This presentation is for educational purposes only

Refer to the project RFP for specific details and instructions

If there are any inconsistencies, the RFP and Amendments shall take precedence over this

presentation

Page 2: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Best-Value Procurement

University of Manitoba Arizona State University

9/11/13

Page 3: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

19 Years | 210+ Publications | 550+ Presentations19 Years | 210+ Publications | 550+ Presentations

1,500+ Projects | $4.6 Billion Procured1,500+ Projects | $4.6 Billion Procured

Page 4: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

What is Best-Value?What is Best-Value?

• Win-Win

• Client:– Outsource to experts– Higher performance– Less management and resources

• Vendor– Control of project/service– Ability to increase profit by

maximizing their efficiency

44

Page 5: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Traditional ModelTraditional Model• Client assumes they have expertise• Client makes decisions on what they think they need to be successful• Client prepares minimum standards• Client prepares documents that describe everything they need/require• Client competes vendors, but primary award factor is cost

55

Inconsistent performance

Inefficiencies

Lack of performance metrics

Lack of accountability

Page 6: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Best-Value ModelBest-Value Model• Experts know more about the project/service than the client• Client does their best job at defining what they think they need• Experts act in the clients best interest• Expert can optimize the service by reducing inefficiencies• Think about the project, use past experience, and layout a specific plan• Focus on the key personnel, lessons learned, and risk mitigation

66

What the Owner Described

What the Owner Really Needed

What the Consultant Specified

What the Contractors Installed

Page 7: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the
Page 8: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Factors For SuccessFactors For Success• Fair (state/follow rules)

• Open (open to all with experience)

• Impartial and Transparent (minimize evaluator bias / provide debriefing)

• Efficient (minimize efforts)

• Award based on value

88

Page 9: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

99

Best Value SystemBest Value System

Page 10: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

1010

Phase 2Phase 2

Page 11: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

1111

Phase 2 is Most CriticalPhase 2 is Most Critical

52 Days 32 Days

High Level Overview

Verify EverythingVendors Are ExpertsDetails

Page 12: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

What is the Clarification Period? What is the Clarification Period? (Proactive vs Reactive)(Proactive vs Reactive)

Minimize All Surprises!!!Minimize All Surprises!!!

Page 13: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

What Could Cause a SurpriseWhat Could Cause a Surprise• Delivering something that doesn’t work• Delivering something that isn’t what the client is expecting• Delivering something that isn’t what the client needed• Requiring the client to do something (that they did not know they had to do)• Requiring things from the client that they cannot provide• Expecting that something will happen as planned• Assuming that things are clear and understandable• Assuming that things will be done/occur as planned• Changes that impact cost• Changes that impact time• Poor satisfaction

1313

Page 14: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

What is the Greatest Source of What is the Greatest Source of Risk?Risk?

1414

Page 15: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

How To Minimize SurprisesHow To Minimize Surprises• Perform a detailed cost verification

– Detailed cost breakdown– Identify why the cost proposal may be significantly different from competitors– Review big-ticket items– Review value added options– Identify how payments will be made and all expectations regarding finances– Provide a pro-forma

• Carefully preplan the project in detail– Coordinate the project/service with all critical parties– Revisit the sites to do any additional investigating– Prepare a detailed project plan – Provide a marketing plan– Provide a transitioning plan & schedule (if the Offeror is not the incumbent)

1515

Page 16: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

How To Minimize SurprisesHow To Minimize Surprises• Align expectations

– Identify any potential deal breakers– Clearly identify what is included and excluded in the proposal– Review any unique requirements with the University– Clearly identify University roles and responsibilities– Review and approve all contract terms and conditions– Introduce the vendors critical personnel to the University team– Provide plan for critical staff retention and plan if these individuals leave

• Identify and mitigate all project risks– Address all client concerns and risks – Address all risks identified by other proposers– Address all risks that occurred on previous past projects

1616

Page 17: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

How To Minimize SurprisesHow To Minimize Surprises• Identify and mitigate all uncontrollable risks

– Identify all risks or activities not controlled by the Offeror– Identify the impact of the risks– Identify what the University can do to mitigate the risks– Address how unforeseen risks will be managed

• Identify all assumptions– Prepare a list of all proposal assumptions (with associated impacts)

• Performance reports and metrics– Identify how the Offeror will track and document their performance– Provide an actual monthly performance metric report– Identify how the University will document this service as a success– Review the Weekly Risk Report

1717

Page 18: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

1818

Pre Planning Reduces RiskPre Planning Reduces Risk

52 Days 32 Days

Page 19: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Pre Award DocumentPre Award Document1. Financial Summary (financial details, how funding will work, etc)

2. Transition Plan & Schedule (showing major milestones, risky activities, client actions, etc)

3. Project Risks/Concerns (all controllable risks/concerns, all non-controllable risks/solutions)

4. Assumptions (all project assumptions with associated impacts, identify what you need from the client and have a plan for obtaining it, roles and responsibilities of the client, etc )

5. Performance Metrics (how the vendor will monitor performance, document success, metrics used, frequency, baseline for comparison, how will it assist the client, etc)

6. Scope of Work (plan of action, detailed work plan, how technical requirements will be met, baseline expectations, implementation plan, transitional plan, staffing plan, communication plan, training plan, organization change plan, what’s included, excluded, etc)

7. Contract (language, terms and conditions, etc)

1919

Page 20: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

2020

Guide Us / Help Us See & Guide Us / Help Us See & UnderstandUnderstand

Page 21: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

2121

Pre Planning Reduces RiskPre Planning Reduces Risk

• Financial Summary• Project Plan• Project Risks/Concerns• Assumptions• Performance Metrics• Contract

Page 22: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

2222

Keep Phase 2 In Mind During Keep Phase 2 In Mind During Phase 1Phase 1

Page 23: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

2323

Best Value SystemBest Value System

Page 24: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Your Proposal Must Minimize Your Proposal Must Minimize SurprisesSurprises• Delivering something that doesn’t work

• Delivering something that isn’t what the client is expecting

• Delivering something that isn’t what the client needed

• Changes that add more cost

• Changes that add more time

2424

Page 25: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

QuestionsQuestions• All proposers must meet the minimum requirements / objectives

• If a proposer does not understand, they must ask a question prior to submitting a proposal. Fax/Email the University Representatives below:– Procurement University Representative - Paul Dugal – Technical University Representative - Andrea Edmunds

• If a proposer cannot meet a requirement, they must inform the client prior to proposing– Identify which requirement cannot be met– Provide recommendations or alternatives that the client may consider– The client will then issue an addendum with their response

2525

Page 26: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Proposal PackageProposal Package• Any proposal that does not adhere to the requirements in this RFP will be

deemed non responsive and rejected.

1. Attachment A – Proposal Form2. Attachment B* – Team Qualifications3. Attachment C* – Project Plan4. Attachment D* – Risk Assessment Plan5. Attachment E* – Value Assessment Plan6. Attachment F – Reference List7. Attachment G – Survey Questionnaires 8. Attachment H – Past Performance Information Scores9. Attachment I – Cost Proposal Form10.A CD or USB containing the proposal as required in Section 4

* Indicates that the entire Attachment must be anonymous. These Attachments must NOT contain any names (company, personnel, project, product, etc.) that can be used to identify the Offeror.

2626

Page 27: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Criteria and WeightsCriteria and Weights

2727

No Criteria Weights

1 Total Financial Contribution 300

2 Interview of Onsite General Manager 300

3 Risk Assessment Plan 150

4 Value Assessment Plan 100

5 Team Qualifications 50

6 Past Performance Information – Firm 50

7 Past Performance Information – General Manager 50Total Points: 1,000 Points

Page 28: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Dominant InformationDominant Information

2828

10 OZ$3.75

A B C

10 OZ$3.50

10 OZ$3.99

Page 29: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Which would you buy?Which would you buy?(If you need to buy Cocoa Puffs)(If you need to buy Cocoa Puffs)

2929

10 OZ$3.50

A B C

12 OZ$1.25

14 OZ$2.99

Page 30: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

““Dominant Information”Dominant Information”

3030

Scenario A Scenario B

Page 31: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Attachment A – Proposal FormAttachment A – Proposal Form

3131

Page 32: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Attachments B, C, D, EAttachments B, C, D, E• Attachments B-E consist of the written proposal

• Offerors must use Attachments as the templates to fill-out

• Offerors are NOT allowed to re-create, re-format, or modify the template (cannot alter font size, font type, font color; add colors, pictures, diagrams, etc.).

• In order to minimize any bias, the evaluated proposal documents MUST NOT contain any names that can be used to identify who Proposer is (such as company names, personnel names, project names, or product names).

• Pay attention to page limits!

3232

Page 33: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

How The Submittal Process WorksHow The Submittal Process Works

Submittal

Evaluation Members

Proposal Form(1 page)

Non-Evaluated Documents

Proposal Form(1 page)

Evaluated Documents

Average Score

ContractingOfficer

PurchasingOfficer

Page 34: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Attachment B – Team Attachment B – Team QualificationsQualifications• Describe the team of key personnel that will be

assigned to this project along with key performance metrics – Years with your company– Years of experience in current position – Number of similar projects– Average customer satisfaction ratings – Documented performance improvements– Awards and achievements

• Differentiate your capability to meet the requirements of this service by aligning your expertise.

• The Team Qualification plan must NOT exceed 1 page

3434

Page 35: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Attachment C – Project PlanAttachment C – Project Plan• Demonstrate to the University that the Offeror can visualize what they are

going to do before they do it. The Project Plan consists of the following sections:– Proposal Summary – describe how the Offeror will meet the University’s

expectations in major activities or tasks.– Project Assumptions – a summary of the major assumptions that have been

made in preparing the proposal. – Roles, Responsibilities, Expectations – brief summary of the expectations and

responsibilities that the Offeror has of the University or University personnel.– Clarification Period Schedule – a high level schedule that included dates of

when the Offeror will accomplish all of the requirements of the Clarification Period

• The Project Plan must NOT exceed 4 pages

3535

Page 36: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Attachment D – Risk Assessment Attachment D – Risk Assessment PlanPlan• Identify and prioritize all major risks (applicable to this project) that may

impact a successful delivery of the project.

• Risk = not completing on time, not finished within budget, generating change orders, or sources of dissatisfaction to the owner.

• The risk should be described in non-technical terms and should contain enough information to understand why the risk is a valid risk. Proposer must also explain how it will avoid or minimize the risks from occurring.

• Solutions must be nontechnical, logical, easily understood, or contain verifiable performance information.

3636

Page 37: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Risk Assessment PlanRisk Assessment Plan• Assessment of Controllable Risks: risks, activities, or tasks that are

controllable by Proposer, or by entities/individuals that are contracted to by Proposer. This includes things that are part of the technical scope of what Proposer is being hired to do. Project risk that other vendors have due to lack of experience and expertise

• Assessment of Non-Controllable Risks: risks, activities, or tasks that are not controllable by Proposer. This may include risks that are controlled by Agency, Agency’s representatives, or completely uncontrollable. Although these risks may not be controlled by Proposer, Proposer must identify a strategy that can be followed or used to mitigate these risks.

3737

Page 38: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

To Be Considered “Dominant”, To Be Considered “Dominant”, Risks/Solutions Should:Risks/Solutions Should:• Be clear and concise

• Non-technical descriptions

• Logical

• Measurements that document time, quality, and cost

• Document performance results

Page 39: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

3939

Risk Assessment Example Risk Assessment Example Controllable RiskControllable Risk

• VENDOR 1 – RISK: This project requires a significant amount of concrete. The cost of

concrete has been rapidly escalating over the past year. – SOLUTION: The owner can be assured all risks associated with concrete

escalations will be eliminated because we offer the benefit of an experienced project team that includes the most detailed, prequalified and extensive list of subcontractors and suppliers, from around the world.

• VENDOR 2– RISK: The cost of concrete has been rising drastically over the past year. Since

this project requires a substantial amount of concrete, cost is a risk. – SOLUTION: To minimize this risk, we have secured and signed a contract with a

local concrete manufacturer to prevent any increase in cost during the duration of this project.

Page 40: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

4040

Risk Assessment Example Risk Assessment Example Controllable RiskControllable Risk

• VENDOR 1 – RISK: Noise from our demolition may result in student/staff complaints (since

we will be doing demo in an in-operational library during finals week). – SOLUTION: We will work with the user to minimize the impact of noise from

demolition.

• VENDOR 2– RISK: Noise from our demolition may result in student/staff complaints (since

we will be doing demo in an in-operational library during finals week). – SOLUTION: To minimize this risk, we have planned to demolition during off

hours and weekends. We will also install rubber sheets on the floors to diminish noise and vibrations. Both solutions can be performed within your budget.

Page 41: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Risk Assessment Example Risk Assessment Example Controllable RiskControllable Risk

4141

RISK: A poor roofing system can result in roof leaks, which may

inconvenience building occupants, increase complaints, increase maintenance, damage building contents, and be a source of mold issues.

Vendor A Solution:• To minimize this risk, our proposed roofing system has been installed on

over 400 roofs and has had an average roof age of 18 years, in which 99% of the roofs don’t leak and 100% of the end clients are satisfied.

Vendor B Solution:• To minimize this risk, we are proposing a thermally-welded roofing system

that has a tensile strength of 2,130 PSI, elongation of 300%, tear strength of 312lbs, has been tested for 10,000, and has a cold brittleness of -30°C.

Page 42: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

4242

Risk Assessment Example Risk Assessment Example Non-Controllable RiskNon-Controllable Risk• VENDOR 1

– RISK: The local water company must have the water turned on by June in order for us to properly water the newly installed recreational fields (or the grass will die).

– SOLUTION: We will coordinate and plan our schedule with the water company as soon as the award is made to make sure that we get water to the site to irrigate the fields.

• VENDOR 2– RISK: The local water company must have the water turned on by June in

order for us to water the newly installed fields (or the grass will die). On past projects, the water company has failed to meet the schedule 90% of the time.

– SOLUTION: To minimize this risk, we will coordinate our schedule with the water company as soon as we are awarded the project. If they fail to meet our schedule, we will setup and connect temporary waterlines to the nearby fire hydrants and we will also have water trucks on-site to irrigate the fields.

Page 43: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Risk Assessment Example Risk Assessment Example Controllable RiskControllable Risk

• RISK: Major risk items typically associated with transit implementations revolve around change management and business process impact. New technology implementations create change for the users. Change often causes issues with technology adoption. Requirements and scope creep also creates challenges. Systems may have thought a certain technology or component was incorporated in the RFP and/or needs assessment process that is not included in the actual scope of work or contract. Communication is also an area that can be a challenge.

• SOLUTION: A clearly defined scope of work and communication of the scope at the beginning of the project minimizes scope creep. If there is a discrepancy, scope or requirements can be discussed early on in the process versus at the end of the process. Communication is the key to successful implementations. Change management and business process re-engineering for organizations can be minimized at the technology and management levels. Management can get early buy-in at the “grass roots” level and include them in the technology planning process. The Team focuses on providing very configurable and flexible tools to minimize process re-engineering tasks. The Team focuses on automating existing business processes and providing additional tools to improve those processes that need to be improved such as data management….

Page 44: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

4444

““If you can't explain it simply, If you can't explain it simply, you don't understand it well you don't understand it well

enough!”enough!”

Page 45: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Attachment E – Value Attachment E – Value Assessment PlanAssessment Plan• Opportunity to identify any value added options or ideas that may benefit

the Owner and Agency.

• This may include ideas or suggestions on alternatives in implantation strategies, timelines, project scope, equipment, goals, financing, etc.

• All value added ideas must be logical and/or based on verifiable performance metrics.

• Value added ideas must NOT be included in the cost proposal. Prior to award, the Owner will determine if the value added items will be accepted or rejected.

4545

Page 46: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

46

Example: Value Added ItemsExample: Value Added Items

• Reroofing this building will not stop all water leaks. The majority of the leaks are caused by cracks in the parapet walls, broken/missing glass, and poor caulking.

Page 47: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Example: Value Added ItemsExample: Value Added Items• You can save 20% in your cost if you substitute the T-3

lighting system for the T-2. The T-3 lights are newer state-of-the-art systems that are known industry wide as the best systems.

• If we can alter the hours of operation at Site B, we can increase revenue overall revenue by 5%. This may be an inconvenience for a small number of people (less than 50 students) during this time period, but the revenue gain is considerable.

Page 48: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Example: Value Added ItemsExample: Value Added Items• Idea: Purchase “Concurrent Licenses” instead of “Named Licenses”

• Why: In a “Named Licensing” model, you must purchase a license for every user and only that particular user can access the software. If that named user is in meetings, on vacation, or not using the system, the license cannot be utilized. In a “Concurrent Licensing” model, the system loans out the licenses to users as they log in. If a user is inactive, the server releases the license and allocates the license to the next user.

• Expected Benefit: The advantage of the concurrent licenses is that the Agency will not have to purchase licenses that are not being used, which can result in approximately 20%-30% savings in cost.

4848

Page 49: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Example: Value Added ItemsExample: Value Added Items• Current Requirement: The current design requires a substantial number of

cast-in-place box culverts. This requires us to create forms (which may be difficult in specific locations), and then we will have to wait for the concrete to cure.

• Alternate: If we can use pre-cast culverts we can save approximately 5% in cost and reduce overall schedule by 10%. Pre-cast culverts can be made to the same specifications as the cast-in-place culverts, and we have found them to be higher in quality since they can be created in a closed environment.

• Documented Performance: We have done this on over 20 projects (similar in scope to this project) and have had high customer satisfaction.

Page 50: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Things to AvoidThings to Avoid• General Statements:

– Our employees will wear safety equipment (hard hats, vests, etc)– Safety: Our goal is to have no accidents or deaths– We will put a fence around the site to prevent outside access

• Marketing data:– Our company is known worldwide as a leader in… – We will use our long history to…– We will use state-of-the-art process to…

• Technical data:– The system we propose has 200% elongation and 600psi tensile strength – The product will pass the ASTM-568a test.

• Transferring risk back to client:– We will work with the owner to resolve issues…– We will have team meetings / partnering meetings with the owner…

Page 51: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Critical Formatting RequirementsCritical Formatting Requirements• Proposal is limited to

– 1 Pages = Assessment of Controllable Risks– 1 Pages = Assessment of Non-Controllable Risks– 1 Pages = Assessment of Value Added Ideas

5151

Page 52: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Remember…Remember…• Be clear and concise

• Non-technical descriptions / solutions

• Logical

• Measurements that document time, quality, and cost

• Document performance results / verifiable results

Page 53: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

How The Submittal Process WorksHow The Submittal Process Works

Submittal

Evaluation Members

Proposal Form(1 page)

Non-Evaluated Documents

Proposal Form(1 page)

Evaluated Documents

Average Score

ContractingOfficer

PurchasingOfficer

Page 54: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Evaluation CommitteeEvaluation Committee• Will be used to evaluate specific portions of the Proposal

• Evaluators will not be provided with the names of any Proposers, product names, cost, or any additional information

• Evaluators will independently (not as a group or consensus) review and score the items comparatively to one another

• Objective of the scoring is to not make a decision (looking for “dominant” differential)

• Evaluations will be scored on a 1/5/10 scale– “10” = Dominantly higher value than the average (clearly shows differential) – “5” = About average (insufficient information to make a clear decision)– “1” = Dominantly below the average (clearly shows differential)

5454

Page 55: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Past Performance InformationPast Performance Information• PPI will be collected on the following Entities:

– The Firm– Onsite General Manager (Individual)

• Each Entity must prepare and submit a Reference List, Survey Questionnaire, and Past Performance Information Scores

5555

VendorVendorENTITYENTITY

Prepare and Send Survey Questionnaires to Past Clients Step 2

Step 3Collect/Receive Completed Surveys

Prepare Reference ListStep 1

Enter data into Reference ListStep 4

Package all material (Reference List and Surveys) and SubmitStep 5

Page 56: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Reference List Reference List • Each Entity must submit a list of clients that will evaluate Entity's performance.

• The maximum number of references that can be submitted is 5 for each Entity.

• The past projects must be installed and operational

• The past projects must be related to food services

• The reference list must contain different projects and clients

• The client must complete the survey

• The University of Manitoba cannot be used as a reference

• Each Entity can use the same references provided that they were used or applied on that particular project.

5656

Page 57: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Survey Questionnaire Survey Questionnaire • For each Entity, Proposer must prepare,

send out, and collect survey questionnaires to each individual listed on the Reference List.

• Proposer must modify so that the surveys are returned back to the Proposer.

• All returned surveys MUST be evaluated AND signed by the client.

• Returned surveys must be packaged together and submitted with Proposer's proposal (Proposer should keep a copy of all returned surveys for Proposer's records).

5757

Page 58: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Past Performance Information ScorePast Performance Information Score

• Proposer shall input the survey scores, and “Overall Average Score”

• Proposer shall also count the “Total Number of Returned Surveys”

• Client may contact the reference to clarify or to obtain additional information. If the reference cannot be contacted, the survey may be deleted.

• The Client may also adjust the scores if the client determines that the criteria/requirements have not been followed.

5858

Page 59: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Attachment I – Cost ProposalAttachment I – Cost Proposal• Total 10-Year Financial Contribution• Overview of Commissions• Transitioning Costs (Offeror shall be responsible for all costs associated for

transitioning the service from the incumbent to the Offeror)• Overview of Major Capital Investments• Value Added Options

5959

Page 60: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

ShortlistingShortlisting• A University Procurement Representative will create a linear matrix model to

assist in analyzing and prioritizing the responsive Proposals based on the submitted information.

• The model will analyze: Cost, Risk Assessment Plan, Value Assessment Plan, Team Qualifications, and Past Performance Information. This model will assign points based on the normalized distance that a score is from the best score.

• A University Procurement Representative will present the results of the model to the Evaluation Committee, which will then identify the top two-to-three highest ranking proposals, and identify them as the Shortlisted Offerors. The Evaluation Committee reserves the right to increase or decrease the number of proposals in this list based on the overall competitiveness of the proposals.

6060

Page 61: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

61

Key Personnel InterviewsKey Personnel Interviews• The University will conduct interviews with the Onsite General Manager from

each of the Shortlisted Offerors.

• This individual must be the same person that is listed in the Offeror’s Proposal (Attachment A). No substitutes, proxies, phone interviews, or electronic interviews will be allowed. Individuals who fail to attend the interview on the date/time specified will be given a “1” score, which may jeopardize the Offeror’s competitiveness.

• Interviews are expected to last approximately 30 minutes per individual.

• No other individuals (from the Offeror’s organization) will be allowed to sit in or participate during the interview session. Interviewees may not bring notes or handouts. The University will interview individuals separately. Interviewees will be prohibited from making any reference to their proposed financial contributions. The University may request additional information prior to interviews and may request to interview additional personnel.

Page 62: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Interview CommentsInterview CommentsGoal Is To Minimize RiskGoal Is To Minimize Risk

“I have no idea why I am here today”…“My boss called me last night and told me to show up for this interview” - $10 Million Project

“I did not participate at all in preparing our proposal”

“I am not currently employed by this company, but if we win this project, they will then hire me” - $25 Million Service Project

“I have never managed a project of this size/scope” - $30 Million Project

“There is no risk on this project” - Large IT Project

“The greatest risk that I always face, is how to accomplish all of the things that our sales team promised we could do” – Cleanroom Design Project

6262

Page 63: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Final PrioritizationFinal Prioritization

6363

NO CRITERIA POINTS FIRM A FIRM B FIRM C BEST FIRM A FIRM B FIRM C

1 Total Financial Contribution 300 1,000,000$ 1,020,000$ 1,050,000$ $ 1,000,000 300 294 286

2 Interview of Onsite General Manager 300 4.2 9.3 6.4 9.3 135 300 206

3 Risk Assessment Plan 150 5.2 8.6 5.1 8.6 91 150 89

4 Value Assessment Plan 100 5.0 9.2 5.0 9.2 54 100 54

5 Team Qualifications 50 5.0 5.0 5.0 5.0 50 50 50

6 PPI – Firm (1-10 Ratings) 25 9.2 9.1 9.3 9.3 25 24 25

7 PPI – Firm (# of Surveys) 25 5 5 5 5.0 25 25 25

8 PPI – General Manager (1-10 Ratings) 25 9.4 9.1 9.5 9.5 25 24 25

9 PPI – General Manager (# of Surveys) 25 3 4 5 5.0 15 20 25

TOTAL POINTS (1,000): 720 988 785

RAW DATA FINAL POINTS

Page 64: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Financial ReasonablenessFinancial Reasonableness• If the highest ranked Offeror’s total financial proposal is within 5% of the

next highest ranked Offeror’s total financial proposal, the University will proceed to invite the highest ranked Offeror to the Clarification Period.

• If the highest ranked Offeror’s total financial proposal is 5% (or more) lower than the next highest ranked Offeror’s total financial proposal, the University reserves the right to invite the second highest ranked Offeror to the Clarification Period.

6464

Page 65: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

6565

Phase 2Phase 2

• Financial Summary• Project Plan• Project Risks/Concerns• Assumptions• Performance Metrics• Contract

Page 66: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

6666

Best Value SystemBest Value System

Page 67: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

6767

Best Value SystemBest Value System

Page 68: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Weekly Risk Reporting SystemWeekly Risk Reporting System• Spreadsheet that documents all risks on the service

• Risk = Anything that may impact performance or financial contributions to the University. Risks can be caused by the Offeror or the University

• Report must be submitted on Friday of every week (until service is complete)

• The WRRS does not substitute or eliminate weekly progress reports or any other traditional reporting systems or meetings (that the Offeror may perform or may be required to perform).

6868

Page 69: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Performance ReportingPerformance Reporting• The Offeror will be required to document the performance of its services

on a monthly, quarterly, and yearly basis.

• The monthly reports shall provide dominant information on the service provided, including (but not limited to):

1. Number of students served for meal plan options2. Amount of capital invested along with the associated depreciation schedules3. Amount of revenue generated with the ability to differentiate on a per outlet

and/or per hour basis4. Average check per customer5. Total amount of revenue paid to the University

• The Contractor will also be required to collect and compile student satisfaction surveys once per year.

6969

Page 70: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

7070

Best Value SystemBest Value System

• Proposal ($)• Past Performance• Team Qualifications• Risk Assessment• Value Assessment• Interviews

• Pre-Planning & Clarification

• Award • Weekly Reporting• Post Award Metrics• Final Documentation• Update PPI

Page 71: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

SuggestionsSuggestions Identify who your best people are (done through measurements)

Have your best people sit down in a room and think about this project

Adapt their comments/ideas into your Risk and Value Assessment Plans

Correlate any suggestions/ideas/solutions to documented performance

Minimize marketing (risk of reformatting, names, words, etc.)

Follow all formatting requirements (no names, page limits)

Be dominant

Be simple, non-technical, and logical

Picture what it takes to make the client very happy at the end

7171

Page 72: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Anticipated ScheduleAnticipated Schedule

No Activity Date1 Project Announcement 08/26/132 Pre-Proposal Conference 09/11/133 Site Walk 09/11/134 Deadline to Submit Questions/Inquiries 09/23/135 Proposal Due Date (4:00 PM Winnipeg Time) 10/17/136 Interviews 10/23/137 Clarification Period 10/28/13 - 11/29/138 Anticipated Date of Award 12/12/139 Transition Period 1/1/14 - 3/30/14

10 Start of Service 4/1/14

7272

Page 73: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Project OverviewProject Overview• The University is looking to secure services equal to, or better than, the

level of service currently provided. The primary goals of this RFP are to increase financial return to the University and to increase satisfaction to the University & Students

• This contract will be a commission-based structure and commence on April 1, 2014. The term of this contract is ten (10) years.

• Vendor is responsible for all transitioning costs

• Required minimum capital investment and buyout (by 4/1/14):– $560,898 for capital equipment buyout;– Approximately $25,000 for Noodles & Soup renovation (currently underway); – Between $225,000-$400,000 for the Starbucks renovation at Bannatyne

Campus

7373

Page 74: This presentation is for educational purposes only Refer to the project RFP for specific details and instructions If there are any inconsistencies, the

Comments / Questions