Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Calhoun: The NPS Institutional Archive
Theses and Dissertations Thesis Collection
2001-06
Analysis and application of earned value
management to the Naval Construction Force
Hayes, Richard D.
http://hdl.handle.net/10945/10949
^mmm^M^¥^!
w%m
em
gjw^ipjjtep;
Analysis and Application of Earned Value Management to the
Naval Construction Force
By
Richard D. Hayes, III
DISTRIBUTION STATEMENT A Approved for Public Release
Distribution Unlimited
June 2001
ONSTRUCTION tflcMIINTflLcI? ANAGEMENT
PURDUE UNIVERSITY
20011023 021
Division of Construction Engineering and Management School of Civil Engineering Purdue University West Lafayette, Indiana 47907-1294
Analysis and Application of Earned Value Management to the
Naval Construction Force
An Independent Research Study Presented to
The Faculty of
The School of Civil Engineering Purdue University
By Richard D. Hayes, III
In Partial Fulfillment of the Requirements for the Degree of
Master of Science in Engineering
June 2001
Approved:
fofessopDaniei W. Halpin Chairman, AdvisorV Committee
Professor Dulcy M. Abraham Member, Advisory Committee
Professor David J. Harmelink Member, Advisory Committee
Abstract
This paper investigates the application of Earned Value Methodology to Naval
Construction Force (NCF) projects. Earned Value Management integrates technical
performance, cost, and schedule goals into a comprehensive analysis tool. A guide to the
elements, metrics, and steps required in implementing an Earned Value Management System
is provided from an extensive literature review on the subject matter. Application to the
Naval Construction Force is made through comparison with existing project management
fundamentals and sample project analysis. While these existing fundamentals include some
of the basics components of earned value analysis, a full utilization of the analysis and
forecasting techniques afforded by the earned value approach is not in place. Conclusions and
recommendations for future research are presented.
Table of Contents
Page
ABSTRACT I
TABLE OF CONTENTS H
LIST OF FIGURES IV
LIST OF TABLES V
LIST OF EQUATIONS VI
LIST OF ABBREVIATIONS AND SYMBOLS VII
1. INTRODUCTION 1 1.1 Research Objective 2 1.2 Research Methodology 2 1.3 Research Organization 2
2. WHAT IS EARNED VALUE MANAGEMENT? 4 2.1 Origin and Evolution 4 2.2 Traditional Cost Management vs. Earned Value 6 2.3 Elements of Earned Value 8
2.3.1 Budgeted Cost of Work Scheduled 8 2.3.2 Budgeted Cost of Work Performed 9 2.3.3 Actual Cost of Work Performed 9
2.4 Summary 9
3. ESTABLISHING AN EARNED VALUE MANAGEMENT SYSTEM 10 3.1 Organization 10
3.1.1 Work Breakdown Structure 11 3.1.2 Organization Breakdown Structure 12 3.1.3 Control Accounts 13
3.2 Planning, Scheduling, and Budgeting 14 3.2.1 Planning and Scheduling of Work Packages 14 3.2.2 Scheduling 15 3.2.3 Estimate and Budget Project Resources 16 3.2.4 Establish Baseline 16
3.3 Revisions 17 3.4 Accounting 17 3.5 Analysis 17
3.5.1 Measuring Earned Value 18 3.5.2 Variances 21
li
3.5.3 Performance Indices 25 3.5.4 Overall Project Status Indicators 28 3.5.5 Forecasting 29
3.6 Summary 34
4. NAVAL CONSTRUCTION FORCE PROJECT MANAGEMENT 35 4.1 NCF Overview 35
4.1.1 Naval Mobile Construction Battalions 36 4.2 Project Planning .36
4.2.1 Fundamentals of Seabee Construction Management 37 4.2.2 Detailed Planning 38 4.2.3 Construction Activity Summary Sheets 40 4.2.4 Construction Scheduling 40 4.2.5 Budgeting of Resources 42
4.3 Project Monitoring and Reporting 43 4.3.1 Situation Reports 43 4.3.2 Estimated Mandays 44 4.3.3 Earned Mandays 44 4.3.4 Expended Mandays 45 4.3.5 Scheduled Percent Complete 45 4.3.6 Actual Percent Complete 45 4.3.7 Analysis of Project Performance 46
4.4 Summary 47
5. PRACTICAL APPLICATION OF EARNED VALUE MANAGEMENT 48 5.1 Application of Earned Value Concepts 48 5.2 Methodology 49 5.3 Review of Application 50 5.4 Obstacles to Implementation 52
5.4.1 Training 52 5.4.2 Accurate Accumulation of Data 52 5.4.3 Revision of Deployment Tasking 53 5.4.4 Support of System 53
5.5 Summary 53
6. CONCLUSIONS AND RECOMMENDATIONS 54 6.1 Conclusions 54 6.2 Recommended Research 55
BIBLIOGRAPHY 56
APPENDDC A. EARNED VALUE MANAGEMENT SYSTEM CRITERIA 60
APPENDIX B. EARNED VALUE QUICK REFERENCE SHEET 63
APPENDIX C. RESULTS OF PRACTICAL APPLICATION 64
in
List of Figures
Page
Figure 1.1 - Earned Value Management an Integrating Tool 1
Figure 2.1 -Traditional Cost Management: Plan versus Actual Costs 7
Figure 2.2 -Earned Value Project Management: Three Dimensional 7
Figure 3.1 - Work Breakdown Structure 12
Figure 3.2-Interrelation ofWBS and OBS 13
Figure 3.3 - Relation of Schedule to Work Breakdown Structure 15
Figure 3.4 - Schedule and Cost Variance Example 23
Figure 3.5 - Graphical View of Schedule and Cost Variances 24
Figure 3.6 - Schedule Performance Index 25
Figure 3.7 Cost Performance Index 26
Figure 3.8 - Six Scenarios of Earned Value Analysis 27
Figure 3.9 - Forecast of Scheduled Completion Date 33
Figure 3.10 - Earned Value Parameters 34
Figure 4.1 - Seabee Multi-Level Construction Management 37
Figure 4.2 - Project Planning Flowchart 39
Figure 5.1 - Tracking Cumulative Cost and Schedule Variances 50
Figure 5.2 - Tracking Cumulative Performance Indices 51
Figure 5.3 - Range of EAC Forecasts on NMCB Project 51
IV
List of Tables
Page
Table 4.1-Units of the NCF 35
Table 4.2 - NMCB Project Planning Milestones 39
Table 4.3 - Production Efficiency Factor Guide 43
Table 5.1 -Comparison of Earned Value and NCF Terminology 49
List of Equations
Page
Equation 3.1 - Schedule Variance 21
Equation 3.2-Schedule Variance Percent 22
Equation 3.3 - Cost Variance 22
Equation 3.4 - Cost Variance Percent 23
Equation 3.5 - Schedule Performance Index 25
Equation 3.6 - Cost Performance Index 26
Equation 3.7-Percent Complete 28
Equation 3.8-PlannedPercent Complete 28
Equation 3.9-Percent Spent 28
Equation 3.10-Estimate at Completion 30
Equation 3.11 - Composite Index 30
Equation 3.12-Schedule Cost Index 30
Equation 3.13 -Variance at Completion 31
Equation 3.14-Variance at Completion Percent 31
Equation 3.15-To-CompletePerformance Index 32
Equation 4.1 - Manday Calculation 42
Equation 4.2 - Seabee Delay Factor 42
VI
List of Abbreviations and Symbols
ACWP ANSI/EIA
BAC BCWP BCWS C/SCSC C/SSR CAS CEC cn CPI CPM CV cv% DOD DSMC EAC ETC EVM EVMS LOE MD NCB NCF NDIA NMCB OBS PERT PMB PMI SCI SITREP SPI SV sv% TCPI VAC VAC% WBS
Actual Cost of Work Performed American National Standards Institute/Electronic
Industries Association Budget at Completion Budgeted Cost of Work Performed Budgeted Cost of Work Scheduled Cost/Schedule Control Systems Criteria Cost/Schedule Status Report Construction Activity Summary Civil Engineer Corp Construction Industry Institute Cost Performance Index Critical Path Method Cost Variance Cost Variance Percent Department of Defense Defense Systems Management College Estimate at Completion Estimate to Completion Earned Value Management Earned Value Management System Level of Effort Manday Naval Construction Brigade Naval Construction Force National Defense Industrial Association Naval Mobile Construction Battalion Organization Breakdown Structure Program Evaluation and Review Technique Performance Measurement Baseline Project Management Institute Schedule Cost Index Situation Report Schedule Performance Index Schedule Variance Schedule Variance Percent To Complete Performance Index Variance at Completion Variance at Completion Percent Work Breakdown Structure
Vll
1. Introduction
"Earned Value Management is the use of an integrated management system that
coordinates work scope, schedule, and cost goals and objectively measures progress toward
these goals. Earned Value Management (EVM) emphasizes the planning and integration of a
program's technical performance, cost, and schedule, to support program manager's
decisions." Figure 1.1 depicts this relationship:1
Figure 1.1 - Earned Value Management an Integrating Tool
EVM uses progress against previously defined work plans to forecast such important
concerns as estimated completion costs, finish dates, and the effectiveness of corrective action
plans. Earned value is the measurement of what was physically received for what was actually
spent, or the value of work accomplished.
The concept of earned value has gone by various titles including industrial factory
standards, earned value management, performance measurement, the Cost/Schedule Control
Systems Criteria (C/SCSC), as well as Program Evaluation and Review Technique (PERT).
Regardless of the term used, the focus of earned value has been consistent: "the accurate
measurement of 'work in progress' against a detailed plan to indicate what will happen to
work on the project in the future."2
1 Defense Systems Management College (DSMC), 2001, p.3 2 Fleming, Koppelman, 1996, p.13
1.1 Research Objective
The primary objective of this paper is to assemble, organize, and assess the applicability
of Earned Value Management to the project management techniques used by the Naval
Construction Force. To achieve this objective, the following questions will be addressed:
1. What is Earned Value Management? Although much has been written concerning this
subject, this paper will attempt to distill the published information into a concise
description of the techniques and methodology that can be used in applying this
concept.
2. What steps are necessary to implement earned value analysis? From the definition of
Earned Value Management that will be provided, a broad overview of the steps
necessary to begin analyzing earned value data will be provided.
3. Are there metrics or tools from earned value analysis that can be applied to Naval
Construction Force project management? Finally, this paper will analyze the results of
an application of earned value metrics to actual Naval Mobile Construction Battalion
projects.
1.2 Research Methodology
To achieve the objectives of this research, a comprehensive literature review was
conducted on the topic of Earned Value Management and how to best implement it. Next an
application of the concept was made utilizing current Naval Mobile Construction Battalion
projects was conducted in order to test the validity of the researched performance metrics.
Conclusions and recommendations for future research were developed from this analysis and
from personnel experiences.
1.3 Research Organization
This research paper is organized into six chapters that will move the reader from an
introduction of earned value management and the processes involved with establishing this
analysis tool, to how it can be utilized by the Naval Construction Force. Projects from two
Naval Mobile Construction Battalions will be utilized to highlight the analysis possibilities
that could be realized. Finally, the research wraps ups with conclusions and recommendations
for future research.
Chapter 1 is an introduction to the subject of Earned Value Management and the
objectives of this paper. Chapter 2 details the evolution of Earned Value Management and the
basic elements involved in analyzing its data. Chapter 3 builds on the concepts presented and
outlines the steps required in implementing an Earned Value Management System. This
chapter also presents performance measurement tools for calculating and analyzing project
data. In Chapter 4, the focus shifts to the Naval Construction Force and its project
management fundamentals. Comparisons are made with these techniques and the earned
value approach. In Chapter 5, a practical application of the methodology identified in this
paper is presented and reviewed along with challenges that could impede the full
implementation of the earned value approach. Finally, Chapter 6 concludes the paper and
recommends areas for future research.
2. What is Earned Value Management?
This chapter presents the evolution of Earned Value Management along with an
introduction to its key elements and concepts. It summarizes the findings of a literature review
on how this management philosophy is described in books, journal articles, papers, and on the
Internet.
2.1 Origin and Evolution
Although it has only been of late that the earned value concept has truly gained in
prominence, it is a concept conceived by industrial engineers who worked in American
factories over a century ago. By converting "planned industry standards" into "earned
standards" and then relating them against "actual hours" these engineers began to focus on true
cost performance. This distinction forms the basis of earned value management.
The driving force behind the evolution of this technique has been the United States
Department of Defense (DOD). In 1958, the U.S. Navy first introduced the Program Evaluation
and Review Technique (PERT) as a network-scheduling device for the Polaris Weapons
System.4 By 1962, PERT incorporated resources into its network analysis thereby managing
both time and cost.5 Due to a combination of insufficient computer resources, complexity, and
rigorous implementation requirements PERT was essentially abandoned as a management tool
by the mid-1960s.6 However, the significance of PERT was not its technique, but that it used
earned value data to monitor the true cost performance during the life of a project.
Realizing the usefulness of earned value data, the U.S. Air Force implemented the first true
earned value management approach as part of their Minuteman Program in 1963.7 One key
difference between this approach and the previous PERT techniques was that the Air Force
compiled thirty-five criteria defining the minimum requirements of an acceptable project
management system. This innovation gave each contractor the flexibility to tailor its individual
3 Fleming, Koppelman, 1994, p. 24 4 Department of the Navy (DON), 1958. 5 Fleming, Koppelman, 1997, p. 13 6 Fleming, Koppelman, 1996, p. 27 7 Abba, 1997, p. 59.
system in order to meet contract requirements. Finally, in 1967, the DOD formally issued what
was called Cost/Schedule Control Systems Criteria (C/SCSC) as part of DOD Instruction
7000.2.8
During the next three decades, significant knowledge was gained regarding the earned
value concept using the C/SCSC. Unfortunately, the concepts of earned value remained largely
restricted to the acquisition of major systems by the government and were not fully embraced
by private industry.9 By 1994, earned value was being described as one of the most
underutilized cost management tools available to project managers.10 Some of the reasons for
this lack of use were excessive checklists and paperwork, specialist acronyms, and rising
administrative costs due to over-implementation of the C/SCSC criteria.11 Some viewed the
earned value methodology as excessive "bean counting",12 a stance resulting from bureaucratic
interpretations of the C/SCSC criteria that were slowly increasing the burden on contractor's
management systems. With concern rising amongst both private industry contractors and the
DOD, the earned value concept was ready for reform.
In order to take Earned Value Management techniques beyond a government mandate,
both private industry and the U.S. government strived to make it more user-friendly. In addition
to being simpler to use, both parties wanted to make the criteria more compatible with the
needs of private industry. As part of a National Defense Industrial Association (NDIA)
initiative, private industry took a proactive role in reengineering the original 35 C/SCSC into
the Earned Value Management System criteria, which consisted of 32 straightforward
guidelines.13
In 1997, these 32 criteria were accepted by the DOD and incorporated as part of DOD
Instruction 5000.2R.14 However, in the course of modifying the criteria, two significant shifts
occurred. First, it came to be identified more as a project management technique vice a
financial management one. Second, the ownership of earned value transferred from the DOD to
8 Department of Defense Instruction (DODI) 7000.2 9 Fleming, Koppelman, 1996, p.30 10 Fleming, Koppelman, 1994, p. 21 11 Antvik, 1998 12 Abba, 1997, p.61 13 Fleming, Koppelman, 1999, p.l 14 DODI 5000.2R
private industry. To solidify these changes, the Earned Value Management System was adopted
as American National Standards Institute (ANSI/EIA) Standard #748 in July 1998.15
Today, Australia, Canada, New Zealand, and Sweden have all expressed interest in
cooperating with the U.S. in making the concept of earned value a worldwide project
management technique. Abba summarizes the evolution and future of earned value
management as:
Nearly 30 years after being introduced as DOD policy, earned value management is seen as a significant reform activity. For people involved in earned value, whether in government, industry, academia, or consulting, these are exciting times. A good idea from three decades ago has been reinvented as a valuable and fundamental tool.16
The viability of earned value management has been tested, improved, and adopted by both
the Government and private industry. With increasing emphasis and widespread use, it truly is
a technique that project managers everywhere can use.17
2.2 Traditional Cost Management vs. Earned Value
In describing earned value, it is probably best to first compare it with a more customary
cost management technique. Under what Fleming and Koppelman describe as traditional cost
management, a two-dimensional approach is employed: the simple relation of planned costs to
the actual costs as shown in Figure 2.1.18 Using this approach, it is difficult if not impossible to
determine the true cost performance, since a comparison between the budgeted plan and actual
costs can be faulty and misleading.19
15 Fleming, Koppelman, 1996, p. 32 16 Abba, 1997, pg. 61 17 Fleming, Koppelman, 1996, p. 32 18 Fleming, Koppelman, 1994, p. 22 19 Fleming, Koppelman, 1996, p. 18
Thousands (000) s^us
Date uuu
750 ,.,- ,'"
Planned Funds -***"
500 = $300K
•i-> Cost Actuals = $300K
250
S ir
1 2 3 4
Authorized Budget
$1,000,000
Quarters
„20 Figure 2.1 - Traditional Cost Management: Plan versus Actual Costs
In contrast, earned value project management adds a third dimension: the amount of work
accomplished or the value of the work performed.21 With this third dimension, a project
manager has a better measure of "what they got for what they paid." By comparing the earned
value to the planned cost for a given period, the project manager can now identify whether the
project is ahead or behind schedule. Similarly, by comparing the earned value to the actual
costs expended during a given period, a determination of whether the project is underrunning or
overrunning its budget can be made.22 See Figure 2.2 below for an illustration of this concept.
Thousan
$1,000
ds{000) s* tus te Authorized
Budget ^-'"' $1,000,000
750 ,..-'''
500 Planned Value
= $300K ,*'" ^"A •*-V Cost Actuals = S300K
250
^' i
—+• EarnedValue = $200K
1 2 3 4 1 Quarters
Figure 2.2 - Earned Value Project Management: Three Dimensional 23
20 Fleming, Koppelman, 1996, p. 18 Fleming, Koppelman, 1994, p. 22
' Christensen, 1994, p. 30 1 Fleming, Koppelman, 1996, p. 19
2.3 Elements of Earned Value
With the introduction of earned value data, the three primary elements for deriving
performance in earned value project management can be defined. The three elements are:
1. Planned Value -» Budgeted Cost for Work Scheduled, (BCWS)
2. Actual Costs -* Actual Cost of Work Performed, (ACWP)
3. Earned Value -» Budgeted Cost of Work Performed, (BCWP)24
2.3.1 Budgeted Cost of Work Scheduled
The BCWS, or "Planned Value", is the sum of the budgets, usually expressed in dollars or
man-hours, for all planned work scheduled to be accomplished within a given period.25 One
common method to develop BCWS is to use a computerized scheduling system and apply
budget estimates to individual schedule activities. Based on the time when the activities are
scheduled to occur, the application produces a histogram and/or a curve that displays the
summation of the activity budgets for the work scope in predetermined time periods.26 When
calculating the BCWS two additional parameters to review are Performance Measurement
Baseline and Budget at Completion.
2.3.1.1 Performance Measurement Baseline
The Earned Value Management Implementation Guide defines the Performance
Measurement Baseline (PMB) as, "The time-phased budget plan against which contract
performance is measured."27 It is the sum of all activities' BCWS for each time period,
calculated for the total project duration. When graphed, the PMB forms the familiar S-curve for
planned work. It is important to note that the BCWS is a segment of the PMB and as such
represents all the tasks scheduled for accomplishment within a given period.28
24 Christensen, 1999, p. 284 25 PMI, 1996, p. 160 26 Short, 1993, p. 36 27 DOD, 1996, p. 10 28 DOD, 1996, p. 10
2.3.1.2 Budget at Completion
Budget at Completion (BAC) is the cumulative sum for all Budgeted Costs of Work
Scheduled and represents the original estimate of the cost for a project. It denotes the
endpoint of the time-phased PMB curve.
2.3.2 Budgeted Cost of Work Performed
The Earned Value Management Glossary defines BCWP, commonly referred to as the
"Earned Value", as "the sum of the approved budgets, usually in terms of dollars or man-hours,
for activities or portions of activities completed during a given period."30 The various methods
for calculating earned value are discussed in the next section of this paper.
2.3.3 Actual Cost of Work Performed
The ACWP are the costs, usually in terms of dollars or man-hours, actually incurred and
recorded for accomplishing the tasks performed on a project within a given time period.31 As
such, it is representative of all accrued expenditures incurred in completing the work.32 This
includes charges for goods and services received and other assets acquired, such as invoices for
work, material delivered, progress payments and fees/profit allocable to the contract.33
2.4 Summary
In this chapter, the history and evolution of Earned Value Management was outlined with
comparisons made with traditional cost management. With earned value management, a key
third element is introduced, namely the "earned value" for the work performed. From the
definitions provided for the basic elements, a further look at the steps to establishing a
management system based on these elements can be made.
29 Air Force Materiel Command (AFMC), 1998, p. 39-26c 30 EVM Homepage: Glossary, p.l 31 AFMC, 1998, p. 39-26a 32 PMI, 1996, p. 108 33 Valkenhoff, 1981, p. 222
3. Establishing an Earned Value Management System
With an understanding of the basic elements in place, the process of initiating an Earned
Value Management System (EVMS) can be discussed. As previously mentioned, 32 criteria
have been internationally accepted for use in establishing an EVMS. These criteria are
expressed in fundamental terms and provide contractors the flexibility to optimize their
management system while remaining fully accountable for its effectiveness.34 The guidelines
are structured in five areas common to a contractor's management processes:35
• Organization
• Planning, Scheduling, and Budgeting
• Revisions
• Accounting
• Analysis
Each of the criteria addresses a principle necessary for effective management of a project.
"For example, one criterion requires that each element of work on the project have a schedule.
Another requires that each element of work on the project have a budget. A sufficient
management control system that promotes proper planning and integration of work on a project
is vital to the effective use of EVM."36
The entire set of 32 criteria that have been adopted can be found in Appendix A. However,
this research paper will not review and analyze each criteria, instead it will focus on a broader
overall view of the major categories to describe the implementation process. It is the author's
belief that this will provide the reader with a simpler understanding of the steps required.
3.1 Organization
The project manager's ability to define and control a project's full scope of the work is a
key element to its success.37 The scope of a project, however, can be different amongst the
various parties involved. While all might agree on what the outcome should be, each
34 DOD, 1996, p.4 35 DODI 5000.2R 36 Delaney, 2000, p3
10
individual's specific involvement varies with the nature of the work they are to perform. A
subcontractor, for example, understands his scope of work in a much narrower degree of detail
than the prime contractor does. As scope is defined, it is important that all involved have a clear
understanding of the tasks necessary to complete the project.
"When there is poor scope definition, final project costs can be expected to be higher
because of the inevitable changes which disrupt project rhythm, cause rework, increase project
time, and lower the productivity and morale of the workforce."38 If the scope of work is not
defined accurately or communicated to all involved, then the outcome of the project will not be
as expected. Consequently, with no baseline against which the scope can be measured, it is not
possible to distinguish scope changes from project development.39 Plainly put, without a well-
defined scope of work, one cannot distinguish between agreed upon work and any additional
work that may arise. Therefore, it is essential to properly define the projects total scope of work
in order to establish a baseline against which to utilize earned value analysis.40
3.1.1 Work Breakdown Structure
During the 1960's, the momentum to develop a tool to help project managers define a
project in a cohesive way gave rise to the development of the Work Breakdown Structure
(WBS).41 John Mansuy's article "Work Breakdown Structure: A Simple Tool for Complex
Structures" offers the following:
"A Work Breakdown Structure is a tool that helps you plan, organize, and control any project. In this age of complex management techniques, it is often overlooked because of its simplicity. Yet, this simplicity makes the WBS a powerful project management tool that can be used with little financial or personnel resources."42
While a Statement of Work defines the overall requirements for a project, the WBS
provides the basic framework for identifying each element of the project in increasing levels of
detail. The Guide to the Project Management Body of Knowledge defines a WBS as:
37PMI, 1996, p.52 38 CII, 1986, p.45 39 Kraus, 1992 40 Fleming, Koppelman, 1994, pp. 22-24 41 DSMC, 2000, p. 3-8 42Mansuy, 1991, p. 15
11
"A task-oriented "family tree" of activities, which organizes, defines and graphically displays the total work to be accomplished in order to achieve the final objectives of a project. Each descending level represents an increasingly detailed definition of the project objectives."43
Breaking the project down into manageable work elements allows these elements to be
used throughout the project for planning, scheduling, budgeting, performance evaluation, and
most importantly, for earned value analysis. See Figure 3.1 for an example WBS.
Level 1 House
1 1
Level 2 House
Grounds House
Structure House
Subsystems Project
Management
1 1 1 1
I Front Yard Driveway Rear Yard Mechanical
Systems Electrical Systems
HVAC
T-Level 3
II I 1 1 1
| Electrical 1 Wiring
Mechanical numbing
Interior Detaiing
Doors and Windows Roof Framing Concrete
Figure 3.1 - Work Breakdown Structure .44
3.1.2 Organization Breakdown Structure
An essential component of the earned value concept is that responsibility be assigned for
each element of the WBS.45 To facilitate this, an Organization Breakdown Structure (OBS) is
used. The OBS defines the organizational elements responsible for performance of the project
work. It is a hierarchical depiction of the management organization required to perform the
work outlined on the Work Breakdown Structure.46 In essence, the OBS should reflect the way
in which a contractor has organized the people who will accomplish the work. The interrelation
of the WBS and OBS is shown in Figure 3.2 on the following page.
PMI, 1987 43
44 Fleming, Koppelman, 1996, p. 55 45 Wilkens, 1997, p.5 46 Fleming, Koppelman, 1996, p. 201
12
c 1
_ i
i a.
SI l s
at ■c i e tu
Work Breakdown Structure - WBS
Project
Coat Accounts
I-Scop« or Work Z- Schedule 3- Budget
Figure 3.2 - Interrelation of WBS and OBS
3.1.3 Control Accounts
At the intersection of the WBS and the OBS, where responsibility has been established for
work activities, one can find the control account (also known as the cost account in C/SCSC
criteria). This resulting intersection creates a performance measurement unit that combines the
schedule, cost, and technical aspects of the project.47 Department of Defense Instruction
5000.2R defines the control account as,
"A management control point at which actual costs may be accumulated and compared to the budgeted cost of work performed. A control account is a natural control point for cost and schedule planning and control, because it represents the work assigned to one responsible organizational element on one work breakdown structure element." 8
Control accounts provide a correlation between the amount of work that is planned and the
resources available to accomplish that work. Each control account generally contains three
pieces of information: the scope of work for the associated WBS element, its schedule, and its
budgeted cost.49 The development of these components will be discussed in the next section.
47 Fleming, Koppelman, 1996 p. 115 48 DODI 5000.2R 49 Fleming, Koppelman, 1995, p. 40
13
3.2 Planning, Scheduling, and Budgeting
Following organization, the next step incorporates the planning of project activities within
the control accounts, logically sequencing them into a project schedule, and then assigning an
estimated budget to that activity.
3.2.1 Planning and Scheduling of Work Packages
Work packages are defined as natural subdivisions of a control account that represent a
particular job assignment or work activity. Work packages also represent the basic building
blocks used in planning, controlling, and measuring project performance.50 As outlined in the
Earned Value Management Implementation Guide, a work package should have the following
characteristics:
• It represents units of work at levels where work is performed.
• It is clearly distinguished from all other work packages.
• It is assignable to a single organizational element.
• It has scheduled start and completion dates and, as applicable, interim milestones, all of which are representative of physical accomplishment.
• It has a budget or assigned value expressed in terms of dollars, man-hours, or other measurable units.
• Its duration is limited to a relatively short span of time or it is subdivided by discrete value milestones to facilitate the objective measurement of work performed.
• It is integrated with detailed engineering, manufacturing, or other schedules.51
Since the work package is the lowest level at which performance data is normally
analyzed, it is important to balance its duration and scope against the length of the reporting
cycle. When longer duration work packages are used, it is harder to determine status due to the
volume of work involved. On the other hand, when work packages are defined at too low a
level of detail, the administrative burden involved with tracking the work can be excessive.
50 PMI, 1996, p. 61 51 DOD, 1996, p. 11
14
Finally, for each work package, the milestones, technical performance goals, or other indicators
that will be used to measure performance should be identified in the initial planning phase.52
3.2.2 Scheduling
It is essential that a project employing the earned value concept have at a minimum a
master project schedule, thereby establishing a baseline against which future performance can
be compared. The master schedule and any subordinate schedules for a project should be
related to the work levels identified by the WBS, as shown in Figure 3.3. Although any
scheduling technique will work, a critical path method (CPM) is generally utilized.54 With the
time-phased sequencing that the CPM affords, the budgeted value for each planned work
package can be aligned to establish the performance measurement baseline. With any project,
there will always be a tradeoff between cost, schedule, and performance. "The best schedule
supports the best tradeoff between these competing demands, taking into account the risks that
are associated with each tradeoff and the impact on the overall program."55
Work Breakdown Structure - WBS
Master Schedule
Intermediate Schedule
■i 'i 'i 'i 'i 'i 'i 'i '. 'i '. CT ','.'. '.\\
Level 2
1.0
l.l 1.2
1.1.1 1.1.2
Delail Schedule
Figure 3.3 - Relation of Schedule to Work Breakdown Structure" 56
52 AFMC, 1998, p. 39-6d 53 Fleming, Koppelman, 1996, p. 67. 54 Fleming, Koppelman, 1996, p. 67. 55DSMC,2000,p.3-13 56 Dua, 1997, p. 6
15
3.2.3 Estimate and Budget Project Resources
After planning and scheduling the activities necessary to complete the project, the next step
is to establish a budget the work. In order to develop a budget, one must forecast what
resources the project will require, the required quantities, when they will be needed, and how
much they will cost. Depending on the resources to be tracked, the budget can be expressed in
any monetary, labor, or other measurable unit. Planning and budgeting can be done at both the
summary and at the detail level. Therefore, two different strategies exist for generating a
budget: top-down and bottoms-up methods.
In the top-down method, budgets are initially set at a higher level and then broken down
into budget estimates for specific tasks and work packages. This process continues until the
project is broken down to the lowest level work package.58 However, according to Fleming
and Koppelman, "...the project baseline needs to be created from detailed bottoms-up
planning."59
In the bottoms-up method, the schedules and budgets for individual WBS elements are
constructed thereby creating a more accurate budget when compared to the top-down method.
These resulting budgets are collected, or "rolled up", to establish the final budget for the
project.60
3.2.4 Establish Baseline
One of the key factors in utilizing Earned Value Management is the creation of a
performance baseline. When a project is in process, costs are incurred due to the consumption
of resources related to the completion of work. To determine how well the project is doing, a
comparison against the original plan is required. Having planned the work packages with
respect to time and budget, a baseline can be created as the basis for this comparison. As
previously identified, this time phased budget plan is known as the performance measurement
baseline.
57 Meredith, 1995, p.289 58 Meredith, 1995, p. 292 59 Fleming, Koppelman, 1996, p.75 60 Meredith, 1995, p. 292
16
3.3 Revisions
Although the scope of work and the work breakdown structure for a project may be well
defined, it is rare that the baseline at the end of the project will be the same as at the beginning.
There are many factors encountered throughout construction of a project that can affect this
baseline. A typical cause of a necessity to revise the baseline is a change to the scope of work.
It is essential that changes to the baseline be documented and controlled in order to distinguish
between the original and new work if the need should arise.61
3.4 Accounting
The incorporation of actual cost data into an Earned Value Management System is referred
to as accounting. The primary concern with the accounting aspect of the earned value concept
is the accumulation and reporting of costs accurately. 62 Costs on a project can be incurred
through labor, material, equipment, subcontracts and other direct or indirect costs. In
preparation for analysis, costs must be correctly applied to the proper work packages to
facilitate summarization by both the WBS and OBS.
3.5 Analysis
The last phase of Earned Value Management is to monitor performance against the
baseline for the duration of the project. To monitor this progress, variances and indices should
be calculated and analyzed by management. Periodically, a forecast of the final costs, the
efficiency required to achieve these costs, and an estimated completion date should be made
and compared with project goals. By interpreting the results of this analysis and the forecasts,
management action may be necessary in order to keep the project's final cost and schedule
within desired goals.
As defined earlier, the key elements of earned value, namely BCWS, BCWP, and ACWP,
are determined for each task and a comparison of these elements provides a measure of
schedule and cost performance. These measurements must be treated with caution, however, as
61 Fleming, Koppelman, 1996, p. 109 62DSMC,2001,p.55
17
they are only indicators of the efficiency or performance of a project. Therefore, they should
only be used as one of the many factors on which project managers base their decisions, and
then only after interpreting all pertinent information.
When analyzed properly, performance measures indicate where shortfalls are occurring
and where extra resources, management action, or other support is required in order to
overcome the problem. In addition, they can also simultaneously foreshadow what may happen
to a project if such remedial actions are not taken.64
In the following subsections, the various methods for calculating earned value, variances,
performance indices, and overall status indicators will be provided. The discussion on analysis
will conclude by detailing the forecasting tools available from earned value data.
3.5.1 Measuring Earned Value
Similar to the budget, earned value can be measured in dollars, man-hours, or any other
measurable unit. There are several methods for measuring earned value dependent on the type
of work being performed. The type of effort involved with the work activity separates the
different methods into three categories, which will be identified. The three categories are:65
• Discrete Effort
• Apportioned Effort
• Level of Effort
3.5.1.1 Discrete Effort
Discrete effort project tasks have a definable scope and objectives that can be scheduled,
and have progress measured against.66 The discrete effort methods of measuring earned value
will now be described in more detail.
Fixed Ratio Formula Method - Perhaps the easiest method to understand and to implement
is a fixed ratio that adds to 100 percent. Common uses of this method are with a 0/100, 25/75,
63 DSMC, 2001, p. 55 64 Fleming, Koppelman, 1996 p. 111 - 119. 65Harroff,2001. 66Harroff,2001.
18
or 50/50 ratio. These methods allow a given percentage complete when an activity starts and
the remainder when its finish date is reported. For example, with the 25/75 method, 25% is
reported complete at the start, and 100% is reported at the finish. However, the accuracy of this
method as a progress measure clearly declines for longer work packages, since there is a
measure of progress only in the period the work starts and the period the work ends. Interim
periods will show no progress; hence, this method will not be consistent with the BCWS for
longer durations.
Weighted Milestone Method - For durations greater than two periods, the use of a
weighted milestone method for planning resources and measuring progress works well. This
method has the advantage of showing physical accomplishment of milestones leading to
completion of the work package. Each milestone is assigned a specific budgeted value, which
will be earned upon physical completion of the task.68
While this is one of the preferred methods for calculating earned value, it requires
significant upfront planning in order to establish the necessary milestones for each task.
Therefore, care should be taken when using this method to ensure that the milestones are not
artificial, but rather a natural subdivision of the work.
Percent Complete Method - If a task is greater than two months in duration and discrete
interim milestones cannot be identified, another technique that can be selected is the percent
complete method. This method is most desirable when the percent complete can be calculated
based on measurable parameters such as length, square feet, or cubic yards of work
accomplished. When such parameters are not available, this method can be questionable since
estimates are frequently made on a subjective basis.69
Percent Complete with Milestone Gates Method - An alternative to the percent complete
method is to introduce milestone "gates" that allow subjective estimates up to a point at which
a designated performance mark must be passed. This method provides a balance between the
67 Fleming, Koppelman, 1996, p 89 68DSMC,2001,p.ll4 69DSMC,2001,p. 115
19
initial planning required with the weighted milestones and the possible subjectivity with the 7ft
percent complete method.
Earned Standards - The earned standards method is useful for production-type work and is
perhaps the most sophisticated method of computing earned value. Standards of performance
based on historical cost data, time and motion studies, etc. are used to measure the earned
value. However, no standard for computing the earned value with this method works best in
every situation, and often several are utilized. A recommended approach is to allow several
standards to be used initially with a management consensus required to determine which one is 71 eventually selected.
Equivalent Unit Method - This method is based on measuring the number of units or items
that have been completed and comparing the result to the total number of units or items that
have to be completed. This approach is best suited for manufacturing or activities with
repetitive elements.72
3.5.1.2 Apportioned Effort
The second of the three categories with which to measure earned value is apportioned
effort. Apportioned effort is useful for tasks whose planning and performance has a direct
relationship to another task. The earned value for the apportioned task is driven by the status on
the linked task. Quality control and inspections are examples of apportioned effort.73
3.5.1.3 Level of Effort
The final category is level of effort. Level of effort is work scope of a general or
supportive nature for which performance cannot be measured or is impractical to measure.
Because these tasks are more time driven than task driven, the earned value always equals the
planned value, regardless of the work done.74 Therefore, level of effort scopes of work do not
70 Fleming, Koppelman, 1996, p 91 71 Fleming, Koppelman, 1996, p 93 72 Fleming, Koppelman, 1996, p 92 73 Harroff, 2001 74 Harroff, 2001
20
have a schedule variance and produce very misleading cost variances. For this reason, this
method is generally not recommended to track earned value.75
3.5.2 Variances
It is safe to say that no plan, schedule or estimate is exact and thus variances are certain to
occur.76 A variance is the difference between the planned, scheduled, or actual costs.77 "Typical
causes of variances include poor initial planning or budgeting, changes to the project's scope,
changes in technology related to the project, changes to the delivery schedule, changes to labor
contracts, changes to material costs, inflation, and measurement error."78 The presence of
significant variance notifies management that something needs to be examined and proper
corrective action taken. With earned value analysis, three main variances can be determined.
The first two, Schedule Variance and Cost Variance, will be defined in this section. The last,
the Variance at Completion, will be discussed after introduction of additional terminology.
3.5.2.1 Schedule Variance (SV)
Schedule variance provides a representation of schedule status, indicating whether
budgeted work is being accomplished as planned.79 It is the difference between the earned
value and the planned value as indicated in Equation 3.1:
SV = Earned Value - Planned Value = BCWP - BCWS
Equation 3.1 - Schedule Variance
The schedule variance may be calculated on current or cumulative data, with the
cumulative schedule variance being used most often for analysis purposes. A positive variance
indicates favorable schedule performance since the amount of work performed is greater than
what was scheduled. Conversely, a negative variance means less work was performed than
planned and the project is behind schedule.80 It is important to note, however, that at contract
75 Fleming, Koppelman, 1996, p. 95 76 Valkenhoff, 1981,p.223 77 Microsoft, p. 307 78 Christensen, 1993, p. 17 79 AFMC, 1998, p. 39-27.2 80DSMC,20001,p. 136
21
completion the schedule variance is always zero because all scheduled work has been
performed.
3.5.2.2 Schedule Variance Percent (SV%)
Although, it does not introduce new data, the schedule variance percent is significant in
that it normalizes the SV by comparing it to the total budget. Equation 3.2 summarizes the
method for calculating the SV%. A positive SV% indicates that the project or activity may be
ahead of schedule and a negative SV% means the project may be behind schedule. As
discussed for SV, the SV% is most meaningful when calculated using cumulative data and 01
when the analysis includes a detailed review of all performance measurements.
SV%: SV SV
Planned Value BCWS
Equation 3.2 - Schedule Variance Percent
3.5.2.3 Cost Variance (CV)
Cost Variance measures the difference between the cost that was planned for a given task
and the cost that was actually incurred in performing the task.82 As such, it is the difference
between the earned value and the actual costs as shown in Equation 3.3:
CV = Earned Value - Actual Costs = BCWP - ACWP
Equation 3.3 - Cost Variance
The cost variance may be calculated on either cumulative or current data. As with the
schedule variance, the cumulative cost variance is most often used for analysis purposes. A
positive cost variance indicates that the contractor is accomplishing work for less than was
budgeted. On the other hand, a negative CV means more money was spent for the work
accomplished than was originally planned.83 An example calculation for both the SV and the
CV is presented in Figure 3.4.
81 AFMC, 1998. p. 39-27.4b 82 DOE, 2000, p. 10-6 83 AFMC, 1998. p. 39-27.1
22
Earned Value Project Management
Planned Value = S300K ~1 Variance from the Planned V Schedule = (-$100K)
Earned Value = $200K J "1 > The True Cost
Actual Costs = $300K J Variance = (-$100K)
Figure 3.4 - Schedule and Cost Variance Example 84
3.5.2.4 Cost Variance Percent (CV%)
This measure expresses the cost variance as a percentage relative to the amount of work
accomplished, as shown in Equation 3.4. A negative CV% means the project is over cost by the
calculated percentage. The CV% value should be compared with the CPI for the same period to or
verify a cost overrun or underrun situation. For example, a CPI of .8 indicates poor cost
performance; therefore, a negative CV% would be expected.
CV%=- cv cv
Earned Value BCWP
Equation 3.4 - Cost Variance Percent
By analyzing the cause of a variance, the project manger can identify significant
differences between the planned and actual cost performance. Generally, a negative variance
can be viewed as bad and a positive variance as good, although this may not always be the case.
For example, a positive variance may be caused from the contractor's front-loading of his
schedule of values, thereby robbing resources intended for later tasks. Another indicator of
problems during variance analysis is if no variances are reported over several periods. This can
indicate a lack of tracking on the contractor's part since it is difficult to forecast work with such
accuracy.
During analysis, if the cumulative CV and SV both reflect negative trends, the task being
performed may be very complex, the contractor may have underestimated the scope of the task,
Fleming, Koppelman, 1996, p. 20 AFMC, 1998. p. 39-27.4a
23
or the method of calculating earned value may not fully take credit for work as it is performed.
Positive values for both variances may be due to good contractor performance, a simple task, or 86 an overly generous contractor estimate for the effort. A graphical representation of both the
Schedule Variance and the Cost Variance is provided in Figure 3.5:
Figure 3.5 - Graphical View of Schedule and Cost Variances
86 AFMC, 1998. p. 39-27.4 87 DOE, 2000, p. A-l
24
3.5.3 Performance Indices
"Performance indices show the percentage of variation, between planned and actual DO
performance, for the current period, cumulative to date, and at the completion of a task." The
Schedule Performance Index and the Cost Performance Index are calculated to provide an
efficiency factor for the work accomplished in either the current period or a cumulative
timeframe. The analysis techniques that produce these two performance indices will now be
described.
3.5.3.1 Schedule Performance Index (SPI)
The SPI indicates the ability of the contractor to control the project schedule and compares
the budget for those tasks scheduled to be accomplished as of the status date with the budget
for the work that was actually accomplished as of that date.89 It is calculated as the ratio of
earned value to planned value as shown in Equation 3.5:
SPI = Earned Value BCWP
Planned Value BCWS
Equation 3.5 - Schedule Performance Index
An SPI of 1.0 indicates that the project is on schedule and performing at 100% efficiency.
An index greater than 1.0 shows an ahead of schedule situation, while one below 1.0 reflects a
behind schedule condition. Figure 3.6 below provides an example.
Earned Value—A Simple Concept What you did (physical work performed = EV)
versus The work you had planned/scheduled to do
32%
100% work done (EV)
100% work planned
earned value planned work scheduled work efficiency factor (SPI) = .75
Figure 3.6 - Schedule Performance Index 90
88 Harroff, 2001 89 Fleming, Koppelman, 1996, p.113 90 Fleming, Koppelman, 1994, p. 22
25
3.5.3.2 Cost Performance Index (CPI)
The CPI indicates the ability of the contractor to control cost and compares the budget for
those tasks that have been accomplished with the actual cost of accomplishing the tasks.91 It is
calculated as the ratio of earned value to actual costs as shown in Equation 3.6:
CPI = Earned Value BCWP
Actual Costs ACWP
Equation 3.6 - Cost Performance Index
The CPI measures the cost efficiency with which work has been accomplished. A CPI of
1.0 indicates that for every actual dollar spent, a dollar's worth of work was accomplished. An
index above 1.0 indicates a cost underrun or higher efficiency, while an index below 1.0
reflects performance below what was expected. "A CPI less than 1.0 is rarely improved upon,
and usually proves to be unrecoverable."92 An example calculation follows in Figure 3.7.
Earned Value—A Simple Concept What you got (physical work performed « EV)
versus The dollars spent (actual costs)
29%
100% work done (EV)
100% funds spent
earned value actual costs " cost eff|C'ency factor (CPI) - .83
Figure 3.7 Cost Performance Index 93
91 AFMC, 1998. p. 39-27.7
93 ' Fleming, Koppelman, 1996, p.l 14 Fleming, Koppelman, 1994, p. 22
26
With the major components of earned value performance measures defined, one can
examine the various scenarios that exist. With an unchanging baseline, six scenarios exist for a
given project as illustrated in Figure 3.8.94 By referencing this figure, a quick determination
can be made as to the budget and schedule status.
CPI<1 CV <0
fc overrunning —I cost
CPI>1 CV >D
fc, within -1 budge'
SPU1 sv <0
w behind —I schedule
SPI < 1 SV <0
^ behind J schedule
CASE I CASE II
CPI>1 cv >0
^ within —> budget
CPU1 cv <0
^ overrunning J r cost
SPI>1 sv >0
^ ahead a', —I schedule
SPI < 1 sv <0
^ behind J w~ scheduie
CASE 111 CASE IV
CPI<1 cv <0
^ overrunning -J cost
CPI>1 cv >0
^ within —1 budget
SPI>1 sv >0
^ ahead oS -J scheduie
SPI > 1 sv >0
^ ahead ol J schedule
CASE V CASE VI
Figure 3.8 - Six Scenarios of Earned Value Analysis
94 Singh, 1991, p. 42
27
3.5.4 Overall Project Status Indicators
In addition to the SPI and the CPI, three other calculations that can be made in order to
determine efficiencies on a project are percent complete, planned percent complete, and percent
spent.
3.5.4.1 Percent Complete
One of the more recognized performance calculations in the construction industry is
percent complete. It is the relationship between the budgeted value for what has been
completed to date and the total budget,95 as shown in Equation 3.7.
Percent Complete = (BCWP / BAC) x 100
Equation 3.7 - Percent Complete
3.5.4.2 Planned Percent Complete
In conjunction with percent complete, the planned percent complete provides a comparison
for what was scheduled to date.96 Equation 3.8 shows the relationship:
Planned % Complete = (BCWS / BAC) x 100
Equation 3.8 - Planned Percent Complete
3.5.4.3 Percent Spent
A comparison of the percent compete with the percent spent indicates performance spend
efficiency. The percent spent indicator is calculated as the ratio of the actual costs to the budget
at completion,97 as shown in Equation 3.9:
Percent Spent = (ACWP / BAC) x 100
Equation 3.9 - Percent Spent
95 DSMC, 2001, p. 139 96DSMC,2001,p. 139 97 DSMC, 2001, p. 138
28
3.5.5 Forecasting
In addition to analyzing variances and performance indices for trends to determine
problems in the execution of a project, earned value data can also be used as a forecasting tool.
During execution of a project, forecasting has two objectives: to provide a forecast for the
outcome of the project based on current status and trends; and second, to highlight trends or
potential budget deviations that require management control.98 When forecasting, one has to
take into account the time phase of the project. At the beginning of a project, uncertainty about
the outcome is higher than at the end of the project. This uncertainty results in a range of
possible final projections. With earned value data, however, early predictions have proven to be
reliable. As described by Fleming and Koppelman:
"Perhaps the single most compelling reason to employ earned value is that it enables the project manager to be able to 'statistically' forecast the (probable) final cost, and schedule results on the project...from as early as the 15 percent completion point. With earned value, the project does not have to wait until it is 90 percent spent to know that it has a problem. The 90 percent point is too late to alter the project's final course. Earned value provides an 'early warning' message to management in time to take corrective action, in time to influence the final results with aggressive action."99
"Successful forecasting is based on a foundation of a good baseline plan, tracking
performance against that plan, and the commitment of upper management to use and act on the
performance data."100 From earned value data and the performance measurements identified, an
Estimate at Completion, To-Complete Performance Index, and the Estimated Completion Date
can be forecasted.
3.5.5.1 Estimate at Completion
The Estimate at Completion (EAC) is an important tool used in forecasting because it
gives an indication as to where the project cost is heading. Christensen presents many methods
to forecast the EAC, however they all take the basic form shown in Equation 3.10:
98McMullan, 1996, p. 20.1 99 Fleming, Koppelman, 1996, p. 127 100 Smith, 1999, p.9
29
__ (BAC-BCWPCUM) EAC=ACWPCUM +
Pf
Equation 3.10 - Estimate at Completion
In the above equation, since the budget for the remaining work is frequently understated, a
performance factor is used to adjust it upward. There are four types of performance factors (Pf)
that can be used, all of which assume that past efficiency will continue in the future.101 The four
factors are:
1. Schedule Performance Index
2. Cost Performance Index
3. Composite Index
4. Schedule Cost Index (SCI)
Since the SPI and CPI have already been discussed, the Composite Index and the Schedule
Cost Index will be reviewed. The Composite Index is the weighted sum of the SPI and CPI,
where the weights add to one. The value assigned to these weights should be based on
experience and historical data from the project. The Schedule Cost Index is the product of the
SPI and CPI. Equations 3.11 and 3.12 depict these two performance factors respectively.102
Composite Index = (Wi x SPI) + (W2 x CPI), where Wj + W2 = 1
Equation 3.11 - Composite Index
Schedule Cost Index (SCI) = SPI x CPI
Equation 3.12 - Schedule Cost Index
In deciding which factor to use, the CPI based performance factor has proven to be the
most useful since the quantity of known data increases as the quantity of work decreases.103
However, through the use of multiple factors, a range of EACs can be produced thereby
increasing the likelihood that the final EAC will be included. The low end of this predicted
range is usually produced using a special case for the performance factor. With a Pf of 1.0, the
assumption is that all future work will be done as planned and the current cost variance will
101 Christensen, 1993, p. 18 102 Christensen, 1999, p. 290 103 Christensen, 1993, p. 21
30
remain constant.104 The high end of the range is generally calculated using the SCI performance
factor.105
3.5.5.2 Variance at Completion
With EAC defined, the last variance can now be calculated. The Variance at Completion
(VAC) is determined by comparing the budget at completion with the latest estimate at
completion as expressed in Equation 3.13:
VAC = BAC-EAC
Equation 3.13 - Variance at Completion
Again, another way at looking at this variance is to express it relative to the original
estimate for the total cost of the project. Equation 3.14 shows the formula for calculating the
Variance at Completion Percent.
VAC% = VAC / BAC
Equation 3.14 -Variance at Completion Percent
With both the VAC and the VAC%, a positive value indicates that, if current performance
continues, the project will be completed below cost. If the result is a negative value, then an
overrun situation at project completion can be expected.106
Regardless of the method used in calculating the EAC, the value should be carefully
reviewed with consideration given to the following:
• Past performance
• Costs incurred to date
• Assessment of tasks remaining
• Future economic conditions
• Cost and Schedule Variance
• Expected future efficiency
• To-Complete Performance Index
104 Fleming, Koppelman, 1996, p. 133 105 Fleming, Koppelman, 1999, p. 290 106 AFMC, 1998. p. 39-27.3
31
The last consideration, the To-Complete Performance Index, is a tool that can be utilized to
test the reasonableness of the forecasted EAC.
3.5.5.3 To-Complete Performance Index
Whereas the SPI and CPI indicate past performance efficiency, the To-Complete
Performance Index (TCPI) indicates the cost efficiency factor that must be attained if the
remaining work is to be completed within a financial goal. This financial goal can be the total
budget, the forecasted EAC, the contract price, or any value less the actual costs that have been
incurred to date.107 Therefore, the TCPI represents the relationship between the work
remaining and the funds remaining to complete the project. The TCPI formula with the EAC as
the financial goal is shown in Equation 3.15:
_ Work Remaining _ BAC-BWCPCUM
Funds Remaining EAC - ACWPCUM
Equation 3.15 - To-Complete Performance Index
A TCPI greater than 1.0 indicates that future efficiency will need to be greater than
planned, while a figure less than 1.0 indicates future efficiency can be less than planned to
achieve the financial goal. Christensen notes that for a project more than 20% complete, if the
difference between the TCPIEAC and the CPIcUm is more than ±10%, the EAC has probably been
understated.108
3.5.5.4 Estimated Completion Date
A forecast of the Estimated Completion Date can be determined by graphically examining
the earned value and planned costs. As shown in Figure 3.9, by measuring the time distance
from the point on the earned value curve that corresponds with the status date, horizontally to
the planned value curve, the schedule variance can be expressed in units of time. By applying
this variance to critical path information, a prediction of the potential completion date for the
project can be made.109
107 DSMC, 2000, p. 140 108 Christensen, 1993, p. 21 109 Fleming, Koppelman, 1996, p. 139
32
When making this prediction, it is essential to consider the total float of the project. By
accomplishing non-critical activities before their planned start date, it is possible to earn more
than what was scheduled. The result of this will be a distortion of the schedule variance and of
the project's progress. Therefore, use of the schedule variance as a time predictor should be
coordinated with the critical path of the project.
Budget Status Date
100% ! ^ Budget • /
s s s 75%
\ y ! / ; y
50% Spend Plan Jc "Wanned Value = 50% ~\ EV Schedule f--Ä Earned Value = 40 % J Variance
/ A'' 1 S .' 25%
y-' s- ' ' Year! | Year2 |f, "j |
^ . . * EV Schedule Status: 1
Figure 3.9 - Forecast of Scheduled Completion Date
33
3.6 Summary
In this chapter, the general steps required to implement an Earned Value Management
System were introduced and discussed. First, the necessity to properly organize the project
scope with a Work Breakdown Structure was pointed out. Next, the need to assign
responsibility and the ways in which the Organization Breakdown Structure accomplished this
were reviewed. The planning, scheduling, and allocation of a budget to work packages and
their role in forming the Performance Measurement Baseline was presented. This chapter then
proceeded to describe the many methods that exist in calculating earned value for work
activities in progress. Finally, various performance measures and forecasting methods that can
be utilized when performing earned value analysis were detailed. Figure 3.11 below
summarizes the earned value parameters reviewed in this paper.
Estimate to Complete
(ETC)
Projected ACWP at Completion (EAC)
Ö-*.
Projected Delay in Project Completion
Projected Cost Overrun at Completion (VAC)
Time- -*• Time Now Planned
Completion Projected
Completion
Figure 3.10 - Earned Value Parameters no
1 DOE, 2000, p. A-2
34
4. Naval Construction Force Project Management
Before applying the earned value concept to Naval Construction Force (NCF) project
management, it is necessary to first review the planning and execution phases utilized
throughout the NCF in construction operations.
4.1 NCF Overview
The Naval Construction Force refers to a group of naval organizations, which possess the
capability to construct, maintain, and operate, both in wartime and in peacetime a myriad of
facilities in support of the U.S. Navy and the U.S. Marine Corps. The mission of the NCF has
been defined as:
With Compassion for others - we build, we fight - for peace with freedom. We provide the Navy, Marine Corps, Unified CINCS, and other customers with rapid contingency response, quality construction, disaster recovery support, and humanitarian assistance. u
Table 4.1 provides a listing of the type and the number of units that make up the NCF.
Table 4.1 - Units of the NCF 112
Type of Seabee Organization Total Number
Total Active
Total Reserve
Naval Construction Brigade 2 2 0
Naval Construction Regiment (Homeport) 2 2 Ö
Naval Construction Regiment (Line) & 2 4
Naval Mobile Construction Battalion 20 8 12
Naval Construction Force Support Unit 2 0 2
Underwater Construction Team 2 2 0
Amphibious Construction Battalion 2 2 0
Construction BattaMon Maintenance Unit 2 0 2
Construction BattaHon Unit 19 19 0
All of these NCF units are comprised of officers of the Civil Engineer Corp (CEC) and
enlisted personnel, commonly referred to as Seabees, trained in construction skills.113 While
construction planning and execution is a common practice throughout each of the units, the
in 112
Department of the Navy (DON) OPNAV 5450.46K, 1999, p. 5 DON, 1997.
35
application of the earned value concept for this research will be centered on the Naval Mobile
Construction Battalion (NMCB).
4.1.1 Naval Mobile Construction Battalions
Naval Mobile Construction Battalions (NMCBs) provide highly skilled construction
support to Navy, Marine Corps, and other forces in military operations. This mission is met
through the construction and maintenance of base facilities, the repair of battle-damaged
facilities, and by conducting limited defensive operations as required. In addition to standard
wood, steel, masonry and concrete construction, NMCBs also perform specialized construction
such as water well drilling and rapid runway repair. In times of emergency or disaster, NMCBs
can also conduct disaster control and recovery operations.114
In peacetime, NMCBs complete a rotation cycle every 14 months. Seven months are spent
at a homeport location and the other seven months on deployment. Currently, the eight active
duty NMCBs are split between the homeport locations of Port Hueneme, CA and Gulfport, MS
and four overseas deployment sites: two in the Atlantic at Roosevelt Roads, Puerto Rico and
Rota, Spain, and two in the Pacific at Guam and Okinawa. Various evolutions during this cycle
prepare, evaluate and maintain the Battalion's readiness for not only responsive military
construction support, but also defensive combat and disaster recover operations.115
4.2 Project Planning
Good construction planning and estimating procedures are essential to the ability of a
Battalion to provide quality construction. Construction management in an NMCB is comprised
of three levels as shown in Figure 4.1.
113 Naval Facilities Engineering Command (NAVFAC) P-315. 114 DON OPNAV 5450.46K, 1999, p. 5 115 DON, 1995, p II-3
36
A16 Figure 4.1 - Seabee Multi-Level Construction Management
The above diagram represents that planning is accomplished as a top-down, bottoms-up
cycle. Once initiated at a generic project level, planning proceeds to the detailed level before
eventually rolling back up into a finalized project package. Further detail as to the amount of
information entailed at each level will be covered under the scheduling section of this chapter.
4.2.1 Fundamentals of Seabee Construction Management
Construction management in the Seabees is based on Critical Path Method (CPM)
scheduling and is nearly identical to construction management techniques used in the private
construction industry. One of the biggest advantages to using CPM analysis is the outstanding
training value it affords the project crewleader. As defined by the Operations Officer
Handbook, NCF project management fundamentals can be categorized into the following steps:
Step 1. Develop construction activities - After careful review of the plans and specifications, the first step is to break the job down into discreet activities. Construction activities are generally less than 15 days in duration and require the same resources throughout. As a rule, an activity should be created for any function that consumes or uses direct labor resources.
• Step 2. Estimate construction activity requirements - For each construction activity, resource requirements need to be identified and evaluated. To track these resources, a Construction Activity Summary (CAS) sheet is used to list all
116 Civil Engineer Corp Officer School (CECOS), 1997, p. 1-1
37
of the material, tool, equipment, and manpower requirements along with safety, quality control, and environmental concerns.
Step 3. Development of the logic network - The logic network is the basic management tool for control, monitoring, and distribution of all resources that are directly related to time. In the planning stage, this logic network is a pure dependency diagram in that all activities are listed in the order they must be accomplished, without regard to particular construction preference.
Step 4. Schedule construction activities - Upon finalizing the logic network, the next step is to determine estimated start and finish dates for each activity based on the sequence and durations of the construction tasks. A critical path is identified to help focus management attention on those activities that cannot be delayed without impacting the project completion date.
Step 5. Resource Management - Resource tracking and control are crucial elements in the successful execution of a project. The project crewleader must ensure that all necessary resources are available when required. Additionally, once on site, resources must be controlled to ensure their productive employment. Proper attention to resource allocation and leveling, the matching of construction activities scheduled to the resources available, will assist in meeting this goal.117
4.2.2 Detailed Planning
Having outlined the general fundamentals used by the NCF in planning, a presentation of
the detailed planning sequence will further explain the generation of a finalized project
strategy. Table 4.2 outlines the project planning milestones from the Seabee Crewleader's
Handbook that form the backbone of NCF project planning. Figure 4.2 presents these steps in
an easy to follow flowchart.
117 NAVFAC 5200.2B, p. II-6
38
Table 4.2 - NMCB Project Planning Milestones
1. Designate Crewleader and Planning Team 13. Complete Construction Activity Summary Sheets 2. Pre-Planning Conference 14. Develop Level III Network 3. Review Plans and Specifications 15. Input Network into Computer 4. Identify Long Lead Materials 16. Resource Level Project 5. Identify Required Skills and Training 17. Develop Level III Bar Chart 6. Complete Project Scope Sheet 18. Complete Master Activity Summary Sheets 7. Complete Master Activity Listing 19. Develop Level II Bar Chart 8. Develop Rough Level II Bar Chart 20. Consolidate Tool Requirements 9. Develop Level II Logic Network 21. Consolidate Equipment Requirements 10. Generate Construction Activity Listing 22. Consolidate Safety Plan 11. Conduct Material Take-offs 23. Consolidate Quality Control Plan 12. Develop Bill of Materials 24. Prepare Project Briefing for Chain of Command
ASSIGN P&E
TEAMS
GENERATE CONSTRUCTION
ACTIVITIES
MATERIAL TAKE-OFF
+ MAN-DAY DURATION ESTIMATES
K TRACK UNTIL \ DEVELOPMENT I
PRECEDENCE DIAGRAM
RESOURCE LEVELING
REVIEW BY OPS
' SAFETY PLAN
SAFETY CHIEF
REVIEW
Figure 4.2 - Project Planning Flowchart 118
' DON, 1995, p. 2-5
39
The results of each of these steps are maintained throughout the life of the project in the
project package, a collection of all the information required to plan, schedule, monitor, and
execute a project.119 Beyond identifying in detail the steps involved in planning an NCF
project, perhaps the most important outcomes of this process are the generation of the
Construction Activity Summary (CAS) sheets, the project schedule, and the allocation of
resources.
4.2.3 Construction Activity Summary Sheets
As previously identified, a CAS sheets is used to list all of the material, tool, equipment,
and manpower requirements along with safety, quality control, and environmental concerns.
Also included are the scheduled start and finish dates for each activity. Just as work packages
are the lowest level element of the WBS, a CAS sheet summarizes the lowest level element in
the NCF project planning. Through the proper use of the CAS sheet, the project crewleader can
greatly reduce the chance of the project being impacted due to a lack of resources. The CAS
sheets are designed to be standalone in that all pertinent information, notes, and calculations
done during the planning and estimating stages are documented. Therefore, practically all
construction effort in the Seabees is driven from the information contained on the completed
CAS sheets.120
4.2.4 Construction Scheduling
Crucial to a workable project schedule is the proper, logical sequence of activities and
good realistic durations.121 Once outlined, the project schedule is displayed and tracked
utilizing a bar chart. Although precedence networks are the primary scheduling tool used in the
NCF, the ease of use and quick presentation of project status are two benefits gained by
utilizing the bar chart.122
119CECOS, 1997, p. 1-5 120CECOS, 1997, p. 2-12 121 PMI, 1996, p. 52 122 Ahuja, 1994, p. 46
40
As discussed, Seabee project planning occurs at three distinct levels that are most readily
apparent through the project schedules.
4.2.4.1 Level III schedule
The most in depth of the three schedules is the Level III, as it represents the detailed
execution plan for a particular construction project. It designates construction activities,
identifies required resources, shows relationships and dependencies amongst activities, and
identifies the critical path. Updated project status is maintained continuously on the jobsite as
reflected on the Level III bar chart.123
4.2.4.2 Level II schedule
At any time during a deployment, a NMCB may be working on 30 or more individual
projects. A condensed project schedule, the Level II, that only lists the master activities, aids in
the management of all NMCB network schedules. Additionally, the Level II contains the plot
of all planned work thereby forming the project baseline against which all future progress is
measured. The Level II schedule provides a broader view for determining if a project is on
schedule, and indicates what particular areas are going well or need greater emphasis.124
4.2.4.3 Level I schedule
For top-level management, the Level I schedule is a consolidated graphic representation of
all projects tasked to a NMCB, either planned or in progress at a given site. While this
integrated project schedule is a rather broad-brush tool, it does indicate particular problems on
an individual project or at a certain detachment site that might require reallocation of resources
from one project to another.125
123 DON 5200.2B, 1999, II-5 124 DON 5200.2B, 1999, II-5 125 DON 5200.2B, 1999, II-5
41
4.2.5 Budgeting of Resources
Vice tracking all project costs as a dollar figure, NCF projects utilize labor mandays as the
primary unit of measure. Performance measurements and analysis of project status are made
through examination of earned mandays, expended mandays, and estimated mandays. A brief
explanation of how mandays and activity durations are calculated will be provided to aid in the
understanding of Seabee project tracking.
The primary reference for Seabee manday estimates is a manual called the Seabee
Planner's and Estimator's Handbook. This manual lists how many man-hours it takes to
complete one unit of work for various tasks and is based on historical data from past Seabee
projects. The total estimated mandays (MDs) for an activity are calculated by using Equation
4.1.
MDs = QTY of WORK -=- UNIT SIZE x MHRS PER UNIT -=- 8 x DF
Equation 4.1 - Manday Calculation
In the equation, a Delay Factor (DF) is utilized to adjust the values from the Seabee
Planner's And Estimator's Handbook for particular jobs site conditions and is calculated using
an average of eight Production Efficiency Factors (PEF)126, as shown in Equation 4.2.
DF = 67 / PEFAVG
Equation 4.2 - Seabee Delay Factor
The intent of a Production Efficiency Factor is to adjust for factors that will make a project
crew more or less productive than the average worker identified in the Seabee Planner's And
Estimator's Handbook. Table 4.3 on the following provides a guide for determining the
subjective values for the eight Production Efficiency Factors.
126 CECOS, 1997, p. 2-5
42
Table 4.3 - Production Efficiency Factor Guide
LOW PRODUCTION AVG PRODUCTION HIGH PRODUCTION 25 35 45 55 65 75 85 95
1. WORKLOAD CONSTRUCTION REQ'T HIGH, MISC. OVERHEAD HIGH
CONSTRUCTION REQ'T AVG, MISC. OVERHEAD AVG
CONSTRUCTION REQ'T LOW, MISC. OVERHEAD LOW
2. SITE AREA CRAMPED WORK AREA, POOR LAYDOWN/ACCESS
WORK AREA LIMITED, AVG LAYDOWN/ACCESS
LARGE WORK AREA, GOOD LAYDOWN/ACCESS
3. LABOR POORLY TRAINED/MOTIVATED CREW
ADEQUATELY TRAINED/MOTIVATED CREW
HIGHLY TRAINED/MOTIVATED CREW
4. SUPERVISION POORLY TRAINED/MOTIVATED OR INEXPERIENCED
ADEQUATELY TRAINED/MOTIVATED EXPERIENCED
HIGHLY TRAINED, MOTIVATED, AND EXPERIENCED
5. JOB CONDITION HIGH-QUALITY WORK REQ'D, SHORT FUSE
AVG QUALITY WORK REQ'D, ADEQUATE TIME
ROUGH/UNFINISHED WORK REQ'D, WELL PLANNED
6 WEATHER ABNORMAL HEAT, RAIN, OR COLD
MODERATE RAIN, HEAT, OR COLD
FAVORABLE RAIN, HEAT, OR COLD
7. EQUIPMENT POORCOND..MAINT., REPAIR, OR APPLICATION
FAIRCOND..MAINT., REPAIR, OR APPLICATION
GOODCOND.,MAINT., REPAIR, OR APPLICATION
8. TACTICAL/ LOGISTICAL
SLOW SUPPLY, FREQUENT TACTICAL DELAYS
NORMAL SUPPLY, FEW TACTICAL DELAYS
GOODSUPPLY.NO TACTICAL DELAYS
From the estimate for the mandays to complete the desired task, the budget is allocated for
each construction activity via the CAS sheet. By rolling the construction activities into a
project schedule, a performance baseline is produced against which future progress can be
measured.
4.3 Project Monitoring and Reporting
Once the project baseline is in place and execution of the construction project begins, the
continued success of the project depends on efficient monitoring and regular updating of the
project schedule. To accommodate this, monitoring and analysis of project progress is
completed bi-weekly during an NMCB deployment. This section will identify the Situation
Report, and the methods utilized in analyzing project performance.
4.3.1 Situation Reports
A Battalion submits a Situation Report (SITREP) on a monthly basis to higher
headquarters to report the progress of their construction tasking. The accuracy of this SITREP
is a reflection of how well the crewleaders have planned the projects work activities,
43
documented actual labor expenditures, and how management guided implementation of the
work plan. In determining the project status for the SITREP, the following are analyzed:
• Estimated Mandays • Mandays Remaining
• Earned Mandays • Scheduled Percent Complete
• Expended Mandays • Actual Percent Complete
4.3.2 Estimated Mandays
Estimated mandays are the planned value for work to be accomplished and are established
during the previously identified planning phases for a NMCB project. Similar to the Budgeted
Cost of Work Scheduled, they form the basis of the performance measurement baseline against
which future progress is measured. Since project planning is completed before a NMCB
deploys, knowledge of on-site conditions is limited thus affecting accuracy of initial project
estimates. For this reason, approximately 45 days into the deployment, a complete review of
performance to date will be conducted. During this 45-day review, adjustments to the project
schedule baseline are allowed in order to account for any unforeseen conditions or start up
inefficiencies. Afterwards, the project baseline is firm and the Battalion is committed to
meeting the scheduled project completion dates.
4.3.3 Earned Mandays
Earned mandays, similar to the Budgeted Cost of Work Performed, are a reflection of the
planned work that has been accomplished. For construction activities in progress, the typical
method of calculating earned mandays is by utilizing the percent complete method. When
available, the earned value of the work in progress is measured on parameters such as length,
square feet, or cubic yards of work accomplished. When these parameters are not available, the
crewleader makes a subjective estimate of the amount of work completed.
4.3.3.1 Mandays Remaining
When describing earned mandays, it is important to discuss the concept of mandays
remaining. Mandays remaining represent how much planned work remains to be done on the
project. They are calculated as the difference between the budget at completion, the original
44
estimate for the planned work, minus the mandays earned to date. This calculation is similar to
the Estimate to Completion forecast made in Earned Value Management.
4.3.4 Expended Mandays
Expended mandays represent the actual mandays required to complete an activity. As such,
they are equivalent to the Actual Cost of Work Performed in an Earned Value Management
System. In the Seabees, timecards are utilized to record mandays expended on a construction
project. Through their use, the efficiency and accountability of a project crew can be
monitored.127
It is important to note that expended mandays are not used in calculating the project
percent complete and, therefore, should not be confused with earned mandays. Expended
mandays should be used for insight as to why a project may be behind schedule or what
activities were under or overestimated. At the end of deployment, the expended mandays on
each project are collected for historical data to be used in future NCF planning.
4.3.5 Scheduled Percent Complete
The scheduled percent complete, or estimated work-in-place percent complete, is similar to
the performance measurement baseline. As such, it represents the time-phased estimate of the
earned mandays for the project. Once established, the scheduled percent complete baseline can
only be revised at the 45-day review or in the event of an approved change to the scope of
work.
4.3.6 Actual Percent Complete
The actual percent complete, or earned work-in-place (WIP) percent complete, is a
measurement of the planned work that has been accomplished to date and is compared to the
scheduled progress. In an earned value project management, this value is similar to the
Budgeted Cost of Work Performed. It is calculated by first determining the weighted percent
for each master activity, which is the ratio of the estimated mandays for that activity over the
total project mandays estimated. Next, by taking the product of this weighted percent and the
45
determined percent complete for each master activity, the actual project percent complete can
be calculated.128
4.3.7 Analysis of Project Performance
From the techniques identified in measuring project performance on a NMCB project,
analysis of the data can now occur. By comparing the scheduled percent complete and the
actual percent complete, a determination of whether the project is ahead or behind schedule can
be made. This analysis should take into account crew efficiency and their availability factor.
The availability factor accounts for crewmembers that are not available as planned for in the
scheduled baseline. Some of the major reasons for non-availability are illness, disciplinary
actions, watches/duties, medical/dental visits, and administrative matters.129 Typical availability
factors on NMCB projects vary between 0.75 and 0.85.13° The following guidance is utilized
when analyzing project performance data:
• If estimated mandays equal actual/expended mandays and the project is behind schedule, the manday estimate is inaccurate and/or the crew is inefficient.
• If estimated mandays equal actual/expended mandays and the project is ahead of schedule, the manday estimate may have been too high and/or the crew is very efficient.
• If the actual/expended mandays are more than the estimated mandays and the project is on schedule, the manday estimates may have been too low.
• If the estimated mandays are greater than actual/expended mandays, the crew is not meeting the planned availability factor, regardless of the project status. Adjustments are necessary to ensure crews get to the work site.131
CECOS, 1997, p. 8-1 127
128 CECOS, 1997, p. 8-1 129DON5200.2B,p. IV-11 130 CECOS, 1997, p. 2-10 131 DON 5200.2B, p. IV-12
46
4.4 Summary
From an overview of the management techniques used in the Naval Construction Force, an
indication of an Earned Value Management System exists. After outlining the construction
management fundamentals and delving into the detailed planning steps, similarities with the
defined earned value methodology were presented. Namely, the five categories associated with
establishing an EVMS system do exist in NCF project management.
However, after a review of the manuals dedicated to project planning in the Seabees, it is
apparent that the performance metrics that are frequently identified with earned value analysis
are not readily used. The author believes that by not exploiting all the available data and
analysis techniques afforded by the earned value methodology, valuable project management
tools are lost.
47
5. Practical Application of Earned Value Management
This chapter examines and presents the results of a practical application of Earned Value
Management to NMCB projects. Specific problem areas that may be met in the utilization of
these techniques are also identified. In reviewing this application, projects were selected from
two Battalions who had recently completed overseas deployments. Two projects from NMCB
SEVEN'S deployment to Puerto Rico; and two from NMCB FOUR'S deployment to Okinawa
were selected.
5.1 Application of Earned Value Concepts
Before applying the concepts learned from earned value management, a review of the data
gathered from each Battalion was conducted. One of the first items that observed was the
difference in the Level Es utilized for project management. Although the general format and
data were similar, there were differences in the metrics displayed beyond the standard
estimated, earned, and expended mandays and calculations for percent scheduled, percent
earned, and percent expended. The intent of this paper is not to point out one Battalion's
techniques over another, but rather to provide an example of the different management
approaches that could be unified with earned value analysis.
For example, NMCB FOUR calculates a current working estimate at completion. This is
the same as forecasting an EAC with a performance factor of 1.0. Other calculations utilized
for managing their projects were: Manday Efficiency per period, Percent Ahead/Behind per
period, and cumulative Percent Ahead/Behind. These measures are analogous to a period, vice
cumulative, Cost Performance Index, Schedule Variance Percent per period, and a cumulative
Schedule Variance Percent.
48
As a review of earned value and NCF project management terminology, Table 5.1 aligns
similar terms to aid in the understanding of the information in this chapter.
Table 5.1 - Comparison of Earned Value and NCF Terminology
EARNED VALUE NCF Planned Value
BCWS Estimated Mandays
Earned Value Earned Mandays Actual Costs
ACWP Expended Mandays
Performance Measurement Baseline Scheduled Percent Complete Curve
Percent Complete Percent Complete Work-in-Place (WIP)
Planned Percent Complete Percent Scheduled Percent Spent Percent Expended
Estimate at Completion Current Working Estimate Estimate to Completion Mandays Remaining Budget at Completion Tasked Mandays
Cost Performance Index Manday Efficiency Schedule Variance Percent Percent Ahead/Behind
5.2 Methodology
In applying the metrics identified with earned value analysis, the following were calculated
for the each project:
Schedule Variance
Cost Variance
Schedule Variance Percent
Cost Variance Percent
Schedule Performance Index
Cost Performance Index
Estimates at Completion
To-Complete Performance Indices
Variance at Completion
Variance at Completion Percent
For EAC, forecasts where made utilizing each of the identified performance factors
including the special case of Pf = 1.0. After calculating the performance measures, plots were
made for the forecasted Estimates at Completion, as well as the calculated cumulative SV,
CV, SPI, and CPI versus time. In all plots, time was representative of the number of bi-
weekly reporting periods since the 45-day review. Additionally, since the Level IIs only
included planned value and earned value plots, a plot of the actual costs was made. The
results of these calculations can be found in Appendix C.
49
5.3 Review of Application
The application of earned value analysis to the sample NMCB projects afforded new
means by which to analyze each project's status. In addition to the plots of the earned value,
planned value, and actual cost data, the graphs of the cumulative CPI, SPI, CV, and SV
provided good indicators of project performance to date. The analysis also highlighted
performance trends that would provide valuable information to management.
After an initial, negative performance trend, most projects tended to level out before
eventually gaining in efficiency. At the beginning of a deployment, project crews need to
familiarize themselves with the project and on-site conditions. Additionally, project support
and material supply issues may not be entirely resolved and therefore can affect performance.
After achieving a certain level of efficiency, an increase can generally be expected towards
the end of the deployment as emphasis on project completion increases. Through careful
review of these issues and tracking of the performance trends during the execution of a
project, management action can be focused as required. Figures 5.1 and 5.2 are examples of
this performance trend:
Tracking the Cumulative SV and CV
-SV
.CV
Time (Reporting Periods Since 45-Day Review)
Figure 5.1 - Tracking Cumulative Cost and Schedule Variances
50
>> 1.20
Tracking the Cumulative SPI and CPI
u
.1 1.00 - u £ U 0.80
1 I 0.60 -
£ fa 0.40 TJ
« 0.20
U 0.00
\ t.|r|t t^»" ^*r — -r»***#i^^ » SPI
a cpi
— f-i v> t^ o —< c> m r~ C\ — m
Time (Reporting Periods Since 45-Day Review)
Figure 5.2 - Tracking Cumulative Performance Indices
The next area that was reviewed from the applied analysis techniques was the forecasting
of an Estimate at Completion. With the final actual cost known, the accuracy of these
predictions could be monitored. As can be expected, the Schedule Cost Index produced the
highest values for projects behind schedule due to the multiplication factor of a SPI and CPI
less than one. With a performance factor of 1.0, the lowest estimates were achieved,
however this factor does not account for past performance efficiencies. Figure 5.3 displays
the trend of the forecasts throughout the duration of one of the projects. The projected values
in this example ended up higher than the final actual costs since the project was not completed
within the deployment and was turned over to the relieving Battalion. By forecasting the
EAC from past performance efficiency, a more accurate estimate of the mandays to be turned
over to the relieving Battalion can be made.
6000
Estimates at Completion
5000
4000
| 3000 .
2000
1000
0 .
.... ^±&S& —♦— SPI
-B—CPI
A SCI
—•— Composite
Pf=l
Actual EAC
jgg*g&*zrz=z^ w
Time (Reporting Periods since 45-Day Review)
Figure 5.3 - Range of EAC Forecasts on NMCB Project
51
Having reviewed the application of the earned value techniques to these sample projects,
the benefits of their use on NMCB projects can be observed. The greatest benefit is perhaps
in the trend analysis that it affords management to avoid future problems and to monitor the
results of implemented changes.
5.4 Obstacles to Implementation
With the implementation of any new management approach, obstacles are bound to be
present. At times, a desire to maintain the "status quo" can prevent changes from occurring.
Although, some of the basics concepts of earned value are utilized in NCF project
management, the author believes that in establishing all of identified methods, techniques, and
analysis tools the following obstacles may appear.
5.4.1 Training
In order to meet the mission identified for the Naval Construction Force, the various units
continuously conduct training in the areas of military and construction proficiency. Just as
earned value methodology evolved from simple concepts introduced by industrial engineers,
to becoming an overbearing requirement implemented by the government, and finally
reforming back into a more widely accepted standard, the implementation of earned value can
probably expect similar results initially in the NCF. Until project crewleaders and
management gain awareness and experience in the techniques identified, training will need to
occur to expedite the learning process.
5.4.2 Accurate Accumulation of Data
Although timecard data is tracked and accumulated for each project, it is the author's
experience that this is a time consuming process involving significant effort to ensure
accuracy. As it currently stands, the timecard accounting system and the project management
system are not integrated. Therefore, the successful application of earned value management
would partly be based on management's ability to quickly gather required data for analysis
when desired.
52
5.4.3 Revision of Deployment Tasking
As was identified, "rapid contingency response" is a key element of the NCF's mission.
When called upon to provide this response, many of the resources that are assigned to on-
going projects will be called upon to fulfill this mission. In order to maintain the validity of
the earned value analysis, adjustments to the affected project's plan would need to be made.
5.4.4 Support of System
The implementation of an Earned Value Management System must be accepted by both
project crewmembers as well as management to be fully successful. To achieve this, the
benefits and knowledge gained through the analysis must be shared amongst all parties
involved. Without this awareness and buy in by the lowest level team member, the
implementation of earned value analysis and the gathering of data can appear as an added
burden to the execution of a project.
Furthermore, the results of earned value analysis must be constructively examined as how
to improve project performance and not individual performance. Otherwise, the possibility of
data manipulation exists in an effort to avoid a poor individual evaluation. Through proper
management focus and the introduction of earned value project management as a tool for
improvement, vice another requirement that must be met, this challenge can be surpassed.
5.5 Summary
In summary, this chapter presented and reviewed the application of the described earned
value analysis metrics to actual NCF projects. The methodology used in employing the
concepts identified in this paper to the sample projects was discussed. Finally, probable
obstacles to the successful introduction and implementation of the earned value management
approach were presented.
53
6. Conclusions and Recommendations
6.1 Conclusions
Earned Value Management is a powerful tool that can assist the Naval Construction
Force in the management of its construction projects. It enables the project team to identify
problems and trends at an earlier stage, thereby allowing appropriate action to be taken. While
it cannot be viewed as a solution to all project issues, it does provide a means to manage a
project in an efficient way.
Through a review of the Naval Construction Force project fundamentals, some basic
elements of Earned Value Management already exist. By adapting the procedures identified,
the full benefits of all three data elements and the analysis tools they provide would be
realized. From the application of Earned Value Management to the sample projects, the future
tracking of variances and performance indices by the Naval Construction Force is
recommended. Furthermore, the use of the forecasting tools provided by earned value
analysis can aid in projecting the project status at the end of a deployment.
The successful implementation of earned value management is dependent upon properly
adhering to many fundamental steps. Although obstacles may present themselves during this
process, they are not insurmountable and with the proper management focus, acceptance from
all team members can be expected.
54
6.2 Recommended Research
During the course of conducting this research the following issues were identified as
recommended areas for future investigation:
• Follow the implementation of Earned Value Management through the full 14-
month planning and deployment cycle of a Naval Mobile Construction
Battalion. This will allow one to monitor its effectiveness at various stages
and to gather additional data points for analysis.
Software applications that integrate project management and accounting
system data into an earned value management tool.
Methods to validate the analysis metrics to detect if data manipulation has
occurred in an effort to report higher progress then what was actually
accomplished.
55
Bibliography
Abba, Wayne. "Earned Value Management: Reconciling Government and Commercial Practices." Program Manager. Jan./Feb. 1997: 58 - 63.
Ajuja, Hira N., et al. Project Management: Techniques in Planning and Controlling Construction Projects. 2nd ed. New York: John Wiley & Sons, Inc 1994.
Air Force Materiel Command "Financial Management Reference System: Chapter 39" Online. Internet: Oct. 1998. <http://www.afmc.wpafb.af.mil/HQ-AFMC/FM/FMRS/ noframes/dtoc39.htm>
Antvik, Sven. "Earned Value Management (EVM) - A 200 Year Perspective." Proceedings of the 29th Annual Projec 9 Oct. - 15 Oct. 1998. the 29th Annual Project Management Institute Seminars & Symposium. Long Beach, CA,
Beach, Chester Paul Jr. "A-12 Administrative Inquiry." Memorandum for the Secretary of the Navy. Washington, DC: Department of the Navy, 28 Nov. 1990.
Brandon, Daniel M., Jr. "Implementing Earned Value Easily and Effectively." Project Management Journal. Jun. 1998: 11-18.
Canepari, John E., and Varrone, Michael J. "Application of a Manual Earned Value System for Small Engineering Projects" AACE Transaction. 1985: A.3.1 - A.3.5.
Christensen, David S. "An Analysis of Management Reserve Budget on Defense Acquisition Contracts." Acquisition Review Quarterly. Summer, 2000: 191 - 207.
Christensen, David S. "Using the Earned Value Cost Management Report to Evaluate the Contractor's Estimate at Completion." Acquisition Review Quarterly. Summer, 1999: 283-296.
Christensen, David S. "The Costs and Benefits of the Earned Value Management Process." Acquisition Review Quarterly. Fall, 1998: 373 - 386.
Christensen, David S. "Project Advocacy and the Estimate at Completion Problem." Journal of Cost Analysis. Spring, 1996: 35-60.
Christensen, David S. "Cost Overrun Optimism: Fact or Fiction?" Acquisition Review Quarterly. Winter, 1994: 25 - 27.
Christensen, David S. "Determining an Accurate Estimate at Completion." National Contract Management Journal. Vol. 25,1993: 17-25.
56
Christensen, David S. and Daniel Ferens. "Using Earned Value for Performance Measurement on Software Development Projects." Acquisition Review Quarterly. Spring, 1995: 155- 171.
Civil Engineer Corp Officer School. Seabee Crewleader's Handbook. Port Hueneme, CA: Government Printing Office. Feb. 1997.
Civil Engineer Corp Officer School. Seabee Project Planning: Student Guide. Port Hueneme, CA: Government Printing Office.
Construction Industry Institute (CII). "Scope Definition and Control" Publication 6-2. Austin, TX.: Construction Industry Institute, Jul. 1986
Defense Systems Management College. Earned Value Management Textbook. Fort Belvoir, VA: Defense Systems Management College Press, Jan. 2001.
Defense Systems Management College. Scheduling Guide for Program Managers. Fort Belvoir, VA: Defense Systems Management College Press, Jan. 2000.
Delaney, Lawrence J. "Embracing Earned Value Management for the 21st Century" Aerospace Acquisition 2000. Jan./Feb. 2000: 1-8.
Department of Defense. Earned Value Management Implementation Guide. Washington, DC: Government Printing Officer, 11 Dec. 1996.
Department of Defense. POD Instruction 5000.2-R, Part 3.3.4.3: Mandatory Procedures for Major Defense Acquisition Programs and Major Automated Information System Acquisition Programs. Washington, DC: Government Printing Office, 15 Mar. 1996.
Department of Defense. POD Instruction 7000.2: Performance Measurement for Selected Acquisitions. Washington, DC: Government Printing Office, 22 Dec. 1967.
Department of Engergy. Project Management Practices: Chapter 10. Online, Internet: 2000. < http://www.er.doe.gov/production/er-80/er-8 l/PDF/practl0.pdf>
Department of the Navy. COMSECONDNCB/COMTHERDNCB INSTRUCTION 5200.2B. Promulgation of NMCB Operations Officer Handbook. Norfolk, VA: N3, 24 Nov. 1999.
Department of the Navy. OPNAVINST 5450.46K, Naval Construction Force Policy. Washington DC, VA: N446, 25 May 1999.
Department of the Navy. NWP 4-04.1/MWCP 4-11.5, Seabee Operations in the MAGTF. Norfolk, VA: Navy Warfare Publications Library, Nov. 1997.
Department of the Navy. Naval Construction Force / Seabee l&C. Norfolk, VA: Naval Education and Training Professional Development and Technology Center, Mar. 1995.
57
Department of the Navy. PERT Summary Report, Phase 1. Washington, DC: Special Projects Office, Bureau of Naval Weapons, 1958.
Dua, Raf M. "Project Management through Earned Value Performance Management: EVPM." Online. Internet: 1997. <http://www.mpi.com.au>
"Earned Value Management Homepage." Online. Internet, <http:www.acq.osd.mil/pm/>.
Fleming, Quentin W. Cost/Schedule Control Systems Criteria: The Management Guide to C/SCSC. Chicago, EL: Probus Publishing Company, 1992.
Fleming, Quentin W., and Joel M. Koppelman. "The Earned Value Body of Knowledge." Proceedings of the 30th Annual Project M Philadelphia, PA: 10 Oct. - 16 Oct. 1999 Proceedings of the 30th Annual Project Management Institute Seminars & Symposium.
Fleming, Quentin W., and Joel M. Koppelman. "Earned Value Project Management: An Introduction." Cross Talk: The Journal of Defense Software Engineering. Jul. 1999: 10- 14.
Fleming, Quentin W., and Joel M. Koppelman. "Earned Value Project Management: A Powerful Tool For Software Projects." Cross Talk: The Journal of Defense Software Engineering. Jul. 1998: 19-23.
Fleming, Quentin W., and Joel M. Koppelman. "Earned Value Project Management" Cost Engineering. Feb. 1997: 13-15.
Fleming, Quentin W., and Joel M. Koppelman. Earned Value Project Management. 2nd ed. Upper Darby, PA: Project Management Institute, 1996.
Fleming, Quentin W., and Joel M. Koppelman. "The Earned Value Concept: Taking Step Four: Establish the Project Baseline." Project Management Network. May 1995: 26-29.
Fleming, Quentin W., and Joel M. Koppelman. "The Earned Value Concept: Taking Step Three with Earned Value: Estimate and Budget Resources." Project Management Network. Jan. 1995: 39-41.
Fleming, Quentin W., and Joel M. Koppelman. "The Essence and Evolution of Earned Value." Cost Engineering. Nov. 1994: 21-27.
Fleming, Quentin W., and Joel M. Koppelman. "The Earned Value Concept: Taking Step Two: Plan and Schedule the Project." Project Management Network. Sep. 1994: 35 - 37.
Fleming, Quentin W., and Joel M. Koppelman. "The Earned Value Concept: Taking Step One: Scope the Project." Project Management Network. May 1994: 22-24.
Harroff, Noel N. "Earned Value." Online. Internet. 17 March 2001. <http://www.nnh.com>
58
Kraus, W. E., and Kenneth R. Cressman. "Project Scope Definition: A Practical Approach." Cost Engineering. Dec. 1992.
Mansuy, John. "Work Breakdown Structure: A Simple Tool for Complex Jobs." Cost Engineering. Dec. 1991: 15-18.
McMullan, Leslie E. "Cost Forecasting: Beyond the Crystal Ball." AACE Transaction. 1996: C&S/M&C 20.1 - C&S/M&C 20.7
Meredith, Jack R., and Samuel J. Mantel, Jr. Project Management: A Managerial Approach. 3rd Ed. New York: John Wiley & Sons, Inc., 1995.
Microsoft Corp. User's Guide for MS Project 98. Redmond, WA: Microsoft Press, 1997.
Naval Facilities Engineering Command. P-315, Naval Construction Force Manual. Alexandria, VA: Government Printing Office, Feb. 1985.
Naval Facilities Engineering Command. P-405, Seabee Planner's and Estimator's Handbook. Alexandria, VA: Government Printing Office, Oct. 1996.
PMI Standards Committee. A Guide to the Project Management Body of Knowledge (PMBOK Guide), 2nd ed. Upper Darby, PA: Project Management Institute, 1996.
PMI Standards Committee. A Guide to the Project Management Body of Knowledge: Glossary of Terms. Newton Square, PA: Project Management Institute, 1987.
Short, Jim W. "Using Schedule Variance as the Only Measure of Schedule Performance." Cost Engineering. Oct. 1993: 35 - 40.
Singh, Amarjit. "Knowledge Bases for C/SCSC." Cost Engineering. Jun. 1991: 39 - 48.
Smith, Larry W., and Steadman A. Todd. "Gaining Confidence in Using Return on Investment and Earned Value." Cross Talk: The Journal of Defense Software Engineering. Apr. 1999.
Valkenhoff, Ben H. "Cost Performance Measurement" Cost Engineering. Aug. 1981: 219 - 225.
Wilken, Tammo T. "Earned Value, Clear and Simple." Proceedings of the 30th Annual Project Management Institute. Seminar/Symposium. Chicago, IL: 29 Sep. - 1 Oct. 1997.
Young, Paul E. "Use of Earned Value Management to Mitigate Software Development Risk" Online. Internet: 21 Apr. 1997. <http://huxley.baz.com/kjordan/swse625/htm/tp-py.htm>
59
APPENDIX A. Earned Value Management System Criteria
Organization
1. Define the authorized work elements for the program. A work breakdown structure (WBS), tailored for effective internal management control, is commonly used in this process.
2. Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work, and define the organizational elements in which work will be planned and controlled.
3. Provide for the integration of the company's planning, scheduling, budgeting, work authorization and cost accumulation processes with each other, and as appropriate, the program work breakdown structure and the program organizational structure.
4. Identify the company organization or function responsible for controlling overhead (indirect costs).
5. Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed.
Planning and Budgeting
6. Schedule the authorized work in a manner that describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program.
7. Identify physical products, milestones, technical performance goals, or other indicators that will be used to measure progress.
8. Establish and maintain a time-phased budget baseline, at the control account level, against which program performance can be measured. Budget for far-term efforts may be held in higher-level accounts until an appropriate time for allocation at the control account level. Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work. On government contracts, if an over target baseline is used for performance measurement reporting purposes, prior notification must be provided to the customer.
9. Establish budgets for authorized work with identification of significant cost elements (labor, material, etc.) as needed for internal management and for control of subcontractors.
10. To the extent it is practical to identify the authorized work in discrete work packages, establish budgets for this work in terms of dollars, hours, or other measurable units. Where the entire control account is not subdivided into work packages, identify the far term effort in larger planning packages for budget and scheduling purposes.
11. Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget.
60
12. Identify and control level of effort activity by time-phased budgets established for this purpose. Only that effort which is immeasurable or for which measurement is impractical may be classified as level of effort.
13. Establish overhead budgets for each significant organizational component of the company for expenses, which will become indirect costs. Reflect in the program budgets, at the appropriate level, the amounts in overhead pools that are planned to be allocated to the program as indirect costs.
14. Identify management reserves and undistributed budget.
15. Provide that the program target cost goal is reconciled with the sum of all internal program budgets and management reserves.
Accounting Considerations
16. Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account.
17. When a work breakdown structure is used, summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements.
18. Summarize direct costs from the control accounts into the contractor's organizational elements without allocation of a single control account to two or more organizational elements.
19. Record all indirect costs that will be allocated to the contract.
20. Identify unit costs, equivalent units costs, or lot costs when needed.
21. For EVMS, the material accounting system will provide for:
(1) Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized, acceptable, costing techniques.
(2) Cost performance measurement at the point in time most suitable for the category of material involved, but no earlier than the time of progress payments or actual receipt of material.
(3) Full accountability of all material purchased for the program including the residual inventory.
Analysis and Management Reports
22. At least on a monthly basis, generate the following information at the control account and other levels as necessary for management control using actual cost data from, or reconcilable with, the accounting system:
(1) Comparison of the amount of planned budget and the amount of budget earned for work accomplished. This comparison provides the schedule variance.
61
(2) Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work. This comparison provides the cost variance.
23. Identify, at least monthly, the significant differences between both planned and actual schedule performance and planned and actual cost performance, and provide the reasons for the variances in the detail needed by program management.
24. Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control, along with the reasons for any significant variances.
25. Summarize the data elements and associated variances through the program organization and/or work breakdown structure to support management needs and any customer reporting specified in the contract.
26. Implement managerial actions taken as the result of earned value information.
27. Develop revised estimates of cost at completion based on performance to date, commitment values for material, and estimates of future conditions. Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements.
Revisions and Data Maintenance
28. Incorporate authorized changes in a timely manner, recording the effects of such changes in budgets and schedules. In the directed effort prior to negotiation of a change, base such revisions on the amount estimated and budgeted to the program organizations.
29. Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control.
30. Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs, earned value, or budgets. Adjustments should be made only for correction of errors, routine accounting adjustments, effects of customer or management directed changes, or to improve the baseline integrity and accuracy of performance measurement data.
31. Prevent revisions to the program budget except for authorized changes.
32. Document changes to the performance measurement baseline.
62
APPENDIX B. Earned Value Quick Reference Sheet
Estimate to Complete
(ETC)
Projected ACWP at Completion (EAC)
Time- Time Now
Projected Delay in Project Completion
Projected Cost Overrun at Completion (VAC)
Planned Completion
Projected Completion
VARIANCES (Favorable is positive, Unfavorable is negative)
•Cost Variance CV = BCWP-ACWP
•Schedule Variance SV = BCWP-BCWS
• Variance at Completion VAC = BAC-EAC
CV%= CV/BCWP
SV%= Sv/ BCWS
PERFORMANCE INDICES
• Cost Efficiency
• Schedule Efficiency
OVERALL STATUS
• Percent Complete
• Percent Spent
(Favorable is > 1_.0, Unfavorable is < 1.0)
CPI = BCWP/ACWP
SPI = BCWP/BCWS
BCWPniM BAC
ACWPCUM
BAC
TO COMPLETE PERFORMANCE INDEX (TCPI)
= WORK REMAINING = BAC-BCWP TCPI (EAC) COST REMAINING
ESTIMATE AT COMPLETION
CUM-
EAC-ACWPCUM
(EAC = ACWP + Estimate for Remaining Work)
EAC BAC CPI CPI CUM
•EACSCI = ACWP BAC - BCWP
CUM CUM
(CPI CUM)* (SPI CUM)
63
APPENDIX C. Results of Practical Application
64
r> «1 u o
_ _ c — S cu u o 41 3 « O E/3 U Qu < Hill j
B O
•■B
E o U
U
saw
o 8
a a. < oo CM
Ö
■< O Q. D
111 > UJ
X 0) H U.
■<t v> in o\ oo
i o\ > z
' 1- s-6 §"
\f
M
si
siis ' sisr'
33 u
Ml
a. u e
a.
E s U
M C a
S
— — o
sjopEjj "ioujpijja oinpoips pire jso3
u < u o a „ - « e
D. 0- U O J u co U w CJ a. <
MM | j
a E o U
« s
saw
3 O
o o
o co
> m < V o 8
co b 3
o o CO CO
o o o
CO 3 0 o
CO o CO
0
to o LU 5
rn >, " to
9 tu s it: i- <o
o en to \ \ o
CO b 3
CO o CO
CO
D O CM
CO
o CO CJ)
CO CM o
CO h 5S
O 0
LU 1- Q: \ \ n a. ^
< m <
in
\" \
lO Ol
o 1 b o
o o CO
■o 1^. s CM O
CO CO
o o CO
g9 CO m
^ 0
O £ \ \ LU
\ \ CO r 1 ^
a: < s \ o 8 CO
3 O
CO CM
o ■fl" 1^ to CM 5
to CO
CM 3 CM
ü C£ \ ö E t r^ \ a»
E m \ o 1 CO
3 3 - 3)
CM CO CO CO
m CM - CO
-a- CO
CM CO S N
a. ] \ m \
EM
\ \ in o CO CO
3 3
o CM CM XI
o m CO - s CO
CM o> o>
to en
'«> CO C7> CO
m \ 0> ■p- CM T- T-
i- CO
m 2 in
CM CO
b CO CO
1^- CO CM 5
in CO
m n to
•t CM CO CO
CO
CO
•- CO CD to
CoVy CO
CO
to CO
CM
CO r*- CM 1 o » h o.
o CO
in CO
CO CM to
5S B
CM to in m
CM
ii z t -^ CO CM
o ^ CO I m V s O
m b o in 1 CM CM
CO
s m CO CM
CO 1 5^ s <o 0 lÖ
CD 1\ m ■«» CM O V
•o
S
CO CO ^ CO £ o cvi
CD m
CO
CJ>
O CO CO
CO CO
CM
T 1»- to 0
lÖ
? ü
V \ \
S5 CM h eo w o CO S m
CO CM
o CO CO
o o O 0
CO CM
"* >J CM CM V o CO \
\ CO m
01 CM se o>
CM to m
CM to CM
8 CO
o o o 0
CO O U5
> V \ \ in V
\ CO
CM o>
CM
CO CM ?r CO
CM CM CM
o co o
o 55 0 0
to - m
< \ u. UJ O < o
\ co ro ■w -V •V •* ■s
o 5 m in m m 1 C o CO CO
5^ o o
5? O 0
to - <o
s N s*
g$ gS gS g? gS gS gS 5? gS gS g$ OJ
m * * O c o
X , CO x* CD uS
1^ to CM U) T- ^ o o £ CO
E
+
i O a z 5 D Z < CO
o
cr ü
?
LU
1-
f- >- > O < 2
UJ
a:
1 UJ
LU
UJ
o 7
z O (0
to LU I CO
< CJ
z
«a S LU Q: > LU 1-
'C
•u a. to lc 1-
u to
> 73 C ra
o
O CO <U
"5
73 O 'C V Q.
!E
"8 E CO
LU VI
e CO
UJ
7>
■c c
S c a.
■c
D-
jz 1-
T3 C
I LL
■a c 0) a
LU
> C to 2
C tu Q
LU
cc
c CO
E Q>
a.
l 1
c CD Q.
UJ
£ en E « LU cr c
I ■c
0. o
\- >
■c 0) Q.
JE 1-
? j= <v m
T) C !E a ■B CO 0}
< c
T3 O
Q) 0.
JE
IB C C3) 'to to <
-O O
■c
CL
1-
0
CL (0
t-
Z
111 O < o LU " ^ u tO V)
¥■ tu
< CL
t/ -J U to u :> a u. 2> H U 75
O o n
a. ra to o in U UJ .1 J^ (0
O
c c
E5* < CM CO T CO en
? h F T3 r F = ?\F
T3 r P T3
r F T3
T3 C
SS 1 1 * O CL k ü|<|2|ü Q_ i U i CL U G
O CM CM
p - CO 0 CO
CO O CO
CO O CO
CO 0 CO
CO
8
O M C3 -
CO 0
CO 0 CO
CO 0 CO
CO 0 CO
CO 0 CO
co CM M Ö
5 en 0 CO
in 0 CO
0 co
to 0 CO 8
CO CO
2 Ö 5 p a 0
0 CO
CO en CM
0 0 CO
to CO *
01 CM
8 s CO CO CM
CO CO CM
01 CO CM
CO n
o> Ö
CM S CM
0
CM
in
CM
CM
CM
CO
CM
CO in
CM m
CO to
CM
8 m to CM
to
CM
O) to CM
CO
rM
en m Ö p
CO £3 CM CO CO
CM CO
m CO C3
p O O
to CO CO
0 s CO
* o> O) Ö
5 s CM m
CO CO
CO CM
0 0 C3 p 0
CO
CD CO CO
0 CO CO
CO CO
0 CO CO
0 0 p p 0
CO CO
O CO CO
0 CO CO
0 CO CO
0 CO CO
0 0 p p 0
CO CO
8 CO
0 CO CO
0 CO CO
0 CO CO
0 0 p 5 0
CO CO
0 CO CO
0 CO CO
0 CO CO
0 CO CO
c
■c to > 0
| 0)
CO (J c ra ■c
CO > 1 <^ CO
CO Ü c CO 'C
> c 0
g9
CO
c CO
c
> 0 0
a T> C
c c to
i •g CO
Q.
<u
x: 0
CO
73
c CO
€ CO
CL
c 0
Q. E 0 Ü
E
LU
O
c
0
E 0 O
0)
CO
E «5 LU
0
Q. E 0 0
1 LU
1 3 c 0
OJ Q. E
cB CO
& 1
1 UJ
c 0 aj Q. E 0
CJ
CO
a>
1 to LU
\+
a. U 13
a CO
et e 2
— O
SJ0J3BJ X3U3piyg 3[np9lp$ pue JS03
U < K ■a
l_l M <—< A T 2 C/3 u CO L) BL, <
\ + \ 1 1 !
a E
> £ co U
H 1 • s
1 ' **>
> / Ä u / £ •o » O £ e / tt / >> > i c to J>
■V >• u
« s E e s r^ <y
U .c ■ o I.
w> a B s IS u E L. H H
1
1
1
1 to
1 r-i
1 —
c
sXepueiY in 33UBUBA
CO OS
h- r*-
o i-
o CO
>- m < v o CO o
CO o o o s b
3 O s 1^
o
CO D w 2 —.
I- CO o < ci>
y CO 3 O
o m
CO o o o
CM s b
o O m
CO n
m b o
a: T- \ •q. CO
in
lO
m CD
CO
CO CO
Sj
CO CO CO CTJ
CO CD
c*) CD m
o M CM ^-
in cS CD r> o
(\ in
CO *- io b
CO
»■ CO
3 b CJ> m
o o m
en o CM m
?\l O en ?f
CM
nr Ö o « E
s tn ^ CO r- c*5
V \ IS ss b Tf CO CD
CO I CO CJ)
CO CO
5?
CO
5Ü en
3? CM
0. \ T_ )
CM
c6 \ $ CO (D
CO i"M CO xi CO
m o CO in
CO CO
O O m CO CO h
CM
CD en CD
m \ u. CM -«- N. in^$ \
m \ \ \
CO
m CO
■fl- to
o CO
CM CO m ro in
in s CO m
CD
CO
in CM CO
CD CM CO
CO CD b CO en CO
CM \ \ \ \ 2 \
CD CM
eet CD CO in
CM CM o LD CM
CM
en o CO A-
CO CO
CM CO
CO CO CM
3S in
CD « CM
UJ Z \ \ ^ T- \
m
\ CO 1^
O r$
CM CM CO
co CM m CO o
en CO
en m s O
CD CO o
In
- \ CO C> CO
to CO
(6 K CD CM
CO CO
en CO
o CO in CO CM S
CM CM
in
co CO
5 o CO CO CD o
In
£ u
\ in
\ \
CD ID
CM CO
CO en
CM CD CD o >>-
CN
CO m
CO o o o o
CD sy
T o CO
«S \ f*. 8 CO r^ en
CM CO CM CO CO CO
o CD o to
LU
g \ z o o
eg CM ^
d m
\ S CM O
s? s CM o ^0 $ CM
o § o m CO
CO o o
5S o o
CD - CD m
2 Q
2 X
\ SIR O) O) ■* ^ \
o ? \ ss CO CO ss jS CO CO S9 S? *- CO (!> CJ \
V a. *
£2 3? gS JS c5 3? 3? eS gS öS eS z ^ 5s ? O)
m iM ^ '"
o o o
o * a ss SS £• io °° *- o 0? iß en s. O o o o O o O o O c> O o o o o o g T~ ■*"
E
id ■o c
1 UJ
& CO
E
LU
03 c
5
LU
1- K > > \- O <
UJ 1 UJ
UJ t- UJ a: ü
> 01 z o
O o z
a z < O
CO LU X CO
< o z < I o
(A Q □ 5 2ui a. > UJ J-
M
o ■c a CL (A .c 1-
18
3
B .c u
CO
■c c CO
S
o
3
CO
■c OJ Q.
!E 1-
E
3 E CO
UJ
1 CO
•5. o
0-
p a) a. co !c 1-
? Cl>
3 TJ c 03 a. X UJ co
T3 C CD
5
1 LU
f
'c CO
E V
1 I V. m
T3 P
0. co !c 1-
1
O ■c
0.
H TJ C lc o m T5
Q) m
1 <
TJ O C eu CL
!c
c C33
'8 <
o ■c CD
a.
IE 1-
73 o ■c CD
a. <o 1c 1-
£ 3 CO UJ o < O UJ "D I
'S
a UJ
■^ <_ CL
< a. u
CO co
-i ID co u £ O u. l- u
CO 3 LU en n
Q-
5 o S LU .i Ü o
c CD
c 01 CJ
C 0) p <
CM CO ■* CO OJ m ? b
F ? F 5 ? fc F ? ? ? 3
F "C H ■o
r s i O Q. ^ O < i U CL i U 2> CL U Q i
o CD o en
ö S S S S s
o CD p en
ö | S s 3
CO in o
o 2 m
CO
o CO
o CO
CO
CO
m CM
CD ■t
p ro en CO in
to
in
CO m m
s !ft
o co en 2 5 s
m
CD CO CO
CO o CM tn
CO o CO CM
CO p 1 s "er 5 CO
in s
■fl- CO
CM
CO p CD CD
en
3 CO CM
CM m
o
8
s CO
en 5 CO CO
en in
CO m
o CO m
in
CO
5 o> - CO en
CO m
CM
a in 8 m
CM CD
CM Ol
s 2 2 CM o m
o o
5 to
8?
o o p p CO CO CO CO CO
1^
o o p p CO CO CO CO CO
o o p p CO CO CO co CO
o o p p CO CO co CO CO
s c CO
CO > =
CD O c
CO > a> 3
V CJ
c
■c
CO > c Ü
CD u c re c CO > o O
■c c
s c
1 CL ©
1
T3 _c
CD CJ
c CO
i € CD
a.
e: O
c o
a> a.
E
c3 CO
CD
to
.§ w
LU
CJ
c o
Q,
E
5 CO
CD ro .§
LU
8 o
CD
o.
E 8 to CD ro E
« LU
£
c o
CD
a.
£
5 ro CD
15
I UJ
c o
CD
a.
E 8 ro £ CO
■I UJ
en U
! + T ■ ii
/
/•
- 0, * u ■o £ « s VI
oi > '■C 00 .5
«3
"O
S s
WD e X
* o M a B OS .* 93 *° E H
i
i
i
i
i
i
Ot 3 \o T r-i o oo ^ > SJopcj Xauapijja ajnpdips pue |s<o
> > «J <->
M "d" m
> ^ U 1 ■a © £ a os « >> > C\
■^
S S E 3 r-
.2
u ft» OJ £ v£) Z sc a. B OS
U. IT)
M .5
H
i
i
i
1 ■*
1 m
1 fS
1 —
v-i o m o io mo
sXBpUBIM III 33UEUBA