-1967, IS:1367-1967, IS:3640-1967, IS:3557-1972, IS:6623-1972, & IS:6639-1972 as appropriate.

Covered electrodes for welding shall conform to IS: 814 (Part 1)-1974, IS:814 (Part 2)-1974 or IS:1395-1971 as appropriate.

f. Bricks: Bricks shall generally comply with IS: 1077 except in size which shall consider the size locally available. Depending upon the quality of bricks they shall be classified at 1st

and 2nd class. Bricks shall be the best quality locally available table moulded well burnt but not over

burnt, have plane rectangular faces with parallel side and sharp right angled edges, and have a fine compact and uniform texture. The bricks shall be free from cracks, chips flaws, stones or lumps of any kind and shall not show efflorescence either dry or

subsequent to soaking in water. It shall emit a clear ringing sound on being struck and shall not absorb water more than 20% by weight. Common building bricks shall have a minimum compressive, strength of 35 kg./sq. cm. when used as panel in frame structure

unless otherwise specifically stated in the schedule of quantities.

g. Water: Water for mixing Cement mortar or concrete shall not be salty or brackish and shall be clean, reasonably clear and free from objectionable quantities of silt and traces of oil,

acid and injurious alkali, salts, organic matter and other deleterious materials which will either weaken the mortar or concrete or cause efflorescence or attack the steel in reinforced cement concrete. Water shall be obtained from sources approved by the

Consultants. Potable water is generally considered satisfactory for mixing and curing concrete, mortar, masonry etc. Where water other than main source is used this shall be tested in an approved testing laboratory to establish its suitability. All charges connected

therewith shall be borne by the Contractor.

Page 113: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 112

Water to be used in the work shall be clean & free from injurious amounts of deleterious materials such as silica, acids, alkalis, salts & vegetable growth. Potable water is

generally considered satisfactory for use in the work. Also refer IS 456: 2000. h. Mortars:

Cement Mortar: Cement Mortar shall be of proportions specified for each type of work in the Schedule.

It shall be composed of Portland cement and sand. The ingredients shall be accurately

gauged by measure and shall be well and evenly mixed together in a mechanical pan mixture; care being taken not to add more water than is required. No mortar that has begun to set shall be used.

If hand mixing is allowed, then it shall be done on good waterproof platform. The gauged materials shall be put on a platform and mixed dry. Water will then be added and the

whole mixed again until it is homogeneous and of uniform colour. Not more than one bag of cement shall be mixed at one time and which can be consumed within half an hour of its mixing, along with specified admixtures.

SECTION – C: WORKMANSHIP

Preparatory works Item 2a of TENDER – Removal of existing finish or paint

The existing concrete surface to expose for retrofitting works. Prepare existing column surface, by scrapping, cleaning the exposed concrete surface to remove any fungus, loosely particles, scales, by a stiff wire brush, clean by water wash the entire surface,

exposed the damaged concrete surface with the help of small chisel and hammer, including collecting, stacking the debris at the site.

Item 2b of TENDER - Removal of Plaster: The loose & damaged plaster shall be broken & removed carefully by chipping or by light chiselling, preferably by special tools / electromechanical cutters or any other

method with the approval of Consultants so as not to disturb the adjoining sound plaster, concrete / brickwork inside. Plaster on concrete surface shall be first roughened by close chipping, & then cleaned with brushing & washing.

The debris shall be taken down & stacked or carted away as directed. Necessary barricades shall be provided to obstruct entry of public to avoid accidents. If the plaster

is to be applied on repaired concrete surface, the base shall be kept rough to provide a key to the plaster.

The surface to be plastered shall be cleaned of loose materials, thoroughly watered & kept adequately wet during plastering.

Item 3 of TENDER - Crystallisation waterproofing stage – I The substrate should be cured, dry, and free from voids. For substrates with oil, grease, fungal growth will clean and dry the surface thoroughly before application.

Zycosil plus should be diluted with portable water (TDS less than 1000 PPM) to obtain a clear transparent solution. The diluted solution should be liberally applied with brush in low pressure until saturation is achieved. To achieve saturation on surfaces, after

repetitive application the solution should drip down the surface. The applications are best done at ambient temperature. It is best to do the application during the morning or

Page 114: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 113

evening hours to avoid peak heat of the sun. Zyco prime must be added to the Zycosil plus solution as specified ratio as better bonder to receive further treatment.

Item 4 of TENDER - Elastomeric waterproofing stage – II The treated stage I waterproofing surface shall be further treated by elastomeric

membrane for Zycosil Plus treated concrete surface. It forms seamless cross linked elastomeric membrane on the concrete surface. The Acrylic composition is ensuring excellent UV stability, high strength and elongation. Prepare waterproofing solution by

mixing one part of Elastobar and cement one part add required water to get slurry consistency to workable. Apply by brush. Apply further coats wet on wet. Allow to air cure over night. Cure with water at least two days.

Item 5 of TENDER- Treating damaged concrete before Jacketing - POLYMER REPAIRS:

1. Remove loose concrete from the damaged structural members such as columns, beams and slabs.

2. Clean the exposed steel surface of any loosely held rust particles, scales, etc. by a

stiff wire brush. 3. Apply a solution of "Rustclean" or equivalent as approved by Engineer-in-charge.

Allow it to dry for the period of at least 4 hours.

4. Apply anticorrosion / preventive coat chemicals or equivalent to the said reinforcement. Allow it to dry for the period of 6 to 8 hrs

5. Wet the prepared concrete and treated steel surface with water.

6. Apply the preventive coat to both concrete and treated steel. During the tacky period of the bond coat when the surface is still wet is ready to receive the polymer mortar.

7. Prepare polymer mortar mixing chemical + cement + Sand in the ratio as per specification.

8. Apply polymer mortar in layer not more than 15 mm thickness (hand packed

method) on the damaged concrete section to bring it to true line and level and shape to match the original designed size of the members.

9. This treatment should be cured by light water sprinkling for at least 3 days

Item 6 of TENDER - Structural bonding to Jacketing - STRUCTURAL STEEL WORK

All Steel Work shall conform to IS : 800 and shall be free from defects impairing strength, durability or appearance and shall be of the best quality for the purposes specified and possessing structural properties to withstand safety stresses to which

these shall be normally subjected. The contractor shall bear the cost of all tests. All structural steel members brought by or handed over to the contractor shall be handled with care, stacked on edge and supported evenly.

The structural steel and rivet bars shall conform to IS: 226. Before any fabrication work is commenced all plates shall be flattened and all bars and sections are straightened or otherwise trued and made free from twist or other distortion. Method adopted for the

purpose shall be such as not to injure the material. Cutting shall be affected by shearing, cropping or sawing and shall be clean reasonably

square and free from distortion if directed the edges shall be ground. Gas cutting by mechanical controlled torch shall be permitted for mild steel only with the approval of the Consultant.

Welding:

Page 115: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 114

Welding wherever indicated on the drawing shall conform to IS: 814-1963 unless otherwise specified. Welding shall be carried out by experienced welders only, who if

necessary, shall produce testimonials about their work or if required by the Consultant shall have to undergo qualifying test as prescribed in IS: 1181. Welding work shall be carried out as per IS: 816.

Welding shall be done in flat position wherever possible and adequate steps shall be taken to maintain the correct length, rate of travel, current and polarity for the type of electrode and nature of work. Steel shall not be painted or oiled and any areas where

welding is to be performed shall be well cleaned to remove any paint, scale or rust immediately before welding or a distance of at least 2 cm on either side.

The work shall be securely held in position by means of tack welds, service bolts, clams or jigs before commencing the welding so as to prevent any relative movement due to distortion, wind or other causes. When welding is liable to cause distortion, the work

shall be securely held in approved frames or jigs. Parts to be filled welded shall be brought in as close contact as practicable and in no event shall be separated more than 4.75 mm. (3/15”). If the separation is 1.6 mm.

(1/16”) or greater, the size of the fillet welds shall be increased by the amount of the separation

The separation between facing surfaces of lap joints shall not exceed 1.6 mm (1/16”). The fit of joints at contact surfaces which are not completely sealed by welds, shall be close enough to exclude water after painting. Abutting parts to be butt welded shall be

carefully aligned. Misalignment greater than 3 mm (1/8”) shall be corrected and in making the correction, the parts shall not be drawn into a sharper slope than two degree (11 mm in 30 cm. Or 7/16” in 12”)

The sequence of welding shall be such that when possible the members which offer the greatest resistance to compression are welded first. Welded joints showing slab

inclusion or lack of proper penetration shall be cut and re-welded overlap of the toe of the weld and under-cutting of the parent metal should be avoided and where present to a serious extent shall be rectified. All slag shall be removed from each run before

another run is superimposed. When cold the final run shall be protected with clean boiled linseed oil and shall not be painted until approved by the Consultant or his representatives.

Grinding of finished weld is permitted provided the weld is not reduced below the prescribed section. All exposed welds shall be ground smooth. Welds which have not

been ground shall be scrubbed with a 10% solution of Hydrochloric acid which shall be washed off with water before paint is applied and alkali paint is used.

Bolting: All turned and fitted bolts shall be parallel throughout the barrel within the tolerance of only minus 0.13 mm and faces of heads and nuts bearing on steel work

shall be machines. All such bolts shall be provided with washers and standard size so that the nut when turned shall not bear screws and shall be well formed. Where the full bearing shall be hexagonal with worth screws and shall be well formed. Where the full

bearing area of the rivet is to be developed, the threaded portion of the bolt shall not be within the thickness of the parts bolted together. Threaded portion of each bolt shall project beyond the nut at least by one thread. Tapered washers shall be provided for all

heads and nuts bearing on levelled surfaces.

Page 116: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 115

Fabrication and Erection: In order to facilitate handling, transportation and execution the contractor may

fabricate the structural members in suitable sections. The details of site connections and their location shall be approved by the Consultant. Frame or lattice sections intended for use as parts of composite construction which are likely to deflect

considerably during handing shall be suitably stiffened by means of steel angles. Roof and other structures shall be supported at close intervals during the welding / bolting of site connections.

The frame of steel skeleton building shall be carried up true and plumb and temporary bracings shall be introduced wherever necessary to take care of all loads to which

structures may be subjected including erection equipment and operation of the same. Such bracings shall be kept in position as long as required for safety.

As erection progresses, the work shall be securely bolted to take care of all dead load, wind load and erection stresses. No riveting or welding shall be done until the structure has been properly aligned. Rivets driven in field shall be heated and driven with the

same care as those driven in the shop. In the setting or erection of steel work the individual pieces shall be considered plumb or level when error does not exceed 1 to 500. For exterior columns the error shall not exceed 1 to 1000.

Slight bends in the members of fabricated structures shall not be straightened unless strictly necessary on account of danger of overstraining connection and rivets, welds or

bolts. Connection plates, if slightly bent or twisted shall be straightened cold, if bend so sharply as to require heating the whole piece this heated shall subsequently annealed. No straightening whatsoever shall be carried out without the previous sanction of the

Consultant. Item 7 of TENDER - Structural bonding to Jacketing – Mechanical Anchor

Providing and fixing mechanical anchor using HILTI product for the length of 100 mm to 150mm and up to 20 mm diameter including drilling holes in concrete up to required depth at required levels in position, cleaning the holes to receive anchor.

Item 8 of TENDER - Steel reinforcement for jacketing works Reinforcement shall be accurately fabricated, placed and adequately, maintained

in position as shown on drawings. All finished bars shall be free from cracks, surface flaws, laminations, jagged and in prefect edges. Cement mortar blocks shall be used to give requisite cover as shown on the drawing or as directed and all intersections of bars

shall be firmly tied with binding wire of 16 to 18 gauge. Reinforcement shall be bent in accordance with the procedure stipulated in IS: 2502-1963 and will not be straightened in a manner which will injure the material. All reinforcement shall immediately before

placing in concrete, be thoroughly cleaned of loose mill scale, loose rust, oil and grease or other deleterious matter that would destroy or reduce bond.

Reinforcement in reinforced concrete members shall not be connected by welding or coupling except in accordance with relevant IS. Overlaps and joints shall be staggered and located at points, along the span where neither shear nor bending moment is in

maximum. Cover:

Page 117: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 116

Reinforcement shall have cover as shown on the R.C.C. drawings and where not specified the thickness of cover shall be as follows. Cement mortar blocks in C.M. 1:1

shall be used for making cover blocks.

(a) At each end of reinforcing bar is not less than 25 mm or not less than twice the

diameter of such rod or bar. (b) For a longitudinal reinforcing bar in a column not less than 40 mm, nor than the

diameter of such rod bar. In the case of columns of minimum dimension of 20

cm. or under whose reinforcing bars do not exceed 13 mm, the cover of 25 mm. may be used.

(c) For longitudinal reinforcing bar in a beam not less than 25 mm, or less than the

diameter of such rod or bar. (d) For tensile, compressive, shear or other reinforcement in a slab not less 13

mm., nor less than the diameter of such reinforcement and

(e) For any other reinforcement not less than 13 mm, nor less than the diameter of such reinforcement.

Item 9 of TENDER – Strengthen the columns by RCC jacketing Generally except where they are varied by the requirements of this

specification due provision of Indian standard specification IS-456-2000 for plain and reinforced concrete and IS –432 part I & II for mild and medium tensile steel bars and hard drawn steel wire for concrete reinforcement and any other relevant IS applicable

together with the latest amendments shall be held to be incorporated in this specification. It shall be intent of these specifications to ensure that all concrete placed at various location of the job should be durable, strong enough to carry the design

loads; it should wear well and practically be impervious to water. It should be free from such defects as shrinkage cracking and honey combing.

Proportioning the Mix: In ordinary concrete excluding controlled concrete proportion of cement to fine and coarse aggregate shall be as specified in the respective items and shall be

accurately measured as in. table “A” below. These proportions are based on assumption that the aggregates are dry. If aggregates are moist, allowance shall be made for bulking in accordance with IS- 2386. Allowance shall also be made for

surface water present in aggregate when computing water content. Surface water present shall be determined by one of field methods described in IS: 2386 (part III) In the absence of exact data the amount of surface water may be estimated from the

values given in table “B” below. Mixing:

Concrete mix shall be mixed in an approved mechanical mixer. The mixer and the mixing platform shall be suitably protected from wind and rain. Aggregate shall be accurately measured out in boxes and mixed dry along with cement, water shall be

added in measured quantity and mixing shall be continued until there is a uniform distribution of the materials and mass uniform in colour and consistency but in no case shall the mixing be done for less than 2 minutes.

When hand mixing is permitted with the approval of the Consultants it shall be carried out on a watertight mixing platform and care shall be taken to ensure that mixing is continued

until the mass is uniform in colour and consistency.

Page 118: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 117

Consistency: Quantity of water for making reinforced concrete shall be sufficient so as to

ensure that concrete shall surround and properly grip all the reinforcement. The best consistency shall be that which will flow sluggishly without flattening out and without separation of coarse aggregates from the mortar. The degree of plasticity shall depend

on the nature of work and atmospheric temperature and whether the concrete is vibrated or hand compacted. The slumps shown in table “C” on relevant TENDER page obtained by the standard slump test carried out in accordance with the procedure laid

down in IS 1199-1959 shall be adopted for different types of works. Admixtures:

The use of admixtures may be allowed as specified in the respective items and shall be accurately measured by measuring jar only.

Transporting: Concrete shall be conveyed from the place of mixing to the place of final deposit as rapidly as practicable by methods which will prevent segregation or loss of any of the

ingredients. If segregation does occur during transport, the concrete shall be remixed before being placed. In no case more than 30minutes shall elapse between mixing and consolidation in its position.

Placing & Compacting: Concrete shall be placed in layers of suitable thickness or in strips and compacted

before initial setting commences and should not be subsequently disturbed. Method of placing shall be such as to preclude segregation and as far as practicable the placing shall be continuous. Special care shall be taken in accordance with IS-456 while lying

concrete under extreme weather. Concrete shall be thoroughly compacted during the operation of placing and thoroughly worked around the reinforcement, embedded fixtures and spaded, against concerns of the form work and by punning, rodding,

mechanically vibrating or by any other approved means. In addition form work shall be tapped lightly by using wooden mallet at the pouring head. The number and type of vibrator to be used shall be subject to the approval of Consultants and in general

immersion type vibrators shall be used. External vibrators shall also be used whenever directed.

The intensity and duration of vibration shall be sufficient to cause complete settlements and compaction without any stratification of successive layers or separation of ingredient or formation of laitance. Vibrator shall be inserted vertically in the concrete at

points not more than 45 cm. apart and withdrawn very slowly when air bubbles no longer come on the surface. Over vibration or vibration of very wet mixes is harmful and should be avoided. Care shall be taken to utilise the vibrator only to compact the

concrete and not to spread it. Sufficient number of reserve vibrators in good working condition shall be kept on hand at all times, so as to ensure that there is no slackening or interruption in compacting.

Curing: Concrete shall be carefully protected during first stage of hardening form harmful

effects of excessive heat, drying winds, rain or running water. It shall be covered with a layer of sacking, sand, canvas, Hessian or similar absorbent materials and kept constantly wet for five days from the date of placing of concrete.

Page 119: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 118

Form Work:

The form work shall conform to the shape, lines and dimensions as shown on the drawings and be so constructed as to remain sufficiently rigid during the placing and compacting of the concrete and shall be sufficiently watertight to prevent loss of cement

slurry from the concrete. Form work or centering shall be constructed of steel or timber and adequately designed to support the full weight of wet concrete with deflection and retain its form during laying, ramming and setting of concrete. Timber used shall be

properly seasoned so as to prevent deformation when wetted.

All props shall be straight and of full height and no joints shall be allowed. Props shall

be braced with thin bamboos or wooden battens and where additional staging is necessary extra care shall be taken to use bigger diameter props with bracing at 4 or 5 levels. All props shall be supported on sole plates and double wedges. At the time of

removing props these wedges shall be gently eased and not knocked out. All rubbish, chippings, shavings and saw dust shall be removed from the interior of the

forms before the concrete is placed and the form work in contact with the concrete shall be cleaned and thoroughly wetted or treated with non-sticking mineral oil or any other approved material. Care shall be taken that oil or such approved material is kept out of

contact with the reinforcement. All form work shall be removed without shock or vibration and shall be eased off

carefully in order to allow the structure to take up its load gradually. Forms shall not be disturbed until concrete has adequately hardened to take up superimposed load coming on it and in no circumstances shall forms be struck until the concrete reaches strength

of at least twice the stress to which the concrete may be subjected at the time of striking.

In the normal circumstances (generally where temperatures are above 21 degrees centigrade) and where ordinary cement is used, forms may be struck after expiry 48 hours or as may be directed.

Strength: Concrete mixed in the proportion desired shall have compressive strength after

placing, not less than the following;-

S.No Concrete Mix Minimum compressive

Strength @ 7 days Minimum compressive Strength @ 28 days

1 1: 1: 2 160 kg./sq.cm.

(2250 Lbs./Sq.inch)

250 kg./sq. cm.

(3500 lbs./sq.inch.)

2 1: 1.5: 3 132 kg./sq.cm.

(1875 lbs./sq.inch) 200 kg./sq.cm.

(2850 lbs./sq.inch)

3 1: 2: 4 106 kg./sq.cm.

(1500 lbs./sq.inch) 150 kg./sq.cm.

(2250 lbs./sq.inch)

Tests on concrete shall be carried out in accordance with IS – 456 and any other ISS applicable. The frequency of works test shall be at such intervals as ordered by the

Consultants and subject to that every 150 cum. concrete placed or part thereof and for a day’s concrete exceeding 5 cum. a batch of 3 cubes shall be tested after 28 days. The criteria for acceptance of a conforming to the specified proportion / grade of concrete shall

Page 120: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 119

be in accordance with IS: 456 and the contractor shall entirely re-do the rejected work at his own cost. Strength of 28 days shall alone be considered for acceptance.

TABLE - ‘A’

S.No. Nominal Mix

Quantity of aggregate required for50 kg. of cement.

Quantity of water required for 50 kg. of cement

Fine Cum Coarse Cum Vibrated

(for dry aggregate)

1. 1 : 1 : 2 0.035

(1.2 Cft) 0.070

(2.4 Cft) 22 Ltr.

(4.8 Gal.)

2. 1 : 1.5 : 3 0.052

(1.8 Cft) 0.106

(3.6 Cft) 23 Ltr. (5 Gal.)

3. 1 : 2 : 4 0.070

(2.4 Cft) 0.138

(4.8 Cft) 27 Ltr. (6 Gal.)

4. 1 : 3 : 6 0.105

(3.6 Cft) 0.210

(7.2 Cft) 28 Ltr.

(6.25 Gal.)

5. 1 : 4 : 8 0.150

(4.8 Cft) 0.280

(9.6 Cft) -

TABLE - ‘B’

S.No. Aggregate Approximate quantity of Surface

water in Lit/Cum

1. 2.

3. 4.

Very wet sand Moderately wet sand

Moist Sand Moist gravel or crushed rock Coarser the aggregate, lesser the water it will carry.

120

80 40

20 to 40

RMC: All RCC works shall be in strict conformity with latest IS 456 & specification appended herewith. Unless otherwise specified all items of RCC are to of RMC as per

the grade specified. The rate shall be inclusive of dewatering, hoisting by normal labour or by means of mechanised equipment. Consolidation by rodding, tamping, vibrating by an approved mechanical vibrator etc. protecting, curing including hacking, roughening of

concrete surface for receiving plaster or any other finish including costs of all tests on all materials & concrete as & when directed by the consultants. Use of admixtures in concrete works is permitted, if specified & approved prior to use in the work. Nothing extra shall be paid for use of such admixtures. Fly ash content should not be more than

20%. The rate shall be deemed to have been quoted for all the elements required to place the concrete in position and nothing extra if any shall be measured & paid for.

Item 10 of TENDER - Protective coat on top of jacketed column

Projecting burns of mortar formed due to gaps at joints in shuttering shall be removed. The surface shall be scrubbed clean with wire brush/coir brush to remove dirt,

dust etc. and the surface thoroughly washed with clean water to remove efflorescence, grease and oil etc., and shall be kept wet for a minimum of six hours before application of plaster. Preparation of surface: All putlog holes in brickwork and junction between

concrete and brickwork shall be properly filled in advance. Joints in brickwork shall be racked about 10 mm and concrete surface hacked to provide the grip to the plaster.

Apply polymer protective coat on top of jacketed column at an average thickness of 12 to 15 mm in exact line & level in the proportion of 1: 4 cement and sand mortar by

Page 121: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 120

manual mixing, with addition of waterproofing chemical @ 150ml and Harbourite 12mm fine fibrillated 100% virgin polypropylene fibers @ 150gm per bag of cement including

curing for at least 7days, carting away a debris, cleaning Projecting burns of mortar formed due to gaps at joints in shuttering shall be removed.

The surface shall be scrubbed clean with wire brush/coir brush to remove dirt, dust etc. and the surface thoroughly washed with clean water to remove efflorescence, grease and oil etc., and shall be kept wet for a minimum of six hours before application of

plaster. Preparation of surface: All putlog holes in brickwork and junction between concrete and brickwork shall be properly filled in advance. Joints in brickwork shall be racked about 10 mm and concrete surface hacked to provide the grip to the plaster.

Sand faced plaster: The surface shall be prepared as above. A coat of cement mortar in proportion 1: 4 or as specified shall be applied uniformly all over the surface to a

thickness of 12 to 14 mm. and finished true to level and line and keys shall be formed on the surface. The surface shall be kept moist till the finishing coat is applied. The surface shall be tapped to uniform grained texture by using sponge pads as directed.

Surface shall be kept wet for seven days. Item 11 of TENDER – Corrosion protective by fixing SACRIFICIAL ANODES

Providing & installation of SACRIFICIAL ANODES, including installation of the Galva shield units, restoration of continuity by effective means. Selecting the location of Galva shield as closer to the edge of the repair zone. Positioning Galva shield units in

and around the repair area. In addition to standard substrate preparation, the Galva shield XPI anode shall be thoroughly pre-soaked in clean water for a minimum of 10 minutes and a maximum of 20 minutes, prior to the application of the repair mortar.

Tighten tie wires using Galva shield Fixing Tool so that no free movement is possible, thus ensuring good electrical continuity. Using continuity meter between tie wires and reinforcement bar to test electrical continuity as complete

Item 12 of TENDER – Floor protection around the column by PU grout Providing and injecting polyurethane waterproofing chemicals and expandable

to stop water flow from ground bellow basement level by mechanical pressure grout method, including fixing metal nozzle by drilling holes in the junction between columns and basement raft slab, packing with polymer modified mortar after completion of

injection, cleaning in all respect. Payment will be made against actual consumption of polyurethane waterproofing chemicals.

Item 13 of TENDER – Weather protective coat on top of treated column Providing & applying top coat as a weather protective layer of waterproofing paint from Zydex.

Item 14 of TENDER - Scaffolding: The sturdy steel scaffolding will include all pipes, H frames, brackets, bracings,

extruders, clamps, working platforms, planks, guy ropes, climbing arrangement, lifting arrangements for materials & manpower, safety arrangements etc. all complete confirming to IS 2750 – 1964, IS:4014 (Part II) – 1967, IS:3696 (Part I) – 1987, IS:4014

(Part I) – 1967 and manufacturers specifications. The contractor shall get approved the design of Scaffolding & erection with necessary anchorage as per IS requirement from the consultants in writing, before commencement of the work. However, the contractor

shall be responsible for the performance of the scaffolding during the currency of contract including safety ensuring it against collapse, the safety of men & materials etc.

Page 122: TICEL BIO PARK LTD RETENDER FOR PROVIDING RECTIFICATION … Tender.pdf · 2019. 7. 4. · ticel bio park ltd retender for “providing rectification of basement strengthening cum

TICEL Bio Park – II Vol-I Rectification work at Basement

Page | 121

The TENDERER is deemed to have studied the sequence of various items mentioned

in the Bill of Quantities & the requirement of scaffolding to execute the items at proper times. Repetition of scaffolding to attend or to correct defective work shall not be paid separately as stated in the preamble.

The scaffolding shall be measured only once for all the TENDER items, variation items and extra items if any. The same shall be kept in position till the satisfactory completion

of all works for which the scaffolding is necessary. Approved chemicals:

S.No. Description of work Approved Chemicals Manufacturers Name

1 Polymer mortar

treatment.

a. Elstobar

b. Master Emaco SBR 2

M/s Zydex Induatries

BASF India Limited Construction Chemicals Division Plot.No.12,TTC

Area Thane Belapur Road, Turbhe Navi Mumbai – 400705

2 Waterproof coating

a. Zycosil plus

b. Zycocil primer c. Elastobar

M/s Zydex Induatries

3 Cleaning of exposed steel

Rust clean M/s Fosroc Chemicals (India) Pvt. Ltd.

4 Fiber mesh in plaster.

Fiber mesh Harbourite M/s Aquva Protection Chennai