44
Thornton Water Project Work Package 1 Pipeline Dewatering Quantity Baseline Report City of Thornton Windsor Segment, Project No. 12-777H3 and Johnstown Segment, Project No. 12-777H4 BMcD Project No. 108405 Revision 1 May 13, 2019

Thornton Water Project Work Package 1 Pipeline Dewatering

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Thornton Water Project Work Package 1

Pipeline Dewatering Quantity Baseline Report

City of Thornton

Windsor Segment, Project No. 12-777H3 and

Johnstown Segment, Project No. 12-777H4 BMcD Project No. 108405

Revision 1May 13, 2019

City of Thornton / Thornton Water Project Table of Contents

108405 / Work Package 1 Page-1 Burns & McDonnell

TABLE OF CONTENTS

Page No.

1.0 INTRODUCTION .................................................................................................. 11.1 Project Background and Description .......................................................................1

1.2 Report Purpose .........................................................................................................2

1.3 Trenchless Construction Coordination ....................................................................3

2.0 PROJECT GEOLOGY ......................................................................................... 52.1 Regional Geology ....................................................................................................5

2.2 Subsurface Investigation ..........................................................................................7

3.0 QUALITATIVE DEWATERING EVALUATION .................................................... 8

4.0 AQUIFER TESTING ........................................................................................... 124.1 Slug Testing ...........................................................................................................12

4.2 Aquifer Pumping Tests ..........................................................................................13

4.2.1 Cache La Poudre River Site ....................................................................13

4.2.2 Little Thompson River Site .....................................................................15

4.2.3 Aquifer Test Analysis .............................................................................16

4.2.4 Water Quality ..........................................................................................18

5.0 DEWATERING ESTIMATES.............................................................................. 195.1 Windsor Alignment ................................................................................................19

5.2 Johnston Alignment ...............................................................................................20

5.3 Limited Dewatering Classification ........................................................................22

6.0 REFERENCES ................................................................................................... 23

APPENDIX A – AQUIFER PUMPING TEST RESULTSAPPENDIX B – WATER QUALITY RESULTSAPPENDIX C – DEWATERING CALCULATIONS

City of Thornton / Thornton Water Project Table of Contents

108405 / Work Package 1 Page-2 Burns & McDonnell

LIST OF TABLES

Page No.

Table 4-1: Summary of Slug Test Hydraulic Conductivity Results ..............................................12

Table 4-2: Summary of Aquifer Test Water Level Conditions .....................................................15

Table 4-3: Summary of Aquifer Test Water Level Conditions .....................................................16

Table 4-4: Summary of Aquifer Test Results ................................................................................17

Table 4-5: Summary of Aquifer Test Results ................................................................................18

Table 5-1: Baseline Dewatering Estimate Windsor Alignment Stations 0+00 to 55+00 ..............20

Table 5-2: Baseline Dewatering Estimate Johnston Alignment Stations 155+00 to

165+00 ......................................................................................................................21

LIST OF FIGURES

Page No.

Figure 1-1 Windsor Segment Alignment .........................................................................................2

Figure 1-2 Johnstown Segment Alignment......................................................................................2

Figure 2-1 Surficial Geology Windsor Segment .............................................................................5

Figure 2-2 Surficial Geology Windsor Segment .............................................................................6

Figure 3-1 Qualitative Dewatering Evaluation Windsor Segment ..................................................9

Figure 3-2 Qualitative Dewatering Evaluation Johnstown Segment .............................................10

Figure 4-1 Pumping Water Level Response for Cache La Poudre Test Well ...............................15

City of Thornton / Thornton Water Project Pipeline Dewatering Quantity Baseline Report

108405 / Work Package 1 Page-1 Burns & McDonnell

1.0 INTRODUCTION

This document contains the Pipeline Dewatering Quantity Baseline Report (Report) for the Windsor and

Johnstown segments of the City of Thornton raw water pipeline (Figure 1-1 and 1-2, respectively). This

Report presents an interpretation of the data presented in the project Geotechnical Data Report (GDR),

developed by Kumar & Associates, Inc. (Kumar and Associates), as applied to the need for construction

dewatering along the two pipeline segments. The dewatering evaluation presented in the Report is only

applicable for open-cut trench installations that will be constructed within the unconsolidated materials

along the pipeline route. Coordination with the project Geotechnical Baseline Reports (GBRs),

developed by Brierly Associates, is required for pipeline installation where trenchless construction is

specified. The dewatering baseline statements contained in this Report are presented in bold, italic font.

In case of conflict between this Report and the GBR, the GBR has a higher order of precedence, meaning

that in the event of a conflict between these two documents the GBR discussions represent the controlling

characterization of ground conditions.

1.1 Project Background and Description

The Thornton Water Project is a proposed program of various water infrastructure improvements

including an approximately 76-mile raw water transmission waterline. Installations are to be located

within Larimer, Weld, and Adams Counties. The Project will convey raw water owned by the City of

Thornton (Thornton), south, from the Water Supply and Storage Company to Thornton. This project will

help to meet the City of Thornton’s future potable water demand projections.

Thornton has engaged Burns & McDonnell (BMcD) to design Work Package 1 associated with the

transmission waterline. Work Package 1 includes two (2) separate sections of a 48-inch transmission

waterline totaling approximately seven (7) miles. One approximate 3.5-mile segment is located within the

jurisdiction of the Town of Windsor, Colorado (Windsor Segment). The other approximate 3.5-mile

segment is located within the jurisdiction of the Town of Johnstown, Colorado (Johnstown Segment). The

two waterline segments are not continuous, they are separated by approximately 6.2 miles. Figure 1-1 and

Figure 1-2 show the general alignment of the two waterline sections.

City of Thornton / Thornton Water Project Pipeline Dewatering Quantity Baseline Report

108405 / Work Package 1 Page-2 Burns & McDonnell

Figure 1-1 Windsor Segment Alignment

Figure 1-2 Johnstown Segment Alignment

1.2 Report Purpose

The purpose of this Report is to present an interpretive summary of the data presented in the project GDR

(Kumar & Associates, 2018), as applied to the need for open-cut construction dewatering along the

Windsor and Johnstown segments of the City of Thornton raw water pipeline (Figure 1-1 and 1-2,

respectively). The Report provides an interpretation of the data reported in the GDR and an analysis of

those data to develop baseline estimates for construction dewatering needs along both pipeline segments.

The dewatering evaluation presented in this Report is only applicable for open-cut trench installations that

will be constructed within the unconsolidated materials along the pipeline route. This Report does not

evaluate the need for construction dewatering associated with the portions of the pipeline alignment

City of Thornton / Thornton Water Project Pipeline Dewatering Quantity Baseline Report

108405 / Work Package 1 Page-3 Burns & McDonnell

where trenchless construction is required, where both tunnels and shafts are required. Coordination of

baseline dewatering estimates for trenchless construction are discussed in Section 1.3.

The interpretive discussions contained within this Report are intended to establish baseline conditions for

dewatering in portions of the pipeline where open-cut trench installation is expected and presents a

summary of anticipated groundwater conditions in these portions of the alignment. Although alternative

interpretations for ground conditions are possible and this Report is not a guarantee, it does provide a

basis for resolving allegations of differing site conditions encountered during construction. The

Contractor's basis of bid and contracting with regards to expectations of the open-cut dewatering work,

requirements of such work, including all materials, labor, equipment, and work required and subsequent

cost shall be as presented in this Report.

1.3 Trenchless Construction Coordination

Trenchless construction is required for pipeline installation at two (2) locations for Windsor alignment

and six (6) locations for Johnstown alignment, which are shown on the Contract Drawings. Anticipated

groundwater conditions for the pipeline alignment areas where trenchless construction is required are

presented in the project GBRs, prepared by Brierly Associates (Brierly Associates, 2018a and 2018b).

Separate GBRs have been prepared for the Johnstown and Windsor pipeline segments and are included in

the Contract Drawings and Specifications. As discussed in the GBRs, watertight shafts are required at the

Little Thompson and Poudre River trenchless crossings. Watertight shafts are likely to consist of sheet

piles with tight interlocks (grouted as necessary), secant pile drilled shafts, jet grout, slurry walls, or

frozen ground. The bottom of the watertight shafts must be designed for stable shaft bottoms and

watertight floors that account for bottom instability, including boiling subgrades. Shaft bottoms may

consist of concrete installed in the wet or on frozen or jet grout or other adequate methods. Two shafts

will be required for each of the trenchless crossings.

For the Johnstown segment, trenchless construction is required at the following locations:

• WCR 13/Colorado Boulevard;

• Colorado Boulevard;

• Great Northern Railroad;

• Hillsborough Ditch Crossing #1;

• Little Thompson River; and

• Hillsborough Ditch Crossing #2.

City of Thornton / Thornton Water Project Pipeline Dewatering Quantity Baseline Report

108405 / Work Package 1 Page-4 Burns & McDonnell

For the Windsor segment, trenchless construction is required at the following locations:

• Highway 392 Crossing; and

• Cache la Poudre River Crossing.

City of Thornton / Thornton Water Project Pipeline Dewatering Quantity Baseline Report

108405 / Work Package 1 Page-5 Burns & McDonnell

2.0 PROJECT GEOLOGY

2.1 Regional Geology The geology along the Johnstown and Windsor segments of the pipeline route is comprised of relatively

thin surficial deposits underlain by bedrock consisting of claystone, siltstone, sandstone, or shale. The

location and nature of the soils and bedrock likely to be encountered by the pipeline corridors are shown

in Figure 2-1 and Figure 2-2.

Figure 2-1 Surficial Geology Windsor Segment

The geologic map referenced in Figures 2-1 is U.S. Geological Survey Geologic Investigations Series I-

855-G, Geologic Map of the Boulder-Fort Collins-Greeley area, Colorado (Colton, R.B., 1978). Based

on geologic maps of the area (Colton, R.B., 1978), the Windsor pipeline segment geology includes:

• Post-Piney Creek alluvium deposited in the Holocene that is composed of dark gray humic, sandy

to gravelly alluvium containing scattered plant remains. This alluvium is typically adjacent to

City of Thornton / Thornton Water Project Pipeline Dewatering Quantity Baseline Report

108405 / Work Package 1 Page-6 Burns & McDonnell

flood plains of streams and terraces that are less than 10 feet above stream level. In some

instances, the alluvium can be underlain by alluvial gravel with a thickness of 5 to 15 feet. The

bedrock that underlays the surficial deposits is the interbedded claystone, siltstone and sandstone

of the undifferentiated, Upper Cretaceous age Denver and Arapahoe formation.

• Pierre Shale (Upper Transition Member): Friable sandstone, soft shaley sandstone containing

thin-bedded sandy shale.

• Eolium – Light Light-brown to reddish-brown to olive-gray deposits of windblown clay, silt,

sand, and granules (generally referred to as loess). Loess is as much as 15 feet thick but generally

is less than 3 feet thick.

Figure 2-2 Surficial Geology Windsor Segment

The geologic map referenced in Figures 2-2 is Palkovic, M., and Morgan, M.L., 2017, Geologic Map of

the Johnstown quadrangle, Larimer and Weld Counties, Colorado: Colorado Geological Survey Open-

file Report 17-02, scale 1:24,000. Based on geologic map described above (Palkovic, M.J., and Morgan,

M.L., 2017), the geology of the Johnston segment of the pipeline includes the following materials:

City of Thornton / Thornton Water Project Pipeline Dewatering Quantity Baseline Report

108405 / Work Package 1 Page-7 Burns & McDonnell

• Eolium: Light Light-brown to reddish-brown to olive-gray deposits of windblown clay, silt, sand,

and granules (generally referred to as loess). Loess is as much as 15 feet thick but generally is

less than 3 feet thick.

• Broadway Alluvium: Well-sorted and well-stratified; size analyses indicate that the average size

distribution is 50% sand, 25% granules and 25% pebbles. Poorly developed brown soil profile.

Along tributaries the Broadway Alluvium is 10 to 15 feet thick.

• Piney Creek Alluvium: Dark-gray sandy to gravelly alluvium containing organic matter. Upper

part is characterized by weakly developed brown soil. Thickness ranges from 0 to 20 feet.

• Colluvium: Bouldery to pebbly sandy silt and clay deposited by gravity and sheet wash on slopes.

May contain and interfinger with alluvium of various ages. Thickness as much as 25 feet but

generally not more than 5 feet.

2.2 Subsurface Investigation A geotechnical investigation was completed by Kumar and Associates and is documented in the project

GDR. The objective of this investigation was to evaluate the subsurface conditions along the pipeline

corridors. Boring logs from the investigation, along with boring location maps, are included in the GDR.

A general summary of the geology encountered in the geotechnical investigation is provided below:

• Flatland areas generally consist of a surficial section of silty to sandy lean clay, with thickness

ranging from approximately zero to 20 feet. These clay sections are underlain by bedrock,

described as claystone/siltstone (referred to as Pierre Shale).

• Areas through river valleys, streams, or natural drainage ways typically include sections of sand

above the shale/claystone bedrock. Depth to bedrock in these areas ranges from roughly 15 to 25

feet.

In addition to the geotechnical field work, a geotechnical laboratory testing program was undertaken to

assist in classification of soil samples and assessment of the hydraulic properties of the soils. Details of

the procedures used for conducting the field work and laboratory testing, and the results of the subsurface

investigations and laboratory testing performed for this project are summarized in the GDR.

City of Thornton / Thornton Water Project Pipeline Dewatering Quantity Baseline Report

108405 / Work Package 1 Page-8 Burns & McDonnell

3.0 QUALITATIVE DEWATERING EVALUATION

Qualitative descriptions of the need for dewatering/groundwater control during pipeline construction were

developed based on the background geologic data described in Section 2. These qualitative descriptions

are based only on the geology and do not include the depth of the pipeline, which is a factor the contractor

must consider when planning construction dewatering. The qualitative levels of dewatering efforts are

classified as follows:

• Limited: These geologic units will likely yield minimal quantities of water during construction.

Groundwater control should be achievable through methods like sump pumping.

• Likely: These geologic units include sands of low to moderate permeability that could produce

groundwater during construction. Groundwater control may require sump pumping and well

points.

• Significant: These geologic units include sands (and some gravel) of moderate to high

permeability that could produce quantities of water during construction that could require active

dewatering with well points or wells.

Areas along the pipeline corridors were assigned qualitative descriptions based on the estimated need for

dewatering/groundwater control during pipeline construction. The descriptions are based on the

anticipated level of effort required to achieve construction dewatering in an open-cut trench installations

within the unconsolidated materials along the pipeline routes.

City of Thornton / Thornton Water Project Pipeline Dewatering Quantity Baseline Report

108405 / Work Package 1 Page-9 Burns & McDonnell

Figure 3-1 Qualitative Dewatering Evaluation Windsor Segment

City of Thornton / Thornton Water Project Pipeline Dewatering Quantity Baseline Report

108405 / Work Package 1 Page-10 Burns & McDonnell

Figure 3-2 Qualitative Dewatering Evaluation Johnstown Segment

City of Thornton / Thornton Water Project Pipeline Dewatering Quantity Baseline Report

108405 / Work Package 1 Page-11 Burns & McDonnell

A general summary of the classification presented in Figures 3-1 and 3-2 is presented below:

• The majority of the Windsor pipeline segment is classified as Limited dewatering potential;

however, the portion of the alignment that is within the Post-Piney Creek alluvium is classified as

Significant. This area includes the Cache la Poudre River valley.

• Nearly all of the Johnstown pipeline segment is classified as Limited dewatering potential. Only

the pipeline segments near the Little Thompson and the Hillsboro Ditch were classified as Likely

dewatering potential.

City of Thornton / Thornton Water Project Pipeline Alignment Dewatering Baseline Report

108405 / Work Package 1 Page-12 Burns & McDonnell

4.0 AQUIFER TESTING

Additional field testing was performed in areas of the pipeline alignment where the qualitative pipeline

construction dewatering requirement was described as Likely or Significant (Section 3). Dewatering

quantities vary proportionally with the hydraulic conductivity of the soil that will be dewatered; therefore,

specific field activities were performed to collect the data need to develop an estimate of the hydraulic

conductivity of the soils that were quantitatively described as having a Likely or Significant potential for

dewatering. Those activities included:

• In-situ hydraulic conductivity tests (slug tests) at boring locations W-6, J-11, J-13 and J-14. The

slug test field procedures and analysis were performed by Kumar & Associates and are described

in the GDR.

• Short duration aquifer pumping tests; performed in test wells that were installed near the Cache

La Poudre and Little Thompson river crossing sites.

4.1 Slug Testing Slug testing was performed by Kumar and Associates and is documented in the project GDR. The slug

testing was performed using a four foot-long, solid “slug”, which consisted of a sand filled 1.50-inch-

diameter plastic pipe. Changes in water levels were recorded using a pressure transducer/data logger.

Both falling head and rising head slug tests were performed. The data collected was analyzed using the

Bouwer-Rice method. Slug test analyses are presented in the GDR and the results are summarized in

Table 4-1.

Table 4-1: Summary of Slug Test Hydraulic Conductivity Results

Piezometer Hydraulic Conductivity Value Feet per day (ft/day)

W-6 3.3

J-11 3.7

J-13 0.069

J-14 0.015

The results presented above indicate that the soils at the W-6 and J-11 borings have a hydraulic

conductivity that is typical for fine grained sand or silt. The soils at borings J-13 and J-14 have a

hydraulic conductivity that is consistent with silt or clay soils.

City of Thornton / Thornton Water Project Pipeline Alignment Dewatering Baseline Report

108405 / Work Package 1 Page-13 Burns & McDonnell

4.2 Aquifer Pumping Tests Short duration (less than eight hour) pumping tests were conducted at the Cache La Poudre and Little

Thompson River crossing sites in order to obtain an estimate of the hydraulic properties of the overburden

materials at these locations. Test pumping wells were constructed near the locations of borings W-5 and

J-15. These test wells were constructed using six-inch diameter PVC casing and PVC screen. The test

wells at Borings W-5 and J-15 were installed as fully penetrating wells, meaning the well screen was

installed from just above the bedrock contact to within a few feet of the ground surface and are screened

across the entire aquifer saturated thickness. Piezometers were installed at both aquifer test sites to

observe water level changes during the pumping test. Like the pumping well, the piezometers were also

completed within the unconsolidated deposits and screened from just above the bedrock surface to near

the ground surface.

Well pumping rates were monitored using an inline flow meter and were also periodically checked by

pumping into a five gallon bucket and measuring the time required to fill the bucket with a stop watch.

All wells were equipped with an In-Situ Level Troll 700 pressure transducer/data logger to monitor and

record changes in water levels observed during the test. In addition to the pressure transducers, manual

water-level data were collected periodically throughout the test using an electronic water-level indicator

to verify the data collected using the pressure transducers. Manual water-level data were recorded in a

field log book and compared to the data from the pressure transducers. A laptop computer was used to

extract the data from the transducers at the end of the tests. A summary of the pumping tests is presented

below.

4.2.1 Cache La Poudre River Site A six-inch diameter test well was installed near the location of boring W-5. This well was used as the

pumping well for the aquifer test performed to characterize the hydrogeology of the unconsolidated

sediments near the Cache La Poudre river crossing. The test well had a total depth of approximately 14.1

feet below ground surface (bgs) and was screened from four to 14 feet bgs. The well casing extended

approximately 3 feet above ground surface. The static water level measured in this test well before the

pumping test began was recorded as 10.2 feet below top of casing, meaning the static depth to water is

approximately 7 feet bgs. The depth to bedrock in the W-5 boring was recorded as 17.5 feet, meaning the

pre-test aquifer thickness at this location is approximately 10.5 feet. The geology of the unconsolidated

materials in the W-5 boring were logged as gravelly and cobbley sand with lesser amounts of clay and

silt. These materials are alluvial deposits of the Post Piney Creek Alluvium.

City of Thornton / Thornton Water Project Pipeline Alignment Dewatering Baseline Report

108405 / Work Package 1 Page-14 Burns & McDonnell

On September 19, 2018, a 335-minute variable rate pumping test was performed using the test well

installed near boring W-5. Two pumping rates were used during the aquifer test, as described below:

• Q1 - 5.5 gallons per minute (gpm) from 0 to 180 minutes;

• Q2 - 10 gpm from 180 to 335 minutes.

Two piezometers were installed near the test well to monitor groundwater levels during the aquifer test;

piezometer MW-NWE was installed 9.4 feet from the test well and piezometer MW-NW was installed

41.2 feet from the test well. A plot of the pumping water level response in the test well in the well is

shown below as Figure 4-1. This figure also illustrates the specific capacity of the pumping well, which

is a measurement of the well discharge per unit drawdown and is presented as gpm per foot of drawdown.

Water levels measurements collected from the piezometers during the aquifer test are presented in

Appendix A. Water level measurements were also collected to monitor recovery of the aquifer after

pumping was stopped. A summary of the water level measurements observed before and at the end of

the aquifer test are provided in Table 4-2.

City of Thornton / Thornton Water Project Pipeline Alignment Dewatering Baseline Report

108405 / Work Package 1 Page-15 Burns & McDonnell

Table 4-2: Summary of Aquifer Test Water Level Conditions Cache La Poudre River Site

Well/Piezometer ID

Distance from Pumping Well (feet)

Depth to Static Water Level (feet below Top of Casing)

Depth to Water at End of Pumping Period (feet bgs)

Drawdown (feet)

Test Well NA 10.19 13.27 3.08

MW NWE 9.4 feet 10.89 11.69 0.80

MW NW 41 feet 10.44 10.74 0.30

Figure 4-1 Pumping Water Level Response for Cache La Poudre Test Well

4.2.2 Little Thompson River Site A six-inch diameter test well was installed near the location of boring J-15. This well was used as the

pumping well for the aquifer test performed to characterize the hydrogeology of the unconsolidated

sediments near the Little Thompson River crossing. The test well had a total depth of approximately 22.7

feet bgs and the well casing extended approximately three feet above ground surface. The static water

level measured in this test well was recorded as 8.1 feet below top of casing, meaning the static depth to

water is approximately five feet bgs. The depth to bedrock in the J-15 boring was recorded as 19.5 feet,

meaning the pre-test aquifer thickness at this location is approximately 14.5 feet. The geology of the

City of Thornton / Thornton Water Project Pipeline Alignment Dewatering Baseline Report

108405 / Work Package 1 Page-16 Burns & McDonnell

unconsolidated deposits encountered at J-15 was described as eolian materials alternating between clayey

sand and sandy lean clay. The geology encountered in boring J-14, drilled on the north side of the Little

Thompson River, showed similar geology to what was observed at J-15 except a poorly graded sand unit

was noted in this boring.

On September 20, 2018, a 180 minute constant rate pumping test was performed using the test well

installed near boring J-15. The well was pumped at a rate of approximately 7.5 gpm. The test was

stopped at 180 minutes because the pumping water level was nearing the suction intake of the well pump.

One piezometer was installed near the test well to monitor groundwater levels during the aquifer test. The

piezometer (LTR MWS) was installed approximately eight feet from the test well. Water level changes in

both the test well and in the piezometer were monitored using the same equipment and approach as

previously described for the Cache La Poudre test. A summary of the water level measurements observed

during the aquifer test are provided in Table 4-3.

Table 4-3: Summary of Aquifer Test Water Level Conditions Little Thompson River Site

Well/Piezometer ID

Distance from Pumping Well (feet)

Depth to Static Water Level (feet bgs)

Depth to Water at End of Pumping Test (feet bgs)

Drawdown (feet)

Test Well NA 8.1 19.29 11.2

LTR MWS 8 feet 8.1 8.73 0.64

4.2.3 Aquifer Test Analysis The water level data collected during the aquifer pumping test were analyzed to estimate the aquifer

parameters that impact how much pumping could be required to achieve dewatering during pipeline

construction. Those aquifer parameters include: aquifer transmissivity, hydraulic conductivity and aquifer

storage. Transmissivity is defined as the rate at which water is transmitted through a unit width of aquifer

under a unit hydraulic gradient. The hydraulic conductivity of the aquifer materials is calculated by

dividing the aquifer transmissivity by the measured aquifer thickness during testing. Aquifer storage, also

known as the storage coefficient, is the volume of water an aquifer releases or takes into storage per unit

surface area of the aquifer per unit change in head.

City of Thornton / Thornton Water Project Pipeline Alignment Dewatering Baseline Report

108405 / Work Package 1 Page-17 Burns & McDonnell

Several standard analytical methods were used to estimate the aquifer parameters for the areas influenced

by the pumping of the test well. The Cooper-Jacob (1946) time drawdown and Theis (1935) recovery

analytical techniques were the primary analytical technique used to estimate the aquifer transmissivity

and storage values for the unconsolidated materials at each river crossing. Details on this analytical

technique are presented in Analysis and Evaluation of Pumping Test Data (Kruseman and deRidder,

1994). The assumptions necessary for the development of each analytical technique used are also

presented in the reference listed above.

The analytical techniques were solved using a Microsoft Excel spreadsheet tool or the pump test analysis

software AQTESOLV®. For both pumping tests, the observed water level changes were first corrected

for changes in aquifer thickness during testing (so that confined aquifer solutions could be used) and then

the corrected water level data were input into the spreadsheet program and AQTESOLV®. The aquifer

test analyses are presented in Appendix A. The estimated aquifer parameter values are summarized

below in Table 4-4 and Table 4-5.

Table 4-4: Summary of Aquifer Test Results Cache La Poudre River Site

Well/ Piezometer ID

Method of Analysis

Depth to Static Water Level* (feet bgs)

Depth to Bedrock (feet bgs)

Transmissivity (ft2/day)

Hydraulic Conductivity (ft/day)

Aquifer Storage (dimensionless)

Test Well (First Step

Only)

Cooper-Jacob Time

Drawdown

7.2 17.5 1,470 143 NA*

MW NW -E Cooper-Jacob Time

Drawdown

1,020 99 0.1

Test Well Theis Recovery

1,060 103 NA*

* Storage cannot be estimated from pumping well data

The aquifer test results for the test performed at the Cache La Poudre River crossing site indicate that the

transmissivity of the unconsolidated materials ranges from 1,000 to 1,400 ft2/day. The saturated thickness

of the unconsolidated materials was measured as approximately 10 feet during testing. The calculated

aquifer transmissivity and hydraulic conductivity values were similar between the test well and

piezometer site, indicating that the unconsolidated materials within the testing radius are relatively

homogenous.

City of Thornton / Thornton Water Project Pipeline Alignment Dewatering Baseline Report

108405 / Work Package 1 Page-18 Burns & McDonnell

Table 4-5: Summary of Aquifer Test Results Little Thompson River Site

Well/ Piezometer ID

Method of Analysis

Depth to Static Water Level* (feet bgs)

Depth to Bedrock (feet bgs)

Transmissivity (ft2/day)

Hydraulic Conductivity (ft/day)

Aquifer Storage (dimensionless)

Test Well Cooper-Jacob Time

Drawdown

8.1 19.5 285 25 NA*

LTR MWS Cooper-Jacob Time

Drawdown

1430 125 0.02

Test Well Theis Recovery

530 NA*

* Storage cannot be estimated from pumping well data

The calculated aquifer transmissivity for unconsolidated materials near the Little Thompson River

crossing range from 260 to 530 ft2/day in the pumping test well to 1,400 ft2/day in the piezometer. The

saturated thickness of the unconsolidated materials was measured as approximately 11.4 feet during

testing. The calculated aquifer transmissivity and hydraulic conductivity values are very different

between the test well and the piezometer site, likely due to desaturation of the aquifer near the test well

and hydraulic inefficiencies of the test well. Since water level responses in the piezometer were not

impacted by well efficiency or desaturation of the aquifer, BMcD considers the aquifer parameters

calculated from the piezometer as representative of the unconsolidated materials and recommends using

these values in evaluation of construction dewatering flow rates.

4.2.4 Water Quality Water samples were collected from the discharge of both test wells in order to characterize the quality of

the water being discharged. The samples were analyzed only for selenium and total suspended solids, as

required for compliance with our site specific Colorado Department of Public Health and Environment

(CDPHE) discharge permit. Sample results are included in Appendix B. The nomenclature used for the

samples is CLP PW1 (Cache La Poudre River test well) and LTR PW1 (Little Thompson River test well).

The sample results indicate that selenium was not detected in the groundwater from the Cache La Poudre

site, but selenium was detected at 21.3 and 21.9 micrograms per liter (ug/L) at the Little Thompson River

site. Total suspended solids ranged from non-detect (ND) at the Cache La Poudre site to 56.8 milligrams

per liter (mg/L) at the Little Thompson River site.

City of Thornton / Thornton Water Project Pipeline Alignment Dewatering Baseline Report

108405 / Work Package 1 Page-19 Burns & McDonnell

5.0 DEWATERING ESTIMATES

A range of plausible dewatering flow rates was developed for the locations along the pipeline route that

were identified as a likely or significant dewatering classification (Figure 3-1 and 3-2). These locations

include:

• Borings W-1 through W-6 along the Windsor segment of the pipeline, and

• Borings J-11/J-12 and J-14/J-15 Johnstown segment of the pipeline.

The dewatering estimates were developed using the geotechnical information presented in the GDR and

the aquifer pumping test analysis presented within this Report. Estimated dewatering quantities are

provided in gallons per day (gpd) for several hypothetical target drawdown scenarios. The amount of

drawdown required will depend upon construction methods. Since dewatering volumes depend upon the

exact construction methods, time of year/season, and exact pipeline burry depths, the calculations

presented in this memorandum focused on estimating the dewatering rate required along a 100 foot long

excavation, for several target drawdown values.

5.1 Windsor Alignment The pipeline alignment corresponding with geotechnical borings W-1 through W-6 was classified as areas

where significant dewatering could be required during construction of the pipeline (see Figure 3-1). This

classification was based solely on the geology observed in the geotechnical boring and did not include

construction considerations such as the burial depth of the pipeline. This portion of the pipeline

alignment corresponds approximately with Stations 0+00 to 56+00. Project drawings indicate that the

pipeline burial depth (top of pipe) in this portion of the alignment is a minimum of five feet and often

more than ten feet below existing grade. This is true for this entire portion of the alignment other than the

undercrossing of the Cache La Poudre River which will be completed by means of trenchless technology.

The water level data presented in the GDR cross sections for borings W-1 through W-6 indicate that the

depth to stabilized (post drilling) groundwater generally ranges from six to eight feet below grade. The

stabilized water level measurements were collected from piezometers several days to over one month

following the drilling of the boring and correlate to the water level measurement observed from the Cache

La Poudre test well and piezometers.

Along the majority of this portion of the pipeline route, at least some portion of the pipeline is typically

below the observed depth to water. An estimate of dewatering requirements for this portion of the

pipeline route was developed for excavations that are performed below the static groundwater level. The

City of Thornton / Thornton Water Project Pipeline Alignment Dewatering Baseline Report

108405 / Work Package 1 Page-20 Burns & McDonnell

dewatering estimate was developed using an equation for long, narrow trenches (Equation 6.12 in

Construction Dewatering, J.P. Powers (1992), 103pg., 2nd ed. John Wiley and Sons, Inc). Dewatering

estimates were developed using the following assumptions:

• Depth to the static groundwater level equals 7 feet bgs.

• Pumping time equals one day.

• Aquifer storage equals 0.1. This value was estimated from the aquifer pumping test.

• Hydraulic conductivity – 140 ft/day. This is the higher value calculated from the aquifer pumping

test.

Given the assumptions listed above, an estimate of the dewatering flow rate per 100 feet of trench

required to achieve a dewatered condition is presented in Table 5-1. This table presents baseline

conditions for dewatering the groundwater level to near the top of the bedrock surface. The required

drawdown needed to install the pipeline will vary based on location within the alignment, burial depth,

construction methods, and time of year of construction. Target dewatering levels should be determined

based on site specific geotechnical conditions and pipeline installation requirements. Calculations are

presented in Appendix C.

Table 5-1: Baseline Dewatering Estimate Windsor Alignment Stations 0+00 to 56+00

Excavation Trench Length (foot)

Excavation Trench Width (foot)

Bottom Depth of Excavation (feet)

Depth to Dewatered Condition (feet)

Target Dewatering Drawdown (feet)

Estimated Dewatering Rate (gallons per day)

100 8 15.0 16 9 208,000

For baseline purposes, in the open-cut sections, a groundwater pumping rate of 145 gpm will exist along any 100 ft portion of the Windsor Alignment Stations 0+00 to 56+00.

5.2 Johnston Alignment In Phase 1 (Desktop Review), the pipeline alignment corresponding with geotechnical borings J-11, J-12,

J-14 and J-15 was classified as areas where dewatering could likely be required during construction of the

pipeline (see Figure 3-2). This classification was based solely on the geology observed in the geotechnical

boring and did not include construction considerations such as the burial depth of the pipeline. Project

drawings indicate that the pipeline burial depth is a minimum of 4.5 feet and more than ten feet below

existing grade near the Hillsborough Ditch.

City of Thornton / Thornton Water Project Pipeline Alignment Dewatering Baseline Report

108405 / Work Package 1 Page-21 Burns & McDonnell

The water level data presented in the GDR cross sections for the Johnston Alignment borings shows a

depth to water generally ranging from five to ten feet bgs. Along the majority of this portion of the

pipeline route, the burial depth is typically within the observed depth to water; however, the

unconsolidated materials along the majority of the alignment are low permeability and are not anticipated

to yield significant volumes of water.

Construction dewatering could be required along the pipeline alignment that includes the crossing of the

Hillsborough Ditch and the Little Thompson River. This corresponds approximately with Stations

134+00 and 140 +00 (Hillsborough Ditch) and stations 155+00 to 165+00 (Little Thompson River). An

estimate of dewatering requirements for the areas of the pipeline route was developed using the

previously described procedure. Assumptions for the calculations are described below:

• Depth to water equals 8 feet bgs.

• Pumping time equals one day.

• Aquifer storage equals 0.02. This value was estimated from the aquifer pumping test.

• Hydraulic conductivity – 125 ft/day. This is the higher value calculated from the aquifer pumping

test.

Given the assumptions listed above, a range of dewatering flow rates per 100 feet of trench was

developed and is presented in Table 5-2. This table presents baseline conditions for dewatering the

groundwater level to near the top of the bedrock surface. The required drawdown needed to install the

pipeline will vary based on location within the alignment, burial depth, construction methods, and time of

year of construction. Target dewatering levels should be determined based on site specific geotechnical

conditions and pipeline installation requirements. Calculations are presented in Appendix C.

Table 5-2: Baseline Dewatering Estimate Johnston Alignment Stations 134+00 to 140+00 and Stations 155+00 to 165+00

Excavation Trench Length (foot)

Excavation Trench Width (foot)

Bottom Depth of Excavation (feet)

Depth to Dewatered Condition (feet)

Target Dewatering Drawdown (feet)

Estimated Dewatering Rate (gallons per day)

100 8 18.0 19 11 160,000

For baseline purposes, in the open-cut sections, a groundwater pumping rate of 110 gpm will exist along any 100 ft portion of the Johnston Alignment Stations 134+00 to 140+00 (Hillsborough Ditch) and Stations 155+00 to 165+00 (Little Thompson River).

City of Thornton / Thornton Water Project Pipeline Alignment Dewatering Baseline Report

108405 / Work Package 1 Page-22 Burns & McDonnell

5.3 Limited Dewatering Classification As presented in Section 3, the majority of both pipeline alignments were classified as having a limited

potential for dewatering during construction. Specifically, these locations include:

• Windsor Alignment Stations 56+00 to End Station.

• Johnston Alignment Stations 00+00 to 134+00, Stations 140+00 to 155+00, and Stations 165+00

to End Station.

For baseline purposes, a groundwater pumping rate of 10 gpm will exist along any 100 ft open-cut section of the Windsor and Johnston Alignments classified as Limited dewatering. By project stationing, these alignment sections are:

• Windsor Alignment Stations 56+00 to End Station.

• Johnston Alignment Stations 00+00 to 134+00, Stations 140+00 to 155+00, andStations 165+00 to End Station.

City of Thornton / Thornton Water Project Pipeline Alignment Dewatering Baseline Report

108405 / Work Package 1 Page-23 Burns & McDonnell

6.0 REFERENCES

Brierly Associates, 2018a. Geotechnical Baseline Report – Draft Thornton Water Project Work Package 1

Windsor Segment. Windsor, Colorado. December.

Brierly Associates, 2018b. Geotechnical Baseline Report – Draft Thornton Water Project Work Package 1

Thornton Segment. Thornton, Colorado. December.

Colton, R.B., 1978. U.S. Geological Survey Geologic Investigations Series I-855-G, Geologic Map of the

Boulder-Fort Collins-Greeley area, Colorado.

Cooper, H. H., and Jacob, C.E. 1946. A Generalized Graphical Method for Evaluating Formation

Constants and Summarizing Well Field History. Amer. Geophys. Union, Vol. 27: pp.526-534.

Kruseman, G.P., and de Ridder, N.A. 1994. Analysis and Evaluation of Pumping Test Data.

International Institute for Land Reclamation and Improvement. The Netherlands.

Kumar and Associates, Inc., 2018. Geotechnical Data Report Thornton Water Line Phase I Windsor And

Johnstown Segments. Weld County, Colorado. November.

Palkovic, M.J., and Morgan, M.L., 2017. Palkovic, M., and Morgan, M.L., 2017, Geologic Map of the

Johnstown quadrangle, Larimer and Weld Counties, Colorado: Colorado Geological Survey Open-file

Report 17-02.

Powers, J.P., 1992. Construction Dewatering, 2nd edition. John Wiley and Sons, Inc.

Theis, C.V., 1935. The Relation Between the Lowering of the Piezometric Surface and the Rate and

Duration of Discharge of a Well Using Groundwater Storage. Am. Geophys. Union Trans., vol. 16, pp.

519-524.

City of Thornton / Thornton Water Project Pipeline Alignment Dewatering Baseline Report

108405 / Work Package 1 Page-23 Burns & McDonnell

APPENDIX A – AQUIFER PUMPING TEST RESULTS

Cache La Poudre RiverTest Well

Cache La Poudre RiverMonitoring Well

Cache La Poudre RiverMonitoring Well

0

0.5

1

1.5

2

2.5

3

3.5

1 10 100 1000 10000

Res

idua

l Dra

wdo

wn

(ft)

Ratio t/t'

THORNTON WATER LINE PHASE I WINDSOR AND JOHNSTOWN SEGMENTSCache La Poudre Test Well Site

Aquifer Test AnalysisTheis Recovery Method

recovery

T = (264*7.5 gpm)/0.25 ftT = 7,920 gpd/ft

Little Thompson River Test Well

Little Thompson RiverMonitoring Well

0

2

4

6

8

10

12

1 10 100 1000 10000

Res

idua

l Dra

wdo

wn

(ft)

Ratio t/t'

THORNTON WATER LINE PHASE I WINDSOR AND JOHNSTOWN SEGMENTS

Little Thompson River Test Well SiteAquifer Test Analysis

Theis Recovery Method

recovery

T = (264*7.5 gpm)/0.5 ftT = 3,960 gpd/ft

City of Thornton / Thornton Water Project Pipeline Alignment Dewatering Baseline Report

108405 / Work Package 1 Page-24 Burns & McDonnell

APPENDIX B – WATER QUALITY RESULTS

#=CL#

October 08, 2018

LIMS USE: FR - DANIEL CLEMENTLIMS OBJECT ID: 60281602

60281602Project:Pace Project No.:

RE:

Daniel ClementBurns & McDonnellP.O. Box 419173Kansas City, MO 64141

Thornton Water Project

Dear Daniel Clement:Enclosed are the analytical results for sample(s) received by the laboratory on September 24, 2018.The results relate only to the samples included in this report. Results reported herein conform to themost current, applicable TNI/NELAC standards and the laboratory's Quality Assurance Manual,where applicable, unless otherwise noted in the body of the report.

If you have any questions concerning this report, please feel free to contact me.

Sincerely,

Keegan [email protected]

PM Lab Management(785)827-1273

Enclosures

REPORT OF LABORATORY ANALYSISThis report shall not be reproduced, except in full,

without the written consent of Pace Analytical Services, LLC.

Pace Analytical Services, LLC525 N. 8th StreetSalina, KS 67401

(785)827-1273

Page 1 of 12

#=CP#

CERTIFICATIONS

Pace Project No.:Project:

60281602Thornton Water Project

Kansas Certification IDs9608 Loiret Boulevard, Lenexa, KS 66219Missouri Certification Number: 10090Arkansas Drinking WaterWY STR Certification #: 2456.01Arkansas Certification #: 18-016-0Arkansas Drinking WaterIllinois Certification #: 004455Iowa Certification #: 118Kansas/NELAP Certification #: E-10116

Louisiana Certification #: 03055Nevada Certification #: KS000212018-1Oklahoma Certification #: 9205/9935Texas Certification #: T104704407Utah Certification #: KS00021Kansas Field Laboratory Accreditation: # E-92587Missouri Certification: 10070Missouri Certification Number: 10090

REPORT OF LABORATORY ANALYSISThis report shall not be reproduced, except in full,

without the written consent of Pace Analytical Services, LLC.

Pace Analytical Services, LLC525 N. 8th StreetSalina, KS 67401

(785)827-1273

Page 2 of 12

#=SS#

SAMPLE SUMMARY

Pace Project No.:Project:

60281602Thornton Water Project

Lab ID Sample ID Matrix Date Collected Date Received

60281602001 CLP PW1 0950 Water 09/19/18 09:50 09/24/18 15:52

60281602002 CLP PW1 1500 Water 09/19/18 15:00 09/24/18 15:52

60281602003 LTR PW1 1355 Water 09/20/18 13:55 09/24/18 15:52

60281602004 LTR PW1 1210 Water 09/20/18 12:10 09/24/18 15:52

REPORT OF LABORATORY ANALYSISThis report shall not be reproduced, except in full,

without the written consent of Pace Analytical Services, LLC.

Pace Analytical Services, LLC525 N. 8th StreetSalina, KS 67401

(785)827-1273

Page 3 of 12

#=SA#

SAMPLE ANALYTE COUNT

Pace Project No.:Project:

60281602Thornton Water Project

Lab ID Sample ID MethodAnalytesReported LaboratoryAnalysts

60281602001 CLP PW1 0950 SM 2540D 1 PASI-KJDA

60281602002 CLP PW1 1500 SM 2540D 1 PASI-KJDA

60281602003 LTR PW1 1355 EPA 6020 1 PASI-KJGP

SM 2540D 1 PASI-KJDA

60281602004 LTR PW1 1210 EPA 6020 1 PASI-KJGP

SM 2540D 1 PASI-KJDA

REPORT OF LABORATORY ANALYSISThis report shall not be reproduced, except in full,

without the written consent of Pace Analytical Services, LLC.

Pace Analytical Services, LLC525 N. 8th StreetSalina, KS 67401

(785)827-1273

Page 4 of 12

#=AR#

ANALYTICAL RESULTS

Pace Project No.:Project:

60281602Thornton Water Project

Sample: CLP PW1 0950 Lab ID: 60281602001 Collected: 09/19/18 09:50 Received: 09/24/18 15:52 Matrix: Water

Parameters Results Units DF Prepared Analyzed CAS No. QualReport Limit

Analytical Method: SM 2540D2540D Total Suspended Solids

Total Suspended Solids ND mg/L 09/26/18 17:095.0 1

Sample: CLP PW1 1500 Lab ID: 60281602002 Collected: 09/19/18 15:00 Received: 09/24/18 15:52 Matrix: Water

Parameters Results Units DF Prepared Analyzed CAS No. QualReport Limit

Analytical Method: SM 2540D2540D Total Suspended Solids

Total Suspended Solids ND mg/L 09/26/18 17:105.0 1

Sample: LTR PW1 1355 Lab ID: 60281602003 Collected: 09/20/18 13:55 Received: 09/24/18 15:52 Matrix: Water

Parameters Results Units DF Prepared Analyzed CAS No. QualReport Limit

Analytical Method: EPA 6020 Preparation Method: EPA 30106020 MET ICPMS

Selenium 21.3 ug/L 10/07/18 14:04 7782-49-210/05/18 11:131.0 1

Analytical Method: SM 2540D2540D Total Suspended Solids

Total Suspended Solids 56.8 mg/L 09/26/18 17:285.0 1

Sample: LTR PW1 1210 Lab ID: 60281602004 Collected: 09/20/18 12:10 Received: 09/24/18 15:52 Matrix: Water

Parameters Results Units DF Prepared Analyzed CAS No. QualReport Limit

Analytical Method: EPA 6020 Preparation Method: EPA 30106020 MET ICPMS

Selenium 21.9 ug/L 10/07/18 14:09 7782-49-210/05/18 11:131.0 1

Analytical Method: SM 2540D2540D Total Suspended Solids

Total Suspended Solids 23.8 mg/L 09/26/18 17:285.0 1

REPORT OF LABORATORY ANALYSISThis report shall not be reproduced, except in full,

without the written consent of Pace Analytical Services, LLC.Date: 10/08/2018 04:39 PM

Pace Analytical Services, LLC525 N. 8th StreetSalina, KS 67401

(785)827-1273

Page 5 of 12

City of Thornton / Thornton Water Project Pipeline Alignment Dewatering Baseline Report

108405 / Work Package 1 Page-25 Burns & McDonnell

APPENDIX C – DEWATERING CALCULATIONS

Client: City of Thornton, CO REV0 date:11/30/2018

Project:THORNTON WATER LINE PHASE I ‐ Windsor Segment Dewatering Estimate

Powers Equation 6.12 ‐ Construction Dewatering, J.P. Powers (1992), 103pg., 2nd ed. John Wiley and Sons, Inc

Q =  pumping rate in ft3/d

K =  hydraulic conductivity in ft/d

Calculation Variabl Value    Description Note:

7Depth to static water (ft)

17

Depth of base of geologic unit to be dewatered (ft)

Approximate depth of bedrock unit below excavation depths

H10

Thickness of geolgic unit prior to dewatering (ft)

K140

ft/day

r w 5 Distance from well point to trench center line (feet)

Calculate Ro for 

t (day) 1 Pumping time (days)

T (ft2/d) 1400 Aquifer Transmissivity (ft2/day)

S 0.10 Aquifer Storage (dimensionless)

R  o (ft) 177 Radius of Influence (ft)

Calculate L for trench equatoin

L (feet)  89 Distance to Line Source of Recharge

L = 1/2 Ro (Powers, 1992)

Foundation  IDa ‐ Excavation Length (ft)

b ‐ Excavation Width (ft)

Bottom Depth of Excavation (ft)Depth to dewatered condition (feet)        

Dewatering Drawdown (feet)

Thickness of aquifer prior to dewatering (ft)

hw ‐ Thickness of aquifer after 

dewatering (ft)

Equivalent Radius (rw) (ft)

Estimated dewatering Q (gal/day) from the ends of the excavation

Estimated dewatering Q (gal/day) from the sides of the excavation

Total Estimated Dewatering per 100 Foot Trench Length (gal/day)

Pipeline Trench* 100 8 7.0 8 1 10.0 9 5.0 17,512 22,421 39,933

Pipeline Trench* 100 8 9.0 10 3 10.0 7 5.0 47,006 60,183 107,189

Pipeline Trench* 100 8 11.0 12 5 10.0 5 5.0 69,126 88,505 157,631

Pipeline Trench* 100 8 13.0 14 7 10.0 3 5.0 83,873 107,386 191,258

Pipeline Trench* 100 8 15.0 16 9 10.0 1 5.0 91,246 116,826 208,072

Flow from ends Flow from SidesNotes

rw is calculated for an excavation length and width that are 20% larger than the needed excavation size.

*Pipeline dewatering estimate is for a 100 foot pipeline length.  

Windsor Segment Station 0+00 to 56+00

Based on geotechnical report

H = hydraulic head of the original water table (ft) 

hw = hydraulic head at maximum dewatering (ft)

Ro =  radius of influence of well (ft)

rw = equivalent radius of the well (ft)

Hydraulic conductivity from aquifer pumping test

Pipeline Trench Dewatering Estimate

ln2 2

Client: City of Thornton, CO REV0 date:11/30/2018

Project:THORNTON WATER LINE PHASE I ‐ Johnston Segment Dewatering Estimate

Powers Equation 6.12 ‐ Construction Dewatering, J.P. Powers (1992), 103pg., 2nd ed. John Wiley and Sons, Inc

Q =  pumping rate in ft3/d

K =  hydraulic conductivity in ft/d

Calculation Variabl Value    Description Note:

8Depth to static water (ft)

20

Depth of base of geologic unit to be dewatered (ft)

Approximate depth of bedrock unit below excavation depths

H12

Thickness of geolgic unit prior to dewatering (ft)

K125

ft/day

r w 5 Distance from well point to trench center line (feet)

Calculate Ro for 

t (day) 1 Pumping time (days)

T (ft2/d) 1500 Aquifer Transmissivity (ft2/day)

S 0.02 Aquifer Storage (dimensionless)

R  o (ft) 411 Radius of Influence (ft)

Calculate L for trench equatoin

L (feet)  205 Distance to Line Source of Recharge

L = 1/2 Ro (Powers, 1992)

Foundation  IDa ‐ Excavation Length (ft)

b ‐ Excavation Width (ft)

Bottom Depth of Excavation (ft)Depth to dewatered condition (feet)        

Dewatering Drawdown (feet)

Thickness of aquifer prior to dewatering (ft)

hw ‐ Thickness of aquifer after 

dewatering (ft)

Equivalent Radius (rw) (ft)

Estimated dewatering Q (gal/day) from the ends of the excavation

Estimated dewatering Q (gal/day) from the sides of the excavation

Total Estimated Dewatering per 100 Foot Trench Length (gal/day)

Pipeline Trench* 100 8 8.0 9 1 12.0 11 5.0 15,324 10,470 25,794

Pipeline Trench* 100 8 9.0 10 2 12.0 10 5.0 29,316 20,030 49,346

Pipeline Trench* 100 8 12.0 13 5 12.0 7 5.0 63,296 43,246 106,542

Pipeline Trench* 100 8 15.0 16 8 12.0 4 5.0 85,284 58,268 143,552

Pipeline Trench* 100 8 18.0 19 11 12.0 1 5.0 95,278 65,096 160,374

Flow from ends Flow from SidesNotes

rw is calculated for an excavation length and width that are 20% larger than the needed excavation size.

*Pipeline dewatering estimate is for a 100 foot pipeline length.  

Windsor Segment Station 0+00 to 56+00

Based on geotechnical report

H = hydraulic head of the original water table (ft) 

hw = hydraulic head at maximum dewatering (ft)

Ro =  radius of influence of well (ft)

rw = equivalent radius of the well (ft)

Hydraulic conductivity from aquifer pumping test

Pipeline Trench Dewatering Estimate

ln2 2

Burns & McDonnell World Headquarters 9400 Ward Parkway

Kansas City, MO 64114 O 816-333-9400 F 816-333-3690

www.burnsmcd.com