69
THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) FIRST ANNUAL COMPLIANCE REPORT JULY 2016

THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

THIRD EDITION ENVIRONMENTAL

IMPLEMENTATION PLAN (EIP)

FIRST ANNUAL COMPLIANCE REPORT

JULY 2016

Page 2: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

2

REVISION HISTORY

Draft or Version Date Author Summary of Changes Changes marked

Version 0 31 August 2015 Rethabile Motloung First draft of compliance

template

Version reviewed and expanded

upon.

Version 1 May 2016 Tammy Christie Draft EIP Compliance Report

with Table of 2015/16

achievements completed.

Tables completed. Chapters

added.

Version 2 (Final) July 2016 Tammy Christie &

Rosemary Jackson

Comments and suggested

changes effected.

Revision to a few indicators.

DISTRIBUTION

Name Role/ Organisation Email

Ronald Mukanya Director: Sustainability [email protected]

Karen Shippey Chief Director: Environmental

Sustainability [email protected]

Piet van Zyl Head of Department [email protected]

Municipal Managers

3rd Floor Floor, Leeusig Building, 1 Dorp Street, Cape Town, 8001 Private Bag X9086, Cape Town, 8000

tel: +27 21 483 9854 fax: +27 21 483 3093 www.westerncape.gov.za/eadp

Page 3: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

3

EIP Original Commenters Contributions on Indicators

Cape Nature: Ernst Baard

DoA: Andre Roux, Ilse Trautmann

DEADP: Albert Ackhurst, Cathy Bill, Sarah Birch, Tammy

Christie, Gerhard Gerber, Jessica Katz, Bernard

Niemand, Eddie Hanekom, August Hoon, Goosain

Isaacs, Lize Jennings-Boom, Zain Jumat, Wilna

Kloppers, Belinda Langenhoven, Joy Leaner, Veronica

Mukasa, Mellisa Naiker, Eshaam Palmer, Keshni

Rughoobeer, Khuthala Swanepoel, Carmen van Uys

DoTP: Hugh Cole

DT&PW: Mario Brown, Gavin Kode, Sharonette Web

EIP Additional Commenters Completion of Indicators &

Additional Information

DEDAT: Anzel Venter

DT&PW: Mario Brown & Danielle Manuel

DHS: Shaanaz Adams & Eugene Visagie

DoTP: Faizel Noordien

Additional Contributions GIS Mapping and

Communications Check DEADP: Andre van der Merwe, Dalene Stapelberg &

Shereen Pearson.

Author/s: Tammy Christie, Rethabile Motloung, Rosemary Jackson

Project Manager: Tammy Christie

Director: Ronald Mukanya

Page 4: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

4

ACRONYMS

AAIA Authorised Asbestos Inspection Authority

CPI Consumer Price Index

DEA National Department of Environmental Affairs

DEADP Western Cape Department of Environmental Affairs and Developing Planning

DEDAT Western Cape Department of Economic Development and Tourism

DOA Western Cape Department of Agriculture

DoHS Department of Human Settlement

DT&PW Department of Transport and Public Works

EIP Environmental Implementation Plan

EMP Environmental Management Plan

EPWP Expanded Public Works Programme

FTE Full Time Employee

GABS Golden Arrow Bus Service

GE Green Economy

IDP Integrated Development Plan

IDMS Infrastructure Delivery Management System

Page 5: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

5

IPIP Infrastructure Programme Implementation Plan

IPMP Infrastructure Programme Management Plan

LG MTEC Local Government Medium-Term Expenditure Committee

NDP National Development Plan 2030

NEMA National Environmental Management Act (Act No. 108 of 1994)

PER Property Efficiency Report

PPP Public Private Partnership

PPTIF Provincial Public Transport Institutional Framework

PSG Provincial Strategic Goal

PTOG Public Transport Operating Grant

RFQ/RFP Request for Quotation/Request for Proposal

SoEOR State of the Environment Outlook Report

TAIIB Treasury Approval II B

WCG Western Cape Government

WCIF Western Cape Infrastructure Framework

Page 6: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

6

TABLE OF CONTENTS

1 INTRODUCTION 7

2 BACKGROUND 9

3 UPDATES TO WESTERN CAPE STRATEGIC CONTEXT AND INFLUENCE ON EIP 10

4 COMPLIANCE WITH OUTCOMES AND KEY PRIORITY INDICATORS OF THE EIP 10

5 SUMMARY OF AMENDMENTS TO THE EIP 57

6 SUMMARY OF TARGET ACHIEVEMENTS FOR 2015/16 59

7 COMPLIANCE WITH EIP COMMITMENTS BY LOCAL GOVERNMENT 61

8 CONCLUSION 69

Page 7: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

7

1 INTRODUCTION

The Environmental Implementation Plan (EIP) is a legal requirement originating from Chapter 3 of the National Environmental

Management Act (Act No. 108 of 1994) (NEMA). It is to be prepared by certain national departments, listed in Schedule 1 of

NEMA, and every provincial department responsible for environmental affairs within five years of the Act coming into operation,

and at intervals of not more than five years thereafter. In addition, Chapter 3 of NEMA states that “every national department

listed in Schedule 2 of NEMA is required to prepare an environmental management plan (EMP) in the same timeframes and

every national department that is listed in both Schedule 1 and Schedule 2 may prepare a consolidated environmental

implementation and management plan”. Municipalities in turn must adhere to the national and relevant provincial

environmental implementation and management plans, and the principles contained in Section 2 of NEMA in the preparation

of any policy, programme or plan, including the drafting of municipal Integrated Development Plans (IDPs).

As per Section 12 of the NEMA, the purpose of the EIP is, in respect of the national and provincial departments in question as well

as all municipalities, to:

coordinate and harmonise environmental policies, plans, programmes and decisions in order to (i) minimise the

duplication of procedures and functions; and (ii) promote consistency in the exercise of functions that may affect the

environment;

give effect to the principle of cooperative government in Chapter 3 of the Constitution;

secure the protection of the environment across the country as a whole;

prevent unreasonable actions in respect of the environment that are prejudicial to the economic or health interests of

other provinces or the country as a whole; and

enable monitoring of the achievement, promotion, and protection of a sustainable environment.

EIPs and EMPs further seek to align the Environmental Sector priorities and long term strategies as identified in the National

Development Plan Vision 2030.

Page 8: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

8

Section 16 (1) (b) of NEMA states that every organ of state must report annually within four months of the end of its financial

year on the implementation of the adopted EIP to the Director-General of the Department of Environmental Affairs (DEA). The

Third Edition of the Western Cape EIP was published in the Provincial Gazette Extraordinary on Friday 2 October 2015. This report

is the first compliance report on the implementation of the Third Edition EIP and is submitted in terms of Section 16(1)(b) of NEMA

for the 2015/16 financial year.

Figure 1: Diagram to illustrate the previous EIP’s published for the Western Cape and the subsequent Compliance Reports that were

produced under each.

Western Cape

EIP 1st Edition

(4 November 2002)

1st Annual Compliance Report

(2002/03)

2nd Annual Compliance Report

(2003/04)

3rd Annual Compliance Report

(2004/05)

4th Annual Compliance Report

(2005/06)

Western Cape

EIP 2nd Edition

(20 August 2010)

1st Annual Compliance Report

(2011)

2nd Annual Compliance Report

(2012)

3rd Annual Compliance Report (2013)

4th Annual Compliance Report (2014)

Western Cape EIP 3rd Edition

(2 October 2015)

1st Annual Compliance Report (2016)

Page 9: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

9

2 BACKGROUND

The underlying structure of the Western Cape’s 3rd edition EIP was aligned with the strategic priorities of Chapter 5 (Environmental

Sustainability) of the National Development Plan 2030 (2012) as these in turn aligned well with the priority areas that emerged from

the Western Cape State of Environment Report in 2013. The one exception is the inclusion of the Green Economy as an additional

strategic priority in the structure of the EIP, as the Western Cape government has chosen to implement many environmental goals

by way of the Green Economy, and it therefore deserves its own priority category. The Western Cape State of Environment Outlook

Report (SoEOR) is currently under development and is due for release early in 2018. The findings of this report will therefore feed into

the EIP Compliance Report of 2018 and 2019, and will inform the new edition of the EIP in 2020.

The categories/ strategic priorities into which the key priority indicators, as identified in Section 6 of the 3rd edition EIP, are grouped

are thus as follows:

Enhancing governance systems and capacity

Sustaining South Africa’s ecosystems and using natural resources efficiently

Managing a just transition and the Green Economy

Building Sustainable Communities

Responding effectively to Climate Change (mitigation and adaptation)

The 3rd edition EIP identifies existing policies, plans and programmes that may significantly affect the environment in the Western

Cape. From these documents a set of 100 priority indicators were identified and listed, together with outcomes and annual targets

for the period 2015 to 2020. This compliance report serves primarily to report on the target achievement for each of these indicators

for the 2015-16 financial year.

Page 10: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

10

3 UPDATES TO WESTERN CAPE STRATEGIC CONTEXT AND INFLUENCE ON EIP

There were no notable updates to strategic documents that have a direct bearing on the EIP during the 2015/16 financial year.

Mention only needs to be made that the Western Cape State of Environment Outlook Report (SoEOR), last published in 2013, is

currently under review and is due for publication early in 2018.

4 COMPLIANCE WITH OUTCOMES AND KEY PRIORITY INDICATORS OF THE EIP

Defining concepts

The following column headings are defined to assist the reader to understand the context in which they are used in the reporting

table.

Indicator Number: These numbers correspond with the indicator numbers assigned in Section 6 of the EIP

published on 2 October 2015.

Activities: The means identified for meeting the outcomes of the projects/ programmes/ plans that

have been identified in the EIP (Section 2) as those that may significantly affect the

environment.

Indicator: The commitment made in the EIP that contributes to a specific outcome/result.

Who is responsible: The particular function department/unit that is responsible for the described indicator.

Target: What needs to be achieved and by when.

Level of achievement: Progress made in implementation is reflected as quality measures (i.e. the state of

improvement or progress made in environmental management by various sector

Page 11: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

11

departments) and/or quantity measures (i.e. a measurable product for example the

number of approved/disapproved Environmental Impact Assessments.)

Challenges/ Barriers/ Reasons for Deviation: Measures in place to address the existing problem or gap, including problems like lack

of capacity and resources. This column will also include new timeframes regarding

adjustments. Explanations for over-achievement of targets will also be included here.

Note: Adjustments to EIPs (highlighted in bold)

New priorities, not reflected in the Third Edition EIP, but that now form part of implementation, are reflected in this Compliance

Report. Adjustments are reflected in two places in the Compliance Report: (i) in Chapter 4, in the EIP indicator implementation

table below, in which actual progress is reflected; and (ii) in Chapter 5, where a summary or overview is presented of the type of

adjustments that have been made to implementation of the EIP.

Page 12: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

12

Table 1: Table of compliance with outcomes and key priority indicators for 2015/2016.

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

Enhancing governance systems and capacity

1

Actively participate in

and support all 30

municipalities.

Number of

intergovernmental

sector tools reviewed

DEADP 2015/16:1 1 (100%)

IDP developed for the

30 Municipalities.

None

2 Actively participate in

and support all 30

municipalities.

Number of legislative

tools to ensure the

protection of species

and ecosystems

developed and

implemented

DEADP

CapeNature

2015/16:1 Draft

Bill Received

by State Law

Advisor

1 (100%)

Draft WC Biodiversity

Bill submitted to State

Law Advisor.

2015/16: 1

Biodiversity

Management Plan for

Cape Mountain Zebra

Park

None

3 Actively participate in

and support all 30

municipalities.

Number of waste policy

instruments developed

DEADP 2015/16:1 1 (100%)

Integrated Waste

Management Model

By-Law developed.

None

4 Actively participate in

and support all 30

municipalities.

Revised Western Cape

Biodiversity Offsets

Guideline developed

DEADP 2015/16:1 1 (100%)

Final draft Biodiversity

Offset Guideline

submitted to HOD.

None

Page 13: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

13

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

5 Develop and

implement legislative

tools (legislation,

guidelines, policies and

procedures) that guide

decision-making and to

ensure the protection of

species and

ecosystems.

Number of legislative

tools developed

DEADP 2015/16:3 3 (100%)

(1) Draft WC

Biodiversity Bill

submitted to

State Law

Advisor.

(2) Final draft

Biodiversity Offset

Guideline

submitted to

HOD.

(3) Integrated Waste

Management

Model By-Law

developed.

None

6 Implementing an

environmental research

programme to support

environmental decision-

making, planning and

policy development.

Number of

environmental research

projects undertaken

DEADP 2015/16:2 2 (100%)

(1) The Feasibility

Study for

Alternative and

Sustainable

Infrastructure and

Services for

Settlements.

(2) The Western

Cape Green

Economy

Indicator Report.

None

Page 14: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

14

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

7 To develop and

enhance, maintain, and

manage the

Departmental GIS.

Geographic Information

Services (GIS)

departmental products

developed/maintained/

enhanced

DEADP 2015/16: GIS

products

developed

PSDF website

maintained

4 (100%)

(1) Waste Sites

(2) Spatial

Application

Management

System data

(SAMS data)

(3) Berg River

Improvement

Plan

(4) Coastal Setback

Lines for

Overberg

8 By developing the

Environmental Impact

Assessment and

Management Strategy

(EIAMS).

Number of functional

environmental

information

management systems

DEADP 2015/16:2 2 (100%)

(1) Integrated

Pollution and

Waste

Information

Systems (IPWIS).

(2) GIS Website.

None

9 By promoting

compliance with

environmental

legislation through

implementing various

legislative enforcement

mechanisms

By providing effective

legal support in terms of

Number of investigations

finalised

DEADP 2015/16:155 182 (117%)

Demand driven

Indicator. Due to

the nature of the

investigations and

enforcement

actions executed,

investigations

could be

finalised. The

Page 15: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

15

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

environmental and

planning legislation.

over-

achievement is

also the result of

additional

graduate interns

appointed in the

component to

assist with the

workload.

10 Number of

intergovernmental

compliance and

enforcement operations

conducted

DEADP 2015/16:6 6 (100%) None

11 Number of litigation

cases managed

DEADP 2015/16:58 55 (95%)

Demand Driven

Indicator. No

control over

cases brought

against

department- the

lower the total of

cases against

department the

better.

12 Number of appeals

finalised

DEADP 2015/16:40 49 (123%) Demand driven.

An additional

staff member was

appointed in in

Page 16: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

16

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

the Sub-

Directorate.

13 Number of 24G

applications finalised

DEADP 2015/16:50 65 (130%) Demand driven.

The number of

S24G applications

finalised is

dependent on

the number of

administrative

fines paid and the

number of

applications

withdrawn. Fewer

S24G applications

were received

and as a result

greater resources

could be directed

towards finalising

applications.

14 Number of completed

criminal investigations

handed to the NPA for

prosecution

DEADP 2015/16:13 18 (139%) The number of

cases handed to

the NPA has

increased as the

number of cases

currently under

investigation,

some from the

previous financial

year, concluded

Page 17: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

17

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

and thus the

target was

exceeded. The

unit also

employed two

contract staff

members.

15 Number of administrative

enforcement notices

issued for non-

compliance with

environmental legislation

DEADP 2015/16:125 178 (142%) Demand driven.

The number of

enforcement

actions finalised

for non-

compliance with

environmental

management

legislation is

dependent on

the number of

complaints

received during

the quarter which

warrant's

administrative

and criminal

enforcement

action. Contract

staff was

appointed to

increase the

capacity of the

Page 18: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

18

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

component and

assist with

workload.

16 Number of enforcement

actions finalized for non-

compliance with

environmental

management legislation

DEADP 2015/16:138 196 (142%) Demand driven.

The number of

enforcement

actions finalised

for non-

compliance with

environmental

management

legislation is

dependent on

the number of

complaints

received during

the quarter which

warrant's

administrative

and criminal

enforcement

action. Contract

staff was

appointed to

increase the

capacity of the

component and

assist with

workload.

Page 19: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

19

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

17 Number of compliance

inspections conducted

DEADP 2015/16:99 127 (128%) Fewer S24G

applications were

received and as

a result greater

resources

directed to

conducting S24G

compliance

inspections.

18 Number of S24G

applications received

DEADP 2015/16:60 39 (65%) Demand driven.

Dependent on

the number of

S24G applications

received.

19 Number of S24G fines

paid

DEADP 2015/16:40 41 (103%) Demand driven.

The number of

fines paid is

dependent on

the applicants

and is voluntary.

20 By assessing the

Municipal IDP/Review

Documentation/

Amended IDP to

evaluate the level of

Number of municipal

IDPs reviewed

DEADP 30 Annually 30 (100%) None

21 Number of municipalities

compliant with legislated

DEADP 30 Annually 0 (0%) Indicator to be

workshopped

and

Page 20: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

20

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

compliance and the

level of performance in

terms of environmental

requirements (including

against the principles

contained in section 2

of NEMA and against

the EIP), and the level of

alignment, as well as to

determine the need for

support and improved

alignment.

environmental

requirements

Wording of indicator

challenging as no

municipalities yet

100% compliant with

all environmental

requirements (see

Chapter 7 below).

reconstructed to

be a valuable

reflection of

municipal

compliance.

22 Number of municipalities

achieving at least an

acceptable level of

environmental

performance in terms of

the IDP and LGMTEC

Assessment Outcomes

DEADP 30 Annually Suggest removal as

not yet measurable.

There is no current

ranking of

municipalities as

“acceptable” or not

based on IDP/LGMTEC

review process. This

indicator can be

amended and

reinstated once

ranking system

developed.

A differentiation

model is being

developed for

categorizing

municipalities into

levels of maturity

but this process is

not yet complete.

23 By annually reviewing

the Provincial

Environmental Impact

Assessment System, and

to implement the

System.

Number of Provincial

Environmental Impact

Assessment System

evaluation reports

DEADP 2015/16:1 1 (100%)

Evaluation of the

Provincial

Environmental Impact

Assessment System

None

24 By finalising EIAs within

the legislated

timeframes.

% of EIAs finalized within

the legislated timeframes

DEADP 2015/16:95% 98% (103% of target) Demand driven.

More EIA

applications were

Page 21: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

21

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

at a stage where

a final decision

could be made

within legislated

timeframes.

25 By developing and

establishing the

Institutional framework

for biodiversity

management in the

Western Cape.

Western Cape Provincial

Biodiversity Strategy and

Action Plan (PBSAP)

DEADP 2015/2016:

Final draft

signed off by

the HoD

1 (100%) None

26 By performing an

effective oversight

function over

CapeNature.

Oversight report on the

performance of

CapeNature

DEADP 2015/16:1 1(100%) None

Sustaining South Africa’s ecosystems and using natural resources efficiently

27 Align existing

infrastructure planning

processes.

WCIF Evaluation Report DT&PW 2015/16:

Evaluation of

the way

infrastructure is

being

delivered in

the province

Indicator to be

removed.

This

recommendation

emanating from

the WCIF was not

translated into an

annual

deliverable for

DT&PW as it was

deemed that

evaluating the

delivery of

infrastructure and

their compliance

Page 22: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

22

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

to environmental

issues is covered

directly by the

other DT&PW

indicators which

are included in

the EIP.

28 Protect and expand the

conservation estate.

A revised Western Cape

Protected Areas

Expansion Strategy is

approved.

CapeNature 2015/16:1 1 (100%)

Signed off by the

CapeNature Board in

March 2016.

None

29 Protect species and

ecosystems.

A Western Cape

Systematic Biodiversity

Spatial Plan produced

CapeNature 2015/2016: 1

A Western

Cape

Systematic

Biodiversity

Spatial Plan

produced

(including

maps)

In progress (0%

completed)

Planned for

completion in

June 2016.

Delay due to

capacity

available to

undertake the

work as well as

the need to focus

the available

capacity on the

Sandveld EMF as

a priority.

30 Promote compliance

with environmental

legislation.

Number of legislative

tools to ensure the

CapeNature 2015/16:1

Indicator to be

removed due to

Page 23: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

23

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

protection of species and

ecosystems developed.

duplication with

Indicator No. 2.

31 Protect and expand the

conservation estate.

Number of hectares in

the CapeNature

conservation estate

CapeNature 2015/16:

Previous year +

10 000 ha

12 491.56 Ha (125%) The target was

exceeded

because four sites

were larger than

initially

anticipated.

32 Support and restore

ecosystems which

provide goods and

services.

Number of new

biodiversity stewardship

sites

CapeNature 2015/16:8 10 (125%) The target was

exceeded as a

result of the

conclusion of the

first and last

contracts for the

year.

33 Protect and expand the

conservation estate.

A revised Western Cape

Protected Areas

Expansion Strategy is

approved

CapeNature Achieved in

2015/16

Indicator to be

removed due to

duplication with

Indicator No. 28.

34 Promote compliance

with environmental

legislation.

Number of criminal

enforcement actions

undertaken for non-

compliance with

environmental

management legislation

CapeNature 2015/16:60 89 (148%) This target is

demand-driven.

An over-

achievement

results from more

actions being

required than

targets set when

Page 24: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

24

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

using baseline

figures.

35 Improving settlement

functionality,

efficiencies and

resilience through

effective air quality

management.

Annual Report on the

State of Air Quality

Management in the

Western Cape

DEADP 2015/16:1 1 (100%) None

36 By incrementally

implementing Air

Quality Management

systems, processes and

measures in the Western

Cape.

Number of stations

continuously monitoring

ambient air quality

DEADP 2015/16:11 11 (100%) None

37 By incrementally

implementing Air

Quality Management

systems, processes and

measures in the Western

Cape.

% of Atmospheric

Emission Licenses with

complete applications

issued within legislated

time frames

DEADP 2015/16:80% 100% (125% of target) All completed

AEL applications

were issued within

legislated

timeframes. This is

a demand-driven

target.

38 By incrementally

implementing Air

Quality Management

systems, processes and

measures in the Western

Cape.

Percentage of facilities

with Atmospheric

Emission Licenses

reporting to the National

Atmospheric Emission

Inventory System (NAEIS)

DEADP 2015/16:100% 100% (100%) None

Page 25: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

25

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

39 By monitoring of water

quality in the aquatic

environment.

Number of river and

estuarine sites monitored

in respect of pollution

control

DEADP 2015/16:30 30 (100%) None

40 By facilitating

integrated water

resource management

and pollution

management in the

Western Cape through

improving institutional

management,

infrastructure and

ultimately water quality

and ecological

functioning of the

catchments.

Annual Report on

Sustainable Water

Management Plan

(SWMP)

DEADP 2015/16:1 1 (100%) None

41 By rehabilitating and

maintaining riparian

sites following alien

clearing by other

programmes, in order to

improve water quality

and ecological

functioning of the

catchments.

Number of riverine sites

targeted for

rehabilitation

DEADP 2015/16:4 4 (100%)

(1) Twee Rivieren

Farm

(2) Extension of Pearl

Valley Golf &

Country estate

site

(3) Grootverlangen

Farm

(4) VinkrivierFarm

None

Page 26: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

26

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

42 By conducting

inspections in priority

catchment areas and

identified sectors to

improve the aquatic

environment.

Number of inspections in

respect of pollution

control

DEADP 2015/16:5 7 (140%)

The number of

inspections was

increased due to

information

received on the

number of

operators working

in the targeted

sector and

geographical

area.

43 By providing integrated

pollution management

and promote resource

efficiency in the

Western Cape through

improving catchment

management, as well

as water quality and

ecological functioning

of the catchments.

% of NEMA: Section 30

cases responded to

DEADP 2015/16:24 34 (142%) Focused

awareness raising

on S30 was

conducted with

Municipalities

during this

quarter, resulting

in Municipalities

reporting more

S30 cases.

44 By providing integrated

pollution management

and promote resource

efficiency in the

Western Cape through

improving catchment

management, as well

as water quality and

Number of remediation

cases responded to

DEADP 2015/16:24 48 47 (98%) This is a demand

driven target and

fewer cases were

received.

Page 27: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

27

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

ecological functioning

of the catchments.

45 By facilitating

integrated waste

management and

resource efficiency.

Number of waste

minimization intervention

(s) undertaken to priority

waste stream

DEADP 2015/16:1 1 (100%)

Status Quo of Abattoir

Waste in the Western

Cape

None

46 By facilitating

integrated waste

management and

resource efficiency.

Municipal integrated

waste management

infrastructure needs

assessment report

DEADP 2015/16: Phase

1 report

Phase 1 Report (100%) None

47 By facilitating

integrated waste

planning and

management.

Review of Western Cape

1st Generation IWMP

DEADP 2015/16:1 1 (100%) None

48 By facilitating

integrated waste

planning and

management.

Number of hazardous

waste intervention (s)

taken

DEADP 2015/16:1 1 (100%) None

49 By facilitating

integrated waste

planning and

management.

Number of waste

management planning

interventions undertaken

DEADP 2015/16:1 1 (100%) None

50 By facilitating

integrated waste

planning and

management.

Annual state of waste

management planning

report development

DEADP 2015/16:1 1 (100%) None

Page 28: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

28

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

51 By facilitating

integrated waste

planning and

management.

% of Waste Management

Licenses finalized within

legislated timeframes

DEADP 2015/16:1 95% 91% (96%) Two waste

management

licences were not

finalised within

the legislative

timeframes due

to delays caused

by applicants in

providing further

information which

was needed to

finalise the

licences.

52 Implementing Coastal

Management.

Finalisation and

implementation of the

Provincial Coastal

Management

Programme (CMP)

DEADP 2015/16:

Provincial CMP

approved by

the Provincial

Minister

Provincial CMP

approved by the

Provincial Minister

(100%)

None

53 Coordinating and

supporting estuaries

management.

Finalise the estuarine

management plan for

the Breede River estuary

DEADP 2015/16:1 0 (0%) Procurement

process & budget

shortages

required sourcing

of additional

funding, resulting

in late

appointment of

service provider.

MEC has signed

off final draft for

advertising.

Page 29: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

29

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

National Minister

must approve

prior to MECs final

adoption.

54 Implementing Coastal

Impact Management.

Completion of technical

determination of Eden

Coastal Setback Line

DEADP 2015/16:1 0 (0%) The reasons for

the delay in the

project relates to

the following

reasons: Staff

Capacity

Constraints,

Development of

the

Implementation

Mechanism as a

priority,

Amendment of

the Scope of the

Project, DEA

Norms and

Standards had to

be clarified

before

proceeding

55 Provide engineering

services to support and

increase agricultural

production and

Number of engineering

services provided to

support and increase

agricultural production

and optimize sustainable

DoA 2015/16:575 652 (113%) Targets for

2016/17 and

beyond reduced

due to budget

constraints. New

Page 30: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

30

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

optimise sustainable

natural resource use.

natural agricultural

resources

target for 2014/15

to 2019/20: 3 367

56 Promote the

conservation of the

natural agricultural

resources.

Number of actions to

promote the sustainable

use and management of

natural agricultural

resources

DoA 2015/16:522 633 (121%) Targets for

2016/17 and

beyond reduced

due to budget

constraints. New

target for 2014/15

to 2019/20: 2 983

57 Provide comments on

subdivision and rezoning

of agricultural land

applications.

Number of regulated

land use actions to

promote the

implementation of

sustainable use and

management of natural

agricultural resources

DoA 2015/16:1000 804 (80%) Service is

demand driven,

less applications

received than

planned for.

Targets for

2016/17 and

beyond reduced

due to budget

constraints. New

target for 2014/15

to 2019/20: 5 700

58 Provide a disaster

management service to

clients, proactively and

reactively.

Number of support

services provided to

clients with regards to

agricultural disaster risk

management

DoA 2015/16:33 41 (124%) Targets for

2016/17 and

beyond

increased due to

more severe

weather

conditions. New

Page 31: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

31

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

target for 2014/15

to 2019/20: 235

59 Appropriate policy

development.

CapeNature Integrated

Catchment

Management Strategic

Plan developed

CapeNature 2015/16:1 1 (100%)

Strategy Complete –

tabled at

Conservation

Committee in March

2016 and approved

by the Board.

None

60 Improve ecosystem

health.

Percentage of protected

areas assessed with a

METT score above 67%

CapeNature 2015/16: 87% 74% (85%) The introduced

changes of the

new assessment

tool negatively

affected the

assessment

outcomes.

61 Implement Protected

Area Management

Plans.

Number of Protected

Area Management Plans

implemented

CapeNature 2015/16:33 44 (133%) Additional PAMPs

(11 land parcels

extra) was

completed during

the year, more

land parcels

applied than

initially planned

for.

Page 32: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

32

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

62 Optimise cost and

space utilisation of

office accommodation

through a reduction in

full time employee cost.

Percentage reduction in

full time employee cost

from 2013 baseline

(target: R45 567- cost per

full time employee)

DT&PW 2015/16:1%

year-on-year

(CPI adjusted)

<Not available at time

of report finalization –

indicator currently

under discussion>

The level of

achievement is

reflected in the

publication of the

annual results in the

Property Efficiency

Reports as well as in

the results themselves.

To date:

2011/2012 - R45 567

(published in 2013 as a

baseline)

2012/2013 – R54 847

2013/2014 – R47 214

2014/2015 – R58 093

Above figures are not

CPI adjusted.

A key driver of the

results stems from the

Office Modernisation

Programme, which

The size of the

reporting portfolio

is increasing

which has a

bearing on ability

to manage costs

down.

There are long

lead times for

projects to bear

fruit and

demonstrate

actual efficiency

gains. A key

challenge relates

to the

compilation of

the results and

availability of final

data sets due to

the independent

verification of the

results through a

London-based

consultancy. For

this reason,

reporting on the

results would be

done

retrospectively i.e.

Page 33: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

33

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

comprises various

projects.

with a year lag

time.

63 Deliver sustainable

provincial infrastructure

and accommodation

projects as per client

infrastructure plans.

Cumulative number of

capital and

maintenance projects

completed

DT&PW 1 Mar 2020:

3500

Maintenance 2015/16

– 353 completed

Capital 2015/16 – 33

completed

Total: 386 (11% of 5-

year target)

See expanded

information below

table. Footnote

(1).

64 Leverage Provincial

properties as part of the

Regeneration project.

Cumulative number of

properties released for

regeneration purposes

DT&PW 2019/20:5 6 in process (0%

complete)

13 Dorp Street

Accommodation PPP

– delay in the

appointment of the

preferred bidder. TAIIB

approval achieved.

Conradie Hospital site

– a provincial Game

Changer project.

Project scoping

finalized,

Development

Framework being

Various projects

at various stages

of release.

Release of

property is a long

term process.

Budget cuts have

precluded further

work in identifying

new opportunities

with a focus on

existing projects.

Page 34: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

34

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

finalized, moving to

tender stage for

Developer

procurement by end

2016

Two Rivers Urban Park

(TRUP) – specialist

studies and planning

underway.

Establishment of

project steering

committee in

progress. MoU

between Province

and City finalised

The planned

construction of a

Visitors Centre in

Oude Molen is no

longer feasible

due to the

inability to secure

appropriate

tenants.

The appointment

of a professional

team to prepare

the development

framework and

ultimately rezone

the precinct has

experienced

delays.

Page 35: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

35

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

Sea Point Main road -

property released but

now subject to legal

dispute process

Top Yard – registered

as a PPP. Compilation

of RFQ/RFP

documentation

currently in progress –

approximately 70%

complete.

Somerset phase 1

(Helen Bowden) -

Maintenance &

security upgrades to

buildings for

decanting. The

Heritage committee

requested further

information which was

Intention to go to

market in 2nd

quarter of 2016

however may be

delayed due to

the Sea Point

case.

Process of

rezoning has its

inherent

challenges.

Rezoning and

related processes

on hold until

Heritage

approval

received.

Page 36: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

36

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

provided by 13 April

2016.

65 Monitoring of the

resource efficiency of

WCG buildings.

Property Efficiency

Report published

DT&PW Annual:

Publication of

a Property

Efficiency

Report for

selected WCG

buildings

Property Efficiency

Reports published

annually (100%)

Cost per full time

employee (FTE)-Full

time equivalent:

2011/2012 - R45 567

(published in 2013 as a

baseline)

2012/2013 – R54 847

(published November

2014)

2013/2014 – R47 214

(published May 2015)

2014/2015 – R58 093

(published February

2016)

Annual space saving

in the region of 40.5%

– 13 504 m2, equates

in rental to a saving of

R58 million per annum.

Data

Data quality and

coverage needs

to be enhanced

significantly.

Data lacks

transparency.

Data is not used

or exploited.

This data should

be used to inform

better strategic

asset

management.

Performance

There are

significant

variations in cost

and utilisation.

There are some

significant outliers.

Leased office

space appears to

Page 37: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

37

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

(as per page 10 of

2013/4 PER)

be less well used

than owned

buildings.

On average, the

DTPW portfolio

performs better

than the private

sector on cost but

much worse on

use of space.

Opportunity

Better use of

space is likely to

deliver the easiest

and meaningful

savings.

There is scope for

rationalising and

reducing the size

of the portfolio-

under-operating

buildings could

be vacated and

the remainder

“sweated” more

effectively.

Page 38: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

38

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

Managing a just transition and the Green Economy

66 By promoting the

Western Cape

Biodiversity Economy.

Eco-Invest Programme

developed and

implemented

DEADP 2015/16:1 1 (100%) None

67 By monitoring and

reporting on Green

Economy indicators in

the Western Cape.

Number of Western

Cape Green Economy

Indicator Reports

compiled

DEADP 2015/16:1 1 (100%) None

68 By promoting

environmental capacity

development and

support.

Review Departmental

Environmental Capacity

Building Strategy

DEADP 2015/16:

Review

Departmental

Environmental

Capacity

Building

Strategy

1 (100%) None

69 By promoting

environmental capacity

development and

support.

Percentage

implementation of the

Local Government

Support Strategy

DEADP

2015/16:100% 98% A coastal

management

support initiative

could not be

implemented due

to resource

constraints.

70 By implementing

community based

environmental

infrastructure

development and

Number of work

opportunities created

through environmental

programmes

DEADP

2015/16:25 51 (204%) The reason for the

deviation is due

to people who

have been

contracted being

Page 39: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

39

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

economic

empowerment

programmes.

able to take up

more permanent

positions or find

alternative work

and therefore

leave the project.

This requires us to

contract labour in

their place which

increases the

number of

employment

opportunities

accounted for on

the project.

71 By promoting

environmental capacity

development and

support.

Number of

environmental capacity

building activities

conducted

DEADP 2015/16:73 80 (110%) Due to a

partnership

developed with

the International

Institute for

Sustainable

Development,

additional Green

Procurement

training was held.

Due to a new

complex EPWP

Reporting System

that was

introduced in

Page 40: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

40

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

June 2015 an

additional EPWP

training session

was required.

Due to

availability, the

WMO Forum took

place earlier than

anticipated.

Special AQOF

held in Nov2015

to discuss the

Review of the WC

AQMP and

training on NAEIS.

Additional

Environmental

Impact

Assessment and

Land Use

Planning

capacity building

workshops were

conducted.

72 Promoting

environmental

awareness raising

through conducting

Number of

environmental calendar

days celebrated

DEADP 2015/16:3 3 (100%)

Abor Day

None

Page 41: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

41

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

environmental

awareness activities

and celebrating

environmental days.

World Environment

Day

Wetlands Day

73 Promoting

environmental

awareness raising

through conducting

environmental

awareness activities

and celebrating

environmental days.

Number of

environmental

awareness activities

conducted

DEADP 2015/16:15 16 (107%) Additional

requests for

Environmental

Compliance and

Enforcement

workshops were

received and

conducted by

department.

74 Promoting

environmental

awareness raising

through conducting

environmental

awareness activities

and celebrating

environmental days.

Number of quality

environmental education

resources materials

developed

DEADP 2015/16:5 5 (100%) Delay in

procurement but

target met in

time.

75 Conduct agricultural

research and

technology

development.

Number of research and

technology

development projects

implemented to improve

agricultural production

DoA 2015/16:98 84 (86%) Year started with

98 projects, and

18 new projects

were approved,

whilst 32 projects

were completed,

bringing the final

Page 42: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

42

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

number to 84.

Budget and

capacity

constraints will

limit the number

in years to come.

76 Engage with

stakeholders to

determine relevant

research needs.

Number of meetings with

industry organizations to

establish research needs

DoA 2015/16:30 35 (117%) None

77 Increase access to

scientific information on

agricultural production

practises to farmers and

clients.

Number of activities

performed where

scientific and technical

information were

provided

DoA 2015/16:424 403 (95%) Less presentations

were done due to

less technology

transfer events

organized by

agribusiness and

other

stakeholders.

78 Increase the on-farm

infrastructure support to

the research effort and

departmental services.

Number of on-farm

infrastructure supported

DoA 2015/16:7 7 (100%) None

79 Monitor the

implementation of the

Western Cape

Environment and

Culture Sector Plan.

Western Cape

Environment and Culture

Sector Plan Monitoring

and Evaluation Report

complete

DEADP 2015/16:1

EAC Report

completed

annually

1 (100%)

Signed off by HOD on

31 July 2015.

Challenge is

working through

different time

frames, i.e. two

different financial

years for the

Page 43: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

43

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

Monitoring and

Evaluation Report

published completed

2015/16: 4

(optional)

M&E Reports

completed

quarterly but

not obligatory

4 (100%) municipalities and

departments.

80 Facilitate a more

energy efficient and

self-sufficient Western

Cape and to promote

the region as a leading

green economic hub.

Number of Green

Economy projects

supported

DEDAT 2015/16:11 12 (109%) None

Building Sustainable Communities

81 Improving settlement

functionality,

efficiencies and

resilience through

effective air quality

management.

Number of designated

organs of state with

approved and

implemented AQMPs

DEADP 2015/16:3 3 (100%) None

82 Improve public and

non-motorised transport

through mobility and

access enhancement

interventions.

Number of mobility and

access enhancement

interventions supported

DT&PW 2015/16:0 The WCG has initiated

the Provincial Public

Transport Institutional

Framework (PPTIF) as

a mechanism to

promote

improvement in public

and non-motorised

transport across the

Stellenbosch

Municipality has

been selected as

the priority

municipality for

PPTIF

implementation

and engagement

will commence in

Page 44: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

44

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

province. The PPTIF

has identified different

typologies in the

province, and

developed an

incremental

approach to

improvement in public

and non-motorised

transport in each of

these typologies. A

strategy document

has been developed,

including an

implementation plan,

priority

implementation areas

and a financial plan.

Cabinet approval for

this strategy is being

sought, leading to

implementation of the

strategy through the

priority areas and

interventions.

2016/17, while

approval from

Cabinet for the

long term PPTIF

Strategy is being

sought in parallel.

83 Number of subsidized

kilometres operated in

terms of the approved

timetable

DT&PW 2015/16:

35 750 656 km

37 495 646km (105%)

The demand for GABS

services has gradually

The chronic

reduction of

subsidized

services will

continue due to

Page 45: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

45

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

increased over the

past year.

The introduction of the

Atlantis MyCiTi service

allowed the

department, in

collaboration with

GABS, to try and

accommodate the

increased demand

through the

reallocation of buses

that were operational

in this area to those

areas where demand

has exceeded supply.

The Metro South East

Corridor (Mitchells

Plain and Khayelitsha)

is one such area

where there has been

an increased demand

for the service. This is

the situation despite

the roll out of the

MyCiTi N2 Express

services to Cape Town

CBD.

Apart from additional

services that were

the historical and

current context

whereby the

PTOG annual

increase did/does

not keep up with

inflation. There is a

need for

increased

investment in

Public Transport

to improve

access to

opportunities.

The nature of the

Interim Contract

(which is a month

to month

contract) limits

the operator to

strategically

expand and

recapitalize its

fleet.

Page 46: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

46

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

rolled out on existing

routes, new services

were also introduced

where public transport

services are either

limited or completely

nonexistent.

The National

Household Travel

Survey 2013 has

highlighted that a

very large

percentage of the

population cannot

afford transport costs.

In order to address the

issue of affordable

public transport, the

2015/16 annual fare

increase was pegged

far below that of

inflation and was kept

to a minimum to

ensure the provision of

access to markets,

economic

opportunities and

access to social

services.

Page 47: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

47

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

The subsidisation of

public transport

services through the

PTOG is pivotal to

poor communities as it

affords them access

to affordable and

accessible transport

which serves as a

catalyst to economic

opportunities.

84 Improve road safety

through the phased

development and

implementation of a

public transport safety

implementation

programme.

Number of public

transport safety

implementation

programmes

implemented

DT&PW 2015/16:0 With mainly

enforcement

measures, the WCG

managed to reduce

fatalities by approx.

28% in the period

between 2010-2013.

However, road deaths

have been resistant, in

recent months and

new strategies are

sought to capture

new ground. As a

result a strategic and

consolidated

approach is required

hence the

commissioning of the

Public Transport Safety

Stellenbosch

Municipality has

been selected as

the priority

municipality for

PPTIF

implementation

and engagement

will commence in

2016/17, while

approval from

Cabinet for the

long term PPTIF

Strategy is being

sought in parallel.

Page 48: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

48

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

Implementation

Programme.

The project will be

carried out through

the Cape Higher

Education Consortium

(CHEC) with the aim

of developing a

strategy, from

recommended

measures through to

an implementation

approach. To achieve

this, the following nine

tasks were identified.

Task 1: Inception

Task 2 Literature

Review

Task 3: Status Quo

Report

Task 4: Safety

Implementation

Framework Report

Task 5: Road Safety

Response Report

Page 49: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

49

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

Task 6: Institutional

Arrangements

Task 7 Financial

Implication Plan

Task 8: Overall

Implementation Plan

Task 9:

Implementation

Programme

The project team

commenced work in

January 2016 and

have finalised tasks 1,

2 and 3.

The intention is for the

project to be

completed by 31

September 2017.

85 Enhance the provincial

approach to rail and

freight through the

development and

implementation of a rail

and freight

implementation

programme.

Number of

implementation

programmes

implemented for rail and

freight

DT&PW 2015/16:0 Rail Implementation

Programme: During

the course of the

2015/16 financial year,

the PPTIF project team

completed some

initial work on rail in

the Western Cape

and have developed

Rail is a national

competency and

the provincial

mandate

regarding rail is

limited. Through

the PPTIF, the

WCG has

identified joint

Page 50: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

50

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

the report “Towards a

Rail Strategy for the

Western Cape”.

During the course of

2016/17 this strategy

will be developed into

a Rail Implementation

Programme, which will

identify specific

opportunities for the

Western Cape

Government to

support rail in the

Western Cape and will

identify priority rail

investment

interventions in the

Province, including

interventions in the

metropolitan area

where rail has

experienced

significant problems

and service

disruptions linked to

asset safety,

vandalism and theft.

A focus for the Metro

rail interventions will

therefore be on rail

safety and asset

planning of rail

interventions as

an opportunity to

enhance rail in

the province. In

addition, WCG

investment in

targeted rail

interventions,

particularly in the

Cape Town

metropolitan

area, is being

considered,

although fiscal

constraints and

institutional

challenges need

to be resolved.

Page 51: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

51

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

security. A detailed

programme of options

is in development.

86 Improve support to

relevant public and

non-motorised transport

stakeholders by

development and

implementation of

institutional change

initiatives.

Number of institutional

change initiatives

DT&PW 2015/16:0 The PPTIF places

significant emphasis

on human capacity

and the establishment

of pragmatic and

implementable

institutional structures

that respond to the

challenges

experienced on the

ground whilst being

consistent with the

policy and legislative

direction. Specifically,

the PPTIF envisages

institutional structures

that allow for the joint

exercise of local

government public

and non-motorised

transport

responsibilities,

leveraging the

experience and

capabilities of the

provincial department

in this regard.

The PPTIF Strategy

will be considered

considered by

the Provincial

Executive

Committee

during the course

of 2016. Once

approval has

been granted,

the institutional,

organizational

and human

resource

recommendation

can be

implemented. A

further challenge

is the current

fiscal and human

resource

environment,

which

complicates the

restructuring of

the Public

Transport branch

Page 52: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

52

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

Moreover, the PPTIF

has recommended a

restructuring of the

Department of

Transport and Public

Works (Public

Transport branch) to

create an incubator

function, for the

development of local

capacity to drive

public transport

transformation and

non-motorised public

transport

improvement at local

government level,

and a platform

function, to leverage

certain centralized

and technical

functions that can be

provided at a

province-wide scale.

In addition, the PPTIF

has a focus on

institutional and

organizational

change interventions

required to improve

the effectiveness of

in the DTPW

significantly. A

further challenge

is the recognition

that an

organizational

and human

resource change

and

development

process takes

significant time,

particularly where

multiple spheres

of government

are involved.

Thus, dedication

to this

programme will

be required over

a period of time

to see full impact.

Page 53: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

53

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

public transport

stakeholders at

provincial and local

government levels.

These structures and

interventions are due

to be implemented

from the current

financial year 2016/17

onwards.

87 Implement an up-

scaled housing delivery

programme.

Total number of housing

units delivered by 31

March 2030

DoHS 2015/16:10240 10884 (106%) None

88 Implement structured

upgrading of informal

settlements to promote

and secure living

environments.

Total number of serviced

sites delivered Number of

families from informal

settlements that have

been afforded with an

improved housing

opportunity by 31 March

2030

DoHS 2015/16:2379

6227

6 280 (101%) Correction to

target and

indicator.

89 Increase the provision

of water and sanitation

services within informal

settlements.

Percentage of informal

settlements with access

to basic services: water

and sanitation. at a level

of 1:5 by 31 March 2020

DoHS StatsSA:

General

Household

Service

database

2015/16:85%

2015 GHS

data: 12.6% no

access to

toilet. Water

supply type

varies, “none”

not indicated.

Indicator to be

amended as it is not

an Annual

Performance

deliverable of DoHS as

it currently stands.

Activity should still

be tracked.

Obtain these

measures from

StatsSA.

Need to define

“access” to

water.

Page 54: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

54

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

90 Improve the living

conditions of

beneficiaries through

the upgrading and

rectification of housing

units.

Total number of human

settlement opportunities

delivered in terms of

Community Residential

Unit Upgrades and the

Rectification

Programmes by 31

March 2020

DoHS 2015/16:735 852 (116%) None

91 To increase sustainable

resource use, which

includes exploring

innovative technologies

in construction, energy,

water and sanitation.

Total number of houses

built using innovative

technology initiatives

such as construction,

energy, water and

sanitation, by 31 March

2020

DoHS 2015/16:3240 936 (29%) Projects with

innovative

technology

initiatives were

not all completed

during the year

under review.

92 By implementing the

Provincial Land

Assembly Strategy and

Action Plan.

Number of Land

Assembly Strategy review

reports

DEADP 2015/16:1 1 (100%) None

Responding effectively to Climate Change (mitigation and adaptation)

93 Ensuring that the

Climate Change

response mainstreamed

in the Western Cape

Government and

municipalities.

M&E report on the WC

Climate Change

Response Strategy

DEADP 2015/16:1 1 (100%) None

Page 55: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

55

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

94 Ensuring that the

Climate Change

response mainstreamed

in the Western Cape

Government and

municipalities.

District municipalities

adequately

incorporating climate

change into IDPs (as

defined in the WC

Climate Change Status

Quo Assessment)

DEADP 2015/16: High

level

assessment

completed for

all

municipalities

(IDP review);

Climate

change status

quo

assessment

completed for

1 district

1 (100%)

Climate change

status quo assessment

and response

framework completed

for the Central Karoo

district.

None

95 Ensuring that the

Climate Change

response mainstreamed

in the Western Cape

Government and

municipalities.

Number of WCG policies

and strategies for

WCCCRS

alignment/misalignment

completed

DEADP 2015/16:3 3 (100%) None

96 Ensuring that the

Climate Change

response mainstreamed

in the Western Cape

Government and

municipalities.

Number of climate

change response tools

developed

DEADP 2015/16:1 1 (100%)

Western Cape

Provincial Climate

Change Response

Strategy Monitoring &

Evaluation Framework

None

Page 56: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

56

Indicator

number

Activities Indicator Who is

responsible

Target Level of achievement Challenges/

barriers/ Reasons

for deviation

97 Improving resilience to

climate change

through effective and

efficient air quality

management.

Progress Report of Air

Quality Health Risk

Assessment

DEADP 2015/16:1 1 (100%)

None

98 Increase mitigation and

adaptation options

against climate change

for farmers.

Climate change

response plan for

agriculture developed

and implemented

DoA 2015/16:

climate

change

response plan

for agriculture

developed

1 (100%)

Plan developed and

launched

Implementation

will have to be

well coordinated

to have the most

effective impact.

99 Number of climate

change projects

executed

DoA 2015/16:14 14 (100%) None

100 Monitoring energy

consumption and GHG

emissions.

Western Cape Energy

Consumption and CO2

Emissions Database

published

DEADP 2015/16:1 N/A Target incorrectly

captured. Should be

N/A this year as target

is biannual.

Target is biannual.

Last Database

published in

2014/15, so next

due in 2016/17.

Future targets to

be adjusted to:

2016/17: 1

2017/18: N/A

EXPANDED INFORMATION FROM TABLE

Footnote (1)/ Indicator 63

Challenges with Capital Projects:

Scope of work increases on the projects. Better planning of projects to be implemented by Client Department and

Implementing Agent.

Page 57: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

57

More compensation events (extra work requested by the Client Department - Contract Instructions).

Slow progress in some instances due to poor management by Contractor (penalties were applied).

New Framework agreement to be implemented.

Poor performance by main contractors, resulting in extension of the contract period and additional requests from clients /

user departments after the award of the contract, which leads to extended contract periods.

Improvement at the scope and definition stage is required to try and minimize the client/ user department changes.

Developing a revised norms and standards document which is more user friendly to try and standardise the designs for office

accommodation.

Initial targets are set well in advance of the IPMP and acceptance of the IPIP. Misalignment at this stage results in unrealistic

targets.

Delays in achieving Practical completion due to the delayed appointment of an AAIA agent.

Challenges with Maintenance Projects:

Client department increased scope requests after tenders have been awarded or contractor on site, which results in delays.

The additional scope has resulted in a number of Extension of Time Claims from the Contractors and planned targets being

exceeded.

Scope changes are authorised by the Project Leader, Programme Manager or Client Department, depending on the extent

of the scope of work and cost. Project leaders and Programme Managers need to ensure that the Client Departments provide

clear briefs and that the IDMS procedures with regard to briefs are applied to maintenance projects as well.

Unforeseen Scope increase during construction. Better planning of projects to be implemented by Client Department and

Implementing Agent.

Some maintenance contractors not capable of delivering projects within the stipulated time due to limited

experience/expertise, which results in potential contract cancellation and/or penalties levied.

Shortage of works inspectors results in capacity constraints.

5 SUMMARY OF AMENDMENTS TO THE EIP

Below is a summary of the amendments to be effected with respect to the 3rd edition EIP as identified during the 2015/16 financial

year. These amendments will be carried forward into subsequent compliance reports. The categories of amendment used are as

follows:

Page 58: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

58

Addition: A new indicator has been added.

Adjustment: The indicator or target has been changed by the responsible Department since the EIP was published in October 2015.

Correction: There was an error in the indicator or target as captured and published in the EIP, which has been corrected.

Removal: An indicator has been removed in its entirety.

Table 2: Table of amendments to the 3rd Edition EIP as identified during 2015/2016.

Indicator Nature of

Amendment

Requested By Reason

2 ADJUSTMENT DEADP/

CapeNature

CapeNature and DEADP both produced a deliverable that falls under

this indicator during this financial year.

22 REMOVAL DEADP Currently not possible to respond to this indicator as a ranking system for

municipalities is not yet in place. This indicator can be reinstated once

system in place.

27 REMOVAL DT&PW This recommendation emanating from the WCIF was not translated into

an annual deliverable for DT&PW as it was deemed that evaluating the

delivery of infrastructure and their compliance with environmental issues

is covered directly by the other DT&PW indicators which are included in

the EIP.

30 REMOVAL DEADP Indicator to be removed due to duplication with Indicator No. 2.

33 REMOVAL DEADP Indicator to be removed due to duplication with Indicator No. 28.

44 CORRECTION DEADP Correction of target for the 2015/16 financial year. Was incorrectly

captured in EIP.

51 CORRECTION DEADP Target captured incorrectly in EIP and replaced as a percentage

achievement.

Page 59: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

59

55 ADJUSTMENT DoA Target adjustment for the 5 year period 2015-2020. Target reduced due

to budget constraints.

56 ADJUSTMENT DoA Target adjustment for the 5 year period 2015-2020. Target reduced due

to budget constraints.

57 ADJUSTMENT DoA Target adjustment for the 5 year period 2015-2020. Target reduced due

to budget constraints.

58 ADJUSTMENT DoA Target adjustment for the 5 year period 2015-2020. Target increased due

to more severe weather conditions anticipated.

79 CORRECTION DEADP Correction to capture that Sector Plan and Monitoring and Evaluation

Report are separate deliverables, the former is required annually but the

latter is done quarterly but this is not obligatory.

88 CORRECTION DoHS Correction to target and indicator as current wording is not reflective of

the Departments annual deliverables.

89 ADJUSTMENT DoHS/StatsSA Indicator to be amended, as it is not an Annual Performance

deliverable of the DoHS as it currently stands. Still to be tracked via

StatsSA: General Household Service database.

98 CORRECTION DEADP Target years incorrectly typed in EIP. Correct years inserted.

100 ADJUSTMENT DEADP Targets incorrectly captured. Target is biannual and therefore

deliverable is only due next year. Future targets corrected.

6 SUMMARY OF TARGET ACHIEVEMENTS FOR 2015/16

With respect to Provincial Government’s implementation of the programmes, plans and policies that have a significant effect on the

environment of the Western Cape, 84.4% of the priority indicators included in the 3rd edition EIP were achieved or over-achieved for

the 2015/16 financial year. This leaves 15.6% of the indicators having been under-achieved.

Page 60: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

60

Figure 2: Pie chart to illustrate the overall achievement of the indicator targets set for the 2015/16 financial year.

Some of the main reasons for over-achievement of targets were:

Demand driven targets e.g. environmental law enforcement investigations where a high number of complaints will lead to

a larger number of investigations and the exact number cannot be predicted.

Employment of additional staff enabled increased outputs.

Target achievement is dependent on voluntary action by members of the public e.g. payment of fines.

Training given to municipalities resulting in more reports of transgressions, pollution incidents etc.

Land secured for conservation being larger than targeted size.

Larger number of support services provided to clients related to agricultural disaster risk, as a result of the current drought.

More work opportunities created through environmental programmes as contract labour positions were filled in the place

of permanent appointments, which increases the number of employment opportunities accounted for on the project.

Additional requests for capacity building leading to larger numbers of events.

The reasons for under-achievement of targets were, in summary:

Page 61: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

61

Demand driven targets e.g. no control over number of cases brought against the DEADP, however, the lower the total

number of cases against the department the better. Therefore the under-achievement for that indicator was desirable.

Other demand driven targets rely on the number of applications received by the public for processing.

Reduced human resource capacity in some Departments resulting in reduced ability to deliver on all projects. This

challenge may be exacerbated by budget constraints into the 2016/17 financial year across Provincial government.

Delays in information being received from the public in order to finalise various applications.

Procurement process related delays.

Budget constraints.

Amendment of the scope of a project after project initiation.

Clarification of DEA Norms and Standards before proceeding causing delay.

The introduction of a new target assessment tool that negatively affects the target assessment outcomes.

Release of property for regeneration is a long term process. Budget cuts have precluded further work in identifying new

opportunities with a focus on existing projects.

Less technology transfer events organized by agribusiness and other stakeholders.

Contractor challenges with capital and maintenance projects.

Projects not being completed in time, during period of review.

7 COMPLIANCE WITH EIP COMMITMENTS BY LOCAL GOVERNMENT

Section 16(4) of NEMA indicates that provinces are responsible for ensuring that all municipalities within the province comply with

the provincial EIP and the principles in Section 2 of NEMA in the preparation of any policy, programme or plan, including the

establishment of integrated development plans (IDPs). In the Western Cape this is done through the IDP review process, during

which the WCG ensures that municipal IDPs comply with all legislated requirements, as well as assessing the level of environmental

performance of the IDP. IDPs are a critical tool for ensuring that municipalities mainstream and budget for all environmental

obligations. Good and effective governance requires that all levels of government function in an integrated fashion. This is the

focus of PSG 5 of the Province and extensive effort is being exerted to improve alignment.

Page 62: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

62

The DEADP is responsible for reviewing all 30 municipal IDPs on an annual basis for compliance with the legislative requirements

that relate to:

Spatial Development (including sustainability, climate change and biodiversity management)

Air Quality Management

Coastal Management

Waste Management

The results of DEADP’s review, as completed in May 2016, are summarised in Table 3 below to provide an indication only as to the

compliance status of the Municipalities. Table 3 has only made use of the ratings of “fully compliant”, “partially compliant”, “non-

compliant” or “not applicable” that were ascribed for the questions contained in the DEADP compliance checklist for the 2016

IDP/LG MTEC review period. This rating therefore does not illustrate the full picture of the detailed statuses and progress in the

individual municipalities. For a more detailed status and progress per Municipality, the following supplementary information from

the 2016 IDP/ LG MTEC Review Cycle must be consulted:

Final Published LG MTEC Assessment Reports: Budget & IDP Analysis, and

Final Collated Compliance Checklists

It is clear that 100% compliance with the full suite of requirements has not yet been achieved by any municipality, although the

District Municipalities (with the exception of Central Karoo District) and the City of Cape Town Metro have all achieved 100%

compliance with the Air Quality Management requirements which is commendable. It is apparent that most municipalities display

around 30% full compliance and around 30% partial compliance at this stage. Some legislative requirements, particularly with

respect to the spatial development section, are new requirements as stipulated in the Spatial Planning and Land Use

Management Act (No.16 of 2013) (SPLUMA) and these requirements only need to be fulfilled by a later date. Therefore full

compliance at this stage is not reasonable in all instances. The large percentage of questions ascribed to “Not applicable” in

some sections may be, for example, because the municipality is not responsible for the development of an Estuarine

Management Plan (EMP) and thus those questions do not apply. The DEADP provides ongoing support to municipalities with

Page 63: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

63

respect to the areas of partial and non-compliance below. Even fully compliant municipalities will continue to receive ongoing

support from the DEADP. These support initiatives are reflected in the Chapter 4 table (Table 1) as indicators under the Policies,

Plans and Programmes to which they relate.

Table 3: Tabulated summary of DEADP’s IDP review results as taken from the final collated compliance checklists per municipality (It

must be noted that although this speaks to legislative compliance, DEADP is moving towards a more performance based analysis

as well as more outcomes based measure).

Municipality Degree of

Compliance

Spatial

Development

(% out of 15 Qs)

Coastal

Management

(% out of 22 Qs)

Air Quality

Management

(% out of 9 Qs)

Waste

Management

(% out of 14 Qs)

Total

(% out of 60 Qs

- coastal; %

out of 38 Qs -

inland)

Eden DM

Full

20

27.3

100

35.7

38.3

Partial 26.7 13.6 0 14.3 15

Non 20 4.5 0 50 18.3

N/A

33.3 54.5 0 0 28.3

George

Full

20

18.2

66.7

35.7

30

Partial 53.3 22.7 11.1 7.1 25

Non 20 9.1 0 57.1 21.7

N/A

6.7 50 22.2 0 23.3

Hessequa

Full

20

22.7

66.7

14.3

26.7

Partial 46.7 22.7 11.1 35.7 30

Non 26.7 4.5 0 50 20

N/A

6.7 50 22.2 28.6 30

Page 64: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

64

Bitou

Full

40

18.2

66.7

50

38.3

Partial 33.3 22.7 11.1 28.6 25

Non 13.3 9.1 0 21.4 11.7

N/A

13.3 50 22.2 0 25

Knysna

Full

13.3

18.2

66.7

42.9

30

Partial 40 22.7 0 35.7 26.7

Non 40 9.1 11.1 21.4 20

N/A

6.7 50 22.2 0 23.3

Kannaland

Full

33.3

55.6

42.9

42.1

Partial 6.7 No Coastline 11.1 28.6 15.8

Non 40 11.1 28.6 28.9

N/A

13.3 22.2 0 10.5

Mossel Bay

Full

20

27.3

66.7

21.4

30

Partial 53.3 18.2 0 28.6 26.7

Non 13.3 4.5 11.1 50 18.3

N/A

13.3 50 22.2 0 25

Oudtshoorn

Full

6.7

0

14.3

7.9

Partial 46.7 No Coastline 33.3 28.6 36.8

Non 40 44.4 57.1 47.4

N/A

6.7 22.2 0 7.9

Cape

Winelands DM

Full

0

No Coastline

100

14.3

28.9

Partial 46.7 0 21.4 26.3

Non 20 0 28.6 3

N/A

33.3 0 35.7 26.3

Page 65: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

65

Breede Valley

Full

13.3

33.3

35.7

26.3

Partial 60 No Coastline 44.4 21.4 42.1

Non 20 0 42.9 23.7

N/A

6.7 22.2 0 7.9

Drakenstein

Full

6.7

66.7

50

36.8

Partial 53.3 No Coastline 11.1 28.6 34.2

Non 40 0 21.4 23.7

N/A

0 22.2 0 5.3

Langeberg

Full

13.3

33.3

35.7

26.3

Partial 40 No Coastline 0 50 34.2

Non 40 66.7 14.3 36.8

N/A

6.7 100 0 26.3

Stellenbosch

Full

20

66.7

57.1

44.7

Partial 46.7 No Coastline 0 21.4 26.3

Non 20 11.1 21.4 18.4

N/A

6.7 22.2 0 7.9

Witzenberg

Full

13.3

66.7

42.9

36.8

Partial 53.3 No Coastline 11.1 21.4 31.6

Non 26.7 11.1 35.7 26.3

N/A

6.7 22.2 0 7.9

Overberg DM

Full

6.7

13.6

100

28.6

28.3

Partial 40 22.7 0 35.7 26.7

Non 20 9.1 0 14.3 11.7

N/A

33.3 54.5 0 21.4 33.3

Page 66: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

66

Cape Agulhas

Full

20

13.6

77.8

42.9

31.7

Partial 46.7 22.7 0 14.3 23.3

Non 20 9.1 0 42.9 18.3

N/A

13.3 54.5 22.2 0 26.7

Overstrand

Full

13.3

18.2

55.6

42.9

28.3

Partial 60 27.3 11.1 14.3 30

Non 13.3 4.5 11.1 42.9 16.7

N/A

6.7 50 22.2 0 23.3

Swellendam

Full

13.3

9.1

77.8

7.1

20

Partial 53.3 22.7 0 35.7 30

Non 20 9.1 0 57.1 21.7

N/A

6.7 4.5 22.2 0 6.7

Theewaterskloof

Full

20

66.7

14.3

28.9

Partial 46.7 No Coastline 11.1 35.7 34.2

Non 20 0 50 26.3

N/A

13.3 22.2 0 10.5

Central Karoo

DM

Full

6.7

77.8

50

39.5

Partial 53.3 No Coastline 11.1 14.3 28.9

Non 0 11.1 35.7 15.8

N/A

40 0 0 15.8

Beaufort West

Full

20

44.4

50

36.8

Partial 53.3 No Coastline 0 14.3 26.3

Non 13.3 33.3 35.7 26.3

N/A

13.3 22.2 0 10.5

Page 67: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

67

Laingsburg

Full

20

0

50

26.3

Partial 40 No Coastline 0 7.1 18.4

Non 26.7 77.8 42.9 44.7

N/A

13.3 22.2 0 10.5

Prince Albert

Full

20

66.7

35.7

36.8

Partial 60 No Coastline 11.1 14.3 31.6

Non 13.3 0 50 23.7

N/A

6.7 22.2 0 7.9

West Coast DM

Full

40

18.2

100

42.9

41.7

Partial 26.7 18.2 0 14.3 16.7

Non 6.7 9.1 0 42.9 15

N/A

26.7 54.5 0 0 26.7

Berg Rivier

Full

40

9.1

55.6

35.7

30

Partial 40 31.8 11.1 35.7 31.7

Non 13.3 9.1 11.1 28.6 15

N/A

6.7 50 22.2 0 23.3

Cederberg

Full

20

9.1

11.1

35.7

18.3

Partial 53.3 27.3 22.2 14.3 30

Non 20 9.1 44.4 50 26.7

N/A

6.7 54.5 22.2 0 25

Matzikama

Full

40

9.1

55.6

0

21.7

Partial 40 22.7 11.1 50 31.7

Non 13.3 22.7 11.1 42.9 23.3

N/A 6.7 45.5 22.2 7.1 23.3

Page 68: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

68

Saldanha Bay

Full

20

13.6

77.8

28.6

28.3

Partial 33.3 22.7 0 21.4 21.7

Non 40 4.5 0 50 23.3

N/A

6.7 59.1 22.2 0 26.7

Swartland

Full

53.3

4.5

77.8

28.6

33.3

Partial 20 18.2 0 28.6 18.3

Non 13.3 22.7 0 42.9 21.7

N/A

13.3 54.5 22.2 0 26.7

City of Cape

Town Metro

Full

80

18.2

100

71.4

58.3

Partial 20 31.8 0 21.4 21.7

Non 0 4.5 0 7.1 3.3

N/A

0 45.5 0 0 16.7

Page 69: THIRD EDITION ENVIRONMENTAL IMPLEMENTATION PLAN (EIP) … EIP 1st... · Project Manager: Tammy Christie Director: Ronald Mukanya . Western Cape Government ... Report (2016) Western

Western Cape Government – 1st Annual Compliance Report on the 3rd Edition EIP – July 2016

69

8 CONCLUSION

The first compliance report on the 3rd Edition EIP has revealed that the Province has achieved (and in some instances over-

achieved) 84.4% of the targets set for the 2015/2016 financial year with respect to all of the priority indicators. There is therefore a

shortfall of 15.6% of targets that were not reached. Detailed reasons for these shortfalls are provided in Table 1, and summarised

in Chapter 6, and have revealed that in many cases demand driven indicators or external factors prevented the responsible

Department from reaching a target. There is always room for improvement and the responsible Departments are requested to

focus their attention on the indicators for which targets were not met.

Capturing local authority compliance with the EIP in a similar format to Table 1 is a challenge as municipalities are already

assessed in terms of their environmental compliance during the extensive IDP review cycle which occurs annually. A summary of

the results of the DEADP IDP review process, focussing on Spatial Development, Air Quality Management, Coastal Management

and Waste Management, has been included this year as an indication of current levels of municipal compliance. This review is

based on legislative compliance. The desired end state is to shift to a more performance-based assessment in future.

The Western Cape EIP Annual Compliance Report 2015/16 is herewith submitted.

_____________________ _21 July 2016__

P VAN ZYL DATE

HEAD OF DEPARTMENT

DEPARTMENT OF ENVIRONMENTAL AFFAIRS AND DEVELOPMENT PLANNING

WESTERN CAPE