Thomas Jefferson National Accelerator Facility
Page 1
UITF Progress meeting
Approved Labyrinth
Fresh air pulled through “chicken wire” gate
Thomas Jefferson National Accelerator Facility
Page 2
UITF Progress meeting
Improving the ventilation in Cave2
Add a wall to help direct air flow
Add ductwork leading to rear of Cave2
Thomas Jefferson National Accelerator Facility
Page 3
UITF Progress meeting
Thomas Jefferson National Accelerator Facility
Page 4
UITF Progress meeting
Cryo lines from CTF along wallGN2 lines along the wall SF6 tank
Thomas Jefferson National Accelerator Facility
Page 5
UITF Progress meeting
Helium dewars: 1,000 liters, 500 liters, 50 liters = 1,550 L
¼ CM LHe capacity, ~ 400 L (?)
Total LHe supply from CTF….
Nitrogen line at 80 psi thru a 3/8 inch pipe = 22 cfm or 1,320 cubic feet per hour
SF6 inside vessel that hold HV power supply: 25 ft3 filled to 70 psi, ~ 54 lbs: total volume if released? 144 ft3
Helium, Nitrogen and SF6
Thomas Jefferson National Accelerator Facility
Page 6
UITF Progress meeting
Rough Dimensions
Cave 1: 12’ x 12’ x 60’ ~ 8,640 ft3
Cave 2: 22’ x 54’ x 12’ ~ 14,256 ft3
Dick Owen made a more exact calculation: 25,704 ft3
Matt’s loose estimate, total volume: 22,896 ft3
Exhaust vent to outside
Exhaust vent to high bay
exit/entrance
exit/entrance
Thomas Jefferson National Accelerator Facility
Page 7
UITF Progress meeting
131211975432
6’ tall Empty space below this metal sheet
66’
14’
4’
10’
Ceiling tiles = 24 Concrete blocks 14’ longThere are two “styles” of Ceiling tile, square and rectangular cross sections
New stairs here
Thomas Jefferson National Accelerator Facility
Page 8
UITF Progress meeting
131211975432
6’ tall Empty space below this metal sheet
66’
4’
Ceiling tiles = 24 Concrete blocks 14’ longThere are two “styles” of Ceiling tile, square and rectangular cross sections
New stairs here
klystrons
Completely empty
One waveguide and LCW
Two waveguides
New electric here
HDIce
14’ 10’
Thomas Jefferson National Accelerator Facility
Page 9
UITF Progress meeting
Thomas Jefferson National Accelerator Facility
Page 10
UITF Progress meeting
Walkway:Backs of racks here
Metal plate, rad shielding
Electronics racks, side view
Front of rack here
Front of rack here
Thomas Jefferson National Accelerator Facility
Page 11
UITF Progress meeting
Device Qty AC Power Each Total AC Power LCW Location
Gun High Voltage power supply
1 30A / 208 VAC 3 phase
30A / 208 VAC 3 phase
None Top of cave
ODH rack needs emergency power
1 20A/120 VAC single phase
20A/120 VAC single phase
Nonefrom an emergency power loop
Trim Rack 2 50A / 208 VAC 3 phase
100A/208 3Phase None Top of
caveChicane power supply 1 30A / 208 VAC 3
phase30A/208 3Phase None Top of
caveChicane magnets 3 none 4
GPM Cave
LLRF/Master Oscillator 1 20A / 120VAC
single phase
20A / 120VAC single phase
None Top of cave
Water skids for chopper & buncher
2 20A / 208 VAC 3 phase
40A/208 3Phase
4 GPM Cave
Solid state RF amps for choppers
420 Amp / 208 VAC single phase
80 Amp / 208 VAC single - phase to phase
Top of cave
4 Amplifiers at 400 Watts each
Solid state amplifier for 750 MHz buncher
1 25A/480 VAC 3 phase
25A/480VAC three phase
Top of cave
Cathode Power Supply for klystrons
1 100A / 480VAC 3 phase
100A / 480VAC 3 phase
None Top of cave
also for High power RF 1
208 VAC three phase and 120 VAC
Top of cave
Klystrons 3 none 16.5 GPM
Top of cave
5.5 GPM each
Circulators & loads 3 none 6
GPMTop of cave
2 GPM each
Cave Vacuum & Utility power
20A / 208 3Phase XX A / 240 VAC X circuits 20 A / 120 VAC
20A/208 3Phase 240 VAC
Cave
Ion Pump power supplies 1 20A 120VAC
single phase20A 120VAC single phasenone Top of
cave
Control Racks including cryo 12 20A / 120VAC
single phase
12 circuits@ 120 VAC@ 20 Amps
Top of cave
Control Room 1 20A / 120VAC single phase
4 circuits@ 120 VAC@ 20 Amps
Control Room
Inside the Cave 20A / 120VAC single phase
12 circuits@ 120 VAC@ 20 Amps
along perimeter of the cave
HDIce gets power from Big Bertha. Big Bertha will get power fed from a distribution panel in the annex. This distribution panel is attached to the generator. Ground isolated linesWalt thinks we might want two additional 480 VAC welding receptacles installed inside the cave too. These additional lines do not need to be attached to a generator.
Thomas Jefferson National Accelerator Facility
Page 12
UITF Progress meeting
Thomas Jefferson National Accelerator Facility
Page 13
UITF Progress meeting
Walt: electronics racks platform design, for Neil to build
Neil Wilson: rack platform, unistrut to wall, temporary stairs, LCW, GN2 and compressed air
Layout of utilities added to unistrut
Have facilities remove stuff from control room wall exterior
Find a concrete block for empty space near control room
Have Walter move concrete block…